Solar-Assisted EV Charging Update

25
Solar-Assisted EV Charging Update TDEC Conference Kingsport, Tennessee March 13, 2013

description

 

Transcript of Solar-Assisted EV Charging Update

Page 1: Solar-Assisted EV Charging Update

Solar-Assisted EV Charging Update

TDEC Conference Kingsport, Tennessee March 13, 2013

Page 2: Solar-Assisted EV Charging Update

ORNL is DOE’s largest science and energy laboratory

$1.65B budget

World’s most intense

neutron source

4,400 employees

World-class research reactor

3,000 research guests

annually

$500M modernization

investment

Nation’s largest

materials research portfolio

Most powerful open

scientific computing

facility

Nation’s most diverse

energy portfolio

Managing billion-dollar U.S. ITER

project

2 Green Economy 1302

Page 3: Solar-Assisted EV Charging Update

3 Managed by UT-Battelle for the U.S. Department of Energy

3 Managed by UT-Battelle for the U.S. Department of Energy

Solar-Assisted EV Charging Project

•  In August 2009, ORNL was awarded $6.8 million for the installation of solar-assisted EV charging stations in Tennessee. This was part of a larger DOE grant to Ecotality for the deployment of EV charging stations in five states

•  The grant to ORNL required a 50/50 cost share match from regional partners. The majority of the cost share has been, or will be met, by the State of Tennessee, TVA, EPRI, and Nissan.

•  The final part of the cost share match is the State of Tennessee project.

•  We have also enjoyed great partnerships and in-kind support from the cities, distributors, and universities with whom we have worked.

Page 4: Solar-Assisted EV Charging Update

4 Managed by UT-Battelle for the U.S. Department of Energy

4 Managed by UT-Battelle for the U.S. Department of Energy

Levels of EV Charging

Voltage AC/DC

Time for Full Leaf Charge (24 kwh)

Range

Level 1 110 AC ~20 hours 4-5 miles per hour of charging

Level 2 220 AC ~7 hours 12 miles per hour of charging

Fast Charger

480 DC 30 minutes (for 80% charge)

80 miles per half-hour of charging

Page 5: Solar-Assisted EV Charging Update

5 Managed by UT-Battelle for the U.S. Department of Energy

5 Managed by UT-Battelle for the U.S. Department of Energy

Levels of EV Charging

Level 2 DC Fast Charger

Page 6: Solar-Assisted EV Charging Update

6 Managed by UT-Battelle for the U.S. Department of Energy

6 Managed by UT-Battelle for the U.S. Department of Energy

Regional Solar-Covered Parking Project Components

2.0 kw of solar per parking space

Electric vehicle

Charging system (EVSE) Level 2

External battery

Grid connection

Page 7: Solar-Assisted EV Charging Update

7 Managed by UT-Battelle for the U.S. Department of Energy

7 Managed by UT-Battelle for the U.S. Department of Energy

Locations of Solar-Assisted Charging in Tennessee

10 stations in Memphis

22 stations

10 stations

30 stations at Nissan

25 stations at ORNL 22 Stations

Knoxville and UTK

6 stations at EPRI

Original map overlays by Ecotality

Page 8: Solar-Assisted EV Charging Update

8 Managed by UT-Battelle for the U.S. Department of Energy

8 Managed by UT-Battelle for the U.S. Department of Energy

ORNL: 25 Solar charging stations

Page 9: Solar-Assisted EV Charging Update

9 Managed by UT-Battelle for the U.S. Department of Energy

9 Managed by UT-Battelle for the U.S. Department of Energy

Completed Installations ORNL/EPRI

Level 2 charges

12 kW solar PV

array

30 kWh battery bank

EPRI Installation 6-solar assisted stations 2 Clipper Creek level 2 chargers 2 EVSE LLC level 2 chargers 2 Eaton level 2 chargers

ORNL Installation 25-solar assisted stations http://ExtWebApps.ornl.gov/PVEV_ext

Blink level 2

chargers

47 kW solar PV

array

60 kWh battery bank

Page 10: Solar-Assisted EV Charging Update

10 Managed by UT-Battelle for the U.S. Department of Energy

10 Managed by UT-Battelle for the U.S. Department of Energy

Nissan HQ Solar-Assisted EV Charging Station, Franklin, TN

Page 11: Solar-Assisted EV Charging Update

11 Managed by UT-Battelle for the U.S. Department of Energy

11 Managed by UT-Battelle for the U.S. Department of Energy

Completed Installations NISSAN

Blink level 2

chargers

19kW solar PV

array

24 kWh battery bank

Franklin 18-solar assisted stations Smyrna, Administration Building 9-solar assisted stations

