Procurement Specification Revision History Sheet

RP 12/14/09

1. Specification No 2. Revision 3. Page

C-SPP-Z-00007 Saltstone Disposal Cells 3 and 5 (U) 0 2 of 3 .

4. Date 5. Revision No. 6. Paragraph No. 7. Description of Changes

12/14/2009 0 All Issue for use

Page 3: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 3 of 3

RP 12/14/09

TABLE OF CONTENTS

SECTION TITLE No. of Pages

- Approval, History and Table of Contents 3 DIVISION 1 – GENERAL REQUIREMENTS

01004 Index Of Documents and Drawings 2 01100 Summary Of Work 8 01250 Change Procedures 3 01320 Site Surveys 6 01330 Submittal Procedures 3

Attachment 01330-A: Engineering Document Requirements 4 Attachment 01330-B: Quality Verification Document Requirements 5

01400 Quality Requirements 3 Attachment 01400-A: Supplier Quality Assurance Program Requirements 3

01450 Inspection and Testing Laboratory Services 4 01600 Material and Equipment 3

DIVISION 2 - SITE WORK

02310 Excavation and Foundation Preparation 5 02320 Backfill and Finish Surface 10 02370 Erosion and Sediment Control 4

Attachment 02370-A: Stormwater Pollution Prevention Plan Inspection Form 2 02378 High Density Polyethylene Liner 13

Attachment 02378-A: Additional HDPE Liner Installation Requirements & Allowances 1 02379 Geosynthetic Clay Liner 12 02625 Liquid Collection Layer 9 02630 Storm Drainage 5 02900 Soil Preparation and Seeding 8

DIVISION 3 - CONCRETE

03300 Cast-In-Place Concrete 11 Attachment 03300-A: Type V Mix Design 1 Attachment 03300-B: Material, Installation, & Inspection Requirements for Type V

Concrete Dry Packing of Bolt Holes 1

Attachment 03300-C: Type V Concrete Compressive Strength Testing Requirements 1 Attachment 03300-D: Type II Concrete Compressive Strength Testing Requirements 1 Attachment 03300-E: Shotcrete Compressive Strength Testing Requirements 1 Attachment 03300-F: Representative Compressive Strength Curves for Type V

Concrete 1

DIVISION 13 – SPECIAL CONSTRUCTION

13210 Storage Tanks 16 Attachment 13210-A: Grout Level Marking Sketch 1 Attachment 13210-B: Anchor Requirements 4 Total No. of Pages: 154

Page 4: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 1 of 2

RP 12/14/09 Section 01004 Index Of Documents and Drawings

INDEX OF DOCUMENTS AND DRAWINGS

SECTION 01004

PART 1 GENERAL

1.1 SECTION INCLUDES

A. List of documents and drawings associated with Saltstone Disposal Cells 3 and 5.

1.2 DOCUMENTS AND DRAWINGS

A. WB00001K-004, Vaults 2A and 2B Tank Drawings (Sheets 1 through 15)

B. WB00001K-006, Tank Calculations

C. WB00122W-002, Z-Area Saltstone Disposal Cells 3 & 5 Overall Site Plan

D. WB00122W-003, Z-Area Saltstone Disposal Cells 3 & 5 Site Clearing And Erosion Control Plan

E. WB00122W-004, Z-Area Saltstone Disposal Cells 3 & 5 Stockpile Clearing And Erosion Control Plan

F. WB00122W-005, Z-Area Saltstone Disposal Cells 3 & 5 Stockpile Area Grading Plan

G. WB00122W-006, Z-Area Saltstone Disposal Cells 3 & 5 Stockpile Area Cross-Sections

H. WB00122W-007, Z-Area Saltstone Disposal Cells 3 & 5 Temporary Sedimentation Basin Plans, Sections, And Details

I. WB00122W-008, Z-Area Saltstone Disposal Cells 3 & 5 Sedimentation Basin Details And Sections

J. WB00122W-013, Stormwater Pollution Prevention Plan (SWPPP)

K. WB00122W-019, Z-Area Saltstone Disposal Cells 3 & 5 Pre-Construction Excavation Plan

L. WB00122W-020, Z-Area Saltstone Disposal Cells 3 & 5 Pre-Construction Excavation Sections And Details

M. WB00122W-021, Z-Area Saltstone Disposal Cells 3 & 5 Pre-Construction Excavation Cross Sections

N. C-CG-Z-00037, Z-Area Saltstone Disposal Cells 3 & 5 Mudmat Marker Cells 3 & 5 Section And Details

O. C-CG-Z-00038, Z-Area Saltstone Disposal Cell 3 &5 Settlement Marker Cells 3 & 5 Section And Details

P. C-CH-Z-00019, CBU - Saltstone Storage Disposal Cells 3A & 3B Drain Water Collection System Piping Arrangement And Pipe Support

Q. C-CH-Z-00020, CBU - Saltstone Storage Disposal Cells 5A & 5B Drain Water Collection System Piping Arrangement And Pipe Support

R. C-CX-Z-00003, Saltstone Disposal Site Cylindrical Disposal Cells General Arrangement Plan

S. P-PE-Z-00010, Savannah River Plant 200-Z Area Saltstone Disposal Site Cylindrical Disposal Cells 3A & 3B Equipment Arrangement Roof Plan & Section

Page 5: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 2 of 2

RP 12/14/09 Section 01004 Index Of Documents and Drawings

T. P-PE-Z-00011, Savannah River Plant 200-Z Area Saltstone Disposal Site Cylindrical Disposal Cells 5A & 5B Equipment Arrangement Roof Plan & Section

U. OSR 45-4, Supplier Deviation Disposition Request (Form)

V. C-QP-Z-00001, Sample Quality Program Guidance for Disposal Cells 3 & 5

PART 2 PRODUCTS Not Used.

PART 3 EXECUTION Not Used.

END OF SECTION

Page 6: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 1 of 8

RP 12/14/09 Section 01100 Summary Of Work

SUMMARY OF WORK

SECTION 01100

PART 1 GENERAL

1.1 SECTION INCLUDES

A. References

B. Definitions

C. Location of the Work

D. Project Summary

E. Work by Others

F. Work Sequence

G. General Requirements

H. Site Requirements

I. Existing Conditions

J. Administration

K. Acceptance and Inspection

1.2 RELATED SECTIONS

A. All Sections in this Specification

1.3 REFERENCES:

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards

1. American Association State Highway Transportation Officials (AASHTO) a. M 294, 2009, Standard Specification for Corrugated Polyethylene Pipe, 300-

to 1500- mm Diameter

2. American Concrete Institute (ACI) a. 117, 2006, Specifications for Tolerances for Concrete Construction and

Materials and Commentary b. 211.1, 1991, Standard Practice for Selecting Proportions for Normal,

Heavyweight, and Mass Concrete c. 229R, 1999 (R 2005), Controlled Low-Strength Materials d. 301, 2005, Specifications for Structural Concrete e. 305R, 1/1/1999, Hot Weather Concreting f. 306R, 1/1/1988, Cold Weather Concreting g. 318, 2008, Building Code Requirements for Structural Concrete (ACI 318-08)

and Commentary

Page 7: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 2 of 8

RP 12/14/09 Section 01100 Summary Of Work

h. 347, 2004, Guide to Formwork for Concrete i. CP-60, 2002, Craftsman Workbook for ACI Certification of Shotcrete

Nozzleman

3. American Society of Civil Engineers (ASCE) a. 7-05, 1/1/2006, Minimum Design Loads for Buildings and Other Structures

4. American Society for Testing and Materials (ASTM) a. A 36/A 36M, 2008, Standard Specification for Carbon Structural Steel b. A 48, 2003, Standard Specification for Gray Iron Casting c. A 193 /A 193M, 2009, Standard Specification for Alloy-Steel and Stainless

Steel Bolting Materials for High Temperature or High Pressure Service and Other Special Purpose Applications

d. A 194 /A 194M, 2009, Standard Specification for Carbon and Alloy Steel Nuts for Bolts for High Pressure or High Temperature Service, or Both

e. A 563 REV A, 2007, Standard Specification for Carbons and Alloy Steel Nuts

f. A 615/A 615M, 2009, Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement

g. A 821/A 821M, 2005, Standard Specification for Steel Wire, Hard Drawn for Prestressing Concrete Tanks

h. A 992/A 992M REV A, 2006, Standard Specification for Structural Steel Shapes

i. A 1008/A 1008M REV A, 2009, Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardenable

j. C 31/C 31M, 2009, Standard Practice for Making and Curing Concrete Test Specimens in the Field

k. C 39/C 39M, 2005 (E 2006), Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens

l. C 40, 1/1/2004, Standard Test Method for Organic Impurities in Fine Aggregates for Concrete

m. C 94/C 94M, 2009, Standard Specification for Ready-Mixed Concrete n. C 109/C 109M, 2008, Standard Test Method for Compressive Strength of

Hydraulic Cement Mortars (Using 2-in. or [50-mm] Cube Specimens) o. C 117, 8/1/2004, Standard Test Method for Materials Finer than 75-µm

(No. 200) Sieve in Mineral Aggregates by Washing p. C 136, 2/15/2006, Standard Test Method for Sieve Analysis of Fine and

Coarse Aggregates q. C 138/C 138M, 6/1/2009, Standard Test Method for Density (Unit Weight),

Yield, and Air Content (Gravimetric) of Concrete r. C 142, 8/10/1997, Standard Test Method for Clay Lumps and Friable

Particles in Aggregates (R2004) s. C 143/C 143M, 2009, Standard Test Method for Slump of Hydraulic-

Cement Concrete t. C 172, 6/1/2008, Standard Practice for Sampling Freshly Mixed Concrete

Page 8: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 3 of 8

RP 12/14/09 Section 01100 Summary Of Work

u. C 231, REV A, 2009, Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method

v. C 443, 2005, Standard Specification for Joints Circular Sewer and Culvert Pipe Using Rubber Gaskets

w. C 566, 1/10/1997, Standard Test Method for Total Evaporable Moisture Content of Aggregate by Drying (R2004)

x. C 602, 2007, Standard Specification for Agricultural Liming Materials y. C 685/C 685 M, 2007, Standard Specification for Concrete Made by

Volumetric Batching and Continuous Mixing z. C 913, 2008, Standard Specification for Pre-cast Concrete water and

Wastewater Structures aa. C 1064, 1/15/2008, Standard Test Method for Temperature of Freshly

Mixed Portland Cement Concrete bb. D 413, 1998 (R2007), Standard Test Method for Rubber Property

Adhesion to Flexible Substrate. cc. D 422, 1963 (R 2007), Standard Test Method for Particle-Size Analysis of

Soils dd. D 792, 2008, Standard Test Methods for Density and Specific Gravity

(Relative Density) of Plastics by Displacement ee. D 1004, 2009, Standard Test Method for Tear Resistance (Graves Tear) of

Plastic Film and Sheeting ff. D 1238, 2004, Standard Test Method for Melt Flow Rates of

Thermoplastics by Extrusion Plastometer. gg. D 1248, 2005, Standard Specification for Polyethylene Plastics Extrusion

Materials for Wire and Cable hh. D 1505, 2003, Standard Test Method for Density of Plastics by the

Density-Gradient Technique ii. D 1556, 2007, Standard Test Method for Density and Unit Weight of Soil in

Place by the Sand-Cone Method jj. D 1557, 2007 (E 2003), Standard Test Methods for Laboratory

Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3))

kk. D 1603, 2006, Standard Test Method for Carbon Black in Olefin Plastics ll. D 2216, 2005, Standard Test Method for Laboratory Determination of

Water (Moisture) Content of Soil and Rock by Mass mm. D 2487, 2006, Standard Practice for Classification of Soils for Engineering

Purposes (Unified Soil Classification System) nn. D 3212, 2007, Standard Specification for Joints for Drain and Sewer

Plastic Pipes Using Flexible Elastomeric Seals oo. D 3350, 2008, Standard Specification for Polyethylene Plastics Pipe and

Fittings Materials pp. D 3786, 2009, Standard Test Method for Hydraulic Bursting Strength of

Textile Fabrics Diaphragm Bursting Strength Tester Method qq. D 3895, 2007, Standard Test Method for Oxidative-Induction Time of

Polyolefins by Differential Scanning Calorimetry

Page 9: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 4 of 8

RP 12/14/09 Section 01100 Summary Of Work

rr. D 4218, 1996 (R2008), Standard Test Method for Determination of Carbon Black Content in Polyethylene Compounds by the Muffle-Furnace Technique

ss. D 4318, 2005, Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils

tt. D 4354, 1999 (R 2009), Standard Practice for Sampling of Geosynthetics for Testing

uu. D 4437, 2008, Standard Practice for Determining the Integrity of Field Seams Used in Joining Flexible Polymeric Sheet Geomembranes

vv. D 4491, 1999 (R2004), Standard Test Method for Water Permeability of Geotextiles by Permittivity.

ww. D 4533, 2004 (R2009), Standard Test Method for Trapezoid Tearing Strength of Geotextiles.

xx. D 4632, 2008, Standard Test Method for Grab Breaking Load and Elongation of Geotextiles

yy. D 4643, 2008, Standard Test Method for Determination of Water (Moisture) Content of Soil by the Microwave Oven Method

zz. D 4716, 2001, Test Method for Determining the (In-Plane) Flow Rate per Unit Width and Hydraulic Transmissivity of a Geosynthetic Using a Constant Head.

aaa. D 4751, 2004, Standard Test Method for Determining Apparent Opening Size of a Geotextile

bbb. D 4832, 2002, Standard Test Method for Preparation and Testing of Controlled Low Strength Material (CLSM) Test Cylinders

ccc. D 4833, 2007, Standard Test Method for Index Puncture Resistance of Geotextiles, Geomembranes, and Related Products

ddd. D 4873, 2002, Standard Guide for Identification, Storage, and Handling of Geosynthetic Rolls and Samples

eee. D 4972, 2001 (R 2007), Standard Test Method for pH of Soils fff. D 5199, 2001 (R 2006), Standard Test Method for Measuring the Nominal

Thickness of Geosynthetics ggg. D 5261, 1992, Standard Test Method for Measuring Mass per Unit Area of

Geotextiles. hhh. D 5268, 2007 (R 2009), Standard Specification for Topsoil Used for

Landscaping Purposes iii. D 5397, 2007, Standard Test Method for Evaluation of Stress Crack

Resistance of Polyolefin Geomembranes Using Notched Constant Tensile Load Test

jjj. D 5887, 2009, Standard Test Method for Measurement of Index Flux Through Saturated Geosynthetic Clay Liner Specimens Using a Flexible Wall Permeameter

kkk. D 5890, 2006, Standard Test Method for Swell Index of Clay Mineral Component of Geosynthetic Clay Liners

lll. D 5891, 2002, Standard Test Method for Fluid Loss of Clay Component of Geosynthetic Clay Liners

mmm. D 5971, 2007, Standard Practice for Sampling Freshly Mixed Controlled Low-Strength Material

Page 10: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 5 of 8

RP 12/14/09 Section 01100 Summary Of Work

nnn. D 5993, 1999 (R 2004), Standard Test Method for Measuring Mass Per Unit of Geosynthetic Clay Liners

ooo. D 6243, 2008, Standard Test Method for Determining the Internal and Interface Shear Resistance of Geosynthetic Clay Liner by the Direct Shear Method

ppp. D 6392, 2008, Standard Test Method for Determining the Integrity of Nonreinforced Geomembrane Seams Produced Using Thermo-Fusion Methods

qqq. D 6495, 2009, Standard Guide for Acceptance Testing Requirements for Geosynthetic Clay Liners

rrr. D 6693, 2004, Standard Test Method for Determining Tensile Properties of Nonreinforced Polyethylene and Nonreinforced Flexible Polypropylene Geomembranes

sss. D 6938, 2008, Standard Test Method for In-Place Density and Water Content of Soil and Soil- Aggregate by Nuclear Methods (Shallow Depth)

ttt. E 329, 2008, Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction

uuu. F 436, 2009, Standard Specification for Hardened Steel Washers vvv. F 439, 2009, Standard Specification for Chlorinated Poly (Vinyl Chloride)

(CPVC) Plastic Pipe Fittings, Schedule 80 www. F 441/F 441M, 2009, Standard Specification for Chlorinated Poly(Vinyl

Chloride) (CPVC) Plastic Pipe, Schedules 40 and 80 xxx. F 1417, 1992 (R 2005), Standard Test Method for installation Acceptance

of Plastic Gravity Sewer Lines Using Low-Pressure Air.

5. American Water Works Association (AWWA) a. D110, 2004, Wire- and Strand-Wound, Circular, Prestressed Concrete Water

Tanks

6. American Welding Society (AWS) a. D1.1/D1.1M, 2008, Structural Welding Code - Steel - 21st Edition;

Incorporated Errata 2/2009

7. International Code Council (ICC) a. IBC, 1/1/2006, International Building Code

8. National Ready-Mixed Concrete Association (NRMCA) a. Checklist for Certification of Ready Mixed Concrete Production Facilities,

Ninth Edition of QC Manual, Section 3

C. Regulations

1. 29 CFR PT 1926, Safety And Health Regulations For Construction

2. FGDC-STD-007.4, Geospatial Positioning Accuracy Standard, Part 2, Geodetic Control Networks

3. Federal Geographic Data Committee, FGDC-STD-007.4-2002, Geospatial Positioning Accuracy Standards PART 4: Standards for Architecture, Engineering, Construction (A/E/C) and Facility Management

4. Permit no. 09-12-Z-22.5, Grading Permit

5. SC R.72-300, Standards for Storm Water Management and Sediment Reduction

Page 11: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 6 of 8

RP 12/14/09 Section 01100 Summary Of Work

6. SCDHEC 61-107.19, Solid Waste Management; Waste Landfills and Structural Fill

7. SCR 100000, Storm Water General Permit

D. Documents

1. See Section 01004.

E. Drawings

1. WB00122W-002, Overall Site Plan

2. See Section 01004.

1.4 DEFINITIONS

A. See individual sections for definitions related to scope of work in the section.

B. Acronyms common to all sections of this Specification

1. SRR Savannah River Remediation, LLC

2. SRS Savannah River Site

1.5 LOCATION OF THE WORK

A. The work is located in Z-Area of the Savannah River Site, a Department of Energy site south of Aiken, South Carolina.

B. See Overall Site Plan – Drawing WB00122W-002.

1.6 PROJECT SUMMARY

A. Overview:

1. Subcontractor scope includes, but is not limited to, excavation, mud mats, tank design and erection, hydrostatic testing, geosynthetic liner installation, backfill, internal coating application, drainwater collection installation and site finishing.

B. Scope includes:

1. Installation of interim erosion and storm water controls.

2. Excavation of the vault working area and stockpiling excavated soil.

3. Heave/settlement monitoring and installation of markers

4. Maintenance of all erosion and storm water controls.

5. Extend existing 30 foot wide crushed stone / gravel road to meet new ramp into excavation.

6. Construction of concrete mud mats for the future tanks.

7. Tank design and construction

8. Perform tank water tightness test

9. Apply internal coating

10. Apply external roof coating

11. Installation of drain water collection systems

Page 12: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 7 of 8

RP 12/14/09 Section 01100 Summary Of Work

12. Installation of Geosynthetic Liners. a. Between mudmats prior to tank construction. b. Around tanks after tank construction – Future installation by others. c. Tank top liner (HDPE) is excluded – Future installation by others. d. Installation of a system located beneath the cell and above the Geosynthetic

Liner to sample liquids on Cell 3A.

13. Backfill after tank construction and exterior liner installation – Future installation by others.

14. Site finish grading for erosion control including grassing.

15. Furnishing all concrete.

1.7 WORK BY OTHERS

A. Clearing of working area in preparation for excavation.

B. Temporary benchmarks and heave marker installation (Ref. Section 01320)

C. Installation of Sedimentation Pond at marked location.

D. Installation of initial storm water management and sediment/erosion control measures.

E. Installation of Process Grout line, electrical power, instrumentation and drainwater return after tank construction and backfill.

1.8 WORK SEQUENCE

A. The following sequence is anticipated to coordinate the earthwork (excavation and backfill) and erosion control with the tank construction.

1. Installation and maintenance of erosion and storm water controls.

2. Gravel road installation and maintenance.

3. Excavation (including surveys)

4. Preparation of foundation including mudmats and sub-base liners prior to tank construction.

5. Tank Construction

6. Install Hilti bolts (for internal drainwater collection system)

7. Perform tank water tightness test

8. Apply internal coating

9. Installation of drain water collection and return systems

10. Complete liner installation around tanks after tank construction (with liquid sampling system on Cell 3A).

11. Backfill, finish grade, and seeding.

12. Apply external coating

13. Installation of Process Grout line, electrical power, and instrumentation (by others) after the finish grading is completed.

Page 13: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 8 of 8

RP 12/14/09 Section 01100 Summary Of Work

1.9 GENERAL REQUIREMENTS

A. Requirements in Division 1 of this Specification apply to all sections of this Specification.

B. Maintain an on-site copy of the latest design documents, drawings and specifications for the duration of the project at all times.

C. Perform excavation, erosion / storm water control, and construction activities in accordance with governing codes, regulations, technical and functional requirements set forth in the Subcontract Documents.

D. Confirm and coordinate all aspects of the work including;

1. Work by subtier contractors,

2. Fabrication processes,

3. Methods and sequences of construction.

E. Provide required testing as identified in the Subcontractor Documents.

1.10 SITE REQUIREMENTS

A. General Provisions, Special Provisions, and Subcontract Field Conditions, are described in the procurement documents.

1.11 EXISTING CONDITIONS

A. Verify existing conditions, utilities, dimensions, and details affecting the work prior to performing other field activities.

B. Report any discrepancies or deviations from Subcontract Documents to SRR as soon as conditions are identified using a Request for Information or Supplier Deviation Disposition Request in accordance with Section 01330 – Submittal Procedures.

1.12 ADMINISTRATION

A. The SRR Subcontract Technical Representative for this effort will be identified at award of the subcontract.

B. The Subcontract Technical Representative is the SRR representative responsible for all technical communication and direction between SRR and the Subcontractor.

C. All technical correspondence shall be directed to the Subcontract Technical Representative with a transmittal copy to the Procurement Representative.

1.13 ACCEPTANCE AND INSPECTION

A. Prior to final acceptance, work will be inspected and accepted by SRR for conformance to Subcontract Document requirements.

PART 2 PRODUCTS Not Used.

PART 3 EXECUTION Not Used.

END OF SECTION

Page 14: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 1 of 3

RP 12/14/09 Section 01250 Change Procedures

CHANGE PROCEDURES

SECTION 01250

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes

1. Request for Information

2. Supplier Deviation Disposition Request

3. Change Notice

B. Definitions

1. Minor Change: Change to the project or clarifications of the Subcontract Documents in which the change does not impact the subcontract, including cost and schedule. a. Changes are initiated by the SRR Subcontract Technical Representative or

the Subcontractor’s Point of Contact. b. Level of quality shall be maintained with a minor change.

2. Deviation: Subcontractor initiated change for which the scope, cost and/or schedule of the Subcontract may be impacted.

3. Subcontractor Authorized Representative: Individual within Subcontractor’s organization authorized to receive change documents and responsible for informing others in Subcontractor's employ or Subtier contractors of changes to the Work Scope.

1.2 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards None

C. Regulations None

D. Documents

1. OSR 45-4, Supplier Deviation Disposition Request (Form)

E. Drawings None

1.3 REQUEST FOR INFORMATION (RFI)

A. Identify questions needing clarification or request services from SRR using a Request for Information (RFI).

1. RFI forms will be available from the SRR Subcontract Technical Representative (STR).

Page 15: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 2 of 3

RP 12/14/09 Section 01250 Change Procedures

B. Transmit the RFI to the SRR STR.

C. RFI issues which, at any time during the course of the subcontract, result in changes to or deviations from the technical or quality requirements or otherwise impact the cost / schedule require the use of an SDDR prior to continuing the affected work.

D. Maintain a tracking log of RFI documents.

1.4 SUPPLIER DEVIATION DISPOSITION REQUEST (SDDR)

A. Prepare a Supplier Deviation Disposition Request (OSR 45-4 Form) for Subcontractor proposed deviations from the technical or quality requirements of this procurement.

B. Applies to proposed deviations that are not Minor Changes after award of subcontract.

1. RFI issues subsequently determined to be non-minor changes to the technical or quality requirements or otherwise impact the cost / schedule require implementation and completion of the SDDR process prior to continuing.

C. For each deviation:

1. Identify the following, as applicable: a. Specification and revision number b. Affected drawing number, revision number, section or detail.

2. Identify criteria that cannot be met by item and specification section number.

3. Present explanation for the deviation.

4. Present proposal for resolution of the deviation.

5. Present price and schedule adjustment for the proposed resolution of the deviation.

D. Nonconforming Conditions

1. Nonconforming conditions are subcontractor installed conditions which do not meet the technical or quality requirements of this subcontract.

2. Document nonconforming conditions on a Supplier Deviation Disposition Request. a. Include supporting technical justification when requesting acceptance of a

"Use-As-Is" or "Repair" disposition.

E. Transmit Supplier Deviation Disposition Request for review and disposition in accordance with Section 01330 - Submittal Procedures.

1. Proposed deviations shall be identified promptly and transmitted to SRR to allow for adequate review and approval durations without impacting the subcontract schedule. (If possible, a minimum of 7 calendar days should be allowed)

F. Do not perform work on affected scope or make delivery of any item for which a SDDR is submitted until a written disposition of the SDDR is received from SRR.

1. Continue the work in accordance with the written SRR disposition of the SDDR.

1.5 CHANGE NOTICE

A. SRR will issue a Change Notice to identify additional scope, including a detailed description of proposed change with supplementary or revised drawings and/or specifications.

Page 16: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 3 of 3

RP 12/14/09 Section 01250 Change Procedures

PART 2 PRODUCTS Not Used.

PART 3 EXECUTION Not Used.

END OF SECTION

Page 17: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 1 of 6

RP 12/14/09 Section 01320 Site Surveys

SITE SURVEYS SECTION 01320

PART 1 GENERAL 1.1 SECTION INCLUDES

A. Site survey services in support of construction B. Maintain control of vertical and horizontal location of constructed items C. Bench marks and heave markers

1.2 RELATED SECTIONS

A. Division 1 - All Sections B. Section 02310, Excavation and Foundation Preparation C. Section 02320, Backfill and Finish Surface D. Section 13210, Storage Tanks

1.3 REFERENCES

A. National Codes / Standards: 1. Obtain SRR prior acceptance for other editions and/or addenda of National

Codes / Standards required by this specification before use. B. Required National Codes / Standards

None C. Regulations

1. FGDC-STD-007.4, Geospatial Positioning Accuracy Standard, Part 2, Geodetic Control Networks

2. Federal Geographic Data Committee, FGDC-STD-007.4-2002, Geospatial Positioning Accuracy Standards PART 4: Standards for Architecture, Engineering, Construction (A/E/C) and Facility Management

3. Use the National Geodetic Vertical Datum of 1929 to reference the temporary bench mark elevations.

D. Documents None

E. Drawings 1. WB00122W-019, Z-Area Saltstone Disposal Cells 3 & 5 Pre-Construction

Excavation Plan 2. C-CG-Z-00037, Z-Area Saltstone Disposal Cells 3 & 5 Mudmat Marker Cells 3 &

5 Section And Details 3. C-CG-Z-00038, Z-Area Saltstone Disposal Cell 3 &5 Settlement Marker Cells 3 &

5 Section And Details

1.4 DEFINITIONS / ACRONYMNS

A. See Section 01100.

Page 18: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 2 of 6

RP 12/14/09 Section 01320 Site Surveys

1.5 TEMPORARY BENCH MARKS AND HEAVE MARKERS

A. SRR will provide and install temporary bench marks in strategic locations (as determined by the STR) adjacent to the work area after general site preparation is complete, and Phase I heave markers as identified on Drawing WB00122W-019.

B. Mud Mat Markers and Settlement Markers 1. SRR will materially provide Phase II mud mat markers and Phase III settlement

markers (for Subcontractor installation) as indicated on Drawings C-CG-Z-00037 and C-CG-Z-00038.

1.6 QUALITY ASSURANCE

A. See Section 01400. B. Perform survey work under the direction of a Professional Land Surveyor registered and

licensed to practice in the state of South Carolina. C. Survey drawings, reports and any other official documents submitted shall be in

accordance with the laws and regulations governing the practice of land surveying in the State of South Carolina.

D. SRR reserves the right to perform independent surveys as needed.

1.7 NOTIFICATION AND COORDINATION

A. Coordinate required surveys through the SRR STR. B. Notify the SRR STR at least 10 days in advance prior to initiating a required survey. C. Contact SRR at least 6 weeks prior to installation of mud mat or roof settlement markers.

1.8 SUBMITTALS

A. Maps and Drawings 1. Provide hard copies for submittals as ANSI D size, 22-inch by 32-inch sheets.

B. See specification Section 3.10 for submittal requirements for surveys, maps and drawings.

C. Submit the following Quality Verification documents in accordance with Sections 01330 and 01400: 1. Settlement Data, 3.10.E.1 2. Final Survey Map / Drawing, 3.10.E.2

1.9 PERFORMANCE REQUIREMENTS

A. Maintain sufficient equipment, materials, parts, tools, and supplies to meet the requirements of the work. Inspect and calibrate surveying equipment at intervals specified by the manufacturer.

1.10 PROJECT RECORD DOCUMENTS

A. Maintain a complete and accurate log of control and survey work as it progresses. This log shall be available for review by SRR upon request.

Page 19: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 3 of 6

RP 12/14/09 Section 01320 Site Surveys

PART 2 PRODUCTS 2.1 MARKERS

A. SRR will materially provide Phase II mud mat markers and Phase III settlement markers per Drawings C-CG-Z-00037 and C-CG-Z-00038.

PART 3 EXECUTION 3.1 ACCURACY

A. Use Third Order/Class I survey accuracy as specified in FGDC-STD-007.4 by the Federal Geographic Data Committee. As-built survey shots shall be recorded to the nearest 0.01 feet.

B. Indicate the degree of accuracy of submitted data and the latest calibration date of equipment used on survey drawings, or submitted in a certified report. Certify by a Professional Land Surveyor registered in the State of South Carolina.

3.2 PREPARATION

A. Use the SRR temporary bench marks for the survey data. B. Resolve any discrepancies noted on the topographic surveys prior to initiation of

construction activities. C. Locate and protect survey control and reference points prior to starting site work;

preserve permanent reference points during construction. D. Promptly report in writing to SRR the loss or destruction of any reference point or

relocation required due to changes in grades or other reason.

3.3 PROTECTION

A. Install three guard posts with reflective paint striping adjacent to temporary benchmarks in high traffic areas to prevent vehicular damage. Inform SRR, in writing, if Subcontractor considers a temporary benchmark not to be in a high traffic area (i.e. guard posts are not installed).

3.4 CONSTRUCTION LAYOUT

A. Perform pre-construction survey to set lines, grades, and/or any other survey controls to aid in locating the proposed construction areas. This includes physical layout for the equipment and structure locations, roads, drainage, grading, etc.

B. Where location tolerances for structure and yard articles are not specified on Contract Drawings, use tolerance of ± 0.10 feet in horizontal and vertical direction.

3.5 MEASUREMENT OF QUANTITIES

A. Survey work required, to determine in-progress quantities and field measurement, includes topographic surveys, field measurements of drainage areas, etc.

B. Place survey controls for future extensions of the survey where portions of a completed section require measurement during construction.

3.6 AS-BUILT SURVEY CRITERIA

A. Perform final topographic surveys, measurements, and recording required to document construction. Include as-built locations and elevations of all disturbed areas and features such as cover boundaries, channels, drainage structures, utilities, high points, change in slope, etc.

Page 20: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 4 of 6

RP 12/14/09 Section 01320 Site Surveys

3.7 REFERENCE ELEVATION MONUMENTS

A. Temporary Bench Marks 1. Temporary bench marks will be installed by SRR and will be set in strategic

locations (as determined by the STR) adjacent to the work area after general site preparation is complete. The bench marks will be similar to those used by the United States Geological Survey (USGS) with the bench mark component location indicator number (provided by SRR) punched on brass caps embedded in concrete. The base datum Mean Sea Level (MSL) will be indicated on the bench marks.

2. The elevation of the temporary bench marks will be set from the nearest bench mark established by the National Geodetic Society (NGS), USGS, or other nationally acceptable surveying standards or agencies.

3. All temporary bench marks shall be protected from damage. 4. Temporary bench marks shall be checked against the NGS, USGS, or SRS

accepted bench marks at 6-month intervals during construction. A complete elevation survey closing at the starting point shall be made. The maximum permissible error shall be ± 0.013 ft milesindistance (First order Class I leveling, Ref. 1.3.C.2 )

3.8 SETTLEMENT, HEAVE AND MUD MAT MARKERS

A. Settlement, heave and mud mat markers are elevation references placed on major structural elements such as columns, walls, chimneys, foundations, or foundation soils.

B. Three types of settlement markers will be used: 1. Heave marker: Heave marker will be a Borros anchor or equivalent installed per

Manufacturer’s instructions. a. Installation by SRR and monitored by Subcontractor.

2. Mud mat marker: Each mud mat marker shall consist of a 9/16” diameter 3 feet long stainless steel rod monument with a cone-shaped point, a 3/4” bronze domed cap (Bernsten No. RBS325BR or equal), a 6-inch long 6-inch diameter schedule 40 PVC pipe, and a benchmark access cover for schedule 40, 6” PVC pipe with recessed hinge (Bernsten No. BMAC6 or equal) installed per manufacturer’s instructions.

3. Horizontal settlement marker: Horizontal marker shall be a 3-1/2” diameter domed bronze concrete survey marker (Bernsten No. C35DB or equal), cast-in place during concrete placement.

4. All markers shall be identified in the field with a unique facility CLI number supplied by SRR. CLI tags will be provided by SRR. The tags shall be affixed adjacent to the marker for the period of time the marker is being monitored. The only “permanent” markers will be the tank roof settlement markers. The CLI tags for those will be epoxyed to the roof after elastomeric coating is applied.

5. Any marker that is destroyed, damaged, or becomes inaccessible shall be replaced or relocated in the same area where possible, before the next scheduled survey. The elevation of a replaced or relocated marker shall be tied to that of the old marker, if possible. An adjusted initial elevation shall be established for the new marker so that an uninterrupted settlement observation of the marker can be maintained.

Page 21: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 5 of 6

RP 12/14/09 Section 01320 Site Surveys

6. It may be necessary to establish temporary settlement markers for facilities under construction, and/or relocate permanent settlement markers during construction activities due to interferences or for ease of survey. New markers should be installed and monitored prior to removal or relocation of the old marker to maintain a constant settlement record. (New markers will be provided by SRR.) NOTE: East - West locations of markers as shown on drawings C-CG-Z-00037 and C-CG-Z-00038 are approximate as horizontal location is not critical for settlement monitoring.

3.9 FREQUENCY OF MONITORING

1. After the initial settlement (or heave) marker elevation is established, surveys shall be scheduled at weekly intervals during construction.

3.10 RECORDING OF DATA

A. A complete set of field notes (hard copy and/or electronic files) shall be kept and maintained for the following: 1. Descriptive location of settlement markers. 2. Records of elevation and settlement each time a survey is made. 3. Relocation of settlement markers. 4. Location and elevation of bench marks and control monuments.

B. After installing the settlement (or heave) markers, the initial elevations and date shall be recorded as soon as possible. A complete elevation survey closing at the starting point (i.e., control monument) shall be made and repeated the same day to establish initial marker elevations. The maximum permissive error shall be ± 0.013 ft milesindistance (First Order Class I Leveling, Ref. 1.3.C.2).

C. In addition to elevation data, the following information shall also be recorded for each survey: 1. Date and time; 2. Survey crew names; 3. Equipment used (including identification numbers and calibration date); 4. Weather conditions; 5. Temperature; 6. Description of any unusual conditions or damage of a marker/monument 7. Relocation of settlement markers 8. Excavation level (if applicable, for heave measurements); 9. During placement of concrete, total weight of concrete computed per design, and

an estimate of cumulative amount of concrete placed; 10. After placement of concrete, any major equipment and commodity loads and

estimated percentage of total foundation load; 11. Current construction operations or any other unusual conditions.

D. Depending on the settlement results, a re-survey may be necessary. This will be determined by SRR following review of settlement data.

E. Transmittal of Settlement Data and Survey Map / Drawing 1. Submit Settlement Data

a. All settlement data shall be transmitted at the recommended survey interval.

Page 22: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 6 of 6

RP 12/14/09 Section 01320 Site Surveys

2. Submit a Final Survey Map / Drawing showing finish grades, final settlement marker elevations, key tank locations and elevations, etc.

END OF SECTION

Page 23: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 1 of 3

RP 12/14/09 Section 01330 Submittal Procedures

SUBMITTAL PROCEDURES

SECTION 01330

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Requirements for submittal of information for SRR review and/or acceptance.

1.2 SUBMITTAL PROCEDURES

A. Required Submittals:

1. Specified in the individual specification sections and listed on the Engineering Document Requirements (EDR) form, Attachment 01330-A and Quality Verification Documents Requirement (QVDR) form, Attachment 01330-B.

2. Review prior to submission.

3. Certify conformance of documents to specification requirements by signature of the Subcontractor’s Authorized Engineering Representative.

