Special guidelines works procurement

65
SPECIAL GUIDELINES WORKS PROCUREMENT Draft for Public Consultation – v1

Transcript of Special guidelines works procurement

SPECIAL GUIDELINES

WORKS PROCUREMENT

Draft for Public Consultation – v1

1

Contents 1. Introduction ............................................................................. 2

2. Project Definition Plan ................................................................. 4

3. Risk Management Plan ............................................................... 14

4. Procurement Plan ..................................................................... 24 Attachment 1: Short Form Procurement Plan ................................................................................... 32

Attachment 2: Contractor Solicitation and Evaluation Process ........................................................ 34

Attachment 3: Consultant Solicitation and Evaluation Process ........................................................ 42

5. Contract Management Plan .......................................................... 51

6. Project / Procurement Management Plan .......................................... 58

2

1. Introduction The following Special Guidelines for Works Procurement are provided in draft form for customisation

by entities to assist them in undertaking works procurement consistent with the objects of the Public

Procurement and Disposal of Public Property Act 2015,as amended (hereafter referred to as ‘the Act’).1

THE ABOVE INTRODUCTORY PARAGRAPH MUST BE CUSTOMISED BY THE ENTITY.

The procurement of works, with the exception of that undertaken in categories assessed as low value

and low risk in the Annual Procurement Plan of the entity, will generally require the development of a

significant procurement strategy. The best practice guidance set out in the section of this Handbook on

Development of Procurement or Disposal Strategy should be followed. All procurement transactions

in categories of works that were assessed as high value and/or high risk in the Annual Procurement Plan

are significant procurements regardless of the value or risk associated with the particular works

procurement transaction. Likewise all procurement transactions in categories of works that were

assessed as low value and low risk in the Annual Procurement Plan are low value/low risk and treated

accordingly.

Works is interpreted in the Act at Section 4 as follows: “Works includes construction and

engineering works of all kinds”.

These Special Guidelines are consistent with but do not subsume the guidance provided in the

Handbook which should be read in conjunction with the Handbook.

Works Process

Schematic 1 below outlines a typical works process flow. This process flow covers a project or

programme of construction or works.

1 Where the term ‘entity’ is used herein, the name of the entity to which these special guidelines apply should be

inserted.

3

Schematic 1 Typical works process flow

The various Plans outlined in the process flow are provided as Sections of the Special

Guidelines. In this format the Plans required are as follows:

o Project Definition Plan

o Risk Management Plan

o Procurement Plan

o Contract Management Plan

o Project Management Plan

Project Definition

Plan

•Objective

•Business Case

•Brief

Risk Management Plan

•Preliminary Risk Assessment

•Risk Identification

•Risk Assessment

•Risk Mitigation Strategies

•Risk Management Plan

•Review and Reporting

Procurement Plan

•Procurement Strategy

•Selection of Forms of Contract

•Market Research

•Consultant Solicitation and Evaluation Process

Contract Management Plan

•Management of the individual Contract or Contracts

•Time Management

•Financial Management

•Scope Management

•Governance

•Resourcing

Project/Procurement

Management Plan

•Overall Mangement of the entire Project /Procurement Activity

•Time

•Scope

•Budget

• Resourcing

•Governance

4

2. Project Definition Plan Format

1.0 Introduction

Project development within the works process flow encompasses the development of:

business cases for individual projects in the project evaluation phase; and

capital works programmes, for which allocations have been made in the Budget, in the

programme formulation phase.

Business cases form the basis for which project proposals are further developed and seek to document

the justification for the undertaking of a project usually based on the estimated cost of development and

implementation against the risks and the anticipated business benefits and savings to be gained. This

may involve undertaking pre-design studies as may be required for the preparation of project briefs.

1.1 Project Objective(s)

This section of the Plan sets out the objective(s) to be achieved. The objectives must clearly reflect the

outcomes and deliverables that would define the success of the project.

1.2 Competencies and resources required

The competencies required to undertake the project definition phase of project delivery comprise a

range of skills, including those for:

facilitation and negotiation

needs analysis

project management

project development, and

value management.

The undertaking of pre-design studies and the preparation of project briefs requires a high level of

technical and professional expertise.

1.3 Scope

This element focuses on the project definition stage of the works management process and, in particular,

on the development of a project brief. It also provides an outline of pre-design studies or, where

applicable accommodation guidelines and their context in the project definition stage.

The scope of pre-design studies required in the project definition stage will depend on the size, nature

and complexity of the project and the extent of any studies undertaken earlier.

The project brief produced as a result of the project definition process provides project managers and

design teams with detailed information that may be translated into successful construction designs.

2.0 Project definition

Project definition is the first stage of the process for implementation of works projects that have

progressed through the project initiation and development phases.

5

Resource and operational strategies should be further developed and documented in conjunction with

the development of the project brief in the project definition stage.

Activities involved in the project definition stage encompass: undertaking of pre-design studies; and,

preparation of the project brief.

There may be a need to commission pre-design studies to adequately define a project. The project brief

developed in the project definition stage details client needs and requirements and establishes the

appropriate standard for the design.

The project definition stage concludes with the completion of a project brief that provides project

managers and design teams with detailed information that may be translated into successful designs for

further development in the project delivery phase.

Business cases undertaken for works projects in the project evaluation phase of project development,

pre-design studies or, where relevant accommodation guidelines are key elements which form the basis

for development of project briefs. The context of these elements within the works process flow is

illustrated in Diagram 1. Please note that the following diagram references building construction but

may also be applicable to other forms of works.

Program

Formulation

Project

Evaluation

Project Proposals

Post-Budget Input

Pre-Budget Input

Accommodation

Guidelines

Business

Cases

Pre-Design

StudiesBuilding Projects Project

Briefs

Project

Definition

Diagram 1 - Context of business cases, pre-design studies or, where applicable accommodation

guidelines The objectives and scope of a project, as well as design and performance aspects

incorporated in a project brief, are endorsed at appropriate management levels prior to implementation

of the design and construction stage.

REQUIRES CUSTOMISATION

2.1 Pre-design studies

The scope of pre-design studies undertaken in the project definition stage will depend on the size, nature

and complexity of the project and the extent of any studies undertaken earlier at a strategic level in the

project evaluation phase. Where appropriate, some studies may be deferred to the design and

construction stage. Pre-design studies may include

6

legislative and policy requirements including:

architectural aspects including, inter alia, investigations of:

o regulatory requirements - which may have significant implications, such as:

the Planning and Facilitation of Development Act, 2014 and all accompanying

regulations and guidelines; and

the Municipal Corporations Act

the Environmental Management Act 2000

o site and location considerations - such as further assessment of impacts or development

of disaster mitigation strategies including preventative measures to safeguard or

minimize the impact on or of all new works projects with respect to local requirements

as may have been identified in the project evaluation phase;

o master planning requirements - to establish a logical framework for future

development, particularly where there are a number of existing or proposed buildings

on a site, such as a school or hospital complex or where there are particular site

constraints or requirements for mitigation of environmental or social impacts;

o general design philosophies - such as interpretation of the entity’s aspirations for the

aesthetic and image characteristics, how it relates to the public and private domains of

the community and integration of art and design;

o accommodation guidelines or entity design policies, and specific needs for particular

types of works projects.

o other aspects - such as landscape considerations, vehicular and pedestrian movement,

climatic considerations, acoustics, materials and finishes, security, construction

feasibility and staging;

civil/structural engineering aspects including, inter alia, investigations of:

o contour and detail surveys, soils (including site contamination issues) and civil

engineering services - such as water supply and sewerage (including headworks and

water quality control aspects), drainage, earthworks, reclamation and roadworks; and

o structural/structural engineering aspects including, inter alia, investigations of:

water tables, coastal erosion, landslides, reactive soils, terrain categories,

supply and suitability of materials, aggressive environments, flooding,

geological faults/ earthquake considerations, subsidence, chemically

aggressive soils, unusual loadings, such as storm surges and serviceability;

electrical engineering aspects including, inter alia, investigations of:

o supply - including local supply source options, physical proximity, technical

requirements and life cycle costs;

o distribution - identifying any major issues such as economic aspects including

possibility of central energy plant and life cycle costs;

7

o emergency and standby power - including consideration of mandatory provisions for

evacuation purposes and provisions for other installations such as computer rooms,

operating theatres, refrigeration, security and specialised communication systems; and

o general requirements - relating to lighting and power, such as application of solar

energy or other energy saving initiatives to achieve ecological sustainability,

communications, security systems, lifts and escalators and fire detection requirements;

and

mechanical engineering aspects including, inter alia, investigations of:

o internal air control - including requirements for air-conditioning, evaporative cooling

or mechanical ventilation and determination of required air conditions, air control

measures (including sound and vibration) and design and operational factors including

life cycle considerations;

o firefighting services - including requirements for fire control systems and consideration

of regulatory requirements;

o industrial services - such as steam, hot water, compressed air, vacuum systems, piped

gas, purified or treated water and special equipment; materials handling facilities -

including any pneumatic, mechanical or hydraulic systems; and

o other services - such as catering and laundry facilities.

Value Management

Value management studies may be undertaken at various points during the project. On some

projects, a value management study may have been undertaken prior to the business case being

finalised. The conduct of a value management study during pre-design studies and prior to the

preparation of a project brief may result in improved project management and implementation

outcomes by identifying innovative solutions, better options, time/cost savings and overall

enhancements.

3.0 Project brief

Development of a project brief should be based on the business case developed in the project

evaluation phase, pre-design studies undertaken in the project definition stage or earlier and,

where appropriate, accommodation guidelines. The scope of a project brief will depend on the

size, nature and complexity of the project. The following contents structure has been developed

to provide guidance on the content and requirements for project briefs.

ENTITIES ARE TO ENSURE THAT, AT A MINIMUM, THE FOLLOWING SECTIOINS ARE

INCLUDED IN A PROJECT BRIEF.

Table of contents

Introduction

Project identity

Objectives and scope of the project

Participants and related groups

Context, aims and resources

8

Project management

Legislative and policy requirements

Financial and programming aspects

Background

Occupancy and use

Design and performance requirements

Location and site

Functional performance requirements

Technical and environmental performance requirements

Economic performance requirements

Symbolic performance requirements

Introduction

The introduction provides a general outline of the nature and purpose of the project, and the

people and organisations taking part. The introduction should include:

1.1 Project identity

the project name - including the title of the project, the location and where applicable

street address;

an introduction and a description of the project (including ownership of land or

buildings); and

identification of the management structure, client and project team;

1.2 Objectives and scope of the project

the project objectives - describing in general terms the entity’s aims and requirements

identified in the project evaluation phase and as documented in an approved business

case. These aims and requirements will be explained and analysed in further detail in

later sections of the project brief;

the scope of the project - with further information on its scale and any cultural,

historical, technical and environmental requirements; and

a statement of the purpose of the project brief - with further description of how it will

be used by relevant parties in subsequent stages of the project delivery;

1.3 Participants and related groups

the participants - providing a list of all parties taking part in the project delivery,

stakeholders and a brief description of the authority, responsibility and role of each

group;

related groups - identifying other groups such as local and national government, the

Regional or Municipal Corporations as well as other groups and persons with special

interest and their consultants; and

9

a diagram - identifying each participant and stakeholder illustrating the relationships

between the parties and the lines of communication.

