Specification & Quantities Estimating Lecturer Maha Muhaisen College of Applied Engineering& Urban...
-
Upload
anabel-robinson -
Category
Documents
-
view
218 -
download
0
Transcript of Specification & Quantities Estimating Lecturer Maha Muhaisen College of Applied Engineering& Urban...
Specification & Quantities Estimating
Lecturer
Maha MuhaisenMaha Muhaisen
College of Applied Engineering& Urban Planning
Course Aims & Objectives
At the completion of this course, the student will:
Recognize the preliminary and detailed estimating methods and focusing on the elements for construction projects
To be familiar with cost analysis and preparation for bidding.
Understanding and be familiar with the construction specification in particular for building.
Course Outline
Part 1 : Quantity SurveyIntroduction to Engineering project including
project cycle, & bidding documents.Quantities surveying and calculation of
different areas.Methods of measurement of the works.Pricing & cost analysis.Payment certificate.Application on Engineering project
Part 2 : Technical specification
Earth worksConcrete worksMasonry worksPlasteringTilingMetal workCarpentry workPainting worksGlazingPlumbing worksElectrical works
The Engineering ProjectThe Engineering Project
ProjectProject
Structural Structural worksworks
Architectural Architectural WorksWorks
Electrical Electrical WorksWorks
Mechanical Mechanical WorksWorks
Types of construction Engineering Types of construction Engineering Projects :Projects :
- Building construction- Roads Construction- Water Systems- Sewerage and Storm water systems
Project Cycle
Studies, design, tendering
Implementation & supervision
Taking- over, and operation
Main stages in construction project1- Concept : identify the project needs, and objectives2- technical studies as feasibility study, possibility of
implementation, primary cost, and possibility of financing …..etc.
3- Preliminary design4- Detailed design including architectural , structural, electrical,
mechanical.5- Tender documents.6 – Tendering7- Contract Award8- contract agreement9- starting construction10- Preliminary handing over the project11- the operation of the project12- maintenance period13- Project final handing over.
Construction Project CycleP
erc
en
t C
om
ple
te
Stage I Stage II Stage III Stage IV
Project "GO" Decision
Major Contracts Let
Installation Substantially Complete
Full Operations
Feasability- P roject Formulation - Feasabiltiy Studies- Strategies Design & Approval
Planning & Design - Base Design - Cost & Schedule- Contract Terms & Conditions. - Detailed P lanning
Turnover & Start Up- Final Testing - Maintenance
Construction - Manufacturing - Delivery - Civil Work - Installation - Testing
Figure 1.1 : Construction Projects Life-Cycle (Ref: PMBK, 2000)
Tender DocumentsTender Documents
Invitation to bid Instruction to bidders Information to bidders & bid data Biding Forms General conditions of contract Specific condition of contract Specification BOQ Drawings Contract forms
The Project Parties
The Employer /OwnerThe consultant: who appointed by the
employer to do the design and bidding documents and supervise the construction work.
The contractor: who was approved by the employer to implement the works according to the submitted bid.
Other PartiesMunicipalities, ministries, suppliers, techniciansSubcontracts, workers,Insurance companiesBanks and other financing agencies.
Construction Project Teams
Main tasks for engineering teams in Main tasks for engineering teams in the project are :the project are :- design- Implementation / construction- supervision
Construction Project Teams
Quantity Surveyor
He the person who is responsible on estimating the quantities from the design drawings, and measurement of the quantities in the site during the project implementation, and preparing the current and final payments.
Quantity Surveys (take off)
It is the quantity of works/material take off , required for the completion of project implementation, and listed as items in table of quantities.
In general we can describe quantity survey In general we can describe quantity survey as follows:as follows:
1.Description and preparation of the bill of quantities and its items required for the tender.
2.Preparation of the site material, material types, and material distribution.
Quantity surveys (take off) .. Cont.Quantity surveys (take off) .. Cont.