4. List the following on each submittal transmittal cover letter: a. Document category number, and applicable specification Section and Article

number (Ref. Columns 1 and 2 of Attachment 01330-A). b. Document description

B. Correspondence, submittals and Supplier Deviation Disposition Request forms:

1. Uniquely identify with a control number

2. Reference the following Information: a. Subcontractor Name, b. Subcontractor’s Order Reference Number, c. SRR Purchase Order No.: (Defined on Award), d. SRR Project Number and Title: (Y546, Saltstone Disposal Cells 3 and 5), e. Date of transmittal, f. Sequence page number and total number of pages on each page.

3. Transmit with a completed Transmittal Letter.

C. Transmit EDR and QVDR submittals, and original Supplier Deviation Disposition Request forms to:

Savannah River Remediation Document Control Center Building 704-1N Aiken, SC 29808 Project: Y546, Saltstone Disposal Cells 3 and 5

Page 24: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 2 of 3

RP 12/14/09 Section 01330 Submittal Procedures

D. Transmit a copy of submittals, a copy of Supplier Deviation Disposition Request forms, and all Request For Information forms to:

Subcontract Technical Representative. Name: (Defined on Award) Savannah River Site Building / Room: (Defined on Award) Aiken, SC 29808

E. Transmit correspondence and a copy of all transmittal letters to: Procurement Representative Name: (Defined on Award) Savannah River Site Location: (Defined on Award) Aiken, SC 29808

F. Mark "RESUBMITTAL” on resubmitted documents and include the previous submittal document number provided with submittal review comments.

G. Paper submittals with less than 25% recycled content is acceptable.

H. Durations provided for submittal and review cycles are calendar days.

I. Where duration “after award” is provided, duration is measured in calendar days after notification of award is given for this Subcontract, rather than any subtier subcontracts.

1.3 REVIEW, ACCEPTANCE AND STATUS OF SUBMITTALS

A. Submit documents listed on the Engineering Document Requirements form, Attachment 01330-A, on or before the submittal schedule identified in column 5.

B. Provide an 8 x 3 inch blank space for status review stamp on the first page of each required submittal.

C. Unless noted otherwise, submittals will be statused and returned to the Subcontractor within 14 days of receipt with status as follows:

1. Status 1: Work may proceed.

2. Status 2: Submit final documentation. Work may proceed.

3. Status 3: Revise and resubmit. Work may proceed subject to resolution of indicated comments.

4. Status 4: Revise and resubmit. Work may not proceed.

5. Status 5: Permission to proceed not required.

D. Incorporate changes as required in accordance with SRR comments.

1. Clearly indicate revisions on all resubmitted documents.

2. Resubmit corrected Engineering Documents for review within 14 days of the date of receipt.

E. Assignment of Status 1 or Status 5 to the Engineering Documents by SRR does not relieve the Subcontractor of any part of their obligation to meet all requirements of this Specification or their responsibility for the correctness of such Engineering Documents, and the adequacy and suitability of material and equipment represented thereon for the intended function.

F. Do not change previously accepted, Status 1 or Status 5, documents without notification to the Subcontract Technical Representative

Page 25: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 3 of 3

RP 12/14/09 Section 01330 Submittal Procedures

1.4 QVDR SUBMITTALS

A. Submit the Quality Verification Document Requirements (QVDR) in accordance with Attachment 01330-B.

1. Unless otherwise noted within the division sections, submit Attachment 01330-B documents on a weekly basis.

2. Develop an itemized list according to the listing in Attachment 01330-B and include with the transmitted document set.

3. Retain copies of QVDR records in accordance with Quality Assurance Program requirements for records. a. Retain records until demobilization.

1.5 ATTACHMENTS

A. 01330-A: Engineering Document Requirements, with Instructions (4 pages)

B. 01330-B: Quality Verification Document Requirements, with Instructions (5 pages)

PART 2 PRODUCTS Not Used

PART 3 EXECUTION Not Used

END OF SECTION

Page 26: Specification c Spp z 00007 Rev 0

OSR 45-6B# (Rev 8-27-91)

Engineering Document Requirements Attachment No. Revision No. Spec/Req’n No.

01330-A . 0 . C-SPP-Z-00007 .

Page 1 of 4 .

RP 12/14/09 Section 01330 Submittal Procedures

4. Permission to

Proceed Required

6. Quantity Required

1. Document Category Number

2. Specification Paragraph Reference

3. Document Description

Yes No

5. Submittal Schedule

Init Final

7. Kind

of copies

8. Remarks

6.0 01400 1.5 G.3

Subcontractor’s Quality Program Manual or Procedures

Y With Proposal 3 Repro

- 01400 1.5 G.5.c.i Retained Records N Upon Contract

Closure 1 Repro

28.0 01450 1.10 A.

Inspection and Testing Laboratory Business Information

N With Proposal 3 Repro

1.0 02310 3.5 C.1 Shoring Design Y 4 Weeks Prior to Use 3 Repro Submit when shoring is

required by OSHA

1.0 02320 3.13 B.

Post Construction As-Built Topographic Survey N

2 Weeks After Mechanical Completion

3 Repro

28.0 02370 1.7 B.

Construction Subcontractor Co-Permittee Certification N 2 Weeks Prior to

Work 3 Repro

11.0 02378 1.5 C.2

HPDE Liner LOC & Mfg Quality Control Test Data N With Material

Delivery 3 Repro

1.0 02378 1.6 B. 2.

HDPE Liner Design Details Drawings Y 8 Weeks Prior to Use 3 Repro

6.0 02378 1.6 D. 8.

HDPE Liner Quality Control and Inspection Plan and Procedures

Y 8 Weeks Prior to Use 3 Repro

1.0 02378 1.6 F.

As-Built Drawing(s) of the HDPE Liner Layout N 2 Weeks After

Completion 3 Repro

28.0 02378 1.7 B.

Subcontractor HDPE Liner Qualification Documentation N With Proposal 3 Repro

28.0 02378 1.7 C. 1.

HDPE Liner Field Supervisor’s or Superintendent’s Resume & References

N 4 Weeks Prior to Work 3 Repro

28.0 02378 1.7 D.1

HDPE Liner Field Crew’s Resumes & References N 4 Weeks Prior to

Work 3 Repro

28.0 02378 1.7 E.3

HDPE Liner IQCI Resume & Certification N 4 Weeks Prior to

Work 3 Repro

4.4 02378 1.8 B. 1.

HDPE Liner Storage and Handling Instructions N 2 Weeks Prior to

Receipt 3 Repro

11.0 02378 2.3 C.

HDPE Liner Product Data and Material Specifications Y 8 Weeks Prior to Use 3 Repro With Product Samples

4.1 02378 2.3 D.

HDPE Liner Installation Specifications Y 8 Weeks Prior to Use 3 Repro

1.0 02378 3.1 A. 5.

HDPE Liner Installation Drawings Y 8 Weeks Prior to Use 3 Repro

11.0 02379 1.5 C.2 & 2.3 D.3

GCL LOC & Manufacturing Quality Control Test Data N With Material

Delivery 3 Repro

1.0 02379 1.6 B. 2.

Geosynthetic Clay Liner Design Detail Drawings Y 8 Weeks Prior to Use 3 Repro

6.0 02379 1.6 D. 8.

GCL Quality Control and Inspection Plan and Procedures

Y 8 Weeks Prior to Use 3 Repro

1.0 02379 1.6 F & 3.5

As-Built Drawing(s) of the GCL Layout N 2 Weeks After

Completion 3 Repro

28.0 02379 1.7 B.

Subcontractor GCL Qualification Documentation N With Proposal 3 Repro

28.0 02379 1.7 C.

GCL Field Supervisor’s or Superintendent’s Resume & References

N 4 Weeks Prior to Work 3 Repro

28.0 02379 1.7 E.3

GCLIQCI Resume, Certification & References N 4 Weeks Prior to

Work 3 Repro

Page 27: Specification c Spp z 00007 Rev 0

OSR 45-6B# (Rev 8-27-91)

Engineering Document Requirements Attachment No. Revision No. Spec/Req’n No.

01330-A . 0 . C-SPP-Z-00007 .

Page 2 of 4 .

RP 12/14/09 Section 01330 Submittal Procedures

4. Permission to

Proceed Required

6. Quantity Required

1. Document Category Number

2. Specification Paragraph Reference

3. Document Description

Yes No

5. Submittal Schedule

Init Final

7. Kind

of copies

8. Remarks

4.4 02379 1.8 B. 1.

GCL Storage and Handling Instructions N 2 Weeks Prior to

Receipt 3 Repro

11.0 02379 2.3 E.

GCL Product Data and Material Specifications Y 8 Weeks Prior to

Ordering 3 Repro With Product Samples

4.1 02379 2.3 F.

GCL Installation Specifications Y 8 Weeks Prior to Use 3 Repro

1.0 02379 3.1 A.3.

GCL Liner Installation Drawings Y 8 Weeks Prior to Use 3 Repro

14.0 02379 3.3 H.5

Alternate GCL Repair Procedures Y 4 Weeks Prior to Use 3 Repro

6.0 02625 1.6 D.5

LCL Quality Control and Inspection Plan and Procedures

Y 8 Weeks Prior to Use 3 Repro

28.0 02625 1.7 B.1

Subcontractor LCL Qualification Documentation Y With Proposal 3 Repro

28.0 02625 1.7 C.1

LCL Field Supervisor’s or Superintendent’s Resume and References

N 4 Weeks Prior to Work 3 Repro

28.0 02625 1.7 E.3

LCL IQCI Resume and Certification N 4 Weeks Prior to

Work 3 Repro

4.4 02625 1.8 B.1

LCL Manufacturer’s Storage and Handling Instructions N 2 Weeks Prior to

Receipt 3 Repro

11.0 02625 2.3 C

LCL Product Data and Material Specifications Y 8 Weeks Prior to Use 3 Repro

4.1 02625 2.3 D

LCL Installation Specifications Y 8 Weeks Prior to Use 3 Repro

1.0 02625 3.1 C

LCL Design / Installation / Details / and Layout Drawings

Y 8 Weeks Prior to Use 3 Repro

1.0 02625 3.3 E LCL As-Built Drawings N 2 Weeks After

Completion 3 Repro

11.0 02630 2.1 A.5

Storm Drainage Product Data/Catalog Cuts Y 4 Weeks Prior to Use 3 Repro

6.0 03300 1.4 F

Concrete Supplier’s Quality Program Manual Y With Proposal 3 Repro

6.0 03300 1.4 G.1.e

NRMCA Certificate of Conformance for Concrete Production Facilities

N With Proposal 3 Repro

6.0 03300 1.4 G.1.f

NRMCA Plant Certification Inspection Check List N With Proposal 3 Repro

6.0 03300 1.4 G.2.b

Batching Accuracy and Mixing Efficiency Tests N With Proposal 3 Repro

8.0 03300 1.7 F.

Concrete, Shotcrete, & CLSM Information Y 4 Weeks Prior to Use 3 Repro

4.1 03300 3.3 A.

Proposed Construction Joint Plan N 2 Weeks Prior to

Placement 3 Repro

1.0 13210 1.5 C Tank Drawings Y 4 Weeks ARO 3 Repro ARO = After Receipt of

Order

8.0 13210 1.5 D

Tank Structural Design Calculations Y 4 Weeks ARO 3 Repro

4.1 13210 1.5 E

Tank Erection Drawings and Installation Instructions Y 4 Weeks Prior to

Installation 3 Repro

4.1 13210 1.5 F

Tank Surface Preparation, Coating Application & Testing Instructions

Y 6 Weeks ARO 3 Repro

28.0 13210 1.8 A.2

Shotcrete Nozzlemen Certification Y 4 Weeks Prior to

Installation 3 Repro

28.0 13210 1.8 B.2

Coating System Installer Qualifications Y 6 Weeks ARO 3 Repro

Page 28: Specification c Spp z 00007 Rev 0

OSR 45-6B# (Rev 8-27-91)

Engineering Document Requirements Attachment No. Revision No. Spec/Req’n No.

01330-A . 0 . C-SPP-Z-00007 .

Page 3 of 4 .

RP 12/14/09 Section 01330 Submittal Procedures

4. Permission to

Proceed Required

6. Quantity Required

1. Document Category Number

2. Specification Paragraph Reference

3. Document Description

Yes No

5. Submittal Schedule

Init Final

7. Kind

of copies

8. Remarks

11.0 13210 2.1 C.2

Steel Coating System Product Data N 6 Weeks ARO 3 Repro

25.0 13210 2.2 A.1.c

Tank Weld Examination Procedure Y 4 Weeks Prior to

Welding 3 Repro

25.0 13210 3.4 A.1.h

Visual Tank Examination Procedures Y 4 Weeks Prior to

Examination 3 Repro

26.0 13210 3.4 B.2.b

Concrete Moisture Testing Procedure Y Prior To Testing 3 Repro

24.0 13210 3.4 B.4.b

Tank Water Tightness Test Procedure Y Prior to Test 3 Repro

14.0 13210 3.4 B.4.c Tank Repair Procedure Y Prior to Test 3 Repro

1.0 13210 3.4 C.1

As-Built Tank Documents and Drawings N 2 Weeks After

Completion 3 Repro

Page 29: Specification c Spp z 00007 Rev 0

OSR 45-6A# (Rev 8-27-91) Attachment No. Revision No. Spec/Req’n No.

01330-A . 0 . C-SPP-Z-00007 .

Engineering Document Requirements Instructions Page 4 of 4 .

RP 12/14/09 Section 01330 Submittal Procedures

Purpose The Engineering Document Requirements (EDR) form is prepared by the originator, establishes a basis for actions required of a Supplier and provides the schedule for the submittal of engineering documents by the Supplier.

Legend Entry No. Information Required

1 Document category number – see below. 2 Applicable specification number and appropriate paragraph. 3 Description corresponding to document category number. 4 Permission to proceed with fabrication or other specific processes is marked yes, if required. 5 List a milestone after award i.e., prior to fabrication, prior to test, prior to shipment, or with shipment that the listed document is to be submitted by Supplier. 6 Number of copies required for submittal. 7 Reproducible, Mylar, Vellum, etc. 8 Enter remarks when appropriate.

Document Category Number and Descriptions 1.0 Drawings

1.1 Outline Dimensions, Services, Foundations and Mounting Details – Drawings providing external envelope, including lugs, centerline(s), location and size for electrical cable, conduit, fluid, and other service connections, isometrics and details related to foundations and mountings.

1.2 Assembly Drawings – Detailed drawings indicating sufficient information to facilitate assembly of the component parts of an equipment item. 1.3 Shop Detail Drawings – Drawings which provide sufficient detail to facilitate fabrication, manufacture, or installation. This includes pipe spool drawings, internal

piping and wiring details, cross-section details and structural and architectural details. 1.4 Wiring Diagrams – Drawings which show schematic diagram equipment, internal wiring diagrams, and interconnection wiring diagram for electrical items. 1.5 Control Logic Diagrams – Drawings which show paths which input signals must follow to accomplish the required responses. 1.6 Piping and Instrumentation Diagrams – Drawings which show piping system scheme and control elements.

2.0 Parts Lists and Costs – Sectional view with identified parts and recommended spare parts for one year’s operation and specified with unit cost. 3.0 Complete SRR Data Sheets – Information provided by Supplier on data sheets furnished by SRR. 4.0 Instructions

4.1 Erection/Installation – Detailed written procedures, instructions, and drawings required to erect or install material or equipment. 4.2 Operations – Detailed written instructions describing how an item or system should be operated. 4.3 Maintenance – Detailed written instructions required to disassemble, reassemble and maintain items or systems in an operating condition. 4.4 Site Storage and Handling – Detailed written instructions, requirements and time period for lubrication, rotation, heating, lifting or other handling requirements to

prevent damage or deterioration during storage and handling at jobsite. This includes shipping instruction for return. 5.0 Schedules: Engineering and Fabrication/Erection – Bar charts or critical path method diagram which detail the chronological sequence of activities, i.e.,

Engineering submittals, fabrication and shipment. 6.0 Quality Assurance Manual/Procedures – The document(s) which describe(s) the planned and systematic measures that are used to assure that structures, systems,

and components will meet the requirements of the procurement documents. 7.0 Seismic Data Reports – The analytical or test report which provides information and demonstrates suitability of material, component or system in relation to the

conditions imposed by the stated seismic criteria. 8.0 Analysis and Design Reports – The analytical data (stress, electrical loading, fluid dynamics, design verification reports, etc.) which demonstrate that an item

satisfies specified requirements. 9.0 Acoustic Data Reports – The noise, sound and other acoustic vibration data required by the procurement documents. 10.0 Samples

10.1 Typical Quality Verification Documents – A representative data package which will be submitted for the items furnished as required in the procurement documents. 10.2 Typical Material Used – a representative example of the material to be used.

11.0 Material Descriptions – The technical data describing a material which a Supplier proposes to use. This usually applies to architectural items, e.g., metal siding, decking, doors, paints, coatings.

12.0 Welding Procedures and Qualifications – The welding procedure, specification and supporting qualification records required for welding, hard facing, overlaying, brazing and soldering.

13.0 Material Control Procedures – The procedures for controlling issuance, handling, storage and traceability of materials such as weld rod. 14.0 Repair Procedures – The procedures for controlling materials removal and replacement by welding, brazing, etc., subsequent thermal treatments, and final

acceptance inspection. 15.0 Cleaning and Coating Procedures – The procedures for removal of dirt, grease or other surface contamination, and preparation and application of protective

coatings. 16.0 Heat Treatment Procedures – The procedures for controlling temperatures and time at temperature as a function of thickness, furnace atmosphere, cooling rate

and methods, etc. 19.0 UT – Ultrasonic Examination Procedures – Procedures for detecting discontinuities and inclusions in materials by the use of high frequency acoustic energy. 20.0 RT – Radiographic Examination Procedures – Procedures for detecting discontinuities and inclusions in materials by x-ray or gamma ray expose of

photographic film. 21.0 MT – Magnetic Particle Examination Procedures – Procedures for detecting surface or near surface discontinuities in magnetic materials by the distortion of an

applied magnetic field. 22.0 PT – Liquid Penetrant Examination Procedures – Procedures for detecting discontinuities in materials by the application of a penetrating liquid in conjunction

with suitable developing materials. 23.0 Eddy Current Examination Procedures – Procedures for detecting discontinuities in materials by distortion of an applied electromagnetic field. 24.0 Pressure Test – Hydro, Air, Leak, Bubble or Vacuum Test Procedures – Procedures for performing hydrostatic or pneumatic structural integrity and leakage

tests. 25.0 Inspection Procedures – Organized process followed for the purpose of determining that specified requirements (dimensions, properties, performance results,

etc.) are met. 26.0 Performance Test Procedures – Test performed to demonstrate that functional design and operational parameters are met.

26.1 Mechanical Tests – e.g., pump performance, data, valve stroking, load, temperature rise, calibration, environmental, etc. 26.2 Electrical Test – e.g., impulse, overload, continuity, voltage, temperature rise, calibration, saturation, loss, etc.

27.0 Prototype Test Reports – Reports of a test which is performed on a standard or typical examination of equipment or item, and which is not required for each item produced in order to substantiate the acceptability of equal items. This may include tests which result in damage to the item(s) tested.

28.0 Personnel Qualification Procedures – Procedures for qualifying welders, inspectors and other special process personnel. 29.0 Supplier Shipping Preparation Procedures – Procedures used by a Supplier to prepare finished materials or equipment for shipment from its facility to the

jobsite.

Page 30: Specification c Spp z 00007 Rev 0

OSR 45-5 (Rev 10-29-2008) Attachment No. Revision No. Spec/Req’n No.

01330-B . 0 . C-SPP-Z-00007. Quality Verification Document Requirements

Page 1 of 5 .

RP 12/14/09 Section 01330 Submittal Procedures

1. Document Category Number

2. Specification Paragraph Reference.

3. Document Description

4. SSR

Release.

5. SRS Receipt

Inspection Check-In

6. Remarks

7. DOC

Supplier Page Count

N/A 01320 3.10 E.1 Settlement Data Weekly Settlement Survey Sheets

N/A 01320 3.10 E.2 Final Survey Map / Drawing

N/A 02310 3.7 B.1.a

Certified Load Ticket (if equivalent proof rolling method is used)

N/A 02320 3.5 B.1.a

Certified Load Ticket (if equivalent proof rolling method is used)

26.0 02320 3.14 A. 4.

Fill Material Laboratory Test Reports

25.0 02320 3.14 B. 3. Field Inspection Reports

26.0 02320 3.14 C. 2.

In-Place Moisture Content Test Reports

26.0 02320 3.14 D. 6. In-Place Density Test Reports

25.0 02370 3.4 D.

Stormwater Pollution Prevention Plan Inspection Forms

26.0 02378 1.6 E. 1. HDPE Liner Field Test Reports

25.0 02378 3.1 D. 2.

Written Acceptance of the Surface to Receive HDPE Liner

25.0 02378 3.4 B.4

HDPE Liner Installation Test Reports of All Field Tests & Inspections (Part 1 – Horizontal)

25.0 02378 3.4 B.5

HDPE Liner Installation Test Reports of All Field Tests & Inspections (Part 2 – Vertical)

8. Supplier’s Order No. 9. Supplier’s Part 10. Supplier’s Part Name 11. Quantity 12. PO No. 13. SRS Line/Equip Tag or Code No. 14. SRS Part Name 15. Supplier’s Conformance Statement We certify that the work and required documents meet the requirements of the procuring documents.

Authorized Supplier Signature Title Date

16. Source Surveillance Representative at Supplier’s Facility Work was released based on satisfactory completion of quality surveillance and review of documentation.

With Authorized Deviations Noted in Column 6 No Deviations

Signature of SSR Date 17. Receiving Inspection at SRS This form and the quality verification documents referenced hereon have been received and their relationship to the hardware verified.

Signature of SRS Inspector Date

Page 31: Specification c Spp z 00007 Rev 0

OSR 45-5 (Rev 10-29-2008) Attachment No. Revision No. Spec/Req’n No.

01330-B . 0 . C-SPP-Z-00007. Quality Verification Document Requirements

Page 2 of 5 .

RP 12/14/09 Section 01330 Submittal Procedures

1. Document Category Number

2. Specification Paragraph Reference

3. Document Description

4. SSR

Release

5. SRS Receipt

Inspection Check-In

6. Remarks

7. DOC

Supplier Page Count

25.0 02378 3.4 C.2

HDPE Liner Final Acceptance & Inspection Report (Part 1 – Horizontal)

25.0 02378 3.4 C.3

HDPE Liner Final Acceptance & Inspection Report (Part 2 – Vertical)

25.0 02379 1.5 D.2.

Geosynthetic Clay Liner Inspection and Acceptance Report (Part 1 – Horizontal)

25.0 02379 1.5 D.3.

Geosynthetic Clay Liner Inspection and Acceptance Report (Part 2 – Vertical)

26.0 02379 1.6 E.1

GCL Acceptance and Inspection Reports

25.0 02379 3.1 D. 2.

Written Acceptance of the Surface to Receive GCL

25.0 02379 3.4 A.3

Final GCL Acceptance & Inspection Report (Part 1 – Horizontal)

25.0 02379 3.4 A.4

Final GCL Acceptance & Inspection Report (Part 2 – Vertical)

26.0 02625 1.5 C.4

LCL Hydraulic Transmissivity Test Data

25.0 02625 1.5 D.3

LCL Final Inspection and Acceptance Report

28.0 02625 2.3 A

LCL Certificate of Compliance and/or Manufacturing Quality Control (MQC) Test Data

8. Supplier’s Order No. 9. Supplier’s Part 10. Supplier’s Part Name 11. Quantity 12. PO No. 13. SRS Line/Equip Tag or Code No. 14. SRS Part Name 15. Supplier’s Conformance Statement

We certify that the work and required documents meet the requirements of the procuring documents.

Authorized Supplier Signature Title Date

16. Source Surveillance Representative at Supplier’s Facility Work was released based on satisfactory completion of quality surveillance and review of documentation.

With Authorized Deviations Noted in Column 6 No Deviations

Signature of SSR Date

17. Receiving Inspection at SRS This form and the quality verification documents referenced hereon have been received and their relationship to the hardware verified.

Signature of SRS Inspector Date

Page 32: Specification c Spp z 00007 Rev 0

OSR 45-5 (Rev 10-29-2008) Attachment No. Revision No. Spec/Req’n No.

01330-B . 0 . C-SPP-Z-00007. Quality Verification Document Requirements

Page 3 of 5 .

RP 12/14/09 Section 01330 Submittal Procedures

1. Document Category Number

2. Specification Paragraph Reference

3. Document Description

4. SSR

Release

5. SRS Receipt

Inspection Check-In

6. Remarks

7. DOC

Supplier Page Count

17.1 02625 2.3 B.2

Material Test Report for LCL Geotextile Filter Fabric Material

25.0 02630 3.2 H.1

Subdrain Discharge Structure Inspection & Test Data

25.0 02630 3.4 D.1

Initial Backfill Inspection & Compaction test Data

25.0 02630 3.5 C.1

Final Backfill Inspection & Compaction Test Data

17.1 02900 2.1 D.1 Topsoil Properties Test Data

17.1 03300 3.8 A.9

Production Aggregate Monthly Testing Report

17.1 03300 3.8 B.9

Test Reports for Concrete and Shotcrete

13.0 03300 3.8 B.10.a Batch Tickets

17.1 03300 3.8 C.3 Test Reports for CLSM

17.1 13210 2.1 A.2

Certified Material Test Reports for Tank Rebar

17.1 13210 2.1 A.3

Certified Material Test Reports for Pre-Stress Wire

25.0 13210 2.2 A.1.d Tank Weld Examination Reports

8. Supplier’s Order No. 9. Supplier’s Part 10. Supplier’s Part Name 11. Quantity 12. PO No. 13. SRS Line/Equip Tag or Code No. 14. SRS Part Name 15. Supplier’s Conformance Statement

We certify that the work and required documents meet the requirements of the procuring documents.

Authorized Supplier Signature Title Date

16. Source Surveillance Representative at Supplier’s Facility Work was released based on satisfactory completion of quality surveillance and review of documentation.

With Authorized Deviations Noted in Column 6 No Deviations

Signature of SSR Date

17. Receiving Inspection at SRS This form and the quality verification documents referenced hereon have been received and their relationship to the hardware verified.

Signature of SRS Inspector Date

Page 33: Specification c Spp z 00007 Rev 0

OSR 45-5 (Rev 10-29-2008) Attachment No. Revision No. Spec/Req’n No.

01330-B . 0 . C-SPP-Z-00007. Quality Verification Document Requirements

Page 4 of 5 .

RP 12/14/09 Section 01330 Submittal Procedures

1. Document Category Number

2. Specification Paragraph Reference

3. Document Description

4. SSR

Release

5. SRS Receipt

Inspection Check-In

6. Remarks

7. DOC

Supplier Page Count

25.0 13210 3.4 A.1.i

Visual Tank Examination Reports

25.0 13210 3.4 A.2.b Anchor Inspection Reports

26.1 13210 3.4 B.1.b Anchor Test Reports

26.0 13210 3.4 B.2.c

Concrete Moisture Testing Report

26.0 13210 3.4 B.3.b Internal Coating Test Reports

26.1 13210 3.4 B.4.d

Tank Water Tightness Test Report

26.1 13210 3.4 B.5.c

Pre-Stress Wire Measurement Reports

8. Supplier’s Order No. 9. Supplier’s Part 10. Supplier’s Part Name 11. Quantity 12. PO No. 13. SRS Line/Equip Tag or Code No. 14. SRS Part Name 15. Supplier’s Conformance Statement

We certify that the work and required documents meet the requirements of the procuring documents.

Authorized Supplier Signature Title Date

16. Source Surveillance Representative at Supplier’s Facility Work was released based on satisfactory completion of quality surveillance and review of documentation.

With Authorized Deviations Noted in Column 6 No Deviations

Signature of SSR Date

17. Receiving Inspection at SRS This form and the quality verification documents referenced hereon have been received and their relationship to the hardware verified.

Signature of SRS Inspector Date

Page 34: Specification c Spp z 00007 Rev 0

Back of OSR 45-5 (Rev 10-29-2008)

Attachment No. Revision No. Spec/Req’n No.

01330-B . 0 . C-SPP-Z-00007.

Quality Verification Document Requirements Instructions Page 5 of 5 .

RP 12/14/09 Section 01330 Submittal Procedures

Purpose The Quality Verification document Requirements (QVDR) is initiated by SRS and completed by the Supplier when providing quality verification documents. The QVDR is a multipurpose form to

Transmit quality verification documents from the Supplier, Provide evidence of SSR release of documentation and /or work, and Provide evidence of an SRS inspection check of documentation received at SRS.

SRS Entries Supplier Entries Entry No. Information Required Entry No. Information Required

1 Enter Document Category Number – see below. 2 Enter Specification Number and Paragraph Reference.

7 Enter number of pages of quality verification document being submitted.

8 Enter information required. 3 Enter Description corresponding to the Document Category Number. 9 Enter information required.

4 SSR to initial upon item release. 10 Enter information required. 6 Enter “Remarks: as appropriate.

16 SSR and dates release.

Field Entries

11 Enter the quantity of units covered by the documents submitted. For each item on Entry No. 12 being released, provide a separate copy of this completed form and the supporting quality verification documents.

Entry No. Information Required 12 Enter information required. 5 SRS inspector at the jobsite to complete check-in. 13 Enter information required.

14 Enter information required. 17 The SRS inspector will review the quality verification documentation package. If found satisfactory, he signs and dates the check-in statement.

15 Supplier – Signature of an employee authorized to sign such documents.

Document Category Numbers and Descriptions 12.0 Welding Verification Reports – Reports of welding performed to include weld identification, and certification that qualified welding procedures

and welders were used. 13.0 Material Verification Reports – Reports relative to material which confirm, substantiate or assure that an activity or condition has been

implemented in conformance with code and material specifications imposed by the procurement documents. 14.0 Major Repair Verification Reports – Reports may include weld repair locations (maps), material test reports for filler metal, pre- and post-weld

heat treatment records, NDE records, etc. The resolution of whether a repair is major or not is an SRS responsibility. 15.0 Cleaning and Coating Verification Reports – Reports include a certification of visual examination for surface preparation, surface profile,

materials, etc.; and also humidity data, temperature data and coating thickness data as required by the procurement documents. 16.0 Heat Treat Reports – Reports normally include furnace charts and similar records which identify and certify the item(s) treated, the procedure

used, furnace atmosphere, time at temperature, cooling rate, etc. 17.0 Material Property Reports

17.1 MTR (Material Test Reports) – These reports include all chemical, physical, mechanical, and electrical property test data required by the material specification and applicable codes. These are applicable to cement, concrete, metals, cable jacket materials, rebar, rebar splices, etc.

17.2 Impact Test Data – Reports of Charpy or drop weight tests including specimen configuration, test temperature and fracture data. 17.3 Ferrite Data – Reports of the ferrite percentage for stainless steel materials used, including castings and welding filler metals as

deposited. 17.4 Materials Certificate of Conformance – Documents which certify conformance to the requirements of the applicable material specification. 17.5 Electrical Property Reports – Reports of electrical characteristics, e.g., dielectric, impedance, resistance, flame tests, corona, etc.

18.0 Code Compliance – Verifying documents (such as data Forms U-1, M-2, State, etc.), which are prepared by the manufacturer or installer and certified by the Authorized Code Inspector.

19.0 UT – Ultrasonic Examination and Verification Reports – Examination results of certain characteristics of discontinuities and inclusions in material by the use of high frequency acoustic energy.

20.0 RT – Radiographic Examination and Verification Reports – Examination results of certain characteristics of discontinuities and inclusions in materials by x-ray or gamma ray exposure of photographic film, including film itself.

21.0 MT – Magnetic Particle Examination and Verification Reports – Examination results of surface (or near surface) discontinuities in magnetic materials by distortion of an applied magnetic field.

22.0 PT – Liquid Penetrant Examination and Verification Reports – Examination results of surface discontinuities in materials by application of a penetrating liquid in conjunction with suitable developing techniques.

23.0 Eddy Current Examination and Verification Reports – Examination results of discontinuities in material by distortion of an applied electromag- netic field.

24.0 Pressure Test – Hydro, Air, Leak, Bubble or Vacuum Test and Verification Reports – Results of hydrostatic or pneumatic structural integrity and leakage tests.

25.0 Inspection and Verification Reports – Documented findings resulting from an inspection. 26.0 Performance Test and Verification Reports – Reports of Test Results

26.1 Mechanical Test, e.g., pump, performance data, valve stroking, load, temperature rise, calibration, environment, etc. 26.2 Electrical Tests, e.g., load, impulse, overload, continuity, voltage, temperature rise, calibration, saturation, loss, etc.

27.0 Prototype Test Report – Report of the test which is performed on a standard or typical example of equipment, material or item, and which is not required for each item produced in order to substantiated the acceptability of equal items. This normally includes tests which may, or could be expected to, result in damage to the item(s) tested.

28.0 Certificate of Conformance – A document signed or otherwise authenticated by an authorized individual certifying the degree to which items or services meet specified requirements.

Page 35: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 1 of 3

RP 12/14/09 Section 01400 Quality Requirements

QUALITY REQUIREMENTS SECTION 01400

PART 1 GENERAL 1.1 SECTION INCLUDES

A. General. B. Site inspection and oversight requirements.

1.2 RELATED SECTIONS

A. All Sections in this Specification

1.3 REFERENCES

A. C-QP-Z-00001, Sample Quality Program Guidance for Disposal Cells 3 & 5

1.4 GENERAL REQUIREMENTS

A. Individual specification sections contain inspection and testing requirements, including associated test and inspection documentation the Subcontractor is required to prepare, retain and/or transmit to SRR.

1.5 QUALITY ASSURANCE

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship to produce work of specified quality.

B. Comply with manufacturer’s instructions. C. Utilize personnel qualified to produce specified quality of work. D. Secure products in place with anchorage devices designed to withstand stresses,

vibration, physical distortion, and/or disfigurement. E. Coordinate clarifications and changes with SRR in accordance with Section 01250. F. Verify compliance to Section 03300, Article 1.4 “Quality Requirements” for Cast-In-Place

Concrete. G. Quality Program Requirements

1. SRS Review a. SRR reserves the right to review aspects of inspection, examination and

testing activities to the extent necessary to ensure compliance to Specification and code requirements. i. This review includes the right of access to the Subcontractor’s facilities,

including sub-tier suppliers, vendors, and subcontractors, for the purpose of review, audit, surveillance, and witnessing of inspection, examination, and testing activities.

2. Work performed in the execution of this specification shall be in accordance with an SRR approved Subcontractor’s Quality Program that complies with the requirements defined in Attachment 01400-A. a. If the Subcontractor’s program includes a graded approach, it will be

evaluated with the rest of the program against the specified criteria. b. The Quality Program may be documented in a single manual or may consist

of individual procedures addressing the applicable elements defined in Attachment 01400-A.

Page 36: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 2 of 3

RP 12/14/09 Section 01400 Quality Requirements

NOTE: Refer to document number C-QP-Z-00001, Sample Quality Program Guidance for Disposal Cells 3 & 5, for an example of the Quality Program documentation expectations.

3. Submit the Subcontractor’s Quality Program Manual or Procedures to SRR with the proposal. a. SRR review and acceptance of the Subcontractor’s Quality Program Manual

is required prior to award of the contract. b. Subsequent revisions to the Subcontractor’s Quality Program Manual shall be

reviewed and accepted by SRR prior to its use in the execution of this specification.

4. Invoke technical and quality requirements of this Specification on sub-tier suppliers when others are contracted to provide for services, items, or parts. a. When the use of sub-tier supplier(s) is deemed necessary, the Subcontractor

is responsible to pass down those Technical and Quality requirements deemed applicable for the activities within its defined scope of work, per referenced Codes / Standards / Material Specifications, etc., identified within this Specification and its associated Purchase Order/Subcontract package, including specifications and/or drawings. The flow down of requirements encompasses verification that the sub-tier supplier has been appropriately qualified for performance of activities complying with this procurement. The Subcontractor shall maintain objective evidence of the successful flow down and provide such evidence to SRR upon request.

5. Subcontractor Records a. Retain documents and other records generated in association with this

specification during the course of the subcontract, to include but not limited to: i. Contract documents, including this specification and associated SDDRs. ii. Documentation submittals. iii. Any document generated for this contract (e.g. procedures, reports,

certifications, qualifications, letters, etc.) not required as a submittal (e.g. “in-process” quality assurance records).

b. The records shall be accessible to SRR, upon request, during construction. c. Records pertaining to this specification shall be retained by the Subcontractor

until contract closure. i. Submit all Retained Records upon contract closure.

1.6 TOLERANCES

A. Monitor construction and installation tolerance control to produce acceptable work. B. Allowing tolerances to accumulate is unacceptable.

1.7 SITE INSPECTION AND OVERSIGHT REQUIREMENTS

A. Work is subject to SRR inspection and testing at all places and at all reasonable times before acceptance in order to ensure strict compliance with the terms of the Subcontract.

B. SRR involvement is intended to verify that specified work meets specification requirements.

C. If the work is determined to be inadequate, the Subcontractor shall implement repairs/modifications/replacements required to bring the work into compliance with the Subcontract Documents.