2.0 Context, aims and resources

This section should provide information on the context, aims and resources of the entity and

user groups. This section should include:

2.1 Project management

the overall management of the project - defining the organisational structure and

process to achieve a comprehensive understanding of the needs and aims of the entity;

and

a preliminary project delivery strategy;

2.2 Legislative and policy requirements

laws, regulations, standards, codes and policies

2.3 Financial and programming aspects

financing - including funding sources that have been identified in the business case and

capital investment plan;

the project budget - including the projected cash flow; and

key programme dates and project timelines;

2.4 Background

earlier planning for service delivery - summarising relevant aspect of the entity’s

corporate plan as well as development of service delivery and resource strategies

previously undertaken, particularly referring to identified needs for elements

incorporated in asset strategies;

pre-design studies - outlining the conclusions of other studies such as master planning,

value management studies and engineering service reports;

earlier decisions - describing the impact of any earlier government or entity decisions

on the project objectives and purpose;

consultations - providing a summary of the outcomes of consultations with client and

user groups, stakeholders and the public; and

site selection - detailing earlier studies undertaken for the selection of a location and

site;

2.5 Occupancy and use (in case of building construction)

(This information will form a link between the service delivery strategies, as previously

defined, and the design and performance requirements in the subsequent section of the project

brief.)

functional requirements - providing detailed analysis and description of individual

activities and services that need to be performed to address project requirements, as

10

defined previously in Objectives and scope of the project and in the Introduction, and

identifying the equipment required to perform these tasks;

special requirements - identifying particular aspects of activities that require special

consideration in the design; and

Priorities - identifying potential competing requirements and establishing a basis for

reconciling any issues.

3.0 Design and performance requirements

This section translates the information in the previous section into specific design and

performance requirements relating to physical aspects of the project site and, where applicable

works requirements. This information should include:

3.1 Location and site

other related works - detailing any project related work that may be required outside of

the project site boundaries and other projects that need coordination (e.g. road

upgrades, or development work on neighbouring sites); and

details of any need for emergency supply of utilities in the case of failure;

3.2 Functional performance and requirements

functional spaces required in and around the works;

minimum area requirements for each functional space;

desired groupings and their respective functional relationships;

quality objectives and standards to be incorporated in the design and works;

details of requirements relating to the site, such as physical characteristics, circulation

and access, safety, environmental, communications, security, appearance, art work and

operational aspects (including where applicable cleaning and maintenance);

the general planning and design principles - which may be established in applicable

policies such as defined in relevant accommodation guidelines; and

space data schedules - including descriptions of functions and relationships, and

planning and fit-out requirements in the case of building construction;

3.3 Technical and environmental performance requirements

health, safety and security requirements;

heating, cooling and ventilation requirements;

lighting and acoustic requirements;

plumbing and electrical requirements;

materials;

information technology requirements - detailing the assessment of strategies for IT

hardware, software, operations, networks and the impact these have on the building and

its design; and

11

equipment requirements - providing a detailed assessment of new and existing

equipment to be accommodated and used in the building. All equipment should be

identified on space data sheets (previously referred to in Functional performance

requirements in Design and performance requirements);

3.4 Economic performance requirements

economic performance - relating to the performance of the asset as an investment of

resources in its operation in delivering the entity’s services. Capital and recurrent

investments as well as investments in, where applicable human resources, equipment,

furniture etc. should be considered in identifying applicable resources; and

whole-of-life issues - providing further assessment of requirements relating to all

recurrent costs associated with asset management and maintenance for the ongoing

provision of the entity’s services. For buildings these would include costs associated

with building occupancy and operations, leasing and lease management, workplace

health and safety, maintenance planning, disposal planning and ecological sustainable

development;

3.5 Symbolic performance requirements

symbolic performance - describing the aspirations for the aesthetic and image

characteristics and how the works relate to the public and private domains of the

community.

For Civil/Structural Engineering Projects

Inception Report -This is a statement of the basis for the project and a review of any historical

supporting documentation or reports

Schedule of Client Output Requirements -The Schedule of Client Output Requirements and

functional needs that establishes the scope of the project.

Design Standards Report -This report sets out the main parameters of the proposed scheme –

for example, proposed waste water treatment standards, capacity (m2/d), road cross section

(motorway, single carriageway), junction treatment, design speed etc. It is critical that design

standards be agreed in writing before the scheme design commences in order to avoid costly

and time consuming rework.

Preliminary Report / Design Brief

The approved Preliminary Report / Design Brief in the Definitive Project Brief.

Following best practice, the Preliminary Report should address all of the project parameters in

the project definition process in some manner.

Design Brief

(Design restrictions / requirements) in the project definition process.

Constraints

The Technical Experts’ report on any constraints (known at the time) that will apply in relation

to design. During the review it may become apparent that a more detailed constraints report is

required.

12

Project Budget

The Design Team reviews and confirms the budget for all project costs.

Project Execution Plan

The approved Project Execution Plan included in the Definitive Project Brief that indicates the

overall timeframe within which the project should be delivered.

Project Programme

This document sets out the timeframe for design, procurement and construction activities. This

timeframe should be consistent with the overall timeframe as set out in the Project Execution

Plan.

Site Investigation Report

The information in this document should be based on borehole logs or trial holes that indicate

the nature of the sub-soil. It probably will not be possible (on a large site) to carry out a full

investigation for the whole site at this stage.

Preferred Route (Location) Report

This report will include a statement of the purpose and need for the project, a description of the

selected design, a discussion of the various alternative designs considered and a comparison of

all of the options which explains the benefits of the preferred solution.

Environmental Impact Statement (EIS) Screening & Scoping Report

This identifies the statutory approvals that will have to be obtained for the scheme prior to

progressing to procurement and construction.

Constraints

Where constraints require further review, it may be necessary to appoint specialist sub-

consultants in areas such as archaeology and ecology to assist the Lead Consultant in the

identification of potential constraints.

Minor Capital Works

Unless the category of works is assessed as high value and/or high risk and therefore as

involving significant procurement actions in the Annual Procurement Plan, minor works may

be managed as low value/low risk procurement activities. In this case, a short form of the brief

described in this section is used to underpin a definition of the project.

Maintenance

There are several approaches to the development of a maintenance programme for works

namely:

Emergent Repairs

The term refers to works that are not planned and emerge during the course of operation. They

are generally not predictable and require a response which is commensurate with the need to

maintain safe and secure operations.

A listing of the response times required for various circumstances is generally developed with

health, safety and security concerns requiring faster response times.

13

Condition Based

This approach is based on establishing standards of serviceability and/or condition for the

individual asset or a portfolio of assets.

Condition assessments are undertaken on a pre-determined cycle. The scope of work for the

maintenance activity is the gap between the agreed standard and the current condition.

The work programme consequently developed is commonly described as a planned

maintenance programme.

Risk Based

As an alternative to a condition based approach the development and prioritisation of a planned

maintenance could be developed based on the scope of work required to minimise risk to the

service delivery requirements of the entity. This approach has been used where funds are

limited.

Statutory Maintenance

There are a number of elements of buildings in particular that are covered by statutes and

licensing requirements. Examples such as lifts, components of building services such electrical

switch boards, machinery and air conditioning plants to name a few.

These maintenance tasks must be done to comply with the law and ensure safe amenity.

An annual maintenance programme would normally be funded under the following sub

headings: emergent, statutory and planned.

Both planned and statutory maintenance tasks require that scope of work to be developed to the

level necessary to secure value for money.

In the case of the planned maintenance programme, the scope of work would come from the

condition audits together with a technical review plan which may be included in the

maintenance manuals supplied with any equipment.

14

3. Risk Management Plan

1.0 Introduction

The Introduction outlines the process for establishing and maintaining a Risk Management Plan.

Each project categorized as significant would benefit from the development and maintenance of

a Risk Management Plan throughout the life of the Project. The reference used for the Risk

Management Plan is ISO 31000:2009, or equivalent.

For works procurement in categories defined as high value and/or high risk categories in the

Annual Procurement Plan, a Risk Management Plan should be developed and maintained

throughout the life of the project or programme cycle. In the case where categories of

consultancies have been assessed as high risk, in the Annual Procurement Plan and the

procurement of such a consultancy is part of a project life cycle, a Risk Management Plan

developed for the consultancy may be incorporated and managed within the overall Project Risk

Management Plan.

The Definition of Risk

• Risk is Defined as “ the effect of uncertainty on objectives”

• Project objectives and uncertainty in meeting those objectives give rise to risks

2.0 Uncertainty of Information

The concept of uncertainty may be listed as a number of elements or pieces of information that:

• is not available

• is available but not accessible

• is of unknown accuracy

• is invalid or unreliable

• involves factors whose relationship or interaction is not known

• is variable or subject to different interpretations

• exceeds the entity’s capacity to process

• is random or chaotic

• is conflicting or inconsistent

• involves a range of known possibilities, whether and when they could occur; or

• changes over time

15

3.0 Project Risk Management Process

Schematic 1: Risk Management Process

Plan to

Address

Risk

Risk

Register

Risk

Variables

Risk

Level

Risk Management Plan

includes risk mitigation

action and assignment of

resources to manage the

risk

Identify Issues / Risks

Collect Data

Assess both consequence

and likelihood of risk

occurring

Measure performance

Risk assessment based

on consequence and

likelihood of risk

occurring

Review Performance

Learn Lessons

Continual Improvement

Continual ImprovementContinual Improvement

Continual Improvement

A Risk Management Plan should be continually reviewed throughout the life of the project in an

iterative fashion as shown in the cycle above.

Suggested minimum review stages are

1. At completion of the Project Definition Stage prior to selection of the Procurement

Method

2. Prior to the award of the contract

3. At regular meetings during the contract management stage

4. As part of the contract review process

4.0 Risk Identification

Risks may be listed under categories as detailed below when developing a Risk or Issues

Register. A productive method for developing a Risk Management Plan may be a facilitated

workshop encompassing the key stakeholders as participants.

Considerations for a Risk Register/ Issues Register include but are not limited to:

• Supply chain issues

• Time

• Budget

• Scope

• Quality

• Stakeholders

16

• Security

• Environment

• Workplace health and safety

• Communication

5.0 Risk Analysis

Events may lead to either specific or a range of consequences (each linked to a particular

objective) of either different types or magnitudes each with its own likelihood)

The process of assessment of risk constitutes the consideration of the consequence and the

likelihood of issue or event occurring. A risk assessment is a means of making sure that the

serious project risks are managed by cost-effective control measures. The issues have been listed

in the Risk Register.

A risk analysis may be considered as outlined in the Schematic 2 below.

Assessed Risk

Consequence

Likelihood

17

5.1 Risk Assessment - CONSEQUENCES

Table 1 Assessment of the consequence of risk occurring

Consequence

level

Financial

impact

People

effects

employees ,

clients

volunteers

Reputation Service

outputs

Legal and

compliance

Management

impact

Very High 5 >$3m One or more

fatalities

National media

coverage

Entity stability in

jeopardy

Total cessation of

multiple services

for many months

Major litigation

>$3m

Investigation by

regulatory body

Restructure of

entity with loss of

many senior

managers

High 5 $1m-3m Extensive injuries

to one or more

Media coverage Disruption of

services for many

months

Major regulation

breach significant

litigation

<$3m

Possible dismissal

of CEO.

Considerable loss

of time and

diversion of

productivity by

senior

management for

over a month or so

Medium 4 $300K-

$999K

Short term

disabilities to one

or more

Local media

coverage

Total cessation of

one service for a

few months

Breach of

regulation with

possible fine and

legal costs up to

$1m

Possible dismissal

of some senior

management.

Event or

disruption that

will require

several weeks

senior

management time

Low 2 $10k-

$299K

Significant

medical treatment

<2 weeks

Media coverage

Complaint to

manager

Some service

disruptions in one

area

Minor fine or

litigation

May be managed

with careful

attention

Negligible 1 <$10k First aid or minor

medical treatment

No media

coverage

Complaint to

employee

Minimal

disruption

Minor legal issues

or breach of

regulations

Will require

several days of

management

attention

There are various methods to assist in the determination of the consequences including through:

• Experimentation

• Research of past events

• Modelling to determine the way in which consequences develop

18

• Considering both immediate consequences and those that might arise after a

certain time has elapsed

• Considering secondary consequences such as those affecting other objectives,

associated systems, activities, equipment or organisations.