Describe the items and preparing BOQPreparing of the cost estimate in BOQ.Preparation of the list of the site needs
(technician / workers)Preparation of the due payment statements
(contractor payments during the construction)
Tasks of the Quantity SurveyorTasks of the Quantity Surveyor
First : in the consultant office :Stage 1 :During the preparation of bidding
documents :- Preparation of the BOQ from the design drawing
which part of bidding documents.- Preparation of cost estimate for items listed in BOQ- Review and check the bids submitted from bidders.- Preparation of the lists of the contents of bids
received.- Sharing in evaluation and preparation of t
recommendation to award the contract to be submitted to owner.
Quantity Surveyor TasksQuantity Surveyor Tasks
22 Stage 2 :Stage 2 : During the supervision of the During the supervision of the constructionconstruction
- Review and checking the payments submitted from the contractor.
- Preparation of the reports about the conformity of the quantities items with contract documents.
Second : In the Contractor CompanySecond : In the Contractor Company
- During the implementation :- During the implementation :- Review and checking the BOQ at the starting of the
work.- Prepare the eng. Measurement for the quantities of
the finished works.- Prepare lists of the site needs (material, workers,
technicians)- Calculate the remuneration of the subcontractors,
workers, equipments,…etc.- Prepare the payment statements- Prepare the detailed reports describing the situation of
the items quantities, (plus or minus the contract BOQ)
Required SkillsRequired Skills
Ability to understand the drawings details, design drawings, shop drawings, as built ).
Excellent knowledge of the calculation of the areas and volumes, knowledge of fees of workers e /technicians/ , rules and law of the contracts,
In addition to the knowledge of related financial issues/ taxes, banks transactions, insurances and its implication.
Knowledge of the productivity of the workers and technicians.
Stages of the Quantity SurveyStages of the Quantity Survey
Stage1 : preparation of the engineering measurement and calculations of the works during the preparation of the bidding documents (consultant) and
- preparation of the measurement of the accomplished works in the site and prepare in the site and prepare the payment (contractor)the payment (contractor)
Stage 2 : preparing BOQStage 3 : review and check the financial
payments.
Areas, Volumes, & Surface areas
See attached PDF file
Next Lecture :Special calculations of the areas and volumes.Measurement of the works.
Method of measurements 1- Conventional measurement (1- Conventional measurement ( البلدي البلدي الكيل ((الكيلDepends on experience, and type of project.Doesn't govern by theories or engineering basics.Not considered as scientific method.Doesn't subtract the opening as windows or doors from the
block, plastering, painting works and computing whole wall.Another example : as the every 3 steps in stair = 1 m3
2- Engineering measurement (2- Engineering measurement ( الهندسي الهندسي الكيل ((الكيلIt is calculating all the works finished after subtracting all
opening.
Cont.unit measurement example
Lump-sum (L.S)
Works have details difficult to be
calculated
Earth work, earthling system (electrical),,
M.R Works have specific length and width
As pipes
No. Works have 3 dim. fixed
Windows, doors,
M2 Works with specific thickness,
as plastering, painting,
M3 Variable dimensions
Footings, columns, stairs,
Ton / kg Have specific width As steel
Day / hrs Labor / equipment Workers wages, equipment,
Types of construction works
Building constructionRoads construction Water Booster P.S and piping,Sewage and storm water P.S and piping.Electrical construction
Preparation of engineering measurements
measurement sheet project name _________________contractor name ____________engineer name _______________
length width heigth Total amountDimension
SN Description Unit Quantity Unit rate
Item unit Method of measurement
Site leveling Lump sum It takes into consideration all site leveling including the excavation, fill, till reach 0+B.M according to design drawing.
Excavation (cut) m3 Measured by 2 methods :1- footings areas according to blinding area * depth of excavation according to drawings.2- external dimensions of the building *depth of footings
Fill (backfill) m3 = excavation – concrete work for footings and columns under ground level. = ground plan *depth of ground beams – (concrete for ground beams and ground floors)
Measurement of works / Earth Work
Concrete works measures engineering measurement
All opening more than 0.1m2 or 0.1 m3 are deducted.
The concrete works more than the areas, volumes in the drawings doesn’t included.
