   Page 1   SOQ Part I Pre‐Submittal Meeting Minutes Project: City of Salina South Well Field and WTP Improvement Project Subject: PreSubmittal Meeting Date: Tuesday, November 29, 2016 Location: City of Salina Public Library Prescott Room Topics: 1.  Attendees refer to Attachment A PreSubmittal Meeting SignIn Sheet 2.  Presentation  a. Introductions of Owner and Owner’s Representative and Project Drivers by Don Lindeman, HDR b. Project Overview by Jessica AdamsWeber, HDR c. Water Treatment Alternatives by Ryan Saffels, HDR d. Progressive DesignBuild Overview by Scott Churilla, HDR e. Procurement Overview by Jessica AdamsWeber, HDR f. Award Schedule and Phase One & Two Milestones by Don Lindeman, HDR 3.  Questions and Answers  Question 1. What kind of Progressive DesignBuild Contract will be issued for Phase One services?  Answer/Response:   DBIA Template  Question 2. Will the Updated Feasibility Study be issued prior to SOQ Part I deadline (Dec 22 nd )?  Answer/Response:   It is not expected that the updated Study will be issued by the SOQ Part I deadline (Dec 22 nd ).   Question 3. Will the City perform parallel cost estimates?  Answer/Response:   Yes, parallel cost estimates will be performed by the Owner’s Representative (HDR) at each design submittal milestone (i.e., 30%, 60%, 90%)  Question 4. Does the procurement schedule provide enough time for contract negotiations?   Answer/Response:   The intent of requesting Progressive DB Contract markups at the time of the Confidential Meetings is to provide the City Attorney additional review time prior to negotiations with the Selected Design Build Team.  Question 5. Do the scoring criteria include a score for the contract markups?   Answer/Response:   Yes.  It is a PASS/FAIL score only to ensure a contract markup is submitted or if no markup, at a minimum acknowledgement of review of the contract is submitted. 

Transcript of SOQ Part I Pre‐Submittal Meeting Minutes

Page 1: SOQ Part I Pre‐Submittal Meeting Minutes

  

 

Page 1 

   

SOQPartIPre‐SubmittalMeetingMinutesProject: City of Salina South Well Field and WTP Improvement Project

Subject: Pre‐Submittal Meeting 

Date: Tuesday, November 29, 2016

Location: City of Salina Public Library Prescott Room

Topics:

1.   Attendees refer to Attachment A ‐ Pre‐Submittal Meeting Sign‐In Sheet

2.   Presentation 

  a. Introductions of Owner and Owner’s Representative and Project Drivers by Don Lindeman, HDRb. Project Overview by Jessica Adams‐Weber, HDR c. Water Treatment Alternatives by Ryan Saffels, HDR d. Progressive Design‐Build Overview by Scott Churilla, HDR e. Procurement Overview by Jessica Adams‐Weber, HDR f. Award Schedule and Phase One & Two Milestones by Don Lindeman, HDR 

3.   Questions and Answers 

  Question 1. What kind of Progressive Design‐Build Contract will be issued for Phase One services? Answer/Response:   

DBIA Template  Question 2. Will the Updated Feasibility Study be issued prior to SOQ Part I deadline (Dec 22nd)?  Answer/Response:   

It  is not expected  that  the updated Study will be  issued by  the SOQ Part  I deadline (Dec 22nd).  

 Question 3. Will the City perform parallel cost estimates?  Answer/Response:   

Yes, parallel cost estimates will be performed by the Owner’s Representative (HDR) at each design submittal milestone (i.e., 30%, 60%, 90%)  

Question 4. Does the procurement schedule provide enough time for contract negotiations?   Answer/Response:   

The  intent  of  requesting  Progressive  D‐B  Contract  mark‐ups  at  the  time  of  the Confidential Meetings  is to provide the City Attorney additional review time prior to negotiations with the Selected Design Build Team. 

 Question 5. Do the scoring criteria include a score for the contract mark‐ups?   Answer/Response:   

Yes.    It  is a PASS/FAIL score only  to ensure a contract mark‐up  is submitted or  if no mark‐up, at a minimum acknowledgement of review of the contract is submitted. 