5.2 Risk Assessment - LIKELIHOOD

Likelihood or Probability may be defined as

Likelihood of

consequences

occurring

= The likelihood of an

event occurring that

may generate particular

consequences

x The likelihood of the event

Methods to estimate likelihood (probability)

• Using historical data on similar events

• Numerical data for systems e.g. plant and equipment

• Structured opinion of subject matter expert (s)

19

Table 2 Assessment of the likelihood of an event occurring

Descriptor Description Indicative return

period

Indicative

probability

Almost certain V The consequence expected to

occur on annual basis

Every year or more

frequently

>0.9

Likely IV The event has occurred several

times during your career

Every three years >0.75,<0.9

Possible III The event might occur once in

your career

Every ten years >0.45,<0.75

Unlikely II The event does occur from time to

time

Every thirty years >0.25,<0.45

Very unlikely I Heard of something like that

occurring elsewhere

Every 100 years >0.05,>0.25

5.4 Risk Assessment - Risk Level

Table 3 below provides a matrix to determine the level of risk for each potential issue based on

the assessment that has been made of the associated consequence and likelihood.

Likelihood

Consequence

1

Negligible

2

Low

3

Medium

4

High

5

Very high

V Almost

Certain

Medium High Very High Very High Very High

IV Likely Medium High High Very High Very High

III Possible Low Medium Medium High Very High

II Unlikely Low Low Medium Medium High

I Very

unlikely

Low Low Low Medium High

6.0 Treatment of Risk

• May depend upon the risk attitude and risk appetite of the entity

– Risk versus reward according to the programme objectives and the external

environment

– Capacity of the entity to manage the risk

20

• Risk treatment options

– Avoidance

– Acceptance

– Transfer

– Reduction

• of consequence and/or

• likelihood

The cost benefit of the treatment of the risk should always be taken into account. In some

cases the risk treatment option may out weight the actual cost to the entity if the event occurred.

A financial break even could be calculated as

Cost of risk

treatment

= Probability of occurrence X cost of the occurrence

Tools to manage or treat risk

• In house resources

• In house systems

• Additional funding

• Consultants

• Contractors

• Roles and responsibilities

• Forms of contract and their risk profiles

• Management resources

• Physical resources

• Management and reporting

• Programme management

7.0 Risk Management Plan

The Risk Management Plan should identify

• The reasons for selection of the treatment options

• Identify who are accountable for approving the plan and those responsible for

implementing the Plan

• Proposed actions

• Resource requirements including contingencies

• Performance measures and constraints

• Reporting and monitoring requirements

• Timing and schedule

The Risk Management Plan is a living document and a regular review of the Risk Management

Plan throughout the life of the programme or project is recommended. The Plan is particularly

valuable to inform decisions on procurement/contract management and project management and

governance. High risk projects would normally entail review of the Risk Management Plan at

each monthly project review meeting.

The review would include

• Ensuring controls are efficient and effective

• Obtaining further information to improve risk assessment

21

• Analysing and learning lessons from events ( including near misses), changes, trends,

successes and failures

• Detecting changes in internal and external environments

• Identifying emerging risks

22

Table 4 Risk Management Plan

Risk Consequence Likelihood Risk level

Risk

treatment

strategy

Risk treatment

action including

resources

required

Responsible

entity

Adjusted

consequence

Adjusted

likelihood

Adjusted

risk

Supply

Time

Budget

Scope

Quality

Stakeholders

Security

Environment

Safety

Communication

Others

23

8. 0 Preliminary Risk Assessment

All procurement transactions in categories of works that were assessed as high value and/or high risk

in the Annual Procurement Plan are significant procurements regardless of the value or risk associated

with the particular works procurement transaction. However, a Preliminary Risk Assessment may be of

benefit to either confirm the category level risk assessment or to check that no low risk procurement

transactions in fact have a high risk associated with their procurement. Any anomalies between the

category level risk assessment as set out in the Annual Procurement Plan and the Preliminary Risk

Assessment must be drawn to the attention of the Chief Procurement Officer for their action if required.

The process of Preliminary Risk Assessment uses a short form version of Table 4 above and considers

only issues related to:

Supply

Time

Cost

Scope management

The format of a preliminary risk assessment is set out as follows.

Table 5: Preliminary Risk Assessment

Risk Consequence Likelihood Risk level

Supply

Time

Budget

Scope

24

4. Procurement Plan

Contents

1. Introduction

1. Objective

2. Scope

3. Competencies for procurement/contract selection

4. Key Definitions

2. Achieving Value for Money

3. Procurement Method Selection

1. When to select a procurement method

2. Factors that influence procurement method selection

3. Selecting the procurement method

4. Confirming the procurement method

4. Market Analysis

5. Contract Selection

1. Minor Works and Maintenance

2. Significant Projects

6. Use of non-price criteria

Attachment 1 Short Form Procurement Plan

Attachment 2 Contractor Solicitation and Evaluation Process

Attachment 3 Consultant Solicitation and Evaluation Process

25

1.0 Introduction

This Plan is developed based on the guidance provided in the Handbook on Procurement and Disposal

Strategy Development.

1.1 Objective

The objective of this guideline is to facilitate consistency in, and provide guidance to entities regarding,

selection of the most appropriate procurement methods and contracts for works projects.

1.2 Competencies for procurement method/contract selection

The selection of appropriate procurement methods and contracts requires knowledge of:

the key objectives of, and constraints on, the construction project

the risks (both typical and specific) that might impact upon or be encountered at each stage in the

delivery of the project, and how best to deal with those risks

the level of complexity of the project

the key processes and activities that must be performed in delivering the project

the nature and operation of the relevant supply market

the available procurement methods and contracts

1.3 Scope

This guideline provides an overview of the procurement methods and contracts that may be used on

works projects and guidance as to their application. It emphasises the need for early selection of the

procurement method and for flexibility after the selection has been made. The guideline also explains

why these aspects are critical to securing planned project outcomes.

1.4 Key definitions

Before selecting procurement methods and contracts for works projects, it is important to understand

the difference between these terms. In the context of this guideline:

‘procurement strategy' refers to the process used to take a project from its early planning

phases to completion – please see and follow the best practice guidance in the Handbook for

guidance on the Development of a Procurement or Disposal Strategy.

‘consultancy contract' means the written agreement between either the entity and a consultant

or the construction contractor and a consultant, for the delivery of consultancy services (such

as design, documentation, cost planning and project scheduling) related to a project

‘contract' means the written agreement between the entity and the contractor for the

construction of the project. The terms of the agreement may provide for the design and

documentation of the project by the contractor, and may also include ongoing maintenance

obligations.

2.0 Achieving value for money

The procurement method and contract selection for works projects is required, among other things, to

achieve value for money.

Achieving value for money typically involves comparing alternatives for the supply of goods and

services to get the best mix of quality and effectiveness for the lowest cost over the required term.

26

Importantly, it involves an appropriate allocation of risk, making the selection of a suitable procurement

method and contract a critical factor in determining whether value for money is achieved.

Assessing value for money involves more than a consideration of price alone. Other factors to be

considered include:

compliance with relevant policy requirements

achieving the objects of the Public Procurement and Disposal of Public Property Act, 2015 and

its associated amendments

cost-related factors such as whole-of-life and transaction costs

non-cost related factors such as fitness for purpose, and the quality, service and support offered

by the tenderers

Sustainability requirements and/or targets.

In terms of procurement, there are a number of factors that typically contribute to value-for-money

outcomes, including:

optimising risk allocation between the parties

using performance specifications, where appropriate, to encourage maximum innovation

ensuring flexibility to secure scope changes at a reasonable cost

using incentives to reward ‘better than business as usual' outcomes

setting an appropriate contract period

ensuring participants have the required skills and capabilities to deliver the planned project

outcomes

adopting a procurement method appropriate to the complexity of the project.

The impact of these factors on the achievement of value for money will depend upon the nature and

specific circumstances of each works project. Entities should pursue factors that may best achieve value

for money and ensure integrity and accountability.

3.0 Procurement method selection

3.1 When to select a procurement method

As a project moves through the phases, knowledge of the project increases. During the project

development phase (i.e. project evaluation and programme formulation), decisions should be made

about the type of asset that is required, when it is needed, and what funds might be available to undertake

the works. This is the ideal time to consider the procurement method or methods that might be best

suited to deliver the required project outcomes.

By the time the project reaches the project delivery phase, project knowledge will be at a level where a

preferred procurement method may be readily identified subject to analyzing the nature and operation

of the relevant supply market.

3.2 Factors that influence procurement method selection

Before selecting the procurement method for a works project, whether at a strategic or detailed level, it

is necessary to first identify the factors which will determine the most suitable procurement method for

the project. These factors are:

27

the key objectives and constraints of the project

the risks that may arise during the delivery of the project and how those risks might best be

dealt with

the level of complexity of the project.

the nature and operation of the relevant supply market.

These factors are considered in developing the procurement strategy and the guidance provided in the

Handbook is to be followed in analysing these factors as a basis for framing the procurement strategy.

The following subsections provide some further details on the factors influencing works procurement

method selection.

3.2.1 Key objectives and constraints

The key objectives of each project will be identified during the project definition stage of the works

management process, as a precursor to procurement method selection. The objectives generally relate

to:

scope (i.e. what is to be delivered) together with any required provision for flexibility in this

regard

cost, including whole-of-life and transaction costs

time, including an appropriate allowance for the contract period

quality, including fitness for purpose considerations

sustainability, including social, economic and environmental aspects

innovation, encouraged through the use of performance, rather than prescriptive, specifications

community or stakeholder needs and expectations

achieving the objects of the Public Procurement and Disposal of Public Property Act 2015 and its

associated amendments

‘better than business as usual' outcomes, encouraged through performance incentives.

Constraints are aspects of the project that limit, restrict or otherwise impact upon the project objectives

in some manner. Constraints are typically unique to each project and may include:

time constraints

budget constraints

physical constraints

availability of resources, including labour resources

skills, capability and capacity of the project participants to deliver the planned project outcomes

supply market conditions

policy requirements.

28

The objectives and constraints of each project are frequently interdependent, and will therefore need to

be considered concurrently. This approach will highlight the objectives and constraints that critically

impact upon the planned delivery of the project and facilitate the selection of the most suitable

procurement method. In some cases, however, it will be clear that one objective or constraint takes

precedence over all others due to its critical impact upon project outcomes. This critical objective or

constraint should then be used to determine the most suitable procurement method for the project.

3.2.2 Risks

The second factor that may influence selection of a procurement method is the risk associated with the

works project. In the context of this guideline, risks are events, both known and unforeseen, that might

occur during the delivery of a construction project and which will usually adversely affect the project

outcomes.

The nature of the risks to the project, and their impact on project outcomes if they occur, are often

determined by the key objectives and constraints of the project. For example, if a project has a

particularly tight timeframe for completion, delays to the works will be a risk to securing the timely

completion of the project. Once the key objectives and constraints of the project have been defined, the

risks may also be identified.

Responsibility for managing or mitigating particular risks is broadly determined by the procurement

method adopted for the project. (For example, where the procurement method is ‘design and construct',

the risk of design errors is, in general terms, passed to the contractor.) Therefore, managers should

consider and determine the most suitable method to deal with the identified risks prior to selecting a

procurement method for the particular project.

As a guiding principle, responsibility for managing a particular risk should be allocated to the party best

able to deal with that risk. Inappropriate risk allocation is likely to result in project budget overruns (as

contractors may reasonably be expected to make allowances in their tenders for the risks for which they

are responsible) and increase the likelihood of contractual disputes and litigation.

3.2.3 Level of complexity

The level of complexity of a project must be considered when selecting an appropriate procurement

method. The complexity of a project is determined by a combination of factors, including:

the size of the project

the duration of the project

the scope of the project

the number of stakeholders involved

the level of technology to be incorporated in the project

the degree of innovation required by the client

market conditions.

While contractually complex procurement methods may sometimes be required for complex projects,

the additional resources needed to administer a complex method are likely to be wasted if a simple

method may achieve the same outcomes. The inappropriate selection of a complex procurement method

may also lead to unsatisfactory project outcomes in terms of cost, as tenderers may make allowances in

their tenders for additional administration costs and the possibility of contractual disputes which might

otherwise not have arisen.