AeroViro-nment level 2

chargers

38 kW solar PV

array

24 kWh battery bank

Page 12: Solar-Assisted EV Charging Update

12 Managed by UT-Battelle for the U.S. Department of Energy

12 Managed by UT-Battelle for the U.S. Department of Energy

Completed Installation Nissan: 3 solar assisted stations

Blink level 2

chargers

6.5 kW solar PV

array

24 kWh battery bank

Battery Plant, Smyrna

Page 13: Solar-Assisted EV Charging Update

13 Managed by UT-Battelle for the U.S. Department of Energy

13 Managed by UT-Battelle for the U.S. Department of Energy

Completed Installation Nashville: 8 solar assisted stations

Blink level 2

chargers

17.2 kW solar PV

array

13 kWh battery bank

LP Field – Sports Authority

Page 14: Solar-Assisted EV Charging Update

14 Managed by UT-Battelle for the U.S. Department of Energy

14 Managed by UT-Battelle for the U.S. Department of Energy

UT Agriculture Campus

Completed Installation UT-Knoxville: 6 solar assisted stations

Blink level 2

chargers

14.4 kW solar PV

array

10 kWh battery bank

Page 15: Solar-Assisted EV Charging Update

15 Managed by UT-Battelle for the U.S. Department of Energy

15 Managed by UT-Battelle for the U.S. Department of Energy

University of Tennessee, Knoxville: 12 solar-assisted charging stations

Blink level 2

chargers

14.4 kW solar PV arrays

10 kWh battery banks

Page 16: Solar-Assisted EV Charging Update

16 Managed by UT-Battelle for the U.S. Department of Energy

16 Managed by UT-Battelle for the U.S. Department of Energy

Civic Coliseum, Knoxville: 6 solar-assisted charging stations

Blink level 2

chargers

14.4 kW solar PV

array

6.7 kWh

battery bank

Solar panels Ribbon cutting, September 2012

Page 17: Solar-Assisted EV Charging Update

17 Managed by UT-Battelle for the U.S. Department of Energy

17 Managed by UT-Battelle for the U.S. Department of Energy

Blink level 2

chargers

10 kW solar PV

array

8.4 kWh

battery bank

Solar panels location

Market Square Garage, Knoxville: 4 solar-assisted charging stations

Charging station

Page 18: Solar-Assisted EV Charging Update

18 Managed by UT-Battelle for the U.S. Department of Energy

18 Managed by UT-Battelle for the U.S. Department of Energy

State Of Tennessee Site Nashville: 4 solar-assisted charging stations

Blink level 2

chargers

8.6 kW solar PV

array

6.7 kWh

battery bank

4th and Harrison

Page 19: Solar-Assisted EV Charging Update

19 Managed by UT-Battelle for the U.S. Department of Energy

19 Managed by UT-Battelle for the U.S. Department of Energy

Completed Installation Vanderbilt University: 10 solar-assisted

charging stations

Eaton level 2

chargers

20 kW solar PV

array

3 kWh battery bank

Page 20: Solar-Assisted EV Charging Update

20 Managed by UT-Battelle for the U.S. Department of Energy

20 Managed by UT-Battelle for the U.S. Department of Energy

Completed Installation Chattanooga: 6 solar-assisted charging stations

Eaton level 2

chargers

12 kW solar PV

array

3.0 kWh

battery bank

Theater Group

Page 21: Solar-Assisted EV Charging Update

21 Managed by UT-Battelle for the U.S. Department of Energy

21 Managed by UT-Battelle for the U.S. Department of Energy

Completed Installation Memphis: 10 solar assisted stations

Eaton level 2

chargers

20 kW solar PV

array

3.0 kWh

battery bank

Shelby Farms

Page 22: Solar-Assisted EV Charging Update

22 Managed by UT-Battelle for the U.S. Department of Energy

22 Managed by UT-Battelle for the U.S. Department of Energy

ORNL,  Q3,  Leaf  

0

50

100

150

200

250

0 10 20 30 40 50 60 70 80 90 100

Freq

uenc

y

Percentage of EV Battery Filled per Charge (%)

Percentage of Nissan Leaf Battery Filled per Charge

DATA ANALYSIS AT ORNL

Drivers at ORNL tend to arrive with their Leaf batteries 40% depleted

Page 23: Solar-Assisted EV Charging Update

23 Managed by UT-Battelle for the U.S. Department of Energy

23 Managed by UT-Battelle for the U.S. Department of Energy

Locations of DC Fast Chargers in Tennessee

Existing

Original map overlays by Ecotality

Page 24: Solar-Assisted EV Charging Update

24 Managed by UT-Battelle for the U.S. Department of Energy

24 Managed by UT-Battelle for the U.S. Department of Energy

Locations of DC Fast Chargers in Tennessee

Existing

Future Original map overlays by Ecotality

Page 25: Solar-Assisted EV Charging Update

25 Managed by UT-Battelle for the U.S. Department of Energy

25 Managed by UT-Battelle for the U.S. Department of Energy

Project Priorities

•  Add DC Fast Charging along the I-40 corridor (to NC state line)

•  Add DC Fast Charging in metropolitan areas

•  Add Level 2 Charging in metropolitan areas