    May 18, 2009 Ref:Mundra/001

    Dear Mr. Lakadawalla,

    Thank you for the enquiries about comparison study for Terminal Operating System for

    Mundra Port Container Terminal, India. We will be glad to make an official proposal

    after the scope of work and level of details are clarified. Could you, please, verify and

    confirm the following table containing scope of work and deliverables.

    Man-DaysVisits required Pages-In Report

    1 Developing Business Requirements for the Terminal 25 2 75

    Container Inventory

    Vessel Operation

    Gate InterchangeRail (Intermodal) Yard Operation

    Container Yard Operation

    EDI

    Billing

    Wireless Infrastructure

    Position Determination System (RFID, GPS, etc)

    2 Developing criteria and selection of potential vendors 2 6

    3 Selection of potential vendors and preparation Of RFP 15 45

    4 Technical Evaluation of the bids (GAP and SWAT Analysis) 15 1 45

    Functionality

    Handling Capacity

    5 Commercial Evaluation Of Bids (Total Cost Of Ownership) 15 45Licensing Cost

    Maintenance Cost

    Implementation Cost

    Hardware Cost

    Future Enhancements Cost

    6 Developing Selection Criteria 5 15

    7 Final Recommendations 5 1 15

    Total 82 4 246

    Modern Port Technologies Inc.

    Alexandre Goussiatiner, P.Eng, MSc, Owner

    1