Social Monitoring Report Project Number: 45021-002 August 2020
PRC: Anhui Intermodal Sustainable Transport Project - Resettlement Monitoring Report
Prepared by Anhui Zhenhua Comprehensive Transport Research Institute of Anhui Communications Vocational and Technical College for the Anhui Provincial Government and the Asian Development Bank This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 1 -
Anhui Intermodal Sustainable Transport
Development Project
External Resettlement Monitoring Report
(11th Report)
Anhui Communications Vocational & Technical College
August 2020
ADB-financed
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 2 -
目录
Notes for the Updated Monitoring Report ......................................................................................................................... - 9 -
1 Overview ......................................................................................................................................................................... - 13 -
1.1 Project Overview ................................................................................................................................................... - 13 -
1.1.1 G206 Dongliu to Yaodu construction project overview .............................................................................. - 14 -
1.1.2 S319 Erba to Wuwei Section Project Overview........................................................................................... - 16 -
1.1.3 S367 Ma’anshan Northern Passage Road Project Overview....................................................................... - 17 -
1.1.4 G318 and S320 Yimu Highway Project overview ....................................................................................... - 18 -
1.1.5 Shuiyang River Inland Waterway Transport Project overview................................................................... - 19 -
1.2 Project Resettlement Impact Overview ................................................................................................................. - 20 -
1.2.1 G206 Dongliu to Yaodu Construction Project Impact Overview ............................................................... - 20 -
1.2.2 S319 Erba to Wuwei Section Construction Project Impact Overview .................................................... - 22 -
1.2.3 S367 Ma’anshan Northern Passage Road Impact Overview .................................................................... - 23 -
1.2.4 G318 and S320 Yimu Highway Project Impact Overview ......................................................................... - 24 -
1.2.5 Shuiyang River Transport Project Impact Overview ................................................................................... - 24 -
1.3 Project Resettlement Implementation Time .......................................................................................................... - 25 -
1.3.1 G206 Dongliu to Yaodu Construction Project Resettlement Implementation Time ................................. - 25 -
1.3.2 S319 Erba to Wuwei Section Construction Project Resettlement Implementation Time ......................... - 28 -
1.3.3 S367 Ma’anshan Northern Passage Road Resettlement Implementation Time ......................................... - 31 -
1.3.4 G318 and S320 Yimu Highway Project Resettlement Implementation Time............................................ - 34 -
1.3.5 Shuiyang River Integrated Transport Development Project Resettlement Implementation Time............ - 37 -
2 Resettlement Organization ............................................................................................................................................. - 44 -
2.1 G206 Dongliu to Yaodu Construction Project Resettlement Organization ................................................... - 44 -
2.2 S319 Erba to Wuwei Section Construction Project Resettlement Organization ........................................... - 45 -
2.3 S367 Ma’anshan Northern Passage Road Project Resettlement Organization.............................................. - 46 -
2.4 G318 and S320 Yimu Highway Project Resettlement Organization ............................................................. - 50 -
2.5 Shuiyang River Transport Construction Project Resettlement Organization ................................................ - 51 -
2.6 Organizational framework and personnel capacity analysis........................................................................... - 52 -
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 3 -
3 Monitoring and evaluation of Resettlement Implementation Process......................................................................... - 55 -
3.1 Monitoring and evaluation of main content..................................................................................................... - 55 -
3.2 Methodology of Monitoring and Evaluation ................................................................................................... - 57 -
3.3 G206 Dongliu to Yaodu Construction Project Resettlement Monitoring and Evaluation Process .............. - 59 -
3.3.1 House Demolition and Resettlement................................................................................................... - 60 -
3.3.2 Permanent land acquisition .................................................................................................................. - 67 -
3.3.3 Temporary land occupation ................................................................................................................. - 67 -
3.3.4 Progress of land acquisition and demolition....................................................................................... - 69 -
3.3.5 Restoration and reconstruction of affected special facilities ............................................................. - 69 -
3.3.6 Restoration and improvement of water system .................................................................................. - 70 -
3.3.7 Vulnerable Groups Affected ................................................................................................................ - 73 -
3.3.8 Technical training ................................................................................................................................. - 74 -
3.4 S319 Wuwei to Erba Construction Project Resettlement Monitoring and Evaluation Process ................... - 77 -
3.4.1 House Demolition and Resettlement................................................................................................... - 78 -
3.4.2 State-owned Land Acquisition Area ................................................................................................... - 79 -
3.4.3 Permanent Land Acquisition ............................................................................................................... - 80 -
3.4.4 Temporary Land Acquisition............................................................................................................... - 80 -
3.4.5 Restoration and Reconstruction of the Affected Special Facilities ................................................... - 81 -
3.4.6 Vulnerable Groups Affected ................................................................................................................ - 82 -
3.5 S367 Ma’anshan Northern Passage Road Resettlement Monitoring and Evaluation Process ..................... - 82 -
3.5.1 House Demolition and Resettlement................................................................................................... - 84 -
3.5.2 Permanent Acquisition of Collective Land......................................................................................... - 86 -
3.5.3 Temporary Land Occupation ............................................................................................................... - 86 -
3.5.4 Pole Line and Other Infrastructure ...................................................................................................... - 87 -
3.5.5 Vulnerable Groups Affected ................................................................................................................ - 87 -
3.6 G318 and S320 Yimu Highway Project Resettlement Monitoring and Evaluation Process ........................ - 88 -
3.6.1 Housing Demolition and Resettlement ............................................................................................... - 91 -
3.6.2 Permanent Acquisition of Collective Land......................................................................................... - 93 -
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 4 -
3.6.3 State Owned Land ................................................................................................................................ - 94 -
3.6.4 TemporaryLand Acquisition................................................................................................................ - 94 -
3.6.5 Infrastructure......................................................................................................................................... - 95 -
3.7 Shuiyang River Integrated Transport Construction Project Resettlement Monitoring and Evaluation Process- 95 -
3.7.1 house demolition and resettlement ...................................................................................................... - 96 -
3.7.2 Permanent Land Acquisition ............................................................................................................... - 98 -
3.7.3 Temporary Land Acquisition............................................................................................................... - 99 -
3.7.4 Infrastucture .......................................................................................................................................... - 99 -
4 Compensation standard for Resettlement...................................................................................................................... - 99 -
4.1 G206 Dongliu to Yaodu Project Compensation Standard ............................................................................ - 100 -
4.1.1 Land acquisition standard .................................................................................................................. - 100 -
4.1.2 Compensation Standard for House Demolition................................................................................ - 108 -
4.1.3 Grave relocation ................................................................................................................................. - 114 -
4.1.4 Affected individual businesses .......................................................................................................... - 114 -
4.2 S319 Wuwei to wuwei-erba Project Compensation Standard and Quantity ............................................... - 117 -
4.2.1 Quantity Standard of Land Acquisition ............................................................................................ - 117 -
4.2.2 Compensation Standard for Collective Land Acquisition ............................................................... - 117 -
4.2.3 Compensation Standard for House Demolition................................................................................ - 120 -
4.2.3.1 Compensation Standard for RuralHousing Demolition ................................................................ - 120 -
4.3 S367 Compensation Standard for Ma'anshan North Passage Project .......................................................... - 124 -
4.3.1 Compensation Standard for Land Acquisition ................................................................................. - 124 -
4.3.2 Compensation standard for rural housing demolition ...................................................................... - 126 -
4.3.3 Compensation for Accessories and Infrastructure............................................................................ - 129 -
4.3.4 Other cost standards ........................................................................................................................... - 130 -
4.3.5 Vulnerable Groups ............................................................................................................................. - 130 -
4.3.6 Women's Support Measures .............................................................................................................. - 131 -
4.4 Compensation Standard for G318 and S320 Yimu Highway Project .......................................................... - 131 -
4.4.1 Compensation Standards of Land Acquisition ................................................................................. - 131 -
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 5 -
4.4.2 Compensation Standard for House Demolition................................................................................ - 136 -
4.4.3 Compensation Rates for Main Attachments and Infrastructure ...................................................... - 139 -
4.4.4 Affected Individual Businesses ......................................................................................................... - 140 -
4.4.5 Other Cost Standards.......................................................................................................................... - 141 -
4.4.6 Vulnerable Groups ............................................................................................................................. - 142 -
4.4.7 Women Support Measures ................................................................................................................. - 143 -
4.5 Compensation Standards for Shuiyang River Integrated Transport Construction Project ......................... - 143 -
4.5.1 Land Compensation Standards .......................................................................................................... - 143 -
4.5.2 Compensation Standards for the Acquisition of Flood Land Reclaimed by Households along the
River ............................................................................................................................................................. - 145 -
4.5.3 Compensation Standard for House Demolition................................................................................ - 146 -
4.5.4 Compensation Standard for Main Accessories and Infrastructure .................................................. - 147 -
4.5.5 Other Cost Standards.......................................................................................................................... - 147 -
4.5.6 Vulnerable Groups ............................................................................................................................. - 148 -
4.5.7 Women's Support Measures .............................................................................................................. - 149 -
5 Monitoring and evaluation mechanisms for resettlement .......................................................................................... - 150 -
5.1 G206 Dongliu to Yaodu monitoring and evaluation mechanisms for resettlement .................................... - 150 -
5.1.1 Internal Monitoring and Inspection ................................................................................................... - 150 -
5.1.2 Public Participation ............................................................................................................................ - 150 -
5.1.3 Grievance Redress Mechanism (GRM) ............................................................................................ - 152 -
5.1.4 Typical Cases ...................................................................................................................................... - 154 -
5.2 S319 Wuwei to Erba Monitoring and Evaluation Mechanisms for Resettlement....................................... - 156 -
5.2.1 Internal Monitoring and Inspection ................................................................................................... - 156 -
5.2.2 Public Participation ............................................................................................................................ - 156 -
5.2.3 Grievance Redress Mechanism(GRM) ............................................................................................. - 157 -
5.3 S367 Ma’anshan Northern Passage Road Construction Project Monitoring and Evaluation Mechanisms for
Resettlement ........................................................................................................................................................... - 159 -
5.3.1 Internal Monitoring and Inspection ................................................................................................... - 159 -
5.3.2 Public Participation ............................................................................................................................ - 159 -
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 6 -
5.4 G318 and S320 Yimu Highway Project monitoring and evaluation mechanisms for resettlement ........... - 165 -
5.4.1 Internal Monitoring and Inspection ................................................................................................... - 165 -
5.4.2 Public Participation ............................................................................................................................ - 165 -
5.4.3 Grievance Redress Mechanism(GRM) ............................................................................................. - 167 -
5.5 Shuiyang River Transport Construction Project Monitoring and Evaluation Mechanisms for Resettlement- 170 -
5.5.1 Internal Monitoring and Inspection ................................................................................................... - 170 -
5.5.2 Public Participation ............................................................................................................................ - 170 -
5.5.3 Grievance Redress Mechanism(GRM) ............................................................................................. - 171 -
6 G206 Dongliu to Yaodu Investigation and Analysis of the Living Standards of the Affected Households .......... - 173 -
6.1 Distribution of survey samples ....................................................................................................................... - 173 -
6.2 Annual Per Capita Income of Affected Families .......................................................................................... - 174 -
6.3 property status of the investigated family ...................................................................................................... - 175 -
6.4 Living Conditions of the Investigated Family ............................................................................................... - 176 -
6.4.1 Basic Public Goods Such as Water and Electricity .......................................................................... - 176 -
6.4.2 House condition .................................................................................................................................. - 178 -
6.4.3 Living Environment ........................................................................................................................... - 182 -
6.5 Analysis of the Economic Income and Source of the Investigated Family ................................................. - 182 -
6.5.1 Economic Income of the Investigated Family .................................................................................. - 182 -
6.5.2 Income source analysis ...................................................................................................................... - 184 -
6.6 Subjective Evaluation of the Living Conditions of the Investigated Families ............................................ - 187 -
6.6.1 Evaluation of Own Production Conditions ....................................................................................... - 187 -
6.6.2 Evaluation of the Economic Situation of the Whole Village .......................................................... - 189 -
6.6.3 Assessment of current living environment ....................................................................................... - 190 -
6.6.4 Evaluation of Neighborhood Relationship ....................................................................................... - 191 -
6.6.5 Evaluation of current life satisfaction ............................................................................................... - 193 -
7 Basic Assessment and Suggestions ............................................................................................................................. - 195 -
7.1 Basic Assessment ............................................................................................................................................ - 195 -
7.2 Basic Suggestions ............................................................................................................................................ - 196 -
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 7 -
8 Attachments .................................................................................................................................................................. - 197 -
Attachment 1: Project Location Diagram............................................................................................................. - 197 -
Attachment 2: G206 Project Approval of constrution land issued by Anhui provincial government ............. - 199 -
Attachment 3: Approval of Construction Land for Road S319 Erba to Wuwei Section Reconstruction Project - 200 -
Attachment 4: Notice on establishment of project resettlement office .............................................................. - 202 -
Attachment 5: Report on the Establishment of S319 Construction Headquarters in Wuwei County .............. - 205 -
Attachment 6: foundation file of anhui Jiaoyuan engineering project management limited company............ - 206 -
Attachment 7: Agreements On Land Acquisition ............................................................................................... - 207 -
Attachment 8: Agreements on Land Acquisition of Forest Farm for G205 Project.......................................... - 209 -
Attachment 9: Staff Meeting File of Forest Farm ............................................................................................... - 211 -
Attachment 10: Lease contract on mixing plant ground in lishan working area ............................................... - 212 -
Attachment 11: Rental Agreement on Temporary Land Use for Mixing Plant in S319 signed by Road and Port
Group ...................................................................................................................................................................... - 215 -
Attachment 12: housing lease contract of project management department in contract 01.............................. - 218 -
Attachment 13: Rental Contract of Project Management Department Signed by Road and Port Group ........ - 220 -
Attachment 14: Housing lease contract of project management department in contract 02 of G206 Project . - 225 -
Attachment 15: Housing lease contract of S319 Project ..................................................................................... - 228 -
Attachment 16: G206 Project housing lease contract of maintenance center .................................................... - 230 -
Attachment 17: G206 Compensation agreement for house demolition ............................................................. - 231 -
Attachment 18: Compensation agreement for power lines reconstruction project ........................................... - 235 -
Attachment 19: G206 Project Compensation agreement for communications trunk cables relocation project- 236 -
Attachment 20: G206 Project Water migration agreement ................................................................................. - 237 -
Attachment 21: G206 Project Forestry land compensation supplemental agreement....................................... - 238 -
Attachment 22: G206 Project Statistics of water conservancy project .............................................................. - 239 -
Attachment 23: G206 Project River restoration task decomposition table ........................................................ - 240 -
Attachment 24: Minutes of Meeting of Coordination Meeting for Pipeline Relocation of S319 Project. ...... - 245 -
Attachment 25: Approval of Construction Land Use for Nanling Yimu Highway Project .............................. - 248 -
Attachment 26: Notice on establishment of Nanling County project resettlement office ................................ - 249 -
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 8 -
Attachment 27: Notice on establishment of Shuiyang River project resettlement office ................................. - 250 -
Attachment 28: Housing lease contract of Nanling Contract 01 ........................................................................ - 251 -
Attachment 29: Housing lease contract of Nanling Contract 02 ........................................................................ - 252 -
Attachment 30:Notification Concerning the Compensation Scheme of House Demolition On Collective Land in
Jishan Town, Gongshan Town.............................................................................................................................. - 254 -
Attachment 31: Agreement on the Compensation of Young Crops for Nanling Yimu Highway.................... - 255 -
Attachment 32:Compensation Agreement On Land Acquisition in Nanling .................................................... - 256 -
Attachment 33 Notice On Establishment of S367 Hanshan Section Reconstruction Project Resettlement Office- 257 -
Attachment 34 Agreement On Land Acquisition for S367................................................................................. - 258 -
Attachment 35: Compensation Standard for House Demolition On Collective Land and Above-Ground
Attachments, and Compensation Standard for Young Crops in Xuanzhou District ......................................... - 259 -
Attachment 36: Compensation Standard for House Demolition in the Collective Land Acquired Within the
Scope of Urban Planning Area of Xuancheng City............................................................................................. - 266 -
Attachment 37: Official Reply to the Construction Land for S367 Project ....................................................... - 282 -
Appendix 38: Ma An Shan Public Participation and Minutes for S367 project............................................. - 284 -
Appendix 39: Compensation Standard on Wuwei County of S319 approved by Wuhu City Government .... - 290 -
Appendix 40: House Demolition Agreement of S319 ........................................................................................ - 297 -
Appendix 41: The establishment of Nanling Organization................................................................................. - 299 -
Appendix 42: Permanent Agreement of Land Acquisition of S319 Project ...................................................... - 300 -
Appendix 43: Compensation of Demolition House and Resettlement Agreement of S367 ............................. - 302 -
Appendix 44:Acquisition Agreement of Land S367 ........................................................................................... - 304 -
Appendix 45: Compensation of Demolition House and Resettlement Agreement of Yimu Road ............... - 305 -
Appendix 46: Land Acquisition Agreement of Yimu Highway ...................................................... - 307 -
Appendix 47: Group Purchase Agreement of Huishang Century City .......................................................... - 308 -
Appendix:48: Demolition agreement of Non-residential house and operation house compensation for
reconstruction from Kedian to Mujiating section of Yimu Highway in Nanling County ................................ - 311 -
Appendix 49: Record Form of Resettlement House for Xiaohekouqiao Pottery Factory ................................ - 314 -
Appendix 50: Shuiyangjiang Waterway Dredging and Dam Project Approved by Xuancheng People's
Government ............................................................................................................................................................ - 315 -
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 9 -
Appendix 51: Evaluation Report on New State-owned Land Acquisition for the Reconstruction Project from
Kedian to Mujiating Section of Yimu Highway in Nanling County .................................................................. - 316 -
Appendix 52: Resettlement Transition Fee for Demolition of Xuanzhou Port Wharf ..................................... - 320 -
Appendix 53: The transition fee for Vouchers resettlement of Xiaohekou Bridge ........................................... - 322 -
Notes for the Updated Monitoring Report
1.The duration of this monitoring report: July to December, 2019
2.For the quantity of land acquisition and demolition, see the table below:
G206 Dongliu-Yaodu Item Unit Planned Accumulated Completion Completion
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 10
Section Construction
Engineering
Part Completion Proportion time
Permanent Land
Acquisition Mu 987.97 1010.336 102.26%
2015.12
Temporary land Mu 180.99 210.943 116.55%
Housing demolition
area ㎡ 2546.09 5096.04 200.15%
Compensation for
permanent land
Ten
thousa
nd
Yuan
2847.37 2936.2083 103.12%
Compensation for
temporary land
Ten
thousa
nd
Yuan
/ 776.0536 /
Compensation for
housing demolition
Ten
thousa
nd
Yuan
151.7 225.48 148.64%
S319 Erba to Wuwei
Section Construction
Project
Permanent Land
Acquisition Mu 500.18 304.7252 60.92%
Temporary land Mu 199 71.37 35.86%
Housing demolition
area ㎡ 9710.8 12277.83 126.43%
Compensation for
land
Ten
thousa
1345.2 1262.4127 93.85%
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 11
nd
Yuan
2018.12
Compensation for
demolition
Ten
thousa
nd
Yuan
1259 1187.2951 94.30%
S367 Maanshan
City Northern
Passage Road
Permanent Land
Acquisition Mu 1440.33 1237.9531 85.95%
2018.12
Housing demolition
area ㎡ 19657 21217.29 107.94%
Compensation for
land
Ten
thousa
nd
Yuan
3998.65 4553.0259 113.86%
Compensation for
housing demolition
Ten
thousa
nd
Yuan
2070.96 3386.6326 163.53%
G318 and S320 Yimu
highway project
Permanent Land
Acquisition Mu 972.13 479.4 49.314% 2019.06
Housing demolition
area ㎡ 7645.3 6706.76 87.72% 2017.12
Compensation for
land
Ten
thousa
nd
Yuan
775.24 602.3045 77.69% 2017.12
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 12
Compensation for
housing demolition
Ten
thousa
nd
Yuan
2259.96 2038.1347 90.18% 2019.06
Comprehensive
shipping development
project of Shuiyang
River
Permanent Land
Acquisition Mu 906.153 917.52 101.25% 2019.12
Housing demolition
area ㎡ 8063 8544.24 105.97% 2019.12
3.Updated the contents of "compensation and implementation time" and "monitoring and
evaluation" in the reporting period;1、Updated the resettlement progress of S319 project;
4.Update the resettlement progress of S319 project;
5.Update the progress of Shuiyangjiang project resettlement site;
6.Updated the complaint cases of the project;
7.Updated the basic evaluation and suggestions of the project;
8.Update the economic level survey and analysis of G206 project;
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 13
1 Overview
1.1 Project Overview 1
The Wanjiang River Urban Belt is the most economically, socially, culturally and
technologically developed region in Anhui Province, and an integral part of the pan-Yangtze River
Delta economic circle. In January 2010, the State Council approved the Development Plan for the
Demonstration Area for Industry Shift to the Wanjiang River Urban Belt. The demonstration area
includes 59 counties (cities/districts) inclusive of Hefei and Wuhu Cities. According to the above
plan, infrastructure construction will be accelerated, an integrated transport system integrated with
the Yangtze River Delta established, regional energy supply level strengthened, and regional
information integration boosted in the Wanjiang River Urban Belt. The construction of the
expressway network will be accelerated and highway network structure improved with focus on
the interconnection of the demonstration area with surrounding areas.
ADB-financed Anhui Intermodal Sustainable Transport Project is composed of road network
reconstruction projects and Inland Waterway Transport (IWT) project. Of which, road network
reconstruction project include:
(1) Road S319 Erba to Wuwei Section: Upgrading of 30.60 km of the existing S319 road in
Jiujiang District (Wuhu City) and Wuwei County from Class II to Class I and adding 5.77 km of a
new road section. The subproject’s owner is Wuwei County Transport Bureau.
(2) S367 Ma’anshan Northern Passage Road: Upgrading of 46.87km of existing S367 within
Hexian County from Class IV to Class II. The owner is Ma’anshan Municipal Highway
Administration Bureau.
(3) Road G206 Dongliu to Yaodu Section: Construction of 15.714 km of a new Class I
highway section (G206) from Dongliu to Yaodu within Dongzhi County. The Owner is Chizhou
Municipal Highway Administration Bureau.
(4) G318 and S320 Yimu Highway: Upgrading of 22.36 km of G318 and S320 Yimu Road
1Resources: Resettlement Plan of the construction projects prepared by PMO in Anhui(Updated version)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 14
within Nanling County from Class II to Class I. The project owner is Nanling County Transport
Bureau.
Inland Waterway Transport Subproject includes:
(1) Shuiyang River Channel Improvement Project: 43.90 dredging, widening, and bank
protection of 43.90 km Shuiyang River channel waterway; construction of one 1000 dwt ship lock;
construction and installation of two low water rubber dams; construction of a new road overbridge
at Xiaohekou. The subproject’s owner is Anhui Provincial Port and Shipping Construction
Investment Group Co., Ltd. (APPSCIG).
(2) Shuiyangjiang xuanzhou Intermodal Port: construction of a new intermodal port on
northeast of Xuancheng industrial part in Xuancheng City, including construction of four
1,000-ton berths, road, storage yard and ancillary works in the rear. The subproject’s owner is
Anhui Provincial Port and Shipping Construction Investment Group Co., Ltd. (APPSCIG).
1.1.1 G206 Dongliu to Yaodu construction project overview
1) G206 Project Overview
Picture 1-1 G206 Project Diagram
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 15
The G206 Dongliu to Yaodu Section Construction Project (the “Subproject”) assumes an
important traffic task, with An average daily traffic volume of 7,948 vehicles (estimated to be
30,115 cars in 2034). Since the existing highway is relatively low in grade and has a mixed traffic,
it has become a bottleneck for the economic and traffic development of this region. In order to
upgrade the highway network of Dongzhi County and its service level, improve the regional
investment environment, and promote the integration of Yaodu and Dongliu Towns, ADB plans to
grant a loan of US$200 million to the PRC for the Anhui Intermodal Sustainable Transport
Development Project. This Subproject is a component thereof.
The subproject starts from G206 pile No.K1275+100 in Xiayang Village, Dongliu Town, goes
through the Zhanggong Reservoir, Zhanggang Village (Exist to Dongliu in Anjing Expressway),
the right bank of the Yaodu River, Tongjiu Railway and Anjing Expressway, and ends at
K1293+820, being a Class-I highway with a full length of 15.714km, a design speed of 80
km/hour, a roadbed width of 34m and a carriageway pavement width of 28.5m.
2) G206 Project approval time and planned start time
Foreign Fund Project Management Office of Anhui Provincial Department of Transport
(APMO) has agreed to include this project into the construction plan in Year 2013 on October 23,
2012; ADB mission had a field visit to Dongzhi, and APMO held meetings and signed a
memorandum with ADB on April 9, 2013; the Feasibility Study Report (FSR) was approved by
Anhui Provincial Development and Reform Commission (PDRC) on July 9, 2013; the project’s
preliminary design was approved by Chizhou Municipal Development and Reform Commission
(MDRC) on August 8, 2013; Design institute has completed construction drawings design on
September 13, 2013. This project is scheduled to start from May 2014 to May 2017, with
construction period of approximately 3 years.
Land acquisition, house demolition, compensation and resettlement works for the project will
be publicized from Sept. 2013 land acquisition and resettlement will be started from, Feb. 2014,
and ended largely in April 2015, all resettlement houses will be built up for residence in Dec.
2015.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 16
1.1.2 S319 Erba to Wuwei Section Project Overview
Road S319 Erba to Wuwei Section Reconstruction Subproject (the Subproject)is a component
of the ADB-financed Anhui Intermodal Sustainable Transport Development Project. The
subproject is located in Jiujiang District of Wuhu City and Wuwei County, starting from ramp
entrance of connecting line to Wuwei County of Hefei-Wuhu Expressway, crossing Xihe River
from east to west, ending at the west bridgehead of Xihe Bridge. It is surrounded by various
zones&parks such as Wuwei County Economic Development Zone, Gaogou Town Industrial Park,
wucheng Industrial Parkin Wuwei County, etc. Along this subproject, which are key areas for
Wuwei County to rely on zones & parks, accelerate industry cluster, as well as undertake industry
transfer from the Yangtze River Delta. In recent years, with the rapid development of national
economy, increasing traffic volume, as well as affected by natural conditions, pavement damage
has occurred in various degrees; some heavily damaged road sections have threaten to traffic safety,
efficiency of operation in existing roadsis constantly lower, which has hindered the development
of transport and economy within regions in the future to some extent. Therefore, expansion works
on this road is very necessary for the purposes of reducing costs of routine maintenance,
improving service levels (fast, safe, comfortable) and traffic capacity of trunk highways as well as
decreasing negative influence on social aspect.
The subproject includes 30.80 km reconstruction project from existing Class II upgraded to
Class I, and newly construction of 5.456 km, totaling about 36.256 km. Reconstruction project will
only widen 0.75m on both sides of the existing subgrade. The existing subgrade section after
reconstruction will have the same width as the newly constructionsubgrade. The designed
standards are Class I highway, with a design speed of 80Km/h, dual way four lanes, and subgrade
width of 26.5 m. The construction works include: 1) road works; 2) bridges &culverts works; 3)
intersection works; 4) traffic engineering. The owner for the part of this subproject located within
Wuwei County is Wuwei County Transport Bureau; the owner for the other part located within
Jiujiang District is Jiujiang District Government.
The subproject is divided into three contracts, namely: No1-1:K0+000-K18+000;
No1-2:K18-K30+800; No1-3:K30+800-K36+256. All three contractors have mobilized
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 17
successively from November 2014; overall works are expected to be completed around June 2017,
with 26 months of construction period as planned.
1.1.3 S367 Ma’anshan Northern Passage Road Project Overview
Figure 1-2 schematic diagram of S367 project
The project is located in the north of Ma’anshan, across He County, Hanshan County from the
east to west. The road starts from the joint of Jiangsu and Anhui, involving four towns, namely,
Shiyang Town, Shanhou Town in He County, Zhaoguan Town, Xianzong Town in Hanshan County,
total length is about 46.419km. Design speed 60km/h, subgrade width 12.0m, in compliance with
Class II highway standard.
This project will be constructed from June 2015 to May 2017, total construction period is 24
months.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 18
1.1.4 G318 and S320 Yimu Highway Project overview
Picture 1-3 Nanling Yimu Highway Project Diagram
Nanling County Yimu Highway Kedian to Mujiating Section Reconstruction Project starts
from Kedian Village, Jishan Town, Nanling County, runs through Nanling County Economic
Development Zone to Tongling westwards, ends at Yingtao Mount Nantong boundary of
Gongshan Town, total length 22.447km, of which Class I highway length 14.072km, biDirectional
four-lane, alignment is 30m; town road length is 8.375km, biDirectional six-lane + non-driveway,
acquisition alignment is 60m, it consists of a part of current G318 Xuannan Road Nanling Section
and S320 Nantong Road Nanling Section. S320 connects Nanling and the area in the west of
Tongling, G318 connects Nanling and Xuancheng, Taihu Region.
This project passes across Nanling County from east to west via Nanling county seat, there
are many fairs along the road, especially Nanling Industrial Park on both sides of the road in the
west of Wulihuandao, it is an east-west urban trunk road, also a necessary passage for daily ravel
of urban people.
According to the Resettlement Plan, land acquisition and resettlement would start from Sept.
2015 and end in June 2016; construction commenced officially from Dec. 2015, the whole line
will be completed for transport in Dec. 2017.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 19
1.1.5 Shuiyang River Inland Waterway Transport Project overview
Figure 1-3 Shuiyang River Transport Construction Project Diagram
Total length of Shuiyang River Integrated Transport Development Project is 43.9 km, in
compliance with Class Ⅳ channel standard, a new ship lock is built, a bridge is reconstructed.
Shuiyang River channel is divided into upper, middle, lower sections, upper section is Helixi to
Haitang Bay, the channel is rated as Class Ⅶ, middle section is Haitang Bay to Xidoumen, rated
as Class Ⅴ, lower section is below Xidoumen, is main part of Wushen Line channel, research
scope of this project is middle section.
Shuiyang River Haitang Bay-Xidoumen Section is about 49km long. In recent decades,
upstream soil erosion in Shuiyang River causes siltation in the navigation channel in successive
years, navigation mileage is shortened ontinuously. The channel could not meet transport
development demand. To meet eastward development strategy of Anhui Provincial Government,
Anhui Provincial Department of Transport decided to control Wushen Canal, open the waterway
transport between Yangtze River and Taihu water systems in 2004.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 20
This project is planned to start from June 2015 and end in Dec. 2017, construction period is
approximately 2.5 years. Land acquisition, house demolition, compensation and resettlement for
the project will start from Dec. 2014, end in Dec. 2016.
1.2 Project Resettlement Impact Overview
1.2.1 G206 Dongliu to Yaodu Construction Project Impact Overview
The main affects in resettlement of road G206 Dongliu to Yaodu section construction project
include collective land acquisition, state-owned land occupation, residential house demolition as
well as temporary land.
According to the Approval of construction land use for National Road G206 Dongliu
(Dongzhi) to Yaodu Section Reconstruction Project (WZD [2012] No.1226) approved by Anhui
Provincial Government, approved actual area of LA are 68.8640 hectares (approximately 1032.96
mu (including the former state-owned construction land of 2.0994 hectares), of which 42.5136
hectares of agricultural land (including 19.6241 hectares of arable land (294.36 mu)), 7.5005
hectares of construction land and 18.8499 hectares of unused land (including 12.5901 hectares of
state-owned unused land).
