KAOMBO Project
19 March 2019
Willy Gauttier – TechnipFMCAymeric Lépinay – Total E&P Angola
2
KAOMBO : An « Iconic » Subsea Project
I – Introduction
II – Challenging Development
III – Approach & Relationship
IV – Kaombo Take Away
3
I - INTRODUCTION
Willy Gauttier – TechnipFMC – TechnipFMC/Heerema Consortium Director Aymeric Lépinay – Total E&P Angola – Kaombo SURF Project Control Manager
CONFIDENTIAL
4
KAOMBO : An « Iconic » Subsea Project
I – Introduction
II – Challenging Development
III – Approach & Relationship
IV – Kaombo Take Away
5
KAOMBO – A FRONTIER PROJECT
CONFIDENTIAL
II - A challenging development
6
II - A challenging development
CONFIDENTIAL
• 1999 PSA signed• 2003-08 Discoveries of the 6 fields:
Gindungo, Canela,Gengibre, Mostarda, Caril and Louro
• 2008-11 Pre-Project studies• 2011-12 Basic Engineering & CFTs• 2013 Project Value Enhancement• 2014 April 14th = FID• 2018 July 27th = First oil
A long journey towards FID, then 4 years to first oil
30%
20%15%
5%
30%
Manjericao
Gengibre Canela
Louro
Salsa
Mostarda
GindungoCaril
Colorau
Alho
Cominhos
Cola
20 km
Kaombo658 Mb
5090 km²
7
II - A challenging development
CONFIDENTIAL
GGR uncertainties and drilling challenges Dispersed reserves: 6 fields, 9 reservoirs Complex structural & sedimentological environment Presence of salt layers Huge subsea layout on a complex seabed 800 km2 Numerous pockmarks and geohazards A first as FPSO Built & Operate model with one
of biggest turret & schedule challenges Over 50 main activity centers in 23 different
countries Scope in Angola: 14 MMhours commitment
140 km2200 kb/d 230 km2
240 kb/d
600 km2200 kb/d
381 km2160 kb/d
800 km2230 kb/d
110 km2250 kb/d
180 km2250 kb/d
400 km2240 kb/d
100 km2100 kb/d
450 km2150 kb/d
0
500
1000
1500
2000
2500
1998 2003 2008 2013 2018
Water dep
th (m
)
First oil date
GIRASSOLDALIA
PAZFLOR
CLOV
KAOMBO
KIZOMBA C
KIZOMBA B
KIZOMBA A
KUITO
PSVM
TOTALPROJECTS
TOTALKAOMBO
OTHER OPERATORS
8
Louro
Mostarda
GengibreCanela
GindungoCaril
SURF290 km of line pipe115 km umbilical6 hybrid production loops5 water injection lines1 gas export line
HSENo permanent flaring(gas export to ALNG)Oily drilling cuttings brought to shore (new law)100+ million man‐hours
2 FPSOs operated – D1B2Converted VLCCsTurret moored/Tandem offloading2 x 115 kbpd oil yearly average1650 m water depth
SPS59 (+6) Vertical Xmas trees19 Production manifoldsSubsea prod. ctrl. systems
Drilling59 wells (23 sub‐salt, 33 OP + 26 WI)Average : 63.5 days / well (with 2 rigs dual derricks x 5 years each)1400 to 1950 m water depth
Geosciences9 dispersed and complex reservoirs of limited volume Limited upsides658 Mb
KAOMBO PROJECT SCOPE
8
9CONFIDENTIAL
II - A challenging developmentUK
SPS engineeringWellheads
Control systemsUmbilicals engineering
SURF FlexjointsSURF multi-jointing
URA/LRA fabrication
AngolaGeosciences, Drilling managementManifolds fabricationXmas trees and wellheads assembliesFlowlines spooling, risers prefabricationUmbilicals fabrication FPSO piles fabrication2 FPSO modules fabricationOperations onshore baseSURF offshore installation vessels
JapanRiser pipes
Conductor pipes
MexicoSURF linepipes
Italy Subsea valves and forgingsSURF linepipes
