Somerset · P 07 5424 4000 F 07 5424 4099 E [email protected] W . 2. ... sa.. powrterad Me...
Transcript of Somerset · P 07 5424 4000 F 07 5424 4099 E [email protected] W . 2. ... sa.. powrterad Me...
SomersetREGIONAL COUNCIL
Officer: Robert Gardiner
Telephone: (07) 5424 4000
Email: [email protected] reference: DA11989
Date: 15'" December 2011
Somerset Regional Council
PO Box 117
Esk, QLD 4311
Decision Notice Approval
Operational WorksSustainable Planning Act 2009
I acknowledge receipt of the above application on 28th October 2011 and confirm the following details:
RE: Development application for Operational Works for Placement of Advertising Signage on landdescribed as Lot 7 RP214853 and situated at 32 Banks Creek Road, Fernvale.
Dear Sir/Madam,
I write to advise that, on 15* December 2011, the above development application was approved in fullwith conditions. The conditions of this approval are set out in Attachment 1.
Approval under s331This application has not been deemed to be approved under section 331 of the Sustainable Planning Act2009 (SPA).
1. Details of the approvalThe following approvals are given:
Sustainable Development PreliminaryPlanning Permit ApprovalRegulation2009, schedule3 reference
Operational work for Placement of Advertising Signage Part 1, table 4, Yes -
item 8
ABN 501 389 582 49Council Chambers - 2 Redbank Street, EskQLD 4312
Address all correspondence to - Chief Executive Officer, Somerset Regional Council, PO Box 117, Esk QLD 4312P 07 5424 4000 F 07 5424 4099 E [email protected] W www.somerset.qld.gov.au
2. Approved plans
The approved plans and/or documents for this development approval are listed in the following table:
Plan/Document number Plan/Document name Date
Drawing No. 0909. W1 Site Plan, drawn by Graham Richardson 30.10.09Architects
- Proposed Sign Display -
Drawing No. 11-372 Structural Details: drawn by ENG Consulting SEPT 11
3. When approval lapses if development not started (s.341)
? 15th December 2013
4. Appeal rights
Appeals by applicants
An applicant for a development application may appeal to the Planning and Environment Court againstthe following:
? the refusal, or refusal in part of the development application
? any condition of a development approval, another matter stated in a development approval and theidentification or inclusion of a code under section 242 of SPA
? a deemed refusal of the development application.
The timeframes for starting an appeal in the Planning and Environment Court are set out in section461(2) of SPA.
Applicants may also have a right to appeal to the Building and Development Dispute ResolutionCommittee. For more details, see SPA, chapter 7, part 2.
Yours si ely
Robert inhie Ex cuti e Officer
Attac en i nditions of the approvalAttach 2-S extract on appeal rights
ATTACHMENT 1 -- PART 1
CONDITIONS - ASSESSMENT MANAGER
SCHEDULE 1 - PlanningAssessment ManagerNo Condition Timing1.1 Carry out the development in accordance with the material At all times
contained in the development application, supportingdocumentation and the plan(s) listed below, except whereamended by these conditions of approval:
- Drawing No. 0909.W1, dated 30.10.09 & drawn byGraham Richardson Architects
- Proposed Sign Display- Drawing No. 11-372, dated SEPT 11 & drawn by ENG
Consulting
1.2 Comply with relevant provisions of the former Esk Shire's At all timesPlanning Scheme 2005 (as amended 17.10.2008), Planning
i Scheme Policies and Local Laws
1.3 A legible copy of this development approval package is to be At all timesI available on the premises at all times during construction
SCHEDULE 2 - EnvironmentalAssessment ManagerNo. Condition Timing2.1 All Structures to which this approval relates shall be maintained at At all times
all times -1. in a in a state of good repair;2. free of accumulated waste and disused materials; and3. shall be removed by the development holder if an
authorised Officer of Somerset Regional Council hasreason to form the opinion that they are unsightly or
detract from the visual amenity of the immediate area.
2.2 Light sources used in the carrying out of this approved At all timesdevelopment, must be positioned and shielded, when necessary,to prevent light spillage causing a nuisance to any other premisesoutside the boundaries of the development site.