By the end of December 2015, the land acquisition, demolition and resettlement of g206
Dongliu Yaodu section construction project have been completed. Permanent land acquisition is
1010.336 mu, temporary land is 210.943 mu, and house demolition is 5096.04
Table 1-1 the Planned and Actual Impact of the Project
Items Unit Planned quantity
Cumulative
completed
quantity
Completion ratio
Permanent land
acquisition mu 987.97 1010.336 102.26%
Temporary land use mu 180.99 210.943 116.55%
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 21
Housing demolition
area ㎡ 2546.09 5096.04 200.15%
Permanent land
compensation
Ten
thousan
d yuan
2847.37 2936.2083 103.12%
Temporary land
compensation
Ten
thousan
d yuan
/ 776.0536 /
Compensation for
house demolition
Ten
thousan
d yuan
151.7 225.48 148.64%
The housing demolition area includes 3194.73m2 of main house demolition, 1901.31m2 of
abandoned management house and temporary construction of auxiliary simple shed / house, so the
house demolition area is 200.15% of the planned resettlement area.
During the implementation of the project, 2 individual businesses will be affected. See table
1-2 for details. According to the survey, in the original resettlement plan, only two households
were regarded as ordinary affected households, and the breeding of both households was in the
wild, and there was no obvious breeding house. Therefore, in the resettlement plan, the chicken
farm and pig farm were regarded as ordinary affected households and were not listed as individual
industrial and commercial households.
Table 1-2 Impacts on Individual Businesses
Types of impacts Types of individual businesses Culture area(m2) Number
Individual businesses Pheasant farm 6000 About 10000
Pig farm 288 120
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 22
1.2.2 S319 Erba to Wuwei Section Construction Project Impact
Overview2
The Resettlement Impact of the project mainly includes permanent land occupation,
demolition of rural residents' houses and demolition of non residential houses.
The land acquisition and demolition work for the reconstruction project of s319 Erjun Road
(Erba Wuwei) class I Highway in Wuwei County has been completed. The project collects
304.7152 mu of permanent land, 71.37 mu of temporary land, 12.624127 million yuan of land
compensation fee, 12277.83 mu of house demolition area and 11.872951 million yuan of house
demolition compensation fee.
T able 1-3 land acquisition and demolition quantity of S319 project
Item Unit Planned
quantity
Cumulative completed
quantity
Completion
ratio Remarks
Permanent land
acquisition mu 500.18 304.7252 60.92% Completed
Temporary land mu 199 71.37 35.86% Completed
Housing demolition
area ㎡ 9710.8
12277.83(Including
housing area of 2
Enterprises)
126.43% Completed
Land compensation
fee
Ten
thousand
yuan
1345.2 1262.4127 93.85% Completed
Compensation for
demolition
Ten
thousand
yuan
1259 1187.2951 94.30% Completed
The reason why the actual land acquisition data of the project is smaller than the data in the
resettlement plan: the Resettlement Impact of S319 project involves four towns, namely Dougou
Town, Fudu Town, Erba town and Tanggou Town, which have a total impact on Wuwei County. In
March 2013, the administrative division of Wuhu City was adjusted. Tanggou town and Erba town
2 Data source: Resettlement Plan of Road S319 Erba to Wuwei Reconstruction Project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 23
were divided into Jiujiang District of Wuhu City. 87.63 mu of land in Tanggou town and Erba
town of Jiujiang district is the auxiliary land of the highway, which does not need to be
expropriated; 107.8248 mu of land in Fudu town of Wuwei County has been expropriated before
the start of the project, when the new area of Chengdong is constructed, which does not need to be
repeatedly expropriated. Therefore, the actual land acquisition of the project is 304.7252 mu.
However, this part of the land that does not need to be repeatedly expropriated is occupied and
cultivated by the residents. Therefore, in the process of resettlement, compensation is still made
according to the compensation standard of the resettlement plan.
1.2.3 S367 Ma’anshan Northern Passage Road Impact Overview3
Main resettlement impacts of this project include permanent and temporary land occupation,
house demolition. The land acquisition and resettlement of this project involves He County and
Hanshan County, of which, He County involves 4 villages, 3 communities in Shiyang Town, 3
villages 1 community in Shanhou Town; Hanshan County involves 3 villages 1 community in
Zhaoguan Town, 1 village 1 community in Xianzong Town.
Table 1-4 completion ratio of land acquisition and demolition of S367 project
Item Unit Planned
quantity
Cumulative
completed
quantity Completion ratio Remarks
Permanent land
acquisition Mu 1440.33 1237.9531 85.95%
Completed
Housing demolition
area ㎡ 19657 21217.29 107.94% Completed
Land compensation
fee
Ten thousand
yuan 3998.65 4553.0259 113.86% Completed
Compensation for
demolition
Ten thousand
yuan 2070.96 3386.6326 163.53% Completed
The permanent land acquisition of the project is 1237.9531 mu, 85.95% of the resettlement
plan; the total area of house demolition is 21217.29m2, 107.94% of the resettlement plan. The land
3 Data source: Resettlement Plan for Yimu Highway Kedian to Mujiating Section Reconstruction Project
in Nanling County (Final Version) 2015
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 24
compensation fee is 45.530259 million yuan, and the house demolition compensation is 33.866326
million yuan.1.2.4 G318 and S320 Yimu Highway Project Impact Overview4
1.2.4 G318 and S320 Yimu Highway Project Impact Overview
According to the design scheme of the project, the Resettlement Impact of the project
involves 2 towns, 10 villages and 49 village groups in Nanling County. The acquisition and
relocation of Yimu highway in Nanling County mainly involves Gongshan town and Jishan town.
In June 2019, the land acquisition and relocation work was completed. The permanent land
acquisition of the project is 479.4 mu, and the house demolition area is 6706.76 m2.
Table 1-5 completion ratio of land acquisition and demolition of Yimu Highway project
Item Unit Planned
quantity
Cumulative
completed
quantity
Completion
ratio Remarks
Permanent land
acquisition Mu 972.13 479.4 49.314% Completed
Housing
demolition area ㎡ 7645.3 6706.76 87.72% Completed
Land
compensation fee
Ten thousand
yuan 775.24 602.3045 77.69% Completed
Compensation for
demolition
Ten thousand
yuan 2259.96 2038.1347 90.18% Completed
1.2.5 Shuiyang River Transport Project Impact Overview
The shipping comprehensive development project of Shuiyangjiang is divided into
comprehensive wharf and waterway regulation project. Among them, the waterway regulation
project includes three subprojects: the construction of Xiaohekou bridge, sluice dam and waterway
dredging regulation project.
Main resettlement impacts of this project include permanent acquisition of collective land,
4 Data source: Resettlement Plan for Yimu Highway Kedian to Mujiating Section Reconstruction Project
in Nanling County (Final Version) 2015
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 25
permanent occupation of state-owned land, temporary land occupation and rural house demolition.
The land acquisition and resettlement of this project involves 5 villages, 7 village groups in towns
of Xuanzhou District, Xuancheng City.
By the end of June, 2018, the land acquisition and demolition work of Shuiyangjiang
shipping comprehensive construction project was completed. The permanent land acquisition of
the comprehensive wharf project is 447.71 mu, and the house demolition is 4660.9 m2. The
permanent land acquisition of waterway regulation project is 491.01 mu, and the permanent land
acquisition of house demolition project is 3883.34 m2, 917.52 mu, and the house demolition area
is 8544.24 m2. The data of compensation for house demolition and land acquisition has not been
finalized due to multi department statistical accounting, and the next report will continue to
monitor.
Table 1-6 statistics of land acquisition and demolition of Shuiyangjiang shipping project
Permanent land acquisition (mu) Demolition area(m2) remarks
RAP plan Actual Completion ratio RAP plan Actual Completion
ratio Completed
Port engineering 499.5375 447.71 89.62% 5203 4660.9 89.58% Completed
Waterway
Engineering 406.6155 447.71 110.11% 2860 3883.34 135.78% Completed
Total 906.153 917.52 101.25% 8063 8544.24 105.97% Completed
1.3 Project Resettlement Implementation Time
1.3.1 G206 Dongliu to Yaodu Construction Project Resettlement
Implementation Time
In the stage of feasibility study, project owner has entrusted Hohai University to prepare the
resettlement plan based on project impacts. In the phase of project implementation, Dongzhi PMO
and project implementing agency have carried out a detailed project survey in December 2013,
Hohai University has updated the resettlement plan survey on the basis of detailed project survey
in February 2014.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 26
Resettlement external monitoring team has been to the field many times to conduct
investigation and interviews. We learned that the activities of LA, HD, Compensation and
resettlement were started in November 2013; (The research work of planning land acquisition and
resettlement programs, demolition area measurement, disbursement way, without access to land
and houses from the hands of affected households), Dongzhi county,the town Yaodu and Dongliu
held town and village levels meeting, inviting most of the affected households participate,fully
solicit the views of affected households on Land Acquisition and Resettlement Program of the
G206 Dongliu to Yaodu Road Section Construction Project (Draft), On this basis, revise and
improve the Program.
Issued Land Acquisition and Resettlement Program of the G206 Dongliu to Yaodu Road
Section Construction Project,November 19, 2013.
December 2013,Yaodu and Dongliu Town widely publicized land acquisition and
resettlement program;
April 2014, Dongzhi County held a land acquisition and resettlement mobilization meeting,
and Dongzhi television carried a report.
July 29, 2014, Magistrate, Sun Gexin in Chizhou city government Web site to promote the
importance of G206 Dongliu to Yaodu Road Section Construction Project, and answer the
questions the masses are concerned about, such as land acquisition and resettlement standards,
resettlement, compensation payment and other issues one by one. The successful implementations
of the project immigrant resettlement provide favorable conditions for the project.
Construction of the project began on September 25, 2014.
In early December 2014,land acquisition and demolition work basically competed.
June 30, 2015, land acquisition and resettlement compensation and resettlement work
basically finished.
Dec. 31, 2015, land acquisition and resettlement and compensation completely finished.
The staff of Monitoring Group learned that, the progress of resettlement implementation is
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 27
shown in Table 1-7.
Table 1-7 Registration Form for Resettlement Implementation Progress
Implementation of Resettlement
Activities Approved by Implementation date Related documents
Project approval Anhui Provincial Development and
Reform Commission Jun. 8, 2012
WFGJCH 2012 No.
【599】
Official reply to preliminary
design
Chizhou Municipal Development and
Reform Commission Aug. 8, 2013
CFGSJ 【2013】
No.297
Official reply to construction
drawing
Chizhou Municipal Transportation
Bureau Mar. 4, 2014 CJJ 【2014】 No.8
Preliminary examination of land Anhui Provincial Department of Land
Resources Oct. 19, 2012
WGTZH 【2012】
No.1834
Official reply to land Anhui Provincial Peop le’s
Government Dec. 2012
WZD 【2012】
No.1226
Preparation of resettlement plan Apr. 2013 Prepared by Hohai
University
Approval of the Resettlement
Plan ADB
Preparation of the Resettlement
Plan (updated) Feb. 2014
Prepared by Hohai
University
Approval of the Resettlement
Plan (updated) ADB
Publicity of LAR Program Sept. 2013
LA implementation (LA
planning and preparation of
program)
In early Nov. 2013
HD implementation In late Nov. 2013
Measurement of LA, HD At the beginning of Nov.
2013
Households Registration Dec. 2013 in early
Engineering construction
tendering
Foreign Investment Office of
Provincial Department of Transport May 2014
Contractor’s mobilization Aug. 2014
Commence of project G206 Project OFFICE Sept. 26, 2014
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 28
Implementation of Resettlement
Activities Approved by Implementation date Related documents
construction
Completion of HD In early Dec. 2014
Land acquisition completed 2014
Resettlement Date Main structures of new houses were completed in
June 2014.
New Houses Move-in Date In Aug. 2015, all resettlement apartments were built
up and resided.
Construction of farm irrigation
water systems was completed
Water system construction was completed in Oct.
2015
Notes: the project contractor has the required work surface during construction on site, so,
house demolition does not affect the construction.
1.3.2 S319 Erba to Wuwei Section Construction Project Resettlement
Implementation Time
In March 2012, Anhui Transport Survey &Consulting Design Institute(hereinafter called the
“Design Institute”) was entrusted by Wuwei County Transport Bureau (WCTB) to launch the
compilation of Feasibility Study Report on Class I Road S319 Erba to Wuwei Section
Reconstruction Project (hereinafter called the “FSR”).
In March 2012, under the strongly support by local PMO in Wuwei County, the design
institute carried out activities including field reconnaissance, site investigation and data collection;
and they has completed the draft of FSR and initially determine the contents and scope of this
project in July 2012.
During September 2012 to December 2012, immigration investigation team from Hohai
University has carried out a general survey on social economic conditions within project affected
areas and project resettlement impacts on the basis of the FSR.
During September 2012 to March 2013, the Resettlement Plan (RP) for this subproject was
completed based on the project’s FSR, survey data and public participation. The resettlement
impacts and risks of this subproject were analyzed and evaluated in this RP, and remedial measures
were also proposed.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 29
In March 2014, the Design Institute has completed the construction drawings design.
In Mar. 2014, House Compensation and Resettlement Scheme for Collective Land in
Chengdong New District, Wuwei County was issued. From Aug. To Oct. 2014, publicity was
carried out in Fudu Town and Dougou Town extensively;
In Apr. 2014, the County government held a land acquisition and resettlement mobilization
meeting, Wuwei television carried a report.
During April to May 2014, a detailed project survey on affected immigrants was conducted
by the Design Institute and Wuwei County PMO in accordance with construction drawings.
On the basis of the above survey,the final Resettlement Plan for Class I Road S319 Erba to
Wuwei Section Reconstruction Project based on Detailed Measurement Survey (the “final RP”)
was completed by immigration investigation teamof Hohai University in July 2014.
The successful implementations of the project immigrant resettlement provide favorable
conditions for the project.
This project was constructed from Aug., Sept. 2015.
LA and HD works were basically completed in early May 2015.
On Jun. 30, 2016, land acquisition and demolition, compensation and resettlement works
were basically completed.
On June 30, 2017, the land acquisition and demolition of S319 project and the relocation of
communication and power lines involved in the project were all completed. The housing
construction project of resettlement site - Chengdong new area was completed, and the supporting
auxiliary facilities project was in progress.
On June 30, 2018, some resettlers were resettled, some of them did not choose the existing
resettlement houses, and they were still waiting for their favorite houses.
On September 30, 2019, the relocated households were organized to select the resettlement
house number.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 30
Table 1-8 Registration Form for Resettlement Implementation Progress
No. Implementation stage of resettlement
activities Approved by
Implementation date or
period Remarks
1 Project approval
Anhui Provincial
Development and
Reform Commission
2013.9.17 WGFWZ [2013]
No.801
2 Official reply to preliminary design
Wuhu Municipal
Development and
Reform Commission
2014.1.10 WFGJT [2014]
No.16
3 Official reply to construction drawing Wuhu Municipal
Transportation Bureau 2014.7.12
WJGC [2014]
No.435
4 Preliminary examination of land Wuhu Provincial Land
and Resources Bureau 2013.5.29
WGT [2013]
No.200
5 Official reply to land Anhui Provincial
People’s Government 2014.1.22
WZD [2014]
No.53
6 Preparation of resettlement plan 2012.9-2013.3 Prepared by Hohai
University
7 Approval of the Resettlement Plan ADB-financed Project
Office 2013.5
8 Preparation of the Resettlement Plan
(updated) 2014.4-2014.6
Prepared by Hohai
University
9 Approval of the Resettlement Plan
(updated)
ADB-financed Project
Office 2014.7
10 Publicity of LAR Program 2014.8-2014.10
11 Measurement and registration of LA, HD 2014.11-2016.5
12 Signing and implementation of the
agreement on land acquisition 2014.11-2016.5
13
Signing and implementation of the
agreement on housing demolition and
relocation
2014.11-2016.5
14 Tendering for project construction Foreign Investment
Office of Provincial
Department of
02 Contract: 2014.4.28
03 Contract: 2014.7.18
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 31
No. Implementation stage of resettlement
activities Approved by
Implementation date or
period Remarks
Transportation
15 Contractor’s mobilization 02 Contract: 2014.11 03
Contract: 2015.4
16 Commence of project construction Wuhu Municipal
Transportation Bureau
02 Contract: 2015.8.10
03 Contract: 2015.9.16
17 Construction time of centralized
settlements
2013.11.20 construction
started
18 Completion time of centralized settlements 2017.6.30
The housing
construction
project completed,
and the supporting
auxiliary facilities
project in
progress
Completion time of centralized settlements 2019.8.30
Supporting
facilities
completed
19 Centralized housing distribution and
selection 2019.9.30
20 Placement time Expected Dec. 2019
1.3.3 S367 Ma’anshan Northern Passage Road Resettlement
Implementation Time
The progress of project demolition and resettlement shall be implemented in accordance with
the overall progress plan of the project. The specific implementation time may be adjusted due to
the deviation of the overall progress of the project. The implementation progress of the project is
as follows:
Land Acquisition and Demolition Scheme for S367 Ma’anshan Northern Passage Road
Project was issued in Aug. 2015.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 32
At the end of Dec. 2015, land data for approval passed the examination of Ministry of Land
and Resources and were submitted to the State Council for approval.
Construction of this project uninvolved with LA and HD contract was commenced from Dec.
20, 2015.
Land requisition and house demolition statistics of the AHs in the restriction line was
completed in Jan. 2016.
In January 2016, we completed the works of land and housing demolition statistics of
households in the restriction line, land and housing measurement, attachments survey, statistics
and the acquisition on the ground.
By the end of December 2016, we completed the permanent land acquisition of Hanshan
county and about 75% of He county.
At the end of December 2016, there was no house demolition work in Xianxu town of He
county, and 50%in Zhaoguan town was completed.
By the end of June 2017, Hanshan county had completed 95% of pole line relocation, and all
the water pipelines had been relocated. In Hexian County, 80% of the relocation work had been
completed, and the relocation of water pipes had been basically completed.
On December 31, 2018, the land acquisition and demolition work was completed.
By the end of June 2019, the resettlement work has been completed.
Table 1-9 Resettlement Implementation Schedule for S367 Ma'anshan Northern Passage Road
No. Implementation stage of resettlement
activities Approved by
Implementation date or
period Remarks
1 Project approval
Maanshan Municipal
Development and Reform
Commission
Apr. 9, 2013 MFGM (2013)
No.27
2 Official reply to preliminary design
Anhui Provincial
Development and Reform
Commission
Oct. 17, 2014 WFGSJH (2014)
No.1030
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 33
No. Implementation stage of resettlement
activities Approved by
Implementation date or
period Remarks
3 Official reply to construction drawing Maanshan Municipal
Transportation Bureau Aug. 5, 2015
MJ (2015)
No.198
4 Preliminary examination of land Maanshan Municipal Land
and Resources Bureau June 20, 2013
MGTZH (2013)
No.73
5 Official reply to land
Ministry of Natural
Resources of the People’s
Republic of China
Feb. 3, 2016 GTZH (2016)
No.51
6 Preparation of resettlement plan Hohai University May 2013
7 Approval of the Resettlement Plan ADB
8 Preparation of the Resettlement Plan
(updated) Hohai University Jan. 2015
9 Approval of the Resettlement Plan
(updated) ADB
10 Land acquisition plan and
scheme formulation Jan. 2016
11 House demolition Plan and
scheme formulation Jan. 2016
12 Publicity of LAR Program Jan. 2016
13 Measurement of LA, HD
completed June 2016
14 Households Registration May. 2016
15 Tendering for project construction Oct. 27, 2015
16 Contractor’s mobilization Dec. 2015
17 Commence of project construction At the end of Dec. 2015
18 Completion of land acquisition and
demolition An the end of 2018
19 Completion of all resettlement work At the end of June 2019
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 34
1.3.4 G318 and S320 Yimu Highway Project Resettlement Implementation
Time
March 2012, Wuhu Municipal Highway Bureau entrusted China Highway Planning and
Design Institute in Anhui Province to prepare Feasibility Study Report on Nanling County Yimu
Highway Kedian to Mujiating Section Reconstruction Project.
Sept. 2012-Oct. 2012, immigration investigation team from Hohai University carried out 100%
investigation on social economic conditions within project affected areas, rural families affected
by land acquisition for the project, physical quantity affected by project demolition according to
the Feasibility Study Report, and carried out sampling survey on social economic conditions of the
affected households (sampling proportion is about 26%), survey contents include family members,
land acquisition impacts, family economy and expected mode of resettlement etc.
From July to December 2014, immigration investigation team from Hohai University carried
out additional investigation in the affected areas according to the changes of project design
construction drawing.
Dec. 2015 ADB approved the updated version of Resettlement Plan.
In June 2014, Land Acquisition and Demolition Scheme for G318 and S320 Yimu Highway
Project was issued.
In June 2014, publicity was carried out extensively in Jishan Town and Gongshan Town.
In Apr. 2014, Nanling County government held a land acquisition and demolition
mobilization meeting.
In early Mar. 2015, land acquisition and demolition work of Gongshan Town was basically
completed.
In Dec. 2015, land acquisition and demolition, compensation and resettlement in Gongshan
Town were basically completed. This project was constructed from Dec. 2015.
In June 2017, land acquisition was completed and demolition was in progress.
In December 2017, the land acquisition and demolition work was basically completed. Seven
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 35
state-owned land assessments were completed and compensation agreements signed.
In June 2018, the resettlement work was completed.
In June 2019, the monitoring team learned that due to the design adjustment, the project does
not need to occupy the state-owned land of Qiangsheng Company, so it no longer needs to be
expropriated. The land acquisition work was completed.
Actual Resettlement Time of G318 and S320 Yimu Highway Project is shown in the table
below:
Table 1-10 Resettlement Implementation Time Table
No. Implementation stage of resettlement
activities Approved by
Implementatio
n date or
period
Remarks
1 Project approval Anhui Provincial Development and
Reform Commission
WFGWZ
No.2013-800
2 Official reply to preliminary design Wuhu Municipal Development and
Reform Commission 24 months
WFGJT
No.2014-62
3 Official reply to construction drawing Wuhu Municipal Transportation
Bureau
4 Preliminary examination of land Wuhu Provincial Land and Resources
Bureau
WGTM
No.2013-202
5 Official reply to land Anhui Provincial People’s
Government
6 Preparation of resettlement plan Hohai University Oct. 2012
7 Approval of the Resettlement Plan ADB
8 Preparation of the Resettlement Plan
(updated) Hohai University July 2015
9 Approval of the Resettlement Plan
(updated) ADB Dec. 2015
10 Publicity of LAR Program The governments of Jishan Town,
Gongshan Town
June
2014-Dec.
2014
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 36
No. Implementation stage of resettlement
activities Approved by
Implementatio
n date or
period
Remarks
11 Measurement and registration of LA,
HD
The governments of Jishan Town,
Gongshan Town
Oct. 2014 –
Mar. 2015
12 Signing and implementation of the
agreement on land acquisition
The governments of Jishan Town,
Gongshan Town Dec. 2015
13
Signing and implementation of the
agreement on housing demolition and
relocation
The governments of Jishan Town,
Gongshan Town Dec. 2015
14 Tendering for project construction Dec. 2014
15 Contractor’s mobilization July 2015
16 Commence of project construction Dec. 2015
17 Construction time of centralized
settlements 2014-2016
18 Completion time of centralized
settlements Oct. 2015 Gongshan Town
19 Move-in time of centralized
settlements Feb. 2016 Gongshan Town
20 Move-in time of centralized
settlements
Resettlement
apartments
have been
built, HD is
being
negotiated
Jishan Town
21 Construction time of the self-built
decentralized resettlement apartments June 2015 Gongshan Town
22 Move-in time of decentralized
resettlement apartment Dec. 2015 Gongshan Town
23 Completed construction of the affected
infrastructures
Constructed
synchronously
with the
project
24 Completion of Demolition Dec.2017
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 37
No. Implementation stage of resettlement
activities Approved by
Implementatio
n date or
period
Remarks
25 Completion of resettlement June 2018
26 Completion of land acquisition June 2019
1.3.5 Shuiyang River Integrated Transport Development Project
Resettlement Implementation Time
Oct. 30, 2006, Anhui Provincial Development and Reform Commission approved the
establishment of Wushen Canal Anhui Section Improvement Project according to the minutes of
meeting of the provincial government.
Nov. 20, 2007, Anhui Provincial Port and Shipping Construction Investment Group Co., Ltd.
Entrusted Anhui Survey and Design Institute of Water Conservancy and Hydropower to prepare
the Project Water and Soil Conservation Program.
Jan. 4, 2008, Anhui Provincial Port and Shipping Construction Investment Group Co., Ltd.
Entrusted Anhui Science and Technology Advisory Center to prepare environmental impact report
of the project, which passed assessment.
March 9, 2008, Anhui Provincial Port and Shipping Construction Investment Group Co., Ltd.
Entrusted Yangtze River Water Conservancy Committee Changjiang Institute of Survey, Planning,
Design and Research to prepare flood control assessment report for the project, which passes
review.
Dec. 3, 2008, Anhui Provincial Port and Shipping Construction Investment Group Co., Ltd.
Obtained letter of opinions on the preliminary examination of construction land from Anhui Land
and Resources Bureau.
According to the Memorandum of ADB Project Advisory Group (Dec. 12-15, 2011),
Shuiyang River channel will be improved according to “Class Ⅳ channel, Class Ⅲ water depth”
standard; research scope has been adjusted to Haitang Bay to Yanchi (Ganjiaguai); connecting line
Xiaocai River of Shuiyang River channel and main channel of Wushen Canal (Yanchi to Xigeng),
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 38
old channel of Shuiyang River (Yanchi to Xidoumen in Jiangsu Province) were compared and
selected on the basis of sufficient study and communication; port work was added, so that this
project became integrated water transport development project.
March 2012, entrusted by the owner, Anhui Provincial Port and Shipping Construction Group
Co., Ltd. , Anhui Traffic Survey Design Institute Co., Ltd. Completed Feasibility Study Report on
Shuiyang River Integrated Transport Development Project (first draft).
Sept. 2012-Dec. 2012, immigration investigation team from Hohai University investigated
social economic conditions and resettlement impact within project affected areas according to the
Feasibility Study Report. And carried out sampling survey of 40 households (sampling proportion:
household proportion is 31.7%) on social economic conditions of the affected households,
investigation content includes family members, impacts of land acquisition, family economy and
expected mode of resettlement etc.
Nov. 28, 2012, the Request of Xuancheng Development and Reform Commission for the
Establishment of Shuiyangjiang xuanzhou Intermodal Port Project was approved by Anhui
Provincial Development and Reform Commission, Approval Document No.WFGWZH
[2012]1259. Sept. 7, 2013, Anhui Provincial Development and Reform Commission replied to the
Feasibility Study Report on Shuiyangjiang xuanzhou Intermodal Port Project for approval (Anhui
Development and Reform Commission Design Letter [2013] No.1031); April 14, 2014,
preliminary design report of Shuiyangjiang xuanzhou Intermodal Port Project was approved by
Anhui Provincial Development and Reform Commission in written form (Anhui Development and
Reform Commission Design Letter [2014] No.347); Sept. 2, 2014, Request of the Provincial Port
and Shipping Construction Investment Group Co., Ltd. Concerning the Construction Drawing
Design of Shuiyangjiang xuanzhou Intermodal Port Project for approval was approved by
Transport Department of Anhui Province in written form (WJJGH [2014] No.423).
Aug. 20, 2013, Letter of the Transport Department of Anhui Province Concerning the
Approval of Proposal for Shuiyang River Channel Improvement Project was approved by Anhui
Provincial Development and Reform Commission (WFGWZH [2013] No.932); Sept. 7, 2013,
Letter of the Transport Department of Anhui Province Concerning the Approval of Feasibility
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 39
Study Report on ADB-financed Anhui Intermodal Sustainable Transport Infrastructure Project
Shuiyang River Channel Improvement Project was approved by Anhui Provincial Development
and Reform Commission (WFGWZH [2013] No.1030); Nov. 7, 2013, Letter of the Transport
Department of Anhui Province Concerning the Approval of Primary Design for ADB-financed
Anhui Intermodal Sustainable Transport Infrastructure Project Shuiyang River Channel
Improvement Project was approved by Anhui Provincial Development and Reform Commission
(WFGWZH [2013] No.1259).
From Jan. To June, 2014, entrusted by provincial PMO of this project —— Anhui Provincial
Department of Transport Anhui Provincial Port and Shipping Construction Investment Group Co.,
Ltd. , Anhui Xuancheng municipal government, Xuancheng Municipal Land and Resources
Bureau carried out detailed measurement and survey in Yangxian Township, Shuiyang Town,
Liqiao Town, Xuanzhou District, Xuancheng City involved in this project.
Dec. 2015, Integrated Shuiyang River Transport Improvement Project entered resettlement
publicity stage, project situation was publicized, compensation program data for land acquisition,
demolition were prepared for publicity. Real situation of the relocated households was investigated,
measurement and registration work was not carried out.
In Jan. 2016, PMO established Resettlement Organization.
In Jan. 2016, Land Acquisition and Demolition Scheme for Shuiyang River Integrated
Transport Development Project was issued.
In early Jan. 2016, pole line relocation scheme and agreement were signed.
In August 2016, land acquisition and demolition work officially began.
At the end of December 2016, the land acquisition and demolition of the comprehensive
wharf and Xiaohekou bridge were completed.
In June 2017, the construction of resettlement housing for Xuanzhou port comprehensive
wharf and Xiaohekou bridge project started. Land acquisition and demolition of gate dam project
and waterway project were in progress. On May 2, 2017, the people's Government of Yangxian
Town and Huishang Century City invested construction unit. Xuancheng Chuangyuan Real Estate
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 40
Development Co., Ltd., signed a commercial housing group purchase agreement. It was agreed in
the agreement that 61 sets of commercial houses of A-03 and A-04 with construction area of 6161
㎡ will be purchased as resettlement houses in the first phase of Huishang century city.
In June 2018, the demolition work of gate dam project and channel dredging project was
completed. Xiaohekou bridge resettlement housing construction started. The channel dredging
project was relocated to Dongyun new village, and the resettlement was completed.
In June 2019, the developer of "Huishang No.1" residential area for centralized resettlement
of Xuanzhou port comprehensive wharf project went bankrupt. And the restructure was in progress.
The resettlement houses of Xiaohekou bridge had been handed over. The gate dam project
completed the water intake relocation and land acquisition.
In December 2019, the land acquisition and demolition work was completed.
