S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at...

53
S.P. 2710 - 47 TH 65 (3rd Avenue Bridge) Industry Informational Meeting October 31, 2017

Transcript of S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at...

Page 1: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

S.P. 2710-47 TH 65 (3rd Avenue Bridge)Industry Informational Meeting

October 31, 2017

Page 2: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

o Introductions

o Disclaimers

o Ground Rules

o Project Overview

o Consultant Contracts

o CMGC RFP

o CMGC Processes

o Conflict of Interest

o DBE Opportunities

o Questions

Outline

Page 3: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Introductions

• MnDOT Project Manager: Christian Hoberg

• MnDOT Construction Project Manager: Timothy Nelson

• Our job is to ensure all proposers have the same information and to partner with the successful CMGC team and consultants.

11/6/2017 3

Page 4: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Introductions

11/6/2017 4

MnDOT

• CMGC Program Manager: Kevin Hagness

• Bridge Office Project Manager: Keith Molnau

FHWA

Timothy Anderson, MnDIV Bridge Engineer

City of Minneapolis

Page 5: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Disclaimers

• This presentation will be posted on-line at

http://www.dot.state.mn.us/const/tools/const-manager-

general-contractor.html

11/6/2017 5

Page 6: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Disclaimers

What is discussed today is informational only, meant to assist proposers in pursuit of contracting opportunities on this project.

The ultimate RFP requirements are included in the final posted documents. Proposers are responsible for following the final RFP(s)

If there are any discrepancies, submit a clarification request.

11/6/2017 6

Page 7: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Ground Rules

As per the CMGC RFP:

• Christian Hoberg is the Single Point of Contact.

• Each Proposing team needs to identify a S.P.O.C.

11/6/2017 7

Page 8: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Project Overview - Location

11/6/2017 TH 65 (3rd Ave Bridge) over Mississippi River | (Google Map) 8

Page 9: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Project Goals

oRedeck and rehabilitate the bridge to achieve a 50-year

design life.

oComplete the project within budget.

oMinimize bridge closure to less than 24 months.

11/6/2017 TH 65 (3rd Ave Bridge) over Mississippi River | mndot.gov/ 9

Page 10: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Project Goals

• Develop a design that meets Secretary of Interior

Standards for Treatment of Historic Properties, in order

to avoid an adverse effect per Section 106 of National

Historic Preservation Act, and Section 4(f) use.

• Minimize impacts to stakeholders (local community,

historic district, parks, businesses) and the

environment, (protected and endangered species, the

river, park land, and properties to the project)

11/6/2017 TH 65 (3rd Ave Bridge) over Mississippi River | mndot.gov/ 10

Page 11: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Project Goals

11/6/2017 TH 65 (3rd Ave Bridge) over Mississippi River | mndot.gov/ 11

• Build a professional and collaborative project team

among the owner, designer, and contractor using

the CMGC delivery method.

Page 12: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Historic Bridge Background/Process

One of MnDOT’s 24 bridges selected for long term preservation

Must comply with Section 106 of the National Historic Preservation Act of 1966, and Section 4(f) of U.S. Dept. of Transp. Act of 1966

Listed on the National Register of Historic Places

Bridge 2440 – Historic Bridge Management Plan

Page 13: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Bridge 2440 – Historic Bridge Management Plan

Historic Bridge Background/Process

Page 14: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Bridge 2440 – Historic Bridge Management Plan

Historic Bridge Background/Process

Page 15: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Historic Bridge Background/Process

Bridge 2440 – Historic Bridge Management Plan

Page 16: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Bridge 2440 – Historic Bridge Management Plan

Historic Bridge Background/Process

Page 17: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Bridge 2440 – Background

• Originally constructed 1917

• 1939 rehabilitation

• Replaced sidewalks

• Replaced balustrade railing with art-deco metal railing

• Replaced original ornamental lights with highway style fixtures

• 1979 rehabilitation

• Replaced spandrel cap beams, pier caps, portions of spandrel columns, approach spans, abutments, approach piers, beam spans, raised grade with new bridge deck, added traffic barrier

• Original/remaining concrete repaired

• Ornamental railing rehabilitated

Page 18: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Bridge 2440 – Background

1979 Rehabilitation

Arch Pier Cap Replacement

Page 19: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Bridge 2440 – Background

19

• Spandrel Cap Replacement

Page 20: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Bridge 2440 - Background

Additional Past Projects:

• 2003 Expansion Joint Reconstruction, shotcrete piers

• 2014 Foundation Repair Project

• Bridge 2440 Third Ave Bridge – Summary Engineering Report, March 5, 2015 (with Appendices)

• Includes Geological Summary & Background Information

• Pier 5 Investigation for Foundation Repairs

• 1968 Bridge Inspection Report

• Other historic information

Page 21: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Project Background Information on ftp site

