Solar and Storage Orchestration to defer Distribution Augmentation · 13.06.19 Solar and Storage...
Transcript of Solar and Storage Orchestration to defer Distribution Augmentation · 13.06.19 Solar and Storage...
Solar and Storage Orchestration to defer Distribution Augmentation
13 June 2019
Australian Solar Storage Conference and Exhibition
Acknowledge
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
United Energy acknowledges funding support for this Project from the Australian Renewable Energy Agency (ARENA) as part of ARENA's Advancing Renewables Programme.
13.06.19
United Energy
Solar and Storage Orchestration to defer Distribution Augmentation
United Energy
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
United Energy is a regulated Victorian electricity distribution business that supplies electricity to approximately 680,000 customers across Melbourne’s eastern suburbs, south eastern suburbs and the Mornington Peninsula. United Energy delivers electricity to homes and businesses in a 1,472 square kilometre area, or around 450 customers per square kilometre.
A CK Infrastructure-led consortium owns 66 per cent of United Energy with the balance owned by SGSP (Australia) Assets Pty Ltd.
United Energy Service Area
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
Item Value
Peak coincident demand (summer 2016/17) 1,858 MW
Record peak coincident demand (summer 2008/09) 2,084 MW
Poles 215,500
Overhead lines 10,043 km
Underground cables 2,834 km
Sub-transmission lines 78
Zone substation 47
Zone substation transformers 112
Distribution feeders 445
Distribution transformers 13,500
13.06.19
Residential Solar Storage Programme
Solar and Storage Orchestration to defer Distribution Augmentation
Content
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
• Objectives
• Key Milestones
• Approach
• Customer Engagement Strategy and Principles
• Typical Customer Installation
• Control Strategy
• Dispatch Results (2018 and 2019)
• Innovation, Benefits and Lessons Learnt
• Conclusions
Objectives
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
• Deployment and testing of Solar and Storage systems across United Energy’s
selected constrained substations to demonstrate their capability to be used as
an alternative to traditional augmentation.
• United Energy and other Utility Benefits
Increase efficiency and reduce network costs at constrained substations.
Deferral of augmentation.
Confidence in replicating similar solutions.
• Customer benefits
Reduce peak demand and network costs.
Energy arbitrage offered by the systems.
Key Milestones (2017 – 2019)
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
• Customer engagement strategy – May 2017.
• Customer marketing – June 2017, October 2017 and February 2018.
• Customer registration – June 2017 to March 2018.
• Site assessments and customer engagement (Q&A) – July 2017 to March 2018.
• Customer Contract execution – July 2017 to March 2018.
• Installation – July 2017 to May 2018.
• Development of operational protocols – July 2017 to March 2018.
• Systems dispatched during summer – December 2017 to March 2018, December 2018
to March 2019.
• Final Report – 30 June 2019.
Approach
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
• United Energy completed an analysis of the 2016/2017 summer data to
identify substations which are overloaded.
• Customers located in constrained substations targeted to reduce demand and
manage outages and equipment life over the coming summers.
• Customer engagement strategy prepared and executed.
• 1500 customers targeted across constrained substations. 150 customers
registered. 85 proposals prepared and submitted to customers.
• Comprehensive investigation into system specifications completed – selected
solar PV system with optimisers (15 Jinko Solar Panels X 270 W = 4 kW,
LGChem RESU10 battery (9.8 kWh), Sungrow SH5k (5 kW) inverter and
Reposit Power equipment as the least-cost lifecycle option for the Program.
• Reviewed a number of technology providers for the installation work selecting
a preferred installer.
Customer Engagement Strategy
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
Personalised Letters to customers via mail.
Dedicated Registration Website and email for correspondence.
Dedicated phone line to discuss questions/queries on any aspect of the
Program.
Submission of a customer personalised proposal containing roof space
analysis, details on the Solar Storage system, description of how the system
would work, estimated energy mix for the customer property, environmental
benefits, customer savings, cost of the proposed system to be borne by the
customer and contract agreement for consideration. This ensured the
customer received a clear and transparent proposal facilitating a valued
decision to proceed or not.
Selection of a preferred installer for installation of the Solar Storage systems.
Customer Engagement Principles
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
Consistency (in communication channels deployed).
Continuity (seamless interaction with communication channels).
Customisation (personalised proposals).
Transparency – Marketing was undertaken to all residential customers residing within a
chosen constrained distribution substation.
Commitment – UE ensured customer questions/queries were addressed fully to enable them
to make their decision.
Timely and Meaningful – UE articulated clearly the purpose of the Program and were flexible
with engagement methods (website, phone conversation, personal meetings) to provide two
way communication.
Accountable – Customers were provided with an easy to read and understand contract. The
engagement methods provided, enabled customers to have their queries answered.
Measurable – The customer engagement approach was refined during the Project to
address feedback being received from initial customer engagement.
Typical Customer Installations
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
Control Strategy
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
• For days when temperature is less than 35°C, the offset demand control strategy as below will be implemented across the selected constrained substations.
• For days when temperature is greater than 35°C, the network support control strategy below will be implemented across the selected constrained substations.
Time Control Comment
All day Offset Demand
Offset demand control is the typical customer mode which
seeks to limit exports to the network and maximise self-
consumption of solar PV generation. The batteries and
solar PV systems will be used to firstly offset customer
usage. The batteries will only charge from excess solar PV
generation which is not used by the customer.