Measurement of works / concrete works
Measurement of works / concrete works
Item unit Method of measurement
Blinding concrete, ground concrete, benching, and slabs concrete with fixed thickness
m2 = length * width (the thickness should be specified in the drawings and specifications) Ribs blocks don’t subtract from the slabs concrete.
Footings, columns, ground beams, stairs, and canopies,
m3 = length*width*thickness-Ground beams are measured from its connection with columns- concrete stars include the stairs , steps, stair slabs, walls supporting the stairs.
Concrete decoration works as curves.
No. The dimensions must be specified in the drawings.
Measurement of works / block worksItem unit Method of measurement
Block works m2 = length * width (the thickness should be specified in the drawings and specifications) - subtracting all openings more than 0.1 cm2.
Measurement of works / Plastering/ painting works
Item unit Method of measurement
Length * width M2 = length * width (engineering measurement after subtracting the openings, more than 0.1 m2) - the area is measured above the skirting (terrazzo chips)
Internal plastering = walls + slabs
Measurement of works / tilling works
Item unit Method of measurement
Terrazzo, marble, ceramic
m2 = length * width (engineering measurement)
Measurement of works / Plastering/ painting works
Item unit Method of measurement
Plastering & painting
M2 = length * width (engineering measurement after subtracting the openings, more than 0.1 m2) - the area is measured above the skirting (terrazzo chips)
Internal plastering = walls + ceiling
Measurement of works / Doors
Item unit Method of measurement
Doors No. The exact dimensions should be specified in the design drawings.Sometimes carpentry works measured in m2 or m length according to the item described in BOQ.
Measurement of works / Windows
Item unit Method of measurement
windows No. The exact dimensions should be specified in the design drawings.Sometimes carpentry works measured in m2 or m length according to the item described in BOQ.
Measurement of works / electrical & sanitary works
Item unit Method of measurement
Electrical and sanitary pieces / accessories
No. The dimensions should be specified clearly in the design drawings as the sockets, lamps, fluorescent lighting,…etc(W.C. , washing basins, sinks, manholes, pumps…etc)
piping M.R The dimension and details should be specified in the drawings, as (cables, pipes, ..etc)
Works with special detail
Lumps sum All details should be specified in the drawings, as earthing, gas network,
Bill of QuantitiesThe results in the quantities book, are recorded in the BOQ table.It is preferable to add 5-10% percentage on the quantities for
contingency to avoid any errors or any.
Preparation of engineering measurements
measurement sheet project name _________________contractor name ____________engineer name _______________
length width heigth Total amountDimension
SN Description Unit Quantity Unit rate
Item unit Method of measurement
Site leveling Lump sum It takes into consideration all site leveling including the excavation, fill, till reach 0+B.M according to design drawing.
Excavation (cut) m3 Measured by 2 methods :1- footings areas according to blinding area * depth of excavation according to drawings.2- external dimensions of the building *depth of footings
Fill (backfill) m3 = excavation – concrete work for footings and columns under ground level. = ground plan *depth of ground beams – (concrete for ground beams and ground floors)
Measurement of works / Earth Work
Concrete works measures engineering measurement
All openinng more than 0.1m2 or 0.1 m3 are deducted.
The concrete works more than the areas, volumes in the drawings doesn’t included.
Measurement of works / concrete works
Measurement of works / concrete worksItem unit Method of measurement
Blinding concrete, ground concrete, benching, and slabs concrete with fixed thickness
m2 = length * width (the thickness should be specified in the drawings and specifications) Ribs blocks don’t subtract from the slabs concrete.
Footings, columns, ground beams, stairs, and canopies,
m3 = length*width*thickness-Ground beams are measured from its connection with columns- concrete stars include the stairs , steps, stair slabs, walls supporting the stairs.
Concrete decoration works as curves.
No. The dimensions must be specified in the drawings.
Measurement of works / block worksItem unit Method of measurement
Block works m2 = length * width (the thickness should be specified in the drawings and specifications) - subtracting all openings more than 0.1 cm2.
