Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other...
Transcript of Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other...
![Page 1: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/1.jpg)
Southern California Edison Energy Storage Activities
Brief Overview
Ignacio Sanchez So. Cal. Edison Engineer - Advanced Energy Storage
12/08/2016
![Page 2: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/2.jpg)
•14 million customers - one of the largest utilities in US
•50,000 square miles service territory
•125+ years of service
•23,000 MW Peak
Southern California Edison
2 Southern California Edison
![Page 3: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/3.jpg)
Background
• California Public Utility Commission (CPUC) Energy Storage Decision
‒ Requires SCE to procure 580MW of energy storage by 2020 and gives SCE the opportunity to own up to 290MW
• SCE Approach ‒ Leverage RFO procurement process
• Provide market services
• Provide distribution capital deferral
‒ Enhance learning and understanding through targeted pilot programs • Support distribution reliability
• Facilitate preferred resources integration
• Investigate microgrids
Southern California Edison 3
![Page 4: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/4.jpg)
Energy Storage Decision D 13-10-040 Requires SCE to procure 580MW of energy storage by 2020 and gives SCE the opportunity to own up to 290MW
Energy Storage Requirements (MW)
Storage Grid Domain (Point of Interconnection)
2014 2016 2018 2020 Total Total
Range
Transmission 50 65 85 110 310 62 - 458
Distribution 30 40 50 65 185 37 - 433
Customer 10 15 25 35 85 85 - 170
Total 90 120 160 210 580 580
Flexibility:
• Up to 50% of total procurement goal can be Utility Owned
• Up to 80% of target MWs can be: – Shifted between Transmission and Distribution domain (only) – Deferred (not past 2020) with a showing of unreasonableness
– Up to 200% of target Customer domain MWs can be counted
• All projects must be installed and operational by 2024
Southern California Edison 4
![Page 5: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/5.jpg)
115
70
25
0
50
100
150
200
250
Transmission Distribution Customer
MW
SCE 2016 Storage Portfolio
2016 ES Procurement Status
Southern California Edison 5
Authorized to be counted towards 2016 targets
2016 procurement target (cumulative) 85 MW excess
capacity
Currently above targets
Excess customer domain capacity
SCE LCR RFO SCE 2014 ES RFO Customer Service Programs
Other (e.g., Pilots & Demos)
Transmission 100 MW - - -
Distribution - 16 MW - 16 MW
Customer 161 MW - 54 MW 11 MW
SCE Procurement Activities
(All numbers rounded to the nearest Megawatt)
![Page 6: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/6.jpg)
SCE Energy Storage Efforts
6 Southern California Edison
Technical Evaluation
• Laboratory Evaluation
• Demos & Pilots
Strategic Planning
• ES Business Cases
• Regulatory Compliance
Simulation & Modeling
• Where?
• What size?
![Page 7: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/7.jpg)
SCE ES Technical Activities
• Storage Technology Laboratory Evaluation ‒ Validate storage technology performance
‒ Create degradation models to optimize system operation (extend life, improve business case)
• System or Sub-system Laboratory Testing ‒ Validate system integration (from a safety and
operational performance perspective)
• Field Demonstration and Pilots ‒ Refine deployment, connection and operation processes
‒ Validate system performance and reliability in the field
Southern California Edison 7
![Page 8: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/8.jpg)
SCE ES Evaluation Philosophy
8 Southern California Edison
Electrochemical Energy Storage Evaluation
- Assess Various Chemistries for Performance and Potential Cost Reduction
- Determine Battery Operational Life
- Provide Input for Strategic Planning
System Evaluation
- Validate Full System Performance
- Validate Control System
- Prepare Documentation for Field Installation
- Train Field Personnel
- Engage Internal and External Stakeholders
Field Evaluation
- Demonstrate Functionality and Value in Actual Applications
- Engage Internal and External Stakeholders
![Page 9: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/9.jpg)
SCE ES Field Evaluation
Southern California Edison 9
Demonstration Programs
Assess Technical Merit - Demonstrate Functionality