NetherlandsSURF engineering
Conductor pipesTurret engineering
FPSO pumps
Czech Republic Umbilicals tubes
NorwaySPS engineering
Manifolds Xmas trees
MPFMFPSO Turbines
USASURF engineeringUmbilicals fabricationDrilling completion, subsea test tree
SingaporeFPSO NORTE conversionand integration
IndonesiaFPSO modules fabrication Pipe coating
ChinaConductor pipes
FranceProject managementEngineering (SURF, FPSO/FOSC)TubingFlexible jumpers
IndiaEngineering (SPS, SURF, FPSO)
GermanyTurret bearings and swivel stack
FinlandXmas trees blocks
MalaysiaControl systems
SPS tubing hangers,Xmas trees
Xmas trees flat packSCMs
MSMs, connectors
BrazilSURF welded linepipes
SpainSURF structures fabrication
United Arab EmiratesLower turret fabrication
Riser piles and buoyancy tanks fabrication
South KoreaDS-8 rig
construction
ChiliLower bearing
CanadaTurret controls
Activities completed
SURFSPS FPSO / FOSCUMBILICALS WELLS & DRILLING
KAOMBO Worldwide sites
FPSO SUL conversion and integration
10CONFIDENTIAL
II - A challenging development
Cut off date: 20 Oct 18
402%
PETROMAR Ambriz2 modules fabrication, suction piles, boat landing
SONILS LuandaAssembly of 21 wellheads &x‐mas trees
ANGOFLEX Lobito Fabrication of dynamic umbilicals
SONAMET LobitoFabrication of 21 PGBs, 19 manifold foundations, 9 manifolds, 35 production jumpers
PAENAL Porto Amboim2 modules integration FPSO South (cancelled)3 SURF riser foundations Structures installation aidsWater injection jumpers
HEEREMA Porto AmboimRiser foundations, multijointing, spool & jumpers, seafastening
TECHNIP DandePipe stalking: 10”/ 16” PIP production, WI, Sl & GE flowlines
145%
148%
139%
137%
111%
59%
152%
Block32
230%
SAIPEM Onshore logistics base133%
TECHNIP ‐ HEEREMASURF offshore installation
SAIPEMFPSO/FOPS offshore works
19.4 M143%
13.5 M manhours
Still active
Still active
All still active
Excellent safety and quality records to date
ANGOLAN CONTENT – MANHOURS STATUS AS OF 20 OCT 18% = EXPENDED HOURS VS. ESTIMATED HOURS
1111
CLOV Kaombo
Duration 46 months 47 months 42 months
Production 220 KBOE/d 160 KBOE/d 230 KBOE/d
# subsea wells 49 34 59
Lines kms 180 180 300
Investment $9b $8b $16b
Larger and quicker
Our core Business BUTbut with a good mix of Organization, Method and Agility !!
II - A challenging development
12CONFIDENTIAL
II - A challenging development
KAOMBO SULKAOMBO NORTE
13CONFIDENTIAL
The Team
II - A challenging development
14CONFIDENTIAL
II - A challenging development
15
Doing twice the same thing with the same level of performance is a challenge.
HSE an interesting journey: when you are halfway you feel as if you've not yet started.It's only when you reach the finish line that you've really achieved anything.
HSEhighest standard
Everyone SAFE at homeNo material damage
Upgrading our leadership…
… and our assets
Up to 1200 POB Block 32 / 18 marine assets
II - A challenging development
16
II - A challenging development
Massive logistics for a flawless 600+ days Offshore Campaign
55.000 tons of material installed by TechnipFMC
Massive Offshore work 5000 vessel days for TechnipFMC with:
1200 Construction + 3800 Third Party15000
Meet & Greet