Page 37: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5 (U)

Page 3 of 3

RP 12/14/09 Section 01400 Quality Requirements

D. The system for notifying SRR and the details for actual verification of work shall be coordinated by the Subcontractor and the SRR Subcontract Technical Representative.

E. Any inspections, testing, and/or approval of work performed by SRR shall not relieve the Subcontractor of the responsibility of performing work in accordance with the Subcontract Documents.

1.8 SUBCONTRACTOR’S INSPECTION AND TESTING SERVICES

A. Inspections and tests indicated in individual specification sections shall be the responsibility of the Subcontractor. 1. Obtain the specified services of independent firm(s)/agency(s) to perform

examinations, inspections, and testing of soil, concrete, geotextiles and geosynthetic clay liners as indicated in individual specification sections. a. Ensure compliance with the requirements of Section 01450.

2. Perform inspection/testing as required by the individual specification sections. 3. Inspections/tests may occur on or off the project site.

B. Submit inspection and test reports as required in the individual specification sections.

1.9 SUBMITTALS

A. Submit the following Engineering documents in accordance with Section 01330: 1. Subcontractor’s Quality Program Manual or Procedures, 1.5 G.3 2. All Retained Records, 1.5 G.5.c.i

PART 2 PRODUCTS Not used.

PART 3 EXECUTION 3.1 EXAMINATION

A. Verify that existing site conditions are acceptable for subsequent work. 1. Beginning new work means acceptance of existing conditions.

B. Examine and verify specific conditions described in individual specification sections.

3.2 ATTACHMENTS

A. 01400-A: Supplier Quality Assurance Program Requirements (3 pages)

END OF SECTION

Page 38: Specification c Spp z 00007 Rev 0

OSR 19-283 (Rev 10-3-2006) Attachment No. Revision No. Spec/Req’n No.

01400-A ____0____ C-SPP-Z-00007.

Supplier Quality Assurance Program Requirements Page 1 of 3___

RP 12/14/09 Section 01400 Quality Requirements

Note Any clarifications/supplements and/or exceptions shall be listed below (if required, add a continuation sheet). Level 1 requirements are subject to evaluation and verification through the performance of an audit. For Level 2 procurements where Supplier quality is deemed necessary, the method(s) of assuring Supplier quality shall be identified in Section D.

Section A ASME NQA-1 Part I Basic (Paragraph 100) Requirements

Organization Quality Assurance Program Design Control Procurement Document Control Instructions, Procedures, and Drawings Document Control Control of Purchase Items and Services Identification and Control of Items Control of Processes Inspection Test Control Control of Measuring and Test Equipment Handling, Storage and Shipping Inspection, Test and Operating Status Control of Nonconforming Items Corrective Action Quality Assurance Records Audits

Section B Other Supplier Quality Program Requirements (ASME NQA-1 Part I Supplemental [Paragraphs 200-900] Requirements; ASME NQA-1 Part II Requirements; and Other National Consensus Standards)

NQA-1 Part II Subpart 2.7 (Software Quality Requirements) NQA-1 Part 1 Requirement 7, Paragraph 503 (C of C Requirements) ANSI/NCSL Z540-1, Part 1 (Calibration Standard) ASME Section VIII Division 1 (Appendix 10) ISO 17025 (Calibration / Testing Standard) Other

X Other Subcontractor’s Quality Program Addressing Criteria in this Attachment – See pages 2 and 3 Other

Section C Clarifications/Exceptions

Section D Methods of Assuring Supplier Quality for Level 2 Procurements For Level 2 Procurements, in addition to reviewing the Supplier’s QA Manual, the items marked below shall be performed to assure Supplier quality (a minimum of one method shall be applied).

Performance of an audit by QCS Performance of an audit by the requesting organization’s CQF

X Document submittals identified on EDR document (e.g., process procedures, welder qualifications, etc.) Submittal of current applicable ASME certificate Supplier Surveillance activities Receipt Inspection activities

X Other SRR Quality Control field surveillance activities. Other

Page 39: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

01400-A . 0 . C-SPP-Z-00007.

Supplier Quality Program Basic Requirements

Page 2 of 3___

RP 12/14/09 Section 01400 Quality Requirements

Provided below is a description of the minimum requirements of the Subcontractor Quality Criteria to be addressed in either a submitted Quality Program Manual(s) or individual procedures addressing applicable elements. Quality Program (a) A documented quality program shall be planned, implemented, and maintained in accordance with

this Specification. The program may be integrated to address each element or addressed separately in independent procedures specific to their applicable quality element. The program shall identify the activities and items to which it applies. The program shall provide control over activities affecting quality to an extent consistent with their importance. The program shall include monitoring activities against acceptance criteria in a manner sufficient to provide assurance that the activities affecting quality are performed satisfactorily. The program shall be established at the earliest time consistent with the schedule for accomplishing the activities. The program shall provide for the planning and accomplishment of activities affecting quality under suitably controlled conditions. Controlled conditions include the use of appropriate equipment, suitable environmental conditions for accomplishing the activity, and assurance that prerequisites for the given activity have been satisfied. The program shall provide for any special controls, processes, test equipment, tools, and skills to attain the required quality of activities and items and for verification of that quality.

(b) The program shall provide for indoctrination, training, and qualification as necessary of personnel, performing or managing activities affecting quality to assure that suitable proficiency is achieved and maintained.

Design Control The design shall be defined, controlled, and verified. Design inputs shall be specified and translated into design documents. Design interfaces shall be identified and controlled. Design adequacy shall be verified by individuals other than those who designed the item. Design changes shall be governed by control measures commensurate with those applied to the original design. Procurement Document Control Applicable design bases and other requirements necessary to assure adequate quality shall be included or referenced in documents for procurement of items and services. To the extent necessary, procurement documents shall require Suppliers to have a quality program consistent with the applicable requirements of this Specification. Instructions, Procedures, and Drawings Activities affecting quality and services shall be prescribed by and performed in accordance with documented instructions, procedures, or drawings that include or reference appropriate quantitative or qualitative acceptance criteria for determining that prescribed results have been satisfactorily attained. The activity shall be described to a level of detail commensurate with the complexity of the activity and the need to assure consistent and acceptable results. The need for and level of detail in written procedures or instructions shall be determined based upon complexity of the task, the significance of the item or activity, work environment, and worker proficiency and capability (education, training, experience). Document Control The preparation, issue, and change of documents that specify quality requirements or prescribe activities affecting quality such as instructions, procedures, and drawings shall be controlled to assure that correct documents are being employed. Such documents, including changes thereto, shall be reviewed for adequacy and approved for release by authorized personnel.

Page 40: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

01400-A . 0 . C-SPP-Z-00007.

Supplier Quality Program Basic Requirements

Page 3 of 3___

RP 12/14/09 Section 01400 Quality Requirements

Control of Purchase Items and Services / Identification and Control of Items The procurement of items and services shall be controlled to assure conformance with specified requirements. Such control shall provide for the following as appropriate: source evaluation and selection, evaluation of objective evidence of quality furnished by the Supplier, and examination of items or services upon delivery or completion. Controls shall be established to assure that only correct and accepted items are used or installed. Control of Processes Special processes that control or verify quality, such as those used in welding, heat treating, and nondestructive examination, shall be performed by qualified personnel using qualified procedures in accordance with specified requirements. Inspection Inspections required to verify conformance of an item or activity to specified requirements or continued acceptability of items in service shall be planned and executed. Characteristics subject to inspection and inspection methods shall be specified. Inspection results shall be documented. Inspection for acceptance shall be performed by qualified persons. Test Control Tests required to collect data to verify conformance of an item to specified requirements, or to demonstrate satisfactory performance for service shall be planned and executed. Characteristics to be tested and test methods to be employed shall be specified. Test results shall be documented and their conformance with test requirements and acceptance criteria shall be evaluated. Control of Measuring and Test Equipment Tools, gages, instruments, and other measuring and test equipment used for activities affecting quality shall be controlled, calibrated at specified periods, adjusted, and maintained to required accuracy limits. Handling, Storage and Shipping Handling, storage, cleaning, packaging, shipping, and preservation of items shall be controlled to prevent damage or loss and to minimize deterioration. These activities shall be conducted in accordance with established work and inspection instructions, drawings, specifications, shipment instructions, or other pertinent documents or procedures specified for use in conducting the activity. Control of Nonconforming Items Items that do not conform to specified requirements shall be controlled to prevent inadvertent installation or use. Controls shall provide for identification, documentation evaluation, segregation when practical and disposition of nonconforming items, and for notification to affected organizations.

Page 41: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 4

RP 12/14/09 Section 01450 Inspection and Testing Laboratory Services

INSPECTION AND TESTING LABORATORY SERVICES

SECTION 01450

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Independent inspection and testing laboratory services.

1.2 RELATED SECTIONS

A. Division 1 – All Sections

B. Section 02310, Excavation and Foundation Preparation

C. Section 02320, Backfill and Finish Surface

D. Section 02378, High Density Polyethylene Liner

E. Section 02379, Geosynthetic Clay Liner

F. Section 02625, Liquid Collection Layer

G. Section 03300, Concrete

1.3 REFERENCES

A. Reference individual sections for applicable references.

B. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

C. Required National Codes / Standards

1. American Society for Testing and Materials (ASTM) a. E 329, 2008, Standard Specification for Agencies Engaged in the Testing

and/or Inspection of Materials Used in Construction

D. Regulations None

E. Documents None

F. Drawings None

1.4 QUALITY ASSURANCE

A. Reference Section 01400.

B. Conform to ASTM E 329 requirements for testing of construction materials.

Page 42: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 4

RP 12/14/09 Section 01450 Inspection and Testing Laboratory Services

1.5 NOTIFICATION AND COORDINATION

A. Notify the SRR STR at least 48 hours prior to expected time for testing operations unless specified otherwise.

1.6 SUBMITTALS

A. Submit the following Engineering Documents in accordance with Section 01330.

1. Inspection and Testing Laboratory Business Information, With Proposal, 1.10 A.

1.7 LABORATORY PERFORMANCE REQUIREMENTS

A. Provide testing laboratory services from a firm authorized to operate in the State of South Carolina.

B. Perform testing in accordance with the requirements specified in the individual sections.

C. Perform specified inspection, sampling, and testing of products in accordance with referenced codes, standards, and the requirements of this specification.

D. Ascertain compliance of physical and chemical properties of materials in accordance with the requirements of the Subcontract documents.

E. Notify SRR of observed irregularities or nonconformance of work or materials.

F. Utilize testing equipment calibrated at intervals with devices traceable to either the National Institute of Standards and Technology (NIST) or accepted values of natural physical constants.

1. As a minimum, calibrate equipment annually under normal use or semi-annually under heavy or dynamic use.

2. Recalibrate or replace equipment in which the standard operating range has been exceeded, damaging physical or electrical conditions have occurred, or otherwise exposed to abnormal operating conditions.

3. Display calibration sticker or certificate on equipment.

G. Subcontractor shall process a Supplier Deviation Disposition Request (SDDR) immediately in accordance with Section 01250 (Change Procedures) upon notification by the Independent Inspection / Testing Laboratory of out of calibration equipment used to perform inspections and testing of the equipment and material used to generate the various Disposal Cell mixes.

1.8 QUALIFICATIONS

A. Staff: Maintain technical engineer(s) on staff for review services experienced in the designated discipline. Engineer(s) shall have a minimum of five years experience on similar projects and hold a license to practice as a Professional Engineer in the State of South Carolina.

B. Testing Laboratory performing the testing of geosynthetic materials shall be accredited by the Geosynthetic Accreditation Institute (GAI).

1. Laboratory staff performing geosynthetic testing shall meet the requirements set forth by GAI.

Page 43: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 4

RP 12/14/09 Section 01450 Inspection and Testing Laboratory Services

1.9 REPORTS

A. After performance of an inspection or test, submit laboratory test reports identified in the individual specification sections in accordance with Section 01330.

B. As a minimum, include the following information on each report:

1. Date issued,

2. SRR Project Title and Purchase Order Number,

3. Name and signature of on-site inspection / sampling / testing personnel,

4. Acceptability when acceptance criteria have been specified,

5. Date and time of on-site inspection, sampling, or test,

6. Identification of Specification number, section and paragraph,

7. Inspection, sample or test location on the project work site,

8. Type of inspection or test,

9. Any deviation from the test method or procedure specified, including technical justification of the deviation and how it meets or exceeds the original requirement,

10. Name and signature of laboratory inspector or test technician,

11. Measurement and date of laboratory test or inspection,

12. Result of laboratory inspection or test,

13. Observations, sketches, drawings, plots, etc. as required by test standards,

14. Standards used, including the date / revision designation,

15. Each criterion tested,

16. Specific acceptance criteria for each criterion tested,

17. Specific result of test for each criterion,

18. Identification and serial number of test apparatus used,

19. Certification of conformance with subcontract documents,

20. Name and Signature of individual checking / reviewing the inspection / test results.

1.10 RESPONSIBILITY

A. Submit Inspection and Testing Laboratory Business Information including:

1. Independent Inspection / Testing Laboratory name, address, telephone number, and names of laboratory technicians and engineers assigned to the Project and the responsible officer. Include personnel resumes, qualifications, and certifications.

2. Documentation of inspection made by a qualified national authority during the most recent tour of inspection with memorandums of deficiencies reported during the inspection tour and the corrective actions taken to resolve the deficiencies.

3. Current accreditation document(s) received from the nationally recognized accreditation organization(s).

Page 44: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 4

RP 12/14/09 Section 01450 Inspection and Testing Laboratory Services

4. Independent Inspection / Testing Laboratory Quality Assurance program details.

5. Documentation of laboratory’s authorization to operate in State in which the laboratory facilities are located.

6. Professional registration documentation of supervising engineer.

7. Current list of testing equipment and associated components with calibration documents for the two (2) most recent calibrations.

B. Update business information for any changes in personnel.

C. Employment of inspection and testing laboratory shall in no way relieve Subcontractor of any obligation to perform work in accordance with requirements of the Subcontract documents.

PART 2 PRODUCTS Not Used

PART 3 EXECUTION Not Used

END OF SECTION

Page 45: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 3

RP 12/14/09 Section 01600 Material and Equipment

MATERIAL AND EQUIPMENT

SECTION 01600

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes

1. Products

2. Manufacturer’s names

3. Product Options

4. Substitutions

5. Transportation, handling, shipping, and storage

B. RELATED SECTIONS

1. Division 1 – All Sections

1.2 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards None

C. Regulations None

D. Documents None

E. Drawings None

1.3 DEFINITION OF PRODUCTS

A. Definition of Products:

1. New material and components forming the work.

2. Does not include machinery and equipment used for preparation, fabrication, conveying and erection of the work.

B. Where two or more units of the same component class are furnished, supply interchangeable components from the same manufacturer.

1.4 MANUFACTURER'S NAMES

A. Reference in this specification to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition.

Page 46: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 3

RP 12/14/09 Section 01600 Material and Equipment

B. The Subcontractor, at its option, may utilize any equipment, material, article, or process that, in the determination of SRR, is equivalent to that named in this specification, unless specifically provided in the Subcontract Documents.

1.5 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description are acceptable.

B. Products Specified by Naming One or More Manufacturers: Products of one of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with Provision for Substitutions (identified as “or equal”): Submit request for substitution for any manufacturer not named in accordance with the following article.

1.6 SUBSTITUTIONS

A. Approval of Substitutions After Award of Subcontract:

1. Process Supplier Deviation Disposition Requests for the substitution of specified products in accordance with Section 01250 – Change Procedures.

2. A substitution request represents that the Subcontractor has performed the following: a. Investigated the proposed product substitution and determined that it meets

or exceeds the quality level of the specified product. b. Provide the same warranty for the substitution as for the specified product. c. Coordinate the proposed product installation and make changes to other

work which may be required for the work to be completed, but with no additional time extensions or additional costs to SRR.

3. Provide documentation such as product data, test reports, etc. including above representations in support of substitution request.

4. Substitutions will not be considered if they are indicated or implied on shop drawing submissions without a previous formal substitution approval or if their implementation will require substantial SRR review or revision of the Subcontract Documents.

1.7 TRANSPORTATION, HANDLING, SHIPPING, AND STORAGE

A. Transport, handle, store, and protect products in accordance with manufacturer's instructions. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.

B. Provide equipment and personnel to handle products and store by methods to prevent soiling, discoloration, staining, disfigurement, or damage.

1. Use of damaged items is unacceptable.

C. Storage - General:

1. Arrange storage of products to permit access for inspection.

2. Periodically inspect to ensure products are not damaged and are maintained under specified conditions.

Page 47: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 3

RP 12/14/09 Section 01600 Material and Equipment

3. Promptly remove damaged material and unsuitable items from the job site and replace with material meeting the specified requirements.

D. Exterior storage of fabricated products;

1. Place on sloped supports,

2. Above ground,

3. Ensure drainage,

4. Prevent entrance of debris,

5. Cover products subject to deterioration or exposure to water vapor with impervious sheet covering, a. This includes materials sensitive to UV deterioration.

6. Provide ventilation to prevent condensation and product degradation.

E. Deliver products in manufacturer's original containers, dry, with seals and labels intact.

F. The SRR Subcontract Technical Representative may reject as non-complying, any materials or products which do not bear product identification satisfactory to the SRR Subcontract Technical Representative as to manufacturer, grade, quality, or any additional product information required for product verification.

G. Store materials in environments as recommended by the manufacturer.

H. Stack pre-formed and pre-finished material to prevent twisting, bending, or abrasion per manufacturer’s instructions.

I. Wrap and/or crate finished components and assemblies at factory to prevent damage or marring of surfaces during shipping and handling.

J. Neatly stack sheet materials lying flat to prevent sagging or damage to edges, ends, and surfaces.

1. All materials shall be stacked in such a manner as to allow safe management and maintenance of storage requirements and safe removal for use.

2. Where manufacturer’s recommendations are available for stacking configurations (i.e., dunnage spacing, maximum safe stacking heights, etc.) they shall be utilized.

K. Protect against dirt, water, chemical, mechanical damage, and construction traffic.

PART 2 PRODUCTS Not Used

PART 3 EXECUTION Not Used

END OF SECTION

Page 48: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 5

RP 12/14/09 Section 02310 Excavation and Foundation Preparation

EXCAVATION AND FOUNDATION PREPARATION

SECTION 02310

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Excavation and Foundation Preparation.

1.2 RELATED SECTIONS

A. Division 1 - All Sections

B. Section 02320, Backfill and Finish Surface

C. Section 02370, Erosion and Sedimentation Control

D. Section 03300, Cast-In Place Concrete

1.3 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards

1. American Society for Testing and Materials (ASTM) a. D 1557, 2007 (E 2003), Standard Test Methods for Laboratory Compaction

Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3))

C. Regulations

1. 29 CFR PT 1926, Safety and Health Regulations for Construction

D. Documents None

E. Drawings

1. WB00122W-019, Z-Area Saltstone Disposal Cells 3 & 5 Pre-Construction Excavation Plan

2. WB00122W-020, Z-Area Saltstone Disposal Cells 3 & 5 Pre-Construction Excavation Sections And Details

3. WB00122W-021, Z-Area Saltstone Disposal Cells 3 & 5 Pre-Construction Excavation Cross Sections

F. Definitions / Acronyms

1. CLSM: Controlled Low Strength Material

Page 49: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 5

RP 12/14/09 Section 02310 Excavation and Foundation Preparation

2. Degree of Compaction: Maximum dry unit weight of representative soil sample is determined by the laboratory test procedure performed in accordance with ASTM D 1557. a. The degree of compaction of in-place soils is described as a percentage of

this maximum dry unit weight and is hereinafter referred to as percent maximum density.

3. Moisture Content: Optimum water content of representative soil sample is determined by the laboratory test procedure performed in accordance with ASTM D 1557. a. The moisture content of in-place soils is described as within defined

percentage points of this optimum water content.

4. Over Excavation: Removal of in-situ materials beyond the limits required by the specification or shown on the Subcontract Documents and not authorized in writing by SRR.

5. Subgrade: The exposed undisturbed surface of naturally deposited inorganic soils upon which soil fill, aggregate base, or concrete foundations/slabs are to be placed.

6. Topsoil is the upper-most layer commonly characterized by dark-colored, organically rich, friable materials.

7. Unsuitable Subgrade Materials: Materials encountered at the design excavation limits or compacted fill surfaces that are determined to be soft or unstable by means of inspections or other specified test methods.

1.4 QUALITY ASSURANCE

A. See Section 01400.

B. Provide the services of an Independent Inspection and Testing Laboratory, in accordance with Section 01450, for the inspections, examinations, and testing required in this section.

1.5 NOTIFICATION AND COORDINATION

A. Notify the SRR Subcontract Technical Representative in the event that non-compliant soils are encountered

1. At the subgrade construction elevation

2. Material to be used to reestablish the subgrade construction elevation.

1.6 SUBMITTALS

A. Submit the following Engineering documents in accordance with Section 01330:

1. Shoring Design, 4 Weeks Prior to Use, 3.5 C. 1.

B. Submit the following Quality Verification documents in accordance with Section 01330:

1. Certified Load Ticket, prior to SRS Geotech Representative final acceptance of proof rolling (if pre-approved equivalent method is used), 3.7 B.1.a.

1.7 QUALIFICATIONS

A. See Section 01450 for Inspection and Testing Laboratory Services.

Page 50: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 5

RP 12/14/09 Section 02310 Excavation and Foundation Preparation

PART 2 PRODUCTS

2.1 FILL MATERIALS

A. See Section 02320

PART 3 EXECUTION

3.1 PREPARATION

A. Confirm existing conditions are as shown on the design drawings prior to beginning earthwork activities.

B. Ensure all erosion and sediment control measures are in place and functional in accordance with Section 02370 prior to commencing any land disturbing activities.

C. Control and maintain runoff, excavation drainage, and dewatering in accordance with Section 02370.

3.2 CLEARING AND STRIPPING

A. Project site will consist of existing newly grassed cover. General site preparation is expected to be complete by late March, 2010.

B. Strip the areas required for extending the roadway, mud mats and drain pipes of vegetative matter and debris to a minimum depth of four (4) inches.

C. Stockpile existing top soil for reuse.

3.3 REMOVAL OF DEBRIS

A. Remove rubble, debris, rock, inert wastes, unsuitable soils and extracted plant life from site and transport to disposal site in accordance with Subcontract Documents.

B. Continuously clean-up waste materials and remove from site. Do not allow materials to accumulate on site.

C. Do not burn or bury materials on site.

D. Leave site in clean condition.

3.4 DEWATERING DURING CONSTRUCTION

A. Ensure that excavation is dewatered such that the sides and base of excavated slope remain stable and that the excavation bottom provides a satisfactory base for the intended use. Dispose of excess water in accordance with the Best Management Practice, Section 02370.

3.5 EXCAVATION

A. Perform excavations, within the excavation limits, to the lines, contours, grades, and elevations and tolerances shown on drawings WB00122W-019, WB00122W-020, and WB00122W-021 and/or specified herein.

1. SRR approval, via SDDR, is required for excavation outside the excavation limits.

B. Protect and support existing or new structures under construction and utilities or parts thereof from weakening or damage during earthwork operations.

Page 51: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 5

RP 12/14/09 Section 02310 Excavation and Foundation Preparation

C. Provide stable and safe excavated slopes or continuously shored slope in accordance with OSHA Standard 29 CFR PT 1926, Subpart P.

1. When shoring is required by OSHA Standards, submit Shoring Design in accordance with Section 01330, with a copy to the Subcontract Technical Representative. a. Shoring design shall be stamped and signed by a licensed Professional

Engineer per OSHA Standard, 29 CFR PT 1926, Subpart P (Excavations) prior to submittal.

D. Maintain a smooth grade and provide positive drainage at all times.

E. Prevent surface drainage from entering open excavations by constructing temporary diversion swales or berms to redirect the surface run-off.

F. Protect subgrade from surface drainage accumulation and remove subgrade that has been allowed to soften.

G. Maintain areas being excavated and areas being filled in a clean condition free from leaves, brush, sticks, trash and other debris.

H. Remove the final six (6) inches of excavation to the subgrade construction elevation beneath load bearing surfaces with either smooth blade equipment or hand excavation.

I. Over excavation is not allowed except for removal of unsuitable subgrade materials.

1. Remove unsuitable subgrade materials to a disposal site in accordance with Subcontract Documents. (Reference Section 02320, Article 1.3.F.7)

J. Reestablish subgrade construction elevation under load bearing surface with compacted Structural Fill or Controlled Low Strength Material.

K. The bearing surface for mats, roadway, and pavement shall bear upon undisturbed naturally deposited proof rolled inorganic soil, or compacted Structural Fill, or Controlled Low Strength Material.

L. Inspect and approve the subgrade condition prior to placement of concrete forms, bedding material, or crusher run.

1. The SRR Subcontract Technical Representative reserves the right to disapprove the subgrade condition after initial approval if the subgrade condition has deteriorated or softened. a. The SRR STR will provide an SRS Geotech Representative to perform the

final inspection and acceptance of the subgrade condition. b. The Subcontractor is required to provide a 3 working day advanced

notification for request of final Geotech inspection. c. The Subcontractor shall include this Geotech inspection on the Integrated

Project Schedule to flag required notifications.

3.6 STOCKPILING

A. Stockpile excavated materials in areas designated in Subcontract Documents.

B. Separate and segregate excavated materials into stockpiles containing Common Fill, Structural Fill and Topsoil and protect from erosion.

C. Intermixing of organic or other deleterious materials with stockpiled materials intended for use as fill material is prohibited.

Page 52: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 5 of 5

RP 12/14/09 Section 02310 Excavation and Foundation Preparation

D. Stockpile excavated material in lifts by dumping and then spread by rolling.

E. Provide stockpile with stable slopes and neat appearance. Grade stockpiles to prevent erosion and facilitate runoff. Install temporary vegetation seeding over unused stockpile areas during construction period.

3.7 PROOFROLLING

A. Proof roll in-situ soil subgrade for areas under pavement / roadways, structures or other load bearing surfaces prior to placement of structural fill or foundation preparation to identify potential unsuitable subgrade materials.

1. Conduct in the presence of the Independent Testing Laboratory Inspector and SRS Geotech Representative.

2. The SRS Geotech Representative will provide the final acceptance.

B. Use a roller of not less than 20 tons, or its equivalent, making a minimum of four passes, two in each of two directions at right angles.

1. A pre-approved equivalent is the use of a tandem or tri-axle dump truck loaded to a minimum total weight of 40,000 lbs. Total weight will be tare weight of the empty truck plus cargo load (stone, rock, dirt, etc.). a. Submit a Certified Load Ticket if this equivalent method is utilized.

C. Excavate the top two feet of any areas that “pump” or appear soft. Replace soil in soft areas with compacted structural fill / CLSM.

3.8 PLACEMENT OF FILL

A. See Section 02320.

3.9 GRADING

A. Rough Grading

1. Contour site areas to lines and grades required to support other earthwork operations. Use excavated material when additional fill is needed.

2. Maintain positive drainage in all areas to prevent ponding or flooding of completed work.

3. Construct temporary drainage swales and/or ditches as necessary. Coordinate with storm water management and sediment and erosion control requirements as specified in Section 02370.

3.10 EXCAVATION TOLERANCES

A. Top surface of subgrade to receive compacted fill or roadway aggregate base: Plus 0.10 feet or Minus 0.25 feet from specified elevations.

B. Top surface of subgrade to receive foundations/slabs and finish grading: Plus or Minus 0.10 feet from specified elevations (Ref. Section 02320).

END OF SECTION

Page 53: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 10

RP 12/14/09 Section 02320 Backfill and Finish Surface

BACKFILL AND FINISH SURFACE

SECTION 02320

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Excavation from stockpile.

B. Future backfill and compaction with lighter equipment around tank, by others.

C. Future backfill and compaction with finish grade, by others.

1.2 RELATED SECTIONS

A. Division 1 - All Sections

B. Section 02310 - Excavation and Foundation Preparation

C. Section 02370 - Erosion and Sedimentation Control

D. Section 02900 – Soil Preparation and Seeding

E. Section 03300 - Cast-In-Place Concrete

1.3 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards

1. American Society for Testing and Materials (ASTM) a. D 422, 1963 (R 2007), Standard Test Method for Particle-Size Analysis of

Soils b. D 1556, 2007, Standard Test Method for Density and Unit Weight of Soil in

Place by the Sand-Cone Method c. D 1557, 2007 (E 2003), Standard Test Methods for Laboratory Compaction

Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3))

d. D 2216, 2005, Standard Test Method for Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass

e. D 2487, 2006, Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)

f. D 4318, 2005, Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils

g. D 4643, 2008, Standard Test Method for Determination of Water (Moisture) Content of Soil by the Microwave Oven Method

h. D 6938, 2008, Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)

Page 54: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 10

RP 12/14/09 Section 02320 Backfill and Finish Surface

C. Regulations

1. 29 CFR PT 1926, Safety And Health Regulations For Construction

D. Documents None

E. Drawings None

F. Definitions / Acronyms

1. CLSM: Controlled Low Strength Material

2. Degree of Compaction: Maximum dry unit weight of representative soil sample is determined by the laboratory test procedure performed in accordance with ASTM D 1557. a. The degree of compaction of in-place soils is described as a percentage of

this maximum dry unit weight and is hereinafter referred to as percent maximum density.

3. Moisture Content: Optimum water content of representative soil sample is determined by the laboratory test procedure performed in accordance with ASTM D 1557. a. The moisture content of in-place soils is described as within defined

percentage points of this optimum water content.

4. Over Excavation: Removal of in-situ materials beyond the limits required by the specification or shown on the Subcontract Documents and not authorized in writing by SRR.

5. Subgrade: The exposed undisturbed surface of naturally deposited inorganic soils upon which soil fill, aggregate base, or concrete foundations/slabs are to be placed.

6. Topsoil is the upper-most layer commonly characterized by dark-colored, organically rich, friable materials.

7. Unsuitable Subgrade Materials: Materials encountered at the design excavation limits or compacted fill surfaces that are determined to be soft or unstable by means of inspections or other specified test methods.

1.4 QUALITY ASSURANCE

A. See Section 01400.

B. Provide the services of an Independent Testing Laboratory, in accordance with Section 01450, for the inspections, examinations, and testing required in this section.

1.5 NOTIFICATION AND COORDINATION

A. Notify the Subcontract Technical Representative in the event that non-compliant soils are encountered

1. At the subgrade construction elevation

2. Material to be used to reestablish the subgrade construction elevation.

Page 55: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 10

RP 12/14/09 Section 02320 Backfill and Finish Surface

1.6 SUBMITTALS

A. Submit the following Engineering documents in accordance with Section 01330.

1. Post Construction As-Built Topographic Survey, 2 Weeks After Mechanical Completion, 3.13 B.

B. Submit the following Quality Verification documents in accordance with Sections 01330 and 01400:

1. Certified Load Ticket, prior to SRS Geotech Representative final acceptance of proof rolling (if pre-approved equivalent method is used), 3.5 B.1.a.

2. Fill Material Laboratory Test Reports, 2 Weeks Prior to Use, 3.14 A.4.

3. Field Inspection Reports, Each Following Monday, 3.14 B.3.

4. In-Place Moisture Content Test Reports, Each Following Monday, 3.14 C.2.

5. In-Place Density Test Reports, Each Following Monday, 3.14 D.6.

1.7 QUALIFICATIONS

A. See Section 01450 for Inspection and Testing Laboratory Services.

PART 2 PRODUCTS

2.1 FILL MATERIALS

A. Use of materials containing brush, weeds, sticks, roots, peat, sod, loam, other organic material, ice, snow, frozen soils, trash, litter, refuse or any deleterious or objectionable material is unacceptable.

B. Common Fill

1. Existing excavated material (stockpile).

C. Structural Fill

1. Well-graded sands (SW) or silty sands (SM) as defined by ASTM D 2487.

2. Existing excavated material (stockpile) that meets structural fill requirements.

3. Free of rocks greater than 2 inches diameter and greater than ½ inch at the exposed surface.

4. Plasticity index less than 15 percent as determined by ASTM D 4318.

5. Well graded within following limits as determined in accordance with ASTM D 422 :

Sieve Size Percent Passing by Weight

3/8 inch 100 No. 4 95 to 100

No. 10 85 to 100 No. 20 70 to 95 No. 40 35 to 85 No. 60 15 to 70

No. 140 2 to 20 No. 200 0 to 15

Page 56: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 10

RP 12/14/09 Section 02320 Backfill and Finish Surface

D. Controlled Low Strength Material (CLSM)

1. Meet requirements specified in Section 03300.

2. As a construction option, CLSM may be used in lieu of Structural Fill and common fill.

E. Fill Materials Source

1. Use common fill and structural fill materials from the segregated stockpiles. Provide additional fill materials from the borrow area specified in the Subcontract Field Conditions.

PART 3 EXECUTION

3.1 PREPARATION

A. Confirm existing conditions are as shown on the design drawings prior to beginning earthwork activities.

B. Ensure all erosion and sediment control measures are in place and functional in accordance with Section 02370 prior to commencing any land disturbing activities.

C. Control and maintain runoff, excavation drainage, and dewatering in accordance with Section 02370.

3.2 REMOVAL OF DEBRIS

A. Remove rubble, debris, rock, inert wastes, unsuitable soils and extracted plant life from site and transport to disposal site in accordance with Subcontract Documents.

B. Continuously clean-up waste materials and remove from site. Do not allow materials to accumulate on site.

C. Do not burn or bury materials on site.

D. Leave site in clean condition.

3.3 EXCAVATION FROM STOCKPILE

A. Perform excavations, within the excavation limits, to the lines, contours, grades, and elevations.

B. Protect and support existing or new structures under construction and utilities or parts thereof from weakening or damage during earthwork operations.

C. Provide stable and safe excavated slopes in accordance with OSHA Standard 29 CFR PT 1926, Subpart P.

D. Maintain a smooth grade and provide positive drainage at all times.

E. Prevent surface drainage from entering open excavations by constructing temporary diversion swales or berms to redirect the surface run-off.

F. Protect subgrade from surface drainage accumulation and remove subgrade that has been allowed to soften.

G. Maintain areas being excavated and areas being filled in a clean condition free from leaves, brush, sticks, trash and other debris.

H. Reestablish subgrade construction elevation under load bearing surface with compacted Structural Fill or Controlled Low Strength Material.

Page 57: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 5 of 10

RP 12/14/09 Section 02320 Backfill and Finish Surface

I. The bearing surface for mats, floor slabs, and pavement shall bear upon undisturbed naturally deposited inorganic soil, or compacted Structural Fill, or Controlled Low Strength Material.

J. Inspect and approve the subgrade condition prior to placement of rebar, concrete forms, bedding material, or crusher run.

1. SRS Geotech Representative will inspect and accept the subgrade condition. a. The Subcontractor is required to provide a 3 working day advanced

notification for request of Geotech inspection.

2. The SRR Subcontract Technical Representative reserves the right to disapprove the subgrade condition if the subgrade condition has deteriorated or softened.

3.4 STOCKPILING

A. Refer to Section 02310.

3.5 PROOFROLLING

A. Proof roll in-situ soil subgrade for areas under pavement / roadways, structures or other load bearing surfaces prior to placement of structural fill or foundations to identify potential unsuitable subgrade materials.

1. Conduct in the presence of the Independent Testing Laboratory Inspector and SRS Geotech Representative.

2. SRS Geotech Representative will provide final acceptance of the subgrades under mud mats prior to placement of mud mats.

B. Use a roller of not less than 20 tons, or its equivalent, making a minimum of four passes, two in each of the two directions at right angles.

1. A pre-approved equivalent is the use of a tandem or tri-axle dump truck loaded to a minimum total weight of 40,000 lbs. Total weight will be tare weight of the empty truck plus cargo load (stone, rock, dirt, etc.). a. Submit a Certified Load Ticket if this equivalent method is utilized.

C. Excavate the top two feet of any areas that “pump” or appear soft. Replace soil in soft areas with fill material and compact.

3.6 PLACEMENT OF FILL

A. General

1. Remove leaves, brush, trash, existing erosion control coverings, and other debris prior to placement of fill materials.

2. An Independent Testing Laboratory Inspector shall inspect and approve the subgrade prior to placement of fill, concrete, crusher run or pavement. a. SRS Geotech Representative will provide final acceptance.

3. Do not place fill against concrete structures until the concrete forms have been removed and concrete has attained 80 percent of the design strength.

4. Suspend material placement and compaction activities when moisture conditioning is required and the ambient temperature is 35 degrees F or less.

5. Do not place fill material on top of frost, snow, ice, or soil that has been permitted to freeze prior to compaction.

Page 58: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 6 of 10

RP 12/14/09 Section 02320 Backfill and Finish Surface

6. Do not incorporate any ice or frozen earth in the fill material.

7. Before placing fill, replace material that is soft and yielding, as result of excess water, with suitable material or scarify and allow the soil to dry to the specified moisture content before compacting.

8. Track in place loose fill material quantities on a weekly basis.

B. Placement of Fill Materials

1. Placement of structural fill under load bearing structures shall extend out to a point five (5) feet, minimum, from a building or structure limits; in fills for roadways; and where indicated in the Subcontract Documents.

2. Place in successive uniform loose layers not to exceed 8 inches where hand-operated compaction equipment is used and 12 inches where self-propelled or towed mechanical equipment is used.