Measurement of works / Plastering/ painting works
Item unit Method of measurement
Length * width M2 = length * width (engineering measurement after subtracting the openings, more than 0.1 m2) - the area is measured above the skirting (terrazzo chips)
Internal plastering = walls + slabs
Measurement of works / tilling works
Item unit Method of measurement
Terrazzo, marble, ceramic
m2 = length * width (engineering measurement)
Measurement of works / Plastering/ painting works
Item unit Method of measurement
Plastering & painting
M2 = length * width (engineering measurement after subtracting the openings, more than 0.1 m2) - the area is measured above the skirting (terrazzo chips)
Internal plastering = walls + ceiling
Measurement of works / Doors
Item unit Method of measurement
Doors No. The exact dimensions should be specified in the design drawings.Sometimes carpentry works measured in m2 or m length according to the item described in BOQ.
Bill of Quantities The results in the quantities book, are recorded in
the BOQ table. It is preferable to add 5-10% percentage on the
quantities for contingency to avoid any errors or any.
No. Item description unit Quantity Unit price($ or NIS …)
Total amount($ or NIS …)
1 The works include…… L.S
Bill of Quantities
See the attached example
The items are classified into categories as shown in the next table.
at the end of BOQ, summary of the items are shown as well as the total amount of the price
Bill of Quantities
Summary tableNo. Item Total amount
($ or NIS …)
1- EXCAVATION & EARTH WORKS
2 CONCRETE WORKS
3- BLOCK WORK
4- CARPENTRY
5- METAL WORK
6- FINISHING WORKS
7- PLUMBING WORKS
8- ELECTRICAL WORKS
9- MISCELLANEOUS
Item description Based on drawings, specification. It should be accurate and reflect the
drawings and specifications, Description should include :
1- description of the works2- unit3- determine the method of measurement.
How to read the description Description of the items Drawings, details Specifications General and specific conditions Instruction of the supervisor engineer
the work price should include The description of the item should
include all the work that the unit price will take account of as will be illustrated in the following
1- Earth work The unit price should include :- Excavation in any kind of soil, rock, etc., starting at reduced
level (bottom of G.B. blinding) down to bottom of foundation blinding including compacting backfill around foundations and shall be applied on layers, 200 mm thick, watered and compacted to 95 % (98%) according to modified AASHTO Density Test T-80.for the excavated foundation and removal of surplus material from site to an approved dumping area complete as per specifications.
- Site Leveling. (Excavation of all Site including External Works). Cut and / or fill in any kind of soil, concrete, or asphalt; to the required Levels approved by the Engineer (Reduced Level). Including scraping of top. Any damage to the external walls, fence, etc. should be maintained without any compensations..
- Test of the soil (4 points at least)- Safety around the site,- Work according to engineer instruction and specifications
Concrete workConcrete works include: All formworks and shuttering in any form, shape and size.
Making chamfered and curved edges, allowing for and making grooves and sleeves and the like; removal of forms and cleaning of all exposed tie wires and rods; making good the harmed surfaces and
Supplying, Casting, vibrating and curing as per specifications. Approved additives and admixtures. Incurred costs on Concrete Mix Designs, Sample taking,
testing and providing test results certificates, storing and saving of samples, and preparation of bar bending schedules and workshops.
Supplying reinforcement of any grade, size and length as detailed in the drawings, storing on site including cutting, bending and fixing in position and providing all tying wires, spacers, shop drawings, testing and bar bending schedules
Concrete work (cont’d) Painting of exposed surfaces of underground
reinforced concrete elements with two coats of Bituminous Emulsion. Supply of Polyethylene sheets under ground slabs.
Steel bars used for alignment and fixing of reinforcement works, and extra steel added to assure proper detailing and safety.
Measurement of Concrete elements shall be the net dimensions as detailed in the drawings. All recesses, openings and voids shall be deducted.
Measurement shall be only for the seen surfaces of elements, overlapping and measuring items twice under separate headings shall not be allowed.
Supplying and fixing of the required steel reinforcement as per drawings and specifications.
Block worksRates of Block works include All works of the bill shall be of Concrete blocks of high
quality standards and as per specifications. Vertical and horizontal joints., Cement and mortar,
Galvanized angles and ties., Closed end blocks at all ends, door and window jambs, reveals and the like.