500 Containers
180 Cargo Barge Approaches
2000 Supply Boat runs
17
II - A challenging development
But simple tools to enable alignment…
Visual time-location chart to spot potential Clash ahead 1000
Offshore Interface Dossierswith CPY
1000Vessels/Rigs moves
24 monthsRIG/vessel clash free
Campaign
De-coupling Deep Blue &Balder upon progress
18
Main Installation Campaign :
De-risking of Rigid Spools installation (Project Risk #1)
Breaking installation timing50 large rigid spools 900Te Crane Upgrade
Lifting weight: Up to 310Te 100% of operability over the year resulting to no stand-by
II - A challenging development
19CONFIDENTIAL
II - A challenging developmentA Unique Technology: 900Te Crane – Constant Tension Pick Up mode
20FPSO heading control ≤ ±30˚ to 15%
when handling
Hook-up Campaign :
De-risking Flexible Jumper Connection to the STTR Upper Riser Assembly
Better than expected since the first one
Stack-up testsFull scale test Connection with
TMOS personnel
Offshore Operations
II - A challenging development
21CONFIDENTIAL
II - A challenging developmentA Unique Technology: EHS (End Handling System)
EHSVideo
22CONFIDENTIAL
Operations
II - A challenging development
23
KAOMBO : An « Iconic » Subsea Project
I – Introduction
II – Challenging Development
III – Approach & Relationship
IV – Kaombo Take Away
24
II – Approach and RelationshipKaombo Frontier Project :
Necessity to establish a proper collaborative working environment
CONFIDENTIAL
5 years14 Sponsors
25
II – Approach and RelationshipFPSO North Campaign :
Alignment on an optimized First Oil sequence with the « Time location chart »
Slot 1 Slot 2 Slot 3 Slot 4 Slot 5 Slot 6 Slot 7 Slot 8 Slot 9 Slot 10 Slot 11 Slot 12 Slot 13 Slot 14 Slot 15 Slot 16 Slot 17 Slot 18
CAN PROD Priority 2
CAN GL Priority 2
CAN WI Priority 6
CAN SERV Priority 2
LOU/MOS WI Priority 7/8 Future Riser
MOS PROD Priority 1
MOS GL Priority 1
MOS SERV Priority 1
LOU SERV Priority 5
LOU GL Priority 5
LOU PROD Priority 5
MOS DPU Priority 1
LOU DPU Priority 5 Future Riser
GE Priority 4
SSIV CC Priority 4
CAN DPU Priority 2
KEY MILESTONES Mooring Sequence (simplified)F F Deploy chainstoppersF F 1 Line SURF SURF hook‐up (Skandi Africa)F F 2 Lines SURF SURF hook‐up (FPSO) Turret Critical Path to Mostarda startupF F 3 Lines ( storm moored) SURF SURF Pre‐commissioning activity F F 4 Lines SURF SURF Subsea Operation FPSO Commissioning ‐ Leak tests during night shif tF F 5 Lines SURF SURF GEP Dewatering / Packing F F 6 Lines No activities in turret due to SURF activity / hydrotest / leak test / well opening / mooring retensioningF F 7 Lines FPSO FPSO hook‐up /Tie‐in activity F F 8 Lines (*) Activity performed during hook ‐up (no tension) phase. Timing subjected to site adjustementsF F 9 Lines SUBSEA Subsea CommissioningF F ROV l ine integrity surveyF F F F ROV l ine integrity survey Dive support
F F F F ROV l ine integrity survey Dive support I tube cover rem I tube cover remF F F F RFHU I tube cover rem I tube cover rem Riser prep
