Software Project Management
description
Transcript of Software Project Management
Cristina Mîndruţă Software Project Management Slide 1
Software Project Management
Course 5
Cristina Mîndruţă Software Project Management Slide 2
COURSE TOPICS
PLANNING PROCESS GROUP.
Time management planning processes Activity definition Activity resource estimating Activity duration estimating Activity sequencing Schedule development
PLANNING PROCESS GROUP.
Management plan processes
Time management planning processes.
Cost management planning processes
Quality planning
HR planning
Communications planning
Risk management planning
Procurement management planning
Cristina Mîndruţă Software Project Management Slide 3
COURSE TOPICS
PLANNING PROCESS GROUP.
Time management planning processes Activity definition Activity resource estimating Activity duration estimating Activity sequencing Schedule development
PLANNING PROCESS GROUP.
Management plan processes
Time management planning processes.
Cost management planning processes
Quality planning
HR planning
Communications planning
Risk management planning
Procurement management planning
Cristina Mîndruţă Software Project Management Slide 4
SCHEDULE DEVELOPMENT process
Def. Project schedule = set of planned dates for performing schedule activities and the planned dates for meeting schedule milestones.
Def. Project schedule process = iterative process that determines planned start and finish dates for project activities.
Cristina Mîndruţă Software Project Management Slide 5
SCHEDULE DEVELOPMENT process
Schedule Development process:
Analyzes:
- schedule activities sequences
- schedule activity durations
- schedule resource requirements
- schedule constraints Creates the project schedule.
Result: Are established the preliminary start and finished dates for project
activities, based on schedule-related assumptions and constraints identified within the PSS.
Obs. As work progresses, the PMP will likely change, and new risks will be identified.
Cristina Mîndruţă Software Project Management Slide 6
SCHEDULE DEVELOPMENT process
Schedule Development – evolving process
Main output:
Schedule Baseline = approved project schedule
against which project progress can be tracked.
Presentation methods for the project’s schedule:
- Milestone schedule
- Summary schedule
- Detailed schedule with logical relationships
Additional outputs:Schedule Model Data – supporting details:
identified assumptions and constraints
alternative schedules
extra time available, if neededRequested Changes documentUpdated Resource RequirementsUpdated Activity AttributesUpdated Project CalendarUpdated PMP with its associated Schedule Management Plan
Cristina Mîndruţă Software Project Management Slide 7
COURSE TOPICS
TOOLS AND TECHNIQUES FOR SCHEDULING Methods Gantt chart characteristics Critical Path Method integrated with PERT
PLANNING PROCESS GROUP.
Management plan processes
Time management planning processes.
Cost management planning processes
Quality planning
HR planning
Communications planning
Risk management planning
Procurement management planning
Cristina Mîndruţă Software Project Management Slide 8
METHODS
Gantt chart
Activity – time diagram.
Simple model.
Limitation: for complex projects, models that integrate procurement, resources and costs are necessary.
A
C
T
I
V
I
T
Y
TIME
Cristina Mîndruţă Software Project Management Slide 9
METHODS
PERT diagram (program evaluation and review technique) Is a network diagram. Activities are represented as boxes. Placed in sequence, to represent the project flow.
Uses statistic instruments to compute the range of the possible values for activities durations.
Used in cases where uncertain, multiple possible values exist for the estimated durations.
Cristina Mîndruţă Software Project Management Slide 10
METHODS
CPM (Critical Path Method)
Network representation.
Allows identifying a sequence of consecutive activities that represent the longest path along the project schedule.
Used in cases where exact estimations can be realized about activities durations.
Cristina Mîndruţă Software Project Management Slide 11
METHODS
DISCUSSION In time, differences between PERT and CPM methods where dimished.In the same time with the evolution of milestone-based planification, some aspects of PERT are introduced with CPM.In software tools for planning, PERT and CPM are integrated.
Def. Milestone = planned event in the project life cycle. • Formal represented as an activity with the duration equal to 0. • Marks the end of an activity or of a project phase.• Helpful in controlling the fulfillment of the contractors’
responsibilities.
Def. Time baseline = Initial schedule of the project.• Used as the referece for comparing the current planification.
Cristina Mîndruţă Software Project Management Slide 12
COURSE TOPICS
TOOLS AND TECHNIQUES FOR SCHEDULING Methods Gantt chart characteristics Critical Path Method integrated with PERT
PLANNING PROCESS GROUP.
Management plan processes
Time management planning processes.
Cost management planning processes
Quality planning
HR planning
Communications planning
Risk management planning
Procurement management planning
Cristina Mîndruţă Software Project Management Slide 13
GANTT CHART CHARACTERISTICS
activity activity duration
activity float (lag)
activity start dateactivity end date
Cristina Mîndruţă Software Project Management Slide 14
GANTT CHART CHARACTERISTICS
Tool for project planning. Project progress is clearly represented. Gantt diagram format facilitates planning information communication and decission
making.
