Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM...

28
30.04.2014 Soil improvement techniques - Bypass Mechelen W. Maekelberg Manager Unit Soil&Water Design department TUC Rail n.v. Belgium

Transcript of Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM...

Page 1: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

30.04.2014

Soil improvement

techniques - Bypass

Mechelen

W. Maekelberg

Manager Unit Soil&Water – Design department

TUC Rail n.v. Belgium

Page 2: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Railwaynet in Belgium anno 1933

Page 3: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Mechelen station

Mechelen (1835) the first trainstop for passengers

Centre of first railwaynet in Belgium

Page 4: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Mechelen station

Mechelen

Antwerp

Brussels

To Liège

Ghent

Page 5: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Mechelen station

Model of old station building (1888)

Renewed in 1955 in

modern building

with 10 plateforms

Page 6: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Projectscope : Road & railway extension

6

Railway extension :

• Increase in line-speed

• Bypass Mechelen station

Part of agreement Belgium-

Netherlands for HSL link

Brussels-Amsterdam

Page 7: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Different project zones 10/20/30

103020

Railway extension project: integrated with• New station and underground parking facilities

• New road access and connections

• Bicycle / walkway network

Page 8: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Some data on foundations/retaining walls

Piled foundations:

• CFA piles with enlarged hollow stem: 1.430 piles

• Cast in situ driven piles: 1.296 piles

• Tubular screw injection piles: 310 piles

• Closed end driven tubular piles: 51 piles

• Stone column soil improvement: 270 columns

• Open end tubular piles, micropiles, cased CFA-piles, …

Retaining walls:

• Sheet piles (permanent): 900 tons

• Combiwall: 750 tons

• Diaphragm wall: 2.200 m3

• Cutter soil mix: 10.000 m2

• Berliner walls, secant pile walls, soil nailing

• Permanent/temporary ground anchors/soil nails: > 1000

8

Page 9: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Railway extension project: integrated with• New station and underground parking facilities

• New road access and connections

• Bicycle / walkway network

Stone columns

Stone column soil improvement

Soil mix

Page 10: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Dry bottom feed vibro replacement:

• Relief soil pressure on

sheet piles (50% less anchors)

Stone column soil improvement

10

Permanent tiebacks

Sheet piles

Page 11: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Stone column soil improvement

11

Tiebacks between rows of columns (unbonded length)

Sheet piles

Dry bottom feed vibro

replacement stone

columns

Permanent tiebacks

Backfill : 2.5mRelief vertical load on anchors when

loaded by new embankment

Page 12: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Stone columns – hydrologic influence

12

• Two aquifers which must remain

separated (dry concrete plugging)

• Rise in groundwater head during

installation (which quickly dissipates)

Dry concrete

Page 13: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Stone columns – design

13

Design according to Priebe method

• Settlement reduction (stiffer equivalent modulus used)

FEM with plaxis model to compare

F.E.M. (PLAXIS-axisemmetry

(K=1)) does not take into

account installation effects

Page 14: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Installation effects within group

14

CPT’s: 4 weeks after

column installation

No influence

beneath columns

Initial CPT

CPT’s mid

between

columns No change in qc in clay layer!

4 x qc in loose sand

Compacted working platform

CPT-position

Page 15: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Installation effects next to group

15

CPT’s: 4 weeks after

column installation

No influence

beneath columns

Initial CPT

CPT’s next

to soil

improvement

(axis of

sheet piles)

No change in qc in clay layer!

2 x qc in loose sand

Compacted working platform

CPT-position

Page 16: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Stone columns – QC/QA

16

CPT’s through column centre to check compaction/presence of dry

concrete (and level)

Page 17: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix soil improvement

CSM

Railway extension project: integrated with• New station and underground parking facilities

• New road access and connections

• Bicycle / walkway network

Stone columns

Page 18: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix soil improvement

Cutter soil mix:

• Retaining wall

• Water (cut-off) wall

• Soil improvement

18

Page 19: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix soil improvement

19

Transverse lamellae of CSM

is used as

strut wall between diaphragm

walls

Page 20: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix soil improvement

20

Soil mix lamellae

Diaphragm walls

Existing railway bridge

Page 21: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix soil improvement – design

21

Design with Plaxis 2D model

• CSM Lamellae executed prior to excavation

• Reduction of displacements, bending moments (-50%) and strut loads

Existing railway bridge

Soil improvement (with

equivalent c, φ and E)

Anchor

before the

section

Page 22: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix soil improvement – design

22

Execution aspect:

Soil void between

diaphragm wall and

csm wall

Top view:Applied pressure from 2D

plane strain cross-section

csm wall

Concentrated forces

Page 23: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix soil improvement – on site

23

Page 24: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix – QC/QA

24

Vertical core drilling in

hardened test pile

Relation qc ~ qsu?

Page 25: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix – QC/QA

25

Wet grab & horizontal core

drillings: larger scatter

Wet grab at depth with

sealed container during

production

Page 26: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix – QC/QA

26

87 test results -

combined

methods

Page 27: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Soil mix – QC/QA

27

UCS ~ E falls within

average & lower limit

Page 28: Soil improvement techniques - Bypass Mechelen · 2018-06-27 · Design with Plaxis 2D model • CSM Lamellae executed prior to excavation • Reduction of displacements, bending moments

Thank you for your attention!!

28