SCHEDULE 3 - Advisory NotesNo. Advice3.1 This approval has effect in accordance with the provisions of Division 5 Section 339 of
the Sustainable Planning Act 2009 (SPA). [A copy of Section 339 will be enclosedwith Council's Decision Notíce]
3.2 In accordance with Division 5 Section 341(3) of the SPA the approved developmenthas a relevant period of 2 years.
3.3 Pursuant to Division 8 Section 461 of the Sustainable Planning Act 2009, theApplicant has the Right of Appeal to the Planning & Environment Court regardingany condition of this approval; another matter stated in the development approval andthe identification or inclusion of a code under section 242 of the 'Act'. [A copy of theRight of Appeal will be enclosed with the Decision Notice/
igir ! - Omei 5x,wm sae P 4
If
I. a .
1, \' -
Is i ji - .
I | \- ·
1 1' E
e Eo 7 APPROVED
q) Soni Regional CouncilENT MANAGER
.I
\.. eo
SB
/2P
oundS
treet
West
ipswich,
QLD
,4806
Ph/F
am07
8389518?
Sig
nPro
ofE
malk
careyogeokosigns.com.au
..
CO
LP
OW
EI.I. P
AR
K
Ph:
54267520
*-
OO
Heh
ScaN
eueU
r96
Bhek-R
egarsu
wn,
oc..nsa..
powrterad
Me
BoM
Um
aLem
onB
dghtO
rangen.hm
ucaer
alack-neyerB
rightR
edD
arkG
rayM
ediumR
edLaS
alleSB
GP
heabove
artwork
isintended
forproofing
ofgram
mar
andlayout.A
nycolours
shown
will
differfrom
fintshedproduct
andshould
bechosen
bycustom
erfrom
asam
plesw
atchr
Pantone
Chart.If
youagree
thattheabove
iscorrectsign
belowand
date.ifyou
wouldlike
tom
akechanges
pleaseIndicate
themon
theproof
andresubm
ittoG
eckoS
igns.
hecustom
eraccepts
funresponsibH
ityfor
spelingand
layoutonce
thisform
hasbeen
signedand
artwork
accepted.Any
Changes
toartw
orkafter
acceptancew
ilbe
atthe
ustomers
expense.B
ysigning
thisproof
youalso
agreethat
Gecko
Signs
shallnot
beheld
responsiblefordam
ageto
vehicleand
orpaint
resultingfrom
removal
ofold
Any!/paint.It
isthe
customers
responsibilityto
ensurethatall
paintedsurfaces
arein
servitablecondition
andthatvehicle
manufacturers
warranty
conditionsare
adheredto.
Any
designprovided
byG
eckoS
ignsis
coveredby
generalcopyright
lawand
shallrem
ainthe
propertyof
Gecka
Signs
unlessarelease
ispaid
forand
signedby
bothparties.
Sgned
thre
ME
MB
ER
SC
HE
DU
LE
1350t35o
C1
-100x4
SH
SD
UR
AC
AL
PO
ST
--------T
OP
OS
TS
WIT
H
2/NO
.14S
CR
EW
S
ER
CR
OS
SIN
G
cisti
Imo
CO
NC
.FO
OT
ING
PLA
NV
IEW
SC
AL£
1:50
SID
EE
LEV
AT
ION
FR
ON
TE
LEV
AT
ION
SC
ALE
1:50S
CA
L£1:50
i
DR
AW
DIG
TIT
I.EP
RO
ÆC
TC
LIEN
TS
UM
ER
SE
TR
EG
ION
AL
CO
UN
CIL
CO
NS
ULT
ING
ST
RU
CT
UR
AL
DE
TA
ILSP
RO
PO
SE
DS
TR
UC
TU
RE
a.........e...:-
-.m
ma
....-
??F
ER
NV
ALE
IND
OO
RS
PO
RT
SC
NT
11-372
man.....
-EC
HS
EP
TIt
apnsaarm
ssam
ramkam
rasam
mm
mW
neht unor
pi)nu
mm
amr
HE
R.W
anarR
mam
mar
,aam
mae
iR
N.0
MM
SR
deM
SH
OW
Sustainable Planning Act 2009Chapter 7 Appeals, ORences and enforcement
Part 1 Planning and Environment Coult
(s458;
458 Privileges, protection and immunity
A person who is one of the following has the same privileges,protection or immunity as the person would have if theproceeding were in the District Court-
(a) the judgepresiding over the proceeding;
(b) a lawyer or agent appearing in the proceeding;
(c) a witness attending in the proceeding.
