Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other...

33
Southern California Edison Energy Storage Activities Brief Overview Ignacio Sanchez So. Cal. Edison Engineer - Advanced Energy Storage 12/08/2016

Transcript of Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other...

Page 1: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Southern California Edison Energy Storage Activities

Brief Overview

Ignacio Sanchez So. Cal. Edison Engineer - Advanced Energy Storage

12/08/2016

Page 2: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

•14 million customers - one of the largest utilities in US

•50,000 square miles service territory

•125+ years of service

•23,000 MW Peak

Southern California Edison

2 Southern California Edison

Page 3: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Background

• California Public Utility Commission (CPUC) Energy Storage Decision

‒ Requires SCE to procure 580MW of energy storage by 2020 and gives SCE the opportunity to own up to 290MW

• SCE Approach ‒ Leverage RFO procurement process

• Provide market services

• Provide distribution capital deferral

‒ Enhance learning and understanding through targeted pilot programs • Support distribution reliability

• Facilitate preferred resources integration

• Investigate microgrids

Southern California Edison 3

Page 4: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Energy Storage Decision D 13-10-040 Requires SCE to procure 580MW of energy storage by 2020 and gives SCE the opportunity to own up to 290MW

Energy Storage Requirements (MW)

Storage Grid Domain (Point of Interconnection)

2014 2016 2018 2020 Total Total

Range

Transmission 50 65 85 110 310 62 - 458

Distribution 30 40 50 65 185 37 - 433

Customer 10 15 25 35 85 85 - 170

Total 90 120 160 210 580 580

Flexibility:

• Up to 50% of total procurement goal can be Utility Owned

• Up to 80% of target MWs can be: – Shifted between Transmission and Distribution domain (only) – Deferred (not past 2020) with a showing of unreasonableness

– Up to 200% of target Customer domain MWs can be counted

• All projects must be installed and operational by 2024

Southern California Edison 4

Page 5: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

115

70

25

0

50

100

150

200

250

Transmission Distribution Customer

MW

SCE 2016 Storage Portfolio

2016 ES Procurement Status

Southern California Edison 5

Authorized to be counted towards 2016 targets

2016 procurement target (cumulative) 85 MW excess

capacity

Currently above targets

Excess customer domain capacity

SCE LCR RFO SCE 2014 ES RFO Customer Service Programs

Other (e.g., Pilots & Demos)

Transmission 100 MW - - -

Distribution - 16 MW - 16 MW

Customer 161 MW - 54 MW 11 MW

SCE Procurement Activities

(All numbers rounded to the nearest Megawatt)

Page 6: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

SCE Energy Storage Efforts

6 Southern California Edison

Technical Evaluation

• Laboratory Evaluation

• Demos & Pilots

Strategic Planning

• ES Business Cases

• Regulatory Compliance

Simulation & Modeling

• Where?

• What size?

Page 7: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

SCE ES Technical Activities

• Storage Technology Laboratory Evaluation ‒ Validate storage technology performance

‒ Create degradation models to optimize system operation (extend life, improve business case)

• System or Sub-system Laboratory Testing ‒ Validate system integration (from a safety and

operational performance perspective)

• Field Demonstration and Pilots ‒ Refine deployment, connection and operation processes

‒ Validate system performance and reliability in the field

Southern California Edison 7

Page 8: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

SCE ES Evaluation Philosophy

8 Southern California Edison

Electrochemical Energy Storage Evaluation

- Assess Various Chemistries for Performance and Potential Cost Reduction

- Determine Battery Operational Life

- Provide Input for Strategic Planning

System Evaluation

- Validate Full System Performance

- Validate Control System

- Prepare Documentation for Field Installation

- Train Field Personnel

- Engage Internal and External Stakeholders

Field Evaluation

- Demonstrate Functionality and Value in Actual Applications

- Engage Internal and External Stakeholders

Page 9: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

SCE ES Field Evaluation

Southern California Edison 9

Demonstration Programs

Assess Technical Merit - Demonstrate Functionality

- Demonstrate Potential Value Streams

- Demonstrate Reliability

Pilot Programs

Provide a System Function

- Provide Grid Function

- Increase Operational Excellence

- Capture Value Streams

- Pursue Standardization

Deployment

Mainstream Grid Device

Page 10: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

LABORATORY EVALUATION

Southern California Edison 10

Page 11: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Energy Storage Laboratory Evaluation