Table 1-11 Implementation Schedule of Shuiyang River Channel Project
No. Implementation stage of resettlement
activities Approved by
Implementation date or
period Remarks
1 Project approval
Anhui Provincial
Development and Reform
Commission
Aug. 20, 2013
2 Official reply to preliminary design
Anhui Provincial
Development and Reform
Commission
Nov. 7, 2013
3 Official reply to construction drawing Transport Department of
Anhui Province Feb. 11, 2014 Xiaohekou Bridge
4 Preliminary examination of land
Anhui Provincial
Department of Land
Resources
Aug. 27, 2013
5 Official reply to land Anhui Provincial People’s
Government Sept. 30, 2014
6 Preparation of resettlement plan May 2013 Prepared by
Hohai University
7 Approval of the Resettlement Plan ADB
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 41
No. Implementation stage of resettlement
activities Approved by
Implementation date or
period Remarks
8 Preparation of the Resettlement Plan
(updated) Nov. 2014
Prepared by
Hohai University
9 Approval of the Resettlement Plan
(updated) ADB
10 Publicity of LAR Program People’s Government of
Xuanzhou District Jan. 25, 2016 Xiaohekou Bridge
11 Measurement and registration of LA, HD Jan. 2016- Xiaohekou Bridge
12 Signing and implementation of the
agreement on land acquisition Jan. 2016- Xiaohekou Bridge
13
Signing and implementation of the
agreement on housing demolition and
relocation
Apr. 2016- Xiaohekou Bridge
14 Tendering for project construction
15 Contractor’s mobilization Oct. 2015 10 Xiaohekou Bridge
16 Commence of project construction Nov. 26, 2015 Xiaohekou Bridge
17 Completion of land acquisition and
demolition Dec. 2016
18 Group purchase of resettlement houses May 2017
19
Bankruptcy and reorganization of
developers of resettlement housing
estate
June 2019
20 Construction time of centralized
resettlement site 2012--
The resettlement
developer went
bankrupt and
reorganized , and
the completion
time is to be
determined
21 Completion time of centralized
resettlement site
22 Occupancy time of Centralized
Settlement
23 Self construction time of scattered
resettlement houses
24 Occupancy time of scattered resettlement
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 42
No. Implementation stage of resettlement
activities Approved by
Implementation date or
period Remarks
houses
Table 1-12 Implementation schedule of Shuiyangjiang waterway project
No. Implementation stage of resettlement
activities Approved by
Implementation date
or period Remarks
1 Project approval
Anhui Provincial
Development and Reform
Commission
Aug. 20, 2013
2 Official reply to preliminary design
Anhui Provincial
Development and Reform
Commission
Nov. 7, 2013
3 Official reply to construction drawing Transport Department of
Anhui Province Feb. 11, 2014
4 Preliminary examination of land
Anhui Provincial
Department of Land
Resources
Aug. 27, 2013
5 Official reply to land Anhui Provincial People’s
Government Sept. 30, 2014
6 Preparation of resettlement plan May 2013 Prepared by
Hohai University
7 Approval of the Resettlement Plan ADB
8 Preparation of the Resettlement Plan
(updated) Nov. 2014
Prepared by
Hohai University
9 Approval of the Resettlement Plan
(updated) ADB
10 Publicity of LAR Program People’s Government of
Xuanzhou District Jan. 25, 2016 Xiao hekou bridge
11 Measurement and registration of LA, HD Jan. 2016----- Xiao hekou bridge
12 Signing and implementation of the
agreement on land acquisition Jan. 2016----- Xiao hekou bridge
13 Signing and implementation of the
agreement on housing demolition and
Apr. 2016----- Xiao hekou bridge
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 43
No. Implementation stage of resettlement
activities Approved by
Implementation date
or period Remarks
relocation
14 Construction unit mobilization Oct. 2015 10 Xiao hekou bridge
15 Commencement of project construction Nov. 26, 2015 Xiao hekou bridge
16 Completion of land acquisition and
demolition Dec.2016
17 Commencement of resettlement housing
construction June 2018 Xiao hekou bridge
18 Completion of lock and channel dredging
demolition June 2018
lock and channel
dredging
19 Completion of Channel dredging
resettlement June 2018
lock and channel
dredging
Completion of resettlement June 2019 Xiao hekou bridge
20 Completion of land acquisition June 2019 Gate dam
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 44
2 Resettlement Organization
2.1 G206 Dongliu to Yaodu Construction Project Resettlement
Organization
Foreign Fund Project Management Office of Anhui Provincial Department of Transport
(APMO) will be the executing agency (EA) for Anhui Integrated Sustainable Transport
Development Project; Dongzhi County PMO will be the EA for G206 subproject, and Chizhou
Municipal Highway Administration Bureau will be the implementing agencies (IA) of the
subproject (G206). The above agencies will be jointly in charge of implementation of resettlement
plan in details with each town government affected.
To ensure the smooth progress of Road G206 Dongliu to Yaodu Section Construction
Subproject, it was decided by Chizhou Municipal Highway Administration Bureau after office
meeting that a resettlement management office would be setup for this subproject, the list of
persons as follows:
Director: Yao Chengyu
Deputy Director: Han Xiuyu
Members: Xu Yong, Wen Fadong
Han Xiuyu will be responsible for specific leadership works for this resettlement project.
It was decided by Dongzhi County Government that resettlement coordination and
management office would be setup for this subproject, name list as follows:
Director: Shi Weimin (County Government’s Office)
Deputy Director: Xu Moyou (Yao Du Town Government)
Wang Qianchun (Dongown Government)
Han Xiuyu (County Transportation Bureau)
Regarding resettlement coordination and management, Mr. Xu Moyou is responsible for
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 45
liaison and coordination in Yaodu Town; Mr. Wang Qianchun is responsible for liaison and
coordination in Dongliu Town.
Yaodu Town Resettlement Leading Group
Leader: Shi Weimin
Members: Xu Moyou, Ruan Zhihua, Zhang Yongjian, Zhao Shuang
Dongliu Town Resettlement Leading Group
Group head: Jiao Shiqing
Deputy Head: Wang Qianchun
Members: Zhu Guoping, Jiang Weihong, Zhang Kelong, Yu Fujin, Zhou Zhengdong, Wu
Zhongfa, Wang Faping, Deng Xin
The Leading Group comprises office, which is located in Dongliu Town Labor and Social
Security Station and Deng Xin serves concurrently as the director.
The office conference has decided that Han Xiuyu, deputy director of PMO serves
concurrently as the chief of local coordination department, is responsible for local environment
coordination and resettlement works.
The preparatory work for land acquisition and resettlement are adequate, with perfect
institutional settings, which ensure the implementation of land acquisition and resettlement work
smoothly.
2.2 S319 Erba to Wuwei Section Construction Project Resettlement
Organization
Project construction headquarters wasset up in project located areas ofwuwei County and
Jiujiang District, respectively.
Wuwei County established a headquarters headed by the standing deputy county mayor Jin
Ligang; Xu Yaguang, a member of standing committee of the chinesepeople’s Political
Consultative Conference (CPPCC) in Wuwei County, serves as vice executive chief, who will be
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 46
in charge of local coordination department and responsible for leading works on resettlement
activities. The name list of Wuwei County Headquarters is shown as following:
Chief: Jin Ligang (member of county standing committee, deputy county mayor)
Political commissar: Zhao Yin (deputy director of the standing committee in Wuwei County)
Deputy Chief: Zhao Qiancheng (director-general of Wuwei County Transportation Bureau),
Xu Yaguang (member of the standing committee of CPPCC in Wuwei County), Jiang Ping (head
of Wuwei County Rural Highway Management Bureau)
Local Coordination Department: He Jiyou, Tang Xiaowei
A headquarters was jointly established by three projects in Jiujiang District including
downtown section of Tongjiang road, Erba (Chang’an) Interchange, as well as Road S319 Erba to
Wuwei Section Reconstruction Project(downtown section). Wang Yang, deputy director of
Engineering Department is in charge of local coordination department and responsible for
resettlement activities. The name list of this headquarters in Jiujiang District is listed as below:
Director: Wang Chunming
Deputy Director: Chen Ruisheng, Wang Yang
Local Coordination Department: Wang Yang (concurrently), Zheng Yutian, Xu Yadong
Thus it can be seen that, preparatory work for the project land acquisition and resettlement
work was sufficient, and institution settings were improved,which ensure the smooth
implementation of land acquisition and resettlement works.
2.3 S367 Ma’anshan Northern Passage Road Project Resettlement
Organization
In order to ensure smooth resettlement and achieve the expected result, an organization from
top to bottom must be set up in the project implementation process for planning, implementation,
coordination and monitoring of the resettlement activities.
This project adopts the management mechanism of unified dispatching at municipal level, the
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 47
counties assume their respective responsibilities.
1) municipal government has established Project Construction Headquarters headed by
deputy mayor in charge, responsible for commanding and coordinating of the project construction,
Headquarters Office is located in the Municipal Highway Management Bureau. Municipal
Highway Management Bureau is the project owner.
2) the government of He County, Hanshan County should establish Project Construction
Headquarters at County Level, which should be headed by the leader of the County government in
charge, directors of relevant departments in the county are members, responsible for commanding
and coordinating of project construction in their jurisdictions.
3) Municipal Highway Management Bureau has established Project Management Office
(PMO for short). Responsible for commanding and coordinating of construction organization of
the project management organization in both counties.
4) Project Construction Headquarters in the counties should establish Project Site
Management Department at County Level (Site Management Department for short), responsible
for organization management of project construction in their jurisdictions, under unified
dispatching and instruction of PMO.
Site Management Department should govern Technical Contract Division, Comprehensive
Coordination Division, Safety and Environment Protection Division, Financial Audit Division etc
according to relevant requirements.
1) 2 directors in Site Management Department (1 person in He County, Hanshan County
each), also as deputy directors of PMO, responsible for comprehensive works of the Site
Management Department in their respective counties.
2) 6 persons in Technical Contract Division (4 persons in He County, 2 persons in Hanshan
County), responsible for engineering work, also responsible for measurement and payment audit of
construction, supervision, test organizations, submit withdrawal and reimbursement data for ADB
loan, review project progress report etc. Such persons should have technical title of highway
bridge above medium grade, with construction project management work experience in no less
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 48
than one Class 2 highway.
3) 5 persons in Comprehensive Coordination Division (3 persons in He County, 2 persons in
Hanshan Count), responsible for local relocation coordination and resettlement, also responsible
for secretarial, general affairs, logistics, advertisement and security guard works. Such persons
should be familiar with the local work environment, with work experience in relocation,
coordination, office etc for 3 years and above.
4) 2 persons in Safety and Environment Protection Division (1 person in He County, Hanshan
County each), responsible for safe production, environmental protection monitoring etc. Such
persons should have relevant work experience.
5) 2 persons in Financial Audit Division (1 person in He County, Hanshan County each),
responsible for financial work, coordinate with audit work, such persons should have accounting
qualification.
The above-mentioned persons in Site Management Department should be assigned by
government of the counties, age should not exceed 50. Drivers, cooks, doorkeepers and other
workers should be assigned according to the requirements.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 49
Picture 2-1 S367 Resettlement Organization Management Organization Block Diagram
In order to ensure successful S367 Hanshan Section reconstruction work, the County
headquarters decided to establish S367 Hanshan Section Reconstruction Resettlement
Management Office (Attachment 32), specific list is given below:
Director: Li Dingguo
Deputy Director: Zhang Yunhai, Gu Congwen, Luo Weibao
Members: Shi Guang, He Chengbo, Jiang Jinfeng
Comrade Gu Congwen is responsible for resettlement coordination management in Zhaoguan
He County
He County Land
Acquisition And Re settlement
Bureau
Hanshan County
Hans han Cou nty Land
Acq uisition And Resettl ement Bureau
367 Provincial Highway Reconstruction Project
Construction Headquarters
He County Section Resettlement
Hanshan Section
Reconstruction Project
Resettlement Management Office
Anhui provincial government
ADB-financed Project Leading
S367 Northern Passage Road
(Ma'anshan Section) Reconstruction
Project Management Office
External independent
Ma’Anhui Provincial
The affected
Village
The affected
The affected household
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 50
Town, Comrade Luo Weibao is responsible for resettlement coordination management in
Xianzong Town.
2.4 G318 and S320 Yimu Highway Project Resettlement Organization
Picture 2-2 Nanling County Yimu Highway Project Resettlement Organization Chart
In order to ensure successful resettlement for the project, Nanling County government
established Yimu Highway Reconstruction Project Site Office, Office organization and members
are as follows:
Director: Ling Xianhua (head of County Department of Transport Bureau)
Standing Deputy Director: Hou Qingran (head of County Highway Branch)
Deputy director: Tao Haibo (County Department of Transport)
Liu Dongan (County Highway Branch)
Zhan Lingsheng (County Relocation Office)
Lu Qin (County Environmental Protection Bureau)
Wang Changsong (County Tourism Investment Company)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 51
Pan Yun(Jishan Town)
Wang Jinping (Gongshan Town)
At the same time, to meet the requirements of Yimu Highway Reconstruction Project Site
Office, Nanling County Land House Acquisition Management Office was organized, special
persons were allocated for resettlement work on site, organization setup and personnel
arrangement are as follows:
Director: Ma Weidong (director of County Acquisition Office)
Standing Deputy Director: Tao Haibo (County Department of Transport)
Deputy director: Zhan Lingsheng (deputy director of County Acquisition Office)
Liu Dongan (County Highway Branch)
Pan Yun(Jishan Town)
Wang Jinping (Gongshan Town)
Members: Liu Jianjun, Hu Enhong, Yu Shoubao, Wang Tianxi
See Annex 40 for specific documents
2.5 Shuiyang River Transport Construction Project Resettlement
Organization
In order to ensure successful resettlement for the project, Shuiyang River Integrated Transport
Development Project Construction Headquarters established Resettlement Office, Office
organization setup and members are as follows:
Municipal Command Office: Leader in charge Song Huahui Transactor Wu Hao
District Command Office: Leader in charge Zhang Guoqing Transactor Zhong Gongwen
Yangxian Township: Leader in charge Jiang Jingbo Transactor Cheng Yan
Liqiao Town: Leader in charge Han Dong Transactor Su Yong
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 52
Shuiyang Town: Leader in charge Ding Weiyin Transactor Wu Yi
Figure 2-3 S367 resettlement organization chart of shipping project on Shuiyang River
See Annex 40 for specific documents.
2.6 Organizational framework and personnel capacity analysis
Project Resettlement Organizations have been established, special persons are responsible for
resettlement-related works. Establishment of resettlement organization and personnel arrangement
are favorable to successful implementation of resettlement work for the project.
Before the project resettlement organizations were established, and after personnel of the
resettlement organizations reached their designated positions, external resettlement monitoring
project leaders, resettlement experts of Anhui Province Foreign Investment Office and Anhui
Jiaoyuan Engineering Project Management Co., Ltd. Provided special resettlement training for the
External Monitoring
Unit
Anhui Project
Offoce
Xuancheng Land and
Resources Bureau
Xuancheng Maritime
Bureau
(Command Office)
District Command Office
Shuiyang
Town
Liqaio Town
Yangxian
Country
Anhui Port and Waterway
Construction Investion Group Co.,Ltd
Project Design
Organiztion
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 53
resettlement organizations and relevant personnel.
Main training content: get familiar with guarantee policy requirements of Asian Development
Bank, understand the features of voluntary resettlement and involuntary resettlement, and current
challenges of involuntary resettlement, utilize abundant examples in the training process, express
significance and challenges of the resettlement vividly, put forward specific working methods of
work personnel related to ADB project resettlement and the details to be noted. The training
enabled the workers in resettlement organizations to get familiar with and master ADB
resettlement security policies, solve problems in land acquisition and resettlement of the project
timely, increase understanding of resettlement personnel on land acquisition and resettlement, laid
solid foundation for more effective land acquisition and resettlement of ADB-financed project in
the future. For project resettlement training meetings, see the figure below.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 54
Picture 2-4 ADB Ⅱ Project Resettlement Training Meetings
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 55
3 Monitoring and evaluation of Resettlement Implementation Process
In March 2014, the foreign funded project management office of Anhui Communications
Department carried out public bidding for the external supervision organization of resettlement.
Anhui Communications Vocational and Technical College submitted and won the bid and became
the external monitoring organization of resettlement of "Anhui multimodal transport sustainable
transport project loaned by ADB", who is responsible for regular monitoring of the entire ADB
loan project and submitting external monitoring report. In order to successfully complete the
external monitoring work and meet the requirements of the public institutions reform, Anhui
Communications Vocational and Technical College registered and established Anhui
Communications Institute Engineering Project Management Co., Ltd. to be responsible for the
external monitoring work.
In July 2014, the external monitoring unit signed an external monitoring contract with the
foreign funded project management office of Anhui Communications Department. Anhui
Communications Vocational and Technical College has been responsible for the external
monitoring of resettlement in many foreign-funded projects, such as the ADB I project and the
world bank loan project, and won good performance. In order to ensure the smooth
implementation of the resettlement work of this project, the foreign funded project management
office of Anhui Communications Department entrusted Anhui Communications Vocational and
Technical College to provide technical guidance for the external monitoring work of resettlement
of ADB II project before the external monitoring bidding.
3.1 Monitoring and evaluation of main content
A. Key Monitoring Indicators
(1) Progress: including preparation, implementation and resettlement for land acquisition,
demolition and immigration;
(2) Quality: including construction quality, satisfaction degree of immigrant resettlement
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 56
during the process of land acquisition, demolition and relocation;
(3) Investment: including fund allocation and usage.
(4) Socio-economic indicators: per capita income, GDP, employment rate.
(6) Institutional indicators: staff composition, quality of personnel, rules and regulations,
equipment, completion rate of transaction handling.
(7) Immigration affected by LA and land occupation: Compensation funds in-position rate,
production arrangement modes, rate of change in income, employment rate, satisfaction degree of
resettlement;
(8) Residential houses: Compensation funds in-position rate, location of new houses, progress
of land acquisition in new location, resettlement satisfaction degree.
(9) Infrastructure: Compensation funds in-position rate, rate of functional recovery.
(10) Temporary occupation: restoration funds in-position rate, progress of land property
recovery.
B. Main indicators for evaluation
(1) Production and living conditions of immigrants
① Economic conditions: Household economy development before and after relocation,
including households’ means of production, possession of subsistence materials, assets, income.
② Environmental conditions: Living environment before and after resettlement, including
public facilities development and changes involved in transportation, education, health, business
services and so on.
③ Employment: Career change before and after migration, labor employment rate, provide
assistance to various people, especially for households in poverty, minority households.
④ Community development: It refers that the status of economic and environmental
development, interpersonal relationships, public opinion in local communities after immigrants are
properly resettled.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 57
(2) Infrastructure
Variations are existed in regions affected by the project before and after infrastructure
implementation.
C. Individual businesses and private shops
Changes are existed in business environment and status before and after resettlement for
individual businesses and private shops.
In addition to monitor the above-mentioned Indicators, resettlement external monitoring
agency also provide resettlement policy advertisement and service training for all participants of
the project, main training contents are Resettlement Plan for the project and the Safeguard Policy
Statement issued by the Asian Development Bank.
3.2 Methodology of Monitoring and Evaluation
The monitoring and evaluation activities would be on the basis of the available data provided
by the design institute and implementation agencies of resettlement; Random samples are required
for quick evaluation based on the all-round knowledge grasped. Some typical samples were
selected to establish evaluation index system for the affected persons and then marked with special
index co-efficiency under back-to-back way and then followed with careful analysis and
calculation.
Independent monitoring and evaluation agencies are involved in the following tasks:
(1) Investigation on the resettled persons’ living conditions
It is tasked to carry out comprehensive baseline survey for the project and collect samples
(there are all random samples at the initial period) selected to learn about such data as production
and living materials. This kind of survey has been conducted for one to two times a year to see
what changes to be happened on local production and living conditions generally in the manner of
periodical survey, random interviews and field visits, on the basis of which the obtained data could
be collated and analyzed and evaluated.
The investigation table designed for learning about the living conditions consists of various
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 58
indicators for measuring production and living conditions. The dynamic changes on the same
indicator just reflects the local conditions on production and living by comparison of before and
after resettlement; furthermore, whether the indicator designed is suitable or not to properly see the
real changes of local production and living, which can be verified through baseline survey and also
be improved in accordance with the local facts to be sure of all-sided information collected to
truthfully show the current quantity and quality of local resettled persons’ living and production
conditions.
(2) Public Consultation
Independent monitoring evaluation institute participated the public consultation meeting held
at the local villages and towns. With these activities, the survey team has found out how well the
resettled persons participated in and has seen how the local transmigrates are cooperative in terms
of resettlement action plan.
(3) Transmigrants’ opinion
Independent monitoring evaluation team visited the resettlement offices at towns and villages
involved to learn about the local resettled persons’ comments, and they often talked to the
transmigrants who had utterances and submitted the ideas and requirements of affected population
and local communities and made out their proposal of improvement in order to make the
resettlement work more efficient while fulfilling.
(4) Other responsibilities
The following activities have been monitored by the external and separate monitoring
evaluation institute while fulfilling:
① Selection of resettlement spots;
② Reconstruction of demolished houses;
③ Production resettlement and renewal;
④ Support to vulnerable group;
⑤ Resettlement of individual businesses and private shops;
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 59
⑥ Rehabilitation and reconstruction of special facilities;
⑦ Payment of compensation funds and quantity;
⑧ Relocation of affected people;
⑨ Employment;
⑩ Establishment of resettlement implementation organization;
○11Usage of collective land compensations and benefits for affected people;
○12 Labor employment and income growth.
○13 the use and effectiveness of the resettlement budget
○14 Operation of complaint mechanism
3.3 G206 Dongliu to Yaodu Construction Project Resettlement Monitoring
and Evaluation Process
The monitoring and evaluation team further inspected the house demolition, land acquisition
and the project resettlement from March to June and November to December 2015.
In the startup stage of resettlement works in G206 subproject, the staff from the Company has
conducted field investigations on this project with four times including in December 2013, January
2014, May 2014, September 2014, October 2015, January 2016 and April 2016 respectively.
Inception Report on External Resettlement Monitoring has been provided to ADB by the Company
in September 2014. The Report has systematically stated the monitoring organization, schedule
and TOR during the implementation of this project. Monitoring and Evaluation Group has
conducted a comprehensive site investigation on resettlement works of G206 Dongliu to Yaodu
Section Construction Project during September to October 2014, and compiled the baseline report
of this project resettlement; meanwhile, the first report of external resettlement monitoring during
these period has also been completed. In April, June, Sept., Dec. 2015, April 2016, Monitoring and
Evaluation Group has conducted a comprehensive site investigation on resettlement works of
G206 Dongliu to Yaodu Section Construction Project, completed External Resettlement
Monitoring Report. In September 2019, Anhui Communications Vocational and Technical College
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 60
carried out the survey of living standards and wrote the 11th monitoring report.
By the end of December 2015, G206 Dongliu to Yaodu Section Construction Project had fully
completed the land acquisition, demolition and resettlement, actually completed the acquisition of
permanent land of 1010.38 mu(The actual land used for the project is 807.066 mu, and the land
occupied for the project is 203.27 mu, which will be used as reserved land after land acquisition),
completed proportion 102%; temporary land 201.94 mu, completed proportion 116.55%; areas of
house demolition 5096.04 ㎡, completed proportion200.15%; land compensation fee 37.1226
million Yuan was paid, completed proportion 130%; Among them, the compensation for
permanent land is 29.362083 million yuan ,completed proportion103.12%; Compensation for
temporary land use is RMB 776.0536, compensations for house demolition 2.2548 million Yuan
was paid, completed proportion 149%.
Table 3-1 Planned impact and actual impact of the project
Item Unit Planned
quantity
Cumulative
completed quantity
Completed
proportion
Permanent acquisition Mu 987.97 1010.336 102.26%
Temporary land Mu 180.99 210.943 116.55%
Housing demolition area ㎡ 2546.09 5096.04 200.15%
Compensation for
permanent land
Thousand
yuan 2847.37 2936.2083 103.12%
Compensation for
temporary land
Thousand
yuan / 776.0536 /
Compensation for house
demolition
Thousand
yuan 151.7 225.48 148.64%
3.3.1 House Demolition and Resettlement
Before December 31, 2014, the affected households have signed the house demolition
agreement, and before December 31, 2015, the resettlement work has been completed. See table
3-2 for the demolition situation.
Table 3-2 Housing Demolition Area
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 61
Dongliu Town Yaodu Town Total
RAP Actual RAP Actual RAP Actual
Housing demolition area
(㎡) 1262.41 1684.98 1283.68 3411.06 2546.09 5096.04
Affected households number (hu) 8 10 6 17 14 27
Note: Through understanding of the personnel involved in the preparation of the resettlement
plan in Yaodu and Dongliu towns, the number of houses demolished in the two towns is less than
one. The GaoWeigui and Gao Guosheng conjoined rooms in JuYang village, Dongliu Town, were
counted by one household. Lin Maosheng and Lin Qinggen in Guanshan village of Yaodu town
were also conjoined houses, which were counted by one household; And another five were
abandoned houses and flood control management houses, which only need monetary
compensation and no resettlement.
In addition, the reasons for the increase of housing demolition area are: on the one hand, the
safety distance of the red line for land acquisition of the newly demolished houses is insufficient,
the lighting is insufficient, the houses are wet and not suitable for living, etc., which are voluntary
resettling households; on the other hand, the houses outside the red line of the road are impacted
by ramming during the construction process, and the house foundation and structure are damaged
to a certain extent, which need to be demolished and resettled, and the affected households shall
negotiate with the project office for settlement with no objection. See Annex 17 for housing
demolition agreement. The statistics of 6 households increased in house area demolition and the
increased area and reasons are as follows:
Table 3-3 increase of demolition area of relocated households.
Town NO. Name
Demolition
area(㎡) Reasons
Yaodu Town 1 Ye Longlin 117.31 Insufficient lighting wet
2 Zhu Wenbiao 78.10 Ramming
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 62
Town NO. Name
Demolition
area(㎡) Reasons
3 Su Renguang 173.43 Insufficient safety distance
4 Liu Airong 69.82 Ramming
5 Su Renya 145.79 Insufficient safety distance
Subtotal 584.45
Dongliu 6 Ding Xiufen 64.19 Insufficient lighting wet
Subtotal 64.19
Total 648.64
The resettlement methods for the relocated households include centralized resettlement and
decentralized resettlement, all of which are monetary compensation and local self built new houses
allocated by the government. The 22 affected households had been completed and relocated before
December 31, 2015.
(1)Yaodu Town
The resettlement methods involved in the demolition of Yaodu town were to disperse the
resettlement according the villagers' personal wishes, and to coordinate the homestead by
themselves. In case of difficulties, village organizations can assist in the coordination. If the water
supply and power supply, cable television and other services of the resettled households needed to
be reopened due to demolition, the government should coordinate with the relevant departments to
properly solve the problem without any cost to the resettled households.
According to the on-site monitoring and inspection by the monitoring team, the new houses
of the relocated households in Yaodu town were completed and moved in before August 31, 2015.
According to the on-site investigation of the monitoring team, the living conditions of the residents
affected by the project had been improved, and the housing conditions had been greatly improved
compared with that before the demolition (see the pictures below for the comparison of the house
photos before and after the demolition). The residents of the house demolition had a relatively
satisfied attitude towards the compensation and resettlement of the demolition.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 63
1) Before and after the demolition of the house of Su Renya
2) Before and after the house demolition of Huang Hanlin
3) Before and after the house demolition of Lin Maocai
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 64
4) Before and after the house demolition of Su Rencai
5) Before and after the house demolition of Su Rencai
6) Before and after the house demolition of Ye Longlin
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 65
7) Before and after the house demolition of Zhang Guofeng
Figure 3-1 comparison of houses before and after demolition
(2) Dongliu town
The villagers involved in Dongliu town's demolition were resettled in a centralized way,
while respecting the individual's will to choose the resettlement way. The transitional housing for
the relocated households were provided by the village committee free of charge.
Four households in Zhanggang village of Dongliu town were relocated, and Zhu bingbin
household was resettled according to his own wish. His homestead was provided by the village
committee free of charge, and the compensation for the original homestead was also paid in full
according to the compensation standard. The other three households were resettled in Zhanggang
village by the village committee. By December 31, 2015, all resettlement houses had been
completed and reached living conditions, and residents had moved in. The relevant approval
documents of the resettlement site project are being processed. Since the land of the resettlement
site is owned by the collective, it cannot be listed for trading, but it can be traded between villagers
within the scope of the village.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 66
Figure 3-2 Housing construction in Zhanggang village, Dongliu town
There are 6 households to be relocated in Xiyang village, Dongliu town. The resettlement
site is located in the beautiful rural construction site to the east of Xiyang village. The village
committee provided the homestead free of charge, and the compensation for the original
homestead of the relocated households was paid in full according to the compensation standard.
The six self built resettlement houses in the JuYang village of Dongliu town were completed by
the end of June 2015 and moved in.
Figure 3-3 Current situation of centralized resettlement sites in Xianyang Village
The cost of water supply, power supply, road traffic and other infrastructure related to
Dongliu town resettlement site were borne by the village committee. The water, electricity and
cable TV of the relocated households without other relating account opening costs can be paid
directly through original accounts.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 67
Figure 3-4 Resettlement inspection meeting of monitoring group
Figure 3-5 Resettlement monitoring team on site inspection
3.3.2 Permanent land acquisition
The collective land acquisition of G206 project involves 2 towns and 6 administrative
villages in Dongzhi County, Chizhou City, Anhui Province. The permanent land acquisition of the
project is 1010.38 mu, the actual land acquisition of the project is 807.066 mu. The remaining
203.27 mu of land for the project is the original old road, beach and acquired construction land, so
no land acquisition area is required for this project.
3.3.3 Temporary land occupation
The temporary land of the project mainly involves four administrative villages in two
towns of Dongliu and Yaodu, affecting 47 households, and the rest are village collective land. The
actual temporary land for the project is 210.943 mu, including 173.673 mu in Yaodu town and
37.27 mu in Dongliu town. See table 3-4 for the temporary land acquisition. The temporary land
was mainly used for borrow area, spoil area and construction access road.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 68
Table 3-4 List of temporarily acquisition land
Town Address
Area
(mu) use
Affected
situation
Caption house
holds
People
number
Dongliu
Bichong
group
Xiayang
village
18.053
Spoil ground
and
construction
access road
14 58
Spoil ground
16.068 mu;
construction access
road1.985 mu
Zhoucun
group
Zhanggang
village
12.847 1#
Borrow area 10 41
Zhang
group
Zhanggang
village
6.370
Spoil ground
at level
crossing
17 54
Area of other plots
included in the
agreement;
Land group
Total 37.27 41 153
Yaodu
Gaunshan
village 84.24
Spoil ground
2#
Borrow area
2
Spoil ground
15.74mu;
2#
Borrow area68.5 mu
Maotian
village 89.433
3#
Borrow area
Spoil area
4
3#
Borrow area
76.44 mu;
Spoil area12.993 mu
Total 173.673 6
temporary land affected
6 households;
The rest is village
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 69
Town Address
Area
(mu) use
Affected
situation
Caption house
holds
People
number
collective land
Actual land
acquisition grand total 210.943 47
The area of
compensation
temporary land is about
150 mu(including
Meicheng forest farm
and Jin Shangsi farm
forest)
RAP land
acquisition grand total 180.9mu
State owned land, no
compensation
3.3.4 Progress of land acquisition and demolition
The monitoring and evaluation team members learned from the inspection that the whole
land acquisition, demolition and resettlement work started in November 2013, and the housing
demolition and land acquisition work were completed on December 31, 2015. In December 2015,
all 22 households that need to be resettled after the completion of resettlement housing moved in.
3.3.5 Restoration and reconstruction of affected special facilities
(1) Compensation for power line reconstruction and demolition
Due to the construction needs of g206 Dongliu Yaodu section, 20 construction projects of
G206 Dongliu Yaodu section need to be reconstructed by Anhui Dongzhi Chengxing Power Co.,
Ltd., with the compensation amount of 2 million yuan.
On December 31, 2015, all pole lines of Anhui Dongzhi electric power management company
were relocated, rebuilt and completed.
Table 3-5 list of migration completion of pole line and water pipeline
Infrastructure impact type Planned quantity(chu) Actual quantity (chu)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 70
Infrastructure impact type Planned quantity(chu) Actual quantity (chu)
tap water 12 11
Power line Low voltage line 20 19
High voltage line 2 1
Communication optical cable 7 7
Total 41 38
(2) Communication optical cable migration (reinforcement compensation)
For the construction of the project, Chizhou line Bureau of Anhui transmission line
maintenance Bureau of China Telecom Co., Ltd. agreed to relocate or reinforce the national
defense trunk line within the red line of the project. Both parties signed compensation agreement,
and the line relocation was completed. Seven sites of G206 Dongliu Yaodu section construction
project, i.e. Kuanyang, Zhanggang, Daqingshan, Linhua plant and Chitou bridge, need to be
relocated and reinforced. At Daqingshan, the original three optical cable lines were translated, and
the rest four were locally reinforced and protected. The total compensation cost was 930000 yuan,
including 530000 buried optical cable lines and 400000 overhead optical cable lines, which were
used in a lump sum. On June 30, 2015, the relocation of seven telecommunication isopods was
completed.
(3) Tap water migration
On November 20, 2014, Dongliu Town People's government of Dongzhi County signed an
agreement with Dongzhi County Waterworks to reach an agreement on the pipeline rerouting,
renewal and sheath involved in stake No.K0+300-K4+080 within the red line of land acquisition
of Dongliu Kuanyang Zhanggang road construction project, and the water supply rerouting of
Dongzhi County G206 Dongliu Yaodu class I highway, Kuanyang Zhanggang section project
started from the date of signing the agreement on November 20, 2014 and was completed on
February 16, 2015. Before December 31, 2015, the relocation of water pipeline was completed.