29

3.3 Selecting the procurement method

Having defined the key objectives and constraints of the construction project, identified the risks,

broadly determined the preferred risk allocation and identified the level of complexity of the project,

the procurement method may be selected.

The procurement method best suited to the project will be the one that best aligns with the key objectives

and constraints of the project, that deals most appropriately with the identified risks, and that suits the

level of complexity of the project.

4.0 Minor Works and Planned Maintenance

Minor works or maintenance may be categorised as low value/low risk in the Annual Procurement Plan.

However, opportunities to improve value for money by aggregating the procurement of these items to

achieve value for money. This is sometimes called bundling. Such aggregation would change the

product category to low risk/high value procurement activity requiring development and

implementation of a significant procurement strategy.

Where the category level strategy set out in the Annual Procurement Plan involves bundling or

aggregation, the procurement method may be to seek tenders to deliver geographically based on a firm

Priced Schedule of Rates Contract or a Contract based on the hourly rates of key trades and mark ups

for materials. These may be solicited competitively on price alone or include a component of non-price

to encompass an evaluation of service quality being offered.

Rather than have only one contractor or supplier, a panel of suitable contractors could be used. This

would be of particular advantage where one contractor is not available. A case in point is where a timely

response is required in an emergent situation.

Statutory Maintenance in most cases are procured through long term contracts usually engaging the

services of the original suppliers who are familiar with their product. They may also be specialist

maintenance contractors with the necessary skills and licenses to perform the work. These procurement

actions may be categorised as high risk in the Annual Procurement Plan and therefore constitute

significant procurements. The use of good scope setting and risk management supports such

procurement together with a proper analysis of the relevant supply market. There are some instances

where the manufacturer or supplier has sole knowledge and expertise to perform the work. The use of

a sole supplier may be the preferred option. In this case, the procurement strategy needs to be clearly

documented to support such action.

5.0 Significant Projects

The following procurement and contracting methods are commonly used for significant projects:

Traditional fully documented – lump sum

The entity engages consultants to design the construction project and prepare documentation which

fully describes the work to be undertaken. The contractor then constructs the project in accordance with

the project documentation prepared by the entity’s consultants, for the agreed lump sum price. This

procurement method is best suited to projects where there is a high degree of certainty regarding the

specific project requirements.

Design and construct – lump sum

The entity engages consultants to prepare a detailed project brief which defines the scope, quality and

functionality requirements of the project. The contractor then completes the design of the project,

prepares construction documentation, and constructs the project for the agreed lump sum price. This is

30

an effective procurement method where the need to achieve defined time and cost outcomes outweighs

the need for quality.

Managing contractor – design and construction management

Typically, this is a two-stage procurement method that provides for early contractor involvement. Prior

to stage 1, the entity engages consultants to prepare a project brief, which includes a budget estimate

and estimated time for completion of the project.

During stage 1, the managing contractor works collaboratively with the design consultants and the entity

to revise the project brief and refine the design to meet budget and time constraints. Prior to stage 2, the

managing contractor makes an offer to the entity based on the revised project brief. If the offer is

accepted, stage 2 commences and the managing contractor completes the design and manages the

construction of the project. This procurement method is best suited to major or significant projects

where there is some uncertainty regarding the specific project requirements.

Alliance

This procurement method also provides for early contractor involvement. An alliance is formed between

key project participants, including the entity and contractor. All members of the alliance are collectively

responsible for all aspects of the delivery of the project. The alliance is generally structured so that

commercial risks and rewards are shared by the alliance members. It is best suited to complex, high risk

projects where alternative strategies for risk allocation will be ineffective.

Bundling

Bundling is a programme management method that involves the delivery of a number of projects (in

some cases, for a number of entities) under a single contract. Bundling may be particularly effective at

times when the market is under strain, or for the delivery of multiple projects in particular locations.

6.0 Confirming the procurement method

For some projects, certain objectives and constraints may be difficult to identify, or may be subject to

change over time. As a consequence, the identified risk management strategy (and hence the

procurement method), while previously well aligned with the key objectives and constraints, may

become unsuitable for the project. In such cases, an alternative procurement method should be selected

and implemented.

Where there is a degree of uncertainty surrounding the key objectives and constraints of the project, the

project team must remain flexible in order to rapidly address any misalignment between these objectives

and constraints and the selected procurement method. To facilitate such flexibility, it is necessary to

monitor the key objectives and constraints as the project progresses and be prepared to adjust the

procurement method accordingly.

7.0 Market Analysis

The supply market analysis undertaken in developing a procurement strategy informs the basis upon

which tenders/offers may be solicited from the market. Where there is repeated requirement for

particular categories of works, the supply market may be segmented as local, national and/or

international. In each segment there may will be companies with various levels of financial and

technical capability to undertake particular categories of works contracts and consultancies

successfully. The data associated with the local and national contractors and consultancies may be set

out in a contractor/consultant pre-qualification system. Such information is useful for analyzing the

operation of the relevant supply market for specific project or programme procurements. A centrally

held data base available to all public procuring entities would be efficient and effective as long as it is

contemporary and continually updated. The Office of Procurement Regulation will manage such a

database.

31

Where initial market analysis has indicated a low probability of securing competitive and value for

money tenders using contractors/consultant identified through a pre-qualification system, it may be

necessary to seek bid/offers internationally.

The Handbook provides more detail on analysis of supply markets applicable to procurement strategy

development.

8.0 Contract selection

Having determined an appropriate procurement method for the project, the relevant entity may select

the contractual form that is optimal in the circumstances. The optimum contract for a particular project

will:

be suitable for use with the chosen procurement method

be in alignment with the key objectives and constraints of the project

deal most appropriately with the identified risks

be suited to the level of complexity of the project.

9.0 Use of non-price criteria

Where both price and non-price criteria are to be used as the basis for a tender evaluation, the non-price

evaluation criteria and the weightings given to those criteria need to be set out in the appropriate

schedule in the conditions of tender. Offerors/tenderers will then be required to respond specifically to

the matters put to them in the non-price criteria when preparing their offers/tenders.

While the contract will allocate responsibility for certain risks and requirements to the consultant or

contractor, it is useful to understand the means by which each offeror/tenderer proposes to manage those

risks and/or meet those requirements before a consultant/contractor is selected.

Effectively drafted and appropriately weighted non-price criteria will elicit responses directly

addressing the risks that are to be managed by the consultant/contractor. In responding to the non-price

criteria, each offeror/tenderer details the commitments they will fulfil once the contract has been

awarded.

A set of effectively drafted and appropriately weighted non-price criteria may be a powerful tool that

provides the offer/tender evaluation team with the opportunity to identify which offeror/tenderer will

best deliver the planned value-for-money and project outcomes. Among other things, non-price criteria

may assist the evaluation team to identify: the particular competencies of each offeror/tenderer that are

relevant to the project; and the way in which each offeror/tenderer intends to address any nominated

entity policy requirements

32

Attachment 1: Short Form Procurement Plan

The Short Form Procurement Plan may be considered for use in works procurement transactions in the

low value/low risk category as set out in the Annual Procurement Plan. This Plan is developed based

on the guidance provided in the Handbook on Procurement and Disposal Strategy Development.

1.0 Brief and issues

Provide a brief description of the project and any information that will assist in determining the most

appropriate procurement method. Only issues considered relevant should be addressed. Information

may include detail such as:

project objectives

stakeholders

scope, including:

o the project’s various elements (e.g. new construction, refurbishment, additions,

demolition, site infrastructure, early works packages)

o a breakdown of the construction budget relative to its elements

o the proposed staging or sequencing of work

o any sketch plans/documentation

o critical activities

time considerations, including:

o key milestones or critical activities

o planning and approval timeframes

o a fixed end date versus flexible timeframes

o any time dependencies or influences from other projects

budget (and possible funding issues) including:

o most recent estimate

o allowance for escalation

o confidence level of estimate

o any cash flow forecasts

tender and evaluation process, including:

o whether open or select tenders are being used

o proposed evaluation criteria and weightings, including whether there are any non-price

criteria

constraints, including:

o supply issues (e.g. market conditions)

33

o site issues (e.g. site access)

environmental issues (e.g. vegetation protection, contamination)

cultural/heritage issues (e.g. all or part of site/building registered as culturally or historically

significant)

assumptions and givens

policy considerations

current position, including:

o the current stage of the project

o any consultancy contracts that have been let

other relevant information, including:

o the likelihood of an adequate pool of eligible tenderers

o any approved deviations from entity policy

o expectations of the entity sponsoring the project (e.g. with respect to sustainability

outcomes)

o external factors/stakeholder issues

o public sensitivities

o security

2.0 Options and analysis

Identify the procurement strategy options and analyse each of them, noting advantages and

disadvantages.

3.0 Recommendation

Recommend an option.

34

Attachment 2: Contractor Solicitation and Evaluation Process

Note: The terms ‘solicitation’ and ‘tendering’ are interchangeable in this document as are the terms

‘evaluation’ and ‘selection’.

1. Introduction

The process of contractor solicitation and evaluation is determined in the procurement strategy, the

development of which is based on the guidance provided in the Handbook on Procurement and Disposal

Strategy Development.

1.1 Objective

This guideline explains the process of selecting suitably qualified contractors to undertake works

projects.

1.2 Achieving value for money

The selection process for works contractors is required, among other things, to achieve value for money

in the expenditure of public funds. In addition to the initial cost of a service, consideration needs to be

given to the total transaction costs and to whole-of-life costs associated with the project.

However, assessing value for money involves more than a consideration of price alone. Non-cost-

related factors such as fitness for purpose, and the quality, service and support offered by the tenderers

should also be considered. Other factors to be considered in a value-for-money assessment include:

achieving the objects of the Public Procurement and Disposal of Public Property Act 2015 and

its associated amendments;

compliance with relevant entity agreements and policies; and,

sustainability requirements and/or targets.

2.0 Selection of the procurement method

The procurement method facilitates the delivery of a project outcome and generally incorporates a

contractual relationship that allocates risk between the entity and the contractor. The procurement

method determines the type of contract to be used and how that contract will be adapted and used for

the project. The risk allocation among all parties along the contractual chain must be clear, with risks

preferably allocated to the party best able to manage them.

Procurement methods available for works procurement include:

Traditional procurement methods Non-traditional procurement methods

Traditional fully documented – lump sum

Bundling (where the process involves two or

more portions being procured using only

traditional procurement methods

Design and construct – lump sum

Managing contractor – design and

construction management

Alliance

Bundling (where the process involves two

or more portions, at least one of which is

being procured using a non-traditional

procurement method)

Construction management

35

3.0. Methods of tendering

Generally the open or select methods of tendering for construction projects are used depending upon

the project requirements and the assessed service risk rating. Whichever process is used, it is important

to ensure that effective competition is achieved and that the total costs of tendering are minimised.

With either method of tendering, where applicable, a quantity surveyor’s project check estimate of the

tender documentation issued to tenderers (including any addenda) should be obtained to provide a

reasonable benchmark to assess the value for money of tenders received.

4.0 Open tendering

Open tendering involves a call for tender submissions from all eligible contractors

Open tendering is used where: there is competition among contractors, project requirements are well

defined, there is no significant construction time constraint, and where the project risks and total cost

of tendering are anticipated to be relatively low. Generally, low-risk lump sum traditional projects

should be procured under open tendering arrangements.

5.0 Select tendering

Select tendering involves the selection of a limited number of pre-qualified contractors who are invited

(in writing) to tender on a project based on the following factors:

financial capacity

management systems’ requirements

location of contractor’s office(s) relative to the location of the project

location of the project

capability for the type of work

cost, size and complexity of the project

current commitments and recent select tender opportunities on public entity projects

past performance regarding time and quality of work and, in particular, any evidence of

superior performance

Select tendering provides a balance between the total cost to the industry participants of tendering and

the advantages of having adequate competition among suppliers. However, entities need to be mindful

of the risk of supplier collusion when using a select tender process and take appropriate steps to reduce

this risk. These steps should include, among other things:

making officers involved in the tendering and evaluation process aware of the risk of collusion;

periodically reviewing the outcomes of tender processes at a project and programme level in an

effort to identify any abnormal patterns, for example, relating to the clustering of tender prices,

withdrawal of tenders or inclusion of unacceptable qualifications by tenderers;

periodically including the maximum number of tenderers rather than the minimum number on

select lists (refer to Table 1 for the recommended maximum numbers);

periodically varying the tender process by using an open tender process where a select tender

process may have been routinely used; and,

ensuring that eligible tenderers are not pressured into tendering and not penalised for failing to

tender.