Def. Float (slack) = the amount of time that a terminal element (in a (WBS) can be delayed by, without causing a delay to the rest of the project.
Gantt chart allows float representation, but:
- inter-task relations are not represented => not visible the effects that the delaying of an activity have on other activities
- before placing an activity on the diagram, decissions about sequencing, duration and resources availability must be taken.
Problem. Gantt charts are not appropriate for complex projects.
Solution. Used in combination with CPM.
Cristina Mîndruţă Software Project Management Slide 15
COURSE TOPICS
TOOLS AND TECHNIQUES FOR SCHEDULING Methods Gantt chart characteristics Critical Path Method integrated with PERT
PLANNING PROCESS GROUP.
Management plan processes
Time management planning processes.
Cost management planning processes
Quality planning
HR planning
Communications planning
Risk management planning
Procurement management planning
Cristina Mîndruţă Software Project Management Slide 16
CRITICAL PATH METHOD integrated with PERT
METHOD objectives:
Activity sequencing (Create activity diagram (activity graph)) Realize PERT analysis for task duration Identifiy critical path
Procedure steps:
1. Create project activity diagram (project network)
2. Estimate activity duration
3. Create activity plan
4. Critical path determination
Cristina Mîndruţă Software Project Management Slide 17
CRITICAL PATH METHOD integrated with PERT
A project network is a graph or flow chart (a schematic representation of an algorithm or a process) depicting the sequence in which a project's terminal elements are to be completed by showing terminal elements and their dependencies.
The WBS show the "part-whole" relations. In contrast, the project network shows the "before-after" relations.
The condition for a valid project network is that it doesn't contain any circular references.
Procedure steps:
Create project activity diagram (project network)
Estimate activity duration
Create activity plan
Critical path determination
Cristina Mîndruţă Software Project Management Slide 18
CRITICAL PATH METHOD integrated with PERT
Activity flow.
Each activity has allocated an identifier (number).
Procedure steps:
Create project activity diagram (project network)
Estimate activity duration
Create activity plan
Critical path determination
Float types:
a). Free float = the amount of time that a terminal element can be delayed by, without causing a delay to the subsequent activities
b). Total float = the amount of time that a graph branch can be delayed by, without causing a delay to the whole project.
- sum of the floats of all activities on the branch
- can be redistributed among all activities on the branch
Cristina Mîndruţă Software Project Management Slide 19
CRITICAL PATH METHOD integrated with PERT
Represent activity time attributes as:
Procedure steps:
Create project activity diagram (project network)
Estimate activity duration
Create activity plan
Critical path determination
Early start Early finish
Late start Late finish
ES, EF - governed by:
- predecessor task EF - current task duration
LS, LF - governed by:
- successor task LF - current task duration
Cristina Mîndruţă Software Project Management Slide 20
CRITICAL PATH METHOD integrated with PERT
Represent activity network :
Procedure steps:
Create project activity diagram (project network)
Estimate activity duration
Create activity plan
Critical path determination
Assumptions:
ES(0) = first activity start
For each consecutive activities k, k+1:
EF(k) = ES(k) + duration(k) –1
ES(k+1)=EF(k)+1
LS(k)=LF(k)-duration(k)+1
LF(k)=LS(k+1)-1Forward pass:
Cover the diagram from left to right and compute ES and EF for each task.
EF(n) = project finish date.
Backward pass:
LF(n)=EF(n) = project finish date.
Cover the diagram from right to left and compute LS and LF for each task.
Cristina Mîndruţă Software Project Management Slide 21
CRITICAL PATH METHOD integrated with PERT
RESULTS:
Activity plan analysis => project duration.
Float(k)=LF(k)-ES(k)-duration(k)
If Float(k)=0 => activity k is on the critical path, meaning that its delay results in the delay of the project.
Procedure steps:
Create project activity diagram (project network)
Estimate activity duration
Create activity plan
Critical path determination
Cristina Mîndruţă Software Project Management Slide 22
CRITICAL PATH METHOD integrated with PERT
CPM advantage:
- discover new relations among activities
- compute the probability to match project’s deadlines
- establish how changes modify the project
- presents complex data in an orderly manner.
The most popular form of project network is activity on node (AoN), the other one is activity on arrow (AoA).
Cristina Mîndruţă Software Project Management Slide 23
EXAMPLE (AoN representation)
Simplified node representation
Cristina Mîndruţă Software Project Management Slide 24
EXAMPLE (AoN representation)
Simplified node representationForward pass:
Cover the diagram from left to right and compute ES for each task.
duration(start)=0
ES(k+1) = ES(k) + duration(k).
Cristina Mîndruţă Software Project Management Slide 25
EXAMPLE (AoN representation)
Simplified node representation
Backward pass: Cover the diagram from right to left and compute LS for each task.