3. Do not leave a lift in an uncompacted state at the close of a day’s operation.

3.7 MOISTURE CONTROL OF FILL MATERIAL

A. Determine material in-place moisture content in accordance with ASTM D 6938.

B. Moisture content during compaction shall be within plus or minus 3 percent of the optimum water content for the material being placed.

C. Moisture condition the fill material that is out of moisture content tolerance.

1. Moisture content is a guidance criterion and should not be a basis for acceptance or rejection for compaction of fill material.

D. Determine the natural moisture content of the fill materials in accordance with ASTM D 2216 or ASTM D 4643 immediately prior to compaction.

E. Adjust the moisture content of loose soil after placement prior to compaction to bring the moisture content of the soil within the specified limits. Use standard industry practices to moisture condition soil materials. Verify moisture content in accordance with ASTM D 4643.

F. Do not compact any fill materials containing soil that is too wet or too dry to be compacted. Work the soil until the moisture content of the material is adjusted within the specified limits.

3.8 COMPACTION OF FILL MATERIALS

A. Bring fill up uniformly around below-grade structures.

B. Compact fill material systematically on all portions of each area.

C. Provide compaction equipment suitable for the type of soil, magnitude of compaction and moisture control required.

D. In areas not accessible to roller compaction equipment, compact fill material with power tampers or vibratory compactors.

E. In areas within 10 feet out from tank walls, compact fill material with power tamper and lighter compaction equipment not to exceed 10,000 lbs.

F. Sloped ground surfaces steeper than one vertical to four horizontal require fill to be place in a stepped or benched fashion.

Page 59: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 7 of 10

RP 12/14/09 Section 02320 Backfill and Finish Surface

G. Roll the final layer of compacted fill placed at the end of each day with a smooth-wheeled roller to eliminate ridges of soil left by earthwork equipment prior to terminating work for the day.

H. Degree of Compaction for Structural Fill: Not less than 95 percent of maximum dry density determined in accordance with ASTM D 1557.

I. Degree of Compaction for Common Fill: Not less than 90 percent of maximum dry density determined in accordance with ASTM D 1557.

3.9 CONTROLLED LOW STRENGTH MATERIAL

A. If CLSM is used in place of Common or Structural Fill, prepare the subgrade, in the same manner required for backfill.

B. CLSM may be screeded, if required, to provide a uniform grade, but shall not be vibrated.

C. CLSM is not designed to resist freeze and thaw or erosive weathering and requires erosion control. Place a minimum of 6 inches of soil fill, select aggregate base coarse, or a protective wearing surface such as asphalt or concrete over the CLSM.

D. In areas where the native soil is highly impervious and standing water does not cause sloughing or penetrates the surface more than 1 inch, the CLSM may be deposited directly into 3 inches or less of standing water. Drainage must be provided to allow the displaced water to runoff.

3.10 GRADING

A. Rough Grading

1. Contour site areas to lines and grades required to support other earthwork operations.

2. Maintain positive drainage in all areas to prevent ponding or flooding of completed work.

3. Construct temporary drainage swales and/or ditches as necessary. Coordinate with storm water management and sediment and erosion control requirements as specified in Section 02370.

B. Finish Grading

1. Smoothly and uniformly grade the finished areas and conform to lines, grades, and elevations as shown on the Subcontract Documents within the specified tolerances.

2. Shape finished areas to provide a smooth and compact surface, free of irregular surface changes. Provide a smooth transition between final and existing grades at the perimeter of the construction site. Make grade changes gradual by blending slopes into level areas.

3. Slope finish grade away from buildings and structures a minimum of 2% or as noted in the Subcontract Documents.

3.11 FINISH TOLERANCES

A. Top of Finish Grade: Plus or minus 0.10 feet from specified elevations. However, maintain a smooth grade to provide positive drainage at all times and provide minimum thickness of fill materials as required by Contract Drawings

Page 60: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 8 of 10

RP 12/14/09 Section 02320 Backfill and Finish Surface

3.12 TOPSOIL PLACEMENT

A. Refer to Section 02900.

3.13 TOPOGRAPHIC SURVEYS

A. Comply with Section 01320.

B. Submit a Post Construction As-Built Topographic Survey of the project site. Indicate contour elevations of the final grades and elevations of structures or utilities (cables, conduits, piping, etc) remaining or discovered during the work activities upon completion of the Work on the As-Built. Include a written statement verifying the final grades are within the specified tolerances.

3.14 FIELD QUALITY CONTROL

A. Fill Material Laboratory Test:

1. Perform the following tests prior to initial use of the fill material area, from location as specified in the Subcontract Documents. a. Soil particle size analysis in accordance with ASTM D 422. b. Laboratory maximum density in accordance with ASTM D 1557. c. Moisture content in accordance with ASTM D 2216 or ASTM D 4643. d. Liquid Limit (LL), Plastic Limit (PL), and Plasticity Index (PI) in accordance

with ASTM D 4318.

2. Testing frequency: One (1) set of tests as follows: a. Prior to initial use of fill material. b. Each time a change in color and / or texture of the fill material becomes

evident. Change in color and texture shall be determined by an experienced soil technician.

c. Every 1000 yards of material obtained from the fill material source. d. When tests indicate the materials do not meet specified requirements,

replace the materials and retest. Notify the SRR STR immediately of failed test.

3. Use of the microwave oven test method for determining moisture content in accordance with ASTM D 4643 requires a correlation between microwave and oven drying tests. a. Establish a correlation between microwave and oven drying tests. b. Perform a minimum of five (5) tests in accordance with both the ASTM D

2216 method and the ASTM D 4643 method. c. After the correlation has been established, perform one (1) oven drying test

for every ten (10) microwave oven tests.

4. Submit Fill Material Laboratory Test Reports from the Independent Testing Laboratory.

B. Field Inspections

1. Subgrade: a. Inspect prior to each fill, concrete, crusher run or pavement placement

Page 61: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 9 of 10

RP 12/14/09 Section 02320 Backfill and Finish Surface

b. Acceptance Criteria:

i. No soft or yielding soil as result of excess water with suitable material ii. No unsuitable material iii. No leaves, brush, trash, debris or other deleterious materials iv. Concrete forms have been removed v. Concrete contiguous with fill has attained 80 percent of the design

strength

2. When inspections indicate the materials do not meet specified requirements, replace the materials and re-inspect. Notify the SRR STR immediately of failed inspection.

3. Submit Field Inspection Reports from the Independent Testing Laboratory to the SRR Subcontract Technical Representative for the work completed in the previous seven (7) calendar days on each following Monday. NOTE: The STR will process the accumulated documentation through the SRR

Document Control Center.

C. In-Place Moisture Content Tests

1. Perform Moisture Content Tests of Fill Materials a. Perform tests in accordance with ASTM D 6938. b. Fill material should be within plus or minus 3 percent of the optimum water

content for the material to be placed. c. Frequency of Testing:

i. One (1) initial test, prior to first fill placement from each stockpile ii. Structural Fill: Minimum one (1) test per 500 cubic yards of materials

placed or one test per day which ever is greater. iii. Subcontractor shall track placed fill weekly by compacted CY volume.

2. Submit In-Place Moisture Content Test Reports from the Independent Testing Laboratory to the SRR Subcontract Technical Representative for the work completed in the previous seven (7) calendar days on each following Monday. NOTE: The STR will process the accumulated documentation through the SRR

Document Control Center.

D. In-Place Density Testing

1. Perform field density tests in accordance with ASTM D 1556 or ASTM D 6938.

2. Testing frequency: One (1) test after first lift is compacted on each shift and one (1) test per 500 cubic yards of material placed subsequently or one test per day which ever is greater. a. Subcontractor shall track placed fill weekly by compacted CY volume.

3. Perform additional density tests if initial or subsequent test results do not meet specified requirements. a. Perform two additional tests within a ten (10) foot radius of the failed test. b. Determine a new compaction value by averaging the test results from the two

additional tests and the failed original test. c. If the average of the three (3) tests does not meet the specified requirements,

the entire non-conforming fill lift shall be reworked and retested.

Page 62: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 10 of 10

RP 12/14/09 Section 02320 Backfill and Finish Surface

4. If nuclear methods are used for density determination in accordance with ASTM D 6938, the testing will require additional field calibration testing, as follows. a. Establish a correlation between nuclear density tests and in-place sand cone

density tests per ASTM D 1556 for fill materials. b. For each of the first ten (10) nuclear density tests performed per ASTM D

6938, perform an in-place sand-cone density test per ASTM D 1556, to establish a site-specific relationship between the two test methods during the construction activities.

c. After the correlation has been established, perform one (1) in-place sand-cone density test per ASTM D 1556, for every ten (10) nuclear density tests performed per ASTM D 6938.

5. When tests indicate the materials do not meet specified requirements, replace the materials and retest. Notify STR immediately of failed test.

6. Submit In-Place Density Test Reports from the Independent Testing Laboratory to the SRR Subcontract Technical Representative for the work completed in the previous seven (7) calendar days on each following Monday. NOTE: The STR will process the accumulated documentation through the SRR

Document Control Center.

END OF SECTION

Page 63: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 4

RP 12/14/09 Section 02370 Erosion and Sediment Control

EROSION AND SEDIMENT CONTROL

SECTION 02370

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Provide erosion and sedimentation control measures including miscellaneous berms, diversion swales, silt fences, hay bale, sediment traps, rock check dams, and erosion control matting in accordance with the Construction Drawings.

B. Maintain erosion control measures, including those installed prior to the start of the Work and installed during all phases of construction, until the completion of construction activities and until disturbed areas have been stabilized.

C. Provide erosion control measures, as required by the execution of the Work, to protect sloping areas from erosion. Locate and size these measures as required to prevent surface runoff from entering the excavation.

D. Dewater areas within the Limits of Construction which collect stormwater.

1.2 RELATED SECTIONS

A. Division 1 - All Sections

B. Section 02300, Earthwork

C. Section 02900, Soil Preparation and Seeding

1.3 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards

1. American Society for Testing and Materials (ASTM) a. D 4751, 2004, Standard Test Method for Determining Apparent Opening Size

of a Geotextile

C. Regulations

1. Permit no. 09-12-Z-22.5, Grading Permit

2. SC R.72-300, Standards for Storm Water Management and Sediment Reduction

3. SCDHEC 61-107.19, Solid Waste Management; Waste Landfills and Structural Fill

4. SCR 100000, Storm Water General Permit

D. Documents

1. WB00122W-013, Stormwater Pollution Prevention Plan

E. Drawings None

Page 64: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 4

RP 12/14/09 Section 02370 Erosion and Sediment Control

1.4 QUALITY ASSURANCE

A. Section 01400 – Quality Requirements.

1.5 NOTIFICATION AND COORDINATION

A. Notify the Subcontract Technical Representative prior to initiation of dewatering activities. The Subcontract Technical Representative will assure appropriate notifications are made to the responsible Environmental Compliance Authority.

1.6 SUBMITTALS

A. Submit the following Engineering documents in accordance with Section 01330:

1. Construction Subcontractor Co-Permittee Certification, 2 Weeks Prior to Work, 1.7 B.

B. Submit the following Quality Verification documents in accordance with Sections 01330 and 01400:

1. Stormwater Pollution Prevention Plan Inspection Forms, Following Monday, 3.4 D.

1.7 PERFORMANCE REQUIREMENT

A. The management of stormwater and the implementation of erosion and sediment control measures shall comply with SC R.72-300, SCR 100000, Grading Permit no. 09-12-Z-22.5, the Stormwater Pollution Prevention Plan no. WB00122W-013, and SCDHEC 61-107.19.

B. Sign and submit the Construction Subcontractor Co-Permittee Certification.

C. Implement and maintain temporary and permanent stormwater erosion and sediment control measures in accordance with Best Management Practices (BMPs) as defined by SC R.72-300.

D. Implement necessary measures for the duration of construction to control erosion and to avoid silting of streams, wetlands, and impoundments.

E. In cases where land disturbing activities will be discontinued for 21 days or more, in any area within the Limits of Construction, hydroseed the area within 14 days of last disturbance.

F. No solid materials, including building materials, shall be discharged to the Waters of the State except as authorized by a Section 404 permit. Follow state and local waste disposal regulations.

G. Minimize the tracking of sediments off-site and the generation of dust by vehicles.

PART 2 PRODUCTS

2.1 SILT FENCE

A. Prefabricated system consisting of wood posts, filter fabric and fabric support system.

B. Filter fabric: Non-woven synthetic polymer, 36 inch wide minimum, US sieve #30 apparent opening size in accordance with ASTM D 4751.

Page 65: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 4

RP 12/14/09 Section 02370 Erosion and Sediment Control

2.2 HAY BALES

A. Commercially available, sturdy bales.

2.3 STONE SURFACING

A. A mixture of clean, sound, durable particles of crushed stone or gravel, together with sand and screenings, commonly referred to as “crusher run”.

2.4 EROSION CONTROL MATTING

A. Coconut fiber or recycled nylon fiber matrix sewn between two nets with a weight of at least 0.5 lbs. per sq. ft. or equivalent, capable of withstanding flow velocities up to 7 ft/sec.

2.5 EMULSIFIED ASPHALT

A. Use commercially available sprayed-on emulsified asphalt. NOTE: Soiltac® soil stabilizer is an approved alternative to emulsified asphalt for erosion control.

PART 3 EXECUTION

3.1 INITIATION OF EROSION CONTROL

A. Install erosion and sedimentation control measures in accordance with the Construction Drawings.

B. Install erosion control features, as required during the execution of the Work, to protect sloping areas from erosion. Locate and size these measures as required to prevent surface runoff from entering the excavation.

C. Install silt fencing around the base of all stockpiles of excavated material within the Stockpile Area indicated on the Construction Drawings.

D. For swales, berms and all slopes greater than 4H:1V install temporary/long-term vegetation seeding with erosion control matting to minimize erosion. Apply sprayed-on emulsified asphalt per manufacturer’s instructions in lieu of vegetation seeding with erosion control matting.

3.2 MAINTENANCE AND INSPECTION

A. Maintain temporary erosion and sedimentation control devices, including features installed prior to the start of the Work and installed during all phases of construction.

B. Maintain stabilized slopes of graded areas by repairing washes and rills.

C. Dewater areas within the Limits of Construction which collect stormwater.

D. Relocate and / or replace erosion and sedimentation control measures to account for changes in the vegetation coverage, site contours and drainage patterns as excavation and grading operations progress.

E. Maintenance of erosion control features includes areas of soil disturbance, areas affected by natural or manmade drainage or runoff, as well as removal of silt buildup in culverts, pipes, excavations, ditches and adjacent watercourses.

Page 66: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 4

RP 12/14/09 Section 02370 Erosion and Sediment Control

F. If changes during the construction phase render the installed erosion and sediment control measures ineffective, provide and install additional measures and / or modify existing measures as required to meet the intent of the Stormwater Pollution Prevention Plan, WB00122W-013.

G. Maintain erosion and sedimentation control devices until disturbed areas are stabilized, permanent erosion control measures are completed, and permanent erosion control measures are accepted at the closure of the subcontract.

3.3 DEWATERING REQUIREMENTS (IF REQUIRED)

A. Discharge water to a level area at a non-erosive velocity.

B. Protect downslope of the discharge point with silt fencing or hay bale barrier

C. Monitor the discharge activity.

D. Discontinue the dewatering activity and install additional controls if protective measures prove to be insufficient.

3.4 INSPECTION

A. Inspect erosion and sediment control devices (new and existing) once every 7 calendar days and within 24 hours following each rainfall event of 0.5 inch or greater, to determine condition and verify effectiveness.

B. Immediately repair existing ineffective device or install additional devices (silt fencing, hay bales, etc.) necessary to control erosion and sedimentation.

C. Inspect areas of land disturbance and areas used for storage of materials that are exposed to precipitation for evidence of or the potential for, pollutants entering the drainage system or entering the environment.

D. Submit Stormwater Pollution Prevention Plan Inspection Forms, Attachment 02370-A.

E. Record the inspections in the Subcontractor Daily Activity Report and address the conditions and effectiveness of existing installed measures, installation or removal of measures, maintenance activities performed, and problems identified. Generalized statements are not acceptable.

F. Subcontractor personnel that will perform the inspection of erosion control measures shall meet the qualifications and requirements set forth in the South Carolina NPDES General Permit for Stormwater Discharge from Large and Small Construction Activities, Permit SCR 100000.

3.5 ATTACHMENTS

A. 02370-A: Stormwater Pollution Prevention Plan Inspection Form, with Instructions (2 pages)

END OF SECTION

Page 67: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

02370 - A . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 1 of 2 .

RP 12/14/09 Section 02370 Erosion and Sediment Control

Stormwater Pollution Prevention Plan Inspection Form Unclassified Information Only

Project Name Outfall No. Inspection Frequency: WEEKLY MONTHLY

Grading Permit No. SCDHEC General Permit No. SCR__________________

Construction Subcontract No.

0.5” Rain Other, Specify_____________

INSPECTION ATTRIBUTES: Accept Reject N/A Location(s)

1. HOUSEKEEPING a) General area and parking b) Material Storage Area, including laydown areas

2. VEGETATION AND SURFACE TREATMENT a) Installed per SMSRP/PPP b) Wash out of vegetative cover visible c) Vegetation initiated on areas where construction activities have ceased for 14

days

d) Vegetation established (final cover) – uniform perennial vegetative cover of 70% 3. EROSION AND SEDIMENT CONTROL MEASURES a) General Area per SMSRP/PPP b) Sediment load no greater than 30% of barrier height c) Evidence of erosion, rills, or gullies d) Evidence of sediment discharge beyond control measures

4. CHANNELS AND CULVERTS a) Installed per SMSRP/PPP b) Sediment load no greater than 20% of channel depth or culvert diameter c) Erosion (scour) evident in channels d) Other obstructions identified e) Evidence of any spills in the area

5. INLET AND OUTLET PROTECTION a) Installed per SMSRP/PPP b) Stable and functioning properly c) Protective liner is stable and remains undamaged 6. SEDIMENT TRAPS AND BASINS a) Installed per SMSRP/PPP b) Basin capacity is ≤ 30% full (sediment depth) 7. PERIMETER PROTECTION a) Outside areas are not being impacted (scour, sediment, etc.)

8. SPILLWAYS a) Installed per SMSRP/PPP b) Stable and functioning properly

9. PPP CONFORMANCE a) Significant changes in activity or material stored in the area since the last

Inspection

b) Plan & Best Management Practices have been implemented c) Plan and sequencing in compliance w/ applicable permits & regulations 10. Note observations and resolutions of deficiencies below, incl. locations of sediment discharges, BMPs needing maintenance, inadequate

BMPs, or where additional BMPs are needed:

Summary of weather since last inspection:

Inspector Name (Print) Signature Job Title / Qualification Date

CERTIFICATION STATEMENT I certify that I am familiar with the information contained in this inspection report and that to the best of my knowledge and belief, the information is true, complete and accurate. Delegated Authority (Print) _____________________________ Signature ________________________________ Date______________

Page 68: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

02370 - A . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 2 of 2 .

RP 12/14/09 Section 02370 Erosion and Sediment Control

Instructions For Stormwater Pollution Prevention Control Inspection Form (FORMS MUST BE RETAINED FOR AT LEAST 3 YEARS FOLLOWING PERMIT CLOSURE)

Project Name / Outfall No: Enter the project name and outfall number (if applicable) Grading Permit / SCDHEC General Permit / Construction Project No: Enter the SRS Grading Permit, SCDHEC General Permit &

Project No.’s Inspection Frequency: Frequency should be performed per the requirements of this

specification. Check the appropriate box for type of inspection.

Inspection Attributes: Check the appropriate box and specify locations (where applicable) for the following questions. 1. HOUSEKEEPING a) Is the housekeeping of the general area and parking areas maintained in an orderly manner? b) Is the housekeeping of the material storage area, including laydown areas, maintained in an orderly manner? 2. VEGETATION AND SURFACE TREATMENT a) Are vegetation and surface treatments installed per the requirements of the SMSRP/PPP? b) If there evidence of washout of the vegetative cover? c) Has the vegetation (or other stabilizing measures) been initiated on areas where construction activities have ceased for 14

days? d) Has the vegetation been established for the final cover of the exposed area – is there a uniform perennial vegetative cover

of 70% or have other ground surfacing measures been established? 3. EROSION AND SEDIMENT CONTROL MEASURES a) Are the erosion and sediment control measures of the general area installed per requirements of the SMSRP/PPP? b) Are the sediment loads on the erosion and sediment control measures ≤30% of the barrier height? c) Is there evidence of erosion, rills, or gullies? If so, repairs may be necessary. d) Is there evidence of any sediment discharge in areas beyond the control measures? 4. CHANNELS AND CULVERTS a) Are channels and culverts installed per the requirements of the SMSRP/PPP? b) Are the sediment loads on the channels and culverts ≤20% of channel depth or culvert diameter? c) Is erosion (scour) evident in channels? d) Are there any other obstructions in the channels and culvert which are affecting their serviceability? e) Are there any signs of spills in the area? Spills are not acceptable and will require immediate cleanup. 5. INLET AND OUTELT PROTECTION a) Are inlet and outlet protection measures installed per the requirements of the SMSRP/PPP? b) Are inlet and outlet protection measures stable and functioning properly? c) Is the protective liner stable and functioning properly? If not, repair or replacement is required. 6. SEDIMENT TRAPS AND BASINS a) Are sediment traps and basins installed per the requirements of the SMSRP/PPP? b) Is the remaining capacity of the sediment basin adequate? If sediment depth ≥ 30%, cleanout must be initiated. 7. PERIMETER PROTECTION a) Are perimeter protection measures protecting the outside areas from being adversely impacted by the construction

activities? 8. SPILLWAYS a) Are spillways installed per the requirements of the SMSRP/PPP? b) Are spillways adequately maintained, stable and functioning properly? 9. PPP CONFORMANCE a) Have there been significant changes in activity or materials stored in the area since the last inspection? If so, do these

changes conform to the requirements of the PPP? Has the PPP been updated to reflect any changes? b) Are the PPP and Best Management Practices being implemented and followed? Does the PPP need to be updated? c) Are all other items/activities, including the sequencing, that could affect compliance with the applicable permits & plans

being identified and implemented? Are adequate measures installed to account for any changes to the sequence? 10. Indicate observations and/or resolutions of deficiencies from above with the location(s) specified. Include a summary of the

weather since last inspection. Inspector: Signature of the person performing the inspection. Delegated Authority: Signature of the Delegated Authority or S.C. Professional Engineer responsible for PPP.

Page 69: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

HIGH DENSITY POLYETHYLENE LINER

SECTION 02378

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Requirements for the procurement, transportation, storage, testing, and installation of the 100 mil thick, High Density Polyethylene (HDPE) Geomembrane Liner.

1. First stage - Under tank foundation, between the mud mats.

2. Future second stage – Around the tank walls, by Others.

3. Future third stage – Above roof, spliced to wall liner, by Others.

B. Interface with and provide protection for the Geosynthetic Clay Liner (GCL).

1.2 RELATED SECTIONS

A. Division 1 – All Sections

B. Section 02310, Excavation and Foundation Preparation

C. Section 02320, Backfill and Finish Surface

D. Section 02379, Geosynthetic Clay Liner

E. Section 02625, Liquid Collection Layer

F. Section 03300, Cast-In-Place Concrete

1.3 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards

1. American Society for Testing and Materials (ASTM) a. D 792, 2008, Standard Test Methods for Density and Specific Gravity

(Relative Density) of Plastics by Displacement b. D 1004, 2009, Standard Test Method for Tear Resistance (Graves Tear) of

Plastic Film and Sheeting c. D 1505, 2003, Standard Test Method for Density of Plastics by the Density-

Gradient Technique d. D 1603, 2006, Standard Test Method for Carbon Black in Olefin Plastics e. D 3895, 2007, Standard Test Method for Oxidative-Induction Time of

Polyolefins by Differential Scanning Calorimetry f. D 4218, 1996 (R 2008), Standard Test Method for Determination of Carbon

Black Content in Polyethylene Compounds by the Muffle-Furnace Technique g. D 4437, 2008, Standard Practice for Determining the Integrity of Field Seams

Used in Joining Flexible Polymeric Sheet Geomembranes

Page 70: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

h. D 4833, 2007, Standard Test Method for Index Puncture Resistance of Geotextiles, Geomembranes, and Related Products

i. D 4873, 2002, Standard Guide for Identification, Storage, and Handling of Geosynthetic Rolls and Samples

j. D 5199, 2001 (R 2006), Standard Test Method for Measuring the Nominal Thickness of Geosynthetics

k. D 5397, 2007, Standard Test Method for Evaluation of Stress Crack Resistance of Polyolefin Geomembranes Using Notched Constant Tensile Load Test

l. D 6392, 2008, Standard Test Method for Determining the Integrity of Nonreinforced Geomembrane Seams Produced Using Thermo-Fusion Methods

m. D 6693, 2004, Standard Test Method for Determining Tensile Properties of Nonreinforced Polyethylene and Nonreinforced Flexible Polypropylene Geomembranes

C. Regulations None

D. Documents None

E. Drawings None

1.4 SUBMITTALS

A. Submit the following Engineering documents in accordance with Section 01330:

1. HDPE Liner Letter of Compliance and Manufacturing Quality Control Test Data, With Material Delivery, 1.5 C.2

2. HDPE Liner Design Details Drawings, 8 Weeks Prior to Use, 1.6 B.2.

3. HDPE Liner Quality Control and Inspection Plan and Procedures, 8 Weeks Prior to Use, 1.6 D.8.

4. As-Built Drawing(s) of the HDPE Liner Layout, 2 Weeks After Completion, 1.6 F.

5. Subcontractor HDPE Liner Qualification Documentation, With Proposal, 1.7 B.

6. HDPE Liner Field Supervisor’s or Superintendent’s Resume and References, 4 Weeks Prior to Work, 1.7 C.1.

7. HDPE Liner Field Crew’s Resumes and References, 4 Weeks prior to Work, 1.7 D.1.

8. HDPE Liner IQCI Resume and Certification, 4 Weeks prior to Work, 1.7 E.3.

9. HDPE Liner Storage and Handling Instructions, 2 Weeks Prior to Receipt, 1.8 B.1.

10. HDPE Liner Product Data and Material Specifications, 8 Weeks Prior to Use, 2.3 C.

11. HDPE Liner Installation Specifications, 8 Weeks Prior to Use, 2.3 D.

12. HDPE Liner Installation Drawings, 8 Weeks Prior to Use, 3.1 A.5.

Page 71: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

B. Submit the following Quality Verification documents in accordance with Sections 01330 and 01400:

1. HDPE Liner Field Test Reports, 2 Weeks After Test, 1.6 E.1.

2. Written Acceptance of the Surface to Receive HDPE Liner, Prior to Installation, 3.1 D.2.

3. HDPE Liner Installation Test Reports of all Field Tests and Inspections (Part 1 – Horizontal), 2 Weeks after Test/Inspection, 3.4 B.4.

4. HDPE Liner Installation Test Reports of all Field Tests and Inspections (Part 2 – Vertical), 2 Weeks after Test/Inspection, 3.4 B.5.

5. HDPE Liner Final Acceptance and Inspection Report (Part 1 – Horizontal), 2 weeks After Inspection, 3.4 C.2.

6. HDPE Liner Final Acceptance and Inspection Report (Part 2 – Vertical), 2 weeks After Inspection, 3.4 C.3.

1.5 TESTING/INSPECTION REQUIREMENTS

A. Utilize Inspection and Testing laboratory services in accordance with Section 01450.

B. Subcontractor Inspection

1. Inspect the HDPE Liner rolls delivered to the site for conformance with the requirements of this Specification.

2. Inspect the HDPE Liner for damage such as cuts, tears, holes, blisters, undispersed raw materials, and other deleterious conditions.

3. Replace damaged or non-conforming materials.

C. Conformance Testing

1. Field conformance testing of the geomembrane material is not required.

2. Submit Letter of Compliance (LOC) referenced to the batch, lot, and roll numbers and Manufacturing Quality Control (MQC) test data for the materials delivered at the project site.

D. Inspection and Acceptance of Installed HDPE Liner

1. Visually inspect the installed HDPE Liner, noting conditions such as overlaps and seams, damaged areas, adequacy of repairs, and quality of installation, in particular where the potential for damage or failure exists.

1.6 SUBCONTRACTOR RESPONSIBILITIES

A. Provide and install leak tight HDPE Liner as indicated on the Installation drawings and follow the Liner manufacturer’s procedures.

B. Perform material selection and prepare the design of all details such as, but not limited to, overlap locations, penetration seals, corners, panel layouts, anchorage, and other necessary details implied or required for the HDPE Liner.

1. The design details drawings shall be verified, reviewed, signed and sealed by a Registered Professional Engineer from the Subcontractor and/or lower tier Specialty Contractors’ organization.

2. Submit the HDPE Liner Design Details Drawings for SRR acceptance.

Page 72: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

C. Utilize the services of an independent inspector per Article 1.7.E and Section 01450 to monitor installation and document testing, placement details, and repair associated with the HDPE Liner.

D. Prepare and execute a Quality Control and Inspection Plan that addresses the following:

1. Quality Control Testing and Inspection;

2. Construction and repair procedures applicable to the fabrication, installation, and repair process,

3. HDPE Liner deployment,

4. Panel identification coding system.

5. Describe in detail how the HDPE Liner materials will be deployed, the equipment that will be used, how it will be coordinated with the GCL and backfill, and precautions that will be taken during installation.

6. Precautions to protect the GCL.

7. Check list for field use.

8. Submit the HDPE Liner Quality Control and Inspection Plan and Procedures to SRR.

E. Utilize the services of a qualified laboratory, per Section 01450, and technicians to sample, test, and prepare test reports for the tests required in this Section.

1. Submit HDPE Liner Field Test Reports to SRR.

F. Prepare and submit As-Built Drawing(s) of the HDPE Liner Layout to SRR in accordance with the requirements of Section 01330.

1.7 QUALIFICATIONS / CERTIFICATIONS

A. Qualifications and certifications of individuals shall adhere to Section 01450 and the requirements of this Section.

B. Subcontractor: Minimum of two similar projects installing HDPE Liner on no less than a combined total of 10 acres in the last 5 years.

1. Submit Subcontractor HDPE Liner Qualification Documentation, including references, which verifies the installation qualifications. NOTE: Specific experience for installing HDPE in > 60 mil thicknesses should be included.

C. Field Supervisor or Superintendent: Minimum of two similar projects installing HDPE Liner on no less than a combined total of 10 acres.

1. Submit HDPE Liner Field Supervisor’s or Superintendent’s Resume and References documenting their qualifications. NOTE: Specific experience for installing HDPE in > 60 mil thicknesses should be included.

Page 73: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 5 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

D. Field Crew: Knowledgeable and skilled in HDPE Liner installation methods and shall have installed, collectively, at least 25 acres of HDPE Liner which shall include HDPE installation on a minimum of 100,000 sq. ft. vertical surfaces similar to this project.

1. Submit HDPE Liner Field Crew’s Resumes and References documenting their qualifications. NOTE: Specific experience for installing HDPE in > 60 mil thicknesses should be included.

E. Independent Quality Control Inspector (IQCI)

1. The IQCI for geosynthetic materials shall function independently and shall not be involved with the performance of construction activities or directly supervise the work being inspected.

2. The IQCI shall: a. Be responsible for inspections, observation, surveillance, and monitoring of

field testing and installation of all geosynthetic materials. b. Produce and submit documented evidence of completion of required tasks of

this Specification in accordance with approved plans, procedures and inspection reports specified in Section 01450 and the contract documents.

c. Meet the following qualifications and requirements:

i. National Institute for Certification (NICET) Level III or certified by the Geosynthetic Certification Institute (GCI) for geosynthetics material testing and installation tasks for all geosynthetic related work activities. NOTE: The GCI program is governed by the Geosynthetic Institute – Inspectors Certification Program (GSI-ICP).

ii. Construction and inspection experience for a minimum of two projects of similar complexity using geosynthetic materials.

iii. Proven familiarity with construction quality assurance, field inspection and monitoring practices, field and laboratory testing procedures required for geosynthetic materials of the project and implementation, monitoring, and application of analytical techniques required for successful laboratory testing programs.

3. Submit HDPE Liner IQCI Resume and Certification, including references documenting their qualifications. NOTE: Specific experience for installing HDPE in > 60 mil thicknesses should be included.

1.8 PACKAGING, HANDLING, SHIPPING, AND STORAGE

A. Comply with the requirements of Section 01600.

B. Assure the HDPE Liner is shipped, stored, stacked, and handled at the SRS in accordance with the manufacturer’s recommendations and as specified herein.

1. Submit the manufacturer’s HDPE Liner Storage and Handling Instructions to SRR.

C. Notify SRR at least twenty-four (24) hours prior to scheduled delivery.

D. Inspect the HDPE Liner rolls delivered to the site for damage.

E. Unload and store with minimal handling.

Page 74: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 6 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

F. Wrap the HDPE Liner in plastic to protect it from moisture and degradation during shipment and storage.

G. Separate damaged rolls from undamaged rolls.

1. SRR will be the final authority on the determination of damage and functionality of the damaged material.

2. Remove rejected HDPE Liner from the SRS.

H. Folded, twisted, or dragged HDPE Liner is not acceptable.

1. Treat the HDPE Liner in accordance with ASTM D 4873, the manufacturer’s recommendations, and this Specification.

I. Mark and identify the individual roll labels with the following information:

1. Manufacturer’s name

2. Product identification

3. Batch, lot, and roll numbers

4. Roll dimensions and weight

5. Date of manufacture

1.9 QUALITY CONTROL REQUIREMENTS

A. Implement the following quality control attributes for the inspection and verification of materials and workmanship:

1. Prior to Installation of HDPE Liner; a. Ensure that the foundation layer is prepared in accordance with the Project

Drawings. b. Ensure that the surfaces of the mud mat and concrete walls are in

accordance with Article 3.1. c. Ensure that the HDPE Liner has been stored in accordance with the

manufacturer’s recommendations and Article 1.8, and that the integrity of the HDPE Liner has not been compromised during storage. Periodic inspections of the storage area shall be performed in accordance with Article 1.8.

2. During Installation of HDPE Liner a. Ensure that HDPE Liner is handled and installed according to manufacturer’s

recommendations and Articles 1.8 and 3.2. b. Install panels and overlap in accordance with the layout drawings and details. c. Ensure overlaps are of required dimensions. d. Ensure that HDPE Liner is dry during placement and is protected from

exposure per Articles 3.2 and 3.6. e. Ensure that HDPE Liner is protected from equipment, foot traffic, and other

vehicles in accordance with Article 3.3. f. Ensure that the HDPE Liner is protected from weather and wind damage per

Article 3.6. g. Repair damaged HDPE Liner in accordance with Article 3.3.

B. Notify SRR prior to and following installation of HDPE Liner material.

Page 75: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 7 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

1.10 PROJECT SITE CONDITIONS

A. The HDPE Liner is part of the closure cover system.

1. The purpose of this layer is to impede infiltration and seepage of stored material.

2. The HDPE Liner shall function as a low permeability barrier and shall be anchored at the top of the tank wall per the details to be developed by the Liner manufacturer.

B. Coordinate HDPE Liner installation with the GCL installation of Section 02379.

1.11 MAINTENANCE

A. Maintain the installed and uninstalled HDPE Liner and protect it from damage and degradation until project completion.

B. Remove excess HDPE Liner brought to the site offsite after project closure and prior to demobilization.

PART 2 PRODUCTS

2.1 PERFORMANCE

A. The installed HDPE Liner shall act as part of the lower-permeability cover system to impede the infiltration of surface and stormwater and the seepage of the stored material.

2.2 REQUIREMENTS

A. The HDPE Liner shall be fabricated at a manufacturing facility.

B. The HDPE Liner shall be manufactured as a uniform layer.

2.3 CRITERIA

A. HDPE Geomembrane

1. The geomembrane shall be smooth, black, high density polyethylene geomembrane manufactured from virgin, first quality polyethylene resin manufactured in the Unites States.

2. The surfaces of the HDPE shall be free of holes, blisters, undispersed raw materials, or any contamination by foreign matter.

3. At a minimum, each lot number of material for the rolls delivered to the project site shall be tested by the Manufacturer Quality Control (MQC). Test data from the manufacturer shall be provided as proof that the HDPE geomembrane components were appropriately tested by the manufacturer, and meet the test values specified in Article 2.3.B.

4. Include test data from the manufacturer, with the Product Data and Material Specifications, as proof the geosynthetic components and the finished HDPE material were appropriately tested by the manufacturer for the properties shown in Article 2.3.B.

B. The HDPE Liner shall meet the following criteria;

1. Thickness – 100 mils, minimum average per ASTM D 5199

2. Density – 0.940 g/cc, minimum per ASTM D 1505 or ASTM D 792

Page 76: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 8 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

3. Tensile Properties, minimum average per ASTM D 6693 Type IV a. Yield Strength – 210 lb/in b. Break Strength – 380 lb/in c. Yield elongation – 12% d. Break Elongation – 700%

4. Tear Resistance – 70 lb, minimum average per ASTM D 1004

5. Puncture Resistance – 130 lb, minimum average per ASTM D 4833

6. Stress Crack Resistance – 200 hr minimum per ASTM D 5397

7. Carbon Black Content – 2.0% – 3.0%, per ASTM D 1603 or ASTM D 4218

8. Oxidative Induction Time – 100 minutes, per ASTM D 3895

C. Submit HDPE Liner Product Data and Material Specifications, with product samples.

D. Submit HDPE Liner Installation Specifications.

PART 3 EXECUTION

3.1 PREPARATION

A. Prepare HDPE Liner Installation Drawings,

1. Show the proposed location, orientation, overlap, penetration, tie-in, and anchor details and all associated materials and work necessary for the HDPE Liner installation.