Additionally, if there is reasonable cause to suspect that a contractor, or contractors may have colluded

on a specific contract, the matter must be referred immediately to the Chief Procurement Officer who

shall report the matter to the Office of Procurement Regulation.

36

6.0 Circumstances where a sole contractor may be invited to tender

The invitation of a sole contractor to tender for (and subsequently undertake) a project without a

competitive tendering process should generally be avoided owing to the perception (if not the reality)

that:

value for money may not be achieved;

the objects of the Public Procurement and Disposal of Public Property Act 2015 and its

associated amendments may be compromised; and that,

access to tendering opportunities by eligible contractors will be diminished

Clear justification for inviting a sole contractor may be set out in the procurement strategy. Such

justification for which there must be supporting evidence may include:

the contract is of a specialist or confidential nature and it is reasonable in all the

circumstances for it not to be tendered more widely;

there is only one contractor able to meet the project requirements;

there is an existing contract underway to which the new procurement is related;

a genuine urgency unrelated to poor planning exists; and/or

a structured process involving market analysis, industry consultation, and a registration and

assessment of interest process has been used to identify only one suitable tenderer.

The reasons for taking such a course of action, including specific identification of how value for money

will be achieved, should be clearly documented in the procurement strategy which must be approved in

the manner set out in the Handbook before any procurement action may be taken.

7.0 Tender framework

Table 1 provides a guide to the preferred number of tenderers and tender period (i.e. the tender

framework) for projects of varying values. The actual number of tenderers/tender period may be

individually assessed, taking into account the procurement method to be used, project time constraints

and the required level of input from tenderers.

Table 1: Preferred number of tenderers/tender period for construction projects

Procurement

method(s) Preferred number of tenderers Tender period2

Works in low risk

categories

Generally, open to all eligible contractors on the pre-

qualified list for that category of works 3 – 4 weeks

Traditional lump sum

without bill of quantities

Generally, select list of 4–6 eligible contractors on

the pre-qualified list for that category of works

4 – 6 weeks

Traditional lump sum with

bill of quantities

Generally, select list of 4–6 eligible contractors pre-

qualified list for that category of works 3 – 4 weeks

2 The tender periods shown are a guide only. If inadequate time for the calling of tenders has been allowed, this

may result in unsatisfactory project outcomes.

37

Procurement

method(s) Preferred number of tenderers Tender period2

Design and construct lump

sum

Generally, a select list of 3–5 eligible contractors on

the pre-qualified list for that category of works

4 – 10 weeks

(depending on

complexity)

Non-traditional, fee-only

managing contractor

Generally, a select list of 4-6 eligible contractors on

the pre-qualified list for that category of works 2 – 4 weeks

A bill of quantities (excluding specialist services such as mechanical services, electrical services,

security, data and communications) may be prepared for all simple construction projects (e.g. housing

units, school buildings and office buildings) over $5 million in value and for all other projects exceeding

$3 million. The provision of a bill of quantities (BOQ) may reduce the risk for tenderers associated with

incorrectly assessing the materials and quantities required for a project.

8.0 Tender documentation

The tender documents for a project underpin the contract that will be established between the entity and

the successful tenderer. The quality of these documents is a major factor in the success of the tendering

and selection process, and ultimately the project outcome. Further, poor documentation is likely to result

in increased project costs. Entities should therefore allow adequate time for the preparation of tender

documents.

All reasonable steps should be taken to ensure the tender documents are prepared by appropriately

qualified staff. Project requirements should be clearly and accurately identified to limit the need for

subsequent amendments. It is also necessary to ensure that the same information is given to all

contractors who collect tender documents.

Tender documents should include as a minimum:

the invitation to tender, stating the closing date, time and place of lodgement for

submissions;

a tender form (provided by the relevant entity) for completion by a tenderer;

conditions of tender;

any general information that will assist the tenderer to prepare the tender, including details

of a nominated contact for further information or queries;

all non-price evaluation criteria (where applicable);

details of any supporting information required from the tenderers;

full details of the work to be covered by the tender (e.g. for major traditional works projects,

this would include drawings and a specification, as a minimum, and a Bill of Quantities

where applicable); and,

general and special conditions of contract.

9.0 Invitation to tender

Whether calling for tenders by advertisement in the public domain (open tenders) or by written

invitation (select tenders), an invitation to tender must clearly state the closing date, time and a place of

lodgement for submissions. This information must also appear on the tender form. The closing date

should not fall on a Monday, an industry-recognised holiday, public holiday, or day following a public

holiday. Receipt of tender submissions should only occur as provided for in the conditions of tender

(e.g. if tender conditions require hard copy submissions, entities should not take receipt of a submission

in electronic form).

10.0 Enquiries during the tender period

38

A nominated representative of the entity should promptly handle and record any enquiries and responses

relating to tender documents for a particular project. Where it is considered necessary to provide

information to tenderers as a result of an enquiry, the information must be issued to all tenderers as soon

as possible. The nominated representative should also request that tenderers confirm receipt of this

additional information. If the information issued is expected to result in tenderers having to significantly

amend their tenders, then an extension to the tender period should be considered.

11.0 Amending tender documents during the tender period

The amendment of tender documents during the tender period should be avoided if possible. This is

best achieved by ensuring that systematic and thorough processes are used to develop and check the

documents before tenders are called.

If amendments to tender documents are required, they must be provided promptly, in the form of an

addendum, to all contractors who were issued with tender documents. The responsible

officer/nominated representative of the entity should request that all contractors:

confirm receipt of any addenda

note in their tender responses that allowance has been made in the tendered amount to cover

such addenda.

If the amendments are significant (i.e. require extensive consideration) or are issued late in the tender

period (i.e. within 5 days of tender close), extension of the tender period should be considered. An

extension to the tender period should also be handled as an addendum.

12.0 Receiving and closing of tenders

Entities should have an auditable system in place to ensure the security and confidentiality of all tenders

received prior to the closing time.

Local tender boxes should be used, where appropriate, to ensure that local industry participants are not

disadvantaged, particularly when using an open tendering process and advertising locally.

All tenders should be opened as soon as practicable following the closing time. Each tender shall be:

checked to ensure that it is complete (i.e. that all parts of the submission have been received)

marked with the date and time of receipt

Initialled and recorded as being received.

This task should be undertaken by at least three people, who should sign and date the summary of

tenders received. Although tender openings may or may not be conducted as public sessions,

information specified in the tender documents as suitable/available for public release should be

disclosed as soon as possible.

13.0 Evaluating tenders and awarding the contract

The aim of the tender evaluation process is to identify the tender that is most advantageous to the entity

and offers the best value for money which may not necessarily be the tender offering the lowest price.

In situations where a high level of accountability must be demonstrated (e.g. cases of complex tender

evaluations), the commissioning of a probity auditor may be warranted.

14.0 Tender evaluation criteria

For projects delivered using the traditional procurement method, where requirements are well defined

and documented, the ‘tender sum’ or ‘tender price’ will be the major factor taken into account when

evaluating tenders. However, non-price evaluation criteria may also be used for these projects, where

39

appropriate. In general, projects delivered using a non-traditional procurement method would include

non-price evaluation criteria.

Non-price evaluation criteria are included in the tender and selection process to support entity policy

and provide a greater level of certainty of project outcomes. For example, on a project with a non-

negotiable completion date (i.e. where time is a critical project constraint), tenderers would be required

to submit details on how they intend to resource the project and coordinate activities in order to ensure

that this critical objective is achieved.

15.0 Evaluation criteria weightings

For projects where non-price evaluation criteria form part of the conditions of tender, tender

documentation should clearly state the weighting given to each evaluation criterion (i.e. an indication

of the relative importance of each criterion, usually expressed as a percentage).

16.0 Tender evaluation panel

A tender evaluation panel is required to evaluate tenders for all projects where non-price evaluation

criteria form part of the conditions of tender. The panel should comprise at least three people, including

the following:

an officer who was involved in preparing the tender documents for the project;

an officer with a sound and current technical knowledge of the construction process capable

of fully understanding and interpreting the tenders;

an officer with sound knowledge of procurement and related policies;

Tender panellists should be aware that information received from tenderers must be treated as

commercial-in-confidence. Panellists also need to be aware of the risk of contractor collusion, be

vigilant in seeking to identify any aspects in the tenders that could be reflective of collusion

All tender evaluation panel members must act ethically and maintain high standards of integrity and

accountability, among other things, this requires that they provide a written declaration noting any

actual, perceived or potential conflicts of interest they may have in relation to their role on a tender

evaluation panel. The Chief Procurement Officer determines how such conflicts may be managed.

17.0 Evaluation of tenders

The tender evaluation process should be transparent and equitable. It is good practice to document and

randomly audit the process to verify its effectiveness. Any discrepancies between submitted tenders and

the tender documentation must be noted and resolved before a final recommendation is made regarding

tender acceptance/award.

If there is reasonable suspicion of collusion associated with the tenders, panel members should refer the

matter to the Chief Procurement Officer for action. Depending on the circumstances, this could require

the release of tenders, and (if it remains the most appropriate procurement method) the recall of tenders.

The tender evaluation process involves a:

‘technical review’ of all tenders

‘capability validation’ of all contractors submitting tenders

‘financial capacity assessment’ of the preferred tenderer.

The technical review also involves an assessment of any conditions or qualifications attached by the

tenderers to their submissions, as well as an assessment of the project’s estimated value and the value

of each tender received. Capability validation includes an assessment of the contractor’s work load over

the period of the proposed contract.

40

Notwithstanding that tenders should be called only when there is an intention to proceed with a project,

the entity may reject all of the tenders and recall tenders in accordance with the conditions of tender.

18.0 Evaluation by a panel

The evaluation process generally involves:

obtaining a written declaration from each panel member regarding any conflicts of interest they

may have in relation to their role on the tender panel so that such conflicts may be effectively

managed;

an initial meeting of the tender panel, prior to tender close, to confirm the members’

understanding of the project time-frame, evaluation criteria, criteria weightings and required

project outcomes;

a subsequent meeting of the panel to evaluate the completeness of tender information received

(i.e. that all parts of each tenderer’s submission have been received);

a meeting of the panel to finalise scoring; and,

the recommendation of a preferred tenderer (pending the outcome of the technical review and

financial capacity assessment).

If non-price criteria represent a significant proportion of the total weightings, tenderers may be invited

to make a presentation to the evaluation panel. In such cases, the purpose of these presentations should

be limited to clarifying aspects of the tenders.

19.0 Approach when a tender price is very low

Where a tender price (or a key element of a tender price) is considered well below the median price

and/or the project's estimated value, further investigations should be undertaken before selecting this

tender as the winning bid. In accordance with Section 34(1) of the Act, a request is made to the tenderer

to review their bid and/or respond to questions regarding particular aspects of the tender. The tenderer

should also be asked to provide written confirmation that the scope of work and contractual obligations

are fully understood3.

20.0 Post-tender negotiations

Post-tender negotiations may be conducted with a tenderer or tenderers in certain circumstances,

although care must be taken to ensure that integrity and accountability requirements are met. Guidance

on best practices in negotiation is provided in the Handbook.

21.0 Tender approval

Subject to a satisfactory financial assessment report on the preferred contractor, the entity will follow

the process of tender approval as set out in the Handbook including:

nominating the preferred tenderer to the relevant approving authority; and

seeking financial approval and approval to accept the tender.

Following the receipt of these approvals, the awarding of the contract may proceed subject to the

observance of any standstill period under Section 35(2) of the Act and in accordance with the process

set out in the Handbook.