F F F I tube cover rem I tube cover rem I tube cover remF F FF F FF F F I tube cover rem I tube cover rem I tube cover rem Riser prepF F F I tube cover rem I tube cover rem I tube cover remF F FF F FF F F I tube cover rem I tube cover rem I tube cover rem Riser prepF F F I tube cover rem I tube cover remF F F SSIV tub precom (*)F F FF F F Riser prep Removal Umb headF F FF F FF F F F F F Umb E&I precom (*) Umb E&I precom (*)F F FF F F Riser prepF F FF F FF F FF F F Install Frame (*)F F FF F F Riser prep Pulling head removeF F FF F F 1F F FF F F 2F F FF F F Riser prep Gauging prep Gauging prep JB + TUB RTMS precom Umb E&I precom 3F F F E&I G&T + TUBF F F FO + TUB RTMS precom Umb E&I precom 1F F F E&I G&T + TUBF F F 2F F FF F F Riser prep FO + TUB RTMS precom 3F F F E&I G&T + TUBF F F FO + TUB PTMS network test F F F E&I G&T + TUBF F FF F FF F F Gauging prep Gauging prep Riser prepF F F E&I G&T + TUB INSTALL FRAME INSTALL FRAMEF F FF F FF F F Riser prep FO + TUB Removal Umb head JB INTALL JB INSTALLF F F TUBING E&I G&T + TUBF F F Note :F F F TopsidesF F F only F F F LTPsF F F Riser prep not shownF F FF F F Flushing FO + TUB E&I G&T +TUB 1F F F TUBING E&I G&T+ TUBF F F INSTALL FRAME (*) 2F F F
F FF F Flushing TUBING JB INTALL FO + TUB 1F F SURFF F SURF 2F F Global LT prep ESDV installation TUB HYDROTEST (Exclusion zone apply during the pressure test)F F SURF 3
F F F SURFF F F LTP 4F F F Spool installation Spool installation Riser prepF F F LTP 5F F F Spool installation Spool installation Spool installation TUB HYDROTEST (Exclusion zone apply during the pressure test)F F F LTP 6F F F E&I and tub conn(*)F F F 1F F F Spool installation Spool installation Riser prep TUBING RTMS E&I G&T FO + TUBF F F LTP 2F F F Spool installation Spool installation Torqueing Torqueing Torqueing TUB + FLUSHING RTMS E&I G&T FO + TUBF F F LTP 3F F F AVT (*) AVT (*) AVT (*) AVT (*)F F F 4F F FF F F LTP 5F F F AVT AVT AVT Riser prep TUB + FLUSHING RTMS E&I G&T FO + TUBF F F LTP 6F F F AVT (*) AVT (*)F F FF F F Riser prep Spool trial fit TUB HYDROTEST (Exclusion zone apply during the pressure test)F F F LTPF F F Torqueing ESDV installation Torqueing Spool trial fit Spool trial fit TUBING RTMS E&I G&T FO + TUBF F F LTPF F F E&I and tub conn(*)F F FF F F Gauging prep Riser prep TUB HYDROTEST (Exclusion zone apply during the pressure test)F F F LTPF F F E&I and tub conn. FLUSHING FO + PCS E&I G&T E&I G&T + TUBF F F LTPF F F AVT (*) E&I and tub conn(*)F F F
F F Spool installation AVT AVT FLUSHING FO + PCS E&I G&T E&I G&T + TUBF F LTPF F Torqueing Spool trial fit Spool trial Fit Flushing TUBING SUPPORTS FO + PCS E&I G&T E&I G&T + TUBF F LTPF F Spool trial fit Spool trial Fit Spool trial fit TUBING FINAL CON FO + PCS E&I G&T E&I RFC Insp. + TUBF F LTPF F E&I and tub conn. RACS tubing TUBING FINAL CON Gauging prep 1F F LTPF F E&I and tub conn. RACS tubing 2 1F F LTP
F Annulus vent tubing leak test prep 3 2F SURFF SURF 3
LTPE&I and tub conn. Gauging prep Gauging prep JB + TUB FO + PCS E&I G&T TUBING 4
LTPE&I and tub conn. DOP INSTALL FO + PCS E&I G&T TUBING 5
LTPLeak test prep ESDV + Actuator 6
Leak test (incl. Subsea network) LTP
ESDV + Actuator 7SURFSURFSURF
RACS tubing ESDV installation DOP REMOVE ScaffoldingLTP
1LTP
Leak test prep Spool installation Spool installation Spool Installation 2SURFSURF 3LTP
