Some Assembly Required Dave Grant

download Some Assembly Required Dave Grant

of 84

Transcript of Some Assembly Required Dave Grant

  • 8/12/2019 Some Assembly Required Dave Grant

    1/84

    The C-141 StarLifter

    Some assembly required

  • 8/12/2019 Some Assembly Required Dave Grant

    2/84

    This is some of the tooling used

    to manufacture the C-141.

    These were used to shape the

    sides of the fuselage.

  • 8/12/2019 Some Assembly Required Dave Grant

    3/84

    In this picture you can see

    the aluminum skin being

    applied to the segment.

  • 8/12/2019 Some Assembly Required Dave Grant

    4/84

    The completed segment is moved

    to a holding area, until needed.

  • 8/12/2019 Some Assembly Required Dave Grant

    5/84

    In the lower foreground, is thelower bulkhead that the upper

    aft fuselage will be built upon.

    The section on the left side of

    the photo is being moved to

    mount on the bulkhead.

  • 8/12/2019 Some Assembly Required Dave Grant

    6/84

    The upper skin segment of the aft

    fuselage is being attached to the

    lower bulkhead. The hole in the top

    will be inside the vertical stabilizer.This is one of several stations

    assembling this segment. All the

    segments are being manufactured

    concurrently, and will be joined at

    the final assembly.

  • 8/12/2019 Some Assembly Required Dave Grant

    7/84

    This is the aft segment of the

    aft fuselage, which will be

    moved and joined with the

    bulkhead, and forward section.

  • 8/12/2019 Some Assembly Required Dave Grant

    8/84

    Aft segment being mated with the

    bulkhead and forward section.

  • 8/12/2019 Some Assembly Required Dave Grant

    9/84

    The aft fuselage upper segment, now

    completed, is being mated with the fuselage

    side segments in an alignment fixture.

  • 8/12/2019 Some Assembly Required Dave Grant

    10/84

  • 8/12/2019 Some Assembly Required Dave Grant

    11/84

    The upper cap for the aft fuselage is

    being installed. The number three

    emergency escape hatch is visiblein the forward section of the cap.

  • 8/12/2019 Some Assembly Required Dave Grant

    12/84

    Upper forward fuselage framework.

    The aluminum skin is being attachedon the left side of the picture.

  • 8/12/2019 Some Assembly Required Dave Grant

    13/84

    Upper forward fuselage with

    the aluminum skin attached.

  • 8/12/2019 Some Assembly Required Dave Grant

    14/84

    Lower forward fuselage beingassembled in fixture. It is assembled

    upside down for ease of assembly.

  • 8/12/2019 Some Assembly Required Dave Grant

    15/84

    Lower forward fuselage being

    moved to mating fixture. The

    section on the right side with the

    two holes is the forward bulkhead

    where the radome will attach.

  • 8/12/2019 Some Assembly Required Dave Grant

    16/84

    The lower forward fuselagesection is in place in the

    alignment fixture as the

    upper section is lowered into

    position for mating.

  • 8/12/2019 Some Assembly Required Dave Grant

    17/84

  • 8/12/2019 Some Assembly Required Dave Grant

    18/84

    The completed forward fuselage

    segment is completed and moved to

    the fuselage mating jig. As you can

    see this is the first C-141A StarLifter.

  • 8/12/2019 Some Assembly Required Dave Grant

    19/84

    Fuselage Station 1058 main frame. This is one of four main frames that

    completely encircle the fuselage. Main frames are located at the front and back

    of the center wing, they support the airplane while airborne. Fuselage station

    998 and 1058 main frames support the airplane while it is on its wheels.

  • 8/12/2019 Some Assembly Required Dave Grant

    20/84

    A section of the center

    fuselage that contains, frombottom to top, the 1058, 998,

    and 958 main frames.

  • 8/12/2019 Some Assembly Required Dave Grant

    21/84

    Center fuselage floor segment being

    lowered into an alignment/mating fixture.

  • 8/12/2019 Some Assembly Required Dave Grant

    22/84

    Center fuselage main frame

    segment being positioned

    near alignment/mating fixture.

  • 8/12/2019 Some Assembly Required Dave Grant

    23/84

    Main frame segment

    being mated with floor

    segment. In the lower

    center of the pictureyou see a large hole

    where the crane cable

    is attached. This will

    be used to hold the

    main landing gear pivot

    pin. It is located in theFS998 main frame.

  • 8/12/2019 Some Assembly Required Dave Grant

    24/84

    Floor panels are installed in the

    center fuselage. In addition to

    acting as a floor, the panels

    provide stability to the structure.If the floor panels were not

    installed the segment could

    become distorted cause failure.

  • 8/12/2019 Some Assembly Required Dave Grant

    25/84

    Main frame segment being

    lowered into alignment and

    mating fixture.

  • 8/12/2019 Some Assembly Required Dave Grant

    26/84

    Lower section of the center wing box being

    installed in an alignment fixture. You can see

    the upper pressure diaphragm that will becontained within the assembly.