459 Payment of witnesses
Every witness summoned is entitled to be paid reasonableexpenses by the party requiring the attendance of the witness.
460 Evidence of local planning instruments or master plans
(1) If a chief executive officer of a local government is satisfied adocument is a true copy of a local planning instrument ormaster plan, or a part of the local planning instrument or
master plan, in force for the local govemment at a time statedin the document, the chief executive officer may so certify thedocument.
(2) In a proceeding, a document certified under subsection (1) isadmissible in evidence as if it were the original local planninginstrument or master plan, or part of the instrument or plan.
Division 8 Appeals to court relating todevelopment applications andapprovals
461 Appeals by applicants
(1) An applicant for a development application may appeal to thecourt against any of the following-
Reprint 1C effective 1 Judy2010 Page 317
Sustainable Planning Act 2009Chapter 7 Appeals, offences and enforcementPart i Planning and Environment Court
\s462)
(a) the refusal, or the refusal in part, of the development
application;
(b) any condition of a development approval, another matter
stated in a development approval and the identificationor inclusion of a code under section 242;
(c) the decision to give a preliminary approval when a
development permit was applied for;
(d) the length of a period mentioned in section 341;
(e) a deemed refusal of the development application.
(2) An appeal under subsection (IXa), (b), (c) or (d) must be
started within 20 business days (the applicant's appeal
period)after-
(a) if a decision notice or negotiated decision notice is
given-4he day the decision notice or negotiateddecision notice is given to the applicant; or
(b) otherwise-the day a decision notice was required to be
given to the applicant.
(3) An appeal under subsection (lXe) may be started at any time
after the last day a decision on the matter should have been
made.
462 Appeals by submitters-general
(1) A submitter for a development application may appeal to thecourt only againet--
(a) the part of the approval relating to the assessment
manager's decision about any part of the applicationrequiring impact assessment under section 314; or
(b) the part of the approval relating to the assessment
manager's decision under section 327.
(2) To the extent an appeal may be made under subsection (I), theappeal may be against I or more of the following-
(a) the giving of a development approval;
Page 318 Reprint 1C eñecive 1 July 2010
sustainaise Planning Act 2oooChapter 7 Appeals, onences and enforcement
Part 1 Planning and Environment Court
is 463]
(b) any provision of the approval including-
(i) a condition of, or lack of condition for, theapproval; or
(ii) the length of a period mentioned in section 341 forthe approval.
(3) However, a submitter may not appeal if the submitter-
(a) withdraws the submission before the application isdecided; or
(b) has given the assessment manager a notice under section339(lXbXii).
(4) The appeal must be started within 20 business days (thesa6ml#er's appeal period) af ter the decision notice or
negotiated decision notice is given to the submitter.
463 Additional and extended appeal rights for submitters forparticular development applications
(1) This section applies to a development application to whichchapter 9, part 7 applies.
(2) A submitter of a properly made submission for the applicationmay appeal to the court about a referral agency's responsemade by a prescribed concurrence agency for the application.
(3) However, the submitter may only appeal against a referralagency's msponse to the extent it relates to--
(a) if the prescribed concurrence agency is the chiefexecutive (environment)-development for an
aquacultural ERA; or
(b) if the prescribed concurrence agency is the chiefexecutive (fisheries)-developmentthat is-
(i) a material change of use of premises for
aquaculture; or
(ii) operational work that is the removal, damage or
destruction of a marine plant.
Repdnt 1C eSecive i July 2010 Page 319
Sustainable Planning Act 2009
Chapter 7 Appeals, ofiences and enfolcementPad 1 Planning and Enwhenment Court
ja464)
(4) Despite section 462(1), the submitter may appeal against thefollowing matters for the application even if the matters relateto code assessment-
(a) a decision about a matter mentioned in section 462(2) ifit is a decision of the chief executive (fisheries);
(b) a referral agency's response mentioned in subsection(2).
464 Appeals by advice agency submitters
(1) Subsection (2) applies if an advice agency, in its response foran application, told the assessment manager to treat theresponse as a properly made submission.