Gauging prep Spool installation Support install. Spool installation ESDV Panel Install Spool Installation 4LTP
Spool installation Torqueing TUB HYDROTEST 5LTP
LTPLeak test prep Torqueing Torqueing Torqueing TUB HYDROTEST
LTP
LTPSpool installation Spool installation E&I and tub conn. PFP ESDV Tub + E&I TUB + FLUSHING
LTPSpool installation Spool installation E&I and tub conn. PFP ESDV Tub + E&I TUB + FLUSHING
LTP
Torqueing Torqueing E&I G&T + TUB ESDV Tub + E&I TUBING 1 1LTP
RACS tubing E&I and tub conn. TUB HYDROTEST 2 2LTP
Annulus vent tubing E&I and tub conn. ESDV Tub + E&I PCS E&I G&T FLUSHING 3 3LTP
PFP E&I G&T + TUB PCS E&I G&T FLUSHING 4 4LTP
5 5LTP
PFP RACS tubing E&I G&T + TUB Leak test prep PCS E&I G&T TUB SUPPORTS 6 6LT ( incl. Subsea network) SURF
PFP RACS tubing E&I G&T + TUB TUBING TUB FINAL CON. SURF 7LTP
PFP Annulus vent tubing E&I G&T + TUB TUBING TUB FINAL CON. 8LTP
PFP PFP E&I G&T + TUB TUBING 9LTP
PFP PFP FO + TUB TUB HYDROTEST 10LTP
PFP FO + TUB FLUSHING 1 11LTP
PFP FO + TUB FLUSHING 2 12LTP
PFP FO + TUB 3 13LTP
PFP FO + TUB PFP 4 14LTP
PFP E&I RFC Insp.+ TUB PFP 5 15LTP
PFP TUB PFP 6 16LTP
1 17LTP
PFP TUB PFP 2 18LTP
PFP TUB HYDROTEST 19LTP
PFP TUB HYDROTEST 4 20LTP
PFP TUB HYDROTEST 5 21LTP
22TUB HYDROTEST
23
24
25
TUB + FLUSHING 1TUB + FLUSHING
TUB 2TUB TEST FLUSHING PFP 3 FLUSHING
TUB SUPPORTS PFP 4TUB FINAL CON.TUB FINAL CON. 5
PFP 6PFP
7
1 8
2 9
3 10
4 11
5 12
6 13
14
15
16
D+71
CAN M
anifo
lds
Commiss
ionn
ing
Chem
ical lines dew
atering
Hybrid loop thermal performance test
Hybrid loop warm up
MOSTARDA Well opening
CANELA SU
BSEA
X‐TRE
E SO
FTWAR
E TEST
S
TIMELIN
E
D+108
D+109
D+110
D+111
D+112
D+113
D 114
D+97
D+98
D+99
D+100
D+101
D+102
D+103
D+104
D+89
D+90
D+91
D+92
D+105
D+96
D+79
METHANOLBUNKERING
Circulation
MOS SU
BSES X‐TRE
E SO
FTWARE
TESTS
D+106
D+107
D+87
D+70
Circulation
D+72
D+73
D+74
D+75
D+76
D+77
D+78
D+93
D+94
D+95
D+80
D+81
D+82
D+83
D+84
D+85
D+86
D+88
MeOH Dewat
Diesel
Hybrid loop thermal performance test
Hybrid loop warm up
CANELA Well opening
X TR
EE COMMISSIONNING
D+61
D+62
D+63
D+64
D+65
D+66
D+67
D+68
D+69
D+52
D+53
D+54
D+55
D+56
D+57
D+58
D+59
D+60
D+43
D+44
D+45
D+46
D+47
D+48
D+49
D+50
D+51
D+34
D+35
D+36
D+37
D+38
D+39
D+40
D+41
D+42
D+25
D+26
D+27
D+28
D+29
D+30
D+31
D+32
D+33
D+16
D+17
D+18
D+19
D+20
D+21
D+22
D+23
D+24
D+7
D+8
D+9
D+10
D+11
D+12
D+13
D+14
D+15
D+0
D+1
D+2
D+3
D+4
D+5
D+6
D+63
D+64
MOS Man
ifolds
EFL conn
ection
Diving
Hook up (#15) Downline
Downline Hook up (#16)
D+8
Hook up (#9)
Diving
Diving
Diving
D+9
D+10
MOORINGFINAL SURVEY
(INCL. H LINKS)
MOORINGLINES
RE‐TENSION(RISK ON PLANNING ‐3
DAYS)
MeOH Dewat
Chem
ical lines dew
atering
Gauging
Spool trial fitSpool trial fit
Diving
D+62
MOS X TR
EE
CAPS & EFLs
MOS Man
ifolds
Commiss
ionn
ing
D+47
D+48
D+49
D+50
D+51
D+52
Downline Hook up (#10)
Gauging
Umb tub precom
Moor. Installatio
n Ve
ssel
Surf IV
‐ Scan
di Africa
DSV ‐ XXX
X
Subsea FOPS
Com
m
LCV BO101
SURF LCV
ops
BE80
5
Tug ‐ m
oorin
g
Tug ‐ h
eading
GaugingGaugingD+23
D+14
D+15
D+16
D+17
D+18
D+19
D+20
D+21
D+22
D+1
D+2
D+3
D+4
DSV MOORING & DIVING PREPARATION
INTE
RIM
MOB
Umb E&I precom
SSIV M
odule
EFL SS con
nection
D+99
