SPP Presentation -ITO
Spring 2008 Stakeholders MeetingNovember 20, 2008
Prepared by:Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
HELPING OUR MEMBERS WORK TOGETHERTO KEEP THE LIGHTS ON… TODAY AND IN THE FUTURE
2
Katherine Prewitt
November 20, 2008
Introductions & Overviews
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
3
Introductions & Overviews
Logistics♦ Safety♦ Breaks/Lunch♦ Restrooms♦ Silence Cell Phones and Blackberries ♦ Introductions
Overview of Meeting
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
4
Katherine Prewitt
November 20, 2008
Open Action Items from Spring 2008 Stakeholder Meeting
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
5
Open Action ItemsDarrin Adams (EKPC): Has there been any curtailment in relation to these TLRs? (Stuart Goza -TVA)) The only curtailments resulting from these TLRs have been the curtailments of scheduled transmission services. ♦ TLRs are listed at the NERC website at the following link.
(http://www.nerc.com/~filez/Logs/tlrlogs.html). ♦ The website posts the TLRs as called by the RC and not by the Control
Area. ♦ Filter the data by RC (TVA) and then compare it to a list of E.ON flowgates
IDs from their OASIS website. ♦ TLR specific information can be requested from the RC by contacting Stuart
Goza with the date and time of the TLR event. Daryn Barker (E.ON-US): Maybe we can limit the data that is presented to only those elements that limit AFC to zero and include monthly’s also. (Jonathan Hayes – SPP) After reviewing the data that was presented, only those limiting elements that went to zero were included in the data posted.
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
6
Open Action ItemsDarrin Adams (EKPC): Has there been any curtailment in relation to these TLRs? TVA suggests that anyone interested in this information can use the following link to search curtailment logs. http://www.nerc.com/~filez/Logs/tlrlogs.htmlDaryn Barker (E.ON-US): Follow up with TVA on the actual process to do this during energy emergency events. TVA is not a party to the CRSG events. The NERC EEA process is defined in NERC Standard EOP-002. See link.ftp://www.nerc.com/pub/sys/all_updl/standards/rs/EOP-002-2.pdf
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
7
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
Questions?
8
Contact SPPITO
http://www.spp.org/itoGeneral Inquiries: 501-614-3200
Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
9
Chris Lax
November 20, 2008
ITO – Operations
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
10
ITO Operations
Operational Data
♦ Tariff Administration
♦ Scheduling
♦ TLR Statistics
Available Transfer Capacity
♦ Daily Firm Statistics
♦ Hourly Non-firm Statistics
Stakeholder Questions
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
11
Tariff Administration
Reservations
♦ 6608 Total Reservations processed
♦ 5749 TSRs Confirmed
♦ 6 TSRs in Study
♦ 455 TSRs Refused or Declined
♦ 398 TSRs Withdrawn, Retracted, Annulled, Invalid or Superseded
Additional Analysis of Reservations can be found athttp://www.spp.org/publications/TSR_Stats_200811.xls
Independent Transmission Organization
12
Scheduling
The ITO processed 8299 e-Tags from May 2008 through September 2008.
Independent Transmission Organization
13
TLR Statistics
Additional TLR information can be found at
♦ http://www.spp.org/publications/TLR_Stats_200811.xls
14
Daily Firm (Day Ahead) ATC Metrics
Analysis of the Daily Firm ATC Metrics can be found at
http://www.spp.org/publications/DF_ATC_Stats_200811.xls
Independent Transmission Organization
15
Hourly Non-Firm ATC Metrics
Analysis of the Hourly Non-Firm ATC Metrics can be found at
http://www.spp.org/publications/HNF_ATC_200811.xls
Independent Transmission Organization
16
Questions
Independent Transmission Organization
Contact SPPITO
Email: [email protected]
http://www.spp.org/itoGeneral Inquiries: 501-614-3200
Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
18
Scott Jordan
November 20, 2008
ITO – Tariff Studies
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
19
Outline
SIS MetricsFS MetricsDNR/NITS Study Process ChangeQuestions
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
20
SIS Metrics – 2008 Q2 and 2008 Q3
New SISA delivered – 8New SISA executed – 8SIS Completed – 9SIS Completed Late – 0SIS Avg. Completion time – 52
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
21
FS Metrics – 2008 Q2 and 2008 Q3
New FSA delivered – 6New FSA executed – 6FS Withdrawn - 1FS Completed – 7FS Completed Late – 1FS Avg. Completion time – 59
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
22
DNR/NITS Study Process Change
Current Study Process♦ OASIS TSRs are currently being used for DNRs
and Load Additions and are accompanied by NITS Applications sent via e-mail.
♦ These TSRs have service times beyond the 18 month planning horizon.
♦ The TSRs have to be evaluated in the SIS/Long Term Planning Process due to the service time being beyond the 18 month window.
♦ The TSR Queue date is used as the study queue.
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
23
DNR/NITS Study Process Change Cont.’
Study Process Change♦ OASIS TSRs will still be used for DNRs♦ NITS Applications will be used for Load Additions but do not
have to have an associated TSR.♦ The Study queues will be decided by the following criteria:
The queue date from OASIS on the TSR for DNRsThe received date from the e-mail containing the NITS application for the Load additionsStudy parameters for each study will be decided by the information from both the DNR and Load addition requests at the time of the submission of either the TSR in OASIS for the DNR orof the NITS application for the Load addition.