(2) The advice agency may, within the limits of its jurisdiction,appeal to the court about-
(a) any part of the approval relating to the assessment
manager's decision about any part of the applicationrequiring impact assessment under section 314; or
(b) any part of the approval relating to the assessment
manager's decision under section 327.
(3) The appeal must be started within 20 business days after theday the decision notice or negotiated decision notice is givento the advice agency as a submitter.
(4) However, if the advice agency has given the assessment
manager a notice under section 339(lXbXii), the adviceagency may not appeal the decision.
465 Appeals about decisions relating to extensions for
approvals
(1) For a development approval given for a development
application, a person to whom a notice is given under section389, other than a notice for a decision under section 386(2),may appeal to the court against the decision in the notice.
Page 320 Reprint 1C eñecive 1 July 2010
Sustainable Planning Act 2009Chapter 7 Appeals, ollences and enlostament
Part 1 Planning and Environment Court
is 486)
(2) The appeal must be started within 20 business days after theday the notice of the decision is given to the person.
(3) Also, a person who has made a request under section 383 mayappeal to the court against a deemed refusal of the request.
(4) An appeal under subsection (3) may be started at any timeafter the last day the decision on the matter should have beenmade.
466 Appeals about decisions relating to permissible changes
(1) Por a development approval given for a developmentapplication, the following persons may appeal to the courtagainst a decision on a request to make a permissible changeto the approvai-
(a) if the responsible entity for making the change is theassessment manager for the application-
(i) the person who made the request; or
(ii) an entity that gave a notice under section 373 or a
pre-request response notice about the request;
(b) if the responsible entity for making the change is a
concurrence agency for the application-the person whomade the request.
(2) The appeal must be started within 20 business days after theday the person is given notice of the decision on the requestunder section 376.
(3) Also, a person who has made a request under section 369 mayappeal to the court against a deemed refusal of the request.
(4) An appeal under subsection (3) may be started at any timeafter the last day the decision on the matter should have beenmade.
Reprint 1C effeedve i July 2010 Page 321
Sustainable Planning Act 2009
Chapter 7 Appeals, offences and enforcementPart 1 Planning and Environment Court
[s 467|
467 Appeals about changing or cancelling conditionsimposed by assessment manager or concurrence agency
(1) A person to whom a notice under section 378(9)(b)giving a
decision to change or cancel a condition of a development
approval has been given may appeal to the court against thedecision in the notice.
(2) The appeal must be started within 20 business days after theday the notice of the decision is given to the person.
Division 9 Appeals to court about complianceassessment
468 Appeals against decision on request for complianceassessment
(1) A person to whom an action notice has been given undersection 405(5)about a request for compliance assessment ofdevelopment, a document or work may appeal to the court
against the decision in the notice.
(2) The appeal must be started within 20 business days after the
notice is given to the person.
469 Appeals against condition imposed on compliancepermit or certificate
(1) A person who is given a compliance permit or compliancecertificate subjectto any conditions may appeal to the court
against the decision to impose the condition.
(2) The appeal must be started within 20 business days after theday the compliance permit or compliance certificate is givento the person.
Page 322 Reprint 1C efecive 1 July 2010
sustainame Planning Act 2009Chapter 7 Appeals, oNences and enforcement
Part 1 Planning and Environment Court
(a470]
470 Appeals against particular decisions about complianceassessment
(1) A person to whom any of the following notices have beengiven may appeal to the court against the decision in thenotice--
(a) a notice of a decision on a æquest to change or withdrawan action notice;
(b) a notice under section 413(2Xc)about a decision to
refuse a request to change a compliance permit or
compliance certificate.
(2) The appeal must be started within 20 business days after theday the notice is given to the person.
Division 10 Appeals to court about othermatters
471 Appeal by appilcant for approval of a proposedmaster plan
(1) A person who has applied for an approval of a proposedmaster plan may appeal to the court against-
(a) the refusal, or the refusal in part, to give the approvat; or
(b) a matter stated in the notice of decision about theapplication; or
(c) a deemed refusal of the master plan application.
(2) An appeal under subsection (1Xa) or (b) must be startedwithin 20 business days (theapplicant's appeal period) afterthe day the applicant is given notice of the decision.
(3) An appeal under subsection (1Xc) may be started at any timeafter the last day a decision on the matter should have beenmade.
Repunt ic elrective i July 2010 Page 323