ES(finish)=LS(finish)
LS(k)=LS(k+1)-duration(k)
Cristina Mîndruţă Software Project Management Slide 26
EXAMPLE (AoN representation)
Simplified node representation
Compute float:
Float(k)=LS(k)-ES(k)
Cristina Mîndruţă Software Project Management Slide 27
EXAMPLE (AoN representation)
Simplified node representation
Critical path
Project duration:
20 +15 +16 = 51
ANALYSIS
If Float(k)=0 => activity k is on the critical path, meaning that its delay results in the delay of the project.
Cristina Mîndruţă Software Project Management Slide 28
COURSE TOPICS
PLANNING PROCESS GROUP.
Cost management planning processes
Cost estimating
Cost budgeting
PLANNING PROCESS GROUP.
Management plan processes
Time management planning processes.
Cost management planning processes
Quality planning
HR planning
Communications planning
Risk management planning
Procurement management planning
Cristina Mîndruţă Software Project Management Slide 29
COST MANAGEMENT PLANNING PROCESSES
Cost estimating process
Cost budgeting process
Closely interrelated.
Cost estimating should be completed before a detailed budget is requested.
Management is concerned in the cost earn relation.
Cristina Mîndruţă Software Project Management Slide 30
COURSE TOPICS
PLANNING PROCESS GROUP.
Cost management planning processes
Cost estimatingCost budgeting
PLANNING PROCESS GROUP.
Management plan processes
Time management planning processes.
Cost management planning processes
Quality planning
HR planning
Communications planning
Risk management planning
Procurement management planning
Cristina Mîndruţă Software Project Management Slide 31
COST ESTIMATING process
Def. Cost estimating process = process of developing an approximation of the cost of the resources needed to complete the project activities.
Involves:• fluctuations
• risk
• other variances
• consideration of cost alternatives
Objective : to determine the most accurate and cost effective estimates.
Main relations with other processes: closely related to Activity Resource Estimating Process. lays the groundwork for Cost Budgeting Process.
Cost estimates are:as good as information available,refined as additional details become available.
Cristina Mîndruţă Software Project Management Slide 32
COST ESTIMATING process
1. Adapt the costs of a previous project.
Has low accuracy.
Approach especially used in initial estimations.
3. Individual cost estimations for activities and work packages.
Combine individual estimations estimated cost of the project
4. Elaborate a mathematical model for the project.
5. Software tools used in combination with previous methods significantly simplify the estimation process.
BUT the project manager still must do the estimations.
Cristina Mîndruţă Software Project Management Slide 33
COST ESTIMATING process
Assessments of the
probable costs of the resources
necessary to complete project activities
•Description of the activity’s scope of work•Documentation about how the estimate were developed•Known constraints•Explanations of assumptions made•Range of possible results
with desired and approved changes that are believed to have an impact on the project’s cost management.
Cristina Mîndruţă Software Project Management Slide 34
COST ESTIMATING process
Causes for incorect estimation:
1. Limited information (accepted in the first part of the PLC)
2. Sub-estimating
3. Lack of knowledge about technical problems
4. Estimated values motivated only by the wish to obtain funds (can be unrealistically low)
Project manager’s responsibilities:
- to realize realistic estimations
- to support and to respect them
Cristina Mîndruţă Software Project Management Slide 35
COURSE TOPICS
PLANNING PROCESS GROUP.
Cost management planning processes
Cost estimating
Cost budgeting
PLANNING PROCESS GROUP.
Management plan processes
Time management planning processes.
Cost management planning processes
Quality planning
HR planning
Communications planning
Risk management planning
Procurement management planning
Cristina Mîndruţă Software Project Management Slide 36
COST BUDGETING process
Def. Cost budgeting process = process of aggregating the estimated costs of individual activities or work packages to establish a cost baseline.
Cost budgeting vs. Cost estimating
shows costs across time shows costs by category (activity)
Cristina Mîndruţă Software Project Management Slide 37
COST BUDGETING process
Predict the costs for the project work.
Dictate when project activities occur and when associated budget monies will be spent.
Details purchasing requirements and associated cost.
Reflects how project costs will be controlled. Time-phased budget, used to measure and monitor overall cost performance on the project.
Usually displayed as an S-curve.
Includes, along with the baseline, a management reserve amount to compensate for either early progress or cost overruns.
Cristina Mîndruţă Software Project Management Slide 38
COST BUDGETING process
Management reserve amount:
– a provision in the PMP to mitigate cost and/or schedule risk
– the difference between the maximum funding and the end of the Cost Baseline.
Management Reserve (MR) budget is an amount of the total allocated budget for management control purposes.
Its purpose is to provide an adequate budget for in-scope but unanticipated work on the contract. As a contract proceeds to completion, and unanticipated, in-scope work is identified, MR budget is allocated to that work.
Once allocated, MR budget becomes part of the performance measurement baseline (PMB) used to measure and control cost and schedule performance on the contract.
Cristina Mîndruţă Software Project Management Slide 39
LABORATORY:
Study “Using Open Workbench” cap 1,3,4,5 and 6.
//blue/cadre/cmindruta/PM_InfoEngl/lab3/lab3_1lab3_2and associated files