1 Br 2440 Summary Engineering Report (HDR)

1b-1f Series: 2014 Foundation Repair (Plans Specs Reports)

2.0-2.2b Series: Inspection Reports

3.0-3.3 Series: Structure Inventory Reports

4a-4e Series: Underwater Inspection Reports

5 Bridge Management Plan

11/6/2017 TH 65 (3rd Ave Bridge) over Mississippi River | mndot.gov/ 21

Page 22: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Project Background Information on ftp site

• 6a-6c Series: 2003 Expansion Joint Reconst. and Shotcrete

• 7 Bridge Utility Files (1998)

• 8a, 8b: 1979 Rehabilitation Plans, Shop Drawings (155,127)

• 9 Br 2440 Original Plans (MnDOT Bridge Office Files) (298)

• 10 Foundation Memo (For current project)

• 11 Br. 2440 Orig. Plans City of MPLS Files (81 sheets)

11/6/2017 TH 65 (3rd Ave Bridge) over Mississippi River | mndot.gov/ 22

Page 23: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Consultant Contracts for Current Project

Phase 1: (Scoping/Inspections/Reports)

HNTB Corporation (Lead Design Engineer of Record)

Wiss Janney, Elstner, Inc. (WJE): Bridge Inspections

Olson & Nesvold Engineers, P.S.C

Dan Brown Associates

Multi Vista, and Survey Solutions

Hess Roise Historical Consultants – Managed by MnDOT CRU

PEER REVIEW Contract (Scope of Work: Dec 1, 2017)

Phase 2 (Begin Preliminary Plans) – June 2018

Phase 3 (Final Design) – August 2018 – August 2019

23

Page 24: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Phase 1: (Scoping/Inspections/Reports)

• Deliverables

• Bridge 2440 Historic Features Report (complete)

• Bridge Inspection and Condition Evaluation Report (complete)

• Draft Bridge Rating Report (work-in-progress)

• Bridge Alternatives Feasibility / Rehabilitation Report (in progress)

• Final Bridge Rating Report (work in progress)

• Bridge Construction, Cost Estimates, Maintenance Projections, and Annualized Repair Cost Report (work in progress)

• LiDAR Report

Task 1: Project Management

Page 25: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Cross Section AlternativesBridge Closure/Staged Construction /ABC Alt.

11/6/2017 Optional Tagline Goes Here | mndot.gov/ 25

Page 26: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Access Considerations

26

Page 27: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Access Considerations

11/6/2017 TH 65 (3rd Ave Bridge) over Mississippi River | mndot.gov/ 27

Page 28: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Stakeholder Considerations

• Minnesota State Historic Preservation Office

• Minnesota Department of Natural Resources

• Minneapolis Public Works

• Minneapolis Traffic

• Minneapolis Park Board

• Minneapolis Bicycle and Pedestrian Advisory Boards

• Federal Highway Administration

• US Army Corp of Engineers

• XCEL Energy

• Federal Energy Regulatory Commission

• University of Minnesota

• Private Utilities carried by the structure

• Businesses

• Residents

• Roadway Users

11/6/2017 TH 65 (3rd Ave Bridge) over Mississippi River | mndot.gov/ 28

This project has a large and complex group of stakeholderswith whom the project will require coordination, including:

Page 29: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Project Challenges

29

Page 30: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

30

Table 2.1 - Procurement Schedule

Issue RFLOI September 1, 2017

Issue Draft CMGC RFP October 16, 2017

Issue CMGC RFP November 2, 2017

Project Informational Meeting November 2, 2017

Deadline for Proposers to Submit Requests

for Clarification on the RFPNovember 20, 2017

Responses to Requests for Clarification on

RFP IssuedNovember 22, 2017

Deadline for Proposers to Submit Proposal December 5, 2017

Interviews December 21, 2017

CMGC Contractor Selected December 22, 2017

Notice to Proceed – P/T Services Contract January 18, 2018

Page 31: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

31

One-step Qualifications-Based Request for Proposals (RFP)

Final CMGC RFP is currently advertised on MnDOT’s Consultant Services website: http://www.dot.state.mn.us/consult/notices.html

Thank you to those who submitted comments on the Draft CMGC RFP

Page 32: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

32

RFP Details:

Interviews

No Stipends

No Co-location

DBE Goal for Construction

No DBE Goal for CMGC P/T Contract

CMGC Team to develop a Subcontracting Plan - Includes approach to DBE

engagement and goal setting for the project

Page 33: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

33

A notification to Proposers has also been posted on MnDOT’s Consultant Services website to help Proposers identify what changed between the draft CMGC RFP and the final CMGC RFP.

In the event of any discrepancies between this document and the final CMGC RFP, the final CMGC RFP shall take precedent.