Page 2: SOQ Part I Pre‐Submittal Meeting Minutes

  

 

Page 2 

 

 Question 6. Do the scoring criteria include a score for the confidential meeting?   Answer/Response:   

No.  Question 7. Who will be on the Selection Committee?  Answer/Response:   

There will be five total Selection Committee members: four City staff and one Owner’s Representative (HDR) staff. 

 Question 8. Can the Respondent provide more than 10 reference projects?  Answer/Response:   

The  Respondent must  submit  at  least  5  reference  design  projects  and  5  reference construction projects. The Respondent may submit more projects provided  the SOQ Part I page limit is not exceeded. The representative design and construction projects can  also  be  design‐build  projects  highlighting  both  the  design  and  construction experience of the team.    However,  for  design‐build  experience  the  Respondent’s  shall  also  submit  a  table showing all design‐build experience for projects of a similar size and content. 

 Question 9. Will the WQ Testing Protocol include MPA testing to determine if the groundwater is 

groundwater under direct influent (GWUDI)?  Answer/Response:   

WQ  Testing  Protocol  is  to  be  determined  and  developed  by  the  Selected  Design‐Builder.   

 Question 10. Will the City provide scores and ranking when the Shortlisted Respondents is released 

or just the list Shortlisted Respondents?  Answer/Response:   

The City will provide to all Respondents the list of Shortlisted Respondents; no scores or ranking will be provided.  

Question 11. Is the existing levee at the proposed project site a USACE levee?  Answer/Response:   

Yes, refer to Draft Feasibility Study for further details.  

4.   Attachments 

  Attachment A. Pre‐Submittal Meeting Sign‐In SheetAttachment B. Pre‐Submittal Meeting Presentation 

Page 3: SOQ Part I Pre‐Submittal Meeting Minutes

  

 

   

AttachmentA‐Pre‐SubmittalMeetingSign‐InSheet 

Page 4: SOQ Part I Pre‐Submittal Meeting Minutes
Page 5: SOQ Part I Pre‐Submittal Meeting Minutes

  

 

   

AttachmentB‐Pre‐SubmittalMeetingPresentation

Page 6: SOQ Part I Pre‐Submittal Meeting Minutes

© 2015 HDR, all rights reserved.

South Well Field and Water Treatment Plant Pre-Submittal Meeting

City of Salina, KansasNovember 29, 2016

Page 7: SOQ Part I Pre‐Submittal Meeting Minutes

INTRODUCTIONS

PROJECT OVERVIEW

PROGESSIVE D-B OVERVIEW

PROCUREMENT OVERVIEW

Page 8: SOQ Part I Pre‐Submittal Meeting Minutes

Martha Tasker, Director of Utilities

Bernie Kitten, Plant Operations Manager

Mark Peterson, Electrical Engineer

Ray Starnes, WTP Operations Foreman

City Staff - Owner Don Lindeman, Project Manager

Ryan Saffels, Water Section Manager

Scott Churilla, Design Build Consultant

Jessica Adams-Weber, Project Engineer

HDR Staff – Owner’s Representative

Introductions

Page 9: SOQ Part I Pre‐Submittal Meeting Minutes

Project Overview

Page 10: SOQ Part I Pre‐Submittal Meeting Minutes

Downtown Facilitieso Downtown WTP (20 MGD)

o Downtown Well Field (15 wells)

• Normal: 15.2 MGD

• Drought: 12.4 MGD

o Smoky Hill River Intake (10 MGD)

Former Schilling Air Force Base Facilities o Schilling Air Force Base WTP

• Emergency supply only

o South Well Field (5 wells, 3 active)

• Existing Capacity: 2.24 MGD

• Water Rights: 3.7 MGD

System Overview

Page 11: SOQ Part I Pre‐Submittal Meeting Minutes

Goal: o Provide water supply during drought

Feasibility Studyo Draft 2016

o Water Supply Alternatives

o Water Treatment Alternatives

Project:o Improvements to five existing wells

o Raw water lines, finished water lines, and other utilities

o Construction of new 3.5 MGD WTP • Lime Softening WTP

• Membrane WTP

Estimated Project Budget:o Approximately $32M to be funded by

SRF

Project Overview

Page 12: SOQ Part I Pre‐Submittal Meeting Minutes
Page 13: SOQ Part I Pre‐Submittal Meeting Minutes

