Solar PV project development

27
Green Intelligence at your side Rooftop Solar PV projects for landlords and investors What you should know prior to meeting a solar salesman Last Updated August, 2012

description

Presentation covers the different issues in setting up a rooftop solar photovoltaic project in Ontario. Things that are addressed is what should be included in feasibility study, different levels of involvement in your project, and risks and concerns during the project set-up and construction stage.

Transcript of Solar PV project development

Page 1: Solar PV project development

Green Intelligence at your side

Rooftop Solar PV projects for landlords and investors

What you should know prior to meeting a solar salesman

Last Updated August, 2012

Page 2: Solar PV project development

Agenda

• Ontario FIT2.0 program

• Property requirements for a solar PV project

• Different ownership models – roof lease, system ownership & ownership with development

• An overview of project progression from idea to commissioning

• Aspects of solar PV technology that affect property owner – financing and taxation

Copyright GreenQ Partners Inc 2

Page 3: Solar PV project development

FIT Program Overview

• Program started with the Green Energy Act in May 2009. New Rules were introduced in August 2012.

• Established rules under which businesses can sell to the grid electricity produced with renewable energy generation technologies, such as solar PV, wind, bio-energy

• Electricity is bought by the OPA on the basis of a 20-year fixed price contract

3Copyright GreenQ Partners Inc

Page 4: Solar PV project development

Ontario FIT Rates for PV

Copyright GreenQ Partners Inc 4

Project Size Rooftop, C$/kWh Ground, C$/kWh

≤10 kW 0.549 0.445

> 10 ≤ 100 kW 0.548 0.388

> 100 ≤ 500 kW 0.539 0.388

> 500 kW 0.487 0.35 (up to 5MW)

0.347 (over 5MW

Page 5: Solar PV project development

FIT Program Requirements

To qualify for FIT rates project must:

• Be located in Ontario

• Pass the transmission/distribution availability test

• 60% of implied project cost* should be incurred in Ontario

• Meet OPA’s size requirements per kW

* While determining compliance with domestic content requirement OPA assigns portions of costs to project activities and materials regardless of actual costs.

Copyright GreenQ Partners Inc 5

FIT

Page 6: Solar PV project development

Site suitability

Copyright GreenQ Partners Inc 6

RoofElectrical

Room

Location

Page 7: Solar PV project development

Suite Suitability - Roof

• Orientation

– South or South-West

• Roof space

– 40,000 sq ft => 250kW system– Other equipment may use up roof space

• Shading

– None or very little

• Roof condition

– Membrane should last at least for 20 years (ideally)

• Structural capacity

– Roof structure must allow for additional 3-7 psf load to accommodate dead and wind load and possible additional snow accumulation

7Copyright GreenQ Partners Inc

Page 8: Solar PV project development

How it looks

Copyright GreenQ Partners Inc 8

Ballasted mounting from SolarDock

Ballasted mounting from Unirac

Example of a penetrating mounting system

Page 9: Solar PV project development

Costs of Roof Imperfections

• Not true south orientation

– 10o off => 0.2% less energy

– 25o off => 1.5% less energy

• Below optimal tilt (<30o)

– 20o => 2.3% less energy

– 10o => 6.3% less energy

– Flat => 12.1% less energy (may lower costs)

• Dirt & snow on panels

– Higher tilt allows for better self cleaning

Copyright GreenQ Partners Inc 9

Page 10: Solar PV project development

Site Suitability - Electrical

• Electrical room

– Space for inverter, connector box,meter, disconnects, etc

– Equipment weight

– Equipment delivery constraints

• Sufficient distribution line to yourbuilding

Images are property of Satcom (top) and Xantrex.

10Copyright GreenQ Partners Inc

Page 11: Solar PV project development

Site Suitability - Location

• LDC capacity availability

– Pre-application consultation with LDC is required to determine if project can be connected

• Local weather conditions

– Snow belt area will have higher losses than Toronto

• Air cleanliness & dirt accumulation

– You only harness the sun that gets to the panels

11Copyright GreenQ Partners Inc

Page 12: Solar PV project development

How involved do you want to be?

Greater involvement leads to greater:

• Required investment

• Return on investment

• Risks

Develop & Ownthe system

Own the system

Lease roof

12Copyright GreenQ Partners Inc

Page 13: Solar PV project development

“Lease” Option

You invite a company to install, own and operate a solar system on your roof and charge them fixed lease payment.

• Investment required– No capital investment

– Legal and organisational costs, pre-application assessments

• Expected revenues: – Around $0.5 per sq ft of used roof per year

• Risks– Roof: Leakage, structural damage, roof traffic, conflicting use during 20 years

of contract,

– Default of your solar tenant

13Copyright GreenQ Partners Inc

Page 14: Solar PV project development

“Own” Option

You invite a company to develop and install a system; you collect payments for produced electricity from the OPA.