Concrete filling including reinforcing steel to cavities at quoins and door and window openings.
Lintels and bond beams to the full length of the wall, and all needed to complete job as per drawings and
specifications concrete infill and transporting, placing compacting,
curing, surface finishing, protection, construction and expansion joints and all labors and materials and tests.
Block works (cont’d)
Block work shall be bonded to concrete columns, wall and the like with concrete infill B250. block must be stopped in graded shape (10-15 cm from the concrete face) one 8 mm bar must cast in columns during casting with 40 cm length fixed every 42 cm horizontally, in addition to two vertical 10 mm bars.
Plastering works, includes The price shall include, all narrow widths, for taking out
joints on block walls or backing concrete face for key, for making good to frames around pipes and other fittings , plastering to jambs and reveals of openings ( النافذة من جانب
للجدار الخارجى السطح وبين اطارها side of columns, window ,(بينsills; all of which shall be included Price shall also include Expanded metal lath, angle beads at all corners and plaster stops at opening edges, expansion joints, sills, labor, curing, erecting and dismantling of scaffoldings سقاالت), additives, pigments and all incidentals required as specified
Material, workmanship, Galvanized mesh, or plastic mesh, False ceiling from galvanized mesh and plastering (fixing mesh , covering it by 3-coats of rough plaster) reinforcement of the joints between different material as
the joints between the wall and columns.
Tilling works Rate shall include preparation of surfaces under tiles, special tile
peace’s for edges and the like, tile surface finishing, Plastic spacers. Pointing and cleaning and all incidental as per specifications.
Supply, Install and Terrazzo Tiles, include, bedding and jointing in cement and sand mortar, pointing with white cement, required sand fill, and polishing, workmanship, and all incidental as per specifications
Isolation works for kitchen and bathroom (layer of fiber glass, and bitumen layers)
Marble includes connections, joints, mortar, and any other needed work. Supply and install a layer of cement and sand under marble and
porcelain , ceramic, according to specification and engineer instruction. Supply and spread a layer of sand under the tiles. Any decoration works as drawings
Painting works All Paints shall be supplied to site in sealed
container, as approved by the Engineer, and site mixing shall not be permitted.
The Contractor rates shall include for supply of all materials, workmanship, samples, surface preparation , protection of painted surfaces , application to all heights as required of works, repair of all damaged surface, as per specification.
CARPENTRY AND JOINERY WORKS (window & doors) Sizes of carpentry works given in the Bills of Quantities are finished sizes
and shall be as per Drawings. Sizes of doors and other items mentioned in the Bills of Quantities shall
allow for tolerance to suit the structural openings shown in the Drawings. Wooden doors and pair of doors shall be measured in square meter for
each structural opening, unless stated otherwise in the Bills of Quantities. Rates for carpentry and joinery work shall include : Shop and coordinated drawings. frames, architrave (عارضة ), and other holders Allowance for plastering and tiling and the like. Cutting and fitting around obstructions, Bedding and painting. Grounds, blocking and backings. Plugging concrete, block work, and stone work , and making good. Ironmongery including cylindrical locks, handles, stoppers, screws,
temporary fixing, re-fixing, oiling and adjusting.
STEEL AND ALUMINUM WORKS
Rates for metalwork shall include for : Preparing shop drawings, Drilling, counter sinking, screwing, bolting and riveting. Sub frames, including galvanized steel frames for Aluminum
windows and architrave. Gaskets, sashes, double weather strips and external and internal
approved quality silicon filling around frames. Ironmonger including cylindrical locks (Union or equal) , stoppers,
handles, temporarily fixing, refitting, oiling and adjusting. Providing two keys for each lock . Glass and glazing including cutting to size, putty and rubber. Preparing surfaces for and painting one coat of primer before
fixing. Sealing and Painting to any area or width in any location including
work in multicolor and cutting in edges. All other accessories and incidentals required to execute the work.
Electrical works All items price to include Supply, Installing, Connecting and
testing unless otherwise indicated, the contractor are requested to have approved full coordinated work shop drawings before starting contract activities, the price also includes all works necessary to implement electrical works in approved manner.