  • 8/12/2019 Some Assembly Required Dave Grant

    27/84

    Lower center wing placed in the alignment

    fixture. Notice the risers on the sides of

    the panels. These were milled to shape in

    order to provide strength to the panels.

  • 8/12/2019 Some Assembly Required Dave Grant

    28/84

    In order to save space on the

    manufacturing floor, the upper

    surface of the center wing wasassembled vertically

  • 8/12/2019 Some Assembly Required Dave Grant

    29/84

    The upper surface of the center wing box

    is being lowered on top of the lower

    surface in the alignment/mating fixture.

  • 8/12/2019 Some Assembly Required Dave Grant

    30/84

  • 8/12/2019 Some Assembly Required Dave Grant

    31/84

    Center wing box being moved to centerfuselage alignment/mating fixture. The

    dark square hole is to provide access

    for maintenance personnel.

  • 8/12/2019 Some Assembly Required Dave Grant

    32/84

    Lowering the center wing box

    into the fixture.

  • 8/12/2019 Some Assembly Required Dave Grant

    33/84

    Fuselage mating fixture. All three segments of the

    fuselage will be aligned and mated in this fixture.

  • 8/12/2019 Some Assembly Required Dave Grant

    34/84

    Center fuselage section from fuselage

    station 734 through station 1058. It is

    being moved toward the mating fixture.

  • 8/12/2019 Some Assembly Required Dave Grant

    35/84

    Center fuselage being placed into the

    alignment/mating fixture. The center

    fuselage is the heart of the airplane. All

    other assemblies will be aligned to it.

  • 8/12/2019 Some Assembly Required Dave Grant

    36/84

    Aft fuselage being lowered onto the

    alignment/mating fixture. Once on thefixture it will be moved forward to mate

    with the center fuselage.

  • 8/12/2019 Some Assembly Required Dave Grant

    37/84

  • 8/12/2019 Some Assembly Required Dave Grant

    38/84

    Main landing gear pods. They do not

    carry structural load, and their only

    purpose is to provide an aerodynamic

    enclosure for the landing gear.

  • 8/12/2019 Some Assembly Required Dave Grant

    39/84

    Main landing gear pod installed on the left

    side of the airplane.

  • 8/12/2019 Some Assembly Required Dave Grant

    40/84

    Main landing gear strut

    ready for build-up

  • 8/12/2019 Some Assembly Required Dave Grant

    41/84

    Adding the brake, wheel,

    and tire assemblies. The

    tires are 28 ply 44 x 16

    inch radials.

  • 8/12/2019 Some Assembly Required Dave Grant

    42/84

    This is the brake assembly. It is a multiple

    disc assembly. Just behind the brake is the

    bogie beam positioner which keeps thewheels level for landing.

  • 8/12/2019 Some Assembly Required Dave Grant

    43/84

    Measure with a micrometer, mark it with chalk, cut it with an ax.

    The landing gear doors are installed and trimmed to fit with the

    landing gear retracted into the wheel well.

  • 8/12/2019 Some Assembly Required Dave Grant

    44/84

    The complete fuselage supported by its own wheels.

  • 8/12/2019 Some Assembly Required Dave Grant

    45/84

  • 8/12/2019 Some Assembly Required Dave Grant

    46/84

    The wings were made off site, and

    brought to Marietta, GA by train.

  • 8/12/2019 Some Assembly Required Dave Grant

    47/84

    The wings are brought into the facility, and

    prepared for assembly. They are only a fuelcell at this point. The trailing edge and

    leading edge components will now be added.

  • 8/12/2019 Some Assembly Required Dave Grant

    48/84

    The facility was also being used forproduction of other airplanes at this time.

    The C-140 (JetStar) in the background

    was in the final production area. Later in

    the production of the C-141A, the C-5A

    production line was started.

  • 8/12/2019 Some Assembly Required Dave Grant

    49/84

    The trailing edges are

    being installed. Thisincludes the flap tracks.

  • 8/12/2019 Some Assembly Required Dave Grant

    50/84

    Once the trailing edge is attached to the wing,

    preparations are made for wing installation.

  • 8/12/2019 Some Assembly Required Dave Grant

    51/84

    The wing is in transit. If you notice the

    crane operator is in the little bucket up

    near the ceiling. At that time, the crane

    operator rode up there, now he walks

    on the floor with a long lead control box.

  • 8/12/2019 Some Assembly Required Dave Grant

    52/84

    Right wing is lowered into position,

    and will be aligned and mated tothe fuselage. Four tension bolts

    and chordwise splice joints hold the

    wing to the fuselage.

  • 8/12/2019 Some Assembly Required Dave Grant

    53/84

    Bringing the left wing into

    position for installation.

  • 8/12/2019 Some Assembly Required Dave Grant

    54/84

    The fuselage now has wings. Next will be

    the ailerons, engines and all the plumbing

    and wiring for the wings and engines.

  • 8/12/2019 Some Assembly Required Dave Grant

    55/84

    The ailerons are swung into position

    and installed.