• Investment required– Around $4,500 per kW of installed system, capital and preparation costs

• Expected revenues

– $450-500 per kW pa on a commercial scale system (100-500kW AC)

– 11% IRR (100% equity financing)

• Risks

– Roof risks, same as in “lease” option

– Performance risks, maintenance risks

14Copyright GreenQ Partners Inc

Page 15: Solar PV project development

Owning a system:Performance Factors

PV technology

• c-Si panels produce more kWh/sft of roof

• Thin film panels are more tolerant to high temperatures, but less productive

• “Shadow resistant” panel designs help avoid some losses

Mounting

• Orientation: ideal is true South and 30° tilt

• Best performance tilt may be not cost effective due to wind load

• Higher tilt => more roof space required, lower tilt => lower wind load

• Roof warranty and mounting warranty

• Ease of temporary relocation

Inverter

• Efficiency, Cooling, Life expectancy

• Reliability, warranty, service

System design

• Losses in cables, due to panel heating, overshadowing, service needs, panel mismatch, etc

• Need for cleaning

• Downtime

• Array capacity vs. inverter capacity

Local conditions

• Local sun access conditions (shadow, smoke, dust, steam, etc)

15Copyright GreenQ Partners Inc

Page 16: Solar PV project development

“Develop & Own” Option

You develop an in-house team that can procure and install the system. The rest is the same as in Own Option. This option is most viable for owners of multiple rooftops.

• Investment required– Cost to setup in-house facility + per-system costs lower than in “own” option

• Expected revenues– $450-500 per kW pa on a commercial scale system

– 11% IRR (100% equity financing) on system

• Risks– Roof risks and Performance risks as in Own option

– Design and procurement (parts) risks

16Copyright GreenQ Partners Inc

Page 17: Solar PV project development

Sample Project

For a 40,000 sq ft, problem-free roof one can expect:

• System size of 250kW DC

• Investments:– Feasibility & Organizational costs - $10-30K (depending on project

complexity)– System cost (“own” option) - $1M

• Revenues– “Lease” revenue - $20,000 pa– “Own” revenue - $110,000 - $120,000 pa

• Bonus for “own” option – 50% depreciation rate on solar equipment; can used against other profits

Copyright GreenQ Partners Inc 17

Page 18: Solar PV project development

Project Progression

1. Project Assessment

– Evaluation of site suitability

– How involved do you want to be?

2. Project setup

– OPA Contract

– Developer Selection

– Project Financing

3. Construction & Operation

Highest impact decisions are made at project assessment stage

18Copyright GreenQ Partners Inc

Page 19: Solar PV project development

Project Setup - OPA Contract

• The party that owns roof access rights should apply for OPA contract

– The application fee is 0.5$ per kW (up to $5,000)

– Application security of $20 per kW is also required. Refundable if project goes into construction

• LDC approval for future system is required

• Contracts are granted based on priority points

• The processing time for an application varies, with “OPA target” of 60 days

19Copyright GreenQ Partners Inc

Page 20: Solar PV project development

Project Setup - Developer Selection

• Free assessment is never free and never unbiased

• Look at IRR and risks; not just cost or performance

• Warranties: for roof, equipment and performance; is developer worth the offered warranty? How is warranty going to work?

• Maintenance schedule: who, when, how

20Copyright GreenQ Partners Inc

The decision you are making will be binding for at least 20 years

Page 21: Solar PV project development

Project Financing

• Debt and equity financing is available from different sources

• CEPP Funding for Ontario organizations can be used to cover soft costs

• Bank loans may be obtained only for projects using bankable equipment

– Banks will typically finance up to 70% of cost for projects that meet their criteria

– Will require adequate project structure and documentation

21Copyright GreenQ Partners Inc

Page 22: Solar PV project development

Other Aspects of Project Setup

• Internal team set-up

– Technical and technology advisors

– Legal advisor

– Financial advisor

• Establishing project schedule and its impact on other activities

• DBF or DBFM approach

22Copyright GreenQ Partners Inc

Page 23: Solar PV project development

Construction – Major Concerns

• Who is responsible for damages to roof? To system?

– Cooperation with roofing company

• Permitting and unexpected fees

• Construction financing

• Interference with primary business

– Length of construction

– Scheduling

23Copyright GreenQ Partners Inc

Page 24: Solar PV project development

Operation – Major Concerns

• Roof warranties during operation

– Cooperation with roofer during construction

• Roof repairs

– Contractual provisions

• System repair and maintenance

– Defined maintenance plan

– Problem response – timing & warranties

– Value of monitoring system

Copyright GreenQ Partners Inc 24

Page 25: Solar PV project development

Taxation Considerations

• Income tax

– System costs are subject to 50% depreciation

– In some cases depreciation can be used against other income

• Property taxes

– System should be treated as “equipment”

– Rooftop PV should not affect property taxes

Copyright GreenQ Partners Inc 25

Page 26: Solar PV project development

Conclusion

For a landlord a solar PV project should not differ much from any other investment project:

• All investment rules apply

• No need to be a pro in solar to benefit from it

• To maximize return – stay within core competence and

assign direct solar risks to solar developer, who can

manage them at a lower cost

Copyright GreenQ Partners Inc 26

When done right, solar PV investment is like bond,

but with 11% IRR

Page 27: Solar PV project development

Copyright GreenQ Partners Inc 27

Questions