2. The design for anchorage (including top of tank wall), splicing, layout, placement, repairs, patching, seams, penetrations, overlaps and other system requirements shall be in accordance with manufacturer’s recommendations.

3. Include splicing detail at top of tank wall for future use by others. a. This detail shall assure that the joint will prevent rain water intrusion between

the liner and tank wall.

4. The splice joint discussed in Article 3.1 A.3 shall also be protected by a rain diversion to channel water away from the joint. The diverter shall be designed to remain in place for at least 20 years until final roof/wall splice joint is complete.

5. Submit the HDPE Liner Installation Drawings to SRR.

B. No metal battens, straps, or hardware shall be used for HDPE Liner handling and installation.

C. Surfaces to be covered with HDPE Liner shall be smooth and free of sharp stones, sharp objects, or debris of any kind. There shall not be any materials/foreign objects between the GCL and HDPE liner materials.

Provide special attention to the detail at changes of direction; e.g. at base and top of tank.

D. Perform a visual inspection of the surfaces to receive the HDPE Liner.

1. Prepare, clean, or repair unacceptable areas as required.

2. Submit a Written Acceptance of the Surface to Receive HDPE Liner prior to commencing installation.

Page 77: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 9 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

E. Repair any deficiencies in the supporting subgrade that have appeared since the acceptance of the soil subgrade.

3.2 INSTALLATION

A. Install the HDPE Liner such that it is in direct and uniform contact with the underlying GCL to the maximum extent possible at completion of the installation. Refer to Attachment 02378-A for additional HDPE Liner installation requirements and allowances.

1. Straighten the HDPE Liner to smooth out creases or irregularities in the runs.

2. The Subcontractor IQCI shall document installation activities in detail and submit daily logs to the SRR STR.

B. Seal the HDPE Liner overlaps or seams per the manufacturer’s recommendations.

C. Install the HDPE Liner in the orientation recommended by the manufacturer.

1. Anchor the HDPE Liner installed on sides, at the top of walls and then unroll so as to keep the material free of wrinkles and folds.

2. A controlled roll-out shall be used.

D. Mark each panel with an “identification code” (numeric or alphanumeric) consistent with the panel layout plan. The identification code shall be simple and logical for SRR use.

E. Deploy material from the higher elevation to the lower elevation to protect the HDPE Liner against the adverse effect of precipitation during deployment.

1. Place the HDPE on vertical surface such that field seams are in vertical direction.

2. Shingle panels in a down slope direction to facilitate runoff on top of the new HDPE Liner rather than below it.

F. The number of panels deployed and the area of exposed panels shall not exceed the area that can be installed and protected from moisture on the same day.

G. Take the necessary precautions to protect materials underlying the HDPE Liner.

H. The HDPE Liner material shall be marked with waterproof overlap marks longitudinally on both faces by the manufacturer to assist in obtaining the proper overlap during installation.

1. Overlap distances shall be per the manufacturer’s recommendation.

2. Overlap seams shall be placed to assure the upper panel aligns with the match line on the lower panel.

3.3 INSTALLATION CONTROL

A. The HDPE Liner shall not be deployed during precipitation, in the presence of excessive moisture, in areas of ponded water, or in the presence of excessive winds. The HDPE Liner installation shall halt during any form of precipitation and exposed HDPE Liner shall be protected and covered immediately.

B. Protect the HDPE Liner against wind in accordance with manufacturer’s recommendations. Construction methods shall employ a means of protecting material from sudden wind damage during installation.

C. Provide earthen berms, swales, sand bags, or other means as required to direct stormwater flows away from the installed HDPE Liner. Implement and maintain erosion reduction measures during HDPE Liner installation process.

Page 78: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 10 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

D. Method of Deployment

1. Use equipment which does not damage the HDPE Liner or the supporting subgrade surface including the mudmats.

2. All personnel working on the HDPE Liner shall wear shoes that do not damage the HDPE Liner.

3. Clamps and other metal tools used in the work area shall have rounded edges (no sharp) corners. Tools shall not be tossed or thrown.

4. Panels shall be unrolled with a method that protects the HDPE Liner from scratches and crimps and protects the GCL from damage.

5. Protect the HDPE Liner in heavy traffic areas by geotextile, extra HDPE Liner, or other suitable materials. a. Materials used for protection shall be temporary and shall not be used as any

part of the permanent installation. b. Heavy traffic areas shall not exceed the manufacturer’s recommendations for

travel over the HDPE Liner.

6. Do not allow vehicle traffic directly on the HDPE Liner surface.

7. After installation, the HDPE Liner surface shall be visually inspected to ensure that no potentially damaging objects are present, such as stones, cutting blades, small tools, sandbags, etc.

E. Overlap seams shall be detailed to have the same hydraulic conductivity as required throughout the body of the HDPE Liner. Follow additional recommendations by the manufacturer regarding overlap and seaming to achieve the equivalent hydraulic conductivity.

F. Repair holes, tears, or rips in HDPE liner using a HDPE patch per Quality Control and Inspection Plan and procedures.

1. Patches shall overlap the damaged area a minimum of 4 inches (or an amount as directed by the IQCI, whichever is greater) in all directions. Nails and staples are not allowed.

3.4 INSTALLATION TESTS

A. Types of Installation Tests

1. The types of HDPE installation tests shall include the following: a. Visual tests, b. Nondestructive tests (NDT), and c. Destructive tests.

B. The frequency of testing and the specific test shall be as outlined in the following Articles:

1. Trial Seam Tests a. Tests may be made on scrap pieces of HDPE to verify that seams and

seaming conditions are adequate. b. Trial seams shall be made at the beginning of each shift and at the end of

each shift for each seaming apparatus used that day, any time the seaming operation or environment is significantly modified, and at the request of SRR,

Page 79: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 11 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

c. Each seamer shall make at least one trial seam each day, d. Trial seams shall be made under the same conditions as the production

seams, e. The trial seam sample shall be at least 5 feet long by 1 foot wide (after

seaming) with the seam centered lengthwise, f. Adjoining specimens, each 1 inch wide, shall be cut from the trial seam

sample:

i. The specimens shall be tested in shear and peel using a field tensiometer and shall not fail in the seam. Testing shall be per ASTM D 6392.

ii. The minimum allowable seam strengths required for the liner are: Shear: 200 lbs/in

Fusion Peel: 130 lbs/in

iii. If a specimen fails, a new trial seam shall be tested. iv. If the additional specimen fails, the seaming apparatus or seamer shall

not be used for seaming until the deficiencies are corrected and two consecutive successful trial seams are achieved.

g. All testing apparatus shall be provided by the Subcontractor and calibrated to the manufacturer’s requirements.

2. Nondestructive Seam Testing a. All seams shall be nondestructively tested over their full length, with the

following exception:

i. HDPE Liner welds to the perimeter embedment strip along the outer edge of the mud mat do not require nondestructive seam testing. However, visual examination shall be performed and documented by the IQCI.

b. Testing shall conform to ASTM D 4437. Use an Air Lance or Vacuum Box test for single fusion weld and extrusion weld seams. Use a Vacuum Box or other test method recommended by manufacturer and SRR approved method for double fusion weld seams. Perform testing as the seaming work progresses.

c. Testing of Defects and Repairs

i. Each location which fails the nondestructive testing shall be marked by the IQCI and repaired by the Subcontractor.

ii. The procedure for seam remediation shall be either (a) to repair the entire seam between acceptable sampling locations, or (b) to retest the seam by splitting the distance between acceptable test locations until the faulty area can be isolated and repaired.

iii. Repaired areas shall not be covered until these areas pass the appropriate tests.

3. Destructive Testing a. Destructive test of the field seam is not required; however SRR reserves the

right to independently test the seam.

4. Submit HDPE Liner Installation Test Reports of all Field Tests and Inspections (Part 1 – Horizontal) for the horizontal liner under the tank base.

5. Submit HDPE Liner Installation Test Reports of all Field Tests and Inspections (Part 2 – Vertical) for the vertical liner around the tank walls.

Page 80: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 12 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

C. Final Acceptance of Installed HDPE

1. Acceptance of the installed HDPE shall be based on visual inspection by SRR and the results of conformance and installation testing per criteria given in the Specification. The visual inspection shall note conditions such as overlaps and seams, damaged areas, adequacy of repairs, and the quality of installation, in particular where the potential for damage or failure exists.

2. Submit a HDPE Liner Final Acceptance and Inspection Report (Part 1 – Horizontal) for the horizontal liner under the tank base.

3. Submit a HDPE Liner Final Acceptance and Inspection Report (Part 2 – Vertical) for the vertical liner around the tank walls.

3.5 AS BUILTS

A. Document the HDPE as-built information per Article 1.6. and Section 1330. The drawing(s) shall include, but not limited to, the following information:

1. Overlap or seam location and date made a. The amount of overlap for adjacent HDPE Liners. b. The overlap distance is sometimes different for the roll ends versus the roll

edges. Twice the recommended overlap distances should be used and the in-place distances documented.

2. Damaged and failed areas

3. Dimensions and type of repair and date repaired

4. Material batch, roll number, and location of the panel and date installed

5. Batch and roll number of repair patches.

3.6 PROTECTION

A. Protect the HDPE Liner during transportation, storage, and installation to prevent damage and degradation.

B. Protect the HDPE Liner from UV light exposure and damage.

C. Protect the HDPE Liner against wind in accordance with manufacturer’s recommendations. Construction methods shall employ a means of protecting material from sudden wind damage during installation.

D. Provide earthen berms, swales, sandbags, or other means as required to direct stormwater flows away from the installed HDPE Liner.

E. Implement and maintain erosion reduction measures during HDPE Liner installation process.

F. Loads placed on the HDPE Liner shall not exceed the manufacturer’s recommendations and shall not cause tearing, puncturing, shoving, or thinning.

G. Equipment used for the deployment of the HDPE Liner shall be as recommended by the manufacturer and shall not damage the HDPE Liner or other materials.

Page 81: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 13 of 13

RP 12/14/09 Section 02378 High Density Polyethylene Liner

3.7 CLEANING

A. Maintain a clean worksite.

B. Upon completion of the HDPE Liner installation, clean the work areas and transport and dispose of waste materials.

C. Remove any debris, trash, or leftover HDPE Liner pieces, damaged or unsatisfactory HDPE Liner material following construction activities.

3.8 ATTACHMENTS

A. 02378-A: Additional HDPE Liner Installation Requirements and Allowances (1 page)

END OF SECTION

Page 82: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

02378 - A . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 1 of 1_

Additional HDPE Liner Installation Requirements and Allowances

RP 12/14/09 Section 02378 High Density Polyethylene Liner

Experience has shown that obtaining direct and uniform contact between the horizontal layer of HDPE and the underlying GCL is complicated by the thermal expansion and contraction of the large HDPE surface. For this reason, the following requirements and allowances are provided. 1) All HDPE seams shall run parallel to each other (i.e. no transverse seams) with the exception

of necessary repair locations and the circumferential perimeter seam. 2) If required, the following is offered as an acceptable means to achieve maximum uniform

contact: a) Anchor/restrain the outer edges of the HDPE Liner to allow “tension” to be applied

uniformly across the HDPE surface. b) When the ambient temperature is warm and the solar radiation effect on HDPE is at its

greatest, remove any slack from the restraint system. c) HDPE shall be inspected when ambient temperature is cool and there is no solar effect

on the HDPE. Excessive waves shall be identified. NOTE: The HDPE Liner shall be installed in direct and uniform contact with the GCL. (e.g. Excessive waves may be defined as nominally ¾” in amplitude to a maximum height of 1-½“. Basis: The GCL underlying the HDPE will hydrate approximately 3 to 4 times its original thickness. This equates to approximately ¾”. It is expected that the weight of the upper mud mat will further compress the HDPE depending on the time and conditions during placement.

d) Tension shall be relieved, excessive waves repaired, and tension reapplied. During the repair process, care shall be taken not to damage the underlying GCL. Overlap of the GCL shall be verified if a repair occurs at the seam of two adjoining pieces of GCL.

e) Repeat process as necessary until HDPE surface is acceptable per visual examination by SRR.

f) Pour upper mud mat while maintaining tension over the complete surface. Tension shall be maintained for a minimum of 7 days following the placement of the mud mat. (Tension should be adjusted during the pour and during the 24 hour period subsequent to the pour to remove any slack that may develop.) It is recommended that the mud mat placement be made at night (or the coolest part of the day) to minimize thermal effects on the HDPE.

NOTE: The number of daily thermal cycles the HDPE is allowed to experience has a tendency to

adversely affect the frequency and amplitude of developing waves. The Subcontractor shall factor this into scheduling and sequencing of work activities to minimize these cycles prior to placing the upper mudmat.

Page 83: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

GEOSYNTHETIC CLAY LINER

SECTION 02379

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Requirements for the procurement, transportation, storage, testing, and installation of the Geosynthetic Clay Liner (GCL)

1. First stage - Under tank foundation, between the mud mats.

2. Future second stage – Around the tank walls, (minimum 2 feet above base tank floor/wall joint), by others.

3. Future third stage – above tank roof, by others.

B. Interface with and provide protection for the High Density Polyethylene (HDPE) Geomembrane Liner.

1.2 RELATED SECTIONS

A. Division 1 – All Sections

B. Section 02310, Excavation and Foundation Preparation

C. Section 02320, Backfill and Finish Surface

D. Section 02378, High Density Polyethylene Liner

E. Section 03300, Cast-In-Place Concrete

1.3 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards

1. American Society for Testing and Materials (ASTM) a. D 2216, 2005, Standard Test Method for Laboratory Determination of Water

(Moisture) Content of Soil and Rock by Mass b. D 4354, 1999 (R 2009), Standard Practice for Sampling of Geosynthetics for

Testing c. D 4632, 2008, Standard Test Method for Grab Breaking Load and

Elongation of Geotextiles d. D 4873, 2002, Standard Guide for Identification, Storage, and Handling of

Geosynthetic Rolls and Samples e. D 5199, 2001 (R 2006), Standard Test Method for Measuring Nominal

Thickness of Geosynthetics f. D 5887, 2009, Standard Test Method for Measurement of Index Flux

Through Saturated Geosynthetic Clay Liner Specimens Using a Flexible Wall Permeameter

Page 84: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

g. D 5890, 2006, Standard Test Method for Swell Index of Clay Mineral Component of Geosynthetic Clay Liners

h. D 5891, 2002, Standard Test Method for Fluid Loss of Clay Component of Geosynthetic Clay Liners

i. D 5993, 1999 (R 2004), Standard Test Method for Measuring Mass Per Unit of Geosynthetic Clay Liners

j. D 6243, 2008, Standard Test Method for Determining the Internal and Interface Shear Resistance of Geosynthetic Clay Liner by the Direct Shear Method

k. D 6495, 2009, Standard Guide for Acceptance Testing Requirements for Geosynthetic Clay Liners

C. Regulations None

D. Documents None

E. Drawings

1. C-CG-Z-00037, Z-Area Saltstone Disposal Cells 3 & 5 Mudmat Marker Cells 3 & 5 Section And Details

1.4 SUBMITTALS

A. Submit the following Engineering documents in accordance with Section 01330.

1. Geosynthetic Clay Liner Design Details Drawings, 8 Weeks Prior to Use, 1.6 B. 2.

2. Quality Control and Inspection Plan and Procedures, 8 Weeks Prior to Use, 1.6 D. 8.

3. As-Built Drawing(s) of the GCL Layout, 2 Weeks After Completion, 1.6 F and 3.5.

4. Subcontractor GCL Qualification Documentation, With Proposal, 1.7 B.

5. GCL Field Supervisor’s or Superintendent’s Resume and References, 4 Weeks Prior to Work, 1.7 C.

6. GCL IQCI Resume and Certification, 4 Weeks Prior to Work, 1.7.E.4.

7. GCL Storage and Handling Instructions, 2 Weeks Prior to Receipt, 1.8 B. 1.

8. GCL Letter of Compliance (LOC) and Manufacturing Quality Control Test Data, With Delivery, 1.5.C and 2.3.D.3

9. GCL Product Data and Material Specifications, 8 Weeks Prior to Ordering, 2.3. E.

10. GCL Installation Specifications, 8 Weeks Prior to Use, 2.3 F.

11. GCL Liner Installation Drawings, 8 Weeks Prior to Use, 3.1 A. 3.

12. Alternate GCL Repair Procedures, 4 Weeks Prior to Use, 3.3 H. 5.

B. Submit the following Quality Verification documents in accordance with Sections 01330 and 01400:

1. Geosynthetic Clay Liner Inspection and Acceptance Report (Part 1 – Horizontal), 2 Weeks After Installation, 1.5 D.2.

Page 85: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

2. Geosynthetic Clay Liner Inspection and Acceptance Report (Part 2 – Vertical), 2 Weeks After Installation, 1.5 D.3.

3. GCL Acceptance and Inspection Reports, 2 Weeks After Test and With the Delivery, 1.6 E.1.

4. Written Acceptance of the Surface to Receive GCL, Prior to Installation, 3.1 D. 2.

5. Final GCL Acceptance and Inspection Report (Part 1 – Horizontal), 2 weeks After Inspection, 3.4.A.3

6. Final GCL Acceptance and Inspection Report (Part 2 – Vertical), 2 weeks After Inspection, 3.4.A.4.

1.5 TESTING/INSPECTION REQUIREMENTS

A. Inspection and Testing laboratory services shall be in accordance with Section 01450.

B. Subcontractor Inspection

1. Inspect the GCL delivered to the site for conformance with the requirements of this Specification.

2. Inspect the GCL for damage such as cuts, tears, holes, blisters, undispersed raw materials, and other deleterious conditions.

3. Replaced damaged or non-conforming materials.

C. Conformance Testing

1. Field conformance testing of the GCL material is not required.

2. Submit Letter of Compliance (LOC) referenced to the batch, lot, and roll numbers and Manufacturing Quality Control (MQC) test data for the materials delivered at the project site.

D. Inspection and Acceptance of Installed GCL

1. Visually inspect the installed GCL, noting conditions such as overlaps and seams, damaged areas, adequacy of repairs, and quality of installation, in particular where the potential for damage or failure exists.

2. Submit Geosynthetic Clay Liner Inspection and Acceptance Report (Part 1 – Horizontal) for the horizontal liner under the tank base.

3. Submit Geosynthetic Clay Liner Inspection and Acceptance Report (Part 2 – Vertical) for the vertical liner around the tank walls.

1.6 SUBCONTRACTOR RESPONSIBILITIES

A. Provide and install GCL as indicated on the project drawings and follow the Liner manufacturer’s procedures.

B. Perform material selection and prepare the design of all details such as, but not limited to, overlap locations, penetration seals, corners, panel layouts, anchorage, and other necessary details implied or required for the GCL.

1. The design details drawings shall be verified, reviewed, signed and sealed by a Registered Professional Engineer from the Subcontractor and/or lower tier Specialty Contractors’ organization.

Page 86: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

2. Submit the Geosynthetic Clay Liner Design Details Drawings for SRR acceptance.

C. Utilize the services of an independent inspector per Article 1.7. E and Section 01450 to monitor installation and document all testing, placement details, and repair associated with the GCL.

D. Prepare and execute a Quality Control and Inspection Plan that addresses the following:

1. Quality Control Testing and Inspection;

2. Construction and repair procedures applicable to the fabrication, installation, and repair process,

3. GCL deployment,

4. Panel identification coding system.

5. Describe in detail how the geosynthetic materials will be deployed, the equipment that will be used, how it will be coordinated with the HDPE installation and backfill operations, and precautions that will be taken during installation.

6. Precautions to protect the GCL.

7. Check list for field use.

8. Submit the GCL Quality Control and Inspection Plan and Procedures to SRR.

E. Utilize the services of a qualified laboratory per Section 01450 and technicians to sample, test, and prepare test reports for the tests required in this Section.

1. Submit GCL Acceptance and Inspection Reports for review and acceptance by SRR.

F. Submit As-Built Drawing(s) of the GCL Layout to SRR in accordance with the requirements of Section 01330.

1.7 QUALIFICATIONS / CERTIFICATIONS

A. Qualifications and certifications of individuals shall adhere to Section 01450 and the requirements of this Section.

B. Subcontractor: Minimum of two similar projects installing GCL on no less than a combined total of 10 acres in the last 5 years. Submit Subcontractor GCL Qualification Documentation, including references, which verifies the installation qualifications.

C. Field Supervisor or Superintendent: Minimum of two similar projects installing GCL on no less than a combined total of 10 acres. Submit GCL Field Supervisor’s or Superintendent’s Resume and References documenting their qualifications.

D. Field Crew: Knowledgeable and skilled in GCL installation methods and shall have installed, collectively, at least 25 acres of GCL.

E. Independent Quality Control Inspector (IQCI)

1. The IQCI for geosynthetic materials shall function independently and shall not be involved with the performance of construction activities or directly supervise the work being inspected.

2. The IQCI shall: a. Be responsible for inspections, observation, surveillance, and monitoring of

field testing and installation of all geosynthetic materials.

Page 87: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 5 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

b. Produce and submit documented evidence of completion of required tasks of the Project Specification in accordance with approved plans, procedures and inspection reports specified in Section 01450 and the contract documents.

c. Meet the following qualifications and requirements:

i. National Institute for Certification (NICET) Level III or certified by the Geosynthetic Certification Institute (GCI) for geosynthetics material testing and installation tasks for all geosynthetic related work activities. NOTE: The GCI program is governed by the Geosynthetic Institute – Inspectors Certification Program (GSI-ICP).

ii. Construction and inspection experience for a minimum of two projects of similar complexity using geosynthetic materials.

iii. Proven familiarity with construction quality assurance, field inspection and monitoring practices, field and laboratory testing procedures required for geosynthetic materials of the project and implementation, monitoring, and application of analytical techniques required for successful laboratory testing programs.

3. Submit GCL IQCI Resume, Certification and References documenting their qualifications.

1.8 PACKAGING, HANDLING, SHIPPING, AND STORAGE

A. Comply with the requirements of Section 01600.

B. Assure the GCL is shipped, stored, stacked, and handled at the SRS in accordance with the manufacturer’s recommendations and as specified herein.

1. Submit the manufacturer’s GCL Storage and Handling Instructions to SRR.

C. Notify SRR at least twenty-four (24) hours prior to scheduled delivery.

D. Inspect the GCL rolls delivered to the site for damage.

E. Unload and store with minimal handling.

F. Wrap the GCL in plastic to protect it from moisture and degradation during shipment and storage.

G. Separate damaged rolls from undamaged rolls.

1. SRR will be the final authority on the determination of damage and functionality of the damaged material.

2. Remove rejected GCL from the SRS.

H. Folded, twisted, or dragged GCL is not acceptable.

1. Treat the GCL in accordance with ASTM D 4873, the manufacturer’s recommendations, and this Specification.

I. Mark and identify the individual roll labels with the following information:

1. Manufacturer’s name

2. Product identification

3. Batch, lot, and roll numbers

Page 88: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 6 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

4. Roll dimensions and weight

5. Date of manufacture

1.9 QUALITY CONTROL REQUIREMENTS

A. Implement the following quality control attributes for the inspection and verification of materials and workmanship:

1. Prior to Installation of GCL a. Ensure that the foundation layer is prepared in accordance with the Project

Drawings.

i. The topographic survey of the foundation layer shall be reviewed and accepted in accordance with Section 02310 and Section 02320.

b. Ensure that the foundation layer has been placed and compacted in accordance with Section 02310.

i. All testing of the foundation layer shall be complete. ii. Ensure mud mat has been placed in accordance with Section 03300. iii. All test results must be reviewed and accepted by SRR prior to GCL

placement. c. Ensure that the surface of the foundation layer is in accordance with Article

3.1. d. Ensure that Manufacturer testing of the GCL has been completed in

accordance with Article 2.3.

i. All test results must be reviewed and accepted by SRR prior to GCL placement.

e. Ensure that the GCL has been stored in accordance with the manufacturer’s recommendations and Article 1.8, and that the integrity of the GCL has not been compromised during storage.

i. Periodic inspections of the storage area shall be performed in accordance with Article 1.8.

2. During Installation of GCL a. Ensure that GCL is handled and installed according to manufacturer’s

recommendations and Articles 1.8 and 3.2. b. Install panels and overlap in accordance with the layout drawings and

details. c. Ensure overlaps are of required dimensions and are adequately sealed with

dry bentonite. d. Ensure that GCL is dry during placement and is protected from exposure per

Articles 3.2 and 3.6. e. Ensure that overlaps are located in accordance with Article 3.2. f. Ensure that GCL is protected from equipment, foot traffic, and other vehicles

in accordance with Article 3.3. g. Ensure that the GCL is protected from weather and wind damage per Article

3.5. h. Repair damaged GCL in accordance with Article 3.3. i. Replace GCL that becomes saturated in accordance with Article 3.2.

Page 89: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 7 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

B. Notify SRR prior to and following installation of GCL material.

1.10 PROJECT SITE CONDITIONS

A. The GCL is part of the closure cover system.

1. The purpose of this layer is to impede infiltration and seepage of stored material.

2. The GCL shall function as a low permeability barrier and be placed over the lower 4 inch mudmat as depicted on Drawing C-CG-Z-00037. The GCL shall also, extend up to a minimum 2 feet height above the tank floor and wall joint per details to be developed by the liner manufacturer.

B. Coordinate GCL installation with the HDPE Liner installation, Section 02378.

1.11 MAINTENANCE

A. Maintain the installed and uninstalled GCL and protect it from damage and degradation until project completion.

B. Remove excess GCL brought to the site offsite after project closure and prior to demobilization.

PART 2 PRODUCTS

2.1 PERFORMANCE

A. The installed GCL shall act as part of the lower-permeability cover system to impede the infiltration of surface and stormwater and seepage of stored material.

2.2 REQUIREMENTS

A. The GCL shall be fabricated at a manufacturing facility.

B. The GCL shall contain a uniform layer of natural sodium bentonite captured between two layers of supporting geotextile that does not displace when cut.

C. Use Reinforced (needle punched or stitch bonded) GCL. Any adhesives used to manufacture the GCL shall not interfere with the swelling, self-healing, or low permeability properties of the sodium bentonite.

2.3 CRITERIA

A. Geotextile Raw Materials

1. The geotextile shall be fabricated from new, first quality resin and synthetic fibers. The upper and lower geotextiles shall be nonwoven.

2. The surfaces of the GCL shall be free of holes, blisters, undispersed raw materials, or any contamination by foreign matter.

3. The Subcontractor shall include test data from the manufacturer, with the Product Data and Material Specifications, as proof the bentonite, geosynthetic components, and the finished GCL’s were appropriately tested by the manufacturer for the properties shown on Article 2.3.C.

Page 90: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 8 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

B. Geotextile Material Requirements

1. The geotextile shall provide the following functional requirements: a. Prevent the bentonite from displacement during shipping, handling, and

installation of the GCL, b. Protect the bentonite from exposure and mass loss, and c. Maintain a minimum puncture resistance. d. Improve interface shear friction angle between geosynthetic materials.

C. Geosynthetic Clay Liner Criteria

1. The sodium bentonite of the GCL material shall meet following requirements: a. Moisture Content: Test Method - ASTM D 2216, Acceptance Criterion - 20%

maximum b. Swell Index: Test Method - ASTM D 5890, Acceptance Criterion - 24ml /2

gm minimum

2. The GCL shall meet following requirements: a. Bentonite Mass per Unit Area (moisture content 0%): Test Method - ASTM D

5993, Acceptance Criterion – 0.75 lb/sf Minimum Average Roll Value (MARV)

b. Thickness: Test Method - ASTM D 5199, Acceptance Criterion – 0.2 in typical

c. Grab Tensile: Test Method - ASTM D 4632, Acceptance Criterion - 90 lbs MARV

d. Peel Strength: Test Method - ASTM D 4632, Acceptance Criterion - 15 lbs. minimum (modified for 180 degree peel of GCL)

e. Hydrated Internal Shear Strength: Test Method - ASTM D 6243, Acceptance Criterion - 500 lb/sf typical (sample hydrated under 250 psf for 24 hours prior to shear @0.04 in. per min.)

f. Fluid Loss: Test Method - ASTM D 5891, Acceptance Criterion - 18ml maximum

g. Index Flux: Test Method - ASTM D 5887, Acceptance Criterion - 1 x 10-8 m3/m2/sec (1 x 10-6 cm3/cm2/sec) maximum and 5 x 10-9 cm/sec maximum for saturated hydraulic conductivity.

D. At a minimum, each lot number of material for the rolls to be delivered to the project site shall be tested per ASTM D 6495 by the Manufacturer’s Quality Control (MQC).

1. Test data from the manufacturer shall be provided as proof that the GCL components were appropriately tested by the manufacturer, and meet the test values specified in Article 2.3.C.

2. The tests sample section shall be in accordance with ASTM D 4354, Procedure 3.

3. Submit MQC Test Data.

E. Submit GCL Product Data and Material Specifications, with product samples.

F. Submit GCL Installation Specifications.

Page 91: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 9 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

PART 3 EXECUTION

3.1 PREPARATION

A. Prepare the GCL installation drawings;

1. Show the proposed location, orientation, overlap, penetration, tie-in, and anchor details and all associated materials and work necessary for the GCL installation.

2. The design for anchorage (including on tank wall), splicing, layout, placement, repairs, patching, seams, penetrations, overlaps and other system requirements shall be in accordance with manufacturer’s recommendations.

3. Submit the GCL Liner Installation Drawings to SRR.

B. No metal battens, straps, or hardware shall be used for GCL handling and installation.

C. Surfaces to be covered with GCL shall be smooth and free of sharp stones, sharp objects, or debris of any kind. There shall not be any foreign materials/objects between the mudmats and GCL or between GCL and HDPE liner materials.

1. The mudmats surface shall provide a firm unyielding foundation for the GCL with no sudden, sharp, or abrupt changes or breaks in grade.

D. Perform a visual inspection of the surfaces to receive the GCL and provide SRR with a written acceptance of the surface prior to commencing installation.

1. Prepare, clean, or repair unacceptable areas as required.

2. Submit a written Acceptance of the Surface to Receive GCL prior to commencing installation.

E. Provide non-angular, gradual, and rounded edges for GCL placement.

F. Repair any deficiencies in the supporting subgrade/mudmats that have appeared since the acceptance.

3.2 INSTALLATION

A. Install the GCL in a relaxed condition and free of tension, stress, or waves at completion of the installation.

1. Stretching of the GCL to fit is not acceptable.

2. Straighten the GCL to smooth out creases or irregularities in the runs.

3. The Subcontractor IQCI shall document installation activities in detail and submit daily logs to the SRR STR.

B. Seal the GCL overlaps or seams per the manufacturer’s recommendations.

1. The upper and lower geotextile layers shall protect the bentonite from dispersion.

C. Install the GCL in the orientation recommended by the manufacturer. Keep the installed materials free of wrinkles and folds.

D. Mark each panel with an “identification code” (numeric or alphanumeric) consistent with the panel layout plan. The identification code shall be simple and logical for SRR use.

E. Place the GCL material such that the seams are in vertical direction against the tank wall.

Page 92: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 10 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

F. Install GCL material such that there is no end-of-roll horizontal seam against the vertical wall of the tank wall.

G. The GCL seams on horizontal surface shall be a minimum of 5 feet apart from each other.

H. The number of panels deployed and the area of exposed panels shall not exceed the area that can be installed and protected from moisture on the same day.

I. Take the necessary precautions to protect materials underlying the GCL. Do not drive construction equipment on top of GCL after its placement.

J. The GCL material shall be marked with waterproof overlap marks longitudinally on both faces by the manufacturer to assist in obtaining the proper overlap during installation.

1. Overlap distances shall be per the manufacturer’s recommendation.

2. Bentonite shall be placed into the overlap per the manufacturer’s recommendations.

3. Overlap seams shall be placed to assure the upper panel aligns with the match line on the lower panel.

K. During placement, care must be taken not to entrap loose bentonite, stones, or sand in or beneath the GCL, which can hamper subsequent seaming of materials either beneath or above the GCL.

L. Trimming of the GCL should be done with care to minimize loss or shifting of bentonite..

M. Provide measures, such as plastic, to protect GCL from being hydrated during installation.

1. In the event the GCL becomes wet for any reason, the GCL shall be replaced.

3.3 INSTALLATION CONTROL

A. The GCL shall not be deployed during precipitation, in the presence of excessive moisture, in areas of ponded water, or in the presence of excessive winds. The GCL installation shall halt during any form of precipitation and exposed GCL shall be protected and covered immediately.

B. Protect the GCL against wind in accordance with manufacturer’s recommendations. Construction methods shall employ a means of protecting material from sudden wind damage during installation.

C. Take precautions and protect GCL from it being damaged during placement on the tank vertical walls. Use appropriate straps to keep GCL in vertical position during placement of HDPE liner.

D. Use protection board or other construction aid materials to protect installed GCL and HDPE materials from being damaged during backfill operations.

E. Provide earthen berms, swales, sand bags, or other means as required to direct stormwater flows away from the installed GCL. Implement and maintain erosion reduction measures during GCL installation process.

F. Method of Deployment

1. Use equipment which does not damage the GCL or the supporting subgrade/mudmat surface.

2. All personnel working on the GCL shall wear shoes that do not damage the GCL.

Page 93: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 11 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

3. Clamps and other metal tools used in the work area shall have rounded edges (no sharp) corners. Tools shall not be tossed or thrown.

4. Panels shall be unrolled with a method that protects the GCL from scratches and crimps and protects the subgrade/mudmat from damage.

5. Protect the GCL in heavy traffic areas by geotextile, extra GCL, or other suitable materials. a. Materials used for protection shall be temporary and shall not be used as

any part of the permanent installation. b. Heavy traffic areas shall not exceed the manufacturer’s recommendations

for travel over the GCL.

6. Do not allow vehicle traffic directly on the GCL surface.

7. GCL exhibiting shoving, shifting, thinning, or rutting shall be replaced.

8. After installation, the GCL surface shall be visually inspected to ensure that no potentially damaging objects are present, such as stones, cutting blades, small tools, sandbags, etc.

9. Avoid any sudden stops, starts, or turns by construction equipment on backfill placed atop any geosynthetic material.

G. Overlap seams shall be detailed to have the same hydraulic conductivity as required throughout the body of the GCL. Follow additional recommendations by the manufacturer regarding overlap and seaming to achieve the equivalent hydraulic conductivity.

H. Repair holes, tears, or rips in geotextiles using a geotextile patch per Quality Control and Inspection Plan and procedures.

1. Bentonite loss or shifting shall require a full GCL patch of the same GCL product.

2. Patches shall overlap the damaged area a minimum of 12 inches in all directions.

3. Carefully place the loose Bentonite to seal the patch.

4. Nails and staples are not allowed.

5. Submit Alternate GCL Repair Procedures to SRR.

3.4 INSTALLATION TESTS

A. Installation Tests

1. No field tests shall be performed for the Installed GCL Layer. However, the installed GCL shall be visually inspected to comply with all attributes of Articles 1.9, and per the Quality Control and Inspection and procedures.

2. The visual inspection shall note conditions such as overlaps, damaged areas, adequacy of repairs, and all the quality of installation, in particular where the potential for damage or failure exists.

3. Submit a Final GCL Acceptance And Inspection Report (Part 1 – Horizontal) for the horizontal liner under the tank base.

4. Submit a Final GCL Acceptance And Inspection Report (Part 2 – Vertical) for the vertical liner around the tank walls.

Page 94: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 12 of 12

RP 12/14/09 Section 02379 Geosynthetic Clay Liner

3.5 AS-BUILTS

A. Document the GCL as-built information per Article 1.6. The drawing(s) shall include, but is not limited to, the following information:

1. Overlap or seam location and date made a. The amount of overlap for adjacent GCL’s shall be documented and

adhered to in-field placement of the materials. b. The overlap distance is sometimes different for the roll ends versus the roll

edges. Twice the recommended overlap distances should be used and the in-place distances documented.

c. If dry or moistened bentonite (or other material) is to be placed in the overlapped region as stated above, the type and amount shall be documented.

2. Damaged and failed areas

3. Dimensions and type of repair and date repaired

4. Material batch, roll number, and location of the panel and date installed

5. Batch and roll number of repair patches.

3.6 PROTECTION

A. Protect the GCL during transportation, storage, and installation to prevent damage and degradation.

B. Protect the GCL from UV light exposure and damage.

C. Protect the GCL against wind in accordance with manufacturer’s recommendations. Construction methods shall employ a means of protecting material from sudden wind damage during installation.

D. Provide earthen berms, swales, sandbags, or other means as required to direct stormwater flows away from the installed GCL.

E. Implement and maintain erosion reduction measures during GCL installation process.

F. Loads placed on the GCL shall not exceed the manufacturer’s recommendations and shall not cause tearing, puncturing, bentonite extrusion, shoving, or thinning.

G. Equipment used for the deployment of the GCL shall be as recommended by the manufacturer and shall not damage the GCL or other materials.

H. Provide necessary measures such as plastic to prevent GCL from being hydrated by rainwater, stormwater, or groundwater, prior to it being covered by HDPE liner and/or other materials.

