Speakers: Alan Ross, Design Manager Phase 1,...
Transcript of Speakers: Alan Ross, Design Manager Phase 1,...
Roads Academy Masterclass Turning Ideas into Delivery
Case Study – A1 Dishforth to Barton Improvements
Speakers: Alan Ross, Design Manager Phase 1, AECOM Chris Hayton, Carillion-Morgan Sindall JV Project Director
Alan Ross, Design Manager Phase 1, AECOM
Content
Project Overview
How were ideas promoted in the design process
Case Study 1: Risk Reviews Case Study 2: Interim Road Safety Reviews Case Study 3: Use of gINT Case Study 4: IDC process
Scheme History
• Award of ECI Contract in March 2004 to Alfred MacAlpine/AMEC
• Bullen Consultants as Lead Designers with sub-consultants Carl Bro and RPS
• Public Consultation in June 2005
• Publication of draft Orders in March 2006
• Public Inquiry Oct 2006
• Secretary of State Decision Letter 31 March 2008
• Dishforth to Leeming commences construction March 2009
• Two schemes developed in early 1990’s
• Public Inquiry held on Leeming Bar to Scotch Corner in 1995
• Orders published but not made on Dishforth to Leeming Bar
• Both schemes withdrawn from Roads Programme in 1996
• Upgrade added to TPI 2002 after a Safety Study
• Preferred route announced in July 2002
Dishforth to Leeming Leeming to Barton
• Award of ECI Contract in March 2004 to Carillion/Morgan Sindall
• AECOM as Lead Designers with sub-consultants Grontmij and RPS
• Public Consultation in June 2005
• Publication of draft Orders in March 2006
• Public Inquiry Oct 2006
• Secretary of State Decision Letter 31 March 2008
• Dishforth to Leeming commences construction March 2009
Promotion of Ideas • How
- working collaboratively
- value management reviews involving:
ECI Team
+ HA Specialists
+ Key Stakeholders
- Ethos developed within team
- Knowledge Transfer from previous M6 ECI team
Case Study 1: Risk Analysis
• Collaborative approach
• Risk Manager
• Output
Collaborative Approach
Team evaluation
Monthly review by key team (HA, Employers Agent, Contractor and Designer
Periodic involvement of Key Stakeholders
Risk Manager Same Person
Was able to bring forward issues currently being experienced
Provided a reality check on the issues being recorded
Output
Greater understanding of the risks leading to better management
Better understanding of stakeholder issues
Increased confidence in the valuation
Case Study 2: Interim Road Safety Review
• Collaborative approach
• Output
Collaborative Approach
Promoted by the design team as a method of raising confidence in the finished product
Facilitated a confidence level with the Client
Essential early involvement of Key Stakeholders
Output Right first time product allowing early opening for traffic – WS1 was 6 months early
Used in review process by Client through Employers Agent to provide confidence in the product
Submitted as part of design package to Local Highway Authority
Case Study 3: Use of gINT
• Identification of the issue
• Resolution of the Issue
• Output
Identification of the Issue
Over 50 years of data available from numerous sources (10 GI’s in the period)
How do you bring them all together and make the information available?
Resolution of the Issue Collate the information within gINT (an Excel based software package)
Software created a colour coded model for the strata layers
Output
Production of geotechnical sections
Output
Earthworks example
Output
Balancing Pond example
Output Structures example
Output - Summary Having over 50 years of ground investigation data in one place and readily accessible has proved invaluable. Visualization and analysis of legacy data at an early stage in the project aided and optimized the scheme specific ground investigation – enabled cost savings. Ability of gINT to produce geological sections in seconds has provided time and therefore cost benefits throughout the project from feasibility through to detailed design.
Case Study 4: IDC Process
• Collaborative approach
• Output
Case Study 4: IDC Process
• Collaborative approach
ECI team involved in IDC processes
IDC Manager + Construction Manager + Discipline Team Leaders
• Output
IDC identified conflicts early in design – reducing abortive costs
IDC adopted collaborative planning to assist sequencing detail design
IDC reduced conflicts during construction