Page 34: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

34

Noteworthy changes from “Draft”

Section 2.1 – Proposals Due December 5, 2017

Sections 2.1 and 5.5 – Interviews December 21, 2017

Section 4.4.4.1 – Prior to Beginning Final Design (30% Design), the Project Manager position and Construction Manager position may be filled by the same person.

Section 4.4.5.3 – Bonding capability increased to $90 million.

Page 35: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

35

Communications

Chris Hoberg, Project Manager, is the sole MnDOT contact person for clarification requests, communications about the project, the RFP, and Proposal submittals.

Email: [email protected]

Page 36: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

36

Communications

CMGC programmatic questions shall be directed to Kevin Hagness, CMGC Program

Manager:

Email: [email protected]

Page 37: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

37

Proposal Delivery, Content, Format

Proposals shall not exceed 18 pages; not including cover letter, table of contents, section dividers, appendices, and required forms

Resumes for Key Personnel shall not exceed two pages per position

2-11x17 pages allowed for Project Experience Table

Page 38: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

38

Addendums and Clarifications

Proposers need to acknowledge all addendums and clarifications issued in their Proposals.

RFP Clarification Request Forms can be found on MnDOT’s CMGC website: http://www.dot.state.mn.us/const/tools/const-manager-general-contractor.html

Page 39: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

39

Mandatory Technical Interviews

Approximately one hour in length

No handouts or formal presentations

Will consist of set questions for all Proposers and clarification questions for each Proposer based on their Proposal

Will not be scored separately – will be used as additional information in support of, and to clarify, the information contained in the proposal

Questions will not be provided to Proposers in advance of the interview

Up to five representatives from Proposer’s team – must include PM, CM, and Lead Cost Estimator

Proposers must email CMGC PM to schedule an interview time

Page 40: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

40

CMGC Experience

Not required. Although CMGC experience can be valuable, there are other ways

proposer’s can demonstrate their ability to be successful in the CMGC process.

Page 41: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

41

Commitment of Key Personnel

Section 4.4.4.1 asks Proposers to identify other Key Personnel commitments and

how those will be managed to meet the commitments for this project.

Section 4.4.4.1 allows for two Key Personnel positions referred to as Project

Specialists that each Proposer considers key to the success of the project. These

positions are not defined by MnDOT, therefore, they could be support staff.

Page 42: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

42

Construction Services Fee

A Construction Services Fee fixed-markup percentage of 12% has been established in

the RFP.

Page 43: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

43

CMGC Estimating Process

Formal workshops for design review, risk, and cost estimating are anticipated to occur at the 30%, 60%, and 90% design milestones.

For each of these milestones, the cost estimates will include an Independent Cost Estimate (ICE), Owner’s/Engineer’s Estimate and the CMGC’s Opinion of Probable Construction Cost (OPCC).

Page 44: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

44

CMGC Price Proposal Validation

The Independent Cost Estimate (ICE) and Engineer’s Estimate (EE) will be used by MnDOT to validate the CMGC Contractor’s price proposal/bid.

Page 45: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC RFP

45

MnDOT CMGC Processes & CMGC Conflict of Interest Policy

Further information available on MnDOT’s CMGC website:

http://www.dot.state.mn.us/const/tools/const-manager-general-contractor.html

Page 46: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

ICE/EE Procurements

46

There will be one RFP advertised for two separate contracts for

the ICE and the Owner’s/Engineer’s Estimating services.

Page 47: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

ICE/EE Procurements

47

Scope of work for both contracts is very similar

production-based, contractor-style estimates at each of the design milestones

and at the price proposal/bid

schedule analysis and development at each of the design milestones and at the

price proposal/bid

Page 48: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

ICE/EE Procurements

48

Desired Skills

production-based, contractor-style estimating for bridge projects of similar size,

scope and complexity

schedule analysis and development for bridge projects of similar size, scope and

complexity

Relevant CMGC experience and an understanding of the CMGC process

Page 49: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

ICE/EE Procurements

49

Responder’s submission of a proposal is acknowledgement that

Responder may be assigned, at MnDOT’s discretion, the ICE or

the EE services contract.

Page 50: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

ICE/EE Procurements

50

Procurements Schedule

RFP scheduled to be advertised late November, 2017

3-week advertisement planned

ICE and EE under contract about the same time as the CMGC Contractor

Page 51: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC/ICE/EE Procurements

51

Continue to watch the MnDOT Consultant Services website for

procurement updates, clarifications, and addendums:

http://www.dot.state.mn.us/consult/notices.html

Page 52: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

CMGC/ICE/EE Procurements

52

If you have any questions, submit a written clarification request

to MnDOT’s Project Manager, Chris Hoberg, at:

[email protected]

Page 53: S.P. 2710-47 TH 65 (3rd Avenue Bridge) Industry ...•This presentation will be posted on-line at ... oRedeck and rehabilitate the bridge to achieve a 50-year design life. oComplete

Thank you again!

Christian Hoberg, Project Manager

[email protected]

53