3.7 CLEANING

A. Maintain a clean worksite.

B. Upon completion of the GCL installation, clean the work areas and transport and dispose of waste materials.

C. The Subcontractor shall remove any debris, trash, or leftover GCL pieces, damaged or unsatisfactory GCL material following construction activities.

END OF SECTION

Page 95: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 9

RP 12/14/09 Section 02625 Liquid Collection Layer

LIQUID COLLECTION LAYER

SECTION 02625

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Requirements for the procurement, transportation, storage, testing, and installation of the Liquid Collection Layer (LCL). (See Article 2.2.B for description of the LCL)

B. Minimum physical, chemical, and mechanical properties of the LCL.

C. This Section applies to Cell 3A only.

1.2 RELATED SECTIONS

A. Division 1 – All Sections

B. Section 02378, High Density Polyethylene Liner

C. Section 13210, Storage Tanks

1.3 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards

1. American Society for Testing and Materials (ASTM) a. D 413, 1998 (R2007), Standard Test Method for Rubber Property Adhesion

to Flexible Substrate. b. D 1238, 2004, Standard Test Method for Melt Flow Rates of Thermoplastics

by Extrusion Plastometer. c. D 1505, 2003, Standard Test Method for Density of Plastics by the Density-

Gradient Technique d. D 1603, 2006, Standard Test Methods for Carbon Black in Olefin Plastics

Technique e. D 3786, 2009, Standard Test Method for Hydraulic Bursting Strength of

Textile Fabrics f. D 4491, 1999 (R2004), Standard Test Method for Water Permeability of

Geotextiles by Permittivity g. D 4533, 2004 (R2009), Standard Test Method for Trapezoid Tearing Strength

of Geotextiles. h. D 4632, 2008, Standard Test Method for Grab Breaking Load and Elongation

of Geotextiles. i. D 4716, 2001, Test Method for Determining the (In-Plane) Flow Rate per Unit

Width and Hydraulic Transmissivity of a Geosynthetic Using a Constant Head.

j. D 4751, 2004, Standard Test Method for Determining Apparent Opening Size of a Geotextile.

Page 96: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 9

RP 12/14/09 Section 02625 Liquid Collection Layer

k. D 4833, 2007, Standard Test Method for Index Puncture Resistance of Geotextiles, Geomembranes, and Related Products

l. D 4873, 2002, Standard Guide for Identification, Storage, and Handling of Geosynthetic Rolls and Samples

m. D 5199, 2001 (R2006), Standard Test Method for Measuring the Nominal Thickness of Geosynthetics

n. D 5261, 1992, Standard Test Method for Measuring Mass per Unit Area of Geotextiles.

C. Documents None

D. Drawings

1. C-CG-Z-00037, Z-Area Saltstone Disposal Cells 3 & 5 Mudmat Marker Cells 3 & 5 Section And Details.

1.4 SUBMITTALS

A. Submit the following Engineering documents in accordance with Section 01330:

1. LCL Quality Control and Inspection Plan and Procedures, 1.6 D.5.

2. Subcontractor LCL Qualification Documentation, 1.7 B.1.

3. LCL Field Supervisor’s or Superintendent’s Resume and References, 1.7 C.1.

4. LCL IQCI Resume and Certification, 1.7 E.3.

5. LCL Manufacturer’s Storage and Handling Instructions, 1.8 B.1.

6. LCL Product Data and Material Specifications, 2.3.C.

7. LCL Installation Specifications, 2.3 D.

8. LCL Design / Installation / Details / and Layout Drawings, 3.1 C.

9. LCL As-Built Drawings, 3.3 E.

B. Submit the following Quality Verification documents in accordance with Sections 01330 and 01400:

1. LCL Hydraulic Transmissivity Test Data, 1.5 C.4.

2. LCL Final Inspection and Acceptance Report, 1.5 D.3.

3. LCL Certificate of Compliance and/or Manufacturing Quality Control (MQC) Test Data, 2.3 A.

4. Material Test Report for LCL Geotextile Filter Fabric Material, 2.3 B.2.

1.5 TESTING/INSPECTION REQUIREMENTS

A. Utilize Inspection and Testing laboratory services in accordance with Section 01450.

B. Subcontractor Inspection

1. Inspect all LCL delivered to the site for conformance with the requirements of this Specification.

2. Inspect the LCL for damage.

3. Replace damaged or non-conforming materials.

Page 97: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 9

RP 12/14/09 Section 02625 Liquid Collection Layer

C. Subcontractor Conformance Testing

1. The LCL shall comply with the requirements of PART 2 of this Section.

2. The LCL shall be tested for hydraulic transmissivity per ASTM D 4716. The conditions for testing are as follows: a. Water temperature shall be 68 °F plus or minus 3 °F. b. Hydraulic gradient shall not exceed 0.1. c. Normal compressive stress shall be 21 psi. d. The LCL shall be placed between a layer of concrete on the upper surface

and the same HDPE used in Section 02378 on the lower surface. e. The minimum test duration shall be 24 hours with measurements recorded at

0, 3, 6, 12, 18, and 24 hrs. f. Minimum hydraulic transmissivity shall be 2 x 10-4 m2/s (2.2 x 10-3 ft2/s). g. Samples shall be tested parallel to the machine direction (MD).

3. Tests shall be performed on a sample from each lot of material used.

4. Submit LCL Hydraulic Transmissivity Test Data to SRR for review and acceptance.

D. Final Inspection and Acceptance of Installed LCL

1. Acceptance of the installed LCL shall be based on visual inspection by SRR and the results of conformance testing per criteria given in the Specification.

2. The visual inspection shall note conditions such as seams, damaged areas, adequacy of repairs, and the quality of installation, in particular where the potential for damage or failure exists.

3. Submit a LCL Final Inspection and Acceptance Report for review and acceptance by SRR.

1.6 SUBCONTRACTOR RESPONSIBILITIES

A. Provide and install the LCL as indicated on the Project Drawings and follow the manufacturer’s procedures.

B. Perform material selection and the design of all details such as, but not limited to, seams, corners, panel layouts, and other necessary details implied or required for the installation of the LCL.

1. Design drawings shall be verified, reviewed, signed and sealed by a Registered Professional Engineer.

C. Utilize the services of an Independent Quality Control Inspector (IQCI) per Article 1.7.E to monitor and document all installations, testing, placement details, and repair associated with the LCL.

D. Prepare and execute a LCL Quality Control and Inspection Plan that addresses the following:

1. Quality Control Testing and Inspection;

2. Construction and repair procedures applicable to the fabrication, installation, and repair process;

3. LCL deployment, and a panel identification coding system.

Page 98: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 9

RP 12/14/09 Section 02625 Liquid Collection Layer

4. Describe in detail how the geosynthetic materials will be deployed, the equipment that will be used, precautions that will be taken during installation, and how concrete will be placed atop the geosynthetics/LCL.

5. Submit the LCL Quality Control and Inspection Plan and Procedures.

E. Utilize the services of a qualified laboratory per Section 01450 and technicians to sample, test, and prepare test reports for the tests required in this Section.

F. Prepare as-built LCL drawing(s).

1.7 QUALIFICATIONS / CERTIFICATIONS

A. Qualifications and certifications of individuals shall adhere to Section 01450 and the requirements of this Section.

B. The Subcontractor shall have successfully installed LCL on a minimum of three similar projects of no less than a combined total of 10 acres.

1. Submit Subcontractor LCL Qualification Documentation, including references, which verifies the installation qualifications.

C. The Field Supervisor or Superintendent who will be supervising the geosynthetics installation shall have been responsible for successfully installing two or more similar closure systems using a similar LCL with a combined total area greater than 10 acres.

1. Submit LCL Field Supervisor’s or Superintendent’s Resume and References documenting their qualifications.

D. The Field Crew shall be knowledgeable and skilled in all aspects of LCL seam preparation and liner installation methods. The Field Crew shall have installed, collectively, at least 25 acres of LCL.

E. Independent Quality Control Inspector (IQCI)

1. The IQCI for LCL shall function independently and shall not be involved with the performance of construction activities or directly supervise the work being inspected.

2. The IQCI shall: a. Be responsible for inspections, observation, surveillance, and monitoring of

field testing and installation of all geosynthetic materials. b. Produce and submit documented evidence of completion of required tasks of

this Specification in accordance with approved plans, procedures and inspection reports specified in Section 01450 and the contract documents.

c. Meet the following qualifications and requirements:

i. National Institute for Certification (NICET) Level III or certified by the Geosynthetic Certification Institute (GCI) for geosynthetics material testing and installation tasks for all geosynthetic related work activities. NOTE: The GCI program is governed by the Geosynthetic Institute – Inspectors Certification Program (GSI-ICP).

ii. Construction and inspection experience for a minimum of two projects of similar complexity using geosynthetic materials.

Page 99: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 5 of 9

RP 12/14/09 Section 02625 Liquid Collection Layer

iii. Proven familiarity with construction quality assurance, field inspection and monitoring practices, field and laboratory testing procedures required for geosynthetic materials of the project and implementation, monitoring, and application of analytical techniques required for successful laboratory testing programs.

3. Submit LCL IQCI Resume and Certification, including references documenting their qualifications.

1.8 PACKAGING, HANDLING, SHIPPING, AND STORAGE

A. Comply with the requirements of Section 01600.

B. The Subcontractor is responsible for assuring the LCL is shipped, stored, stacked, and handled at SRS in accordance with the manufacturer’s recommendations and as specified herein.

1. Submit a copy of the LCL Manufacturer’s Storage and Handling Instructions.

C. Notify SRR at least twenty-four (24) hours prior to scheduled delivery.

D. Inspect the LCL rolls delivered to the site for damage.

E. Unload and store with minimal handling.

F. Wrap the LCL in plastic to protect it from moisture and degradation during shipment and storage.

G. Separate damaged rolls from undamaged rolls.

1. SRR will be the final authority on the determination of damage and functionality of the damaged material.

2. Remove rejected LCL from SRS.

H. No hooks, tongs, or other sharp tools or instruments shall be used for handling the LCL.

1. Use cloth chokers and spreader bars for loading and unloading and spreader bars and roll bars for deployment.

2. Rolls shall be lifted by inserting a steel bar capable of supporting the full weight of the roll through the center core.

3. Manufactured or specially fabricated spreader bars shall be certified and clearly marked with maximum load limitations.

I. The LCL shall not be folded, twisted, or dragged.

1. Treat the LCL in accordance with ASTM D 4873, the manufacturer’s recommendations, and this Specification.

J. Mark and identify the individual roll labels with the following information:

1. Manufacturer’s name

2. Product identification

3. Batch, lot, and roll numbers

4. Roll dimensions and weight

5. Date of manufacture

Page 100: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 6 of 9

RP 12/14/09 Section 02625 Liquid Collection Layer

1.9 PROJECT SITE CONDITIONS

A. The LCL is part of the liquid sampling system. This will be placed over the HDPE and below the upper mudmat. (Reference C-CG-Z-00037)

B. Installation of the LCL may begin as soon as the HDPE has been installed and approved.

1.10 MAINTENANCE

A. Maintain the installed and uninstalled LCL and protect it from damage and degradation until the upper mudmat has been placed.

B. Remove from SRS any excess LCL brought to the site after project closure and prior to demobilization.

PART 2 PRODUCTS

2.1 PERFORMANCE

A. In the event that liquid leaks from the cell, it is gravity-drained to the LCL. The LCL shall provide effective transport of liquid from beneath the base of the cell to the collection sump.

B. The LCL shall resist biological fouling, provide support to the overlying layers, and shall not slip with the overlying concrete and the underlying HDPE.

2.2 REQUIREMENTS

A. The LCL shall be fabricated at a manufacturing facility and shall be manufactured of new, first quality materials.

B. The LCL shall consist of an HDPE geonet with a geotextile fabric bonded to both sides and shall maintain sufficient shear strength to prevent internal slippage during and after construction.

C. The LCL composite shall be furnished free of holes, blisters, undispersed raw materials, striations, roughness, or any sign of contamination by foreign matter. Defective material shall be replaced by the Subcontractor.

2.3 CRITERIA

A. Submit a LCL Certificate of Compliance and/or Manufacturing Quality Control (MQC) Test Data from the manufacturer as proof that the LCL components were appropriately tested by the manufacturer for the properties shown in the table below.

1. Documentation shall include reference to the batch, lot and roll numbers.

Page 101: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 7 of 9

RP 12/14/09 Section 02625 Liquid Collection Layer

Property Test Method Units Value

GEONET

Resin Density ASTM D 1505 g/cm3 0.94 (minimum) Resin Melt Flow Index ASTM D 1238 g/10 minutes 1.0 (maximum) Thickness ASTM D 5199 mils 100 (minimum) Carbon Black Content ASTM D 1603 percent 2 to 3 (typical)

GEOTEXTILE

Weight (Upper/Lower) ASTM D 5261 oz/yd2 5.7 (minimum) Grab Tensile Strength ASTM D 4632 lbs 150 (minimum) Puncture Strength ASTM D 4833 lbs 75 (minimum) Trapezoidal Tear ASTM D 4533 lbs 60 (minimum) Mullen Burst Strength ASTM D 3786 psi 220 (minimum) Apparent Opening Size ASTM D 4751 sieve size 70 to 120 (typical) Hydraulic Conductivity /Permeability ASTM D 4491 cm/sec 0.01 (max)

GEOCOMPOSITE

Thickness ASTM D 5199 in 0.2 (minimum) Peel Strength ASTM D 413 lbs/ft 24 (minimum) Transmissivity ASTM D 4716 m2/sec 2 x 10-4 (minimum)

B. Perimeter Drainage Materials

1. Geotextile filter fabric shall be nonwoven, spun bonded 100 percent continuous filament polypropylene with a minimum average roll value weight of 8 ounces per square yard (per ASTM D 5261) and possess an equivalent apparent opening size of 70 to 120 sieve as determined by ASTM D 4751.

2. Submit a Material Test Report for LCL Geotextile Filter Fabric Material.

C. Submit LCL Product Data and Material Specifications, with product samples.

D. Submit LCL Installation Specifications.

PART 3 EXECUTION

3.1 PREPARATION

A. Prepare LCL Design / Installation / Details / and Layout Drawings showing the proposed location, orientation, splices, and anchor details for the LCL and all associated materials and work necessary for the LCL installation.

B. The design for anchorage, splicing, layout, placement, repairs, and other system requirements shall be in accordance with manufacturer’s recommendations and shall be the responsibility of the Subcontractor.

C. Submit the LCL Design / Installation / Details / and Layout Drawings.

D. No metal battens, straps, or hardware shall be used for LCL handling and installation.

E. Any deficiencies in the HDPE that have appeared since acceptance of the HDPE surface shall be repaired.

Page 102: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 8 of 9

RP 12/14/09 Section 02625 Liquid Collection Layer

3.2 INSTALLATION

A. The LCL shall be installed in a condition that conforms to the underlying HDPE at completion of the installation. The LCL shall be straightened to smooth out creases or irregularities in the runs.

B. The LCL shall be installed as recommended by the manufacturer.

C. Each panel shall be marked with an “identification code” (numeric or alphanumeric) consistent with the panel layout plan.

1. The identification code shall be simple and logical and approved for use by SRR.

D. The number of panels deployed and the area of exposed panels shall not exceed the area that can be installed and protected from weather on the same day.

E. Take the necessary precautions to protect materials underlying the LCL.

1. Manufacturer’s recommendations shall apply to working on the HDPE surface. Refer to Section 02378 for damage and repair of the HDPE.

F. Joining of the LCL panels shall be per the manufacturer’s recommendations.

1. All panels shall be aligned with no gaps between panels.

2. The drainage function and efficiency of the LCL shall not be hindered in any way.

G. Document the LCL seam information on the LCL As-Built Drawings.

H. Trimming of the LCL should be done with care to prevent tearing of the geotextile from the geonet or the geotextile itself.

3.3 INSTALLATION CONTROL

A. The LCL shall not be deployed during precipitation, in the presence of excessive moisture, in areas of ponded water, or in the presence of excessive winds.

B. Method of Deployment

1. Use equipment, which does not damage the LCL or the liners beneath.

2. All personnel working on the LCL shall wear shoes that do not damage the LCL.

3. Panels shall be unrolled with a method that protects the LCL from scratches and crimps.

4. Do not allow vehicle traffic directly on the LCL surface.

5. After installation, the LCL surface shall be visually inspected to ensure that no potentially damaging objects are present, such as stones, cutting blades, small tools, sandbags, etc.

C. Holes, tears, or rips in geotextiles shall be repaired in accordance with the approved manufacturer’s repair procedures.

D. Prepare LCL As-Built Drawings including, but not limited to, the following information:

1. Seam location and date made.

2. Damaged and failed areas, dimensions, and type of repair and date repaired.

3. Material batch, roll number, and location of the panel and date installed.

4. Batch and roll number of repair patches.

Page 103: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 9 of 9

RP 12/14/09 Section 02625 Liquid Collection Layer

E. Submit the LCL As-Built Drawings.

3.4 PROTECTION

A. Protect the LCL against wind in accordance with manufacturer’s recommendations. Construction methods shall employ a means of protecting material from sudden wind damage during installation.

B. The LCL shall be protected during transportation, storage, and installation to prevent damage and degradation.

C. Loads placed on the LCL shall not exceed the manufacturer’s recommendations and shall not cause tearing, puncturing, shoving, or thinning. Equipment used for the deployment of the LCL shall be as recommended by the manufacturer and shall not damage the LCL or other materials.

D. The upper mudmat shall be placed on the LCL in accordance with the requirements of Sections 03300 and 13210.

3.5 CLEANING

A. Maintain a clean worksite. Do not leave any debris, trash, or leftover LCL pieces after the installation of the LCL.

B. Excess LCL brought to the site shall be removed from SRS and dispositioned by the Subcontractor after project closure and prior to demobilization.

C. Remove from SRS and disposition damaged or unsatisfactory LCL material.

END OF SECTION

Page 104: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 5

RP 12/14/09 Section 02630 Storm Drainage

STORM DRAINAGE

SECTION 02630

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Storm drainage pipe, culverts, and appurtenances

B. Subdrain Discharge Structure and appurtenances

1.2 RELATED SECTIONS

A. Division 1 – All Sections

B. Section 02370, Erosion & Sediment Control

1.3 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards

1. American Society for Testing and Materials (ASTM) a. A 48, 2003, Standard Specification for Gray Iron Casting b. C 443, 2005, Standard Specification for Joints Circular Sewer and Culvert

Pipe Using Rubber Gaskets. c. C 913, 2008, Standard Specification for Pre-cast Concrete water and

Wastewater Structures d. D 1248, 2005, Standard Specification for Polyethylene Plastics Extrusion

Materials for Wire and Cable e. D1557, 2007 (E2003), Standard Test Methods for Laboratory Compaction

Characteristics of soil Using Modified Effort f. D 3212, 2007, Standard Specification for Joints for Drain and Sewer Plastic

Pipes Using Flexible Elastomeric Seals g. D 3350, 2008, Standard Specification for Polyethylene Plastics Pipe and

Fittings Materials h. D 3786, 2009, Standard Test Method for Hydraulic Bursting Strength of

Textile Fabrics Diaphragm Bursting Strength Tester Method i. D 4751, 2004, Standard Test Method for Determining Apparent Opening

Size of a Geotextile j. D 4833, 2007, Standard Test Method for Index Puncture Resistance of

Geotextiles, Geomembrane and Related Products. k. D 5261, 1992, Standard Test Method for Measuring Mass per Unit Area of

Geotextiles. l. F 1417, 1992 (R 2005), Standard Test Method for installation Acceptance of

Plastic Gravity Sewer Lines Using Low-Pressure Air.

Page 105: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 5

RP 12/14/09 Section 02630 Storm Drainage

2. American Association State Highway Transportation Officials (AASHTO) a. M 294, 2009, Standard Specification for Corrugated Polyethylene Pipe, 300-

to 1500- mm Diameter

C. Regulations None

D. Documents None

E. Drawings

1. WB00122W-020, Z-Area Saltstone Disposal Cells 3 & 5 Pre-Construction Excavation Sections And Details

1.4 DEFINITIONS

A. Bedding – Fill materials placed from the subgrade of the excavation to the bottom of the pipe.

B. Final Backfill – Fill material placed above initial backfill to finish grade.

C. Initial Backfill – Fill material placed around the pipe and up to a point one foot above the top of the pipe.

D. Over Excavation – Removal of in-situ materials beyond the limits required by the specification or shown on the Construction Drawings and not authorized in writing by SRR.

1.5 QUALITY ASSURANCE

A. Reference Section 01400 – Quality Requirements.

1.6 SUBMITTALS

A. Submit the following Engineering Documents in accordance with Section 01330:

1. Storm Drainage Product Data/Catalog Cuts, 4 Weeks Prior to Use, 2.1 A.5

B. Submit the following Quality Verification documents in accordance with Sections 01330 and 01400:

1. Subdrain Discharge Structure Inspection And Compaction Test Data, 3.2.H.1

2. Initial Backfill Inspection and Compaction Test Data, 3.4.D.1

3. Final Backfill Inspection and Compaction Test Data, 3.5.C.1

1.7 PACKAGING, HANDLING, SHIPPING, AND STORAGE

A. Package, handle, ship, store and protect products in accordance with Section 01600.

Page 106: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 5

RP 12/14/09 Section 02630 Storm Drainage

PART 2 PRODUCTS

2.1 PIPE AND ACCESSORIES

A. Corrugated Plastic Pipe and Fittings:

1. Material: Perforated and non-Perforated (French drain) pipes- High Density Polyethylene ASTM D 3350 minimum cell classification 335420C, or ASTM D 1248 Type III, Class S, Category 4, Grade P33 meeting AASHTO M 294, Type S.

2. French Drain Perforations: Class S pipe with Class 1 perforations

3. Fittings: AASHTO M 294, Fabricated fittings shall be welded on the interior and exterior at all junctions.

4. Joint for Storm Drain: Bell and Spigot joints per AASHTO M 294 with elastomeric rubber gasket for water tightness per ASTM D 3212-A and/or ASTM F 1417.

5. Submit Storm Drainage Product Data /Catalog Cuts a. Provide for pipes, fittings, joint materials, and associated accessories.

2.2 BACKFILL MATERIALS:

A. Bedding material and initial backfill materials for the storm drain shall be CLSM per Section 03300 or Structural Fill material per Section 02320.

B. Final backfill material for the storm drain can be common fill or structural fill material per Section 02320.

2.3 GEOTEXTILE FILTER

A. Material shall be a non-woven, spun bonded 100 percent continuous filament polypropylene, unit weight of 8 ounces per square yard as determined by ASTM D 5261.

B. Equivalent apparent opening size of 70 to 120 sieve as determined by ASTM D 4751.

C. Puncture resistance of 100 pounds as determined by ASTM D 4833

D. Bursting Strength of 300 psi as determined by ASTM D 3786.

PART 3 EXECUTION

3.1 PIPE INSTALLATION

A. General:

1. Verify existing conditions before starting work. Verify excavation base is ready to receive work and excavations, dimensions, and elevations are as indicated on Construction Drawings.

2. Provide methods to carry the pipe to final location for placement. Do not drop or drag the pipe.

3. Divert drainage or dewater trenches/excavations during construction as necessary.

B. Excavation:

1. Excavate in accordance with Contract Drawings. Trenches excavated shall be maintained in clean condition and shall be free from leaves, brush, trash and other debris.

Page 107: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 5

RP 12/14/09 Section 02630 Storm Drainage

2. Where unyielding material is encountered in the bottom of trench, remove material 4 inches below the required grade and replace with CLSM or structural fill material.

3. Do not compact CLSM layer. Compact the structural fill material to not less than 95% of the laboratory maximum dry density as determined by ASTM D 1557.

C. Pipe Placement:

1. Inspect pipe for damage or defects prior to placement. Replace damaged items.

2. Lay pipe to the location, line, grade and slope gradients noted on Construction Drawings Remove and reinstall if grade is disturbed after laying.

3. Laying pipe in water or when trench conditions are unacceptable is prohibited.

D. Pumping:

1. Provide pumping necessary for dewatering trenches and to maintain proper work conditions for installation of pipe.

3.2 SUBDRAIN DISCHARGE STRUCTURE INSTALLATION

A. Install pre-fabricated Subdrain Discharge Structure as shown on drawing WB00122W-020.

B. Pre-cast Subdrain Discharge Structure shall conform to ASTM C 913 and shall be able to withstand AASHTO HS-20 loading.

C. Joints for pre-cast Subdrain Discharge Structure stacks shall be tongue and groove with rubber-type gaskets meeting the requirements of ASTM C 443. Openings in the Subdrain Discharge Structure walls for incoming and outgoing pipes shall be pre-cast and, after installation, sealed with a non-shrink grout.

D. Castings for the Subdrain Discharge Structure shall conform to the requirements of ASTM A 48, Class 35B.

E. Install Subdrain Discharge Structure atop 12 inches thick compacted gravel base.

F. Use structural fill or CLSM as backfill material around Subdrain Discharge Structure.

G. Place structural fill material uniformly along each side of the Subdrain Discharge Structure in loose layers not exceeding six (6) inches, and compact fill material with hand held compactor taking care not to damage the Subdrain Discharge Structure, piping or piping accessories.

H. Compact initial fill material to not less than 95% of the laboratory maximum dry density as determined by ASTM D 1557.

1. Submit Subdrain Discharge Structure Inspection And Compaction Test Data.

3.3 BEDDING

A. Use CLSM as bedding material.

B. CLSM may be screeded, if required, to provide a uniform grade but shall not be vibrated.

C. Care shall be taken to prevent floating or displacement of the pipe. Place CLSM only to the pipe spring line and allow CLSM to set until no longer fluid. There are no compaction or lift thickness requirements with use of CLSM.

Page 108: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 5 of 5

RP 12/14/09 Section 02630 Storm Drainage

3.4 INITIAL BACKFILL

A. Use CLSM or structural fill material for initial backfill.

B. Prevent floating or displacement of the pipe when CLSM is used as initial fills material.

C. Place structural fill material uniformly along each side of the pipe in loose layers not exceeding six (6) inches, and compact fill material with hand held compactor taking care not to damage the piping or piping accessories.

D. Compact initial fill material to not less than 95% of the laboratory maximum dry density as determined by ASTM D 1557.

1. Submit Initial Backfill Inspection and Compaction Test Data.

3.5 FINAL BACKFILL

A. Use common fill or structural fill material for final backfill.

B. Place fill material uniformly along each side of the pipe in loose layers not exceeding twelve (12) inches, and mechanically compact.

C. Compact final backfill material to not less than 90% of the laboratory maximum dry density as determined by ASTM D 1557.

1. Submit Final Backfill Inspection and Compaction Test Data.

D. Repeat placement of fill and compaction to depth noted on Construction Drawings.

3.6 INSTALLATION TOLERANCES

A. Horizontal alignment: Plus or Minus 2 inches.

B. Vertical alignment: Plus or Minus 0.10 feet.

3.7 INSPECTION

A. Inspection Requirements

1. Inspect work to confirm that the following attributes meet specified requirements: a. Excavation and trenching within specified requirements. b. Proper materials utilized. c. Installation meets specified requirements.

END OF SECTION

Page 109: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 8

RP 12/14/09 Section 02900 Soil Preparation and Seeding

SOIL PREPARATION AND SEEDING

SECTION 02900

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Preparation of subsoil.

B. Seeding and hydroseeding.

C. Erosion control matting

D. Maintenance.

1.2 RELATED SECTIONS

A. Division 1 – All Sections

B. Section 02310, Excavation and Foundation Preparation

C. Section 02320, Backfill and Finish Surface

D. Section 02370, Erosion and Sediment Control

1.3 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards

1. American Society for Testing and Materials (ASTM) a. C 602, 2007, Standard Specification for Agricultural Liming Materials b. D 4972, 2001 (R 2007), Standard Test Method for pH of Soils c. D 5268, 2007, Standard Specification for Topsoil Used for Landscaping

Purposes

C. Regulations None

D. Documents 1. WB00122W-013, Stormwater Pollution Prevention Plan (SWPPP) for Z –Area

Saltstone Disposal Cells 3 and 5.

E. Drawings None

1.4 QUALITY ASSURANCE

A. Provide seed mixture in containers showing percentage of seed mix, germination percentage, inert matter percentage, weed percentage, year of production, net weight, date of packaging, and location of packaging.

Page 110: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 8

RP 12/14/09 Section 02900 Soil Preparation and Seeding

1.5 NOTIFICATION AND COORDINATION

None

1.6 SUBMITTALS

A. Submit the following Quality Verification documents in accordance with Sections 01330 and 01400:

1. Topsoil Properties Test Data, 2.1.D.1

1.7 DELIVERY, STORAGE, AND HANDLING

A. Section 01600 - Product Requirements: Product storage and handling requirements.

B. Deliver grass seed mixture in sealed containers. Seed in damaged packaging is not acceptable.

C. Tag seed containers to show weight, seed analysis, percent germination, and vendor name.

D. Deliver fertilizer in waterproof bags showing weight, chemical analysis, and name of manufacturer.

E. Handle and store products in accordance with the manufacturer's recommendations.

1.8 COORDINATION

A. Coordinate installation of ground cover with cessation of earthwork activities.

1.9 ACCEPTANCE OF LONG TERM VEGETATION

A. Provide a satisfactory stand of perennial grass whose root system has developed sufficiently to survive dry periods, winter weather conditions, and be capable of reestablishment in the spring.

1. Acceptance is based on ESS/SCDHEC and Natural Resources Conservation Service (NRCS) standards and field walk downs.

2. Minimum acceptance criteria for establishment of vegetation shall be: a. A uniform 70 percent cover of long term vegetation over the area requiring

vegetation, and b. Minimal quantity of bare spots as noted below.

B. Rectify conditions as noted if criteria is not met.

1.10 MAINTENANCE AND SERVICES

A. Comply with the requirements of the Stormwater Pollution Prevention Plan (SWPPP), Document, WB00122W-013.

B. Maintain the seeded/sodded area until final acceptance of controls and water as necessary to promote growth until establishment and acceptance of long term grass. Sources of water are specified in the Subcontract Field Conditions.

1. Perform reseeding and re-fertilizing of areas where required during the maintenance period.

2. Maintenance period shall be defined as the period between commencement of seeding and/or sodding and acceptance per Article 1.9.

Page 111: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 8

RP 12/14/09 Section 02900 Soil Preparation and Seeding

3. Mowing shall be performed as necessary to maintain and promote the establishment of grasses. Mowing shall be performed in a manner and frequency such that cut grass does not significantly clump and/or cover underlying grasses to a point that it expires.

C. Repair and maintain areas that have eroded due to runoff until completion of all construction activities. Erosion control measures per Section 02370 shall be implemented as necessary.

D. Refer to Subcontract Field Conditions for additional turnover requirements.

PART 2 PRODUCTS

2.1 SOIL PREPARATION MATERIALS

A. Topsoil: Use existing topsoil that was excavated and stockpiled. Provide additional topsoil as required from offsite source.

B. Topsoil: Friable soil capable of supporting vegetative growth that is free from trash, debris, stones larger than 1-1/2 inches, weeds, roots, sticks, brush, and other vegetation not suitable for subsequent seeding operations and maintenance.

C. Topsoil shall be medium–textured soil such as loam or sandy loam that complies with requirements of ASTM D 5268 with following properties:

1. Organic matter content greater than 3 percent by weight

2. pH greater than 5

3. Soluble salts less than 500 ppm

4. Sodium adsorption less than 12

D. Perform a minimum one (1) test for the above parameters (Article 2.1.C) from a composite sample for every 500 CY of topsoil to be installed.

1. Submit Topsoil Properties Test Data.

E. Use commercially available products to adjust the Organic matter content, pH, soluble Salts and Sodium adsorption content within specified limits, if their values are not within the specified limits. Blend the additives and topsoil, as required such that the topsoil will result with uniform consistency of additives.

F. Mulch Binder: Commercially available organic glue type tackifier or chemical mulch binder.

G. Fertilizer: Commercial grade 10-10-10; uniform in composition, dry and free flowing to the following proportions: Nitrogen ten (10) percent, phosphoric acid ten (10) percent, soluble potash ten (10) percent .

H. Lime: ASTM C 602 REV A, Class T or Class O agricultural limestone containing a minimum 80 percent calcium carbonate equivalent.

I. Water: Clean, fresh and free of substances or matter capable of inhibiting vigorous growth of grass.

2.2 TEMPORARY SEEDING

A. Fall and Winter Planting: Use Annual Ryegrass at rate of 56 pounds per acre.

B. Spring and Summer Planting: Use Brown top Millet at a rate of 40 pounds per acre.

Page 112: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 8

RP 12/14/09 Section 02900 Soil Preparation and Seeding

2.3 PERMANENT/LONG TERM SEEDING

A. September – February:

Seed Rate (Pounds per Acre)

Rye (Grain) 10 Common Bermuda (unhulled) 130

1. Seeding planted during the months from September to February may fail to

provide adequate vegetative cover. If it is determined that permanent vegetation is sparse and not adequately established, then re-fertilization of the affected areas and over seeding shall be performed at the following rates (the topsoil shall be scarified prior to re-seeding or over seeding): a. Early March:

Seed

Rate (Pounds per Acre)

Rye (Grain) 10 Common Bermuda (hulled) 86

b. Late March:

Seed Rate (Pounds per Acre)

Brown Top Millet 10 Common Bermuda (hulled) 86

B. March:

Seed Rate (Pounds per Acre)

Rye (Grain) 10 Common Bermuda (hulled) 90

C. April - July:

Seed Rate (Pounds per Acre)

Browntop Millet 10 Common Bermuda (hulled) 45 Centipede 5

NOTE: Carpetgrass at a rate of 40 pounds per acre may be used in lieu of centipede.

D. August:

Seed Rate (Pounds per Acre)

Browntop Millet 10 Common Bermuda (hulled) 65 Common Bermuda (unhulled) 65 Centipede 5

NOTE: Carpetgrass at a rate of 40 pounds per acre may be used in lieu of centipede.

Page 113: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 5 of 8

RP 12/14/09 Section 02900 Soil Preparation and Seeding

E. July – August:

1. Seeding requirement in Articles 2.3.C and 2.3.D are the minimum recommended for bidding purposes only. These months are marginal for planting and establishing permanent vegetation. Therefore the seeding shall be as recommended by the NRCS. The Subcontractor may plant temporary vegetation during this time frame and wait to plant long term vegetation during a more optimal planting season. In either case, acceptance and maintenance per Articles 1.9 and 1.10 shall apply.

2.4 MULCH

A. Straw: Long stem rye, wheat, oats, or barley that is not rotten or brittle.

B. Hydromulch: Natural wood cellulose with no bark; may contain 100 percent recycled material.

2.5 EROSION CONTROL MATTING

A. Coconut fiber or recycled nylon fiber matrix sewn between two nets with a weight of at least 0.50 lbs per sq. ft. or equivalent capable of withstanding flow velocities up to 7 ft/sec.

2.6 SOD

A. Sod shall be commercially available Centipede or Bermuda sod.

PART 3 EXECUTION

3.1 GENERAL

A. Temporary Vegetation

1. Install temporary vegetation seeding with erosion control matting or sprayed-on emulsified asphalt on the side slopes of the excavated area.

2. Install temporary vegetation seeding all temporary berms, cut and fill slopes, and diversion channels.

3. Install temporary vegetation seeding on stock pile.

B. Permanent/Long-Term Vegetation

1. Install long term vegetation seeding over all finish grades of disturbed areas including stock pile area.

2. Install sod in permanent channels and their side slopes and on all graded areas with side slopes greater than 4H:1V.

3.2 PREPARATION OF SUBSOIL

A. Prior to the placement of topsoil on excavated and filled slopes, roughen the slope surface by creating shallow groves to depth of 1.5 inches where topsoil is to be placed. Repeat cultivation in areas where equipment, used for hauling and spreading topsoil, has compacted sub-soil.

Page 114: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 6 of 8

RP 12/14/09 Section 02900 Soil Preparation and Seeding

3.3 PLACING TOPSOIL

A. Place topsoil to minimum depth of 4 inches over area to be seeded with long term vegetation.

1. Use existing stockpiled topsoil and/or from offsite source.

2. Rake until smooth.

3. Lightly compact the topsoil to ensure good contact with the underlying soil, but avoid excessive compaction by utilizing a roller.

B. Place topsoil during dry weather and on dry unfrozen subgrade.

C. Remove vegetable matter and foreign non-organic material from topsoil while spreading.

D. Grade topsoil to the grades indicated on the contract drawings to eliminate rough, low or soft areas, and to ensure positive drainage.

E. Scarify the topsoil to a depth of 1-1/2 inches and water with a fine spray.

F. Place lime, fertilizer, seed and mulch with in 72 hours of topsoil placement.

3.4 FERTILIZER AND LIME

A. Determine pH of soils in accordance with ASTM D 4972, Method B. Apply fertilizer and lime at planting in accordance with the soil analysis recommendations.

B. Apply fertilizer and lime at the following rates at time of planting when soil analysis recommendations are not available:

1. 10-10-10 fertilizer or equal at a maximum rate of 1000 pounds per acre when the fertilizer is worked into the soil and lime at 1.5 tons per acre.