The contractor intended to order main and final distribution panel boards according to approved manufacturer drawings.
The price to include submittals, catalogs, any manufacturer instruction .
The contractor should install and construct all works according to drawings , specification tender documents, and requirement of Electrical Co.
Contractor should also test & submit the electrical Work to the Electricity Co. & Municipality.
PLUMBING, SANITARY AND MECHANICAL WORKS
Rates shall include all fittings , fixtures , appliances and pipe laying Supply of material, workmanship, installation, testing and commissioning.
Rates to include also all peaces and fittings, including by passes , floats, cleaning outlets , automatic vents, vents and stack covers, valves and non return valves and the like needed to complete works as per specifications.
Insulation and painting as called for in specifications. Excavation and cutting for all pipe laying works, bedding
back filling and all works connected with pipe laying. All ties, sleeves, joints, tie bolts and rods, brackets and
the like. Rates to include Workshops, Coordinated and as- built
drawings as approved by the Engineer
Pricing & price analysis Before construction three types of pricing :
1- cost estimate2- pricing3- cost analysis
Factors affecting the pricing
Raw material Workmanship, labor, sub-contractors Administration cost including direct cost as salaries,
equipments, transportation ..etc. and indirect cost as electricity, communication cost, banks , municipality fees, ,,,etc.
Unforeseen expenses & risk (3-5%) Insurances Taxes as income tax, V.A.T, Profit (7-10%)
Productivity of labor
It is necessary to calculate the productivity for the work teams either worker or technicians / equipments to calculate wages, for workers / subcontractors.
Productivity is measured per hour or per day.
Pricing analysis stages :Estimate the price for raw material and
workmanship.Estimate the percentage of the specified
work from the total project work . (work item/total work *100%)
Estimate the cost of administration / management , tax, insurances, risk, and profit.
Estimate the total cost for all works item.Estimate the unit price for each item.
Example:Analyze the prices, and find the unit price for
the following, knowing that, 1- Administrative expenses is fixed (1000$) for
project2- Unfixed expenses / indirect (400$)3- Insurance 200 $
ID Description of work unit quantity
1 Concrete footings M3 78
2 Block works for wall (20*20*24cm) M2 100
3 Internal plastering M2 200
4 Wooden door 90*220 No. 10
1- Price for raw material and workmanship- Concrete footing (B250)
ID Description Raw material per m3
price workmanship
1- Concrete footings (B250) Concrete 190 100Steel 170Wires 5
Nails, bolts 2
Water 1isolation 3
total 371 100Total price (NIS) 471Total price ($) 134$
Total for 78 m3 134*78 = 10,960 $
ID Description Raw material per m2
price workmanship
Block 20*20*40 block 12.5*2=25 6
Morter 3
Moving the blocks
2
Joints, concrete fill
5
total 35 6
Total price (NIS) 41
Total price ($) 11.7
Total for 78 m3 11.7*100= 1170$
Block work (20*20*40 cm)
Internal plastering
ID Description Raw material per m2
price workmanship
Internal plastering scaffolding o.5 6
Morter 4
Angles, metal grid, ..etc
0.5
water 0.5
total 6 6
Total price (NIS) 12
Total price ($) 3.4
Total for 200 m2 3.4*200= 680$
Wooden doors 220*90 cm
ID Description Raw material per m2
price workmanship
Wooden door 220*90 material 400 50
Misce. 20
total 420 50
Total price (NIS) 470
Total price ($) 135
Total for 10 doors 135*10 =1350$
percentage of the specified work from the total project work
ID Description Total work price % from total work
1 Concrete footings (B250) 10960 77.40%
2 Internal plastering 680 4.80%
3 Wooden door 220*90 1350 9.53%
4 Block 20*20*40 1170 8.26%
5 Total 14160 100.00%
2- the cost of administration / management , tax, insurances, risk, and profit.
