SOUTHERN CALIFORNIA EDISON SM Local Capacity Requirements (LCR) RFO for New Resources and Other SCE...

7
SOUTHERN CALIFORNIA EDISON SM Local Capacity Requirements (LCR) RFO for New Resources and Other SCE Solicitations Stu Hemphill September 26, 2013

Transcript of SOUTHERN CALIFORNIA EDISON SM Local Capacity Requirements (LCR) RFO for New Resources and Other SCE...

Page 1: SOUTHERN CALIFORNIA EDISON SM Local Capacity Requirements (LCR) RFO for New Resources and Other SCE Solicitations Stu Hemphill September 26, 2013.

SOUTHERN CALIFORNIA EDISON

SM

Local Capacity Requirements (LCR) RFO for New Resources and Other SCE

Solicitations

Stu Hemphill

September 26, 2013

Page 2: SOUTHERN CALIFORNIA EDISON SM Local Capacity Requirements (LCR) RFO for New Resources and Other SCE Solicitations Stu Hemphill September 26, 2013.

SOUTHERN CALIFORNIA EDISON

SM

Page 2

SCE’s LCR Procurement Authorization

• D.13-02-015 orders SCE to procure the following resources by 2021 to meet LCR need due to the expected retirement of OTC units

– Authorizes bilaterally negotiated AB1576 “cost of service” PPAs

– West LA Basin gas-fired generation beyond minimum consistent with the preferred loading order

– Moorpark Sub-Area has no specific technology requirements (consistent with loading order)

West LA Sub-Area Moorpark Sub-Area:

•215-290 MW in Ventura/Big Creek

Page 3: SOUTHERN CALIFORNIA EDISON SM Local Capacity Requirements (LCR) RFO for New Resources and Other SCE Solicitations Stu Hemphill September 26, 2013.

SOUTHERN CALIFORNIA EDISON

SM

Page 3

RFO Schedule

Timeline Event

September 12, 2013 RFO documents issued

December 2, 2013Deadline to submit Non-binding Notice of Intent to Offer

December 16, 2013Deadline to submit Indicative Offer and completed Offer Submittal Package

January 30, 2014 Shortlist notification

May 22, 2014Deadline to complete negotiations of Agreement(s)

May 29, 2014 5:00 Deadline to submit Final Offer

June 26, 2014Last date for notification of successful Offers and to sign Agreements

• SCE will run a two round RFO process

• Bidders Conference will likely occur on October 16– Check the RFO website for details

Page 4: SOUTHERN CALIFORNIA EDISON SM Local Capacity Requirements (LCR) RFO for New Resources and Other SCE Solicitations Stu Hemphill September 26, 2013.

SOUTHERN CALIFORNIA EDISON

SM

Page 4

LCR RFO Commercial Highlights

• SCE has prepared seven pro-forma contracts:– Energy Efficiency – Demand Response– Energy Storage– Resource Adequacy

• Pro forma contracts are intended to capture the majority of the offers, but can be customized to meet any offer

– SCE regularly negotiates the terms of its pro forma contracts

• LCR RFO documents can be found at on.sce.com/lcrrfo

– Questions should be directed to [email protected]

– Renewable– Combined Heat and Power– Conventional Gas-Fired

Page 5: SOUTHERN CALIFORNIA EDISON SM Local Capacity Requirements (LCR) RFO for New Resources and Other SCE Solicitations Stu Hemphill September 26, 2013.

SOUTHERN CALIFORNIA EDISON

SM

Page 5

LCR Challenges

• Geographic constraints – Western L.A. basin

• Timing – resources need to be available in 2021

• Availability of 50 MW of energy storage?

• Availability of emissions permits

• Resource counting

Page 6: SOUTHERN CALIFORNIA EDISON SM Local Capacity Requirements (LCR) RFO for New Resources and Other SCE Solicitations Stu Hemphill September 26, 2013.

SOUTHERN CALIFORNIA EDISON

SM

Page 6

Highlights of SCE’s Track 4 LTPP Testimony

CPUC’s LTPP Track 4 is intended to identify incremental need due to the closure of SONGS

•SCE has requested 500 MW of initial additional authority that would be procured through its LCR RFO

– The remainder of any Track 4 procurement authorization provided to SCE would be purchased in a separate solicitation

•SCE has proposed to develop sites for 500 MW of contingent generation to backstop its proposed Preferred Resource Pilot

– If needed, these contingent generation projects would be secured from the market through a competitive process for IPP construction and ownership under a PPA with SCE

•SCE has also proposed to contract for “options” for up to 1000 MW of generation as a backstop for transmission development and LTPP planning assumptions not materializing

– SCE would sign PPAs with a termination right for SCE that would cover the IPP’s project development costs

Page 7: SOUTHERN CALIFORNIA EDISON SM Local Capacity Requirements (LCR) RFO for New Resources and Other SCE Solicitations Stu Hemphill September 26, 2013.

SOUTHERN CALIFORNIA EDISON

SM

Page 7

SCE Solicitations

Solicitation Timeline

RAM 5/6/13 – 9/30/13 (similar schedule in 2014)

RA RFO 8/22/13 – 9/27/13

SPVP 9/4/13 – 2/3/14

CHP RFO 9/12/13 – 4/1/14

LCR RFO 9/12/13 – 6/24/14

CAM Energy Auctions Auctions close 10/21/13 (El Segundo & Walnut)

Re-MAT Bi-monthly starting 11/1/13

RPS RFO Expected 12/13 – 9/14

GHG Offset RFO Anticipated Q1, 2014

All Source RFO Anticipated 7/14 – 10/14

Transmission RFO Anticipated Q3, 2014

Energy Storage RFO Anticipated 12/14