D+100
D+101
D+102
D+103
D+104
D+105
D+106
D+107
D+90
D+91
D+92
D+93
D+94
D+95
D+79
D+72
D+46
TOPSIDES COMMISSIONNING
METHAN
OL
DEAD
OIL
FLAR
E SYSTEM
OIL TREATM
ENT
SEA WATER
TREA
TMEN
T an
d WAT
ER IN
JECT
ION
GAS COMPR
ESSION
GAS
DEH
YDRA
TION &
TEG REG
EN.Leak Test Slots
in Turret
SURF / SUBSEA / STARTUP
EFL CO
NNEC
TIONS
SOFTWAR
E TE
STS
SUBS
EA M
ANIFOLD
S CO
MM
CHEM
ICAL LINES
DEW
ATER
ING
MET
HANO
L LINES
DEW
ATER
ING
PROD LO
OP
DEW
ATER
ING W
ITH
DIESEL
D+44
D+65
SUBSEA
X‐ TRE
ES
COMM
D+5
D+6
D+7
Umb tub precom
DSV MOORING & DIVING PREPARATION
Hook up (#3) Downline
Umb tub precom
Hook up (#6) Downline
MOS+LOU WI lines dewatering
WI service test
Gauging
Dewatering
PLR Removal SS
OPEN PLEM valves
Global leak test
Leak test
Gauging
Leak test preparation
Global leak test prep
PLR Removal SS
Gauging Gauging
Downline
D+30
D+34
D+35
D+36
D+37
D+38
D+39
D+40
Downline
Downline
D+73
D+74
D+75
D+76
D+77
D+66
D+67
D+43
Gauging
Leak testD+54
D+55
D+56
D+57
Diving
Leak test (incl. Subsea network)
D+41
D+42
PLR Removal SS
D+111
D+112
D+113
Leak test (incl. Subsea network)
WI service test
CAN WI lines dewatering
D+78
D+80
D+96
D+97
D+98
D+81
D+82
D+83
D+84
D+85
D+86
D+87
D+88
D+89
D+110
CdFWorking Draft
revision 211 Oct 2018
Canela Cluster Mostarda Louro Cluster East Cluster
Hook up (#2)
Diving
Diving
Hook up (#1)Downline
Dummy Spool Removal
Dummy Spool Removal
Dummy Spool Removal
Downline
D+0Dummy Spool
RemovalDummy Spool
RemovalDummy Spool
RemovalDummy Spool
Removal
SURF / FPSO Coordination for Turret activities
TIMELIN
E
Global leak test prep
DELUGE (TBC) DELUGE (TBC)
BLACK START BLACK START BLACK START
Umb tub precom
Downline Hook up (#4)
Diving
Marine Coordination
D+70
D+71
Leak test preparationLeak test (incl. Subsea network)
Downline Hook up (#8)
PLR Removal SS
Leak test
Global leak test prep
Hook up (#11)
Global leak test Global leak test
Diving D+32
D+33
D+45
D+68
D+53
D+59
D+60
D+61
D+24
D+25
D+26
D+58
Diving
Downline
Umb tub precom
Leak test preparation
Hook up (#13)
Diving
DELUGE (TBC)
Umb E&I precomDiving
Hook up (#5) Downline
D+13
Diving
Hook up (#7)
D+12
D+27
D+31
D+28
D+29
D+11
D+69
Downline
Diving
Global leak test
Diving
Downline
Hook up (#12)
Spool trial fitSpool trial fit
Diesel
CANELA X TR
EE
CAPS & EFLs
LOURO
X TRE
E CA
PS & EFLs
D+109
Umb E&I precom
Hook up (#14)
X TR
EE COMMISSIONNING
LOURO
Man
ifolds
EFL conn
ectio
nCA
N M
anifo
lds
EFL conn
ectio
n
MOS SU
BSEA
MANIFOLD
S SO
FTWAR
E TEST
SCA
NELA SU
BSEA
MANIFO
LDS
SOFTWAR
E TEST
SLO
URO
SUBS
EA M
ANIFOLD
S SO
FTWARE
TESTS
Mobilisation of Dewatering Equipment
(on P1 and S1)
Final Rig‐up(on P1 and S1)
+functional testing
equipement(on P1 and S1)
Packing
Load and launch Pig Train
GEP inerting
LOURO
SUB
SEA X‐TR
EE
SOFTWARE
TESTS
LOU M
anifo
lds
Commission
ning
Chem
ical line
s de
watering
C irculation
NG
MeOH Dewat
Di lD 114
D+108
RFC
RFC
RFC
RFC
DSV MooringAlongside + Turret Prep
PSV AlongsideUnloading SURF material
RFC Partial E&I
MOORING 9 LINES
Ready forMethanol bunkering
Ready forFirst Oil
Ready forDiesel Circulation
No activities during MeOH first circulationNo activities during MeOH first circulationNo activities during MeOH first circulation
