![Page 1: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/1.jpg)
Soil Excavation and Concrete Penetration Permitting Process at LLNL
Dennis ChewPlant Engineering Department
September, 2006
UCRL-PRES-224319This work performed under the auspices of the U.S. Department of Energy by the University of California, Lawrence Livermore
National Laboratory, under Contract No. W-7405-ENG-48
![Page 2: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/2.jpg)
4
![Page 3: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/3.jpg)
![Page 4: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/4.jpg)
![Page 5: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/5.jpg)
Brief History
Began with the purchase of LLNL’s first Audio Frequency instrument in the early 1990. Proactive step taken by LLNL as a result of an increasing number of utility
strikes Locates were performed out of the Craft Shop of Plant Engineering External building Locates
Between 1990 and 1998 Permit Process Documents Internal & External building Locates 30” No Dig rule Ferromagnetic scanners & Ground Penetrating Radar (GPR)
Between 1999 and 2000 Established Permit Database – issuing paper permits LLNL “One Call” center concept
Mindset / Purpose Preventing unplanned outages Reducing unplanned project costs Safety
![Page 6: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/6.jpg)
Where we are at today
Permit Office has grown Size and responsibility Improved database tracking methods Two types of permits
• Soil Excavation and Concrete Penetration
Mindset / Purpose Preventing unplanned outages and reducing unplanned project costs Safety Culture shift
Today the permit office issues an average of 60 permits per month
Education/Training 3rd party certification required Safety Video
Incorporating new technologies Radio/Audio, GPR, and ferro-magnetic scanning Marker Ball program (open trench)
• Integrating with the Facility Information Center
![Page 7: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/7.jpg)
The Permit Process
Responsible Individuals LLNL employees who serve as the point of contact Partnering with the Permit Office to ensure compliance Annual training requirement
Permit Office Locators
• Perform the locates and add any comments they may have on the permit – resources include As-builts / construction drawings / Utility drawings, etc…
Issue the permit upon receiving all approvals• Regulatory approvals • Utility Owner approvals• Signature Approvals
Job site field visits• Compliance Inspections
Permit Closure• Archived into the Permit database
![Page 8: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/8.jpg)
The Permit Process
Utility Location Database
Locate Findings / Field Markings
![Page 9: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/9.jpg)
Locating Instruments
![Page 10: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/10.jpg)
Programmable Marker Ball Program
![Page 11: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/11.jpg)
Documentation and Configuration Management
Governing procedures for the permit process
Continually evolving Lessons Learned & Process Improvement Customer feedback Staying ahead of the game
On-going Communication Roll-out meetings and newsletters Eyes and Ears in the field
Partnering with the Utility owners Provide up to date utility documentation Involve them in the approval process as owners
PROC-CON 0002 Concrete Penetration PROC-CON 0003 Soil Excavation
![Page 12: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/12.jpg)
Safety Integration
* * Safety Video * ** * Safety Video * *
* * Job Safety Analysis * ** * Job Safety Analysis * *
* * Locator Field Survey * * * * Locator Field Survey * *
* * Pre-Task Hazard Analysis * ** * Pre-Task Hazard Analysis * *
* * Compliance Inspections * ** * Compliance Inspections * *
* * Outage Requirement * ** * Outage Requirement * *
* * 30” No Dig Zone * ** * 30” No Dig Zone * *
![Page 13: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/13.jpg)
Closing Thoughts
InnovativeThinking
Continued Awareness Of the Safety Culture
Partnering
![Page 14: Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work.](https://reader036.fdocuments.us/reader036/viewer/2022081519/56649f445503460f94c64d69/html5/thumbnails/14.jpg)
Q & A