• Evaluate top battery manufacturer technologies to establish operational life

‒ Design appropriate test methodology

‒ Model energy storage technologies degradation • Model allow to optimize operational life when used as a dual use asset

(distribution and market applications)

• Evaluate sub-system or full energy storage systems and associated component performances prior to the field deployment

Southern California Edison 11

Page 12: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Tehachapi Storage Project

Large-scale Energy Storage (8MW/32MWh – Q3 2014) • Evaluate a utility scale lithium-ion battery’s ability to increase grid performance &

integrate wind generation

Distributed Energy Storage Integration 1 (DESI 1) Pilot Program (2.4MW/3.9MWh – Q2 2015) • Deploy energy storage on the distribution system to solve a challenge or for economic

benefit

Large Commercial PLS Program (100kW/500kWh – Q4 2014) • Evaluate Energy Storage for Large Commercial Customer Permanent Load Shifting

Large Distributed Energy Storage (2MW/500kWh unit – Q1 2014) • Evaluate containerized battery systems in field trials

Community Energy Storage (CES) (25kW/50kWh – Q3 2013) • Evaluate system ability to enhance circuit efficiency, resilience, and reliability

Residential Home Energy Storage Unit (RESU) (4kW/10kWh – Q3 2013) • Evaluate home storage integration with customer HAN, smart appliances, solar PV, PEV,

etc.

1 2 4 5

SCE’s ES Current and Past Demonstration and Pilot Activities

1

2

3

4

6

6

Irvine Smart Grid Demo Decommissioned

3

Southern California Edison 12

5

Page 13: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Distributed Energy Storage Integration 2 & 3 (DESI 2 & 3) Pilot Program (2MW/4MWh & 1MW/1MWh – Q4 2017) • Evaluate aggregated energy storage units on the distribution system with optimized control

Distribution Reliability Improvement (3 systems – 2017/2018) • Mitigate Duck Bank temperature violation • Mitigate Planned Load Limit violation • Mitigate N-1 contingency

Preferred Resources Integration (3 systems – 2018) • Focus on circuit with high PV penetration • Mitigate voltage fluctuation • Increase PV dependability • Minimize reverse power flow

Strategic Applications (4 systems – 2018/2020) • Leverage storage fast response capabilities • Increase grid resiliency for critical and/or remote loads • Support micro grid developments • Support projects that enable electrification and carbon reduction objectives

SCE’s ES Upcoming Pilot Activities

Energy Storage Integration Program

Southern California Edison 13

Integrated Grid Project

Page 14: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

DEMO PROGRAMS

Southern California Edison 14

Page 15: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Tehachapi Storage Project (TSP)

• Installed at an SCE substation

• 9 MVA / 32 MWh

• 6,300 sq. ft. building

• Connected at sub-transmission level through a 12/66kV transformer

• In operation since July 2014

• Evaluating 13 grid-reliability and market-function operational uses

Southern California Edison 15

Page 16: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

System Configuration

16

x 56 x 18 x 151 x 4

Cell Module Rack Section System

Quantity 608,832 10,872 604 4 1

Voltage 3.7 V 52 V 930 V 930 V 930 V

Energy 60 Wh 3.2 kWh 58 kWh 8.7 MWh 32 MWh (AC)