3.3.6 Restoration and improvement of water system
For the affected infrastructure, the governments at all levels and the resettlement office shall,
in accordance with the compensation standards and procedures, formulate the corresponding
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 71
specific recovery measures according to the specific conditions of the town (Village);
For the affected households to be resettled in a centralized way, unified planning was adopted,
and the cost of water supply and power supply, road traffic and other infrastructure construction in
the centralized resettlement site were borne by the village committee;
In the construction process of the project, the farmland irrigation water system was inevitably
damaged. The town government coordinated with the construction unit to take temporary measures
to ensure the normal production and life of the farmers. After the project was completed, it was
actively restored. If it cannot be restored, the scientific planning should be carried out again to
avoid the impact on the production and life of the farmers.
The large water system had been fully considered in the design of bridges and culverts in the
construction drawing, but the restoration of ponds and culverts within the red line was not fully
considered, and it was not considered outside the red line. Therefore, in January 2015, the county
government allocated 10 million yuan of special funds for the reconstruction of pump stations,
supporting transformation and new water conservancy facilities, totaling 14 (5 within the red line).
See Annex 22 for statistics of water system restoration project. The new gate dam is shown in the
figure below. On December 31, 2015, all reconstruction and reconstruction of water conservancy
facilities were completed.
(1) Comparison of demolition and construction of Zetanwei gate station
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 72
(2) Comparison of demolition and construction of Da Qingshan gate station and weir
(3) Comparison of demolition and construction of Da Qingshan gate station and weir
(4) Comparison of demolition and construction of wuguitang culvert gate
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 73
(5) Small water conservancy projects Dongliu town is responsible for the construction
Figure 3-6 built drawing of reconstructed and newly built water conservancy facilities
3.3.7 Vulnerable Groups Affected
Monitoring group learned from field investigation, vulnerable group is only involved in
Yaodu Town during this immigration, of which 2 households with low income and 3 people with
disabilities.. All vulnerable groups involved enjoy subsistence allowances. See details in Table 3-6.
Table 3-6 List of land acquisition Du Yao vulnerable situation
No. Belonging to Name Gender Age ID No. Type of
difficulties
1
Tiaokou Group
in Maotian
Village
Peng
Suping Male 39 342921197412063116
Low-income
household
2
Shiyin Group
in Jiandong
Village
Zhang
Guangrong Male 61 342829195301043000
Low-income
household
Zhang
Shuanglong Male 34 342921198011233318
Low-income
household
with
disabilities
3
Shiyin Group
in Jiandong
Village
Jiang
Zhongxiang Female 44 342829197012223323
With
disabilities
4 Shiyin Group
in Jiandong
Zhang
Hong Female 23 342921199111233328
With
disabilities
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 74
No. Belonging to Name Gender Age ID No. Type of
difficulties
Village
Suffering from hepatitis E, Peng Suping is low-income household of Class B, safeguarding 4
persons with 560 yuan monthly subsistence allowances; his mother has grown old and frail, his
wife is a farmer, his son is in middle school. He enjoys the treatment of subsistence allowances.
The low-income household Zhang Guangrong is living with his second son Zhangshuang
Long, and his son has severe mental disability. Two persons are safeguarded by the subsistence
allowances with 280 yuan per month. They are enjoying the treatment of subsistence allowances.
Jiang Zhongyuan, with Grade I of visual disability, lives with the head of household her
husband Xu Xueyi. She is enjoying subsistence allowances.
Zhang Hong is the granddaughter of the household’s head Zhang Sijiu, who has Grade II of
intellectual disability. She is enjoying the subsistence allowances.
3.3.8 Technical training
The resettlement work at earlier stage guarantees the migrants to obtain the compensation
specified in the Resettlement Plan, production and living standards, living environment of the
affected households are restored or improved. With the support of relevant departments, migrant
training modes include centralized training and release of fortune and popular science data for
migrants. Seven phases of centralized skills training were provided in relevant administrative
villages in 2014, 2015 respectively, centralized training content: cereals & oils and cotton planting,
production technology, oil tea cultivation technology, 912 trainees; content of popular science data:
household service, edible fungus, vegetables, melon and fruit planting technology, 1520 copies of
data have been released, totally 3213 person-times trained.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 75
Picture3-7 Site of technical training
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 76
Picture 3-8 Technical training data and content
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 77
Figure 3-9 kick off meeting for external monitoring of resettlement in Dongzhi County
Figure 3-10 interview of resettlement monitoring and evaluation group
3.4 S319 Wuwei to Erba Construction Project Resettlement Monitoring
and Evaluation Process
In the start up stage of resettlement works in S319 subproject, the monitoring team from
AJEPM has conducted field investigation and interviews on this project’s resettlementin October
2014. Inception Report on External Resettlement Monitoring has been provided to ADB by
AJEPM in September 2014. In September 2014, AJEPM submitted the start report of external
monitoring on resettlement to ADB, which systematically described the monitoring organization,
monitoring work plan and outline during the implementation of the project.The Report has
systematically stated the monitoring organization, schedule and TOR during the implementation of
this project.
External Monitoring Group has conducted a comprehensive inspection on resettlement works
of Road S319 during 12 to 13 January 2015 along with APMO, Wuhu Municipal Transport Bureau,
etc. June 2015, External Monitoring Group conducted field investigation and interviews on the
resettlement progress, submitted the first External Monitoring Report. In Sept., Dec. 2015, and
April 2016, External monitoring agency conducted sampling survey on compensation standards,
compensation and living standards of the affected households.
The land acquisition and demolition work for the reconstruction project ofS319 Erjun Road
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 78
(Erba Wuwei) class I Highway in Wuwei County has been completed. The permanent land
acquisition of the project is 304.7252 mu, and the temporary land occupation is 71.37 mu. The
housing demolition of the project involves 56 houses and 2 enterprises. The total demolition area
is 12277.83m2.
3.4.1 House Demolition and Resettlement
The project involves the houses of rural residents in Fudu community and Hualong co
mmunity of Dougou town. The house demolition involves 56 houses and 2 enterprises, wit
h a total demolition area of 12277.83 ㎡. The area of 56 households is 9947.91 ㎡, and t
he compensation amount is 6.43145 million yuan; the demolition area of the other two ent
erprises is 2329.92 ㎡, and the compensation amount is 5.4415 million yuan; the total de
molition area is 12277.83m2. Among them, there are 4 households in Dougou town with
an area of 461.44 ㎡, 52 households in Fudu town with an area of 11816.39 ㎡. Of the
56 households, 6 choose monetary compensation and 50 choose centralized resettlement, wi
th 110 resettlement houses.
Table 3-7 statistics of housing demolition area
Contents Towns
Number of relocated
households(hu)
Demolition area
(㎡)
Compensation for
demolition(yuan)
Dougou Town 4 461.44 509826.81
Fudu Town 52 11816.39 11363124.42
Total 56 12277.83 11872951.23
By December 30, 2019: among the 50 households of centralized resettlement, 24 households
have been fully resettled (38 resettlement houses), 17 households have not been fully resettled (54
resettlement houses should be resettled, 24 resettlement houses have been actually resettled), 9
households have not been resettled (18 resettlement houses), that is, 110 resettlement houses have
been resettled 62 sets, and 48 more need to be resettled. The main reasons for incomplete
resettlement and non resettlement are as follows: first, the housing resources of type C (90 ㎡)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 79
resettlement agreed by resettlement community (Chengdong new area) are insufficient; second,
some resettlement households have multiple resettlement houses, voluntarily give up the
resettlement housing resources of Chengdong new area, and they are required to be resettled in
different resettlement areas.
The resettlement community under construction includes Jingfuyuan, Linyu, Donglefu, etc. in
September 2019, the house number of the relocated households has been selected, and the
resettlement house is planned to be delivered centrally during the Spring Festival in 2020. During
the period of waiting for resettlement, the transition fees of resettlement households have been
paid in full on time, and most of the households who have not been allocated have also selected
1-2 sets of resettlement houses or other housing in Chengdong new area.
Figure 3-11 resettlement site of Chengdong new area
3.4.2 State-owned Land Acquisition Area
S319 mu of state-owned land as transferring land will be occupied permanently for the
subproject, affecting two enterprises (Changba Cotton Industry Co., Ltd. & Fangsu Edible Fungi
Co., Ltd. ) with 45 workers. Externalmonitoring group learned that, after consultation with
affected enterprises, Changba Cotton Industry Co., Ltd. was eliminated due to market factors, the
owner agreed only cash compensation; Fangsu Edible Fungi Co., Ltd. Agreed the resettlement
mode of relocation and cash compensation.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 80
Current Status of Wuwei Changba Cotton Industry Co., Ltd.
Interview in Wuwei Fangsun Edible Fungi Co., Ltd.
Figure 3-12 pictures of state owned land enterprises before demolition
See table 3-8 for state-owned land acquisition
Table 3-8 List of state owned land acquisition
Town Village Village
group Name of Enterprises Area(mu) Nature Aps Compensation (ten
thousand RMB)
Fudu
Town
Fudu
Community Changba
Changba Cotton Industry Co.,
Ltd. 5.7 Transfer 30
299.9393
Fudu
Town
Fudu
Community Changba Fangsun Edible Fungi Co., Ltd. 5 Transfer 15
244.2107
total 2329.92 45 544.15
3.4.3 Permanent Land Acquisition
The project actually completed 304.7252 mu of permanent land acquisition, 184 Mu less than
the resettlement plan. The reason is that other projects in Fudu town have been levied by the
government, and there is no need to levy repeatedly in this project. (The land requisition has been
used for the construction of the project, and the land acquisition standard is the same as the
compensation standard for land acquisition of the project)
See Annex 40 for land acquisition agreement
3.4.4 Temporary Land Acquisition
According to the final Resettlement Plan, this subproject will involve 199mu of temporary
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 81
land for borrow pits and disposal sites in Fudu Town&Shijian Town of Wuwei County. Of which
9.87 mu in Shibei Village, Fudu Town is occupied for mixing station in Contract 02; 7.22 mu in
Wangfu Administrative Village Lingzhuang Natural Village of Wucheng Town is occupied for the
mixing station, reinforcement processing plant in Contract 03; 7.89 mu in Changba Village, Fudu
Town is occupied for temporary spoil grounds.
3.4.5 Restoration and Reconstruction of the Affected Special Facilities
S319 project involves the relocation and reconstruction of facilities such as water supply
pipelines, communication optical cables, high voltage rod lines and signs along the whole route.
To adhere to the principle of “minimum impact”, mobilization and coordination meetings on
demolition works of rod lines, pipelines and signs along the route were held by the Wuwei County
Headquarters on June 26 and November 13, 2014 as well as April 13, 2015. The meetings have
determined the contacts and responsible departments to negotiate with various property units
including power supply, China Mobile, China Telecom, China Unicom, Cable Television and
water supply companies. Currently, specific compensation rates and quantities are under
negotiation.
For the relocation of high and low voltage rod lines (K0 + 000 ~ K18 + 000) involved in
S319 project within Jiujiang District, Jiujiang District Construction Commission entrusted by
Wuhu Municipal Transport Bureau will sign an agreement with electrical contractor and be in
charge of relocation; for relocation of water supply pipelines within the scope of 35m from the
center line to both sides of the downtown section, Jiujiang District Resettlement Office will be
responsible for negotiation with the property owner of water supply together with Erba and
Tanggou Town Governments; the section from K7 + 000 ~ K18 +000 is relocated within the scope
of 18m from center line to both sides; weak current rods&lines and underground cables will be
executed by Wuhu Municipal Transportation Bureau in accordance with the document of GG
[2014] No.96, and the specific construction will be conducted bythe project construction office.
All need to remove the non-benchmark lines (K0 + 000 ~ K18 + 000) is responsible for the
Jiujiang.
External monitoring group learned that, relocation status of pole and pipe lines for S319 Erba
to Wuwei Section Reconstruction project (Urban Area Section) as of June 30, 2016 are as follows:
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 82
the original 16 m wide pavement was widened to 25.5 m, the land in the widened construction
scope was already acquired in 2000, now becomes road shoulders and side ditches. Through
investigation, except Italian poplars, buried optical cables, tap water pipes and a number of
communication and power rod lines across highway, there are no house and other ancillary
facilities in the widened scope, personnel resettlement did not occur.
3.4.6 Vulnerable Groups Affected
According to the final report of the migration plan, the project involves 28 vulnerable groups,
including 7 households with five guarantees, 21 households with low guarantees and 3 disabled
people. After the field investigation, the external monitoring team learned that: Erba and Tanggou
did not involve vulnerable groups, Dougou and Fudu towns involved 16 vulnerable groups, 11
low-income households and 1 disabled person.
The external monitoring team learned that the low-income insurance households currently
enjoy the low-income insurance treatment, with the standard of 150 yuan / month.
3.5 S367 Ma’anshan Northern Passage Road Resettlement Monitoring and
Evaluation Process
External monitoring survey group learned that, since permanent land acquisition required for
construction was not approved at early stage of the project, land acquisition and demolition was
not carried out substantially for the project. In Feb. 2016, land use formalities required for project
construction was approved by the Ministry of Natural Resources, land acquisition and demolition
was started for the project from Apr. 2016. Since May 2016, typhoon in coastal areas of China
caused rainstorm and flood disasters in the districts of Anhui Province, delayed acquisition and
demolition seriously, so acquisition and demolition for this project proceeded slowly. At the end of
July 2016, land acquisition and demolition work was officially started. In June 2019, the land
acquisition, demolition and resettlement of the project were completed.
The S367 project involves Hanshan and Hexian counties.
Table 3-9 summary of land acquisition and demolition of S367 project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 83
contents
towns
Land
acquisition
area
(mu)
Compensation
for land
acquisition
(ten thousand
yuan)
Relocated households(hu)
Demolition
area
(㎡)
Demolition
compensation
(ten thousand
yuan)
Compensation
for
appurtenances
and structures
only(hu)
Compensation
for
appurtenances
and structures
(ten thousand
yuan))
Within
the red
line
Outside
the red
line
subtotal
He County 958.694 3625.2244 100 43 143 17589.49 2546.8864 22 20.0184
Hanshan
County 279.2591 927.8015 25 5 30 3627.8 839.7462 0 0
total 1237.9531 4553.0259 125 48 173 21217.29 3386.6326 22 20.0184
The permanently expropriated land in Hanshan county is 279.2591 mu, and the compensation
for land acquisition is 9.278015 million yuan, including 30.8918 mu, 1.13613 million yuan,
24.83673 mu, 8.141912 million yuan in Xianxu Town, Zhaoguan town. The project involves 30
households of house demolition, including 7 households within 5m outside the red line, with a
total area of 3627.8m2, all of which are monetary compensation, with a compensation amount of
8.397462 million yuan.
The main reason for the demolition within 5m outside the red line of Hanshan county project
is that the houses outside the red line of land acquisition along the road are close to the road.
Considering the factors such as ensuring the operation safety after the completion of the road, the
residents took the initiative to require the demolition. Referring to the relevant practices of land
acquisition and relocation of other highways (such as S226 and S105) in Hanshan County, the 16th
executive meeting of the people's Government of Hanshan county decided on June 22, 2018 to
demolish the main houses of households along the project within 5 meters (including 5 meters)
from the red line of highway construction land.
The permanent land acquisition of the project in Hexian county is 958.694 mu, with the
compensation amount of 36.25224 million yuan, including 561.786 mu in Shanhou Town, with the
compensation amount of 22.353622 million yuan, and 396.908 mu in Shiyang Town, with the
compensation amount of 13.898622 million yuan. The project involves the demolition of 143
houses, with a total area of 17589.49 ㎡, and a total compensation of 25468864 yuan. Shanhou
town involves 83 households of house demolition (including 19 households within 3 meters
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 84
outside the red line), with demolition area of 9938.33 ㎡ , compensation amount of RMB
13.514535 million; only 22 households of accessory and structure compensation, compensation
amount of RMB 201.84 million, total compensation amount of RMB 13.714719 million.
In Shiyang Town, Hexian County, 60 households (including 24 households within 3 meters
outside the red line) are involved in house demolition. The demolition area is 7651.16 ㎡, and the
compensation amount is 11954329 yuan. The main reason for the demolition within 3 meters
outside the red line of land acquisition of Hexian county project is that the residential houses are
close to the red line of land acquisition. Considering the factors such as ensuring the operation
safety after the completion of the road, the residents took the initiative to require the demolition.
Figure 3-13 Ma'anshan data collection by monitoring group
3.5.1 House Demolition and Resettlement
1) Demolition
The demolition of this project does not involve the demolition of non residential houses. They
are all rural residential houses.
See Annex 41 for the agreement on compensation and resettlement for house demolition.
Hanshan project involves 30 households of house demolition, including 7 households within 5m
outside the red line, with a total area of 3627.8m2, all of which are monetary compensation, with a
compensation amount of 8.397462 million yuan.
The permanent land acquisition of the project in Hexian county is 958.694 mu, with the
compensation amount of 36.25224 million yuan, including 561.786 mu in Shanhou Town, with the
compensation amount of 22.353622 million yuan, and 396.908 mu in Shiyang Town, with the
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 85
compensation amount of 13.898622 million yuan. The project involves the demolition of 143
houses, with a total area of 17589.49 ㎡, and a total compensation of 25468864 yuan. Shanhou
town involves 83 households of house demolition (including 19 households within 3 meters
outside the red line), with demolition area of 9938.33 ㎡, compensation amount of RMB
13.514535 million; only 22 households of accessory and structure compensation, compensation
amount of RMB 201.84 million, total compensation amount of RMB 13.714719 million. Shiyang
town involves 60 houses to be demolished (including 24 houses to be demolished within 3 meters
outside the red line), with an area of 7651.16 ㎡ and a compensation of 11.954329 million yuan.
The main reason for the demolition within 3 meters outside the red line of land acquisition of
Hexian county project is that the residential houses are close to the red line of land acquisition.
Considering the factors such as ensuring the operation safety after the completion of the road, the
residents took the initiative to require the demolition. The main reason is as shown in Figure 3-24.
Figure 3-14 residential houses along the widening section
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 86
2) Resettlement
Of the 143 households involved in house demolition in the Hexian project, 83 households in
Shanhou town were all monetary compensation; 4 households in 60 households in Shiyang town
were property right replacement resettlement, of which 3 households were concentrated in the
resettlement site of Daima in Shiyang community, 1 household was relocated in other places, and
the others were monetary compensation.
Figure 3-15 centralized resettlement site of Daima in Shiyang community
3.5.2 Permanent Acquisition of Collective Land
The permanently expropriated land in Hanshan county is 279.2591 mu, and the compensation
for land acquisition is 9.278015 million yuan, including 30.8918 mu, 1.13613 million yuan,
24.83673 mu, 8.141912 million yuan in Xianxu Town, Zhaoguan town.
The permanent land acquisition of the project in Hexian county is 958.694 mu, with the
compensation amount of 36.25224 million yuan, including 561.786 mu in Shanhou Town, with the
compensation amount of 22.353622 million yuan, and 396.908 mu in Shiyang Town, with the
compensation amount of 13.898622 million yuan.
3.5.3 Temporary Land Occupation
The temporary land occupation of the project is rural collective land, and all of them are
unused land. The property right belongs to the village collective, so the project does not affect the
population. Compensation shall be made according to the compensation standard.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 87
3.5.4 Pole Line and Other Infrastructure
The whole line units of the project are divided into mobile, Unicom, telecom, national
defense and township waterworks. Compensation shall be made according to the compensation
standard.
3.5.5 Vulnerable Groups Affected
The affected population of the project is all Han nationality. According to the survey, the main
vulnerable groups of the project are low-income and five guarantee households. According to the
survey, 55 households and 164 people are vulnerable groups. In the whole process of resettlement,
PMO, implementing agencies and local governments paid special attention to the resettlement of
vulnerable groups. In addition to living and production resettlement for vulnerable groups
according to the project implementation plan, it also provides some help to improve production
and living conditions. Mainly as follows:
Five guarantees
The village collective reserves the compensation, provides the allowance to the five
guarantees every month, and provides the free medical treatment;
Low security households
1) Two family members in each household have access to technical training opportunities, at
least one of them is female. Meanwhile, priority should be given to arranging employment
opportunities related to project construction, providing them with employment related information,
etc.
2) Local governments pay pensions.
In addition to the above vulnerable groups, the households seriously affected by land
acquisition (the land loss rate is more than 10%) will also enjoy the following measures:
1) More than 10% of the seriously affected households will be given priority to the
employment opportunities for the construction and operation of the project, and participate in
various agricultural and non-agricultural technical training for the farmers who have been
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 88
requisitioned for the project.
2) If possible, the replaceable land will be given priority.
Figure 3-16 Ma'anshan household survey by resettlement monitoring group
3.6 G318 and S320 Yimu Highway Project Resettlement Monitoring and
Evaluation Process
Field investigation was conducted for ADB-financed Anhui Nanling County Yimu Highway
Project in Sept. 2014. Inception Report on External Resettlement Monitoring has been provided to
ADB by the Company in September 2014. The Report has systematically stated the monitoring
organization, schedule and TOR during the implementation of this project.
According to Nanling County Yimu Highway Project Resettlement Plan (before updating),
resettlement work would start from March 2014, end in Dec. 2014, so Nanling County Project
Office started publicity of resettlement policies and compensation standards into households
related to the project from May 2014. Nanling County Project Office completed land acquisition
setting-out, house measurement and registration from May to Dec. 2014; and signed compensation
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 89
agreement with the affected households. Meanwhile, Anhui Jiaoyuan Engineering Project
Management Co., Ltd. Entered the project site for investigation and visits, focus on the
resettlement progress. Dec. 2015, resettlement plan of this project based on detailed investigation
was approved by ADB. From November to December 2015, April, October and December 2016,
the resettlement monitoring team conducted an investigation on the resettlement progress of Yimu
road in Nanling County.
The monitoring evaluation group learned from this investigation that, Nanling Yimu Highway
project acquired permanent land 654.71 mu as of Jun. 30, 2016, completed proportion 94.02%;
acquired temporary land 353.5 mu, completed proportion 37.81%; Areas of house demolition 3813
㎡, completed proportion 55.45%; land compensation fee 13.51 million Yuan was paid, completed
proportion 81.63%; compensations for house demolition 2.515 million Yuan was paid, completed
proportion 18.98%.
Figure 3-17 monitoring team visit
Figure 3-18 resettlement training and field discussion
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 90
Figure 3-19 data collection of Yimu road by monitoring team
Figure 3-20 interview survey of resettlement monitoring group
The acquisition and relocation of Yimu highway in Nanling County mainly involves
Gongshan town and Jishan town. In June 2019, the land acquisition and relocation work was
completed. Permanent land acquisition is 479.4 mu, accounting for 49.314% of the planned
number of immigrants; house demolition area is 6706.76 m2, accounting for 87.72% of the
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 91
planned number of resettlement.
Table 3-10 summary of land acquisition and demolition of Yimu highway
contents
towns
Land acquisition
area(mu)
Compensation for land
acquisition
(ten thousand yuan)
Number of
demolition
households
(hu)
Demolition area
(㎡)
Compensation for
demolition
(ten thousan yuan)
Gongshan Town 337.86 976.8163 15 3127.13 16.7045
Jishan Town 141.54 1061.3184 23 3579.63 585.6
Total 479.4 2038.1347 38 6706.76 602.3045
The reason why the number of land acquisition and demolition is less than that of the
resettlement plan: in other projects of Jishan Town, the government has completed the land
acquisition and demolition of some land houses, so it is not necessary to repeat the expropriation.
3.6.1 Housing Demolition and Resettlement
The demolition area of Gongshan town is 3127.13 ㎡, and 15 households are involved in the
demolition, of which 14 households are resettled in Daitang community, one household is
monetary compensation, and the compensation amount for demolition is 167045 yuan.
The demolition area of Jishan town is 3579.63 ㎡ , involving 23 households in total,
including 13 households and 10 non residential houses (individual businesses), with the
compensation amount of 1981762 yuan.
All the 10 households of non residential house demolition are property right replacement,
while resettlement, the part of business area is compensated by 600 yuan / m2, see the following
table for the specific compensation amount.
Table 3-11 list of affected individual businesses
No. Self employed householder Area(㎡) Compensation amount(yuan)
1 Yuan yuxia 57.45 34470
2 Wang jianhui 62.11 37266
3 Wang yifa 62.11 37266
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 92
No. Self employed householder Area(㎡) Compensation amount(yuan)
4 Zheng aiying 63.00 37800
5 He hongxiang 63.36 38016
6 Fan hunyin 55.08 33048
7 Hu shiwen 63.00 37800
8 Huang jinlin 94.20 56520
9 Yi changshou 82.93 49758
10 Zhangshun 66.98 20094
Total 670.22 382038
See Annex 43 for the agreement on compensation and resettlement for house demolition.
According to the relevant staff of Jishan Town, the resettlement sites of Jishan town include
Qilin villa, Meiyuan New Village Phase II and Chengbei phase II for the relocated households to
choose from.
Kylin Villa
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 93
Meiyuan New Village Phase II
Chengbei phase II
Figure 3-21 resettlement community
3.6.2 Permanent Acquisition of Collective Land
The land acquisition and demolition work in Nanling County involves Jishan town and
Gongshan town. In Gongshan Town, 337.86 mu of land is permanently expropriated, and the
amount of land compensation is 9.768163 million yuan. Jishan town permanently expropriates
141.54 mu of land, and the amount of land compensation is 10.613184 million yuan. The part of
collective land within the red line of Jishan town has been expropriated by other projects from
2005 to 2013, so it does not need to be expropriated again.
See Annex 44 for land acquisition agreement.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 94
3.6.3 State Owned Land
In June 2019, a total of 7 state-owned land acquisition projects were finally determined. In
December 2017, 7 state-owned land assessments were completed and compensation agreements
were signed, and compensation funds were issued.
No. Name of Affected Unit Compensation(ten thousand yuan)
1 China National Gas Corporation 59.4655
2 Peng Zhenhua 13.9842
3 Zhenyun logistics company 250.7895
4 South bus station 62.3403
5 PetroChina gas station 158.6962
6 Wuhu Hongshun Real Estate Development Co., Ltd 105.3729
7 Wuhu Tengxin Industry Co., Ltd 1.5455
3.6.4 TemporaryLand Acquisition
353.5 mu of temporary land for the project:
Lot 01 mixing plant is located in Mingtai glass plant, No. 18 Huashan Road, Nanling
Economic Development Zone, covering an area of about 30 mu; small prefabrication plant is
located in Nanling Development Zone, covering an area of about 10 mu; borrow pit is located in
the south side of Nanling Development Zone, covering an area of about 100 mu; waste dump is
located in LUOJIACHONG, Dagang village, Jishan Town, Nanling County, covering an area of
about 60 mu;
Lot 02 mixing plant is located in Gongyi village, Gongshan Town, Nanling County, covering
an area of about 60 mu; small prefabrication plant is located in Gongshan Town, Nanling County,
covering an area of about 15 mu; borrow pit is located in Gongyi village, Gongshan Town,
Nanling County, covering an area of 50 mu; spoil heap is located in Gongyi village, Gongshan
Town, Nanling County, covering an area of about 15 mu; lot 02 road or other infrastructure is
located in Gongshan Town, Nanling County, covering an area of about 10 mu.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 95
3.6.5 Infrastructure
The project has a total impact on walls, fences, cement floors, poles, wires, street lights,
junction boxes, transformers, graves, wells, trees, etc. All of them are compensated according to
the compensation standard.
3.7 Shuiyang River Integrated Transport Construction Project
Resettlement Monitoring and Evaluation Process
Nov. And Dec. 2015, Anhui Jiaoyuan Engineering Project Management Co., Ltd.
Resettlement Monitoring Group carried out field investigation on the ADB-financed Anhui
Shuiyang River Integrated Transport Construction Project, provided training for resettlement work
of this project.
Picture 3-22 Shuiyang River Resettlement Training Meeting
Picture 23- Baseline Survey on Living Standards of the Farmers Affected by Shuiyang River
Integrated Transport Project
In December 2016, the external monitoring team went to the water Yangjiang project site to
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 96
investigate and interview the progress of resettlement work, and completed the external monitoring
report of resettlement in this period. From June to July 2016, the rainstorm and flood disaster
weather in Anhui Province led to no significant progress in the relocation work. By the end of
November 2016, the land acquisition and demolition of Xuanzhou port comprehensive wharf and
Xiaohekou bridge project were completed. In December 2016, land acquisition and demolition
work for waterway regulation began.
By the end of June 2018, the permanent land of 917.52 Mu has been expropriated for the
Shuiyangjiang shipping comprehensive construction project; the house demolition area is 8544.24
m2.
Table 3-12 statistics of land acquisition and demolition of Shuiyangjiang shipping project
Port engineering
Permanent land acquisition
(mu) Demolition area(m2)
RAP plan Actual RAP plan Actual
499.5375 447.71 5203 4660.9
Waterway
Engineering
Xiaohegou
bridge
406.6155
37.13
2860
925.61
Gate dam 353.4 772.78
Channel
dredging 79.28 2184.95
Subtotal 406.6155 447.71 2860 3883.34
合计 906.153 917.52 8063 8544.24
3.7.1 house demolition and resettlement
As of December 2016: 8544.24 ㎡ of houses demolished in the project. 4660.9 ㎡ of port
engineering demolition; 3883.34 ㎡ of channel engineering house demolition, including 925.61
m2 of Xiaohekou bridge demolition, 772.78 m2 of gate dam demolition, 2184.95 m2 of channel
dredging demolition. The resettlement is as follows:
1) Resettlement of Xuanzhou port comprehensive Wharf Project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 97
Xuanzhou port comprehensive wharf project involves demolition of 28 residential houses
(including 1 smoke pit), with demolition area of 4660.99 ㎡. 26 of these relocated households
choose the way of property right replacement for resettlement, and 2 households choose monetary
compensation for resettlement. A total of 60 houses with an area of 5780 ㎡ need to be resettled
in the way of property right replacement. The local government plans to place the resettlement
houses in the "Huishang No.1" community.
As of June 30, 2019, the monitoring team learned that the developer responsible for the
construction of "Huishang No.1" had gone bankrupt and was being restructured; the resettlement
community could not be completed on schedule, and the 26 relocated households to be resettled
were still in the transitional period; the government of Yangxian Township had paid the transitional
fee for the first half of 2019.
2) Arrangement of Xiaohekou Bridge
The Xiaohekou bridge project involves the demolition of 11 houses. One of the relocated
households chose to resettle 10 old workers' dormitories with monetary compensation. The
property right of the houses belongs to the pottery factory under the county economic and
Information Commission. Xuanzhou District Economic and Information Commission has built 10
new resettlement houses in the pottery factory and continued to place the original households in
the resettlement houses. The auxiliary facilities of the original demolished houses have been
compensated to each household in currency. The resettlement housing construction project was
started on May 10, 2018, delivered in June 2019, and the transition fee has been issued.
3) Gate and dam project placement
The demolition of the project involves three houses, a shipyard, a water intake of a water
plant and a slaughterhouse. Among the three households, one house is shifted, two houses are built
on their own and one house is compensated with money. The demolition area is 772.78 ㎡, and
the compensation amount is 1042619 yuan. The shipyard has been closed for many years, and it
does not have the conditions to continue its business. The compensation amount is 5603238 yuan.
The water intake of the waterworks does not meet the requirements of the health code after the
completion of the shiplock The relocation of the water intake is carried out and the cost is paid by
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 98
the project owner. The relocation of the water intake has been completed. At present, the advance
payment of 4.43 million yuan has been paid, and the final cost will be settled according to the
actual situation after the government audit. After receiving monetary compensation, the
slaughterhouse improved its operation conditions and continued its production and operation.
4) Demolition and resettlement of waterway dredging project
The demolition involves 23 houses and 2 ship building factories in Liqiao town. 23
households have been demolished, among which 13 households have chosen monetary
resettlement and 10 households have chosen non local resettlement. The demolition area is
2184.95 ㎡, and the compensation amount is 2483099 yuan. The resettlement of non local
resettlement is chosen in the new rural resettlement site of Dongyun village. Two ship repair and
construction plants are monetary compensation, with the compensation amount of 3.06 million
yuan.
Figure 3-25 resettlement site of Dongyun New Village
3.7.2 Permanent Land Acquisition
The three sub items of the project involve collective land and state-owned land acquisition.