- Demonstrate Potential Value Streams
- Demonstrate Reliability
Pilot Programs
Provide a System Function
- Provide Grid Function
- Increase Operational Excellence
- Capture Value Streams
- Pursue Standardization
Deployment
Mainstream Grid Device
![Page 10: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/10.jpg)
LABORATORY EVALUATION
Southern California Edison 10
![Page 11: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/11.jpg)
Energy Storage Laboratory Evaluation
• Evaluate top battery manufacturer technologies to establish operational life
‒ Design appropriate test methodology
‒ Model energy storage technologies degradation • Model allow to optimize operational life when used as a dual use asset
(distribution and market applications)
• Evaluate sub-system or full energy storage systems and associated component performances prior to the field deployment
Southern California Edison 11
![Page 12: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/12.jpg)
Tehachapi Storage Project
Large-scale Energy Storage (8MW/32MWh – Q3 2014) • Evaluate a utility scale lithium-ion battery’s ability to increase grid performance &
integrate wind generation
Distributed Energy Storage Integration 1 (DESI 1) Pilot Program (2.4MW/3.9MWh – Q2 2015) • Deploy energy storage on the distribution system to solve a challenge or for economic
benefit
Large Commercial PLS Program (100kW/500kWh – Q4 2014) • Evaluate Energy Storage for Large Commercial Customer Permanent Load Shifting
Large Distributed Energy Storage (2MW/500kWh unit – Q1 2014) • Evaluate containerized battery systems in field trials
Community Energy Storage (CES) (25kW/50kWh – Q3 2013) • Evaluate system ability to enhance circuit efficiency, resilience, and reliability
Residential Home Energy Storage Unit (RESU) (4kW/10kWh – Q3 2013) • Evaluate home storage integration with customer HAN, smart appliances, solar PV, PEV,
etc.
1 2 4 5
SCE’s ES Current and Past Demonstration and Pilot Activities
1
2
3
4
6
6
Irvine Smart Grid Demo Decommissioned
3
Southern California Edison 12
5
![Page 13: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/13.jpg)
Distributed Energy Storage Integration 2 & 3 (DESI 2 & 3) Pilot Program (2MW/4MWh & 1MW/1MWh – Q4 2017) • Evaluate aggregated energy storage units on the distribution system with optimized control
Distribution Reliability Improvement (3 systems – 2017/2018) • Mitigate Duck Bank temperature violation • Mitigate Planned Load Limit violation • Mitigate N-1 contingency
Preferred Resources Integration (3 systems – 2018) • Focus on circuit with high PV penetration • Mitigate voltage fluctuation • Increase PV dependability • Minimize reverse power flow
Strategic Applications (4 systems – 2018/2020) • Leverage storage fast response capabilities • Increase grid resiliency for critical and/or remote loads • Support micro grid developments • Support projects that enable electrification and carbon reduction objectives
SCE’s ES Upcoming Pilot Activities
Energy Storage Integration Program
Southern California Edison 13
Integrated Grid Project
![Page 14: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/14.jpg)
DEMO PROGRAMS
Southern California Edison 14
![Page 15: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/15.jpg)
Tehachapi Storage Project (TSP)
• Installed at an SCE substation
• 9 MVA / 32 MWh
• 6,300 sq. ft. building
• Connected at sub-transmission level through a 12/66kV transformer
• In operation since July 2014
• Evaluating 13 grid-reliability and market-function operational uses
Southern California Edison 15
![Page 16: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/16.jpg)
System Configuration
16
x 56 x 18 x 151 x 4
Cell Module Rack Section System
Quantity 608,832 10,872 604 4 1
Voltage 3.7 V 52 V 930 V 930 V 930 V
Energy 60 Wh 3.2 kWh 58 kWh 8.7 MWh 32 MWh (AC)
Weight 380 g 40 kg 950 kg N/A N/A
How to get 32MWh from 60Wh battery cells
Southern California Edison
![Page 17: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/17.jpg)
TSP Layout
Southern California Edison 17
PCS units
12kV/66kV transformer BESS Building
![Page 18: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/18.jpg)
TSP Facilities
Southern California Edison 18
![Page 19: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/19.jpg)
TSP Power Conversion System
Southern California Edison 19
![Page 20: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/20.jpg)