Weight 380 g 40 kg 950 kg N/A N/A

How to get 32MWh from 60Wh battery cells

Southern California Edison

Page 17: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

TSP Layout

Southern California Edison 17

PCS units

12kV/66kV transformer BESS Building

Page 18: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

TSP Facilities

Southern California Edison 18

Page 19: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

TSP Power Conversion System

Southern California Edison 19

Page 20: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Irvine Smart Grid Demonstration (ISGD)

Southern California Edison 20

Storage elements

Page 21: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

ISGD - Storage Elements

• Residential Energy Storage Unit (RESU) ‒ 4kW / 10kWh ‒ Installed in 13 homes

• Community Energy Storage (CES) ‒ 25kW / 50kWh ‒ One device serving 9 homes

• Electric Vehicle Charging Station with PV and Storage (BESS)

‒ 100kW / 100 kWh ‒ Paired with 20 EV charging stations & 48kW PV array

• Distribution Battery Energy Storage System (DBESS) ‒ 2MW / 500kWh ‒ Connected to 12kV distribution circuit

Note: decommissioning is in progress

Southern California Edison 21

Page 22: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

PILOT PROGRAM - DESI

Southern California Edison 22

Page 23: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Distributed Energy Storage Integration (DESI) Pilot 1

• Installed to support overloaded 12kV distribution circuit

• Rated at 2.5MVA / 3.9MWh

• Located in dense urban area environment ‒ Sited on customer easement

• Extremely compact system ‒ Entire system fit within 1,600 sq. ft. easement (including

12kV transformer, switchgear and protection)

• In operation since May 2015

Southern California Edison 23

Page 24: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

DESI Site

PCS

12 kV/480 V Transformer

BESS Building

Switchgear

Connection Point

Southern California Edison 24

Page 25: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

DESI 1 Key Components

• Battery System

• Power Conversion System (PCS)

• Medium Voltage Transformer

• Medium Voltage Switchgear and Protection

Southern California Edison 25

Page 26: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Battery System

PCS 12kV Switchgear

Fire Suppression System

Southern California Edison 26

Page 27: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Modes of Operation

• Maintain distribution circuit current to a pre-defined threshold based on measurement made on the circuit or near/at substation [by discharging the battery system]

• Recharge the battery system during time of low line loading

• Optionally, provide reactive power to support local voltage or maintain zero reactive power at the substation

Southern California Edison 27

Page 28: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational
Page 29: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Remaining Challenges/Gaps

• Capturing promised value streams in actual applications & building positive business cases

• Availability of truly grid-ready integrated systems ‒ Storage component may be mature, integration into complete

turn-key system has not reached full maturity

• Siting, Siting, Siting ‒ Land availability, system footprint

• Demonstrating required reliability at the system level

• Integrating with existing utility communication infrastructure & new Smart Grid technologies

• Validating large systems prior to deployment

• Availability of standard application definitions and test procedures

Southern California Edison 29

Page 30: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Distribution Benefits Analysis

Southern California Edison 30

Page 31: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Building Business Cases

• Many challenges still remain: ‒ Defining practical use cases

‒ Capturing sufficient value streams

‒ Identifying appropriate circuit & location

‒ Integrating seamlessly with company distribution planning practices

Southern California Edison 31

Page 32: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Benefits Overview

Identifying, quantifying, monetizing and capturing storage distribution values

Identified, quantified,

monetized Values Identified, quantified

Values Identified Values

• Deferral value of distribution upgrades

• Market services value (AS, RA, and energy arbitrage) 1

• Equipment life extension • Voltage optimization

• DER integration enhancement

• Grid reliability (SAIDI/SAIFI) • Power quality improvement • Reactive power

compensation • Phase balancing • Other

Southern California Edison 32

1 Market values

Page 33: Southern California Edison Energy Storage Activities Brief Overview · 2016. 12. 8. · Other (e.g., Pilots & Demos) Transmission 100 MW - - - ... • Model allow to optimize operational

Thank you

Southern California Edison 33