The land acquisition of the project involves 5 villages and 7 villagers' groups in Yangxian
Township, Liqiao town and Shuiyang Town, Xuanzhou District, Xuancheng City, Anhui Province.
A total of 917.52 mu of land is permanently expropriated for the project, including 447.708 mu of
port works and 469.81 mu of waterway works.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 99
3.7.3 Temporary Land Acquisition
Temporary land for construction refers to the land temporarily borrowed during the
construction period of the project, including the land occupied by borrow areas, production and
living areas and temporary roads during the construction period. The temporary land occupation of
the project is mainly the temporary land occupation of the dumping site, which does not involve
the temporary land occupation of the borrow area. Compensation shall be made according to the
compensation standard.
3.7.4 Infrastucture
The project affects 350kv high-voltage line, 10kV line, irrigation and drainage station,
transformer, etc., and compensates according to the compensation standard.
4 Compensation standard for Resettlement
According to the regulations and policy requirements of the Chinese government and the
Asian Development Bank, the principle of compensation and rights and interests of the project is
formulated. The goal is to ensure that the resettlers receive adequate compensation and assistance
measures, at least to ensure that their living standards are restored to the level before the project
starts. The resettlement principles of the project can be seen in table 4-1.
Table 4-1 The project resettlement principles
Principles
1 If possible, avoid involuntary resettlement
2 The compensation and rights that the affected people get can be maintained as their living
standards before the "no project" state, and may also improved.
3 Regardless of legal rights or not, the affected people will receive resettlement compensation
and assistance.
4 If the land of each person after land acquisition is not enough to sustain his / her livelihood,
the loss of land shall be compensated in cash or material, as well as other income generating
activities.
5 The affected people have a full understanding of the qualifications, compensation methods
and standards, livelihood and income recovery plan, project schedule, and participate in the
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 100
Principles
implementation of the resettlement plan.
7 The implementing agencies and independent / third parties will monitor the operation of
compensation and land acquisition and resettlement.
8 Vulnerable groups receive special assistance or treatment to ensure that they live better, and
all affected groups should have the opportunity to benefit from the project. Each resettling
family has two family members who have received skills training, at least one is a female.
9 The resettlement plan is consistent with the overall plan of the affected cities (districts,
counties) and towns.
10 The resettlement costs will fully cover all affected areas in full.
4.1 G206 Dongliu to Yaodu Project Compensation Standard
4.1.1 Land acquisition standard
G206 Dongliu to Yaodu Permanent land required for the project has received the approval of
Anhui Provincial Government (see Attachment 1). Approved land area 1032.96 mu, the approved
land quantity exceeds permanent land quantity in the resettlement action plan and actually
acquired land quantity.
It is learned through investigation that, after procedures of submission for approval on land
are completed, each villager and household affected by land acquisition have signed resettlement
grant agreements (Attachment 4), the compensations for appendages on the expropriated land,
crop compensation fees and resettlement subsidies owned by individuals have been directly
transferred to the account provided by the farmers in the form of cash.
The situation of social insurances for households with less than 0.3mu arable land per capita
after land acquisition are not involved in the project land acquisition.
4.1.1.1 Quantity and Compensation Standard for Collective Land Acquisition
Table 4-2 Compensation standard for permanent collective land acquisition
Region Farmland Construction Land and Unutilized Land
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 101
Updated
Planned
Actual
Executed
Received
By
household
Updated
Planned
Actual
Executed
Received
By household
Zhaqiao, Maotian,Jiandong
Villages in yaodutown 36800 36800 36800 18400 18400 18400
Guanshan Village in Yaodu Town 32780 32780 32780 16390 16390 16390
Dongliu Town 32780 32780 29651 16390 16390 16390
In accordance with the stipulations in the Notice of the Anhui Provincial Government on
Adjusting Compensation Rates for Land Acquisition of Anhui Province (APG [2012] No.67), and
Work Scheme for Land Acquisition of G206 Dongliu to Yaodu Construction Project in Dongzhi
County(DLZ[2013] No.31), Agreement for Compensation on Land Acquisition have been reached
after consultation among Town’s Government, Village Committee and villagers affected land
acquisition. According to the compensation standards indicated in above mentioned two
documents, the land is provided. The compensation standards are:
(I) Agricultural land:
(1) the compensation standard of 32,780 Yuan/mu will be used in Xiayang, Zhanggang,
Villages in Dongliu Town and Guanshan Village in Yaodu Town, of which it has paid
29,651yuan/mu to each household (i.e.land compensation (70%) with the standard of
7,301yuan/mu + resettlement subsidy with the standard of 22,350 Yuan/mu);
(2) the compensation standard in Zhaqiao, Maotian, Jiandong Villages in Yaodu Town is
36,800 Yuan/mu. Of which, each household has received 32,960 Yuan/mu (i.e.land compensation
fee(70%) with the standard of 8960 Yuan/mu + resettlement subsidy of 24,000 Yuan/mu);
30% of land compensation will be allocated to collective-economic organization in village
level, which will be used for public welfare organizations and safeguard for land-lost peasants in
village level within the region of land acquisition and resettlement.
Withdrawal and Retention are on the basis of “Notice of Issuance of Work Scheme for Land
Acquisition of G206 Dongliu to Yaodu Construction Project in Dongzhi County” (DLZ [2014]
No.1). During the actual implementation, full compensation amount of land acquisition have been
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 102
paid to farmers with two time appropriation and without withdrawal and retention in any forms by
Yaodu Town according to farmers’ requirements.
(II) Compensation standard for young crops is 700 Yuan/mu.
(III) Annual rent of temporary land is 1390 Yuan/mu.
(IV) according to the Resettlement Plan and WZ [2012] No.67 Document, the compensation
standards for unused land and construction land take a half of compensation rate for agricultural
land.
To summrize the above-mentioned indicators, compensation standards for permanent
acquisition of collective land meet the compensation standards of the project in the resettlement
plan, and meet policy requirements in China.
4.1.1.2 Area and Compensation Standards for State-owned Land Acquisition
Township Dongliu Town Yaodu Town
Permanent occupation
planned compensation standard 32780yuna/mu 36800yuan/mu
Permanent occupation
executive compensation standard 36800yuan/mu 36800yuan /yuan
Compensation for the woodland acquired for the Subproject is based on the Notice of the
Anhui Provincial Government on Adjusting Compensation Rates for Land Acquisition of Anhui
Province (APG [2012] No.67) (May 19, 2012), whose Article 2 writes, “If land of a state-owned
agricultural (forest, livestock or fish) farm is acquired, the compensation rates for land acquisition
of the area in which such farm is located shall apply. If such farm spans more than one area, the
highest rate of such areas shall apply. “It is stipulated that the compensation rate for state-owned
farmland is 36,800 Yuan/mu in Yaodu Town, and that for state-owned construction land and
unused land 18,400 Yuan/mu; the compensation rate for state-owned farmland is 32,780 Yuan/mu
in Dongliu Town, and that for state-owned construction land and unused land 16,390 Yuan/mu; the
compensate rate for temporary land is 1,390 Yuan/mu rent per year; Temporary land will be
restored to woodland after completion, which the charge of vegetation restoration will be paid by
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 103
property owner to provincial finance in accordance with the standard of 6yuan/m2 to be used for
vegetation restoration of temporary land..
Monitoring Group County learned from Dongzhi County Forestry Bureau that, two parties
have signed an agreement on permanent land acquisition, actual compensation amount of
permanent land acquisition in state-owned woodland is 3,509,952 yuan with compensation rate
executed in deed is 16,000 Yuan/mu as of Oct. 2014. The compensation standards for temporary
forest land acquisition is also compensated in accordance with the compensation standard for
permanent forest land requisition of 16,000 Yuan/mu, and make a clear definition in the Agreement
for temporary land acquisition that, if the forest land acquired for this project temporarily will be
used for commercial exploitation in the future, the compensation fund should make up any
difference as the compensation rate during land acquisition. The forest farm is responsible for the
cutting works of trees in woodland acquired, and the timbers owned by the forest farm. Given the
forest farm may be used for commercial development in the future, involving compensation again,
and the discrepancy of compensation amount this time have no impact on the forest farm;
meanwhile taking into account Dongzhi County Government having actual difficulties in
counterpart fund, two forest farm have agreed by Staff Meeting held (meeting documents
Attachment 6) that the compensation rates for permanent and temporary land are carried out in
accordance with the standard of 16,000 Yuan/mu, and signed Agreements of Land Acquisition of
their own accord.
Since Dongzhi government paid compensation to 2 Forest farms according to the
compensation standards lower than the compensation standards in the Resettlement Plan, External
monitoring agency disclosed this issue in previous monitoring report, which arounsed the attention
of Anhui PMO, Anhui PMO obliged Dongzhi PMO to compensate according to the compensation
standards in the Resettlement Plan, supplement the difference. On March 18, 2015, G206 Dongliu
to Yaodu Section Construction Project Coordination Office signed additional compensation
agreement with Meicheng Forestry, Jin Sishan Forestry, executive compensation standards of the
original compensation agreement were adjusted to 36800 yuan/mu. Of Dongliu Town eventual
implementation compensation standard is 36,800 yuan/mu, higher than the RAP original
compensation standards 32,780 Yuan/mu, Woodland compensation standards of Yaodu Town36800
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 104
Yuan/mu, which is the same with the RAP standards.
Through the interviews with the heads of two woodland and Dongzhi County Forestry Bureau,
Monitoring Group learned that Jinsishan and Meicheng Forest Farms are enterprise-style
management public institutions with its expenses paid by its earning and carrying out the principle
of “one-level accounting, two-levels management”; salaries for staff are paid according to the
wages standard of public institutions, which do not directly relate to the income of woodland.
Dongzhi County Forestry Bureau has a positive attitude to the issue of woodland acquired by this
project, and fully understands local government’s difficulties in counterpart funds; they will fully
cooperate with woodland acquisition works and process relevant approvals submission actively.
Jinsishan Forest Farm which has the area of 35,000mu, 128 employees and approximately
annual income of 10million yuan, its main revenue includes timbers felling, selling of seeding
cultivation as well as subsidies for national public welfare forest. Farm income is used for wages,
social insurance and routine office expenses. The woodland area of 105.319 mu in Jinsishan Forest
Farm are acquired for permanent land acquisition of this project, which land lost rate is 0.3%;
115,440 Yuan was paid in total during land acquisition, which is about one-tenth of annual income.
This compensation fund from land acquisition will be used as surplus of forest farm, not for the
purposes of payments for salaries and insurances, etc. Therefore, there is very limited impact on
forest farm’s income and living levels of staff.
Founded in 1958, Meicheng forest farm now has operating area of 26000mu, 138 employees
and annual revenues of around 9 million yuan, which main income are selling of seeding
cultivation as well as subsidies for national afforestation. The forest’s annual income essentially
keeps balance with its expenditures. The woodland area of 64.20 mu in Meicheng Forest Farm are
acquired for permanent land acquisition of this project, which land lost rate is 0.25%; 1.6 million
yuan was paid in total during land acquisition, which is about one-ninth of its annual income. This
compensation fund from land acquisition will be used uniformly, not for the purposes of payments
for salaries or welfares, etc. Salaries for staff are paid according to the wages standard of public
institutions, which do not directly relate to the income of woodland. Land acquisition has no
impact on living levels of staff in Meicheng forest farm.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 105
To sum up the above-mentioned monitoring, compensation standards for G206 permanent
acquisition of state-owned land did not meet the compensation standards in the Resettlement Plan
approved by ADB at the beginning. After disclosed by the external monitoring agency, ADB
experts put forward feedback requirement, Anhui Provincial PMO obliged Dongzhi government to
compensate relevant fees, finally the compensation standards of the project for Permanent
state-owned land acquisition meet the compensation standards in the Resettlement Plan.
4.1.1.3 Area and Compensation Standards for Temporary Land Acquisition
According to the applicable state and provincial provisions, compensation for temporary land
occupation includes compensation fees young crops and ground attachments, and land reclamation
costs. Land will be occupied by borrow areas and spoil grounds during project construction.
All land temporarily occupied (180.9mu) is state-owned land. The borrow areas are located
on state-owned hilly land, and the spoil grounds are located on state-owned wasteland, involving
no compensation. Monitoring Group learned on-site that actual project temporary land is 201.943
mu, of which the area of temporary land for borrow pits involved compensation increases 150mu,
this is the reason about an increase of about 7 million cost.
4.1.1.4 Renting of Houses and Construction Grounds for this Project
This project is divided into two sections by public bidding organized by APMO, It needs to
rent grounds of 53.55mu according to construction needs, of which 11mu for mixing plant,
approximately 2.55mu for residential area in Contract 01, as well as 40mu for residential area in
total in Contract 02.
The mixing plant located in Lishan work area belonging to Dongzhi Highway Sub-bureau is
rent by Contract 01 as their mixing plant for 2 years with annual rent of 30,000 Yuan and paid
every year. The maintenance work area in Lishan has 11mu of temporary land acquisition.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 106
Picture 4-1 Mixing plant in Lishan Work Area
Dongzhi County Fangjin Furniture Factory located nearby Erjing Highway in Zhaqiao Village
in Dongzhi County was rent by Contract 01 as residential area, with construction area of
approximately 1700m2 and rent of 25,000 yuan/month, paid monthly.
The land for the second phase (about 40mu) of Dongzhi County Domestic Sewage Treatment
Plant was rent by Contract 02 used for residential construction of project manager’s department,
with annual rent 25,000 Yuan, two years and paid in a lump sum.
Dongliu Maintenance Branch Center including office building, dormitory building and dining
hall belonged to Anjing (Anhui-Jingdezhen) Expressway is leased out to Dongzhi County Urban
Management Investment Co., Ltd. (DCUMI) by Anhui Provincial Expressway Holding Group Co.,
Ltd. (APEHG). The rental area is about 2600m2,a payment of 100,000 Yuan per month for 3 years.
On behalf of Dongzhi County Government, DCUMI is responsible for external financing and
project management, and has directly authorized the right to use the rental site to G206 Project
Management Office in Dongzhi. Mixing plant of 01 Contract is the original mixing plant of
Chizhou Highway Bureau conservation work area without hardened, the land is hardened in
Contract 01. Mixing plant of 02 Contract is the original construction site of water plant without
smooth, two sections respectively hardening the land, after the end of the project, the site can still
be used, does not require restitution.
No additional collective land or state-owned land are increased for Dongzhi PMO, residential
areas for two contractors, mixing plant, which all use existing ground. The saving of land
resources is maximized, and income of original property unit is increased. After completion of this
project, the property unit could continue to use them, and reducing the cost of the restoration for
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 107
temporary works.
4.1.1.5 Land Restoration Measures and Compensation Payment
After field investigations, Monitoring and Evaluation Goup learned that land compensation
rates are divided into three types of collective land acquisition, temporary land use as well as using
of state-owned land in accordance with the nature of highway construction land demands.
The compensation standard for collective land acquisition is decided in accordance with land
management laws and regulations including the Notice of Adjusting on Compensation Standards
for Land Acquisition issued by Anhui Provincial Government (WZ [2012] No.67) and the Notice
of Compensation Standards for Ground Attachments such as Young Crops and Housing
Expropriated in Dongzhi County Announced by Chizhou County Government “(CZ [2012] No.90).
According to the Approval of construction land use for National Road G206 Dongliu (Dongzhi) to
Yaodu Section Reconstruction Project (WZD [2012] No.1226) approved by Anhui Provincial
Government. Procedures of Land submission for approval are completed; compensations for land
acquisition are in place partly; each villager and household affected by land acquisition have
signed agreements on land acquisition and resettlement; the compensations for attachments and
young crops owned by individuals on the occupied land as well as resettlement subsidies have
been paid to individuals. Compensation is uniformly paid to town level by headquarters, then town
level will directly deposit into the accounts of individuals and village collective organization.
Compensation has been fully paid.
Regarding the resettlement subsidies for farmland acquisition, it shall be paid to land
contractor if the farmland belongs to farmers; and it shall be paid to collective economic
organization if it belongs to village collective land. Regarding the resettlement subsidies for
construction land and unused land acquisition, of which, the subsidies for unused land shall be
paid to village collective economic organization; for construction land shall be paid depending on
land use. Following the principle of “managed by village finance, deposited in special account, and
used for special purposes”, land compensations are used for public welfare and social security
within the scope of village groups affected by land acquisition.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 108
4.1.2 Compensation Standard for House Demolition
4.1.2.1 Compensation Standard for Rural Housing Demolition
The executable file of compensation standards for demolition is the Notice of Announcement
on Compensation Standards for Young Crops and Housing Attachments on Land Occupied in
Dongzhi County and Other Places issued by Chizhou Municipal Government (CZ[2012] No.90).
The Notice refines and improves the compensation standards in the RP, in favor of implementation
of compensation works smoothly, fairly and impartially. Specific criteria are detailed as follows:
(1) Compensation Standards for Main House Demolition
Type Structure COMPENSATION
STANDARDS in RAP
Compensation
Standards Executed Remarks
Main House
Frame structure 735 Yuan/m2 735 Yuan/m2
Masonry concrete
structure 645 Yuan/m2 645 Yuan/m2
Masonry timber
structure 510 Yuan/m2 510 Yuan/m2
(2) Compensation Standards for Outbuildings and structures
Type Features
COMPENSATION
STANDARDS in
RAP
Compensation
Standards
Executed
Outbuildings
Masonry concrete, the area are calculated
completely if the height of eaves are no
less than 2.2m; the area is reduced by half
if the height of eaves are less than 2.2m.
/ 260 Yuan/m2
Masonry bricks, the area is calculated
completely if the height of eaves are no
less than 2.2m; the area is reduced by half
if the height of eaves are less than 2.2m.
/ 140 Yuan/m2
Earth bricks, the area is calculated
completely if the height of eaves are no
less than 2.2m; the area is reduced by half
if the height of eaves are less than 2.2m.
/ 80 Yuan/m2
The houses have simple walls at four sides,
tile-roofed and the height of eaves is less / 60 Yuan/m2
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 109
Type Features
COMPENSATION
STANDARDS in
RAP
Compensation
Standards
Executed
than 1.5m.
Pigsty,
toilet:
Masonry bricks and cement ground Toilet: 80
Yuan/m2;
live-stock shed: 30
Yuan/m2
60 Yuan/m2
Masonry concrete and cement ground 80 Yuan/m2
Floors Cement 18 Yuan/m2 18 Yuan/m2
Masonry / 10 Yuan/m2
Walls Masonry / 26 Yuan/m2
Notes: compensation standards in the Resettlement Plan are not listed completely in this table,
actual standards are universal compensation standards for domestic fund projects, more specific
and perfect than the standards in the plan.
(3) Relocation compensation standard for attachments
Items Standard
in RAP
Executive
standards Remarks
Pot and stove
Single stove / 80 yuan/piece
Compensation based on single
stove
Twin stoves / 120 yuan/piece
Triple stoves / 140 yuan/piece
Cooking
bench board / 100 Yuan/m2
Air-conditioner
Cabinet type / 220 yuan/set
Subsidies for relocation and
installation
Split type / 180 yuan/set
Window
type / 100 yuan/set
Water heater
Solar power / 100 yuan/piece
Electrical
energy / 80 yuan/piece
Coal, gas / 80 yuan/piece
Communications Telephone / / Relocation compensation in
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 110
Items Standard
in RAP
Executive
standards Remarks
Cable
television / /
accordance with
communications department
and television station
Sanitary
equipment
Bathtub / 150 yuan/piece
Pedestal pan / 100 yuan/piece
Squatting
pan / 80 yuan/piece
Wash basin / 50 yuan/piece
Outdoor facility
Weld mesh
screen / 70 yuan/m2
Subsidies
Rolling door / 100 yuan/m2
Self-made
security door / 180 yuan/piece
Iron gate in
courtyard / 150 yuan/piece
Others
Al-alloy
doors&
windows
/ 120 yuan/m2
Subsidies
Timber
doors &
windows
/ 70 yuan/m2
PVC
DOORS &
WINDOWS
/ 140 yuan/m2
Kitchen
ventilator / 80 yuan/piece Demolished by themselves
Pool / 50 yuan/piece
Compensations
Coal pool / 50 yuan/piece
Rain shed / 50 yuan/m2
Glass fiber
reinforced
plastics
/ 80 yuan/m2
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 111
Items Standard
in RAP
Executive
standards Remarks
appentice
Notes: for other activities outside of the scope of compensation, the compensation will be
calculated as per quality.
(4) Compensation rate for interior decoration
Items Standard in
RAP
Executive
standards Remarks
Suspended
ceiling
Wallpaper
ceiling / 18 Yuan/m2
Compensation shall be not
calculated
Fiberboard,
pinch / 15 Yuan/m2
Plaster / 28 Yuan/m2
Plywood / 25 Yuan/m2
Wall
surface
Ceramic tile / 25 Yuan/m2
Wall cloth / 22 Yuan/m2
Plywood / 25 Yuan/m2
Spraying
Painting,
ceramic,
plastics
/ 12 Yuan/m2
Interior
floor
Wood floor / 60 Yuan/m2
Floor tile / 40 Yuan/m2
Terrazzo / 20 Yuan/m2
Marble / 60 Yuan/m2
Granite / 70 yuan/m2
Painted ground / 8 Yuan/m2
Others
Skirting / 10 yuan/m Compensation calculated as per
actual measurements for
undecorated suspended ceilingand
and floor tile or floor Line / 10 yuan/m
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 112
Items Standard in
RAP
Executive
standards Remarks
Door surround / 55 yuan/piece
Compensations
Window
surround / 45 yuan/piece
Screen / 50 yuan/piece
Screen window / 45 yuan/piece
(5) Compensation standards for attachments such as scattered trees, garden plant
Diameter of trees
(cm)
General tree Fruit trees
Standard in RAP Executive
standards
Standard in
RAP Executive standards
2.0~10.0 / 5yuan/tree / 8 yuan/tree
11.0~15.0 / 15 yuan/tree / 30 yuan/tree
16.0~20.0 / 20 yuan/tree / 40 yuan/tree
Above 21.0 / 35 yuan/tree / 50 yuan/tree
Grape
/ Bearing no fruit: 15
yuan/tree
/ Bearing fruit: 70
yuan/tree
Moso bamboo / 10 yuan/tree
Tea trees in tea garden / 18 yuan/tree
Notes: 1. The measurement of trunk diameter is calculated at the place of 1m from the
ground, 1 yuan will be increase for additional 1 cm if the tree is higher than 21 cm.
2, the trees transplanted and fell down are all owned by original owner.
3, 1500 yuan/mu for taking full responsibility for a large-scale woods; 500 yuan/mu for taking full
responsibility for mixed bamboo forest; 300 Yuan/mu for taking full responsibility for shrub
wood.
(6)Compensation standards for other attachments
Items Type Standard in RAP Executive standards
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 113
Items Type Standard in RAP Executive standards
Well
Tractor-ploughing well
within 5 m depth or
pressurized well 1200 yuan/well 500 Yuan/well
Deep well(above 5m) 1200 yuan/well
Pole Concrete pole(above 5m) / 150 yuan/piece
Wooden pole / 20 yuan/piece
Tombs Single coffin
1500 yuan/set 1000
Double coffin 1500
Plastic shed Steel frame / 8 Yuan/m2
Bamboo frame / 5yuan/m2
Dung depositary Outdoor / 80 yuan/piece
For better implementation of demolition work, the compensation standards for wells and
tombs of different sizes are detailed according to detailed implementation rules of the policies in
China. After investigation and detailing, the compensation standards are no lower than
replacement price of the project. All compensation standards for housing demolition are no less
than the compensation standards listed in the Resettlement Plan.
4.1.2.2 Relocation Compensation and Temporary Transition Subsidies
The compensation for relocated households involved in this project, shall be implemented in
strict accordance with the provisions of compensation standards stated in the document filed (CZ
[2012] No.90), and be paid in a lump sum in cash to the accounts provided by farmers after
agreement signed. According to on-site investigation, Monitoring Group learned that actual
situation of relocation compensation and temporary transition subsidies for affected households are
shown in the table below.
Table 4-3 Relocation Compensation and Temporary Transition Subsidies
Compensation
Items
Relocation
subsidies(yuan/household)
Compensation for
homestead
(yuan/household)
Temporary transition
subsidies (calculated as 6
months)
Scheduled 1000 4000 5 yuan/m2
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 114
Compensation
Items
Relocation
subsidies(yuan/household)
Compensation for
homestead
(yuan/household)
Temporary transition
subsidies (calculated as 6
months)
Executive
standards 1000 4000 5 yuan/m2
Others Reward 10% of housing compensation
In addition to compensation for house demolition according to the standard, each relocated
household will received transition subsidy of 5 Yuan/m2 per household per month for 6 months of
transition period; and relocation subsidy of 1000 Yuan/household, with housing plot for free to
build resettlement housing; Dongliu Town also provides 4000 Yuan to each household as
compensation for housing plot; no transition resettlement will be provided to those AHs only
affected by demolition of attached facilities, without demolition of main house. If the relocation
could be completed within specified time, affected households can be rewarded as 10% of housing
compensation amount; while all relocated households have enjoyed 10% bonus.
4.1.3 Grave relocation
Number demolition grave, affecting households and the number of statistics in the following
table:
Town Quantity
Number of households and persons Unit
Price(Yuan) Compensation(Yuan)
Household Number of
people
Yaodu 131 131 576 1000 131000
Dongliu 31 31 166 1000 31000
Subtotal 162 162 742 / 162000
4.1.4 Affected individual businesses
Monitoring Group after the investigation learned that affected individual businesses are two
households including pheasant farm and pig farm along the whole alignment, located in Xiayang
and Zhanggang Villages respectively.
(1) Pheasant farm
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 115
The villager Xu Haizhou in Bichong Group of Xiayang Village is breeding pheasant. The
relocation of pheasant farm is affected by the project, and the houses need to be demolished and
resettled. Total compensation for chicken farm is 237167 Yuan, see Table 4-4.
Table 4-4 Compensation list for relocation of pheasant farm
No. Contents Compensation(Yuan) Remarks
1 Replacement of
management houses 24000 120m2×200 Yuan/m2
2 Migration costs 7795 Calculated by county animal
husbandry bureau
3 Replacement of
pheasant farm 205372 Negotiation
4 Subtotal 237167
An Agreement on compensation for farm relocation was signed between Xu Haizhou and
Dongliu Town Government on December 12, 2013, and then the relocation and compensation
were carried out. Pheasant farm was relocated to new site, and Xiayang Village Committee in
Dongliu Town is responsible for water supply, power supply and road for pheasant farm after
relocation to meet the requirements of the farm.
Monitoring Group learned that, pheasant farm resumed the breeding works in May 2014..
Production status in the pheasant farm before and after relocation is shown in Table 4-5.
Table 4-5 Comparison of pheasant farm before and after relocation
Breeding area(mu) Annual amount of adult
pheasants(10000)
Annual amount of
eggs(10000)
Before 9 1.0 4.5
After 15 1.5 7
The situation of pheasant farm has changes a lot due to improved environment for cultivation
after relocation of pheasant farm. The main changes include: the area of cultivation has been
expanded from original9 mu to existing 15mu;, about 15,000 adult pheasants with 70000 eggs
produced annually after relocation, while there are only about 10000 adult pheasants with 45000
eggs in previous year.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 116
Picture 4-2 Management houses in pheasant farm before and after relocation
Picture 4-3 Environment improvement in pheasant farm after relocation
Xu Haizhou expanded the scale of farming with increase of egg quantity after the relocation
of pheasant farm affected by the project. Meanwhile, Xu’s family has moved to resettlement site
and their living conditions were improved. The head of this household is very satisfied with the
situation of demolition, relocation and compensation.
(2) Pig farm
An agreement on compensation for pig farm was signed between a self-employed
businessman Hu Baowei and Dongliu Town Government on December 30, 2013, totaling 151,200
yuan of compensation expense, as shown in Table 4-6.
Table 4-6 Compensation for pig farm
No. Contents Compensation Remarks
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 117
No. Contents Compensation Remarks
1 Replacement of hog
house 115200 288m2×400 yuan/m2
2 Loss of pigs 36000 120 pigs ×300 yuan/pig
Subtotal 151200
Monitoring Group learned that the original self-employed household would like to switch to
another job. Before career changes, there are about 100 giant pigs in the previous year and about
240 piglets sold out annually with normal annual value of production of 100,000 Yuan. Currently,
3 persons in this household have employed in Zhanggang Restaurant with family annual income of
120,000 Yuan. No reemployment problems for staffs are involved in the pig farm.
4.2 S319 Wuwei to wuwei-erba Project Compensation Standard and
Quantity
4.2.1 Quantity Standard of Land Acquisition
According to the final Resettlement Report, there are land acquisition of412.55mu inthis
subproject, of which, permanent collective land of 401.85mu, and state-owned land of 10.7mu.
Permanent land required by this subproject was approved by Anui Provincial Government (in the
file of WZD[2014] No.52), with land of 16.905 hectares (253.587 mu) approved.
The compensation standards of land acquisition are classified as three types: collective land,
state-owned land and temporary land in accordance with the various demands for land use of road
construction.
The compensations for attachmentson the acquiredland, crop compensation fees and
resettlement subsidies owned by individuals will be directly transferred to the account provided by
the farmers in the form of cash.The situation of social insurances for householdswith less than
0.3mu arable land per capita after land acquisition are not involved in the project land acquisition.
4.2.2 Compensation Standard for Collective Land Acquisition
Compensation standards in this subproject are carried out in accordance with the stipulations
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 118
in the Notice on Adjustment on Standards of Land Acquisition Compensations in Anhui
(WZ[2015]No.24) issued by Anhui Provincial Government. Agreements on compensations of land
acquisition are negotiated among town government, villager committee and affected villagers,
please see compensation standards for collective land in Table 4-7:
Table 4-7 Compensation Standards for Collective Land Acquisition in this Project
Unit: Yuan/mu
No. Area Town
Farmland Construction Land and
Unutilized Land
Standard in
RAP
Executive
standards
Standard in
RAP
Executive
standards
1 Wuwei
County
Fudu Town,
Dougou Town 33000 38280 16500 19140
2 Wucheng Town 35420 40260 17710 20130
In addition, compensation standardfor young cropsis 800 yuan/mu.
With respect to the compensation agreement for land acquisition and resettlement of the AH,
Zhang Yifan, see Attachment 33.
To sum up the above-mentioned monitoring, compensation standards of collective land
permanently acquired for the project are higher than the compensation standards in the
resettlement plan.
4.2.2.1 Compensation Standard for State Owned Land Acquisition
The houses to be demolished shall be compensated according to the compensation standard
for houses, and the land area to be expropriated shall be compensated according to the
compensation standard for construction land.
4.2.2.2 Compensation Standards for Temporary Land Acquisition
According to the notice on Strengthening the Management of Temporary Land Use (wtzz
[2010] No. 119) issued by the Land and Resources Department of Anhui Province, the
compensation standard for temporary land use shall refer to the unified annual output value of the
land expropriated or the compensation standard for young crops to compensate the farmers or
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 119
affected villages. In this project, the compensation for temporary land occupation is based on the
unified annual output value standard, i.e. Fudu town is 1500 yuan / mu / year. The temporary land
occupation period of the project is 2 years.
After the expiration of the temporary land occupation period of the project, Wuwei County
Transportation Bureau and the project contractor are responsible for the restoration of the land, and
the restoration cost is included in the general budget of the project.
For land reclamation agreement and temporary land use permit, see Annex 3
4.2.2.3 Renting of Houses and Construction Grounds
Construction of S319 project is divided into three contracts. All contracts need rent land used
for precast yard, mixing plant and construction site of project management department. In line
with the principle of land conservation and contributing to the development of local economy,
shutdown or abandoned factories are rent as precast yard and construction site of project
management department required in these three contracts. On the one hand, land resources and
cost of project land construction are saved; on the other hand, shutdown enterprises and
personnel’s incomes have been increased, which are benefit for the production and development of
the enterprises in the future. S319 project involves 30 mu land within the factory, office building
and civil housing of 2680 ㎡ in total, with a rent of 40,560 yuan/year. The rent will be paid once
per year in the form of cash or paying to account. For example, it is stipulated in the clause of “4.3
payment method” of Lease Contract for Project Residence Area in Contract NO1-1 that: the rent
shall be paid to the Party A (Wang Yalin) by the Party B (Project Management Department of
Contract NO1-1) before 30 working days prior to the expiration of each rent period.