Continued use of vertical wells and vested water rights

Offset Wells 1 and 5

Rehabilitate Wells 2, 3, and 4

New for all wells:o Pumps

o Flow meters

o Pump housing

o Discharge piping

o I&C

o Electrical

Water Supply Scope

Water Well Road

Ohi

o St

reet

Page 14: SOQ Part I Pre‐Submittal Meeting Minutes

Coagulation with Ferric Addition

Lime Softening

Recarbonation

Gravity Filtration

Disinfection (Chloramines)

Clearwell

High Service Pumping

Solids:o Gravity Thickening

o Dewatering Lagoons

Water Treatment Alternatives

Aeration

Green Sand Filtration

Nanofiltration (2-stage)

Disinfection (Chloramines)

Clearwell

High Service Pumping

Solids:o Membrane Waste Solids Separation

o River Discharge or Deep Well Injection

Lime Softening Treatment Membrane Treatment

Page 15: SOQ Part I Pre‐Submittal Meeting Minutes

Progressive Design-Build Overview

Page 16: SOQ Part I Pre‐Submittal Meeting Minutes

South Well Field and

Water Treatment

Plant

Single Point of Accountability

Establish Project

Budget Prior to Design

Maximize Contractor

Involvement in Design Cost Estimating

Early Collaboration

Between Owner’s Team and D-B Team

City’s Objectives

Page 17: SOQ Part I Pre‐Submittal Meeting Minutes

Procurement

Pre-Design• Evaluate Treatment

Alternatives• Establish Project

Budget with Contractor Estimates

Design and Cost Estimating• BODR• 30%• 60%• 90%

GMP

Finalize Design Construction Start-up & Operation

Phase 1

Phase 2

Progressive Design Build Overview

Page 18: SOQ Part I Pre‐Submittal Meeting Minutes

Procurement Overview

Page 19: SOQ Part I Pre‐Submittal Meeting Minutes

Submission of SOQ Part I

Short-List up to 3 Qualified Respondents

RFQ Part I

Confidential Meetings

Submission of SOQ Part II

Interviews

Selection of Design-Builder

Negotiation for Award

RFQ Part II (Shortlisted Respondents Only)

Procurement Overview (Section 1.1)

Page 20: SOQ Part I Pre‐Submittal Meeting Minutes

Advertise RFQ November 14, 2016

RFQ Acknowledgement November 21, 2016

Pre-Submittal Meeting November 29, 2016

Deadline for Questions December 9, 2016

Deadline for SOQ Part I December 22, 2016

Notification to Short-Listed Respondents January 9, 2017

Procurement Overview – RFQ Part I

Page 21: SOQ Part I Pre‐Submittal Meeting Minutes

Advertise RFQ November 14, 2016

RFQ Acknowledgement November 21, 2016

Pre-Submittal Meeting November 29, 2016

Deadline for Questions December 9, 2016

Deadline for SOQ Part I December 22, 2016

Notification to Short-Listed Respondents January 9, 2017

Procurement Overview – RFQ Part I

Page 22: SOQ Part I Pre‐Submittal Meeting Minutes

Advertise RFQ November 14, 2016

RFQ Acknowledgement November 21, 2016

Pre-Submittal Meeting November 29, 2016

Deadline for Questions December 9, 2016

Deadline for SOQ Part I Thursday, December 22, 2016 3:00 pm

Notification to Short-Listed Respondents January 9, 2017

Procurement Overview – RFQ Part I

Page 23: SOQ Part I Pre‐Submittal Meeting Minutes

Submission Deadline Thursday, December 22, 2016 3:00 pm

Submission Location

Submission:o 8 Paper Documents (1 original, 7 copies)

o 1 Electronic Version on Flash Drive (pdf)

Addressed to: City ClerkUtilities Department300 W. Ash, P.O. Box 736Salina, KS 67402-0736

SOQ Part I – Submission Requirements (Section 4.1.1)

Page 24: SOQ Part I Pre‐Submittal Meeting Minutes

Evaluation Criteria Scoring

Respondent’s Team 32%

Respondent’s Team Experience and Capabilities 63%

Safety record, including the EMR for the last 5 years 5%

Financial strength of the Respondent Pass/Fail

Legal/Litigation History for the last 10 years Pass/Fail

Licensing and Registration in the State of Kansas Pass/Fail

Respondent’s Acknowledgement of RFQ Pass/Fail

Respondent’s Signatory Certification Form Pass/Fail

Compliance forms (Appendix F) Pass/Fail

SOQ Part I – Evaluation Criteria(Section 5.1.4)