22.0 Awarding the contract

3 34. (1) Where a procuring entity is of the opinion that a submission is abnormally low, it shall request, in writing

from the supplier or contractor, details of the submission that gives rise to concerns as to the ability of the supplier

or contractor to perform the procurement contract.

41

Once approval has been received from the relevant approving authority, a ‘letter of acceptance’ is issued

to the successful tenderer (a ‘purchase order’ may also be issued). At this point, the contract has been

awarded.

A number of documents typically constitute the agreement between the parties (i.e. the contract),

including:

a copy of the tender documents, including drawings and specifications and any

correspondence or addenda issued during the tender period;

the original submitted tender;

any post-tender correspondence and clarifications;

the letter of acceptance; and

where applicable, a formal Instrument of Agreement (i.e. a deed attached to

the Special Conditions of Contract that identifies the documents forming the

contract.

42

Attachment 3: Consultant Solicitation and Evaluation Process

Note: The terms ‘solicitation’ and ‘tendering’ are interchangeable in this document as are the terms

‘evaluation’ and ‘selection’.

1.0 Pre-invitation activities

The process of consultant solicitation and evaluation is determined in the procurement strategy, the

development of which is based on the guidance provided in the Handbook on Procurement and Disposal

Strategy Development.

The quality of the initial planning and documentation is critical to the selection of suitable consultants

and ensuring successful project outcomes. Prior to inviting and selecting consultants, the entity needs to

undertake specific tasks including:

preparation of comprehensive and well defined Terms of Reference, (refer to the Project

Definition Plan);

completion and approval of a procurement strategy based on the guidance and process set out

in the Handbook including:

o preparation of a commission fee estimate;

o selection of an appropriate procurement method; and,

o identification of consultants with capabilities specific to the commission requirements.

2.0 Consultant invitation

2.1 Invitation methods

Two methods are available to identify consultants who will be invited to submit proposals – select

invitations to pre-qualified consultants and expressions of interest. Both methods ultimately involve the

preparation of a shortlist of consultants but the initial approach differs.

An analysis of the detailed commission requirements provides the basis for reducing the long list of

appropriately qualified and eligible consultants to the shortlist of consultants who will be invited to

submit proposals. Factors taken into account in preparing the select list from the long list include:

the consultant’s demonstrated performance, particularly on previous; and,

the consultant’s current commitments and capacity to serve any new commitments;

The number of consultants on the select list is determined by factors such as type and value of the

commission, the risk and urgency; however it should generally not be less than three or more than five.

Notwithstanding, there are circumstances, e.g. emergent commissions or where the service is highly

specialised or unique, that an exception to this provision may be warranted, resulting in a select list of

one or two consultants. In such cases, the reason for any departure from the general provision should be

recorded.

A selection panel should determine the select invitation list of consultants. The panel should comprise at

least three people; namely, the entity officer administering the commission (i.e. a professionally qualified

person - preferably from the same or related discipline as the required consultant) and a person with a

sound knowledge of procurement.

In determining the final list, it is advisable to have identified additional consultants beyond the select list

in the event that one or more consultants is not in a position to submit a proposal. The proposed select

invitation list, and the documented method used to determine it, should then be reviewed and approved

43

by the assigned Senior Procurement Officer in the case of a low risk/low value consultancy and by the

Chief Procurement Officer in the case of a significant procurement.

Prior to finalising the list, it is good practice to contact the short-listed consultants and determine their

availability and/or interest in being invited to submit a proposal. Any decline by a consultant at that stage

will not reduce that consultant’s opportunities to be invited to submit future proposals.

2.2 Expressions of interest

Expressions of interest should only be used as an invitation method where:

special skills or a high level of innovation are required (e.g. associated with a design

competition); or

it is desirable to facilitate opportunities for consultants to work together (in particular to meet

the policy objectives associated with local industry participation).

In relation to the second bullet point, the expressions of interest process may not be necessary if there is

an adequate pool of prequalified consultants in the area where the project is located.

To achieve optimum local industry participation, advertising for expressions of interest should be limited

to the relevant local area and may include provision for consultant - sub consultant and consortia

arrangements.

The expressions of interest process involves an invitation to consultants to make submissions:

to state their ability to meet specific project requirements, either individually or by combining their

abilities; and

to be assessed as the basis for determining their inclusion or otherwise in a shortlist for invitation to

submit a consultancy proposal.

Specific activities should be undertaken in the early planning stages of the expression of interest, to

manage risk associated with the procurement of consultant services. They include:

assessment of supply market for the consultant services;

alignment of project requirements and the supply market capability; and

preparation of the expression of interest Terms of Reference.

After a decision has been made to seek expressions of interest, a Terms of Reference should be prepared.

Care needs to be taken to ensure that the effort and documentation required from consultants is

minimised. The Terms of Reference should limit the requested information to that which is essential to

assess the consultant’s capability and interest. It should not require duplication of information that has

already been provided and is available in any pre-qualification system, nor should it require information

more appropriately addressed in the subsequent stages of selection.

Whether invited by letter or public advertisement, the invitation for expressions of interest should always

explicitly state the intention of the expression of interest process, which is to identify a shortlist of

consultants for invitation to submit a proposal for ultimate selection as the consultant.

The invitation activities need to be managed to enable invited consultants to develop proposals

appropriate to the Terms of Reference and within the nominated timeframe. These activities include

preparation and distribution of documents, responding to consultant inquiries during the proposal

preparation period, and receiving and closing of proposals. For some commissions, it may also be

appropriate to schedule pre-invitation briefings with consultants on the select list.

44

2.3 Invitation documents

The invitation documents for a commission underpin the agreement between the entity and the

consultant. All reasonable steps should therefore be taken to ensure that adequate time is allowed for the

preparation of these documents and that they are clear and accurate to reduce the likelihood of subsequent

amendments.

The entity should provide an invitation package to each of the consultants on the select list. The package

should contain all information necessary to enable the consultants to prepare a concise and conforming

proposal. The same package should be given to all consultants.

As a minimum, the package should include:

• a Letter of Invitation including evaluation criteria and any applicable weightings;

• conditions of offer;

• the Terms of Reference detailing the specific service requirements and scope of the

commission;

• a copy of the General Conditions of Engagement of Consultants;

• a copy of any Special Conditions of Engagement; and

• instructions regarding the required structure and/or format of proposals.

The invitation should not require consultants to provide information that has already been provided.

Consultant responses to price and non-price criteria should always be sought in separate parts (envelopes

or electronic files depending on whether the process is paper-based or involves electronic tendering) to

allow the relative merits of each consultant’s non-price proposal to be assessed separately and before the

fee proposal is sighted. This should be made clear to consultants in the instructions relating to the format

of proposals.

2.4 Enquiries/amendments during the invitation period

The entity officer nominated to manage the commission should promptly attend to and record any

enquires and responses relating to invitation documents for a particular commission. Where it is

considered necessary to provide information to consultants as a result of an enquiry, the information

should be issued to all invited consultants as an addendum as soon as possible. Each consultant should

be requested to confirm receipt of all addenda at the time of submitting their proposal.

Amendment to invitation documents during the invitation period should be avoided. However, if

required, amendments should be provided as addenda to all invited consultants and the consultants

requested to confirm receipt of such addenda.

If the amendments are significant and require extensive consideration or are issued late in the invitation

period, an assessment should be made of the likely impact on the adequacy of the proposals sought and

whether the invitation period should be extended. If it is subsequently determined to extend the invitation

period, the extension should also be handled as an addendum.

3.0 Receiving and closing of proposals

A closing date, time, and place of lodgement should be nominated in the invitation documents. The

closing date should allow a reasonable time for the preparation of proposals and take account of addenda

that may have been issued and public holidays that fall within the proposal period.

Entities should have a documented and auditable system in place to ensure the security and

confidentiality of all proposals received prior to the closing time. When receiving paper-based proposals,

45

the use of a locked box provides assurance that proposals are appropriately secured. Where electronic

lodgement of proposals is used, processes need to be in place to ensure that the electronic files are stored

securely.

Unless an entity has an electronic tendering system, proposals should be opened as soon as practicable

following the closing time, checked, dated and signed by at least three people, their receipt recorded in

a register and acknowledged in writing. Alternatively, where an electronic tendering system is used, the

receipt of proposals will be electronically recorded and acknowledged.

4.0 Consultant Fees

While fees are an important aspect of any proposal, it is important that they are not over-emphasised

relative to the non-price evaluation criteria.

Consultants should receive a fee commensurate with the level of required service. A number of key

industry bodies produce fee guides for varying types and levels of service. These may be helpful as a

reference.

Fees should be determined in accordance with requirements specified in the invitation documents and

will usually be described in the form of a lump sum or percentage of the estimated works project cost.

It is expected that the fee will take into account such factors as specified quality requirements, required

documentation levels, known risks and contractual obligations (e.g. ownership of copyright) together

with any value-adding to be delivered by the consultant through activities such as research, option

studies, design innovations and coordination of sub consultants.

Where there is a particular need to achieve a required level of service, agencies may find it beneficial to

fix a minimum fee for commissions.

Generally, consultants cannot claim fees for the preparation of proposals. However, where the

commission is complex and is likely to involve considerable cost to the consultants in preparing their

proposals, the entity should give consideration to allowing invited consultants to claim some portion of

their costs. In such cases, these arrangements should be identified in the invitation documents.

5.0 Consultant Selection

5.1 Evaluation methods

There are two main methods for the evaluation of consultant proposals:

Value selection; and

Qualification Based Selection.

5.1.1 Value Selection

Value Selection should be the evaluation method used where the commission service requirements are

either well defined and/or of a routine nature (i.e. in the majority of cases). This evaluation method will

identify proposals that represent the best value for money, with value for money being determined using

an evaluation of consultant responses to both price and non-price criteria. This method rewards the

consultant who has the highest overall weight adjusted score for both price and non-price criteria.

Price scoring

The highest score for the price criterion should be awarded to the proposal offering the fee closest to the

average and the lowest score(s) should be awarded to the fee(s) furthest from the average, whether above

or below. This approach requires a minimum of three fee proposals and will result in a negative score if

a fee is less than half the average.

46

The score should then be weight-adjusted using whatever pre-established weighting has been determined

for the price criterion. The price score should then be added to the scores for the non-price criteria to

arrive at an overall score for each proposal.

Subject to value for money considerations, where three proposals have been sought by an entity but only

two proposals are received, the highest score for the price criteria will generally be awarded to the

proposal offering the lowest price. However, where three proposals have been sought and only one

proposal is received, the officer responsible for the invitation process should carefully consider whether

invitations for proposals should be re-called.

5.1.2 Qualification Based Selection

Qualification Based Selection should be the evaluation method used when the commission service

requirements lack definition and/or require significant innovation.

The Qualification Based Selection method identifies consultants who are best qualified to address the

commission's non-price selection criteria. Selection is based on an evaluation of consultant responses to

non-price criteria only (i.e. the fee proposal is not considered in the initial evaluation).

The fee proposal should be opened only after a preferred consultant is identified and then only for that

preferred consultant. The fee proposal is used as the starting point for negotiations with the preferred

consultant regarding the scope of work and associated fees. If agreement cannot be reached with the

preferred consultant, negotiations may then begin with the second ranked consultant and so on through

the rankings until agreement is reached. All unopened fee proposals should be returned to unsuccessful

consultants.

The Qualification Based Selection method and the associated negotiations require professional and

technical expertise.

5.2 Evaluation criteria and weightings

5.2.1 Evaluation criteria

The evaluation of consultants should be undertaken using price and non-price evaluation criteria.

The approach to evaluation of consultant responses to the price criterion through their fee proposals is

covered in section 5.1.1.

The non-price criteria may include:

understanding project objectives;

method;

resource strategy;

value adding; and

support for local industry.

Information sought from consultants in response to these criteria should be limited to the critical aspects

of the service to be provided. The level of detail sought in the proposals should be commensurate with

the value and service risk associated with the commission.

