Southern Nuclear Operating Company
ND-19-0152
Enclosure 2
Vogtle Electric Generating Plant (VEGP) Units 3 and 4
Presentation Material: Functional Arrangement (FA) ITAAC, FA System Package Examples – Closed
Meeting (Non - Proprietary)
(Enclosure 2 consist of 26 pages, including this cover page)
![Page 2: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/2.jpg)
Functional Arrangement (FA) ITAAC
FA System Package ExamplesClosed Meeting (Non - Proprietary)
February 14, 2019
ND-19-0152
Enclosure 2
Page 2 of 26
ONE TEAM. ONE VISION. ONE GOAL.
![Page 3: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/3.jpg)
2
Agenda
• Examples of FA ITAAC and Documentation
• System Safety Functions in Other ITAAC
ND-19-0152
Enclosure 2
Page 3 of 26
.. ~ Southern Nuclear A Georgia Power
Building the future of nuclear power in America
![Page 4: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/4.jpg)
3
FA Example #1 -WSS
• ITAAC 2.3.12.01:
• The “Design Description” in COL Appendix C section 2.3.12 provides a description of what the system does:
“The solid radwaste system (WSS) receives, collects, and stores the solid radioactive wastes received prior to their processing and packaging by mobile equipment for shipment off-site.”
ND-19-0152
Enclosure 2
Page 4 of 26
![Page 5: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/5.jpg)
4
Example #1 -WSS
• The major system components to accomplish this are included in Table 2.3.12-2 (there is no Tier 1 Figure for WSS):
ND-19-0152
Enclosure 2
Page 5 of 26
![Page 6: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/6.jpg)
5
Example #1 -WSS List of Items
• Using guidance from ND-RA-001-012, these Two (2) Items represent the scope of the WSS Walkdown
a,c
ND-19-0152
Enclosure 2
Page 6 of 26
![Page 7: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/7.jpg)
6
Example #1 -WSS Field Sketcha,c
ND-19-0152
Enclosure 2
Page 7 of 26
![Page 8: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/8.jpg)
7
FA Example #2 -PXS
• ITAAC 2.2.03.01:
• The “Design Description” in COL Appendix C section 2.2.3 provides a description of what service the system is intended to provide:
“The passive core cooling system (PXS) provides emergency core cooling during design basis events. The PXS is as shown in Figure 2.2.3-1 and the component locations of the PXS are as shown in Table 2.2.3-5.”
Table 2.2.3-4
Inspections, Tests, Analyses, and Acceptance Criteria
No. ITAAC No. Design Commitment Inspections, Tests, Analyses Acceptance Criteria
158 2.2.03.01 1. The functional arrangement of the PXS is
as described in the Design Description of this
Section 2.2.3.
Inspection of the as-built system will
be performed.
The as-built PXS conforms
with the functional arrangement
as described in the Design
Description of this Section 2.2.3.
ND-19-0152
Enclosure 2
Page 8 of 26
![Page 9: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/9.jpg)
8
Example #2 -PXS
• The major system components to accomplish this shown in Figure 2.2.3-1 (Sheet 1):
ND-19-0152
Enclosure 2
Page 9 of 26
![Page 10: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/10.jpg)
9
Example #2 -PXS
• The major system components to accomplish this shown in Figure 2.2.3-1 (Sheet 2):
ND-19-0152
Enclosure 2
Page 10 of 26
![Page 11: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/11.jpg)
10
Example #2 -PXS
• The major system components to accomplish this are included in Table 2.2.3-5:
ND-19-0152
Enclosure 2
Page 11 of 26
![Page 12: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/12.jpg)
11
Example #2 -PXS List of Items
Using guidance from ND-RA-001-012, this LOI is the scope of the PXS Walkdown (Four (4) of 103 Line Items Shown a,c
ND-19-0152
Enclosure 2
Page 12 of 26
![Page 13: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/13.jpg)
12
Example #2 -PXS Field Sketch (One of Five (5))a,c
ND-19-0152
Enclosure 2
Page 13 of 26
![Page 14: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/14.jpg)
13
FA Example #3 -DWS
• ITAAC 2.3.14.01:
• The “Design Description” in COL Appendix C section 2.3.14 provides a description of what the system does:
“The demineralized water transfer and storage system (DWS) receives water from the demineralized water treatment system (DTS), and provides a reservoir of demineralized water to supply the condensate storage tank and for distribution throughout the plant.”
ND-19-0152
Enclosure 2
Page 14 of 26
![Page 15: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/15.jpg)
14
Example #3 -DWS
• ITAAC 2.3.14.01 (Continued):
• The “Design Description” in COL Appendix C section 2.3.14 goes on to provide additional description of what the DWS does:
“Demineralized water is processed in the DWS to remove dissolved oxygen. In addition to supplying water for makeup of systems which require pure water, the demineralized water is used to sluice spent radioactive resins from the ion exchange vessels in the chemical and volume control system (CVS), the spent fuel pool cooling system (SFS), and the liquid radwaste system (WLS) to the solid radwaste system (WSS)”
ND-19-0152
Enclosure 2
Page 15 of 26
![Page 16: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/16.jpg)
15
Example #3 -DWS
• The major system components to accomplish this are included in Table 2.3.14-3 (there is no Tier 1 figure for DWS):
• Because there is no Tier 1 figure for DWS and limited components listed on Table 2.3.14-3, four additional components were added per procedure ND-RA-001-012 to address the design description.
ND-19-0152
Enclosure 2
Page 16 of 26
![Page 17: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/17.jpg)
16
Example #3 - DWS List of Items
• Using guidance from ND-RA-001-012, this LOI is the scope of the DWS Walkdown (3 of 20 Line Items shown)
a,c
ND-19-0152
Enclosure 2
Page 17 of 26
![Page 18: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/18.jpg)
17
Example #3 -DWS Field Sketch (One of Five (5))a,c
ND-19-0152
Enclosure 2
Page 18 of 26
![Page 19: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/19.jpg)
18
System Safety Functions in Other ITAACND-19-0152
Enclosure 2
Page 19 of 26
![Page 20: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/20.jpg)
19
System Safety Functions in Other ITAAC
ND-19-0152
Enclosure 2
Page 20 of 26
![Page 21: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/21.jpg)
20
System Safety Functions in Other ITAAC
ND-19-0152
Enclosure 2
Page 21 of 26
![Page 22: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/22.jpg)
21
System Safety Functions in Other ITAACND-19-0152
Enclosure 2
Page 22 of 26
![Page 23: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/23.jpg)
22
System Safety Functions in Other ITAAC
ND-19-0152
Enclosure 2
Page 23 of 26
![Page 24: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/24.jpg)
23
System Safety Functions in Other ITAAC
ND-19-0152
Enclosure 2
Page 24 of 26
![Page 25: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/25.jpg)
24
System Safety Functions in Other ITAACND-19-0152
Enclosure 2
Page 25 of 26
![Page 26: Southern Nuclear Operating Company ND-19-0152Southern Nuclear Operating Company ND-19-0152 Enclosure 2 Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Presentation Material:](https://reader035.fdocuments.us/reader035/viewer/2022062506/5f0d71ff7e708231d43a6456/html5/thumbnails/26.jpg)
25
Questions
ND-19-0152
Enclosure 2
Page 26 of 26