administration expenses
ID Description fixed (1000$)
variable (400$)
tax (10%)
Insurance
(200$)
risks (5%)
profit (10%)
Total
1 Concrete footings (B250)
774.01 309.6 1096 154.8 548 1096 3978.4
2 Internal plastering
48.02 19.21 68 9.61 34 68 246.8362
3 Wooden door 220*90
95.34 38.14 135 19.07 67.5 135 490.04
4 Block 20*20*40 82.63 33.05 117 16.53 58.5 117 424.70
total cost for all works itemID Description stage (1) stage (2) total
1.00 Concrete footings (B250)
10,960.00 3,978.42 14,938.42
2.00 Internal plastering 680.00 246.84 926.84
3.00 Wooden door 220*90 1,350.00 490.04 1,840.04
4.00 Block 20*20*40 1,170.00 424.70 1,594.70
unit price for each itemID Description unit quantity unit price total
1.00 Concrete footings (B250)
m3 78.00 191.52 14,938.42
2.00 Internal plastering m2 200.00 4.63 926.84
3.00 Wooden door 220*90
no 10.00 184.00 1,840.04
4.00 Block 20*20*40 m2 100.00 15.95 1,594.70
Lecture 7Estimating & Evaluation
Form of evaluation based on cost per unitID Description unit Unit price
1 Concrete footings m3 200
2 Block 20*20*40 m2 20
3 Wooden door 220*90 cm no 300
4 Internal plastering m2 6
Cost per m2 of floor area(residential building)
Description (m2)
stores Ground floor
First floor
Structural elements
70 80 60
finishing 40 80 80
total 110 160 140
Cost of housing unit = cost of m2 * the areas of the unit
Analysis of quantitiesAnalysis to raw material quantities for example
:- Concrete : cement, water, aggregate, steel, - Cement in 1m3:- Mixing proportion (4:2:1) = 300kg, 6:3:1 =
200 kg, - 8:4:1 = 150 kg- 1m3 concrete = 80% aggregates, 40% sand- 1m3 (footings) = 60kg
Miscellaneous works1m2 block (40*20*20) = 12.5 block1m2 tiling (25*25) = 16 1 sack of cement = 1 m2 plastering1 sack cement = built 100 blocks
Estimation of Concrete price1 m3 concrete consist of :350 kg cement 1.2 ton aggregates0.8 ton sandPrice of mixing and pouring, transportationThe total price will be = 0.35
*300NIS+1.3*40+0.8*120+20 (mixing)
Steel reinforcement In general and according to practices, the
following elements contains , Steel reinforcement
Footings = 60kg/m3Columns = 200 kg/m3Ground beams, stairs,= 80kg/m3Slabs = 17kg/m2
Payment certificateFinancial Request for payment, prepared by
contractors, and approved by consultant / owner , describing the actual achieved works , by calculating the unit price by the quantity of item done.
It is important for the contractor as well as for the owner. For the contractor, he gets the value of works done, and save to him liquidity
for the owner , he become aware of the progress, achieved (actual) and planned, therefore, he can know if there is any obstacles or delay.
Preparation of payment
Types of payment certificates1- interim payment certificate2- final statement / final payment certificates
1- interim payment certificateIt is request for payment, contains quantity
survey for the accomplished works , and other supporting details submitted by contractor over the progress period of the project, .
The amount of each request should not be less than 10% of the contract value or according to contract conditions
Contents of the payment certificate1- Financial Payment Certificate: it is a survey
of the accomplished works (actual done), multiplied by its value according to the contract.
2- Measurements : 3- Drawings : as built drawings.
Content of the Payment Certificate
It contains :1- summary, describing the commencement date,
project end date, in addition to other data as contract value, variation order, percentage of the accomplished works, value of the current payment, and due payment, any amount to be deducted for retention, Percentage of retention stated in the Contract Data to the total of the above, and Retention Money (if any) stated in the Contract Data; any amounts to be added and deducted for the advance payment , the deduction of amounts certified in all previous Payment Certificates.
Payment Certificate2- total price of the accomplished works, and
percentage of the work done in relation to total project.
3- other supporting documents including the description of the items, progress in each item previously and also current, unit price, total percentage of the project progress.