Time Control Comment
All day Network Support
Ensure battery is charged prior to the weather event
condition. On the weather event condition day, ensure
battery is discharged between a selected duration (e.g. 5pm
and 8pm; or 4pm to 7pm) with due consideration to limits on
battery State of Charge (SOC). For Solar PV, limit export to
network and maximise self-consumption.
Average Dispatch Performance – 23 Jan 2019
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
Maximum Temperature: 25°C
Average Dispatch Performance – 24 Jan 2019
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
Maximum Temperature: 37°C
Average BESS State of Charge – 24 Jan 2019
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
Dispatch Results 3 Jan 2019 – 16°C to 29°C (Normal Day)
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
On a normal day (03
January 2019), a maximum
reduction in demand of up to
6.6% was achieved (52.16
kW down to 48.73 kW).
When in Offset Demand
mode, the solar PV
generation is used to first
meet household
consumption, with excess
generation used to charge
the battery, with any
additional excess generation
exported to the grid.
Dispatch Results 6 Jan 2018 (42°C)
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
6 Jan 2018 (42°C)
Dispatch on 6 Jan 2018 achieved a 7% reduction
in demand which in effect will defer augmentation
by 7 years.
Advantage of Solar and Storage system is the
ability to incrementally add to the network to
continue achieving deferral of augmentation.
For Network support mode, battery pre-charges
overnight to allow solar energy to support
network during the day.
Battery exports full capacity in the early evening
during peak demand when solar output reduces.
Test on 6 Jan 2018 demonstrated that solar
storage can address network constraints.
Dispatch Results 7 Jan 2018 (22°C)
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
7 Jan 2018 (22°C)
The impact of Solar PV should be noted during
the middle of the day.
When Solar PV generation is high, demand is
reduced and excess solar generation is used to
charge the battery.
When demand increases in the evening, battery
commences discharging to support the increased
demand maximising customer benefits.
For energy arbitrage mode, battery charges from
solar energy during the middle of the day.
Innovation & Benefits
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
United Energy owner with customer approval for deployment during peak
demand days.
Customers benefit with lower electricity bills with exposure to Solar and
Storage systems.
Solar and Storage systems can be an economic network augmentation
alternative, in certain instances. Networks can potentially procure such a
solution to achieve prudency of investment and reduce network costs for
customers.
Improved quality of Supply.
This Program highlights the value of renewable energy and storage
systems to regulators and policy makers, to enable them to establish
appropriate frameworks to encourage increased customer take-up.
Lessons Learnt
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
Batteries are discharging as expected but require accurate forecasting to
shave peak demand.
Insufficient roof space and shading are the two most common criteria
resulting in elimination of ineligible sites. (To streamline process assessments
are done using google maps data).
Need to assess types of roof tiling and the need to source spare roof tiles
(roof tiles being cracked as part of the installation is common). (Installers
prearrange supply of tiles prior to commencing installation).
Wi-Fi connectivity at some sites has posed issues. (During site visits, details
on Wi-Fi connections are being gathered to ensure installation proceeds
smoothly).
Initial installations took 2 days to complete with subsequent installations
undertaken in a day as the installers became more familiar with equipment
and installation requirements. (Plan is to utilise existing installers to complete
additional installations).
Lessons Learnt – Continued
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
Some installations required installation of concrete slabs which increased the
installation time. (Installers are now advised of this immediately after the site
visit to fast track installation).
Ideal sites are those with a west or north facing roof with no shading from
surrounding trees. Ensure the roof is clear of flu pipes, antennas or satellite
dishes on the face where panels are to be installed. (This is assessed during
the site visit).
The batteries should be installed close to the switchboard and solar panels to
minimise the length of the AC and DC cable runs. (This is assessed during
the site visit).
Ensure switchboard has sufficient spare terminals to accommodate the critical
load and VT/CT reference MCCBs. (This is assessed during the site visit).
It is essential to engage a reliable installer to ensure installations are
completed in a timely manner and any issues identified are rectified quickly.
Lessons Learnt – Continued
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
Reliability of components (i.e., inverter as power conversion equipment
typically has a high rate of failures at the beginning - 2 installations had to
have their inverters replaced due to failure).
Extensive monitoring of the battery systems such as voltage, temperature,
current as well as redundant monitoring and control in terms of a fail-safe
battery management system is crucial for a safe operation of the System to
minimise the risk of a thermal run-away.
A control challenge in most applications is the accuracy of the State of Charge
(SoC) value. The uncertainty in SoC estimation therefore needs to be
considered in all control strategies which aim at managing SoC. The typical
limited Storage capacity needs careful management of SoC levels.
It is necessary to implement a Life Cycle Strategy to address the operations
and maintenance of the Solar Storage systems over the contract period.
Conclusions
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation
• This Program has involved recruiting a large base of customers across a
number of constrained sub-stations to reduce constraints on the selected
constrained sub-stations. This has allowed United Energy to halt growth and
defer network augmentation across the selected constrained substations.
• Customer Lessons:
Duration of Contract.
Ownership of the system.
Unfamiliarity with technology.
Upfront payment.
Questions
13.06.19 Solar and Storage Orchestration to defer Distribution Augmentation