4.2.2.4 Land Restoration Measures and Compensation Payment
After field investigations, Monitoring and Evaluation Goup learned that land compensation
rates are divided into three types of collective land acquisition, temporary land use as well as using
of state-owned land in accordance with the nature of highway construction land demands. The
compensation standard for collective land acquisition is decided in accordance with land
management laws and regulations including the Notice of Adjusting on Compensation Standards
for Land Acquisition issued by Anhui Provincial Government (WZ [2015] No.24), the standards
specified in the document WZM [2012] No.254 issued by Wuhu Municipal Government and a
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 120
delivery report (MECG [2014] No.35) issued by the Office of Wuhu Municipal Government, in
accordance with the official reply of Anhui provincial government (WZD [2014] No.52).
Procedures of Land submission for approval of S319 project are completed; compensations for
land acquisition are in place partly; each villager and household affected by land acquisition have
signed agreements on land acquisition and resettlement; the compensations for attachments and
young crops owned by individuals on the occupied land as well as resettlement subsidies have
been paid to individuals.
4.2.3 Compensation Standard for House Demolition
4.2.3.1 Compensation Standard for RuralHousing Demolition
The relocation of S319 project and the resettlement of small and medium-sized enterprises
comprehensive industrial park in Wuwei County are both in the Chengdong new area of Wuwei
County. Wuwei County has established the Chengdong new area headquarters to be responsible for
the resettlement work in this area. The compensation standard for rural housing shall be
implemented together with the compensation and resettlement plan for collective land and housing
in Wuwei Chengdong new area from 2014 to 2015 issued by the headquarters of Chengdong new
district of Wuwei County on December 1, 2014. The compensation scheme can be divided into
property right exchange and currency compensation, which can be selected by the expropriated: if
the property right is exchanged, it shall be implemented according to the principle of "one levy and
one compensation"; if currency compensation is selected, it shall be 35 m2 per capita For the
boundary, the replacement price of the house plus the market evaluation price (higher than the
replacement price of the house) shall be implemented. Its implementation is as follows:
Table 4-8 compensation standards for demolition of residential buildings and ancillary
facilities
Unit:yuan/㎡
Impact
types type unit RAP standards Executive Standards
Housing
compensaframe ㎡ / 1380
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 121
Impact
types type unit RAP standards Executive Standards
tion Brick and
concrete ㎡ 1180 1180
Brick and
tile ㎡ 930 930
Civil
Engineeri
ng
㎡ 380 380
Other
compensa
tion
Relocation
subsidy
yuan/h
u 200
For monetary
compensation, the legal
construction area of the
house to be expropriated
is 4 yuan / m2 once; for
property right control, the
subsidy is twice according
to the above standard.
Temporar
y
resettleme
nt subsidy
yuan/
㎡.mo
nth
According to the legal building
area of the house area, the
temporary resettlement subsidy
is 2.5 yuan / m2. Month for
every 50 M2 (including 50 m2)
of legal building area, and 2 yuan
/ m2. Month for the part
exceeding 50 m2. If the property
right is exchanged, the temporary
resettlement subsidy for one year
shall be paid in advance to the
expropriated household for one
year. Until 4 months after the
resettlement and the transition
period is more than 18 months,
the temporary resettlement
subsidy fee and the second
relocation fee shall be paid
according to the double standard.
One time relocation fee and
4-month temporary resettlement
subsidy are paid for monetary
compensation.
For monetary
compensation (including
existing house
resettlement), the
temporary resettlement
fee for 4 months shall be
subsidized at the rate of 4
yuan / m2 per month; for
the option of property
right exchange, the
subsidy shall be 4 yuan /
m2 per month within 18
months and temporarily
paid for one year; from 18
months to 24 months, it
shall be 6 yuan / m2 per
month, and for more than
24 months, it shall be 8
yuan / m2 per month from
the date of exceeding the
month until four months
after resettlement.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 122
4.2.3.2 relocation compensation and temporary transition subsidy
In order to encourage the expropriated to move actively, s319 did not set up incentive
measures for the PMO. The expropriated households who completed the relocation within the
specified time and signed the housing expropriation compensation and resettlement agreement will
be rewarded in terms of resettlement area and relocation time. For example, for the resettlement
area award, on the basis of "one demolition and one compensation", it is allowed to purchase 45
square meters per capita at the cost price; if currency compensation is selected, the compensation
standard will be appropriately increased to the market evaluation price; for the resettlement time
award, 100, 150, 200 yuan / m2 will be given to the expropriated households who move within the
specified time limit, sign the expropriation compensation agreement and hand over the house for
demolition.
The external monitoring team understands that the compensation standards for demolished
houses are not lower than the compensation standards in the final report of the resettlement plan.
Housing demolition and resettlement standards
The project involves the demolition of rural residential houses on collective land, with an area
of 8733.8 m2, affecting 63 households and 240 people. The affected areas are Fudu community of
Fudu town and Hualong community of Dougou town. There are some problems in the demolished
rural houses, such as imperfect indoor supporting facilities, obsolete structure and poor lighting
and ventilation conditions, and the supporting conditions around the residential areas are also poor.
The relocation and resettlement activities of the project will provide opportunities for the relocated
households to improve their living conditions and environment. According to the investigation,
after fully soliciting the wishes of the land expropriated farmers, no resettlement plan has been
provided for the county project office and the project implementation organization, including
property right exchange and currency compensation:
Property right exchange
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 123
Property rights exchange standard and price difference settlement
The resettlement site of the project is located in the resettlement site of Chengdong new
district, crossing Changba and Xuqiao villages of Fudu community in Fudu town. The resettlement
community covers an area of 108 mu, with a total construction area of about 180000 m2, of which
the construction area of phase I project is about 100000 m2. The land acquisition for the
resettlement project of Chengdong new area was completed in December 2012. The resettlement
project only involves collective land acquisition, not housing demolition. The construction of
resettlement community began in July 2013, with 1900 houses planned to be built for resettlement.
The house type design of the resettlement site includes: type A (about 135 ㎡); type B (about 110
㎡); type C (about 90 ㎡); type D (about 70 ㎡); type E (about 48 ㎡).
Figure 4-4 Resettlement site in Chengdong new district of Wuwei County (phase I)
Figure 4-5 Effect drawing of centralized resettlement point
Monetary compensation
The housing area within 35 ㎡ per capita shall be settled according to the market evaluation
price (the estimated market price is 1800 yuan / ㎡), and the houses exceeding 35 ㎡ per capita
shall be settled according to the house replacement price. The replacement price standard is 1300 /
㎡ for frame, 1180 yuan / ㎡ for brick concrete, 930 yuan / ㎡ for brick and tile, and 380 yuan /
㎡ for civil engineering.
4.2.4 Affected Individual Businesses
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 124
According to the investigation team, there are no individual businesses affected by s319
project.
4.3 S367 Compensation Standard for Ma'anshan North Passage Project
4.3.1 Compensation Standard for Land Acquisition
4.3.1.1 Compensation Standard for Collective Land Acquisition
According to the spirit of land management law of the people's Republic of China, guiding
opinions on improving land acquisition compensation and resettlement system, land management
law of the people's Republic of China implemented by Anhui Province, and notice of the people's
Government of Anhui Province on adjusting land acquisition compensation standard of Anhui
Province (WZ [2012] No. 67), the project and Shiyang Town, Shanhou town and Zhaoguan of
Hanshan County . The compensation standards for land acquisition of towns and xianzhuzhen are
the same, see table 4-9 and table 4-10 for details.
Table 4-9 multiple and standard of compensation for collective land acquisition of the project
(resettlement plan)
N
o.
Distric
t Area
Unifie
d
annua
l
output
value
standa
rd
(yuan
/ mu)
Agricultural land Construction land and unused land
Land
compensat
ion
multiple
Multiple
of
resettleme
nt
compensat
ion
Compensat
ion
standard
for land
acquisition
(yuan /
mu)
Land
compensat
ion
multiple
Multiple
of
resettleme
nt
compensat
ion
Compensat
ion
standard
for land
acquisition
(yuan /
mu)
1
Hexia
n
county
Shiyan
g
town、
Shanho
u town
1565 7 14 32865 5 5.5 16433
2 Hansh
an
Shaogu
an 1566 7 14 32886 5 5.5 16443
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 125
county town、
Xianzo
ng
town
Table 4-10 multiple and standard of compensation for collective land acquisition of the project (actual
implementation standard)
No. District Area
Unified annual
output value
standard (yuan
/ mu)
Agricultural land
Construction
land and unused
land
Land
compensation
multiple
Multiple of
resettlement
compensation
1 Hexian
county
Shiyang
town、
Shanhou
town
1800 7 14 37800 5 5.5 18900
2 Hanshan
county
Shaoguan
town、
Xianzong
town
1780 7 15 39160 5 6 19580
4.3.1.2 compensation standard for temporary land occupation
According to the impact analysis of the project, the impact of temporary land occupation of
the project is all unused land, and the compensation standard is 1500 yuan / mu / year. According
to the construction design, the temporary occupation period of the project is 2 years. See table 4.11
for compensation standard of temporary land occupation.
Table 4-11 compensation standard for temporary land occupation
Type Unit Hexian
county
Hanshan
county Remarks
Land for borrow piand spoil yuan/mu.year 1500 1500 Calculated by 2
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 126
years
General temporary land
occupation yuan/mu.year 1500 1500
Calculated by 2
years
4.3.2 Compensation standard for rural housing demolition
The compensation standard for the demolition of rural residential houses of the project is
determined according to the replacement price of the demolished houses. See Annex 34 for the
calculation of relocation and replacement price of rural housing in Hexian county and Hanshan
county. See table 4-12 and table 4-13 for the compensation standard of rural housing demolition in
this project. The resettled homestead will be obtained before the demolition, and the site selection
of homestead will be determined by the villagers and the affected immigrants. After the project
affected farmers get compensation, they can fully use the compensation money to build new
houses. The three connections and one leveling of the homestead will be carried out by the
construction company, and the cost will be included in the project budget by.
Table 4-12 compensation standard for demolition of rural housing and auxiliary facilities in
Hexian County
Type Structure
type Unit
Price (yuan )
Remarks RAP
compensation
standard
Actual
implemented
standard
House
compensation
Framework ㎡ 1220 1342
Masonry
timber
structure
㎡ 965 1062
Masonry tile ㎡ 765 842
Earth-timber ㎡ 305 336
Other
compensation
Moving
subsidy hu 500 500-1000 One off subsidy
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 127
Type Structure
type Unit
Price (yuan )
Remarks RAP
compensation
standard
Actual
implemented
standard
Transition
subsidy ㎡·month 6 6
According to the
actual transition time,
generally no more
than 18 months, 8
yuan / m2 / month
compensation
standard will be paid
for more than 18
months
Temporary resettlement transition fee shall be paid at 6 yuan per square meter per month
(calculated from the date of relocation). The temporary resettlement transition fee of 6 months
shall be paid in one time to the person who chooses monetary compensation and the person who
chooses homestead resettlement; the temporary resettlement transition fee of the person who
chooses property right exchange shall be paid to 4 months after the house is delivered. The person
to be expropriated shall complete the relocation within the relocation period stipulated in the
expropriation compensation agreement or determined by the expropriation compensation decision.
The resettlement transition will be solved by itself.
Payment method of compensation and resettlement. If the expropriated person chooses the
method of homestead resettlement or monetary compensation, the two sides of the expropriation
shall reach a consensus through consultation and conclude the agreement of house expropriation
and resettlement and the agreement of land expropriation, and the expropriated person shall
complete the house relocation and deliver the house to be demolished, the expropriated person
shall pay the compensation and resettlement money in one time. If the expropriated person chooses
to change the property right, the account shall be calculated according to each other and the
original price difference shall be found between each other Then, the relocation compensation and
resettlement fee will be directly converted into the purchase price, and the difference will be
settled according to the prices of different types of resettlement houses selected by the
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 128
expropriated. If the compensation is greater than the purchase price, the surplus part shall be
immediately paid to the person to be expropriated after all the relocated households have
completed the relocation and the house has been completely delivered and demolished; if the
compensation is less than the purchase price, the difference part shall be settled and settled by the
person to be expropriated once the resettlement house is selected.
Table 4-13 compensation standard for demolition of rural residential houses and auxiliary
facilities in Hanshan County
Type Structure
type Unit
Price (yuan )
Remarks RAP
compensation
standard
Actual
implemented
standard
House
compensation
Framewor
k ㎡ 1400 2160
Masonry
timber
structure ㎡ 1075 1530
Masonry
tile ㎡ 885 1400
Earth-tim
ber ㎡ 380 600
Other
compensation
Moving
subsidy hu 6 6
Transition
subsidy ㎡·
month 4 4
According to the actual transition
time, generally no more than 18 months, 8
yuan / m2 / month compensation standard
will be paid for more than 18 months
Relocation compensation standard:
(1) If monetary compensation is selected, the relocation compensation shall be paid
according to the standard of 6 yuan / m2 of the main building area of the house to be demolished;
(2) If the homestead is selected for resettlement, two relocation compensation shall be paid
according to the standard of 6 yuan / m2 of the main building area of the house to be demolished
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 129
(3) If the area of the house to be expropriated is less than 50 square meters, it shall be
calculated as 50 square meters
Compensation standard for temporary resettlement:
(1) If monetary compensation is selected, temporary resettlement compensation for six
months shall be paid at one time according to the standard of 4 yuan / m2 per month for the main
building area of the house to be demolished.
(2)If the homestead is selected for resettlement, temporary resettlement compensation shall
be paid according to the standard of 4 yuan / m2 per month for the main building area of the house
to be expropriated, and the actual number of transitional months shall not exceed 18 months; if the
homestead cannot be obtained in time, it shall be taken as the main building area of the house to be
demolished after the overdue period
Standard resettlement compensation of 8 yuan / m2 per month for the building area of the
house
(3) The number of months of actual transition refers to the number of months of actual
temporary transition from the date when the relocated households have moved to the date when the
houses have been built and capped.
4.3.3 Compensation for Accessories and Infrastructure
According to the principle of replacement price, determine the compensation standard for the
affected accessories and infrastructure of the city and county within the scope of the project. See
table 4-14 for details.
Table 4-14 compensation standards for accessories and infrastructure
Accessories Unit RAPstandard
(yuan/unit) Hexian county Hanshan county
Pole
Cement Stick 200 200 300
Wood Stick 60 60 100
Tomb tomb 600 600(mud single)1100(mud double) 600(mud)/800(cement)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 130
Accessories Unit RAPstandard
(yuan/unit) Hexian county Hanshan county
1200(brick single)2400(brick double)
Public restroom 160 60-80/m2 200
Vegetable shed ㎡ 12 8000-10000/mu 12
Motor-pumped well eye 2500 2500 2500
Enclosing wall m 60 60 60(stone)/80(brick)
Pigsty ge 600 60/80/m2 300/m2
Tree ke 15 18-84 20/40/50
Fruit tree ke 20 37-130 20/50
4.3.4 Other cost standards
See table 4-15 for other expense standards.
Table 4-15 resettlement tax standard of the project
No. Tax name Standard
1 New construction land use fee 10000Yuan/mu(15yuan/㎡)
2 Cultivated land reclamation fee 30000yuan/mu
3 Land occupation tax 1333.34yuan/mu(yuan 元/㎡)
4 Land acquisition management fee 850yuan/mu
5 Water conservancy fund 500yuan/mu
6 Survey and design cost 1% of basic cost
7 External monitoring and evaluation fee 1% of basic cost
8 Technical training cost 0.5% of basic cost
9 Administrative expenses 2% of basic cost
10 Unforeseen expenses 10% of basic cost
4.3.5 Vulnerable Groups
In addition to the aforementioned land acquisition compensation policies, vulnerable groups
affected by the project can also enjoy other preferential policies:
(1) Provide vocational training for the labor force in the vulnerable groups' families, and
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 131
provide various employment information and guidance to increase employment opportunities;
(2) In the process of project construction, priority should be given to recruiting the labor force
of vulnerable groups to do some non-technical work;
(3) Cooperate with the social labor and social security departments of counties and cities to
set up a special support fund to provide assistance, which will be paid from the resettlement
management fees.
4.3.6 Women's Support Measures
In addition to the policy of land acquisition compensation, women also enjoy special support
policies
(1) Priority is given to employment opportunities, and 30% of women have access to
non-technical employment opportunities.
(2) Priority will be given to agricultural and non-agricultural technical training. 12000 people
will receive agricultural and non-agricultural technical training in this project, including at least
6000 women (50%)
(3) Affected women have access to relevant information during the resettlement process and
can participate in fair consultation and resettlement.
(4) During the implementation of resettlement, a special women's forum was held to
introduce relevant policies of resettlement, so as to improve women's awareness.
(5) The compensation agreement must be signed by both husband and wife.
4.4 Compensation Standard for G318 and S320 Yimu Highway Project
4.4.1 Compensation Standards of Land Acquisition
4.4.1.1 Compensation Standard for Collective Land Acquisition
Nanling County Project Office announced and publicized the land acquisition scheme at early
stage of land acquisition.In the Project Resettlement Plan, compensation standards for permanent
acquisition of collective land should execute WZ (2012) No.67 document, actually executed
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 132
compensation standards also follow WZ (2012) No.67 document, compensations are paid to the
households affected by land acquisition according to the standards in the table below, the rest
money is used for public welfare of village collective and social security for landless
peasants.With respect to the compensation standards for permanent acquisition of collective land,
see the table below.
Table 4-16 Compensation Standards for Collective Landland Acquisition
Unit:Yuan/mu
Region
Farmland Construction land and unused land
Planned
compen
sation
standar
ds
Actual compensation
standards
Pl
anned
compe
nsatio
n
standa
rds
Actual compensation standards
Distribu
tion to
househo
lds
Land lost farmers
fund and village
collective land
social welfare
total
Distrib
ution
to
househ
olds
Land lost farmers
fund and village
collective land social
welfare
total
Jishan
Town 36300 32800 3500 36300 18150 15675 2475 18150
Gongsha
n Town 32130 28917 3213 32130 16065 13770 2295 16065
Take an example of Jishan Town, compensation methods for collective land acquisition are as
follows:
Agricultural land:land compensation 11550 Yuan/mu(30% of the land compensation fund is
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 133
used to pay for the land lost farmers' fund and the social welfare of rural collective land, and 70%
is paid directly to the households affected by land acquisition), resettlement subsidies 24750
Yuan/mu are paid to bank cards of the households affected by land acquisition directly.Total land
compensation and resettlement subsidies are 36300 Yuan/mu, the amount paid to the households
affected by land acquisition is 8085+24750=32800 Yuan/mu, the rest payment is used for public
welfare of village collective and pension insurance of landless peasants affected by land
acquisition.
Construction land and unused land:land compensation 8250 Yuan/mu(of which 30% is used
unified for security fund of landless peasants, i.e.2475 Yuan, 70% is paid to the units or individuals
affected by land acquisition, i.e.5775 Yuan), resettlement subsidies 9900 Yuan/mu.Total land
compensation and resettlement subsidies are 18150 Yuan/mu, payment to the households affected
by land acquisition is 5775+9900=15675 Yuan/mu, which is paid directly to the units or
individuals affected by land acquisition via bank card.
In the Resettlement Plan, compensation standard for young crops in the acquired cultivated
area follows unified annual production value standard, i.e.1650 Yuan/mu in Jishan Town, 1530
Yuan/mu in Gongshan Town.According to the monitoring, crops on the cultivated area are
basically mulberry and green seedlings etc, compensations are given to the attachments in actual
compensation process, hardly involving any category of common young crops. Compensation
standards for attachments meet the compensation standards in the Resettlement Plan.
It may be seen from the above-mentioned monitoring result that:compensation standards for
permanent land acquisition of Nanling County Yimu Highway meets ADB standards in the
Resettlement Plan.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 134
Picture 4-6 Announcement On Land Acquisition Program in Jishan Town
4.4.1.2 Compensation Standards and Quantity of Temporary land
According to the Notice of Anhui Provincial Office of Land and Resources Concerning the
Enhanced Temporary Land Management (WGTZ (2010) No.119), compensation for temporary
land should take reference to unified annual value of production or young crops compensation
standard for local land acquisition to the households or affected village groups, compensation for
temporary land occupation should comply with unified annual production value standard, i.e.1650
Yuan/mu. Year in Jishan Town, 1530 Yuan/mu. Year in Gongshan Town. Temporary land
occupation period in this project is 2 years. During actual implementation, temporary land
compensation standard in both Jishan Town and Gongshan Town is 2000 Yuan/mu. After
temporary land occupation period for this project expires, Nanling County Department of
Transport and project contractor are responsible for land restoration, restoration costs are included
in general estimate of the project.
It may be seen from the monitoring that: temporary land compensation standards for the
project are higher than the resettlement scheduled, and in compliance with relevant domestic
policies, benefits of the affected households are guaranteed.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 135
4.4.1.3 Renting of Office Grounds for This Project
Nanling Yimu Highway Construction Project is divided into two contract sections, office of
Contract 01 rents the whole fourth floor, dormitory on the fifth floor and kitchen and dining room
on the first floor of the office building of Anhui Mingtai Glass Technology Co., Ltd. , contract has
been signed, tenancy is 3 years, rent is 200,000 RMB per year, rent of every year should be paid
before Aug. 20 in advance. Contract 02 rents about 25 mu land of Anhui Nantian Building
Material Technology Co., Ltd. , as well as the office on the third floor as PMO command land,
tenancy is 2 years, 200,000 RMB per year. For rental agreement, see the Attachment27、28.
Picture 4-7 Site of Contract 01 Project Management Department
Picture 4-8 Site of Contract 02 Project Management Department
Picture 4-9 the Site Leased for Contract 02 Project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 136
It may be seen from the monitoring that: temporary land of PMO for this project does not use
new land, but utilizes the houses and land of plant buildings, which increases the income of local
enterprises. And after the construction is completed, the hardened land may be reused by the
factories, which may reduce expenditure of the enterprises.
4.4.2 Compensation Standard for House Demolition
In Nanling County, demolition should be completed for 22 households in Gongshan Town,
and should be completed for 23 households in Jishan Town. Demolition was completed for 21
households in Gongshan Town, the remaining 1 household signed agreement for demolition and
resettlement, yet demolition was not performed, 6 households signed agreement for demolition and
resettlement in Jishan Town, of which demolition was completed for 1 household, demolition of
the rest households will be performed according to the project progress
Compensation standards for house demolition in Gongshan Town follow GZ (2014)No.56
document, compensation standards in Jishan Town follow NZ (2013) No.72 document, as shown
in the table below.
Table 4-17 Compensation Standards for Houses
Structure type Unit Jishan Town Gongshan Town
Planned Actual Planned Actual
Masonry concrete
structure Yuan/㎡
Masonry
concrete
structur of
three-story
and above
three-story
e:920,
Five-story
and above
960
Masonry
concrete
structur of
three-story
and above
three-story
e:920 Yuan/㎡,
Masonry
concrete
structur of
three-story
and above
three-story
e:920,
Masonry
concrete
structure
below
three-story:88
0
Three-story
and
four-story:92
0 Masonry
concrete
structure
below
three-story:88
0
Masonry
concrete
structure
below
three-story:88
0 Yuan/㎡
One-story
and
two-story:88
0
Masonry timber Yuan/㎡ Masonry Two-story 700 700
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 137
Structure type Unit Jishan Town Gongshan Town
Planned Actual Planned Actual
timber of
two-story and
above
two-story:860
and above
860
One-story
masonry
timber:840
One-story:84
0
Makeshift Yuan/㎡ 180
Class 1 200
180
180 for
below
2.2m;200 for
above 2.2m Class 2 180
Movin
g
subsid
y
Residential Yuan/household·tim
es 250 500 250 500
Non-residenti
al Yuan/㎡ 8 8 8 8
Transition subsidy Yuan/
㎡·month 3 5 3 3
Relocation incentive
fees
(move out within 10
days)
Yuan/㎡ / / / 20
Relocation incentive
fees
(move out within 20
days)
/ 100 / /
Relocation incentive
fees
(move out within 40
days)
/ 50 / /
Cash compensation for resettlement will be given to the property owner according to the
replacement price of the houses;Compensation for homestead will follow compensation standards
for construction land in the Notice of the Anhui Provincial Government on Adjusting
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 138
Compensation Rates for Land Acquisition of Anhui Province (WZ [2012] No.67).
Property swap in Gongshan Town will adopt “unified construction and repurchase” mode, the
affected towns should construct resettlement communies, the AHs will repurchase the resettlement
house after compensation for demolition is settled according to the replacement price, resettlement
standards are as follows:
1)if original per capita residential area of the APs is less than or equal to 30 ㎡, resettlement
according to per capita 30 ㎡;
2)if original per capita residential area of the APs is larger than 30 ㎡ yet less than 45 ㎡,
resettlement according to the effectgive area of the APs house.
3)if original per capita residential area of the APs is larger than 45 ㎡, resettlement according
to per capita 45 ㎡ in principle.
If original residential area of the APs is small, resettlement area is inconvenient for residence
after convertion, resettlement area needs to be added, the AHs should submit application to the
town government for approval, then each AH may add resettlement area of 10 ㎡ according to the
preferential price determined by the government (1.4 times of the average price of the resettlement
sites), if area of the demolished house exceeds the area of the resettlement house, the excessive
part will be compensated through market assessment.
It may be seen from the monitoring that:Gongshan Townadopts property swapmode for
demolition, the rights and interests of households of the AHs are guaranteed.
Picture 4-10 Gongshan Town Compensation Standard for House Demolition announcement
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 139
Picture 4-11 Announcement On the Resettlement Scheme of Jishan Town
4.4.3 Compensation Rates for Main Attachments and Infrastructure
For the Compensation Standards Executed for main attachments and infrastructure in the
project and the compensation standards in the Resettlement Plan, see the table below,
Compensation standards for other attachmentss in house demolition, see the Attachment.
Table 4-18 Comparison Table of Compensation Rates for Main Attachments and Infrastructure
Types of Impact Planned compensation standards Actual compensation
standards
Walls (m2) Masonry (dry): 20 Yuan/m2, Masonry
(mortar): 30 Yuan/m2 The same as the plan
Fencing (m) Earth, fence: 15 Yuan/m2 The same as the plan
Floors (m2) Cement floors 25 Yuan/m2 Cement floors 25 Yuan/m2;
Masonry floors 15 Yuan/m2
Tombs (piece)
Earth grave: 200 Yuan/grave (one-grave
one-coffin); 300 Yuan/grave (one-grave
two-coffin or above two coffins)
Cement structure grave: 300 Yuan/grave
(one-grave one-coffin); 400 Yuan/grave
(one-grave two-coffin or above two coffins)
Earth grave: 400 Yuan/grave
(one-grave one-coffin); 500
Yuan/grave (one-grave
two-coffin or above two
coffins)
Cement structure grave: 500
Yuan/grave (one-grave
one-coffin); 600 Yuan/grave
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 140
Types of Impact Planned compensation standards Actual compensation
standards
(one-grave two-coffin or
above two coffins)
Well (piece) 150 Yuan/well Pressure well 150 Yuan/well
Deep well 1000 Yuan/well
Trees (tree)
General trees: circumference below 10 cm:
10 Yuan/tree; 11-20 cm: 30 Yuan/tree; 21-30
cm: 50 Yuan/tree; 31-40 cm: 60 Yuan/tree;
41-50 cm: 70 Yuan/tree; 51-60 cm: 80
Yuan/tree; 61-70 cm: 90 Yuan/tree; above 71
cm: 100 Yuan/tree.
Fruit trees: circumference below 10 cm: 50
Yuan/tree; 11-20 cm: 100 Yuan/tree; 21-30
cm: 250 Yuan/tree; 31-40 cm: 350 Yuan/tree;
41-50 cm: 450 Yuan/tree; above 51 cm: 500
Yuan/tree.
The same as the plan
Pole (piece)
According to the signed agreement, property
units should be responsible for their
relocation during construction, will not be
compensated
The same as the plan
Electric wires (m)
According to the signed agreement, property
units should be responsible for their
relocation during construction, will not be
compensated
The same as the plan
Road lamp (piece)
According to the signed agreement, property
units should be responsible for their
relocation during construction, will not be
compensated
The same as the plan
Transformer (unit) Relocation subsidies: 6000 Yuan/unit. The same as the plan
Cross-connecting
boxes (piece)
According to the signed agreement, property
units should be responsible for their
relocation during construction, will not be
compensated
The same as the plan
Compensation standards for attachments meet the compensation standards in the
Resettlement Plan.
4.4.4 Affected Individual Businesses
The affected individual industrial and commercial households involved in the Yimu highway
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 141
project in Nanling County are mainly concentrated in Jishan town. While the houses are
demolished and resettled, compensation is given to the operating area. See the table below for the
specific compensation standards.
Table 4-19 list of affected individual businesses
NO. Individial business
householder
Area
(㎡)
Compensation standard
(yuan/㎡)
Compensation amount
(yuan)
1 Yuan yuxia 57.45 600 34470
2 Wang jianhui 62.11 600 37266
3 Wang yifa 62.11 600 37266
4 Zheng aiying 63.00 600 37800
5 He hongxiang 63.36 600 38016
6 Fan chunyin 55.08 600 33048
7 Hu shiwen 63.00 600 37800
8 Huang jinlin 94.20 600 56520
9 Yi changshou 82.93 600 49758
10 Zhangshun 66.98 300 20094
Total 670.22 382038
4.4.5 Other Cost Standards
See 4-20 for Other Expense Standards.
Table 4-20 resettlement tax standard of the project
Table 4-20 resettlement tax standard of the project
NO. Item Charging
standard Basis Accept objects
1 Land occupation
tax
17500yuan/mu
(26.25yuan/
㎡)
WZC [2008] No. 367
Collection by
Land and
Resources Bureau
2 Cultivated land
reclamation fee 8yuan/㎡ Wcz [2001] No. 1061
Land and
Resources Bureau
3 Land acquisition 2.8% of the total WJF [2002] No. 47 Land and
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 142
NO. Item Charging
standard Basis Accept objects
management fee basic cost Resources Bureau
4
New
construction land
use fee 16yuan/㎡
Ministry of Finance, Ministry of
Land and Resources, people's
Bank of China
Notice on adjusting the policy of
paid use fee of new construction
land (CZ [2006] No. 48)
Land and
Resources Bureau
5 Survey and
design cost
3% of the total
basic cost
Design
Department
6 Administrative
expenses
5% of the total
basic cost
Resettlement
implementation
agency
7 Technical
training cost
3% of the total
basic cost
8
External
monitoring and
evaluation fee
2% of the total
basic cost
9
Internal
monitoring and
evaluation fee
0.5% of the total
basic cost
10
Water
conservancy
fund
500yuan/mu
Notice of the people's
Government of Anhui Province
on printing and distributing the
administrative measures for
raising and using local water
conservancy construction funds
of Anhui Province (WZ [2012]
No. 54)
11 Unforeseen
expenses
0% of the basic
resettlement
cost
4.4.6 Vulnerable Groups
In addition to the aforementioned land acquisition compensation policies, vulnerable groups
affected by the project can also enjoy other preferential policies:
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 143
(1) Provide vocational training for the labor force in the vulnerable groups' families, and
provide various employment information and guidance to increase employment opportunities;
(2) In the process of project construction, priority should be given to recruiting the labor force
of vulnerable groups to do some non-technical work;
(3) Cooperate with the social labor and social security departments of counties and cities to
set up a special support fund to provide assistance, which will be paid from the resettlement
management fees.
4.4.7 Women Support Measures
In addition to the policy of land acquisition compensation, women also enjoy special support
policies.
(1) Priority is given to employment opportunities, and 30% of women have access to
non-technical employment opportunities.