2. 10-10-10 fertilizer or equal at a maximum rate of 500 pounds per acre at time of seeding and 500 pounds per acres after the seed has germinated when the fertilizer is not worked into the soil and lime at 1.5 tons per acre.

C. Place soil nutrients in direct contact with the soil. Adjust the soil nutrient equipment to ensure the applications are within 10 percent of the specified rates. Do not clean soil nutrient equipment within an environmentally sensitive area.

3.5 MECHANICAL SEEDING

A. Apply seed as shown on the Contract Drawings. Additionally, apply seed on areas disturbed during construction.

B. Apply seed at the rates noted in Articles 2.2 and/or 2.3 using a mechanical spreader.

C. Place straw mulch at a rate of 4000 pounds per acre within 24 hours after seed placement. Straw mulch should be anchored 3 inches into soil with special implement or a farm disc set straight.

D. Wet thoroughly.

E. Maintain the area in a moist condition after seeding is complete until final acceptance of permanent controls. Use fine spray techniques for watering to avoid soil erosion.

Page 115: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 7 of 8

RP 12/14/09 Section 02900 Soil Preparation and Seeding

3.6 HYDROSEEDING

A. Hydroseed disturbed areas after placement of topsoil.

B. Use a slurry application rate of 2500 gal/acre.

C. Slurry Mix

1. 1200 pounds per acre hydromulch.

2. Organic tackifier or chemical mulch binder (rate per manufacturer’s recommendations).

3. 500 pounds per acre fertilizer.

4. Seed mix as specified in Articles 2.2 and/or 2.3.

D. Use a follow-up application of fertilizer at a rate of 500 pounds per acre of fertilizer after germination of the seedlings.

E. Maintain the area in a moist condition after seeding is complete until final acceptance of permanent controls. Use fine spray techniques for watering to avoid soil erosion.

3.7 EROSION CONTROL MATTING

A. After seeding, install erosion control matting in accordance with the manufacturer’s instructions for the anchor trench at the top of slope, lap splices, and staple patterns.

B. Install staple checks horizontally along slopes exceeding 2:1 in grade, one row to be located one-third of the distance below the top of slope.

C. Each staple check consists of two rows of staples spaced 4 inches apart, with the horizontal spacing in each row being also 4 inches between staples. Stagger the rows.

3.8 SODDING

A. Install sod in accordance with the guidelines indicated below. Use the manufacturer’s recommendation when they exceed the guidelines indicated below.

B. Place centipede or bermuda sod in all channels/swales, and on backfill areas with slope greater than 4H:1V.

C. Prepare soil before installing sod, including application of lime, fertilizer, and other corrective agents to adjust the soil pH as required. Soak area to be sodded prior to placing sod.

D. Stagger joints in each row in a brick laying fashion. Avoid gaps and overlaps.

E. Avoid placing small trimmed pieces along the edge as they will not retain moisture. Avoid repeated walking or kneeling on the sodded area while it’s being installed or after watering.

F. Butt or push edges and ends against each other tightly, without stretching. Don’t drag sod into place as this damages exposed roots and promotes separation of soil and roots.

G. Roll the sod in the entire area immediately after it has been transplanted using a lawn roller one third full of water or other SRR accepted methods to improve sod to soil contact and to remove air pockets. Roll perpendicular to the direction of the sod was laid.

Page 116: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 8 of 8

RP 12/14/09 Section 02900 Soil Preparation and Seeding

H. Do not install sod if ground is frozen or when the ambient temperature is 32 degrees and falling. Apply seed in accordance with the requirements of this Section.

I. Installation on Slopes and in Channels/Swales

1. Prior to sod placement proof roll topsoil on side slopes and channels/swales. Begin at the top of the slope. Extend a minimum of 5 feet beyond the top of the slope. Install strips of sod with their longest dimension perpendicular to the slope or flow direction in the drainage channels/swales.

2. Place sod over the compacted trench and down the slope.

3. On slopes 4 to 1 or steeper, anchor sod with wire staples in a 2-foot by 2-foot pattern across the entire slope. Stagger placement of staples across the slope. Place a second row 4 inches down slope of the first row in a staggered pattern.

4. Staple bottom end on a 4-inch spacing. Staple sod between edges on a 2-foot by 2-foot pattern. Maintain sod to soil contact over entire area.

5. In channels, begin at top of the channel (direction of flow). Anchor sod with wire staples in a 2-foot by 2-foot pattern. Ensure sod to soil contact is maintained.

6. Install a staple check slot (line) at intervals of 30 to 40 feet. The staple check slot shall extend the entire width of the channel. Staple check slots are installed by placing a row of staples 4 inches apart across the entire channel and then placing a second row 4 inches down stream of the first row in a staggered pattern.

J. Water newly transplanted sod immediately to wet the soil below to a 3 inch depth to enhance rooting. Water the sod daily for a continuous one hour (excluding rain days) during maintenance and establishment period to allow the sod roots to mature. Minimal watering rate shall be ½-inch of water over the entire sodded area each day. If sodded area does not meet acceptance criteria per Article 1.9 and Subcontractor is unable to transfer the site maintenance and custodianship to SRR at the end of the four (4) weeks after sod placement, Subcontractor shall continue watering on alternate days at the same rate until the site responsibility is transferred to SRR.

3.9 CLEANING

A. Do not leave any waste, debris, or other surplus material upon completion of this construction activity. Restore any areas inadvertently disturbed to their original condition.

END OF SECTION

Page 117: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

CAST-IN-PLACE CONCRETE

SECTION 03300

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Cast-in-place concrete

B. Shotcrete

C. Form Work

D. Controlled Low Strength Material (CLSM)

1.2 RELATED SECTIONS

A. Division 1 - All Sections

B. Section 02310, Excavation and Foundation Preparation

C. Section 02320, Backfill and Finish Surface

D. Section 02378, High Density Polyethylene Liner

E. Section 02379, Geosynthetic Clay Liner

F. Section 13210, Storage Tanks

1.3 REFERENCES

A. National Codes / Standards:

1. Obtain SRR prior acceptance for other editions and/or addenda of National Codes / Standards required by this specification before use.

B. Required National Codes / Standards

1. American Concrete Institute (ACI) a. 117, 2006, Specifications for Tolerances for Concrete Construction and

Materials and Commentary b. 211.1, 1991, Standard Practice for Selecting Proportions for Normal,

Heavyweight, and Mass Concrete c. 229R, 1999 (R 2005), Controlled Low-Strength Materials d. 301, 2005, Specifications for Structural Concrete e. 305R, 1/1/1999, Hot Weather Concreting f. 306R, 1/1/1988, Cold Weather Concreting g. 318, 2008, Building Code Requirements for Structural Concrete (ACI 318-08)

and Commentary

2. American Society for Testing and Materials (ASTM) a. C 31/C 31M, 2009, Standard Practice for Making and Curing Concrete Test

Specimens in the Field b. C 40, 1/1/2004, Standard Test Method for Organic Impurities in Fine

Aggregates for Concrete

Page 118: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

c. C 94/C 94M, 2009, Standard Specification for Ready-Mixed Concrete d. C 117, 8/1/2004, Standard Test Method for Materials Finer than 75-µm (No.

200) Sieve in Mineral Aggregates by Washing e. C 136, 2/15/2006, Standard Test Method for Sieve Analysis of Fine and

Coarse Aggregates f. C 138/C 138M, 6/1/2009, Standard Test Method for Density (Unit Weight),

Yield, and Air Content (Gravimetric) of Concrete g. C 142, 8/10/1997, Standard Test Method for Clay Lumps and Friable

Particles in Aggregates (R2004) h. C 143/C 143M, 2009, Standard Test Method for Slump of Hydraulic-Cement

Concrete i. C 172, 6/1/2008, Standard Practice for Sampling Freshly Mixed Concrete j. C 231, REV A 2009, Standard Test Method for Air Content of Freshly Mixed

Concrete by the Pressure Method k. C 566, 1/10/1997, Standard Test Method for Total Evaporable Moisture

Content of Aggregate by Drying (R2004) l. C 685/C 685 M, 2007, Standard Specification for Concrete Made by

Volumetric Batching and Continuous Mixing m. C 1064, 1/15/2008, Standard Test Method for Temperature of Freshly Mixed

Portland Cement Concrete n. D 4832, 2002, Standard Test Method for Preparation and Testing of

Controlled Low Strength Material (CLSM) Test Cylinders o. D 5971, 2007, Standard Practice for Sampling Freshly Mixed Controlled Low-

Strength Material

3. National Ready-Mixed Concrete Association (NRMCA) a. Checklist for Certification of Ready Mixed Concrete Production Facilities,

Ninth Edition of QC Manual, Section 3

C. Regulations None

D. Documents None

E. Drawings None

1.4 QUALITY REQUIREMENTS

A. See Section 01400 – Quality Requirements

B. Perform work under this section in accordance with ACI 301 and ACI 318.

C. Provide independent testing agency for testing of concrete in accordance with Section 01450.

D. Protect GCL and HDPE Liner during mud mat placement.

Page 119: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

E. Execute a Quality Program NOTE: The Quality Program outlined below applies to concrete suppliers.

1. A documented quality program shall be planned, implemented, and maintained.

2. The establishment of the program shall include consideration of the technical aspects of the activities affecting quality.

3. The quality program shall identify the activities and items to which it applies.

4. The program shall provide control over activities affecting quality to an extent consistent with their importance.

5. The program shall include monitoring activities against acceptance criteria in a manner sufficient to provide assurance that the activities affecting quality are performed satisfactorily.

6. The program shall be established at the earliest time consistent with the schedule for accomplishing the activities.

7. The program shall provide for the planning and accomplishment of activities affecting quality under suitably controlled conditions. a. Controlled conditions include the use of appropriate equipment, suitable

environmental conditions for accomplishing the activity, and assurance that prerequisites for the given activity have been satisfied.

8. The program shall provide for any special controls, processes, test equipment, tools, and skills to attain the required quality of activities and items and for verification of that quality. Control of the design process and control of materials, in both mix design qualification and production is of special interest.

9. The organization shall establish and implement processes to detect and correct quality problems.

10. The program shall provide for indoctrination, training, and qualification as necessary of personnel performing or managing activities affecting quality to ensure that suitable proficiency is achieved and maintained.

11. Management shall regularly assess the adequacy and effective implementation of the quality assurance program.

F. Submit a copy of the Concrete Supplier’s Quality Program Manual with the Proposal.

1. Include the Concrete Supplier’s current National Ready Mixed Concrete Association (NRMCA) certification documentation with the Quality Program Manual submittal.

G. Concrete Production Facility Certification

1. Batch Process Production Facilities a. Batch process concrete production facilities shall comply with the National

Ready-Mixed Concrete Association, QC Manual, Section 3, “Certification of Ready Mixed Concrete Production Facilities” requirements.

b. Certification shall be in effect during any qualification or production of concrete at the facility.

Page 120: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

c. If a proposed facility is not certified by NRMCA, equivalent documentation that demonstrates that the batching facility and mixer units have received independent inspection within the six (6) months prior to bid submittal is acceptable.

d. Equivalent documentation includes:

i. Certification by a governmental agency, such as the US Army Corps of Engineers, Cognizant Authority of the state (not a political subdivision of a state) where production facility is located.

ii. An inspection and report performed by an independent inspection agency or laboratory and certified by a Registered Professional Engineer.

iii. Equivalent certification or inspection to have been received within the six (6) months prior to any qualification or production of concrete at the facility.

e. Submit a copy of the Supplier’s Current “NRMCA Certificate of Conformance for Concrete Production Facilities” or equivalent with the proposal.

f. Submit a copy of the complete results of the most recent NRMCA Plant Certification Inspection Check List or equivalent with the proposal for each facility proposed.

2. Volumetric Batching and Continuous Mixing Production Facilities a. Volumetrically batched and continuously mixed concrete production facilities

shall comply with ASTM C 685/C 685M requirements. b. Submit a copy of the complete results of the most recent Batching Accuracy

and Mixing Efficiency Tests in accordance with ASTM C 685/C 685M with the proposal for each facility.

H. Invoke technical and quality requirements of this Specification on sub-tier suppliers when others are contracted to provide for services, items, or parts.

1. When the use of sub-tier supplier(s) is deemed necessary, the Subcontractor is responsible to pass down those Technical and Quality requirements deemed applicable for the activities within its defined scope of work, per referenced Codes / Standards / Material Specifications, etc., identified within this Specification and its associated Purchase Order/Subcontract package, including specifications and/or drawings. The flow down of requirements encompasses verification that the sub-tier supplier has been appropriately qualified for performance of activities complying with this procurement. The Subcontractor shall maintain objective evidence of the successful flow down and provide such evidence to SRR upon request.

I. SRR reserves the right to review aspects of inspection, examination and testing activities to the extent necessary to ensure compliance to Specification and code requirements.

1. This review includes the right of access to the Subcontractor’s facilities, including sub-tier suppliers, vendors, and subcontractors, for the purpose of review, audit, surveillance, and witnessing of inspection, examination, and testing activities.

1.5 NOTIFICATION AND COORDINATION

A. Notify the SRR STR 48 hours prior to placement of concrete or CLSM.

Page 121: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 5 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

1.6 SUBMITTALS

A. Submit the following Engineering documents in accordance with Section 01330:

1. Concrete Supplier’s Quality Program Manual, with proposal, 1.4 F.

2. NRMCA Certificate of Conformance for Concrete Production Facilities, with proposal, 1.4 G.1.e.

3. NRMCA Plant Certification Inspection Check List, with proposal, 1.4 G.1.f.

4. Batching Accuracy and Mixing Efficiency Tests, with proposal, 1.4 G.2.b.

5. Concrete, Shotcrete, and CLSM Information, 4 Weeks Prior to Use, 1.7 F.

6. Proposed Construction Joint Plan, 2 Weeks Prior to Placement, 3.3 A.

B. Submit the following Quality Verification documents in accordance with Sections 01330 and 01400:

1. Production Aggregate Monthly Testing Report, monthly, 3.8 A.9.

2. Test Reports for Concrete and Shotcrete, 7 Days After Test, 3.8 B.9.

3. Batch Tickets, weekly, 3.8 B.10.a.

4. Test Reports for CLSM, 7 Days After Test, 3.8 C.3.

1.7 DESIGN REQUIREMENTS

There are 4 basic mix designs required for the construction of the Disposal cells: Type V, Type II, Shotcrete, and CLSM.

A. Type V Design - A class III sulfate resistant mix utilizing Type V cement. This mix, developed by SRR, shall be obtained only from the following supplier:

Lafarge Batch Plant Facility 50 Main Street Jackson, SC 24831

1. The approved Type V mix is D5000-8-S-2-AB. Refer to Attachment 03300-A for details of the Type V Mix Design and Attachment 03300-B for Type V Dry Pack Instructions. a. The products and constituents used shall not be changed without prior SRR

acceptance.

B. Type II Design – A mix design utilizing Type II cement. This mix design shall be developed by the Subcontractor and shall meet the following requirements:

1. Prepare concrete mix designs including separate mix designs when admixtures are required for hot and cold weather concrete work.

2. Identify mix ingredients and proportions, including admixtures.

3. Design and proportion concrete mixes in accordance with ACI 211.1.

4. Include in the mix design the dry weight of cement, weight of pozzolans, saturated surface dry weights of fine and coarse aggregates, and quantity of admixtures and water per cubic yard of concrete for each concrete mix.

Page 122: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 6 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

5. Provide concrete to the following mix design criteria: a. Compressive Strength (7 day): 1400 psi b. Compressive Strength (28 day): 2000 psi

C. Shotcrete Design – This mix design shall be developed by the Subcontractor.

D. CLSM Design

1. Prepare CLSM Mix Designs including separate mix designs when admixtures are required for hot and cold weather concrete work.

2. Identify mix ingredients and proportions, including admixtures.

3. Design and proportion CLSM mixes in accordance with ACI 229R.

4. Include in the mix design the dry weight of cement, weight of pozzolans, saturated surface dry weights of fine and coarse aggregates, and quantity of admixtures and water per cubic yard of concrete for each concrete mix.

5. 28-Day Compression Strength: 30 psi minimum, 150 psi maximum

6. Density: 115 to 145 lb/ft3

E. Mix Design Identifiers

1. Mix Design Identifiers shall follow SRS format and utilize 9 to 12 characters as follows:

(EXAMPLE: D5000-8-S-2-AB) a. First five characters are for the Compressive Strength at 28 days.

i. A2000 = 2000 psi mix ii. B3000 = 3000 psi mix iii. C4000 = 4000 psi mix iv. D5000 = 5000 psi mix

b. Sixth character is for the Maximum Slump in inches (whole number). c. Seventh character is “S” indicating Mix with Slag/Silica Fume. d. Eighth character is for Aggregate Size.

i. 0 = No coarse aggregate ii. 1 = 3/8 inch iii. 2 = 3/4 inch iv. 3 = 1 1/2 inch v. 4 = Hi-Density Aggregate

e. Ninth and above characters are for Admixtures (identify all included in mix).

i. A = Air Entrained Admixture and / or Water Reducing Admixture ii. B = High Range Water Reducing Admixture iii. R = Retarder Admixture iv. S = Special Admixture

f. Utilize “X” where a digit or letter is not applicable.

F. Submit Concrete, Shotcrete, and CLSM Information, which includes:

1. Mix designs, including the Mix Design Identifier.

2. Characteristics of components.

Page 123: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 7 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

3. Concrete, Shotcrete, and structural CLSM Inspection and Testing Plan. a. Identify applicable national codes and standards that will be applied to

accomplish inspection and testing.

PART 2 PRODUCTS

2.1 CONCRETE AND CLSM

A. Provide concrete, Shotcrete, and CLSM in accordance with SRR accepted mix design.

B. Deliver concrete, Shotcrete, and CLSM in accordance with ASTM C 94/C 94M REV A.

PART 3 EXECUTION

3.1 FORMWORK

A. Earth forms are not acceptable.

B. Construct forms to correct shape and dimensions, mortar-tight, braced, and of sufficient strength to maintain shape and positions under imposed dead and live loads from construction operations.

C. Complete wedging and bracing before placing concrete.

D. Verify horizontal and vertical positions of forms. Correct misaligned or misplaced forms before placing concrete.

3.2 BATCHING REQUIREMENTS

A. Use SRR accepted mix designs.

B. Measure and batch concrete in accordance with:

1. ASTM C 94/C 94M for a batching and mixing facility.

2. ASTM C 685/C 685M for a batching and mixing facility using volumetric batching and continuous mixing (auger mixer).

C. Monitor and record the moisture content of the fine aggregates and the coarse aggregates in accordance with ASTM C 566.

D. Adjust the quantity of concrete mix water.

1. Use aggregate moistures as a determinate in adding water.

2. Do not exceed the maximum total quantity of water specified in the approved mix design.

E. Record on the batch tickets, water added to the concrete (two separate entries):

1. At the batching and mixing facility.

2. Prior to placement (do not exceed maximum water quantity in mix design).

3. Retain batch tickets from each delivery per Section 13 of ASTM C 94/C 94M or per Section 15 of ASTM C 685/C 685M.

F. Provide the concrete within the temperature range specified for the approved mix design.

1. Control the temperature of the concrete in accordance with ACI 305R for hot weather concreting and ACI 306R for cold weather concreting.

Page 124: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 8 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

2. Measure temperature at the discharge of the delivery transportation system in accordance with ASTM C 172.

3. Reject and do not use concrete if the temperature range is exceeded.

G. Any materials manually added to the mix (e.g. silica fume) shall not be added in water soluble bags. Bags shall be opened, material added, and the bags disposed of.

3.3 PLACING CONCRETE

A. Prior to the first concrete placement, submit a Proposed Construction Joint Plan, include marked-up design drawings showing proposed construction joints and locations.

1. Construction joints are not allowed in the upper mudmat, tank floor, or roof.

B. Place concrete in accordance with ACI 301 and ACI 318/318R.

C. Consolidate concrete by mechanical vibrators.

D. Maximum drop height shall not exceed 5 feet and lifts shall not exceed 18” in depth.

E. Maintain records of concrete placement. Record date, location, quantity, air temperature, and test samples taken.

F. Place concrete continuously between predetermined expansion, control, and construction joints.

3.4 CONCRETE FINISHING

A. Finish concrete surfaces in accordance with ACI 301. Mudmats shall have a floated finish in accordance with ACI 301 and meet the moderately flat requirements of ACI 117 using the straight-edged tolerance requirements. No abrupt changes in the surface finish are allowed.

3.5 CURING AND PROTECTION

A. Cure and protect in accordance with ACI 301, Section 5.3.6. NOTE: Minimization or elimination of surface cracking is a key concern during the

construction of the tanks. Plastic shrinkage cracking is usually associated with the rapid loss of moisture caused by a combination of factors that include high air and concrete temperatures, low relative humidity, and high wind velocity at the surface of the concrete. Concrete with lower amounts of bleed water, such as those containing mineral admixtures (especially silica fume) have a greater tendency to undergo plastic shrinkage cracking than concrete with a greater tendency to bleed. Because plastic shrinkage cracking is due to a differential volume change in the plastic concrete, successful control measures require a reduction in the relative volume change between the surface and other portions of the concrete. Steps can be taken to prevent rapid moisture loss due to hot weather and dry winds. These measures include the use of fog nozzles to saturate the air above the surface and the use of plastic sheeting to cover the surface between finishing operations. Windbreaks to reduce the wind velocity and sunshades to reduce the surface temperature are also helpful. It is good practice to schedule flatwork after the windbreaks have been erected. During hot, windy weather with low humidity, it is sometimes advisable to reschedule the concrete placement or to initiate concrete operations at night. Any and all precautions stated here and in ACI 301 shall be considered.

Page 125: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 9 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

B. Additional construction activities (other than concrete related repair, surfacing, curing or protection) are permitted on the concrete only after curing is complete.

1. Attachment 03300-F is included to provide representative compressive strength curves experienced on a previous vault construction activity utilizing the Type V mix identified in Article 1.7.A.

3.6 FIELD QUALITY CONTROL

A. Field inspection and testing will be performed in accordance with ACI 301 and under provisions of Section 01400 and Section 01450.

B. Maintain a record of the date, placement location, quantity, ambient temperature, and test cylinder samples taken for each concrete placement.

C. Sample structural CLSM in accordance with ASTM D 5971.

D. Prepare structural CLSM test cylinders in accordance with ASTM D 4832.

3.7 DEFECTIVE CONCRETE

A. Concrete not conforming to required lines, details, dimensions, tolerances or specified requirements is to be removed and replaced.

B. Do not patch, fill, touch-up, or repair exposed concrete except upon express direction of SRR STR for each individual area.

3.8 INSPECTION AND TESTING REQUIREMENTS

A. Production Aggregate Testing

1. Perform the following tests prior to the initial use in the production of the concrete mixes and at the testing frequency identified below for each class of fine and coarse aggregates from each production facility.

2. Aggregate Moisture Content: a. ASTM C 566 b. Frequency:

i. For batches less than 100 CY per day, one test at the beginning of each day, minimum.

ii. For batches greater than 100 CY per day, one test at the beginning of each day, and a second test (minimum) that day.

iii. Upon moisture change during the day.

3. Fine Aggregate Gradation: a. ASTM C 136 b. Frequency: Weekly

4. Materials Finer than 75µm (No. 200) Sieve for Fine Aggregate: a. ASTM C 117 b. Frequency: Monthly

5. Organic Impurities in Fine Aggregates: a. ASTM C 40 b. Frequency: Monthly

Page 126: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 10 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

6. Clay Lumps and Friable Particle in Fine Aggregates: a. ASTM C 142 b. Frequency: Monthly

7. Coarse Aggregate Gradation: a. ASTM C 136 b. Frequency: Weekly

8. Materials Finer than 75µm (No. 200) Sieve for Coarse Aggregate: a. ASTM C 117 b. Frequency: Monthly

9. Submit Production Aggregate Monthly Testing Report from each production facility.

B. Production Concrete and Shotcrete Testing

1. Retain batch tickets from each delivery truck per Section 13 of ASTM C 94/C 94M or per Section 15 of ASTM C 685/C 685M.

2. Obtain samples in accordance with ASTM C 172.

3. Sample and cast sets of concrete and shotcrete cylinders as follows: a. Type V Concrete: per Attachment 03300-C. b. Type II Concrete: per Attachment 03300-D. c. Shotcrete: per Attachment 03300-E.

4. Perform field tests on the fresh concrete and shotcrete samples for the following attributes: a. Temperature: ASTM C 1064 b. Slump or Flow Consistency: ASTM C 143/C 143M c. Air Content: ASTM C 231 d. Bulk Density or Unit Weight: ASTM C 138/C 138M e. Field tests shall be performed on the following frequency:

i. From the first three (3) cubic yards of mix delivered or discharged each day.

ii. From every one hundred (100) cubic yards, or fraction thereof, of each mix delivered in any twenty-four (24) hour period.

5. Cylinders shall be six (6) inches in diameter x twelve (12) inches long, in accordance with ASTM C 31/C 31M. a. Maintain test cylinders on-site for twenty-four (24) hours and then transport to

the laboratory for curing in accordance with ASTM C 31/C 31M b. One additional test cylinder shall be taken during cold weather concreting,

cured on the job site under the same conditions as the concrete it represents and tested.

6. Test the cylinders for Compressive Strength in accordance with ASTM C 39/C 39M as follows: a. Type V Concrete: per Attachment 03300-C.

Page 127: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007 Revision: 0

Saltstone Disposal Cells 3 and 5

Page 11 of 11

RP 12/14/09 Section 03300 Cast-In-Place Concrete

b. Type II Concrete: per Attachment 03300-D. c. Shotcrete: per Attachment 03300-E.

7. Compressive strength testing dates of the concrete and shotcrete which fall on a weekend or a holiday may be adjusted within -1 or +2 days of the corresponding test dates.

8. Prepare Test Reports for Concrete and Shotcrete in accordance with the SRR accepted Concrete and Shotcrete Inspection and Testing Plans, including the following as a minimum: a. A separate report for each batch sampled which includes the field test results,

the laboratory test results and the batch tickets.

i. For Type V Concrete: include 90 day compressive strength results test with a complete set of previous test results.

ii. For Type II Concrete and Shotcrete: include 28 day compressive strength results test with a complete set of previous test results.

9. Submit Test Reports for Concrete and Shotcrete.

10. Batch tickets shall be per ASTM C 94/C 94M or ASTM C 685/C 685M. Record any water added at the jobsite, the time of completion of discharge and the total number of drum revolutions on the ticket. a. Submit all Batch Tickets weekly.

C. CLSM Testing

1. Inspect and test CLSM in accordance with SRR accepted CLSM Inspection and Testing Plans.

2. Prepare Test Reports for CLSM in accordance with SRR accepted CLSM Inspection and Testing Plans.

3. Submit Test Reports for CLSM.

3.9 ATTACHMENTS

A. 03300-A: Type V Mix Design (1 page)

B. 03300-B: Material, Installation & Inspection Requirements for Type V Concrete Dry Packing of Bolt Holes (1 page)

C. 03300-C: Type V Concrete Compressive Strength Testing Requirements (1 page)

D. 03300-D: Type II Concrete Compressive Strength Testing Requirements (1 page)

E. 03300-E: Shotcrete Compressive Strength Testing Requirements (1 page)

F. 03300-F: Representative Compressive Strength Curves for Type V Concrete (1 page)

END OF SECTION

Page 128: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

03300 - A . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 1 of 1__

Attachment 03300-A: Type V Mix Design

RP 12/14/09 Section 03300 Cast-In-Place Concrete

Mix Design Identifier: D5000-8-S-2-AB Materials Used in Mix Mix Characteristics Cement: Lehigh – Leeds, Alabama, Type V Slump: Before HRWR 0.25” to 3” Slag: Holcim, Grade 100 Slump: After HRWR 3” to 8” Fly Ash: Southeastern Fly Ash Co., Class F Workability: Sticky Silica Flume: Force 10,000, W.R. Grace & Co. Segregation: None Sand: Foster Dixiana # 33, Clearwater Sand Plant Bleeding: None Stone: Rinker Aggregates # 67, Dogwood Quarry Air: 3% to 6% AEA: Darex II, W.R. Grace & Co. Unit Weight: 139.6 WRA: WRDA 35, W.R. Grace & Co. W/C Ratio: 0.38 Maximum HRWR: ADVA 380, W.R. Grace & Co. Concrete Temp: 50 °F to 90 °F Water: City / County Fine / Course Ratio: 35:65

Mix Quantities: Cubic Yard Batch Specific Gravity Cubic Feet Cement: 213 lbs. 3.15 1.084 Slag: 284 lbs. 2.90 1.569 Fly Ash: 163 lbs. 2.20 1.187 Silica Flume: 50 lbs. 2.20 0.364 Sand: 991 lbs. 2.63 6.039 Stone # 67: 1850 lbs. 2.64 11.230 Design air 4.5% 1.215 AEA: 3.91 ozs. WRA: 42.6 ozs. HRWRA 34.1 ozs. Water 269 lbs. 4.311 Total 27.00

Page 129: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

03300 - B . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 1 of 1__

Attachment 03300-B: Material, Installation & Inspection Requirements for Type V Concrete Dry Packing of Bolt Holes

RP 12/14/09 Section 03300 Cast-In-Place Concrete

1.0 Material

1.1 Utilize Type V Lehigh cement with cement to sand ratio of 1:2.5 (max). As an option, the Subcontractor may use Sikadur 31 Hi-Mod Gel LPL installed per manufacturer’s instructions.

1.2 No coarse aggregate shall be used. 1.3 Cement and sand shall be obtained from the Lafarge Jackson Plant and conform to the

requirements in Attachment 03300-A, Type V Mix Design, with the following exception: A. The sand used for dry packing needs to be finer than that which is in the normal mix.

Therefore the mix sand for this application shall be run through a #16 sieve prior to use in the dry pack mix. NOTE: The Subcontractor shall provide labor and storage containers (i.e. 5 gallon plastic

buckets with lids) to store type V cement and sized sand in a dry location at the jobsite until needed.

2.0 Installation

2.1 Clean the hole with air pressure and thoroughly presoak it with clean water for a minimum of 6 hours prior to dry packing.

2.2 Verify that the hole is damp and no standing water is present inside prior to dry packing. 2.3 Using water just enough to produce a mortar that will stick together, mold the mortar into a ball

by hand. The ball shall neither slump when placed on a flat surface, nor crumble due to lack of water. NOTE: The dry pack mix temperature shall be in the range of 50 to 80 °F and the receiving

surface shall be in the range of 45 to 90 °F. 2.4 Place and pack the mortar immediately after molding using a wooden stick in layers thin enough

to be fully compacted. Tamp the mortar directly and at an angle to ensure maximum compaction.

2.5 Overfill the hole slightly with the final layer, then place the flat side of a hardwood piece against the hole and strike it several times with a hammer.

2.6 Cure the surface with clean wet rags for a minimum of 72 hours or utilize curing compound. NOTE: If curing compound is utilized, removal of any residual will need to be addressed in the

surface preparation requirements for application of the internal coating. (Reference Section 13210)

3.0 Inspection

3.1 SRR Quality Control will verify material types and mix proportions, presoak, mixing, placement method, and curing meet the requirements specified above with the following frequency:

A. The first dry pack batch utilized for each tank will be verified. NOTE: The Subcontractor shall notify the STR in advance of mixing and installing the first

dry packing operation on each tank structure. HOLD POINT B. One other verification will be performed for each tank during the dry pack process on a

random batch. 3.2 Compressive strength testing is not required for dry pack.

Page 130: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

03300 - C . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 1 of 1__

Attachment 03300-C: Type V Concrete Compressive Strength Testing Requirements

RP 12/14/09 Section 03300 Cast-In-Place Concrete

Testing For Placements > 100 CY (e.g. Tank Floors and Roof)

Frequency No. Test Cyl. 14 Day 21 Day 28 Day 56 Day 90 Day Hold To SRR First Truck 7 1 1 1 1 1 1 1 At 100 CY 7 1 1 1 1 1 1 1 At 200 CY 7 1 1 1 1 1 1 1 At 300 CY 7 1 1 1 1 1 1 1 At 400 CY 7 1 1 1 1 1 1 1 At 500 CY 7 1 1 1 1 1 1 1

Totals 42 6 6 6 6 6 6 6

Testing For Placements < 100 CY (Wall Panels)

Frequency No. Test Cyl. 14 Day 21 Day 28 Day 56 Day 90 Day Hold To SRR First Truck 7 1 1 1 1 1 1 1

Intermediate Truck 7 1 1 1 1 1 1 1 Last Truck 7 1 1 1 1 1 1 1

Totals 21 3 3 3 3 3 3 3

Testing For Placements < 100 CY (Closure Strips)

Frequency No. Test Cyl. 14 Day 21 Day 28 Day 56 Day 90 Day Hold To SRR

First Truck 7 1 1 1 1 1 1 1 Totals 7 1 1 1 1 1 1 1

Testing For Placements < 100 CY (Columns / Inner Curbs)

Frequency No. Test Cyl. 14 Day 21 Day 28 Day 56 Day 90 Day Hold To SRR First Truck 7 1 1 1 1 1 1 1 Last Truck 7 1 1 1 1 1 1 1

Totals 14 2 2 2 2 2 2 2

Page 131: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

03300 - D . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 1 of 1__

Attachment 03300-D: Type II Concrete Compressive Strength Testing Requirements

RP 12/14/09 Section 03300 Cast-In-Place Concrete

Frequency No. Test Cyl. 7 Day 28 Day Hold

First Truck 3 1 1 1 At 100 CY 3 1 1 1 At Each Successive 100 CY Thereafter 3 1 1 1

Page 132: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

03300 - E . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 1 of 1__

Attachment 03300-E: Shotcrete Compressive Strength Testing Requirements

RP 12/14/09 Section 03300 Cast-In-Place Concrete

Frequency No. Test Cyl. 7 Day 28 Day Hold

Outside Core Wall 8 2 4 2 Cover Coat 8 2 4 2

Totals 16 4 8 4

Page 133: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

03300 - F . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 1 of 1__

Attachment 03300-F: Representative Compressive Strength Curves for Type V Concrete

RP 12/14/09 Section 03300 Cast-In-Place Concrete

4290

5417

6824

940

60706317

7922

1644

3524

50565237

8406

3240

5540

7182

4947

1638

6475

7848 8303

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

3 days 7 days 14 days 21 days 28 days 42 days 56 days 72 days 90 daysNUMBER OF DAYS

CO

MPR

ESSI

VE S

TREN

GTH

(psi

)

Previouly Tested (Lab Cured) Top Mudmat (46 Deg. F When Placed) Vault Floor Concrete (57 Deg.F When Placed)

Page 134: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 1 of 16

RP 12/14/09 Section 13210 Storage Tanks

STORAGE TANKS

SECTION 13210

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Four pre-stressed, concrete storage tanks (3A/3B, 5A/5B), including upper and lower mud mats.

B. Associated drain water collection system.

C. Internal coatings and external roof coatings.

1.2 RELATED SECTIONS

A. Division 1 – All Sections

B. Section 02310, Excavation and Foundation Preparation

C. Section 02320, Backfill and Finish Surface

D. Section 02370, Erosion and Sediment Control

E. Section 02378, High Density Polyethylene Liner

F. Section 02379, Geosynthetic Clay Liner

G. Section 02625, Liquid Collection Layer

H. Section 03300, Cast-In-Place Concrete

1.3 REFERENCES

A. National Codes and Standards

1. American Concrete Institute (ACI) a. 347, 2004, Guide to Formwork for Concrete b. CP-60, 2002, Craftsman Workbook for ACI Certification of Shotcrete

Nozzleman

2. American Society of Civil Engineers (ASCE) a. 7-05, 1/1/2006, Minimum Design Loads for Buildings and Other

Structures

3. American Society for Testing and Materials (ASTM) a. A 1008/A 1008M REV A, 2009, Standard Specification for Steel,

Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardenable

b. A 193 /A 193M, 2009, Standard Specification for Alloy-Steel and Stainless Steel Bolting Materials for High Temperature or High Pressure Service and Other Special Purpose Applications

c. A 194 /A 194M, 2009, Standard Specification for Carbon and Alloy Steel Nuts for Bolts for High Pressure or High Temperature Service, or Both

Page 135: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 2 of 16

RP 12/14/09 Section 13210 Storage Tanks

d. A 36/A 36M, 2008, Standard Specification for Carbon Structural Steel

e. A 563 REV A, 2007, Standard Specification for Carbons and Alloy Steel Nuts

f. A 615/A 615M, 2007, Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement

g. A 821/A 821M, 2005, Standard Specification for Steel Wire, Hard Drawn for Prestressing Concrete Tanks

h. A 992/A 992M REV A, 2006, Standard Specification for Structural Steel Shapes

i. C 109/C 109M, 2008, Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2-in. or [50-mm] Cube Specimens)

j. C 138/C 138M, 6/1/2009, Standard Test Method for Density (Unit Weight), Yield, and Air Content (Gravimetric) of Concrete - AASHTO No.: T121

k. C 143/C 143M, 2009, Standard Test Method for Slump of Hydraulic - Cement Concrete

l. C 231, REV A 2009, Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method

m. C 31/C 31M, 2009, Standard Practice for Making and Curing Concrete Test Specimens in the Field

n. C 39/C 39M, 2005 (E 2006), Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens

o. C 685/C 685 M, 2007, Standard Specification for Concrete Made by Volumetric Batching and Continuous Mixing

p. C 94/C 94M, 2009, Standard Specification for Ready-Mixed Concrete q. F 436, 2009, Standard Specification for Hardened Steel Washers r. F 439, 2009, Standard Specification for Chlorinated Poly (Vinyl

Chloride) (CPVC) Plastic Pipe Fittings, Schedule 80 s. F 441/F 441M, 2009, Standard Specification for Chlorinated

Poly(Vinyl Chloride) (CPVC) Plastic Pipe, Schedules 40 and 80

4. American Welding Society (AWS) a. D1.1/D1.1M, 2008, Structural Welding Code - Steel - 21st Edition;

Incorporated Errata 2/2009

5. American Water Works Association (AWWA) a. D110, 2004, Wire- and Strand-Wound, Circular, Prestressed

Concrete Water Tanks

6. International Code Council (ICC) a. IBC, 1/1/2006, International Building Code

B. Regulations None

Page 136: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 3 of 16

RP 12/14/09 Section 13210 Storage Tanks

C. Documents

1. WB00001K-006, Tank Calculations

D. Drawings

1. C-CG-Z-00037, Z-Area Saltstone Disposal Cells 3 & 5 Mudmat Marker Cells 3 & 5 Section And Details

2. C-CH-Z-00019, Disposal Cells 3A and 3B Drain Water Collection System, Piping Arrangement & Pipe Support

3. C-CH-Z-00020, Disposal Cells 5A and 5B Drain Water Collection System, Piping Arrangement & Pipe Support

4. P-PE-Z-00010, Savannah River Plant 200-Z Area Saltstone Disposal Site Cylindrical Disposal Cells 3A & 3B Equipment Arrangement Roof Plan & Section

5. P-PE-Z-00011, Savannah River Plant 200-Z Area Saltstone Disposal Site Cylindrical Disposal Cells 5A & 5B Equipment Arrangement Roof Plan & Section

6. WB00001K-004, Vaults 2A and 2B Tank Drawings (Sheets 1 through 15)

1.4 DEFINITIONS

A. See Section 01110

B. Previous Tank Design: previously developed design documents (drawings and calculations) identified in Articles 1.5 A.2 and 1.5 A.3 for Saltstone Vaults 2A and 2B.