The evaluation criteria and associated sub criteria are addressed in further detail at Appendix 1 -

Evaluation criteria and sub-criteria for consultancy proposals.

47

5.2.2 Weightings

The weightings for particular criteria should be aligned to the achievement of an appropriate balance of

project and other outcomes consistent with the objects of the Act, while at the same time being responsive

to factors such as project size, complexity, profile, budget, timeframe, specialist nature, site conditions

and location.

5.3 Evaluation of proposals

The aim of the proposal evaluation process is to identify the most advantageous proposal for the entity,

that is, the proposal that offers the best value for money.

The review and evaluation process must be transparent, fair and equitable. It is good practice to document

and randomly audit the process to verify that it is working effectively. Any discrepancies should be noted

and addressed before a final recommendation is made.

Any proposal that is not lodged by the closing date (unless a consultant may provide a reasonable written

explanation of causes beyond their control which caused this) or that does not comply with the

requirements of the conditions of offer included in the invitation package may be deemed non-

conforming and be rejected without evaluation.

The entity also has the option to reject all proposals and recall invitations in accordance with the

conditions of offer. However, it is important that this step be undertaken with good reason.

5.3.1 The evaluation panel

The evaluation of submissions is to be undertaken by an evaluation panel of at least three people

comprising:

one professionally qualified officer involved in preparing the invitation documents;

one officer (preferably from the same discipline as the consultant required) with sound technical

knowledge and capable of understanding and interpreting the proposals; and

one officer with a sound knowledge of procurement procedural requirements.

One of the panel members should assume the role of evaluation panel chairperson. The panel chairperson

is responsible for ensuring that the proposal evaluation process is conducted in a timely, competent and

accountable manner.

5.3.2 Proposal evaluation plan

On high value, high risk and/or sensitive commissions it is appropriate to prepare a proposal evaluation

plan to assist evaluators in their task and help ensure that the process is conducted in a timely, competent

and accountable manner. The plan should comprise:

a description of the evaluation criteria and associated weightings. It may also be useful to provide a

list of sub-criteria presented in the form of a checklist to assist evaluation of the proposals;

a description of the scoring method to be used; and

a brief explanation of the evaluation method being used (that is, Value Selection or Qualification

Based Selection – refer section) and an overview of the steps in the process.

5.3.3 Approach when the proposal fee is very low

Care should always be exercised in selecting proposals where the whole or a key element of the proposal

is at a fee level considered well below the average proposal fee, and/or the fee estimate for the

commission.

48

While the price scoring approach used in the Value Selection method significantly reduces the likelihood

of a proposal with a very low fee emerging as the preferred proposal, this could occur if the consultant

scored highly in response to the non-price criteria. Low fee proposals may also be encountered where

there is a sole invitee or two invitees.

In this situation, in accordance with Section 34(1) of the Act, it is necessary to request the consultant

offering the very low fee to review their proposal and/or respond to questions regarding particular aspects

of the proposal and confirm in writing that the Terms of Reference and contractual obligations are fully

understood before proceeding. If the consultant has made a mistake in preparing their proposal, there is

an opportunity for the consultant to withdraw the proposal.

5.3.4 Evaluation criteria and sub-criteria for consultancy proposals

The following criteria may be used to evaluate consultant proposals:

understanding project objectives

method

resource strategy

value adding

support for local industry

price

These criteria are discussed as follows:

5.3.5 Understanding project objectives

The consultant’s understanding of project objectives is important, particularly for design commissions

associated with larger projects. Consultant responses to this criterion should convey the consultant’s

analytical understanding of the objectives and not simply repeat those stated in the Terms of Reference.

The consultant’s understanding of project objectives should also be evident in their response to other

criteria.

Relevant sub-criteria that consultants may be requested to address in their proposals include:

the scope of work identified in the Terms of Reference

project objectives and deliverables in terms of time, cost, quality and function

design intent

operational efficiency requirements / intended service delivery

flexibility requirements

asset life-cycle factors such as maintenance, operating costs, etc.

5.3.6 Method

This criterion is concerned with the consultant’s processes for delivery of the required service.

Consultant responses may include diagrammatic representation of the proposed processes, reporting

relationships, systems, procedures, etc. Items the consultant may be requested to address in their

proposals to include:

process management

overall design (or trade package) documentation process

programming issues

cost planning and cost management

built asset life-cycle cost issues

training, handover and commissioning processes

buildability issues

quality management, safety and environment policies

49

management systems

key support equipment and systems

built asset whole-of-life cost issues

alternative forms of procurement

strategy for maximising value for money

community consultation strategy

environmental management/sustainability

5.3.7 Resource Strategy

The criterion seeks to clarify how the consultant will resource the project in line with the project

objectives. The required resources should be outlined, including back-up resources and any special

expertise considerations.

Relevant sub-criteria that consultants could be requested to address in their proposals include:

capability of the project team (both managerial and supervisory personnel and key team

members)

personnel backup strategies

referees

resource management strategies

management structures and reporting relationships (including identification of key activities and

the proportion of time that identified personnel will be allocated to these activities)

past and current time related performance

impact on entity resources

use of special information technology packages

5.3.8 Value adding

This criterion provides consultants with an opportunity to state benefits that they may offer over and

above those sought in the Terms of Reference. The information provided should demonstrate how the

consultants propose to add value to the delivery process or the project outcome.

Relevant sub-criteria that consultants could be requested to address in their proposals include:

innovative approaches to design issues described in the Terms of Reference

incorporation of research and development findings into project deliverables

prior knowledge of the particular site

understanding of local issues

special skills of personnel (may also be reflected in resources section)

contribution to the built environment

5.3.9 Support for local industry

This criterion is concerned with local industry participation issues and requires consultants to explain

how full, fair and reasonable access will be provided. Relevant sub-criteria that consultants could be

requested to address in their proposals include:

strategy for use of local sub consultants and/or service providers and suppliers

strategy for providing training and/or skills/technology transfer to local consultants and/or local

service providers or suppliers

opportunities for local product specification / import replacement

5.3.10 Price (fees)

50

This criterion is relevant to both Value Selection and Qualification-based Selection as it provides the

basis for assessment of value for money of consultant proposals. Under Value Selection, price scores

are calculated using a price scoring formula; whereas under Qualification-based Selection, price scoring

is relevant only to the extent of providing a starting point for negotiations with the preferred consultant

after that consultant has been initially identified based on responses to the non-price criteria.

Consultant fees need to be stated in accordance with the invitation documents. Generally, this will be in

the form of a lump sum or percentage of the estimated construction cost or based on an hourly rate with

an agreed maximum limit.

6.0 Pre-approval activities

Prior to recommending a preferred consultant, the identified consultant’s current workload should be

clarified to confirm that the consultant is still eligible to undertake the commission in terms of currency

of registration/licensing, management systems, insurances or any other issues that may preclude the

awarding of the commission to that consultant.

7.0 Awarding the commission

Subject to satisfactory pre-approval checks, the evaluation panel should nominate the preferred

consultant to the relevant approving authority.

After approval, a Letter of Commission should be issued to the successful consultant commissioning the

consultant under the General Conditions of Engagement.

Each unsuccessful consultant should be advised in writing of the outcome of the evaluation process and

of the name of the successful consultant.

8.0 Standard consultant agreements

Requires customization and further development by each enterprise

9.0 Debriefing

Debriefing meetings to discuss evaluation results should be available to consultants upon request. The

debriefings should be held on an individual basis and be conducted by at least two members of the

evaluation panel.

The purpose of the debriefing is to provide constructive feedback on areas where the consultant could

improve for future proposals. In this regard, the panel should advise the consultant on:

the adequacy of the consultant’s proposal in relation to the evaluation criteria; and

the relativity of the consultant’s response to each of the criteria in comparison to the successful

consultant, taking care not to disclose actual scores.

51

5. Contract Management Plan

The following template for contract management of works contracts has been adapted from the Procurement

and Disposal Handbook to suit the process normally associated with Management of Construction Contracts.

A draft Contract Management Plan using this template is to be developed and included in the procurement

strategy in accordance with the guidance and processes set out in the Handbook.

Focus Element Detail to be completed

Contract

Management

Plan:

Title and Purpose Insert title of plan and summarise its

purpose.

Identify the significant procurement action

to which this plan related

Identify the significant procurement

strategy of which this plan forms a part.

.

Contract

Structure:

Contract summary Summarise key contract details, for

example:

contract number,

commencement date,

contract term/duration

approved users of the contract

contract value

Background Provide a brief summary of the

procurement objectives and actions that

give rise to the contract

Contract purpose, objectives, scope, and

key deliverables of the contract.

Documentation List all documentation relating to the

contract that is held by the Contract

Manager e.g.,

Project Definition Plans

Procurement Plans

Tender evaluation reports,

Risk management plans etc.

Contract term and

extension options Contract start and end dates

Contract extension options

Pricing Total contract value,

Payment arrangements including any

payment schedule

Variations

Fluctuation formulae if applicable

52

Focus Element Detail to be completed

Group roles and

responsibilities:

Contact details Contract management contacts: Entity

Contract/relationship management

contacts: Contractor

Other key entity and supplier entity

contacts

Employer under the Contract

Employers Representative

Key stakeholders List key stakeholders and their major

responsibilities in relation to the contract

Stakeholder

management and

communications

strategies

Project governance

Methods to be used for liaison,

Reporting arrangements,

Strategies for building relationships with

key stakeholders

Project governance arrangements

including

o Project Manager

o Project Steering Committee

o Project Control Group

Delegations for approval of variations

incurring cost and time.

Delegations for issuing instructions

without a financial implication

Delegations for granting extensions of

time

Delegations for approval of progress

payments

Delegations to issue the final certificate

Document

Management

Managing Requests for

Information from the

Contractor

Managing Transmittal

and Receipt of

Amendments to

Drawings and Technical

data

Instructions to

Contractor

Process to be developed jointly with the

Contractor defining such elements as

o Communication Media

o Roles and Responsibilities

o Response Timeframes

Conditions of

the Contract:

General conditions Identify the form of contract used

Special conditions Special conditions:

Warranties

53

Focus Element Detail to be completed

Intellectual property ownership etc.

Government policy requirements

Contract variations

(price, product/services

or other)

Contract variations

Requirements that need to be met to allow

a variation as per contract provisions.

Process of evaluation of variations for

particularly time and cost

Insurance Details of insurances held

Details of currency and adequacy of

insurance certificates

Procedures for obtaining evidence from

the supplier/contractor of future currency

Financial

Considerations:

Payment conditions Contract conditions relating to payment

Details of payment schedule and basis for

payment

Documentation of payments made with

reference to ensuring that through Budget

Management there are funds available to

discharge the Contract Payment

conditions/obligations

Incentives or rebates Describe any incentive arrangements

included in the contract and how they are

to be calculated.

Penalties or

disincentives

Describe any penalties that may be

included in the contract and how they are

to be calculated and applied e.g. liquidated

damages, performance guarantees

Budget management Maintain a record of the overall project

budget including

Total project budget

Contingency

Actual budget allocated to this

contract

Variations approved

Variations committed but not

approved

Balance of funds available ( i.e. not

committed )

Invoicing

Detail the invoicing requirements for the

contract as well as

54

Focus Element Detail to be completed

format for progress claims and the

process for lodgement of progress

claims

assessment and certification of

progress claims

process to ensure payments are

made within the provisions of the

contract

Performance

Measurement:

Key performance

measures Key performance measures/indicators to

be used for measuring the performance of

contract.

Performance measures are identified in the

approved procurement strategy, in the

solicitation documentation and in the

contract.

Performance

incentives/disincentives

List any non-financial performance

incentives or disincentives that are

applicable to the contract and the key

performance indicators that trigger them.

Performance monitoring May not apply for all Contracts

Describe the data collection and analysis

methods to be used for monitoring and

assessing performance (e.g. user surveys,

third party certification, benchmarking

etc.)