(2) Priority will be given to agricultural and non-agricultural technical training. 12000 people
will receive agricultural and non-agricultural technical training in this project, including at least
6000 women (50%)
(3) Affected women have access to relevant information during the resettlement process and
can participate in fair consultation and resettlement.
(4) During the implementation of resettlement, a special women's forum was held to
introduce relevant policies of resettlement, so as to improve women's awareness.
(5) The compensation agreement must be signed by both husband and wife.
4.5 Compensation Standards for Shuiyang River Integrated Transport
Construction Project
4.5.1 Land Compensation Standards
4.5.1.1 Collective Land Compensation Standards
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 144
Actual amounts for Shuiyang River Integrated Transport Project comply with the Notice of
the Anhui Provincial Government on Adjusting Compensation Rates for Land Acquisition of
Anhui Province (WZ [2015] No.24). Actual amount standards are higher than the compensation
standards in the Resettlement Plan. For the Resettlement Plan and Actual Compensation Standards
Executed, see the table below.
Table 4-21 Compensation Standards of Collective Land Acquisition for the Project
Unit: Yuan/mu
Region
Unified
annual
production
value standard
Farmland Construction Land and Unutilized Land
Compensation
standards for land
acquisition in the
Resettlement Plan
Actual
Compensation
Standards
Executed
Compensation
standards for land
acquisition in the
Resettlement Plan
Actual
Compensation
Standards
Executed
Shuiyang
Town 1610 37030 42320 18515 21160
Yangxian
Township,
Liqiao Town
1550 34100 39820 17050 19910
Compensation Standards Executed for permanent land acquisition of Shuiyang River
Integrated Transport Project are higher than the compensation standards in the Resettlement Plan.
With respect to young crop compensation standard for the cultivated area acquired, see Table
4-12.
Table 1-6 Young Crop Compensation Standards for Collective Land Acquired
Unit: Yuan/mu
Lands Paddy field Dry land
Compensation standards in the Resettlement Plan 900 800
Actual standards 1000 800
Actual Compensation Standards Executed for young crop involved with Shuiyang River
Integrated Transport Project are no lower than the compensation standards in the Resettlement
Plan.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 145
4.5.1.2 Compensation Standard for Permanent Occupation of State Owned Land
The permanently occupied state-owned land of the project includes state-owned agricultural
land, construction land and unused land. The compensation for expropriation of state-owned forest
land of the project shall be implemented in accordance with the notice of the people's Government
of Anhui Province on adjusting the compensation standard for expropriation of land in Anhui
Province (WZ [2012] No. 67 (May 19, 2012). The second article of the circular stipulates: "the use
of state-owned agricultural (forestry, animal husbandry and fishery) land shall be carried out in
accordance with the compensation standard for land acquisition of agricultural (forestry, animal
husbandry and fishery) sites in rural (town and street) areas (districts). If there are multiple areas
(districts) around the agricultural (forestry, animal husbandry and fishery) site, the highest standard
of the surrounding areas (districts) shall prevail."
4.5.1.3 Compensation Standard for Temporary Land Use
According to the regulations of the state and Anhui Province on the temporary land
occupation, the compensation for the temporary land occupation includes the compensation for
young crops / ground accessories and the compensation for land reclamation. In the construction
process of this project, temporary land occupation of borrow area and dumping site is involved.
Earthwork (such as gravel, stone and other construction materials) required for construction shall
be purchased from Xuanzhou Industrial Park, so no land occupation and compensation are
involved. The temporary land occupation of the dumping site is all the unused ponds of the village
collective. After the coordination of the project office, the owner unit has reached a preliminary
agreement with the village collective for the temporary land occupation, which will be
compensated by 1200 yuan / mu / year. According to the construction design, the occupation
period of the temporary land occupation of the project is 2 years, so the compensation period is
also 2 years, that is, during the 2 years, the collective economic organization of the temporary land
occupation village can obtain 2400 yuan / mu compensation fund.
4.5.2 Compensation Standards for the Acquisition of Flood Land Reclaimed by
Households along the River
(1) with respect to the compensation for flood land for which agricultural tax was paid in the
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 146
past, in compliance with the Notice of the Anhui Provincial Government on Adjusting
Compensation Rates for Land Acquisition of Anhui Province (WZ [2015] No.24) if the farmers
could provide original evidences or copy of evidences for payment of agricultural tax.
(2) compensation for “Erduowei” flood land along the river should take reference to flood
land acquisition standard of Shuiyang River Kaika and Shuiyang River Road Closed Section,
compensation standard is 15,000 RMB/mu, a lump sum for the town.
(3) ony compensation for young crops is given to the flood land outside “Erduowei”.
Such compensation standards meet domestic and ADB policies, are favorable to land
acquisition work for the project, could increase activeness of the households affected by land
acquisition, guarantee the rights and interests of households affected by land acquisition.
4.5.3 Compensation Standard for House Demolition
1. Compensation for house acquisition out of the scope of urban planning areas should be
given according to the Notification of the People’s Government of Xuanzhou District Concerning
Adjustment of the Compensation and Resettlement Standard for Collective Land House
Acquisition, and the Compensation Standard for Above-Ground Attachments and Young Crops in
Xuanzhou District(XQZM (2016) No.18).for specific standard, see Attachment 34.
2. Compensation for house acquisition within the scope of urban planning areas should be
given according to the Notification of Xuancheng Municipal People’s Government Office
Concerning Further Normalization of Compensation and Resettlement for House Acquisition On
Collective Land Within the Scope of Urban Planning Area (XZB (2015) No.11).for specific
standard, see Attachment 35.
Table 4-22 compensation standard for demolition of rural residential houses and auxiliary facilities
Affected
type
Structure
type Unit
Plan
compensation
standard(yuan/
㎡)
Actual
compensation
standard
Remarks
Housing Brick
concrete
㎡ 850 850-900
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 147
compensation structure
Brick wood
structure ㎡ 750 800
Simple
structure ㎡ / 300
Other
compensation
Housing
relocation
subsidy
yuan/hu 8yuan /㎡ 500yuan/person
Transitional
living
allowance
yuan/
㎡·month 6yuan/㎡
6 yuan / m2
within 18 months;
12 yuan / m2 after
18 months
The monetary compensation is
calculated and issued for 6
months, the property right
replacement is calculated and
issued for 4 months based on
the existing housing
resettlement, and the
outstanding housing is
calculated and issued for 18
months at 6 yuan / month per
square meter
4.5.4 Compensation Standard for Main Accessories and Infrastructure
For the compensation standard for above-ground attachments and compensation standard for
house demolition involved with Shuiyang River Integrated Transport Construction Project, see
Attachment 34. Agreement for the relocation of pole lines was signed in early May 2016. In Jul. 28,
Municipal Guidance Office held a promotion meeting for the relocation of pole lines, land
acquisition and demolition of Shuiyang River Integrated Transport Development Project, defined
to complete land acquisition and demolition, and relocation of pole lines completely before Aug.
20.
According to the principle of replacement price, determine the compensation standard for the
accessories and infrastructure of the project, which shall not be lower than the resettlement plan
standard in the implementation process.
4.5.5 Other Cost Standards
See 4-23 for other expense standards.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 148
Table 4-23 resettlement tax standard of the project
No Item Charging
standard Basis
1 Land occupation tax 2yuan/㎡ Measures of Anhui Province for the implementation of land
occupation tax (wcrch [2008] No. 367)
2 New construction
land use fee 28yuan/ ㎡
ircular of the Ministry of finance, the Ministry of land and
resources, the people's Bank of China on the adjustment of the
policy on the paid use fee of the newly added construction land
(November 7, 2006) (CZ [2006] No. 48)
3 Cultivated land
reclamation fee 8yuan/㎡
Detailed rules for the implementation of the management of
collection and use of cultivated land reclamation fees in Anhui
Province (wcz [2001] No. 1061)
4 Land acquisition
management fee
4% of total land
acquisition cost
5 Survey and design
cost
3% of total land
acquisition cost
6 External monitoring
and evaluation fee
1% of total land
acquisition cost
7 internal monitoring
and evaluation fee
0.5% of total land
acquisition cost
8 Water conservancy
fund 500yuan/mu
Notice of the people's Government of Anhui Province on printing
and distributing the administrative measures for raising and using
local water conservancy construction funds of Anhui Province (WZ
[2012] No. 54)
9 Administrative
expenses
5% of total land
acquisition cost
10 Technical training
fee
1% of total land
acquisition cost
11 Contingency
(reserve)
10% of the basic
resettlement cost
4.5.6 Vulnerable Groups
In addition to the aforementioned land acquisition compensation policies, vulnerable groups
affected by the project can also enjoy other preferential policies:
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 149
(1) Provide vocational training for the labor force in the vulnerable groups' families, and
provide various employment information and guidance to increase employment opportunities;
(2) In the process of project construction, priority should be given to recruiting the labor force
of vulnerable groups to do some non-technical work;
(3) Cooperate with Xuanzhou District Social Labor Security Department of Xuancheng City
to set up a special support fund of 200000 yuan to provide help.
4.5.7 Women's Support Measures
In addition to the policy of land acquisition compensation, women also enjoy special support
policies.
(1) Priority is given to employment opportunities, and 30% of women have access to
non-technical employment opportunities.
(2) Priority will be given to agricultural and non-agricultural technical training. 3000
agricultural and non-agricultural technical training will be conducted in this project, of which at
least 1500 (50%) women will be trained.
(3) Affected women have access to relevant information during the resettlement process and
can participate in fair consultation and resettlement.
(4) During the implementation of resettlement, a special women's forum was held to
introduce relevant policies of resettlement, so as to improve women's awareness.
(5) The compensation agreement must be signed by both husband and wife.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 150
5 Monitoring and evaluation mechanisms for resettlement
5.1 G206 Dongliu to Yaodu monitoring and evaluation mechanisms for
resettlement
5.1.1 Internal Monitoring and Inspection
Resettlement organizations have been available. Coordination Office entrusted by Anhui
Provincial Department of Transport (APDOT) through Dongzhi County Government, is
responsible for the project implementation and resettlement works. County government established
a resettlement leading group, and set up resettlement offices at county, town and village level.
Personnel and equipments have been mobilized.
During the implementation, resettlement offices at town level would collect implementation
information on the basis of individual, family and unit and submit to the County (District) Office;
after that, the information was forwarded to Coordination Office by County (District) Resettlement
Offices; Coordination Office reports the information to Foreign Investment Project Management
Office of the Transport Department of Anhui Province; APMO will regularly the resettlement
works at all levels and inspect the materials submitted and implementation progress. Thus, the
resettlement works at all levels will be incorporated in the monitoring mechanism.
5.1.2 Public Participation
In the stage of implementation, the various governments and affected enterprises and
individuals along the alignment would share the following activities concerning resettlement work:
(1) Compartmentalizing of the compensation scope and defining of compensation standard
(2) Determination of compensation agreement
(3) Selection of resettlement types
(4) Selection of new resettlement spots
(5) Redistribution of land
(6) Relocation and Resettlement for affected individual businesses;
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 151
(7) Investigation and coordination on grievance;
(8) Monitoring and evaluation on resettlement work.
As learned, the main Items concerning the public participation activities are summarized as
below:
Table 5-1 public participation
Purpose Mode Time Unit Participants Topics
Announcement on
compensation scheme
for land acquisition
Focus group and
field guidance
and advertisement
Nov.
2013
Relevant town
government in
Dongzhi County
All Affected
Persons(APs)
Compensation, type and policy
of payment
Preparatory works of
land acquisition and
demolition at earlier
stage
Focus group Nov.
2013
Relevant town
government in
Dongzhi County
All Affected
Persons(APs)
County and town levels
headquarters have setup, which
have held twice mobilization
meetings on land acquisition
and demolition for this project.
Preparatory works of
land acquisition and
demolition at earlier
stage
Focus group and
field guidance
and advertisement
Nov.
2013
PMO of
G206Dongliu to
Yaodu Section
Construction
Project
All Affected
Persons(APs)
Establishment of office staff,
issue the documents of land
acquisition and demolition,
carry out implementation.
Announcement and
implementation on
compensation scheme
for land acquisition
Focus group and
field guidance
and advertisement
Nov.
2013
Relevant town
government in
Dongzhi County
All Affected
Persons(APs)
Compensation, type and policy
of payment
Resettlement and
resettlement housing
construction
Consultative
Meeting
Dec.
2013
Maotian Village in
Yaodu Town Affected persons
Listen to the views of the
affected people for the time of
the resettlement sites and
housing construction
Resettlement questions Focus group April
2014
Zhanggang
Village, Dongliu
Town
Affected persons,
Village
government
officials
Demolition and resettlement of
relocated residents had no
objection
Part of the resettlement
housing construction
time
Into the
household
interviews
May
2014
Xiayang and
Zhaqiao Village Affected persons
Respect the wishes of the
individual affected households,
according to the individual
preparation time building
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 152
Purpose Mode Time Unit Participants Topics
Woodland
compensation Focus group
Oct.
2014
Meicheng
Forestry, Jin
Sishan Forestry
Forestry center
grows, workers’
representatives
Executive compensation
standard is not less than the
ADB policy Compensation
Standard
5.1.3 Grievance Redress Mechanism (GRM)
Stage 1: If any AP is dissatisfied with resettlement activities, he/she may file an oral or
written appeal to the village committee orally or in writing; if the complainant are not satisfied
with settlement decision, they could appeal at Dongzhi County Transportation Bureau (DCTB)
after receiving decisions; if they are still not satisfied with DCTB’s decision, they could provide
complain to Dongzhi County PMO after receiving decision; Stage 4: If the AP is dissatisfied with
the disposition of Stage 3, he/she may file an appeal to the Wuwei PMO after receiving such
disposition; Stage 5: If the AP is dissatisfied with the disposition of Stage 4, he/she may file an
appeal to the Anhui PMO after receiving such disposition; the AP may also bring a suit in a civil
court in accordance with the Administrative Procedure Law of the PRC at any point in the process.
Project Coordination Office establishes a complaints hotline, and posts the notice of the
complaints hotline in each village, so that the affected households in the resettlement process in a
timely manner to reflect emerging issues and in a timely manner for the Project Coordination
Office to solve problems for the affected households. Complaint Hotline Post published as the
pictures shown below.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 153
Picture 5-1 publication of Complaint Hotline and setting of report box
Monitoring and Evaluation Group learned that some village resettlement offices received
some complaints and questions, which have been settled after careful investigation and on-site
processing, such as water system, road system damage problems reflected by affected households.
Of which, affected households in Fangshan Group informed that the domestic water is affected by
water system destruction. Resettlement Office asked the staff in each township water station
together with technicians to fully check the water system and find out problems, then provide the
inspection results to County Transportation Bureau, in order to timely take measure. County
Transport Bureau makes special arrangements on County and Town Governments. Totaling 6
locations (4 locations within the red line) of water facilities are identified to be transformed, newly
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 154
built and rebuilt after field investigation, including: transformation of a drainage and irrigation
station, 4 locations of sluices at entrance and exit, one staunch, and taking into account the small
water system problems. As of June 30, 2016, Water restoration project is basically completed,
residents live, production water is not affected by adverse effects.
5.1.4 Typical Cases
Case 1: During the process of house demolition within the scope affected by the project,
there are 27 house-demolished households, of which actual affected are 22 households, involving
main houses and outbuilding; In addition, Yaodu town involves the demolition of five houses, all
of which are for management auxiliary use only for seasonal use. As the five households have
corresponding housing facilities in other locations, there is no need for resettlement. But the owner
of the house complained that it would be demolished.
Solution: demolish the house according to the requirements of the owner, and compensate the
house in the compensation process. See Table 5-1 for the housing situation and demolition
compensation. The situation of some demolished houses is shown in Figure 5-2.
Table 5-1 Demolition and compensation status for discarded houses
Location Head of
household Compensation(Yuan) Type of Housing
Guansha n
Village
Ding
Longquan 2698
Outbuilding abandoned many years, no
one lives there
Zhaqiao
Village
Village
collective 185307
Fishing lake management room belongs
to village collective
Maotian
Village Hu Mingsheng 348160
Original duck shed, abandoned many
years
Maotian
Village Zhao Zhenzhu 30448
Outdated fishing lake management
shed, no one live there
Jiandong
Village Li Qing 5574
Abandoned house in farmland, no one
live there
Compensation Subtotal 572187
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 155
(a) Fishing lake management room belongs to Zhaqiao village collective
(b) Zhao Zhenzhu’s fishing lake management shed
(c) Ding Longquan’s outbuilding without living (d) Li Qing’s broken house located in farmland
Picture 5-2 Original pictures of demolished houses for the purposes of production and management
Case 2: March 19, 2015 one side of the construction of access roads is arable land at Dongliu
Town, due to heavy rains, resulting in the loss of topsoil sidewalk slope covered with a small
amount of farmland, and choked ditches, so farmers through the complaint hotline complained to
the Project Coordination Office.
Solution: March 20, 2015, by field investigation, Coordination Office, the construction team
and other relevant persons of Xiayang Village jointly propose solutions: I. The construction team
complete refurbishment sidewalk slope and clear ditches work before March 22; II. And the
affected households responsible for clean-up arable land, the construction team paid to the affected
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 156
households for the costs of clean-up, there is no objection. Construction team complete the
renovation of slope and gutter clear in a specified time, and timely payment of arable land mud
clean-up costs, without bad influence.
5.2 S319 Wuwei to Erba Monitoring and Evaluation Mechanisms for
Resettlement
5.2.1 Internal Monitoring and Inspection
Resettlement organizations have been established for S319 Wuwei Section. Wuwei County
Transportation Bureau entrusted by Anhui Provincial Department of Transport (APDOT) through
Wuwei County Government, is responsible for the project implementation and resettlement works.
The governments at all levels are responsible for the project implementation and relevant
resettlement, conducting the internal monitoring work as well as completion of Internal
Monitoring Report. County government established a resettlement leading group, and set up
resettlement offices at county, town and village level. Personnel and equipments have been
mobilized.
5.2.2 Public Participation
Great importance is given to aps’ participation of and consultation at the preparation and
implementation stages of S319 project. During the implementation, public participation will be
further carried out. PMO has issued a booklet of resettlement information to aps. The group
learned the records on public participation shown as below:
Table 5-2 Records of Public Participation
Purpose Mode Time Unit Participants Topics
Training
program
Village
meeting
Dec. 2014 –
Dec. 2015
Officials fromwuwei
PMO, WCTB, county
land and resources
bureau, town and
village
All APs Discussing training
needs
M&E Sampling
survey, FGD
and
Dec. 2014 –
Jun. 2017
Aexternal Resettlement
Monitoring Agency,
officials of town and
All APs
1) Resettlement
progress and impacts
2) Payment of
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 157
Purpose Mode Time Unit Participants Topics
interview village compensation
3) Information
disclosure
4) Livelihood
restoration and house
reconstruction
M&E
Informal
discussion
and
interview
Jan.
2016-Apr.
2016
External
Resettlement
Monitoring Agency,
Cadres of the
towns/townships,
villages
All APs
1) Resettlement
progress and
impacts 2)
Livelihood
recovery and house
reconstruction 3)
information
disclosure
M&E
Informal
discussion
and
interview
Dec.2016
External
Resettlement
Monitoring Agency,
Cadres of the
towns/townships,
villages
All APs
Resettlement
progress and
situation
Resettlement Meeting Sept.,2019 Wuwei County
Project Office
Households
to be
resettled
Resettlement house
selection
5.2.3 Grievance Redress Mechanism(GRM)
S319 Erba to Wuwei Section Reconstruction Project Field Office established S319 Erba to
Wuwei Section Reconstruction project Resettlement Management Office. Personnel and
equipments have been mobilized.
Project Coordination Office establishes a complaints hotline, and posts the notice of the
complaints hotline in each village, so that the affected households could reflect emerging issues in
the resettlement process in a timely manner and the Project Coordination Office could solve
problems for the affected households in a timely manner.
Stage 1: If any AP is dissatisfied with resettlement activities, he/she may file an oral or
written appeal to the village committee orally or in writing; Stage 2: If any AP is dissatisfied with
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 158
the disposition of Stage 1, he/she may file an oral or written appeal to the township government
orally or in writing; if any complainant still feels dissatisfied with the decision of Wuwei County
Transport Bureau, the complainant may file a complaint at Dongzhi County Project Office after
receiving the decision, if the complains are still not resolved, they may be submitted to Anhui
Provincial PMO, or an appeal may be lodged to justice department according to Civil Procedure
Law.
Case 1: on Nov. 25, 2015, Ji Changtian from Jicun appealed to the Resettlement Management
Office that the construction team of Contract 03 caused dead of some fish in his pond during
construction, and he asked for compensation of his loss.
Transaction situation: the headquarters coordinated the Project Department of the Fifteenth
Bureau to compensate his loss 500 Yuan.
Case 2: on Dec. 8, 2015, Zhang Zhiqing from Makan appealed to the Resettlement
Management Office that the construction team of Contract 03 affected the rest of pregnant women
during nighttime construction, asked to take corresponding measures.
Transaction situation: the headquarters compensated him 3000 Yuan to find another place for
rest.
Case 3: the S319 project of Wuwei County adopted the construction of bilateral widening,
which was the main road from Wuwei County to Wuhu City. The traffic flow is large, and the road
construction brings hidden dangers to the traffic safety.
Transaction situation: the project headquarters of Wuwei County strictly required the
construction unit to add security facilities such as warning pile guardrail on the basis of the
procurement contract, and invited the traffic police department to add vehicle speed measuring
device in the construction section to prevent the accident risk caused by too fast speed.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 159
5.3 S367 Ma’anshan Northern Passage Road Construction Project
Monitoring and Evaluation Mechanisms for Resettlement
5.3.1 Internal Monitoring and Inspection
S367 Ma’Anshan Northern Passage Road Construction Project Resettlement Organization
Municipal Project Office asked the counties (refer to Hanshan County in this monitoring report,
resettlement related work has not been carried out in He County, the same below) to establish and
allocate special persons for specific resettlement work; deputy director of the Site Department
should be in charge of resettlement related work; deputy town chief of the towns along the line
should be responsible for resettlement related work, and should dispatch personnelfamiliar with
such work and the leaders of relevant administrative villages to coordinate with resettlement work,
classify resettlement-related data for archiving.
To enable the people along the line to further understand relevant ADB policies, promote
successful proceeding of resettlement work, Hanshan County headquarters issued the Resettlement
Plan for Maanshan City Northern Passage Road Project, ADB Security Policies etc and issued to
the villages; relevant resettlement personnel in the town communicated with some AHs for the
compensation standards for acquisition and demolition.
According to the Resettlement Plan for Maanshan City Northern Passage Road Project, in
combination with specific conditions in the counties, Implementation Scheme of Compensation
and Resettlement for House Demolition for S367 Maanshan Section (Northern Passage Road)
Reconstruction Project was formulated in the counties, provided reliable basis for acquisition and
demolition later. Relevant image data were collected timely according to the work progress.
Permanent land acquisition data in the restriction line have been collected, image data of housing
demolition and resettlement sites etc will be collected at next step.
5.3.2 Public Participation
During the feasibility study in the project preparation stage, Ma'anshan PMO has repeatedly
solicited suggestions and opinions from relevant government departments, affected towns, villages
and affected households on the resettlement work of the project.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 160
Since August 2012, under the guidance of technical assistance consulting experts, Academy
of Jiangsu Transportation Sciences Co., Ltd., Ma'anshan project office, Hexian County, Hanshan
County Transportation Bureau and the investigation team of Hehai University have carried out a
series of socio-economic surveys and public consultation (30% of women participated). During the
preparation of the project, the PMO, the implementing agencies and the Design Institute conducted
extensive consultation on the land acquisition and resettlement of the project. See Annex 37 for the
minutes of public participation. The migration information booklet was issued in December 2012.
With the continuous progress of project preparation and implementation, the project
implementation agency will also carry out further public participation. See table 5-3 for details of
public participation arrangements.
The resettlement plan was opened. Before January 31, 2015, the resettlement plan would be
made public in the project office of Ma'anshan City, the office of Transportation Bureau of He
county and Hanshan County, as well as on the website of Ma'anshan municipal government, and
the announcement would be published in the main local newspapers so that the resettlement
householders could consult and put forward their opinions.
Resettlement information book. The main part of the resettlement plan was compiled into
resettlement information manual, which was released to the resettling people before May 31, 2013.
The main contents of the information book include: project overview, project impact,
compensation policy, implementation agency, appeal channel, etc.
Table 5-3 project public participation plan
Purpose Mode Time Unit Participants Topics
Release of
resettlement
plan or
information
book
Release
information
book
May,2013 Ma anshan
project office
Transporta
tion
Bureau of
Hexian
county and
Hanshan
County,
township
governme
nt and
Officially inform
the immigration
plan and its main
contents
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 161
Purpose Mode Time Unit Participants Topics
village
committee
Release of
resettlement
plan
website June,2013 ADB
Anhui and
Ma'anshan
PMO
resettlement plan
website open
Announcement
of land
acquisition
Village
bulletin
board and
villagers'
meeting
Feb.,2015
Ma'anshan PMO,
Transportation
Bureau, land and
Resources
Bureau, township
and village cadres
of He county and
Hanshan County
All APs
Announcement of
land acquisition
area,
compensation
standard and
resettlement way,
etc
Announcement
of
compensation
and
resettlement
plan for land
acquisition
Village
bulletin
board and
villagers'
meeting
Feb.,2015
Ma'anshan PMO,
Transportation
Bureau, land and
Resources
Bureau, township
and village cadres
of He county and
Hanshan County
All APs
Compensation fee
and payment
method
Physical
quantity
review
field
investigatio
n
Mar.,2015
Ma'anshan PMO,
Transportation
Bureau, land and
Resources
Bureau, township
and village cadres
of He county and
Hanshan County
All APs
1)Check the
leakage and make
up the deficiency,
and confirm the
final impact
2)List of land
occupied by
immigrants and
assets lost
3)Prepare
compensation
agreement basic
contract
Determine
revenue
villagers'
meeting
Before
implementa
Ma'anshan PMO,
Transportation All APs Discuss the final
income recovery
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 162
Purpose Mode Time Unit Participants Topics
recovery plan
and its
implementatio
n
(many
times)
tion Bureau, land and
Resources
Bureau, township
and village cadres
of He county and
Hanshan County
plan and the use
plan of
compensation
funds
training plan Villagers
meeting
2014.12~
2015.12
Human resources
and Social
Security Bureau,
township and
village cadres
All APs Discuss training
needs
monitor
Villagers
participate
in the
meeting
2014.12-20
17.7
township and
village cadres All APs
1) Resettlement
progress and
impact2) Payment
of compensation
3) Information
open
4)Recovery of
production and
life, resettlement
of demolished
houses
monitor
Villagers
participate
in the
meeting
2015.11.02
Project
officeCounty and
township
resettlement
personnel
Part of
APs
Resettlement
training
At present, the vulnerable groups of the affected households of the project have been
investigated, and relevant assistance measures have been formulated (such as technical training,
employment arrangement of the project, life assistance, etc.)
Note: in April 2016, the Ministry of land and resources has issued the reply on the
construction land for the reconstruction project of Ma'anshan section (Northern passage) of the
comprehensive transportation infrastructure project loaned by ADB (GZH [2016] No. 51), see
Annex 36.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 163
During the implementation of the resettlement plan, the resettlement agencies at all levels
shall register and manage the complaint data and processing result data, and report to the project
office of Ma'anshan City in written form once a month. Ma'anshan PMO will regularly check the
registration of complaint handling.
In order to fully record the complaints of the affected population and the handling of related
problems, Ma'anshan PMO and the project implementation agency formulated the registration
form of complaints and grievances of the affected population. See table 5-2 for the format sample.
Table 5-4 resettlement complaint and appeal registration form
Accepting unit: Time: Location:
Name of
complainant
Complaining
content Solution required
Proposed
solutions Actual handling
complainant
(signature)
recorder
(signature)
Note: 1) The recorder shall truthfully record the contents and requirements of the complaint.
2) The grievance process should not be disturbed or obstructed.
3) The proposed solution shall be replied to the complainant within the specified time.
The resettlement agencies of the project will arrange the main person in charge to receive and
handle the complaints and grievances of the affected population. See table 5-5 for names and
contact numbers of offices at all levels and their responsible persons.
Table 5-5 Information on complaint and grievance institutions and personnel of the affected
population
Relevant unit Contact person Telephone
Anhui provincial project office Wufei 0551-63756191
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 164
Ma'anshan PMO He changshenf 0555-2471127
Hexian Transportation Bureau Director Miao 0555-5313006
Transportation Bureau of Hanshan County Director Huang 0555-4314354
Case 1:
Complaint content: local residents of K15 + 231.5 passage bridge in Shiyang community,
Shiyang town complained that construction road is too close to the specified distance which will
be harmful to the growth of trees,and asked for compensation.
Transaction situation: After the study of the PMO, it was agreed that the number involved the
villagers' requirements, the number of felling and compensation. The villagers were satisfied with
the result.
Case 2:
Complaint content: Lu changcui, the householder of Dongxing village, Zhaoguan Town,
Hanshan County, whose house is 5 meters away from the red line of land acquisition, asked to be
demolished because the house was higher than the road surface and inconvenient to travel .
Transaction situation: The county and town governments studied and decided not to dismantle,
but repaired the part from the front of the gate to the road, and gave 35000 yuan as compensation.
The householder was satisfied with this treatment. The repaired pavement as shown in the figure.
Figure 5-3 pavement repaired at the gate of Lu changcui in Hanshan County
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 165
5.4 G318 and S320 Yimu Highway Project monitoring and evaluation
mechanisms for resettlement
5.4.1 Internal Monitoring and Inspection
Resettlement organizations have been set up for Yimu Highway in Nanling County. Transport
Department of Anhui Province authorized Nanling County Transport Bureau to be responsible for
overall implementation and corresponding resettlement of this project via the people’s government
of Nanling County, the town governments are responsible for the project implementation and
relevant resettlement, conducting the internal monitoring work as well as completion of Internal
Monitoring Report. County government established a resettlement leading group, and set up
resettlement offices at county, town and village level. Personnel and equipments have been
mobilized.
During the implementation, resettlement offices at town level would collect implementation
information on the basis of individual, family and unit and submit to the County (District) Office;
County (District) Relocation & Resettlement Office reports the information to Nanling County
Department of Transport; Nanling County Department of Transport Relocation & Resettlement
Office reports the information to the Foreign Investment Office of the Transport Department of
Anhui Province; APMO will regularly the resettlement works at all levels and inspect the materials
submitted and implementation progress. Thus, the resettlement works at all levels will be
incorporated in the monitoring mechanism.
5.4.2 Public Participation
In the stage of implementation, the various governments and affected enterprises and
individuals along the alignment would share the following activities concerning resettlement work:
(1) Compartmentalizing of the compensation scope and defining of compensation standard
(2) Determination of compensation agreement
(3) Selection of resettlement types
(4) Selection of new resettlement spots
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 166
(5) Redistribution of land
(6) Relocation and Resettlement for affected individual businesses;
(7) Investigation and coordination on grievance;
(8) Supervision and evaluation on resettlement work.
Supervision and evaluation team learned from the inspection that, the main items concerning
the public participation activities are summarized in the table below:
Table 5-6 registration form of public participation
Purpose Mode Unit Time Participants Subject
Announcement
on
compensation
scheme for
land
acquisition
Focus group
and field
guidance and
advertisement
Relevant
township,
town
governments
in Nanling
County
May 2014
All Affected
Persons(APs),
as well as
cadres of towns
and villages etc
Compensation,
type and policy of
payment
Preparatory
works of land
acquisition and
demolition at
earlier stage
Focus group
and field
guidance and
advertisement
Project
construction
Management
Office
June 2014
All Affected
Persons(APs),
as well as
cadres of towns
and villages etc
Establishment of
office staff, issue
the documents of
land acquisition
and demolition,
carry out
implementation.
Announcement
and
implementation
on
compensation
scheme for
land
acquisition
Focus group
and field
guidance and
advertisement
Relevant
township,
town
governments
in Nanling
County
Nov.