  • 8/12/2019 Some Assembly Required Dave Grant

    56/84

  • 8/12/2019 Some Assembly Required Dave Grant

    57/84

    The engines are hung,

    and the necessary wiringconnected and routed

    back to the fuselage.

  • 8/12/2019 Some Assembly Required Dave Grant

    58/84

    Engine cowl door will be placed on the engine once the

    engine is completely installed on the pylon.

  • 8/12/2019 Some Assembly Required Dave Grant

    59/84

    Engine installed with cowl

    doors open. You can see the

    wiring, fuel and hydraulic

    lines running up the leadingedge of the pylon.

  • 8/12/2019 Some Assembly Required Dave Grant

    60/84

  • 8/12/2019 Some Assembly Required Dave Grant

    61/84

    The fuselage, wings, and

    engines are installed, now

    its time to work on the tail.

  • 8/12/2019 Some Assembly Required Dave Grant

    62/84

    Petal door being brought intoposition for installation. The cutout

    on the left end was where the

    auxiliary petal door was located.

    The first few models had this

    feature for the paratroopers to jump

    out. Unfortunately, they wouldbump their heads, so the door was

    eliminated, and they jump out the

    side doors now, or the back with

    the petal doors open to the air drop

    position.

  • 8/12/2019 Some Assembly Required Dave Grant

    63/84

  • 8/12/2019 Some Assembly Required Dave Grant

    64/84

    The petal doors are

    installed. As you can see

    inside the fuselage there is

    still a lot of work being done.

    The pressure door will be

    installed next.

  • 8/12/2019 Some Assembly Required Dave Grant

    65/84

  • 8/12/2019 Some Assembly Required Dave Grant

    66/84

    Horizontal stabilizer. Actually this is a test assembly

    used to ensure the T-tail could be attached to the

    airplane while inside the building.

  • 8/12/2019 Some Assembly Required Dave Grant

    67/84

    Vertical stabilizer. The

    horizontal stabilizer will be

    attached to the top of thisassembly in the fixture on

    the right side of this picture.

  • 8/12/2019 Some Assembly Required Dave Grant

    68/84

    Fully assembled horizontal stabilizer

    being moved into position for mating tovertical stabilizer.

  • 8/12/2019 Some Assembly Required Dave Grant

    69/84

    Once mated, the T-tail will

    be moved to the fuselage

    and installed as an

    assembly.

  • 8/12/2019 Some Assembly Required Dave Grant

    70/84

    During the mating process, thenose of the airplane was jacked

    approximately five feet off the

    ground to allow the crane operator

    to position the T-tail. Once

    attached, the airplane could sit

    normally on its wheels withadequate clearance for the T-tail.

  • 8/12/2019 Some Assembly Required Dave Grant

    71/84

  • 8/12/2019 Some Assembly Required Dave Grant

    72/84

    Before we get too far, we need to take the

    plane over to the paint barn and get allthe correct markings and insignias.

  • 8/12/2019 Some Assembly Required Dave Grant

    73/84

    Back from the paint barn, we have all themarkings. Final flight control rigging, and

    other cosmetic operations are being

    completed in preparation for roll out.

  • 8/12/2019 Some Assembly Required Dave Grant

    74/84

    August 22, 1963 the first C-141 airplane AF61-2775

    rolled out of the Marietta, GA facility

    The C-141 on display with

  • 8/12/2019 Some Assembly Required Dave Grant

    75/84

    The C 141 on display with

    a C-130 and C-47.

  • 8/12/2019 Some Assembly Required Dave Grant

    76/84

    First flight of the C-141 took place on December 17, 1963. The

    sixtieth anniversary of the Wright brothers first flight.

  • 8/12/2019 Some Assembly Required Dave Grant

    77/84

    The 285th C-141 built was made as acommercial demonstrator (designated

    the L300). It was acquired by NASA in

    March 1971, and modified to carry an

    airborne telescope.

  • 8/12/2019 Some Assembly Required Dave Grant

    78/84

    In December 1975, the C-141Awas brought to Marietta, GA for

    stretch modification prototype.

    This modification added 23 feet

    to the length of the airplane.

    271 airplanes were modified.

  • 8/12/2019 Some Assembly Required Dave Grant

    79/84

    In February 1979, the first

    MAC C-141s arrived formodification. At peak

    production, a rate of 10

    airplanes per month were

    being modified.

  • 8/12/2019 Some Assembly Required Dave Grant

    80/84

  • 8/12/2019 Some Assembly Required Dave Grant

    81/84

    July 18, 1979 the first stretched C-141 rolled out of the B1

    manufacturing facility. The first operational C-141B was

    assigned to Travis AFB, CA on April 11, 1980

    Some were equipped for

  • 8/12/2019 Some Assembly Required Dave Grant

    82/84

    Some were equipped for

    special missions.

  • 8/12/2019 Some Assembly Required Dave Grant

    83/84

    In 1997, the automatic flight controlsystem and flight instruments were

    upgraded to the glass cockpit. This

    created the C-141C model.

  • 8/12/2019 Some Assembly Required Dave Grant

    84/84