SOQ Part I scores weighted as 35% of overall score

Page 25: SOQ Part I Pre‐Submittal Meeting Minutes

Selection committee will use 100-point scale

Shortlist up to 3 Respondents

Owner will notify Respondents of rankings

Shortlisted Respondents invited to submit SOQ Part II

SOQ Part I – Evaluation & Shortlisting

Page 26: SOQ Part I Pre‐Submittal Meeting Minutes

Notification to Short-Listed Respondents January 9, 2017

Deadline for Contract Markup January 19 and 20, 2017

Conduct Confidential Meetings January 19 and 20, 2017

Submission of SOQ Part II February 10, 2017

Interviews February 16 and 17, 2017

Notification of Selection February 17, 2017

Procurement Overview – RFQ Part II

Page 27: SOQ Part I Pre‐Submittal Meeting Minutes

Notification to Short-Listed Respondents January 9, 2017

Deadline for Contract Markup January 19 and 20, 2017

Conduct Confidential Meetings January 19 and 20, 2017

Submission of SOQ Part II February 10, 2017

Interviews February 16 and 17, 2017

Notification of Selection February 17, 2017

Procurement Overview – RFQ Part II

Progressive D-B Contract will be provided as an Addenda prior to Shortlisting.

Page 28: SOQ Part I Pre‐Submittal Meeting Minutes

Notification to Short-Listed Respondents January 9, 2017

Deadline for Contract Markup January 19 and 20, 2017

Conduct Confidential Meetings January 19 and 20, 2017

Submission of SOQ Part II Friday, February 10, 2017 3:00 pm

Interviews February 16 and 17, 2017

Notification of Selection February 17, 2017

Procurement Overview – RFQ Part II

Page 29: SOQ Part I Pre‐Submittal Meeting Minutes

Submission Deadline Friday, February 10, 2017 3:00 pm

Submission Location

Submission:o 8 Paper Documents (1 original, 7 copies)

o 1 Electronic Version on Flash Drive (pdf)

Addressed to: City ClerkUtilities Department300 W. Ash, P.O. Box 736Salina, KS 67402-0736

SOQ Part II – Submission Requirements (Section 4.2.1)

Page 30: SOQ Part I Pre‐Submittal Meeting Minutes

Evaluation Criteria Scoring

Respondent’s Project Approach 100%

Acknowledge review of Contract and/or markup Pass/Fail

Short-Listed Respondent’s Signatory Certification Form Pass/Fail

SOQ Part II & Interview – Evaluation Criteria(Section 5.2.3)

SOQ Part II & Interview scores weighted as 65% of overall score

Page 31: SOQ Part I Pre‐Submittal Meeting Minutes

Procurement Overview – Final Selection

Selection Criteria Total Score

SOQ Part I 35%

SOQ Part II & Interview 65%

Page 32: SOQ Part I Pre‐Submittal Meeting Minutes

Notification of Selection February 17, 2017

Begin Negotiations February 20, 2017

City Commission Meeting for Approval March 13, 2017

Execution of Contract March 2017

Procurement Overview – Contracting Schedule

Page 33: SOQ Part I Pre‐Submittal Meeting Minutes

Project Design Phase (April 2017 to June 2018)

Design Kickoff Meeting April 2017

Consultant/Design-Builder Pre-Design June 2017

BODR and Project Budget June to August 2017

30% Document Development September 2017

60% Document Development November 2017

90% Document Development February 2018

Guaranteed Maximum Price Proposal May 2018

Execute Phase 2 Construction Contract June 2018

Progressive Design Build Proposed Milestones

Page 34: SOQ Part I Pre‐Submittal Meeting Minutes

Construction Services (June 2018 to November 2020)

Begin Construction June 2018

Substantial Completion November 2019

Final Completion March 2020

Progressive Design Build Proposed Milestones

Page 35: SOQ Part I Pre‐Submittal Meeting Minutes

QUESTIONS?

Page 36: SOQ Part I Pre‐Submittal Meeting Minutes