Second : measurementsAnd it is table of actual quantity survey
accomplished, including item description, number, volume (length, width, height) and the total.
Third : As build drawings, describing the details of the work done,
Payment Certificate
Final payment certificateIt is called the final payment / certificate after
the primary taking over the project.The process of approval as follows:1- after taking over the project, final request
for payment is prepared, the contractor signed the request for
payment and the measurement sheet, and submitting it to engineer / owner.
2- to be paid the following documents should be attached :
Copy of taking over certificate signed form the committee
Copy of the bid submitted from the contractor after considering the prices in the request for payment
defect liability securityAll tests resultsDeduction of the works that mentioned in the
taking over or any liquidated damages.Letters of project extension if it was
extended.
Final payment certificateContents of the final payment certificate :Application for the requestList of the actual accomplished works and its
value.List of measurementsAs build drawings as it was approved from
the engineer.
Table of reinforcement steel weights :
Diam Wt of 1m length(kg) Area of section (mm2) Perimeter (mm)
6 0.222 0.283 1.884
8 0.395 0.502 2.521
10 0.617 0.785 3.14
12 0.888 1.13 3.768
14 1.209 1.539 4.396
16 1.58 2.01 5.024
18 1.999 2.543 5.652
20 2.468 3.14 6.28
22 2.986 3.799 6.908
25 3.856 4.906 7.85
28 4.837 6.154 8.792
32 6.318 8.038 10.048
36 7.996 10.174 11.304
40 9.872 12.56 12.56
Weight of 1m of steel bar = (diameter, cm)2 * 0.617
Area of section = π r2
Perimeter (mm) = 2 π r
Footing tableF1, C1F2, C2 F3, C3F4, C4
Length of steel Bars :F1 : 1.5 x 1.3 x 0.45 m, Reinforcement
= 11φ12 , & 9 φ12F2 = 1.7 x 1.5 x 0.45 m,
Reinforcement = 13φ12 , & 11 φ12F3 = 1.9 x 1.7 x 0.45 m, Reinforcement
= 14φ12 , & 12 φ12F4 = 2.1 X 1.9 X 0.5 m, Reinforcement
= 16φ12 , & 14 φ12Concrete cover = 5 cm
For F1: Length of steel in longitudinal direction: Ls = 1.5 - .05*2 =1.4 m In vertical direction at both sides = (0.45-0.05*2)/3 *2= 0.24 m The total for bar in longitudinal direction =
1.4+0.24+0.12*2=1.88 m The total length for all steel in longitudinal direction = length of 1
bar *number of bars in the direction = 1.88*11=20.57 m In traverse direction: = 1.3 – 0.05*2+0.12*2+0.24 = 1.68m Total length for all steel in the short direction = 9 *1.68 = 15.12
m The total in both direction = 35.69 m WT of steel for one foot type F1 = 35.69 * 0.888= 31.693 kg For all F1 = 31.693 *4 = 126.77kg.
ID Item description
unit Diam. Length of bar
Total length
Wt of 1m
Total Wt
No. of footings
Total WT for all F1
drawings
1 Reinforcement steel for footings :
F1 Kg Φ12 In long direction = 1.88
In short direction = 1.68
1.88*11+1.68*9 =
35.69 m
0.888 31.693
4 126.77
For column neck:
C1 = 25*60, 6φ14 (F1 : 1.5 x 1.3 x 0.45 m,
Reinforcement = 11φ12 , & 9 φ12)Length of one bar:Excavation depth = 1.5 m, floor
height = 0.48 mSteel leg = 1.5 – (0.05*2)/4 = 0.35
mThe total length = 1.5
+0.48+0.35+0.14 – 0.1 – 0.05 – 0.024 = 2.296 m
For stirrups:If length of column section <60cm, one
stirrup is needed, but if it is > 60cm, two ties is needed
Concrete cover for column = 2.5 cmFor C1 = 25*60Length of stirrups= (0.6 – 0.05)*2 = 1.1mWidth of stirrup= (0.25-0.05 )*2 = 0.4mTotal length of the stirrup= 1.1+0.4+0.08*2
= 1.66m