Detail who will undertake performance

monitoring including: responsibility for

collecting and analysing data; how

frequently monitoring will take place; the

reporting arrangements; and any processes

to review the arrangements.

Contract

Administration:

Supplier/contractor

obligations

Detail all obligations the contractor has

under the contract including:

contract construction deliverables (May be

defined by reference to the Contract

Schedule e.g. Conditions of Contract,

Technical Specification and Drawings)

any other deliverables covered by the

contract

timeframes to be met

specified personnel nominated in the

contract

reporting requirements

provision of equipment

back-up arrangements.

55

Focus Element Detail to be completed

Entity’s obligations Detail all obligations the entity has under

the contract including:

access to site

provision of utilities e.g. power ,

water

security arrangements

information to be made available to

the contractor

equipment to be provided

accommodation

feedback and satisfaction reporting

scheduling of meetings

Product or service

standards expected Product or service standards included in

the contract (Generally defined in the

Technical Specification)

How they are to be administered

(commissioning processes, quality

assurance, site inspections)

Compliance

management Detail relevant procurement related

polices and obligations that the entity and

the suppliers/ contractor are required to

comply with and how these will be

managed.

The contract manager is responsible for

the management of these obligations.

Transition Arrangements for managing any transition

and attach transition strategies or plans.

Reporting requirements Refer also to section on governance

List the reporting requirements:

reports to whom

what is to be reported

format of reporting

frequency of reporting

schedule of reports

Audit requirements Requirements for internal and independent

audits

Elements of the contract to be audited

The timeframe for the audit

Resources required (in-house or external)

Contractor meetings Schedule of meetings specific to the

contract

56

Focus Element Detail to be completed

Process for inviting and reminding

relevant parties

Risk assessment

and

management

strategy:

Procurement Risk Plan Risk management plan included in the

Significant Procurement Strategy

Identify risks that carry through to the

contract management phase.

Update Risk Management Plan as a

regular monitoring item normally an

agenda item for Project Meetings

identified in the Governance Section

Contract Risk Plan Refer to Risk Management Plan

Details of contract risk planning

Risks and mitigation strategies.

Contract risk plan to Risk Management

Plan.

Issue Register Refer to Risk Management Plan

Issues (realised risks) that may arise and

how they are to be managed

Identify locus of responsibility for

managing each issue/risk.

Contract Review Refer to the Sections on Governance and

Reporting Requirements

Outline regular reviews and their timing

Detail how they will be conducted

including data collection responsibilities

Identify trigger point(s) at which contract

review becomes necessary due to

underperformance.

Dispute Resolution

Process Dispute resolution clauses in solicitation

documents and in the contract

Procedures for addressing the dispute.

Termination Termination clauses in contract

Conditions for termination

Termination process to be followed

Contract

Review:

Renewal or extension Process to be followed in assessing

whether to renew or extend the contract

Steps to be followed as the contract nears

expiry.

57

Focus Element Detail to be completed

Contract closure List the tasks that are required to

successfully complete and close the

contract including but not limited to:

commissioning plan

recovery of entity material and

equipment

handover procedures

security and access closure

contract evaluation

resources required (in-house or

external)

documentation of lessons learned

notification to stakeholders

Attachments: All documents relevant to contract

management to be attached including:

General Conditions of Contract

Special Conditions of Contract

Schedule of Technical Data

Technical Specification

Bill of Quantities

Schedule of Rates

Provisional Quantities

Contract Programme

Schedule of Drawings

Letter of Acceptance

Documents exchanged Pre

Contract Award

Instructions to Contractor Post

Award

Project Correspondence

Variations Issued

Budget Management

Time Management

Approvals

Project Governance Meetings

Risk Management Plan

58

6. Project / Procurement Management Plan

1.0 Introduction

1.1 Purpose of this document

A project management plan as described in the Project Management Body of Knowledge -

PMBOK Guide Sixth Edition is a formal approved document that defines how the project is

executed, monitored and controlled. It may be in summary form or detailed and may be

composed of one or more subsidiary management plans (appendices) and other planning

documents. The objective of a project management plan is to define the approach to be used

by the project team to deliver the intended project management scope of the project. The attached

appendices capture live project information.

2.0 Project Details

Project Name

Project Short Description

Physical Location

3.0 Scope

3.1 In Scope

The scope inclusions are those specifically included in the Bill of Quantities and cost

estimate.

3.2 Out of Scope

Any items not included in the Bill of Quantities and cost estimate have not been

allowed in the project.

3.3 Related Projects

Any related projects?

3.4 Constraints

The issues constraining this project are as follows:

3.5 Urgency

If any

3.6 Assumptions

An example

The following assumptions are part of this project management plan:

Funding will be identified, confirmed and approved prior to formal project

commencement.

Timing constraints from both political and funding obligations will be

59

confirmed prior to formal project commencement.

The preliminary design proposed in the current master plan forms a substantial

basis of the final design.

A design and construct delivery model for a guaranteed maximum price

Political support for the project will continue.

4.0 Impacts

Areas within the entity

e.g. Maintenance and Operations

Nature of Impact e.g. costs

Areas external to the entity

e.g. Public Safety

5.0 HR Management Plan

This is normally contained in a HR Management Plan including contract

administration summary; staff roles and responsibilities; responsibility assignment

matrix and consultancy list.

5.1 Project Customer

5.2 Project Sponsor

5.3 Project Manager

5.4 Governance Structure

An example

The project will be governed by a Project Control Group. This will consist of

delegated representatives of both the Project Customer and the Project Sponsor, as

well as the Project Manager and representatives from the contractor. An independent,

third - party superintendent will be appointed to manage the contract administration

and perform a role in the assessment, valuation and certification of contractual

claims. A detailed organisational structure for the project is attached at Appendix D

Detailed Human Resource

60

6.0 Scope Management

6.1 Risks and Issues

For additional information refer to Risk Management Plan

6.2 Time Management

An Example

During the pre-contract phase of the project the Project Manager will be

responsible to ensure that the project programme remains on target. This

occurs through regular review of project progress in relation to programme

milestones. During the contract phase project the management of time and

resources will be obligations of the contractor overseen by the Project

Manager. There will be contractual mechanisms in place to ensure that

these are appropriately managed. Regular meetings of the Project Control

Group and reporting of progress are the responsibility of the Project

Manager. The Project Manager remains responsible to ensure that

satisfactory project progress is maintained.

A detailed Project Schedule is contained Appendix B: Project Schedule

6.3 Cost Management

An example

The design and construction contract will be structured to guarantee the maximum

price of the works. Value for money is ensured by the supply of a bill of quantities

and rates at tender. The competitive nature of this phase ensures keen pricing.

Variations are managed through scope manipulation but the contractor is bound

by the quantities and rates submitted at tender. Change to costs are managed then

through a change in scope, but only where there is a clearly demonstrated case

arising from circumstances or facts that could not reasonably be known at tender.

Independent, third-party oversight of rates and quantities throughout the

construction phase is a contractual requirement.

A detailed Project Schedule is contained in Appendix C: Project Budget and Estimate

6.4 Human Resources Management

An example

Internal human resources required to manage the project are identified in the Project

Team organisation structure at Appendix D.

6.5 Communication

An example

Appendix E

Communication Management Plan identifies, analyses and classifies stakeholders,

61

includes communication methods, tools and techniques, and reporting systems.

6.6 Project Control

An example

Project control is managed through the Project Control Group. This group

meets regularly throughout the project to identify, discuss and determine issues

that confront the project. Minutes from these meetings form instructions to the

contractor and others. The Project Manager is responsible for taking and

distributing minutes and ensuring that follow up action occurs. Issues that are

beyond the authority of the Project Control Group are escalated to the Project

Sponsor for determination. It is the responsibility of the Project Manager to

ensure that this occurs where necessary and is managed in a timely fashion in

order to maintain the progress of the project.

Design documentation is prepared as part of the contract works. This is

progressively approved or amended by the Project Control Group during the

contract phase of the project and this documentation then forms part of the

contract.

6.7 Contract Management

This is outlined in sufficient detail to inform the Project Management Plan

particularly as it relates to Project Management Resourcing Strategies

6.8 Quality Management

An example

Quality through the design phase of the project is managed in the first instance by

the detail included in the specification at tender.

Quality through the construction phase of the project is managed by regular

inspection of the works; hold points at key milestones in the contract; and third

party certification of prescribed portions.

6.9 Integration

Note areas where there could be integration with other projects.

7. Safety

An example

Occupational Health and Safety (OH&S) throughout the design and

construction contract will be the responsibility of the contractor. He will be

nominated as the person in charge of the workplace and will need to

demonstrate at the EOI stage of the selection process that there are appropriate

systems in place to meet these obligations.

A detailed OH&S Construction Checklist will be required to be prepared and

submitted as part of the tender process.

62

8. Operational Issues

Any general operational issues such as site access, site security, safety

requirements, etc.

9. Project Performance Measurement

An example

Success

Criteria Responsibility

Measurement

Method KPI Target

On-time Delivery Project Manager

Assessment of

planned progress

against actual

progress

On budget delivery Project Manager

Assessment of

outturn cost against

Budget

Ongoing

Operational Costs

Operations

and

Maintenance

Manager

Assessment of

planned

expenditure

against actual

expenditure.

Stimulus to

commercial

environment

Number of full

time equivalent

(FTE) positions

employed in

commercial

environment

10. Project Management Plan Acceptance

In signing this approval:

• I agree that the document meets the standard required for the project

management plan deliverable (requirements above).

• I understand the financial and other impacts associated with approving this project

plan

• I authorise progression to the implementation stage.

The following officers have approved this document.

Project Manager (accountable for ensuring the project is clearly defined to all

stakeholders, with strategies to deliver the project efficiently and effectively)

63

Name:

Position: ------------

Signature: Date: I

Name: _

Position: _

Signature: Date: I

Appendix A - Business Plan

Appendix B - Project Estimate

Appendix C- Risk Management Plan

For the purposes of establishing the Project Management Plan and for handover to a project or

contract manager the following checklist has been provided. The checklist covers the entire

project life-cycle and may be cut down to suit the individual project or contract management

role.

Project Management Plan Approval Checklist

What the project is expected to achieve has been determined. (For example

potential costs and benefits based upon current knowledge and understanding).

There are clear justifications for the project

The real underlying problem to be addressed has been identified

Project governance is documented. Project customer, sponsor and manager have

been identified and accept their responsibility

The products or services to be delivered, and how they specifically address

requirements have been clearly determined.

Background details include (in summary format if possible):

Who initiated the project and how current situation

(problems, needs or opportunities) will affect the

project

The products or services that will be delivered

Potential costs and benefits based upon the current

knowledge and understanding the history of the project

Any other initiatives carried out previously to address related issues.

The scope outlined in the business case is confirmed or updated.

Any scope creep is noted

Internal and external impacts, and possible mitigation

strategies, are identified

The business case investigations, research method and

engagement are clear.

The risk management plan is attached. The issues management

plan is included where appropriate.

The broad strategy to deliver the project is clear.

Adequate project controls are included (including integration, scope, time, cost,

64

quality, HR, communication, risk and procurement management.

Environmental management, cultural heritage management and safety are addressed.

Operational issues asset transfer or ownership, commissioning, handover

support, maintenance, warranty and management strategies identified.

Project performance measurement and product benefits realisation are clear.

The costs incurred to date are identified. (preparation of options analysis, and

project proposal).

Financial impact analysis) attached, including cash flows, estimated costs for

each phase, contingencies, financial indicators and expected year for

programming of fund.

Funding Source is clear

The recommendation is clear, e.g. reason why the project should proceed to

the next stage and identify the impacts of not proceeding.

Deliverables

Appendix A- Project Scope

Appendix B- Project Schedule

Appendix C- Project Budget& Estimate

Appendix D - Human Resource Management Plan

Appendix E - Communication Management Plans - Internal and External

Appendix F - Risk Management Plan

Appendix G - Procurement Requirements Plan

Appendix H - Project Controls

Appendix I - Quality Plan

OH&S Construction Checklist

Environmental Management Checklist