♦ Propose to start this new processJanuary 1, 2009
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
24
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
Questions?
25
Contact SPPITO
http://www.spp.org/itoGeneral Inquiries: 501-614-3200
Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
2626
Jonathan Hayes
November 20, 2008
ITO – LGI Studies
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
27
Topics
Update
Achievements
New goals
27
Independent Transmission Organization
2828
Update / Coordination
♦ 3 Active requests (end of 3rd
Quarter)
♦ Public info (Oasis)
♦ Process Overview
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
29
Public Info Update Generation
Interconnection Number
Nearest Town or County State CA In-Service Date
(proposed) CAPACITY (MW) Type STATUS
LGE-LGI-2007-002 Central City KY LGEE 6/1/2014 610.0
Combined Cycle
SYSTEM IMPACT STUDY COMPLETE/
LGE-LGI-2007-004
Henderson County KY LGEE 3/31/2011 640.0
Combined Cycle
IMPACT STUDY BEING REVIEWED
LGE-LGI-2008-001 Wise County VA 12/1/2011 150.0 Wind
FEASIBILITY STUDY SET TO BEGIN
29
Independent Transmission Organization
30
GI Process Overview
Agreements/Bids (triplicate) New templates
Scoping Meeting(s) Changes
Prepare Models
Perform Feasibility Analysis (Power Flow/ Short Circuit)
Perform System Impact Analysis (Power Flow, Short Circuit, and Dynamic)
Review/Prepare/Post Results and Report
Coordinate data transfer
30
Independent Transmission Organization
31
Achievements
Will be executing power flow study for BP wind.
New templates posted on oasis
Identified and resolved issues to make the process better.
31
Independent Transmission Organization
3232
New Goals
Training to bring short circuit and dynamic parts of analysis in house
Streamline Application
Look for ways to improve Communication / Coordination.
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
33
Questions ?
33
Independent Transmission Organization
34
Contact SPPITO
Email: [email protected]
http://www.spp.org/itoGeneral Inquiries: 501-614-3200
Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
3535
David Kelley
November 20, 2008
ITO – 2007 Transmission Expansion Plan
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
363636
ITO’s Assessment of E.ON’s 2007 TEP
2007 TEP based on summer and winter peak models for 2008, 2011, and 2016ITO Assessment Includes:♦ Planning Guidelines♦ Model Validation♦ Powerflow Analysis♦ Operating Guidelines Assessment♦ Planned Project Assessment
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
373737
Planning Guidelines Review
2007 TEP based on September 2007 revision of planning guidelines♦ ITO validated that 2007 TEP consistently adhered to
the criteria in the planning guidelines and good utility practice
♦ Subsequent revisions of the planning guidelines were also reviewed and the most recent version is posted on OASIS
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
383838
Model Validation
Accuracy ♦ ITO compared first tier control area generation dispatch
and facility characteristics from E.ON’s models with those included in MMWG models
♦ Reviewed 2007 TEP and ensured that the unit generation simulated in the models is what was expected
Performance♦ E.ON’s generation was verified to be operating within
minimum and maximum operating limits♦ Compared models that included planned projects against
models that did not to ensure projects properly incorporated into the models
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
3939
Powerflow Analysis
Identified potential thermal and voltage issues in the models
Results analyzed against criteria provided in planning guidelines♦ Thermal issues: Flow above 100 percent of applicable
normal or contingency rating
♦ Voltage issues: Voltage below 94 percent or above 105 percent nominal during normal conditions and below 90 percent and above 105 percent nominal during contingency conditions
Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
4040
Powerflow Analysis Results
3 contingency situations created potential thermal and/or voltage issues affecting 12 monitored elements♦ 2 need projects to be expedited
♦ 1 requires coordination between E.ON and EKPC
Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
4141
Operating Guidelines Assessment
Each operating guideline identified by E.ON as a solution to a violation in the Powerflow Analysis was independently verified.♦ Does it satisfactorily mitigate the violation?
♦ Does it cause issues on neighboring systems?
♦ Does it require coordination with neighboring systems?
Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
4242
Planned Project Assessment
Each project identified by E.ON as solutions to Powerflow violations was independently evaluated.♦ Is it properly modeled?
♦ Is the project adequately timed?
♦ Does the project resolve the violation?
Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
434343
Dynamic Study Assessment
The dynamic models and studies were provided to the ITO in Apr 08.
The ITO reviewed the analysis for adherence to applicable NERC stability standards.
The dynamic study has been included in the ITO’s independent assessment report.
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
444444
TEP Coordination
RC Coordination♦ TEP presented to TVA as the RC in March 2008♦ RC comments included as part of the ITO’s
independent assessment report
Stakeholder Meeting Presentation♦ Any additional stakeholder questions or concerns
will be considered for the next 30 days♦ Final report will be posted on OASIS by Dec. 31
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
454545
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable
Independent Transmission Organization
Questions?
46
Contact SPPITO
http://spp.issuetrak.com/Login.asp
http://www.spp.org/itoGeneral Inquiries: 501-614-3200
Independent Transmission Organization
Relationship-Based • Member-Driven • Independence Through DiversityEvolutionary vs. Revolutionary • Reliability & Economics Inseparable