1.5 DESIGN REQUIREMENTS

A. Previous Tank Design

1. Previous tank design for Saltstone Vaults 2A and 2B was generated by: a. The Crom Corporation

250 S.W. 36th Terrace Gainesville, FL, 32607 Telephone: (352) 372-3436 Fax: (352) 372-6209 www.cromcorp.com

i. Crom Job Number: 08084 ii. SRR PO Number: WB00001K

2. Previous tank design is depicted in the following Contract Drawings: a. WB00001K-004, Sheets 1 through 15

3. Previous tank design calculations associated with the tank drawings are provided in the following Contract Documents: a. WB00001K-006

4. Previous tank design was based on the requirements of AWWA D110 and was completed under the contract listed in Article 1.5.A.1.a.ii above.

Page 137: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 4 of 16

RP 12/14/09 Section 13210 Storage Tanks

B. Employ the services of the Crom Corporation to provide the design documents specific for Disposal Cells 3 and 5. While utilizing the previous tank design as extensively as possible, the design shall be reconfirmed to satisfy the following requirements:

1. Tank is required to contain the saltstone grout, without leakage, during the saltstone grout fill operation stages and after the saltstone grout has solidified. a. Tank orientation shall be in accordance with drawings P-PE-Z-00010

and P-PE-Z-00011.

2. Design Parameters a. Nominal Size: 150 feet inside diameter (fixed) by 22 feet high

(minimum inside height at top of wall) for a total capacity of 2.9 million gallons per tank.

b. Minimum Design Life:

i. Operating: 10 years with a water tight seal ii. Structural: 25 years

c. Design, construction, examination, and testing shall be in accordance with AWWA D 110.

i. The use of AWWA D110 is limited to concrete panels incorporated into the structure.

ii. Tank Floor – Cast-in-place concrete iii. Walls

1. Pre-cast concrete 2. Pre-stressed in the circumferential direction.

iv. Roof – Cast-in-place concrete d. Special Design Conditions

i. Lateral forces will be present due to the empty tank being buried to the roof line using dynamic compaction equipment.

ii. The tank will be filled with water for purposes of leak testing but not during backfill. (See Article 3.4.B.4)

1. Do not consider sloshing. 2. Do not provide drainage for the tank.

iii. Filling of the tank with liquid saltstone grout will be done with incremental lifts over a period of several months. For design purposes, each incremental lift will not exceed 12 inches. Individual lifts will undergo initial curing prior to placement of the next lift.

e. Tank top – capable of supporting 30 pounds per square foot live load and the equipment loads listed below:

Page 138: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 5 of 16

RP 12/14/09 Section 13210 Storage Tanks

Equipment Description Maximum Loading Thermowell Tree 150 lbs. Lateral; 250 lbs. Vertical Camera Port 500 lbs. Dead Load Camera Junction Box - Embed Plate 250 lbs. Dead Load Grout Fill Line Supports - Embed Plates 200 lbs Lateral; 500 lbs. Vertical Conduit Support Embeds 50 lbs. Lateral; 100 lbs. Vertical Ventilation Port 400 lbs. Dead Load Drain Water Return Line Support Embeds 50 lbs. Lateral; 100 lbs. Vertical NOTE: Refer to drawings P-PE-Z-00010 and P-PE-Z-00011 for equipment

locations.

f. Design roof interior columns and any required intermediate supports to minimize obstruction / resistance to saltstone grout flow to perimeter walls.

g. Minimum thickness of concrete components:

i. Tank Floor: 8 inches with a minimum of 3 inch cover for reinforcing steel (top / inside face).

ii. Walls: 8 inches with a minimum of 3 inch cover for reinforcing steel (inside face).

iii. Roof: 8 inches. NOTE: The surface finish of these surfaces shall be determined by the tank designer per the requirements of Section 03300, Article 3.4.A. These finishes shall be listed on the tank design drawings.

h. Design the roof assembly of each tank in accordance with drawings P-PE-Z-00010 and P-PE-Z-00011, as well as the previous tank design drawing WB00001K-004 Sheets 1 through 15, including:

i. Penetration sleeves ii. Embed plates, including supported loads iii. Penetration covers and plugs

i. To allow membrane installation at later date:

i. Provide the tank exterior surfaces with a smooth finish (sides and top).

ii. Reinforcing ribs and projections on exterior walls of the tank are not permitted.

j. Saltstone Grout Material Characteristics:

i. Weight of grout while fluid: 110 pounds per cubic foot. ii. Temperature Range during placement (based on heat of

hydration during curing): 50°F to 195°F. iii. pH: Approximately 13.7.

k. Soil Properties

i. Average groundwater table elevation is 224 to 250 feet mean sea level with seasonal fluctuation of ± 5 feet.

ii. Wet density of the backfill is 125 pounds per cubic foot.

Page 139: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 6 of 16

RP 12/14/09 Section 13210 Storage Tanks

iii. Lateral earth pressure coefficients for the backfill are: 1. Active earth pressure coefficient, Ka = 0.33 2. Passive earth pressure coefficient, Kp = 3.0 3. At-rest earth pressure coefficient, Ko = 0.5

iv. Allowable soil bearing pressure: 3500 pounds per square foot at elevation 261 feet.

v. Subgrade modulus, in pci (pounds per square inch per inch of deformation):

1. 10 to 20 for a 150 foot diameter foundation. 2. 100 to 130 for a 30 inch diameter plate.

3. Structural Requirements a. Design for seismic loads in combination with other concurrent service

and environmental loads in accordance with ICC IBC, Chapter 16, “Structural Design” and ASCE 7-05 using the following parameters:

i. SS, 0.2 sec spectral response acceleration = 0.6g ii. S1, 1.0 sec spectral response acceleration = 0.2g iii. Site Class for SRS (Seismic Design Category): D iv. Importance factor IP = 1.5 v. Service loads concurrent with seismic loads shall include

operating temperature and pressure. vi. Design to prevent damage to the structure from a seismic event.

The associated tank equipment (by others) does not need to function during or after the seismic event.

b. Design the tank for the following loading without leaks:

i. Loading combinations required by AWWA D110. 1. In addition to the settlement criteria allowed by AWWA D110,

the design shall also allow for a maximum differential settlement between the tank center and perimeter of ½ inch.

2. The differential settlement evaluation shall also include the effects at column locations and roof slab.

ii. During saltstone placement, design the tank for the full hydrostatic head of saltstone drain water with a density of 82 pounds per cubic foot.

iii. After the saltstone is solid, design foundation slab to withstand the full height of solid saltstone with a density of 113 pounds per cubic foot.

c. Construction Loads

i. Design empty tank to withstand backfill static and dynamic loads during backfilling.

ii. Design components and lifting lugs for hoisting into position. iii. Design of lifting lugs to consider post-installation surface

condition to allow for exterior liner installation.

Page 140: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 7 of 16

RP 12/14/09 Section 13210 Storage Tanks

4. Service Conditions / Environmental Conditions a. Operational Environment Conditions (i.e. while Tank is being filled):

i. Pressure: Atmospheric plus hydrostatic head ii. Temperature:

1. Minimum: 50 oF (10 oC) 2. Maximum: 195 oF (90 oC) (at the center of the tank)

iii. Relative Humidity range: 20% to 100% (Condensing) b. Ambient Outdoor Environmental Conditions

i. Temperature: 1. Minimum: 20 oF (-6 oC) 2. Maximum: 110 oF (40 oC)

ii. Relative Humidity range: 5% to 100% (Condensing)

5. One of the following coating systems shall be applied to the walls, floor of the tanks and a minimum of 1 foot up each of the roof support columns. The coating system selected shall incorporate a conductive primer to support holiday testing. a. 68 Tank Lining System (Ceilcote), consisting of:

i. 680 Primer with C-1 powder at 7-10 mils. ii. Trowel basecoat will silica filler (68 lining + S-1 powder) (40-60

mils). iii. 1 reinforcing mat/ 1 nexus veil layer (45 mils), saturated with 68

lining resin. iv. 662 Flakeline topcoat (20-25 mils). v. Total system thickness of 110-130 mils.

b. TL-45-S High Build Novolac Epoxy Tank Lining (Blome International), consisting of:

i. Surface out with 83 MP (if needed, check primer sequence with vendor).

ii. Prime with 75 (2-4 mils) – add carbon to create conductive primer.

iii. 2 coats of TL-45S with fabric embed between coats; film thickness 30-40 per coat. Use .5-.75 chopped strand mat.

c. Semstone 245AFRC (Carboline), consisting of:

i. Carboguard 510 surfacer (if needed). ii. Semstone 110 Primer (now 110/110EP) - 4-6 mils. iii. Semstone 245 basecoat (25-35 mils) - For a vertical surface, the

base coat should be mixed with Cab-O-Sil (TS 720) at a 1:1 volume ratio.

iv. Semstone Scrim Cloth (lay cloth into basecoat). v. Semstone 245 mortar at 90-100 mils. vi. Nominal system thickness: 125 mils.

d. Expresscoat HCR/Sher-Tuff Epoxy (Sherwin-Williams), consisting of:

i. Surfacer if needed (Kem Cati-Coat or equal). ii. Corobond Conductive Epoxy Primer @ 4.0-6.0 DFT. iii. Putty: Steel Seam FT910 (for repairs and transitions). iv. Base Coat: Sher-Tuff Epoxy @ 20.0-30.0 mils (80%el).

Page 141: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 8 of 16

RP 12/14/09 Section 13210 Storage Tanks

v. Laminate Coat: Cor-Cote HP Clear Resin @ 20.0-30.0 mils with 1.0 oz Chopped Strand Mat.

vi. Topcoat: ExpressCote HCR @ 20.0-30.0 mils DFT (total system = 64.0 -96.0 mils DFT).

6. A drain water collection system shall be provided as depicted in the drawings C-CH-Z-00019 and C-CH-Z-00020. a. Design output documents shall include the anchor requirements of

Attachment 13210-B. b. Anchors shall be installed and masked prior to the coating

application defined in Article 1.5 B.5.

7. Design shall include the addition of the following for steel items: a. Applicable ASTM material standards. b. Coating requirements for exposed surfaces.

8. Design shall include the addition of a system located beneath the cell and above the geosynthetic liner to sample liquids on Disposal Cell 3A as depicted on drawing C-CG-Z-00037, Section C. a. Sample removal pump will be provided by SRR. b. Sample tube and conductivity probe shall be provided and installed

by the Subcontractor. c. The collection volume shall have a nominal volume of 5 gallons. d. The collection volume shall be located in the South-West quadrant of

the tank.

C. Submit Tank Drawings:

1. General Arrangement Drawing: Includes layout and dimensions, including roof openings and embeds.

2. Structural Drawings: Provide drawings for tank structure (complete tank includes sections and details as applicable).

3. Drawings shall specify any fabrication and/or erection tolerances and any structural welds.

4. Each drawing / sheet shall be individually numbered / identified to facilitate future revisions of each individual drawing / sheet.

D. Submit Tank Structural Design Calculations:

1. Provide supporting calculations including any internal roof supports.

2. Load cases shall include: a. Dead loads, live loads, and seismic loads. b. Construction loads. c. Operating loads during the filling of tank with saltstone grout.

E. Submit Tank Erection Drawings and Installation Instructions, including:

1. Requirements from Section 03300 relative to formwork, placing, finishing, curing, protecting, and repairing concrete. NOTE: Rebar spacing as discussed in Article 3.3.F.4.d shall be reflected.

2. Sequencing, required equipment, Shotcrete application, pre-stressing, rigging, bracing, shoring, etc. for all tank activities.

Page 142: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 9 of 16

RP 12/14/09 Section 13210 Storage Tanks

3. Include instructions for removal of lifting lugs or attachment points and smoothing of surface to meet surface finish requirements.

4. Include Shop Detail Drawings for each pre-cast component including interconnections and tensioning components.

F. Submit Tank Surface Preparation, Coating Application and Testing Instructions

1. Include coating components and any special details.

2. As a minimum, address storage areas, environmental conditions, dry film thickness inspections, holiday testing, etc.

G. Drawing Requirements

1. Drawing and lettering shall be of such size and density that, after reduction to half scale, information is clearly legible.

2. Drawings, including reproducibles and prints will become the property of SRR.

3. The Reference Drawing block on each drawing shall list drawings referenced on that sheet (at a minimum).

H. Calculation Requirements

1. Calculations shall include a Table of Contents.

2. Prepare calculations in sufficient detail to ensure that allowable criteria and proper factors of safety have been followed.

3. Provide each calculation with a statement of its problem, the codes and standards governing its design, and a conclusion.

4. Evaluate accepted calculations and revise accordingly to reflect asbuilt configurations.

5. Analytical Methods and Computations – Provide a clear, step-by-step description of method of solution, numerical computations (including identification of units used), and identification of the source or derivation of all equations that are not common usage (including computer codes used). For spreadsheet computations, describe, in the body of the calculation, the equations used or reference a printout of the equations used and attach the printout to the calculation. The explanation of the calculation method and the computations themselves should be succinct yet detailed enough to permit a qualified Verifier/ Checker to perform the technical review with minimal interpretation or clarification of the facts presented. Include assumptions, as applicable, pertaining to the limitations of the calculation methodology. If engineering software is used, sufficient information shall be provided to allow an independent Verifier/ Checker to assess equations or algorithms for correctness and applicability as well as verify selected input and output values calculated in the software.

Page 143: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 10 of 16

RP 12/14/09 Section 13210 Storage Tanks

1.6 QUALITY ASSURANCE

A. See Section 01400.

1.7 NOTIFICATION AND COORDINATION

A. Coordinate with Subcontract Technical Representative for the following:

1. Water for field testing of tanks as described in Part 3.

1.8 QUALIFICATIONS

A. Shotcrete Nozzlemen

1. Shotcrete shall be applied by or under direct supervision of nozzlemen certified by the American Concrete Institute as outlined in ACI Certification Publication CP-60.

2. Submit Shotcrete Nozzlemen Certification

B. Interior Coating System Installers

1. Interior coating systems shall be installed by qualified personnel experienced in the lining of secondary containments, tanks, vaults and other specialty applications. a. Experience with the specific products involved is required in order to

minimize errors.

2. Submit Coating System Installer Qualifications

C. Design Certification of Storage Tanks

1. A Professional Engineer of the appropriate discipline registered in the State of South Carolina shall seal the drawings and calculations.

2. Subcontractor’s seal of corporate Certificate of Authorization and seal of the Professional Engineer of the appropriate discipline, signed and dated, is required to certify the information is in accordance with the requirements of this specification.

1.9 SUBMITTALS

A. Submit the following Engineering documents in accordance with Section 01330.

1. Tank Drawings, 1.5 C.

2. Tank Structural Design Calculations, 1.5 D.

3. Tank Erection Drawings and Installation Instructions, 1.5 E.

4. Tank Surface Preparation, Coating Application and Testing Instructions, 1.5 F.

5. Shotcrete Nozzlemen Certification, 1.8 A. 2.

6. Coating System Installer Qualifications, 1.8 B. 2.

7. Steel Coating System Product Data, 2.1 C. 2.

8. Tank Weld Examination Procedure, 2.2 A. 1.c.

9. Visual Tank Examination Procedure, 3.4 A. 1.h.

10. Concrete Moisture Testing Procedure, 3.4 B. 2.b.

Page 144: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 11 of 16

RP 12/14/09 Section 13210 Storage Tanks

11. Tank Water Tightness Test Procedure, 3.4 B. 4.b.

12. Tank Repair Procedure, 3.4 B. 4.c.

13. As-Built Tank Documents and Drawings, 3.4 C. 1.

B. Submit the following Quality Verification documents in accordance with Sections 01330 and 01400:

1. Certified Material Test Reports for Tank Rebar, prior to installation, 2.1 A.2.

2. Certified Material Test Reports for Pre-Stress Wire, prior to installation, 2.1 A.3.

3. Tank Weld Examination Reports, 2.2 A. 1.d.

4. Visual Tank Examination Reports, 3.4 A. 1.i.

5. Anchor Inspection Reports, 3.4 A. 2.b.

6. Anchor Test Reports, 3.4 B. 1.b.

7. Concrete Moisture Testing Report, 3.4 B. 2.c.

8. Internal Coating Test Reports, 3.4 B. 3.b.

9. Tank Water Tightness Test Report, 3.4 B. 4.d.

10. Pre-Stress Wire Measurement Reports, 3.4 B. 5.c.

1.10 DELIVERY, STORAGE AND HANDLING

A. See Section 01600.

PART 2 PRODUCTS

2.1 DESCRIPTION

A. Materials

1. Furnish all materials identified on SRR accepted Tank Drawings except for items designated “By Others”.

2. Submit Certified Material Test Reports for Tank Rebar to SRR prior to installation.

3. Submit Certified Material Test Reports for Pre-Stress Wire to SRR prior to installation.

B. Welding of Carbon Steel

1. Comply with AWS D1.1/D1.1M

C. Coating of Exposed Carbon Steel Surfaces

1. Coating: Supplier’s standard shop primer or galvanized finish. a. Surface preparation: In accordance with manufacturer instructions. b. Application: In accordance with manufacturer instructions.

2. Submit Steel Coating System Product Data a. Include manufacturer’s surface preparation and application

instructions.

Page 145: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 12 of 16

RP 12/14/09 Section 13210 Storage Tanks

D. Concrete and Shotcrete Requirements

1. Use concrete and shotcrete in accordance with: a. SRR accepted Tank Drawings. b. SRR accepted concrete and Shotcrete Information.

E. Surface Finish Requirements

1. Remove surface discontinuities 1/8 inch or greater in height from surfaces of pre-cast components which are from casting, formwork mismatches, grouting or other fabrication processes.

2. Break sharp edges and corners.

3. Formwork seam lines or metal to concrete interface discontinuities are not acceptable.

4. Burrs, weld splatter, and arc strikes are not acceptable.

2.2 INSPECTION / EXAMINATION / TESTING

A. Examinations

1. Visual Examination a. Comply with the requirements of AWS D1.1/D1.1M for structural

carbon steel. b. Visually examine 100 % of structural welds. c. Submit Tank Weld Examination Procedure. d. Submit Tank Weld Examination Reports.

2. Comply with SRR accepted Inspection and Testing Plans.

PART 3 EXECUTION

3.1 GENERAL

A. Crom Corporation Services

1. Employ the services of the Crom Corporation to provide the following during tank erection activities: a. Technical Supervision. b. As needed specialty equipment for tank fabrication/erection.

3.2 PREPARATION

A. Prior to tank erection, verify completion of the following:

1. Excavation and foundation preparation in accordance with Sections 02310 and 03300.

2. The first stage of geotextile installation in accordance with Section 02378.

3. The first stage of geosynthetic clay lining installation in accordance with Section 02379.

4. The Liquid Collection Layer installation on Cell 3A per Section 02625.

B. Comply with applicable “Field Verification” notes of SRR accepted Tank Drawings.

Page 146: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 13 of 16

RP 12/14/09 Section 13210 Storage Tanks

3.3 FABRICATION / CONSTRUCTION / INSTALLATION REQUIREMENTS

A. Fabricate pre-cast tank sections at a location within acceptable ASTM travel times for concrete delivery.

B. Fabricate and erect tanks in accordance with:

1. SRR accepted: a. Tank Drawings. b. Tank Installation Instructions. c. Tank Surface Preparation and Coating Application Instructions.

2. Drawings C-CH-Z-00019 and C-CH-Z-00020.

C. Grout Level Markings

1. Provide saltstone grout level markings on three internal tank columns at three equally spaced (≈ 120° increments) locations in each tank adjacent to the camera ports in accordance with Attachment 13210-A. a. Material selected for these markings shall be compatible with coating

selected of Article 1.5 B.5 (for the bottom 1 foot of the column).

D. Protect and maintain existing facilities and temporary structures during construction / installation activities through final acceptance. This includes:

1. Existing structures / systems.

2. Liner buried at perimeter of the mud mat.

3. Erosion control features within the work area.

4. Passive dewatering features within the excavated area.

5. Graveled access road.

6. Surveying monuments in the vicinity of tank’s site used by Subcontractor to maintain elevation and horizontal controls of his work.

E. Welding of Carbon Steel

1. Comply with AWS D1.1/D1.1M

F. Formwork

NOTE: The Formwork requirements of this Article are in addition to those of Section 03300.

1. Responsibility: Design and construction of formwork is sole responsibility of Subcontractor.

2. Design Criteria: a. Design formwork system with adequate bracing, strength, and

stability to ensure finished concrete within tolerances specified in ACI 347.

b. Provide formwork sufficiently tight to prevent leakage of mortar.

3. Coating Forms: a. Coat forms with bond breaker before placing reinforcing steel.

Page 147: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 14 of 16

RP 12/14/09 Section 13210 Storage Tanks

b. Do not allow excess form coating material to stand in puddles in forms or to come in contact with concrete against which fresh concrete is to be placed.

c. Clean reinforcing steel contaminated with bond breaker before placing concrete.

4. Embedded Items: a. Clean items to be embedded in concrete free from oil or foreign

matter capable of reducing bond of concrete to these items. b. Install inserts, anchors, sleeves, and other items specified under

other sections of these specifications. c. Close ends of conduits, piping, and sleeves embedded in concrete

with caps or plugs. d. Special attention shall be directed towards spacing of steel

reinforcement with respect to other embedded items. The requirements of ACI 117 shall be used as a guideline.

5. Waterstops: a. Install waterstops in accordance with manufacturer's instructions. b. Support and protect portion of waterstop extending beyond bulkhead

during placing of concrete and subsequent removal of forms. c. Make watertight field splices by heat-sealing. Maintain continuity of

ribs and bulbs. Allow splice to cool before stressing reinforcement. d. Repair damaged waterstops before placing concrete.

G. Removal of Forms

1. Do not remove forms until members have acquired sufficient strength to support their own weight and imposed loads safely.

H. Maintain erosion control measures in accordance with Section 02370.

I. Backfill and finish in accordance with Section 02320.

J. Install the second stage of:

1. Geotextiles in accordance with Section 02378.

2. Geosynthetic clay liner in accordance with Section 02379.

K. Apply an elastomeric coating, Duracool 1 (white) or approved equal, to the exterior roof surface of each tank. Surface preparation and coating installation shall be in accordance with manufacturers instructions.

L. Interior Coating System Installation

1. Verify moisture testing of concrete is performed prior to applying coating.

2. Apply coating in accordance with SRR accepted Tank Surface Preparation, Coating Application and Testing Instructions.

Page 148: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 15 of 16

RP 12/14/09 Section 13210 Storage Tanks

3.4 INSPECTION / EXAMINATION AND TESTING

A. Examinations

1. Visual Examination a. Comply with the requirements of AWS D1.1/D1.1M for structural

carbon steel welds.

i. Visually examine 100 % of structural welds. b. Verify dimensional configuration of tank field components are in

accordance with SRR accepted Tank Drawings. c. Visually inspect 100% of the waterstop joints. d. Verify embedded items are in proper location in accordance with

SRR accepted Tank Drawings.

i. Verify Certified Material Test Reports for Tank Rebar are on file and have been submitted to SRR prior to installation.

e. Tank Installation Examinations: Verify tank is installed in accordance with:

i. SRR accepted Tank Drawings ii. SRR accepted Tank Installation Instructions

f. Coating Examinations: verify coating was installed per design and accepted submittal requirements.

i. Provide for on-site inspections performed by the coating manufacturer’s representative to insure satisfactory results.

ii. On-site inspections shall include pre-job visit, visit during application and acceptance of completed results.

g. Drain Water Collection System Examinations

i. Verify system was installed per drawing requirements. ii. Verify system is obstruction free.

h. Submit Visual Tank Examination Procedure. i. Submit Visual Tank Examination Reports.

2. Anchor Inspections a. Comply with the requirements of 13210-B. b. Submit Anchor Inspection Reports.

B. Tests

1. Anchor Tests a. Comply with the requirements of 13210-B. b. Submit Anchor Test Reports.

2. Moisture Testing of Concrete a. Prior to coating application, moisture testing of the concrete shall be

performed. Surfaces shall be free of contaminates. b. Submit Concrete Moisture Testing Procedure. Procedure shall

address the following:

i. Moisture vapor transmission. ii. Presence of surface contaminates.

Page 149: Specification c Spp z 00007 Rev 0

C-SPP-Z-00007Revision: 0

Saltstone Disposal Cells 3 and 5

Page 16 of 16

RP 12/14/09 Section 13210 Storage Tanks

c. Submit Concrete Moisture Testing Report.

3. Internal Coating Tests a. Test internal coating in accordance with SRR accepted Tank Surface

Preparation, Coating Application and Testing Instructions. b. Submit Internal Coating Test Reports.

4. Water Tightness Tests a. On completion of a tank and prior to any specified backfill placement

at the footing or wall, perform the following to determine water tightness:

i. Preparation: Fill the tank with water to the maximum level and let it stand for at least 24 hours.

ii. Measurement: Measure the drop in liquid level over the next 72 hours to determine the liquid volume loss. Evaporation losses shall be measured or calculated and deducted from the measured loss to determine the net liquid loss (leakage). The net liquid loss for a period of 72 hours shall be zero.

iii. Damp Spots: Damp spots on the exterior wall surface or measurable leakage of water at the wall base is not permitted. Damp spots are defined as spots where moisture can be picked up on a dry hand. The source of water movement through the wall shall be located and permanently sealed in an acceptable manner. Leakage through the wall-base joint or footing shall likewise be corrected.

iv. Repairs: Make all necessary repairs if the tank fails the water tightness test or is otherwise defective.

b. Submit the Tank Water Tightness Test Procedure. c. Submit the Tank Repair Procedure. d. Submit the Tank Water Tightness Test Report.

5. Wire Pre-Stress Tests a. Verify Certified Material Test Reports for Pre-Stress Wire are on file

and have been submitted to SRR prior to installation. b. Pre-stress wire in accordance with SRR accepted Tank Drawings. c. Submit Pre-Stress Wire Measurement Reports.

C. Prepare As-Built Tank Documents and Drawings to update SRR accepted design documents and drawings which have been modified or clarified during tank erection and testing based on approved SDDRs.

1. Submit As-Built Tank Documents and Drawings.

3.5 ATTACHMENTS

A. 13210-A: Grout Level Marking Sketch (1 page)

B. 13210-B: Anchor Requirements (4 pages)

END OF SECTION

Page 150: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

13210 - A . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 1 of 1

Attachment 13210-A: Grout Level Marking Sketch

RP 12/14/09 Section 13210 Storage Tanks

5” 1’- 0” 5”

Typical Interior Column Elevation

Showing Elevation Marks Not to Scale

NOTES:

1. Paint scale on interior column using non-reflective paint (over interior coating described in Article 1.5 B.5). The background shall be white per dimensions given. Elevation numbers and lines shall be black.

2. Provide elevation numbers centered at 1 ft intervals as shown. Numbers shall be 4 inches high. Scale shall be oriented such that numbers are visible from 2 cameras. Columns selected should be as near to the tank wall as practical and should consider future visual obstructions caused by thermocouple trees and grout pouring.

3. Elevation lines shall be 1 inch thick by 1 ft long and placed at 3 inch intervals as shown.

4. XX at the 22 ft level denotes the cell number (3A, 3B, 5A, or 5B).

21

2

1

XX-22

Page 151: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

13210 - B . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 1 of 4

Attachment 13210-B: Anchor Requirements

RP 12/14/09 Section 13210 Storage Tanks

Drilling of Holes in Concrete Locations of post-installed anchors shall be as shown on the Contract Drawings. The hole diameters and depths shall be as recommended in the manufacturer’s instructions unless otherwise specified. Subcontractor shall verify depth of the member before drilling holes. The embedment depth of the post-installed anchor shall not exceed the greater of 2/3 of the concrete thickness or the concrete thickness less 4 inches. Drilling Equipment All drilling in concrete shall be accomplished utilizing carbide tipped tools and a drill stop. Drilling holes for post-installed anchors and rock bolts may be made with equipment specifically recommended by the anchor manufacturer, but with carbide tipped tools and a drill stop. The use of a diamond bit shall be permitted only when SRR has consented in writing to the cutting of the rebar or embedded construction aids. The use of a drill stop device is mandatory. Just before use, the drill stop device shall be tested by touching the drill bit to a ground source to ensure it trips. The drill stop device may be deactivated while the bit or the coring tool is in contact with a bar or embedded construction aids approved to be cut. Installation of Post-installed Anchors Post-installed anchors shall be installed in accordance with the manufacturer’s specifications, unless stated otherwise in the following sections. Anchor installers shall be trained and made fully familiar with the manufacturer’s installation procedures including additional requirements as noted in this document. Post-installed anchors shall be properly seated and expanded to achieve a good "grip" in the concrete by three to four turns of the nut, but in any case, the tightening torque shall be within the range specified by the manufacturer. The torque shall be applied with a manually operated torque wrench, or the anchor tensioned with a hydraulic tensioner, calibrated in accordance with an approved site calibration procedure. The torque wrench used shall have a range so that the tightening torque value is near the middle range of the wrench. Where no range for the torque is specified, the specified torque shall be the minimum value for the torque wrench, with a tolerance of -0%, +5%. Installation equipment shall be checked on a periodic basis, and shall include a calibration program. The tightening torque specified by the manufacturer corresponds to the minimum embedment depth and/or minimum concrete strength specified by the manufacturer. Torque values for embedment depth less than the specified minimum, or for other concrete strengths, shall be determined by the Subcontractor. Flat washers supplied with post-installed anchors shall be used in all cases except where details on the Contract Drawings specify the use of another washer under the nuts. A washer may be trimmed to clear interferences. The trimmed edge shall not be closer than 7/8 of the bolt diameter from the center of the washer.

Page 152: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

13210 - B . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 2 of 4

Attachment 13210-B: Anchor Requirements

RP 12/14/09 Section 13210 Storage Tanks

Post-installed anchors installed within 5 degrees of perpendicular to the nominal concrete surface are acceptable. Care shall be exercised to avoid bending anchors to match baseplate holes, or loosening of anchors by prying sideways after tightening. Care shall also be exercised to ensure that the cone nut of an undercut anchor does not become loose from the stud during the setting or tensioning operation. The center to center distance between two load bearing post-installed anchors shall not be less than three times the embedment depth. Unless otherwise noted on the drawings, the center to center distance between a new post-installed anchor hole and an exploratory or unused hole or an abandoned cut-off anchor shall not be less than three times the diameter of the larger hole or 1” of clear concrete between the holes, whichever is greater. Unused holes shall be grouted with non-shrink grout (refer to Section 03300, Attachment 03300-B). When exploratory or unused holes are grouted with non-shrink grout and the grout has attained the strength of the concrete, the clear distance requirement is waived. INSPECTION AND TESTING OF CONCRETE ANCHORS Visual Inspection Inspection of anchors shall be performed as specified in Table 1. All anchors shall be visually inspected and documented for correct installation. The visual inspection of drilled holes shall be in accordance with Manufacturer’s instructions. The visual inspection of post-installed anchors shall be documented according to Table 1 and the following:

• The projection shall be measured from the exposed end of the anchor to concrete surface to verify embedment depth.

• If visual inspection reveals that the installed anchor does not meet the requirements of this document, the anchor shall be relocated as permitted by this document, or shall be removed and replaced by another anchor, or referred to SRR for evaluation.

Testing of Post-installed Anchors The testing of post-installed anchors for permanent plant installation is mandatory. The following two methods of testing are acceptable for post-installed anchors. One or both may be used in a single test program. The testing of post-installed anchors may be completed prior to or after installation of the attachment/baseplate. Torque Method The installed post-installed anchors shall be tested with a manually operated calibrated torque wrench. Acceptable test torque values for anchors tested after installation shall not be less than 80% of the tightening torque as specified by the manufacturer, or project documents. Post-installed anchors may be tested at the time of installation, by utilizing the torque values specified by the manufacturer, or the project documents.

Page 153: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

13210 - B . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 3 of 4

Attachment 13210-B: Anchor Requirements

RP 12/14/09 Section 13210 Storage Tanks

Proof-Load Method The installed post-installed anchors shall be tested with a tensioner using tensioning loads specified by the manufacturer. This tensioning load corresponds to the minimum embedment depth and/or minimum strength of concrete specified by the vendor. If the actual embedment is smaller than the specified minimum, or the concrete strength is lower than the specified minimum, the tensioning load needs to be adjusted, contact SRR or the Vendor. After satisfactory installation and testing, if the attachment is removed, or the nut loosened, the threads shall be cleaned, and the nut tightened to snug tight**. The anchor then shall be re-tightened to the installation torque. If the torque is attained within ¼ turn, the anchor is acceptable. If the torque is eventually achieved with more than ¼ turn, repeat the procedure after 7 days. If at that time the installation torque is achieved within ¼ turn, the anchor is acceptable. If not, the anchor shall be replaced. ** Snug tight may be attained by a few impacts of an impact wrench or the full effort of a man using an ordinary spud wrench. Testing Frequency of Post-installed Anchors The number of test anchors shall be as per Table 1. Test anchors shall be randomly selected so that they are representative of the anchors and installation conditions in the group in which they are located. If the selected test anchors meet the torque/test load requirements, and the concrete around the anchors did not break out nor did the anchors fail, the remaining anchors in the group shall be considered satisfactory. If one of the test anchors fails, the test percentage as shown in Table 1 shall be doubled. If another one fails, all remaining anchors in the group shall be tested. The anchors that exhibit a low torque value as well as the remainder of the anchors in the connection shall be re-tightened no more than once to achieve the "torque at installation." Documentation The following information for installation and testing shall be verified: • Brand, type, diameter, identification mark of anchor • General location of anchor and group represented • Method of test or verification • Test results, accepted or rejected • Inspector’s name • Date of test • For anchors that have failed, include location of failed anchors and type of failure All repairs of expansion anchors and undercut anchors that have failed under test shall be in accordance with Manufacturer’s instructions.

Page 154: Specification c Spp z 00007 Rev 0

Attachment No. Revision No. Spec/Req’n No.

13210 - B . 0 . C-SPP-Z-00007 .

Saltstone Disposal Cells 3 and 5

Page 4 of 4

Attachment 13210-B: Anchor Requirements

RP 12/14/09 Section 13210 Storage Tanks

TABLE 1

INSPECTION OF ANCHOR INSTALLATION, TESTING OF CONCRETE ANCHORS, AND DOCUMENTATION

INSPECTION ACTIVITY APPROVED ANCHOR TYPE CONDITION OF HOLE NUMBER OF ANCHORS SIZE OF ANCHORS MIN EMBEDMENT DEPTH FULL NUT THREAD ENGAGEMENT MIN CONCRETE STRENGTH PRIOR TO INSTALLATION OF ANCHOR TIGHTENING TORQUE AFTER INSTALLATION OF ATTACHMENT SPACING EDGE DISTANCE NO REBAR CUTTING UNLESS AUTHORIZED *TORQUE OR PROOF LOAD FOR POST-INSTALLED ANCHORS (5%). DATE OF TEST INSPECTOR’S NAME DOCUMENTATION

* The group of anchors to be tested shall consist of randomly selected anchors that are representative of a homogeneous population by their design and installation conditions. When the number of test anchors is less than one, a minimum of one anchor shall be tested. If one of the test anchors fails, double the specified percentage shall be tested; if another one fails, all anchors in the population shall be tested.