No activities during Diesel first circulationNo activities during Diesel first circulationNo activities during Diesel f irst circulation
MOSTARDA HOOK‐UP START UP MIN REQUIREMENTS COMPLETEDDiving Final Survey
Tug Demobilisation
No activity in the turret during Mostarda startup activities No activity in the turret during Mostarda startup activities No activity in the turret during Mostarda startup activities
RFC Partial E&I
No activity in the turret during Canela startup activities No activity in the turret during Canela startup activities No activity in the turret during Canela startup activities
No activities during MeOH first circulationNo activities during MeOH first circulationNo activities during MeOH first circulation
No activities during Diesel first circulationNo activities during Diesel first circulationNo activities during Diesel f irst circulation
RFC Partial E&I
Topsides ready forWater Injection
WARNINGTHE TOPSIDES READINESS DATES ARE GIVEN IN LINE WITH THE "TOPSIDES COMMISSIONNING ROAD MAP" . DATES / DURATIONS ARE TO BE
CONFIRMED
WARNING !!THE METHANOL
BUNKERING WINDOW IS TO BE CONFIRMED
WARNING !!SHALL MOORING LINE RETENSIONNING BE
REQUIRED IT WILL IMPACT ALL TURRET ACTIVITIES
FOR SURF : PLEASE COMMENT ON THE DURATION OF DEWATERING AND PACKING ACTIVITIES KNOWING THAT THE GAS EXPORT TIE‐ IN IS ~ 5 KM AWAY AS COMPARED TO ~50 KM ON NORTE
NOTE : DECK SPACE STUDY TO BE PERFORMED TO CONFIM THEFEASEABILITY OF THE EARLY MOBILISATION OF THE DEWATERING SPREAD.
DATE TBC
SUBSEA HPUto be ready (AKER)
LINK TO SUBSEA SCOPE
Mob FPSO Leak Test Spread
No activities during Diesel first circulationNo activities during Diesel first circulationNo activities during Diesel first circulation
No activities during MeOH first circulationNo activities during MeOH first circulationNo activities during MeOH first circulation
!
SURF / SUBSEA COM TO REVIEW THE EFLs SCOPE DESCRIPTION /
DURATION
!IN CASE OF ANTICIPATEDDIESEL CIRCULATION THE CASE OF LIFTING THE LOURO SPOOLS ABOVE THE MOSTARDA ONES FULL OF HYDROCARBON WILL HAVE TO BE ADRESSED FROM HSE POINT OF VIEW
Level 1Safest de-riskedsequence
Quickest Hook-Up ever for TOTAL
0,8 0,80,4 0,4 0,5 0,3
0,90,3
1,0
4,13,5
2,5
3,92,9
3,9
4,1
3,5 2,4
0,0 months
1,0 months
2,0 months
3,0 months
4,0 months
5,0 months
Project #1 Project #2 Project #3 Project #4 Project #5 Project #6 Project #7 Project #8 KAOMBO N
FPSO/FPU offshore timing comparison
Hookup & Commissioning
Mooring
26
II – Approach and Relationship
FPSO moving target : « give a chance to chance » with no pressure !!unlocking L2 critical path to enable earlier FPSO Access
100% strike with the “Plan B”!
Optimistic scenario achieved !
FPSO Access 26th Jan. 2019
25.000 Fruit Trees
CO2 Offset initiative 50/50 funding with CPY Negative Float in Sept 2018
27
KAOMBO : An « Iconic » Subsea Project
I – Introduction
II – Challenging Development
III – Approach & Relationship
IV – Kaombo Take Away
28
Kaombo Take Away: a part of the recipe!
Interfaces
Digitalisation for Material Management
Agility for Plan « B »
Governanceand mindset…
Amongst other 1.000.000 Lessons Learned…
EngineeringProcurement
Fabrication
Installation
SPS