Irvine Smart Grid Demonstration (ISGD)
Southern California Edison 20
Storage elements
![Page 21: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/21.jpg)
ISGD - Storage Elements
• Residential Energy Storage Unit (RESU) ‒ 4kW / 10kWh ‒ Installed in 13 homes
• Community Energy Storage (CES) ‒ 25kW / 50kWh ‒ One device serving 9 homes
• Electric Vehicle Charging Station with PV and Storage (BESS)
‒ 100kW / 100 kWh ‒ Paired with 20 EV charging stations & 48kW PV array
• Distribution Battery Energy Storage System (DBESS) ‒ 2MW / 500kWh ‒ Connected to 12kV distribution circuit
Note: decommissioning is in progress
Southern California Edison 21
![Page 22: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/22.jpg)
PILOT PROGRAM - DESI
Southern California Edison 22
![Page 23: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/23.jpg)
Distributed Energy Storage Integration (DESI) Pilot 1
• Installed to support overloaded 12kV distribution circuit
• Rated at 2.5MVA / 3.9MWh
• Located in dense urban area environment ‒ Sited on customer easement
• Extremely compact system ‒ Entire system fit within 1,600 sq. ft. easement (including
12kV transformer, switchgear and protection)
• In operation since May 2015
Southern California Edison 23
![Page 24: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/24.jpg)
DESI Site
PCS
12 kV/480 V Transformer
BESS Building
Switchgear
Connection Point
Southern California Edison 24
![Page 25: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/25.jpg)
DESI 1 Key Components
• Battery System
• Power Conversion System (PCS)
• Medium Voltage Transformer
• Medium Voltage Switchgear and Protection
Southern California Edison 25
![Page 26: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/26.jpg)
Battery System
PCS 12kV Switchgear
Fire Suppression System
Southern California Edison 26
![Page 27: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/27.jpg)
Modes of Operation
• Maintain distribution circuit current to a pre-defined threshold based on measurement made on the circuit or near/at substation [by discharging the battery system]
• Recharge the battery system during time of low line loading
• Optionally, provide reactive power to support local voltage or maintain zero reactive power at the substation
Southern California Edison 27
![Page 28: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/28.jpg)
![Page 29: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/29.jpg)
Remaining Challenges/Gaps
• Capturing promised value streams in actual applications & building positive business cases
• Availability of truly grid-ready integrated systems ‒ Storage component may be mature, integration into complete
turn-key system has not reached full maturity
• Siting, Siting, Siting ‒ Land availability, system footprint
• Demonstrating required reliability at the system level
• Integrating with existing utility communication infrastructure & new Smart Grid technologies
• Validating large systems prior to deployment
• Availability of standard application definitions and test procedures
Southern California Edison 29
![Page 30: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/30.jpg)
Distribution Benefits Analysis
Southern California Edison 30
![Page 31: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/31.jpg)
Building Business Cases
• Many challenges still remain: ‒ Defining practical use cases
‒ Capturing sufficient value streams
‒ Identifying appropriate circuit & location
‒ Integrating seamlessly with company distribution planning practices
Southern California Edison 31
![Page 32: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/32.jpg)
Benefits Overview
Identifying, quantifying, monetizing and capturing storage distribution values
Identified, quantified,
monetized Values Identified, quantified
Values Identified Values
• Deferral value of distribution upgrades
• Market services value (AS, RA, and energy arbitrage) 1
• Equipment life extension • Voltage optimization
• DER integration enhancement
• Grid reliability (SAIDI/SAIFI) • Power quality improvement • Reactive power
compensation • Phase balancing • Other
Southern California Edison 32
1 Market values
![Page 33: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational](https://reader035.fdocuments.us/reader035/viewer/2022071411/61077afbe94cf115c0122069/html5/thumbnails/33.jpg)
Thank you
Southern California Edison 33