2014
All Affected
Persons(APs),
as well as
cadres of towns
and villages etc
Compensation,
type and policy of
payment
Resettlement
and
resettlement
housing
construction
Consultative
Conference
Nanling
County Jan. 2015
Affected
persons, as well
as cadres of
towns and
villages etc
Listen to the
affected people’s
view on the time
of resettlement
sites and housing
construction
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 167
Purpose Mode Unit Time Participants Subject
Resettlement Consultative
Conference
Jishan
Town,
Nanling
County,
Gongshan
Town
Dec. 2015
External
monitoring
group, Affected
persons,
township, town,
village cadres
etc
Listen to the
affected people’s
view on the time
of resettlement
sites and housing
construction
Resettlement
Focus group
and field
guidance and
advertisement
Relevant
township,
town
governments
in Nanling
County,
external
monitoring
group
Jan. 2016
All Affected
Persons(APs),
township, town,
village cadres
etc
Information
disclosure,
including the
selection of
resettlement
mode, selection
of resettlement
sites and
distribution of
house sites,
construction of
resettlement
apartments etc
Resettlement Consultative
Conference
External
monitoring
group
Apr. 2016
Affected
persons as well
as township,
town, village
cadres etc
Impact survey
before and after
the resettlement
of the already
resettled aps
Resettlement Household
survey
External
monitoring
group
Dec.,2016
Affected
persons as well
as township,
town, village
cadres etc
Sample survey on
living standards
of the affected
people
5.4.3 Grievance Redress Mechanism(GRM)
Nanling Yimu Highway Project Coordination Office established complaints mechanism, and
propagandized the complaints process and procedures in the form of poster, so that the affected
households could reflect emerging issues in the resettlement process in a timely manner and the
Project Coordination Office could solve problems for the affected households in a timely manner.
The poster is shown in Fig.5-4 below. At the same time, Resettlement Office established
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 168
resettlement complaint standing book to archive and solve the problems reflected by farmers
timely. Resettlement complaint Record standing book is shown in Fig.5-5.
Picture 5-3 Resettlement Complaint Procedure and Flow Chart Poster
Picture 5-4 Resettlement Complaint Record Standing Book
Case 1:
Complaint content: Five households along the line of Gongshan town are less than 1m away
from the red line of the road. After the completion of the road, frequent vehicle traffic brings
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 169
certain safety hazards to residents' travel, and traffic noise, dust and other negative impacts on
Residents' lives. In addition, the way of centralized resettlement was adopted in Gongshan town.
Once the houses were demolished, the demolished households can get higher economic income
Benefit and improve the quality of life. The five households asked the PMO to demolish the
houses and resettle them.
Transaction situation: The appeal requirements of 5 households attracted the attention of
Nanling County Government and Gongshan town government. The government department
carried out a special study and agreed that the five households, like other relocated households in
the red line of the road, would enjoy the policy of demolition and resettlement, and all of them
would be demolished and resettled in the Datang community together with other relocated
households.
Case 2:
Complaint content: on January 8, 2016, there were no K30 + 215, K30 + 300, k29 + 850
culverts in the construction drawing of Yimu road in Gaoling village, Gongshan Town, which led
to the covering of these culverts in the construction, and the villagers could not get water for
irrigation in the fields. Therefore, they applied to the people's Government of Gongshan town to
install culvert pipes in K30 + 215, K30 + 300, k29 + 850 sections.
Transaction situation: it was agreed to install culvert pipes to ensure villagers' irrigation.
Case 3:
Complaint content: Bao Zhengsheng said that his old house was in disrepair for a long time,
and his family worked in Beijing for a long time, resulting in the collapse of the old house. He
wanted to rebuild the house, but the Yimu road will be rebuilt immediately, which will affect the
basic road surface, and he asked to be resettled according to the transitional households in this
resettlement.
Transaction situation: the people's Government of Gongshan Town, after investigation and
verification, reflected the truth of the situation, and the town government decided to give
transitional resettlement. He was very satisfied.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 170
5.5 Shuiyang River Transport Construction Project Monitoring and
Evaluation Mechanisms for Resettlement
5.5.1 Internal Monitoring and Inspection
Resettlement organizations have been set up for Shuiyang River Transport Project.
Xuancheng City the governments at all levels are responsible for the project implementation and
relevant resettlement, conducting the internal monitoring work as well as completion of Internal
Monitoring Report. County government established a resettlement leading group, and set up
resettlement offices at county, town and village level. Personnel and equipments have been
mobilized.
5.5.2 Public Participation
Great importance is given to aps’ participation of and consultation at the preparation and
implementation stages of this project. During the implementation, public participation will be
further carried out. PMO has issued a booklet of resettlement information to aps. The group
learned the records on public participation shown as below:
Table 5-7 Records of Public Participation
Purpose Mode Time Unit Participants Subject
Training
program
Village
meeting
Dec. 2014 –
Dec. 2015
Officials from
Xuanzhou District
PMO, Xuancheng
Municipal
Transportation Bureau,
County Land and
Resources Bureau,
towns and villages
All APs Discussing
training needs
Monitoring
Sampling
survey, FGD
and
interview
Dec. 2014 –
Jun. 2017
External Resettlement
Monitoring Agency,
officials of town and
village
All APs
1) Resettlement
progress and
impacts
2) Payment of
compensation
3) information
disclosure
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 171
Purpose Mode Time Unit Participants Subject
4) Livelihood
recovery and
house
reconstruction
Monitoring Field survey Apr. 2016 External monitoring
group
External
monitoring
group and the
affected
persons
Investigation of
the properties
related to vital
interests of the
APs after
resettlement, yet
sufferred from
loss
Monitoring Field survey Dec.,2016 External monitoring
group
The affected
persons
Survey the living
standards of the
affected people
after resettlement
Monitoring Field survey Apl.,2020 External monitoring
group
The affected
persons
Survey the living
standards of the
affected people
after resettlement
5.5.3 Grievance Redress Mechanism(GRM)
Case 1: Due to the shutdown of the construction of Huishang Century City, the resettlement
house of Xuanzhou port comprehensive wharf project, the relocated households were not able to
get the resettlement house within the agreed time (Huishang century city was originally scheduled
to hand over the house on December 31, 2018).
Transaction situation: The local government actively communicated and coordinated with
Anhui Huishang group and Xuancheng Chuangyuan Real Estate Development Co., Ltd.
(developer). Considering that Huishang group was still in the period of internal structure
integration, Xuancheng Chuangyuan Real Estate Development Co., Ltd. was unable to determine
the specific delivery time of Huishang shijicheng project. According to the agreement, the people's
Government of Yangxian township issued the temporary resettlement extension transition fee to
December 31, 2018 (it had been issued to June 30, 2018, and the transition fee from July 1, 2018
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 172
to December 31, 2018 will be issued to January 2019). From January 2019, Xuancheng
Chuangyuan Real Estate Development Co., Ltd. bore the temporary resettlement delay transition
fee. If the company fails to pay on time, the people's Government of Yangxian township will
deduct the future generations from the purchase price to pay, so as to effectively protect the
legitimate rights and interests of the relocated households. External monitoring units will continue
to pay attention to resettlement.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 173
6 G206 Dongliu to Yaodu Investigation and Analysis of the Living
Standards of the Affected Households
The resettlement work of each sub project of Anhui multimodal transport sustainable
transportation project loaned by ADB has been basically completed. Since the project involves
relatively scattered affected residents, the external monitoring plan starts this period of monitoring
report. In each report, 1 to 2 sub projects are selected to investigate the restoration of economic
and living standards affected by resettlement, and make analysis reports. This report is an
investigation report on G206 Dongliu Yaodu section project.
6.1 Distribution of survey samples
During December 2013-January 2014, April-May 2014, random samples were made by the
Monitoring and Evaluation Group for investigation on land-affected and house-demolished
families, totaling 46 families, that is, 36 land-affected households, 7 house-demolished families,
and 5 households with land-affected and house-demolished families. The above-mentioned
samples were carried out with baseline investigation and filed.
From April 2020 to may 2020, the survey objects of the affected households are 44 affected
households along the road, including 34 affected by land acquisition, 5 affected by house
demolition, and 5 affected by land acquisition and demolition. The sample distribution is shown in
table 6-1:
Table 6-1Household sample distribution of living standard basic survey
Village(town、street) Number of households
affected
Number of households
investigated Sample
proportion 2013 2019
Xiayang 53 8 8 15.09%
Zhanggang 156 9 9 5.77%
Gaungshan 205 13 13 6.34%
Mantian 206 14 14 6.80%
Among them, there are 53 affected households in Kuanyang village, 8 in this survey; 156 in
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 174
Zhanggang village, 9 in this survey; 205 in Guanshan village, 13 in this survey; 206 in Maotian
village, 14 in this survey. The distribution and basic characteristics of the family members selected
in this survey are relatively uniform and representative, which can truly reflect the basic living
standards of the affected households.
6.2 Annual Per Capita Income of Affected Families
In April 2020, the testing team members investigated the annual per capita income of 2017,
2018 and 2019 of the affected households who established the archives.
Table 6-2 annual per capita income of affected families
No. Name Affected type annual per capita income (yuan)
2014.12 2015.12 2016.12 2017 2018 2019
1 Lin guocai Land acquisition 20000 21050 22166 23000 23000 24000
2 Zhang
shouyuan Land acquisition 25000 26312 27707 28000 29000 29000
3 Hu demo Land acquisition 15000 15787 16624 17000 17000 20000
4 Ding longquan Demolition 50000 52625 55414 56000 57000 57000
5 Ye longlin Demolition 40000 42100 44331 46000 46000 47000
6 Zhang guofeng Demolition 15000 16874 17223 18000 20000 21000
7 Hu dekui Land acquisition、Demolition 20000 21056 22166 23000 23000 24000
8 Liu airong Land acquisition、Demolition 15000 15789 16624 17000 18000 20000
9 Su rencai Land acquisition、Demolition 15000 15442 17588 18000 20000 21000
10 Su renguang Land acquisition 20000 21009 22623 23000 24000 24000
From the above monitoring results, it can be seen that the construction of G206 Dongliu
Yaodu project has little negative impact on the family income of local residents. The main reasons
are as follows: the resettlement progress of the project is relatively fast, the period of influence on
the affected households is relatively short, the affected households have enough time to engage in
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 175
the original work, and the impact on family income is relatively small. The households affected by
the project are less dependent on the land and the amount of land is small.
6.3 property status of the investigated family
In order to fully reflect the economic situation of the investigated family, this survey took the
investigated family property as an important content. In the survey, 12 kinds of durable consumer
goods or important production materials were selected. Compared with the types of basic living
standard survey, pad and air conditioning projects were increased, DVD / VCD indicators were
reduced, and the rest were basically consistent, trying to reflect the economic level of the
investigated families. See table 6-3 for the specific situation of the average amount of durable
consumer goods owned by the affected households.
On the whole, in April 2020, the survey found that the lowest distribution of indicators was
pad and air conditioner. With the gradual improvement of living standards, the surveyed
households have gradually used pad, and the number of air conditioner is gradually increasing;
broadband ownership is 0.84 per household, computer ownership is 1.84 per household, and
telephone and mobile phone ownership are 4.42 per household. The possession of broadband,
mobile phone, TV and computer is relatively high, which shows that the information between
villagers and society is unobstructed, which has a positive role in promoting the social
development of rural collective. At the same time, with the development of mobile phone network,
the possession of TV has declined. The number of refrigerators and washing machines per
household is 1.21. It can be seen from the data comparison of the two surveys that the ownership
of broadband and computers of residents has greatly increased in 2019 and 2013, on the one hand,
the reason is that the information consumption cost has been greatly reduced; on the other hand,
the income level of residents has been greatly improved, affected by the convenience of the
improvement of communication and the improvement of income level, cars, motorcycles / electric
bikes The quantity of non necessities has also been greatly increased.
Table 6-3 average household ownership of durable consumer goods of affected households
Xiayang Zhanggang Guanshan Maotian Population
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 176
Property name 2013 2019 2013 2019 2013 2019 2013 2019 2013 2019
broadband 0.71 0.75 0.82 0.89 0.73 0.85 0.71 0.86 0.74 0.84
Computer 1.43 1.75 1.55 1.89 1.46 1.85 1.43 1.86 1.46 1.84
Pad / 0.38 / 0.33 / 0.54 / 0.43 / 0.43
M-phone 3.86 4.00 4.46 4.50 3.73 4.00 4.07 5.00 4.00 4.42
TV set 3.36 3.50 0.36 1.11 3.27 3.08 2.86 3.00 2.58 2.73
Air conditioner / 0.50 / 0.33 / 0.46 / 0.57 / 0.48
refrigerators 1.07 1.00 1.27 1.11 1.00 1.00 1.21 1.57 1.14 1.20
washing machine 1.00 1.00 1.27 1.00 1.00 1.00 1.21 1.23 1.12 1.07
bike 1.71 1.75 1.27 1.33 1.55 1.54 1.64 1.43 1.55 1.50
motorcycles / electric bike 1.36 1.75 1.36 1.56 1.55 1.77 1.43 1.71 1.44 1.70
car 0.21 0.25 0.91 1.00 0.18 0.46 0.57 0.64 0.46 0.59
Agricultural machinery 0.36 0.38 0.82 0.78 0.46 0.38 0.72 0.86 0.59 0.61
6.4 Living Conditions of the Investigated Family
6.4.1 Basic Public Goods Such as Water and Electricity
6.4.1.1 Domestic Water
The domestic water is mainly from three aspects: tap water, well water, pond water, etc. in
fact, there is no use of lotus pond water, so it will not be shown in the table. See table 6-4 for
details.
Table 6-4 domestic water situation of investigated households (%)
Xiayang Zhanggang Guanshan Maotian total
Year 2013 2019 2013 2019 2013 2019 2013 2019 2013 2019
Tap
water 16.9 87.5 12.56 88.89 32.7 84.62 12.39 85.71 19.39 86.36
Well
water 83.1 25 87.44 22.22 67.3 23.07 87.61 14.26 80.61 20.44
total 100 112.5 100 111.11 100 107.69 100 105.39 100.00 106.81
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 177
Figure 6-1 domestic water sources in 2013 and 2019 (%)
Figure 6-2 source of domestic water (%)
In general, 19.39% of households use tap water in 2013, and 80.61% use well water. With the
policies of better rural construction and other policies, all rural areas have access to tap water. In
2020, the proportion of total use of tap water has increased significantly, to 86.36%. There are
problems in living habits. Some residents still use well water at the same time, and the proportion
of total use of well water has decreased significantly to 20.44%, totaling 100% The reason why the
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
2013 2019
Tap water Well water
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 178
ratio is more than 100 is that some families use tap water and well water at the same time.
6.4.1.2 Domestic Electricity
According to the analysis of three indicators, the household electricity consumption of the
investigated households is all guaranteed, and there are no households with no electricity.
Sufficient electricity can ensure the daily production and living needs of the residents. See table
6-5 for the specific situation of domestic power consumption in the sample village.
Table 6-5 household electricity consumption (%)
Xiayang Zhanggang Guanshan Maotian Population
2013 2019 2013 2019 2013 2019 2013 2019 2013 2019
Guaranteed 100 100 100 100 100 100 100 100 100 100
Yes, but no
guarantee
0 0 0 0 0 0 0 0 0 0
No 0 0 0 0 0 0 0 0 0 0
6.4.2 House condition
6.4.2.1 HouseType
81.64% of the total families are buildings. Compared with 63.6% in 2013, the proportion of
buildings has increased, because the productivity development level along the line is high, the
family living standard is good, and the housing conditions are good. See table 6-6 for details.
Table 6-6 investigated family buildings (%)
Xiayang Zhanggang Guanshan Maotian Population
2013 2019 2013 2019 2013 2019 2013 2019 2013 2019
Bungalow 37.5 12.5 33.33 11.11 46.15 23.08 28.57 21.43 36.40 18.36
Building 62.5 87.5 66.67 88.89 53.85 76.92 71.43 78.57 63.60 81.64
total 100.00 100.00 100.00 100.00 100.00 100.00 100.00100.00 100.00 100.00
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 179
Figure 6-3 house types of surveyed households in 2013 and 2019 (%)
Figure 6-4 proportion of total house types of surveyed households (%)
The distribution structure of sample villages of bungalows and buildings is basically
consistent with the overall sample. The proportion of buildings in all sample villages is more than
75%. The proportion of buildings and bungalows in Xiyang village is 87.5:12.5, that in Zhanggang
village is 88.89:11.11, that in Guanshan village is 76.92:23.08, and that in Maotian village is
78.57:21.43.
6.4.2.2 House Structure
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 180
From the perspective of housing structure, in 2013, 86.96% of the households in the overall
sample were brick and concrete houses, with the proportion of brick and wood houses ranking
second, 8.69%, and the proportion of civil houses and simple houses was 2.17%, respectively, with
a high overall living level; in 2019, the survey showed that the proportion of frame structure
houses was 31.82%, the proportion of brick and concrete structure houses was 67.02%, the
proportion of simple houses was 1.16%, and the proportion of brick and wood houses and civil
structure houses was 0. See table 6-7 for details.
Table 6-7 house types of the investigated households (%)
Xiayang Zhanggang Guanshan Maotian Population
2013 2019 2013 2019 2013 2019 2013 2019 2013 2019
Frame 0.00 50.00 0.00 44.44 0.00 38.46 0.00 7.14 0.00 31.82
Brick 62.50 43.60 88.89 55.56 100.00 61.54 86.67 92.86 86.96 67.02
Brick and
wood 12.50 0.00 11.11 0.00 0.00 0.00 13.33 0.00 8.69 0.00
Civil
Engineering 12.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.17 0.00
Simple 12.50 6.40 0.00 0.00 0.00 0.00 0.00 0.00 2.17 1.16
Total 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 181
Figure 6-5 house structure of the surveyed households in 2013 and 2019
Figure 6-6 house structure of the investigated families in each village
The characteristic distribution of each sample village is slightly different. Before the
demolition, there was no frameless structure in the investigation sample. After the demolition,
31.82% of the houses were rebuilt as frame structures. From the perspective of brick and concrete
houses, the highest proportion is Maotian village, which is 92.86%. The house type is mainly
frame and brick and concrete structure, and very few families have civil structure houses and brick
and wood structure houses. There are basically no civil and simple houses. The overall living
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 182
conditions are good.
6.4.3 Living Environment
The target of this analysis design is the distance from the place where we live to the nearest
hospital, school, shopping center and bus station and the time needed. Table 6-8 shows the distance
and time of the nearest public facilities in the residence of the investigated family. There is
basically no change between the survey results and the base survey in 2019. But after the new road
is built, the road condition is greatly improved, the travel is more convenient, and the time is
shortened. It is more convenient for residents to travel.
Table 6-8 the distance between the nearest public facilities in the residence of the investigated
family (km)
Bus
station
Towns at or above the
county level
Market
town
Primary
school
Middle
school Hospital
Xiayang 7.5 9 4 0.8 1 1
Zhanggang 9 14 1 1 1 1
Guanshan 8 8 1 1 1 1
Maotian 6 7 1 1 1 1
6.5 Analysis of the Economic Income and Source of the Investigated
Family
6.5.1 Economic Income of the Investigated Family
According to the survey and statistics, before the land acquisition of each village involved in
the project, there are 5892.11 mu of cultivated land, with an average per capita cultivated land of
1.11 mu / person. 294.36 mu of cultivated land is expropriated for the project, with an impact rate
of 4.9%. After land acquisition, the per capita cultivated land is 1.052 mu / person. The vast
majority of people affected by land acquisition will lose only part of their land. According to the
socio-economic survey, the situation of cultivated land before and after land acquisition in the
affected villages was compared and analyzed. Among the six affected villages, none of them lost
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 183
more than 25% of the land. The highest loss rate was 20.62% (Tiaokou group, Maotian village,
Yaodu town), and the lowest loss rate was 1.53% (huatuple, Maotian village, Yaodu town). In
general, the level of land loss in the villages affected by the project is very low. The agricultural
production and operation status of the investigated family is not affected by the land acquisition of
the project.
From the perspective of the income level of the surveyed households, the average income
level of the surveyed households was 69792 yuan in 2013 and 81100 yuan in 2019. The income of
the investigated families all increased.
Table 6-9 annual average income of families (yuan)
Village Xiayang Zhanggang Guanshan Maotian Average annual income per household
Year 2013 2019 2013 2019 2013 2019 2013 2019 2013 2019
Income
(yuan) 45575 59000 57400 68800 87700 96000 73429 87800 69792.07 81100.00
Figure 6-7 average income of each village household surveyed in 2013 and 2019 (yuan)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 184
Figure 6-8 average income of each village investigated (yuan)
6.5.2 Income source analysis
According to the survey, the construction industry, commerce and service industry are the
first income sources, followed by industry and food planting. This income structure shows that
along the G206 Dongliu Yaodu section, farmers' household income is no longer dominated by
agricultural production. Construction industry, commerce and service industry are the main
sources of farmers' income. See table 6-10 and 6-11 for the specific data of the income
composition of farmers' households in each village.
Table 6-10 distribution of income sources of surveyed households in 2013 and 2019 (yuan)
Food / crop
cultivation
Fishing or
poultry
keeping
Industry construction
industry
commerce and
service industry
Other
industry total
Xiayang
2013 9200 63 14625 4812 14375 2500 45575
2019 9300 0 20000 10700 17000 2000 59000
Zhanggang
2013 12818 0 15136 14545 13091 1818 57408
2019 14000 0 18000 19500 14400 2900 68800
Guanshan 2013 11950 0 13350 43600 16800 2000 87700
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 185
Food / crop
cultivation
Fishing or
poultry
keeping
Industry construction
industry
commerce and
service industry
Other
industry total
2019 13000 0 15500 46000 18900 2600 96000
Maotian 2013 12214 0 13929 31143 13286 2857 73429
2019 12800 0 16000 35000 19500 4500 87800
Pupolation
2013 11728 11 14110 27108 14507 2331 69794
2019 12375 3 14884 33700 16531 3128 80622
Figure 6-9 income sources of households surveyed in 2013 and 2019 (yuan)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 186
Figure 6-10 proportion of average income sources of households in the overall survey
for 2013 and 2019 (%)
Table 6-11 proportion of household income sources (5%)
Food / crop cultivation Fishing or poultry
keeping
Industry construction
industry
commerce and
service industry
Other
industry
2013 16.80 0.02 20.22 38.84 20.79 3.34
2019 15.35 0.00 18.46 41.80 20.50 3.88
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 187
Figure 6-11 proportion of average income sources of households surveyed in 2013, 2019 (yuan)
6.6 Subjective Evaluation of the Living Conditions of the Investigated
Families
6.6.1 Evaluation of Own Production Conditions
The evaluation of self production conditions can be divided into five grades: very good, good,
general, poor and very poor. Generally speaking, the majority of people hold "general", "good" and
"very good" opinions, and they do not hold a poor and very poor evaluation attitude towards their
own production conditions. Therefore, these two items are omitted in the following chart. With the
economic development, the proportion of residents who hold a "good" attitude towards their own
production conditions has increased, indicating that the residents are satisfied with the current
production conditions. See table 6-11for the specific situation.
Table 6-11 evaluation of the investigated families on their own production conditions (%)
Village Very good Good General total
Xiayang 2013 37.5 25 37.5 100
2019 37.5 37.5 25 100
Zhanggang 2013 0 100 0 100
2019 33.33 66.67 0 100
0
5
10
15
20
25
30
35
40
45
Grain crop Poultry Industry Architecture Business and
Service
Other
2013年 2019年
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 188
Guanshan 2013 0 40 60 100
2019 30.77 38.46 30.77 100
Maotian 2013 21.4 28.6 50 100
2019 28.57 35.72 35.71 100
Population 2013 13.50 45.41 41.09 100.00
2019 31.72 42.92 25.36 100.00
Figure 6-12 evaluation of production conditions of investigated families in each village (%)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 189
Figure 6-13 overall evaluation of production conditions of the surveyed families (%)
6.6.2 Evaluation of the Economic Situation of the Whole Village
The evaluation of their own economic situation is also divided into five grades, which belong
to the whole village: first-class, middle-class, middle-class, middle-class, and low-class. According
to the survey in April 2020, 97.73% of them are above average. See table 6-12 for details.
Table 6-12 evaluation of the economic status of the investigated families in the whole village (%)
Superior Upper-middle Middle Below-middle Inferior total
Xiayang 2013 12.5 12.5 62.5 12.5 0 100
2019 25 25 37.5 12.5 0 100
Zhanggang 2013 9.1 90.9 0 0 100
2019 33.33 66.67 100
Guanshan 2013 30 10 60 0 0 100
2019 38.46 28.57 32.97 100
Maotian 2013 0 28.6 64.3 7.1 0 100
2019 28.57 21.43 50 100
Population 2013 13.08 32.33 50.10 4.49 0 100.00
2019 31.82 33.44 32.47 2.27 0.00 100.00
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 190
Figure 6-14 evaluation of the economic situation of the investigated families in each village
Figure 6-15 evaluation of the overall economic status of the surveyed families
6.6.3 Assessment of current living environment
From the overall point of view, the assessment of the current living environment of the
surveyed families is generally good and good. Among them, the very poor level. With the
improvement and construction of national environmental requirements, the residents' environment
has been greatly improved. At present, there are no poor residents in the residential environment
assessment, so the list is no longer reflected. The overall evaluation is good. See table 6-13 for
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 191
details.
Table 6-13 assessment of current living environment of surveyed families (%)
Very good Good General Total
Xiayang 2013 25 50 25 100
2019 50 25 25 100
Zhanggang 2013 0 100 0 100
2019 55.56 44.44 0 100
Guanshan 2013 40 30 30 100
2019 46.15 30.77 23.08 100
Maotian 2013 21.4 28.6 50 100
2019 28.57 35.71 35.72 100
Population 2013 23.50 46.72 29.78 100.00
2019 43.18 34.09 22.73 100.00
Figure 6-16 evaluation of living environment of surveyed families in each village
6.6.4 Evaluation of Neighborhood Relationship
In the evaluation of neighborhood relationship, the poor evaluation of each sample village is 0,
and the poor proportion is the lowest. See table 6-14 for details.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 192
Table 6-14 evaluation of neighborhood relationship of surveyed families (%)
Very good Good General Poor total
Xiayang 2013 25 50 12.5 12.5 100.00
2019 50 25 12.5 12.5 100.00
Zhanggang2013 18.2 36.4 36.4 9 100.00
2019 44.44 33.33 22.22 0.00 100.00
Guanshan 2013 20 40 30 10 100.00
2019 30.77 46.15 15.38 7.69 100.00
Maotian 2013 21.4 42.9 28.6 7.1 100.00
2019 28.57 42.86 21.43 7.14 100.00
Population 2013 20.97 41.98 27.75 9.29 100.00
2019 36.36 38.64 18.18 6.82 100.00
Figure 6-17 evaluation of the relationship between themselves and their neighbors
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 193
Figure 6-18 the overall evaluation of the relationship between themselves and their neighbors
The evaluation of the relationship with the neighborhood has greatly improved the overall
quality of the residents compared with the previous ones because of the higher and higher cultural
education they have received. Among the sample villages surveyed in 2020, the highest proportion
was 12.5% in Kuanyang village, 7.69% in Guanshan village, 0% in Zhanggang village and 7.14%
in Maotian village. It is believed that 70% of them have a good relationship with their neighbors. It
can be seen that the investigated family has a good neighborhood relationship.
6.6.5 Evaluation of current life satisfaction
Overall, in 2019, 65.91% of the respondents were satisfied with their current life, 25% of
them were generally satisfied, and the overall evaluation was relatively high. In the overall sample,
7.69% of them were not satisfied with their current living conditions. In the sample survey
households, there were no samples that were very dissatisfied with their life satisfaction.
According to the survey, the dissatisfaction of the sample families is mainly caused by the high
level of material living and the high pressure of life. The main factors that lead to the high pressure
of life are the high cost of education for children, the large expenditure of human relationship, and
the great uncertainty of income. The overall satisfaction in 2019 is higher than that in 2013. See
table 6-16 for details.
Table 6-15 evaluation of life satisfaction of surveyed families (%)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 194
Very satisfied Satisfied General satisfied Dissatisfied Total
Xiayang 2013 12.50 37.50 25.00 25.00 100.00
2019 25.00 37.50 25.00 12.50 100.00
Zhanggang 2013 9.00 27.30 45.50 18.20 100.00
2019 33.33 44.44 11.11 11.12 100.00
Guanshan 2013 10.00 30.00 40.00 20.00 100.00
2019 23.08 46.15 23.08 7.69 100.00
Maotian 2013 7.20 35.70 35.70 21.40 100.00
2019 21.43 35.71 35.71 7.14 100.00
Population 2013 9.33 32.63 37.07 20.97 100.00
2019 25.00 40.91 25.00 9.09 100.00
Figure 6-19 evaluation of the family's life satisfaction
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 195
Figure 6-20 evaluation of the overall satisfaction of the surveyed families to their lives
In 2019, 25%, 37.5%, 25% and 12.5% of Panyang village were very satisfied, general
satisfied and dissatisfied with life; 33.33%, 44.44%, 11.11% and 11.12% of Zhanggang village
were very satisfied, general satisfied and dissatisfied with life; Guan Shan village was very
satisfied and satisfied with life 23.08%, 46.15%, 23.08% and 7.69% respectively were very
satisfied, satisfied, general satisfied and dissatisfied with life in Maotian village, 21.43%, 35.7%,
35.7% and 7.14% respectively.
7 Basic Assessment and Suggestions
7.1 Basic Assessment
1) The implementation agencies of each subproject of multimodal transport sustainable
transportation project can carry out the work in accordance with the resettlement action plan, and
pay attention to the policy publicity and public participation of resettlement. The resettlement
action plan has been well implemented.
2) The resettlement work of G206, S367 and Yimu road has been completed.
3) S319 resettlement is planned to be completed during the Spring Festival in 2020.
4) The land acquisition of Shuiyangjiang shipping comprehensive development project has
been completed, but the resettlement of relocated households has not been completed.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 196
5) According to the economic survey and analysis of G206 affected households, the negative
impact of G206 project construction on the affected households is relatively small, and the
economic income, living environment, etc. are increased or improved.
7.2 Basic Suggestions
1) The sub project implementation organization that has completed the resettlement work
shall prepare the resettlement summary report in time, so as to summarize the resettlement
summary report of the whole multimodal transport project.
2) The implementation agency shall continue to pay attention to the living standard and
income recovery of the affected households after resettlement, and ensure that the living standard
and income of the affected households are not lower than the level before the implementation of
the project.
3) The implementation organization of the second military road of S319 in Wuwei County
should properly settle the relocated households as soon as possible, and prevent and timely deal
with the problems that may occur during the period of waiting for the completion of the
resettlement community.
4) The construction of 319 phase II project may involve the households affected by land
acquisition and demolition. It is suggested that the external monitoring of resettlement of phase II
construction project be combined with the construction project of S319 Erba Wuwei section for
external monitoring.
5) The relocation households of the comprehensive wharf of Shuiyangjiang shipping
comprehensive development project have not completed the resettlement. The project
implementation agency actively coordinates with the local government to promote the construction
progress of "Huishang No.1" resettlement site. Resettle the relocated households as soon as
possible.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 197
8 Attachments
Attachment 1: Project Location Diagram
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 198
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 199
Attachment 2: G206 Project Approval of constrution land issued by Anhui provincial government
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 200
Attachment 3: Approval of Construction Land for Road S319 Erba to Wuwei Section Reconstruction Project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 201
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 202
Attachment 4: Notice on establishment of project resettlement office
(1) Otice on establishment of Chizhou Municipal project
resettlement office
(2) Notice on establishment of Dongzhi County project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 203
resettlement office
(3) Assignment of responsibilities in G206 PMO
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 204
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 205
Attachment 5: Report on the Establishment of S319 Construction
Headquarters in Wuwei County
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 206
Attachment 6: foundation file of anhui Jiaoyuan engineering project
management limited company
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 207
Attachment 7: Agreements On Land Acquisition
G206 Project Compensation for land acquisition agreement
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 208
S319 Project compensation agreement
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 209
Attachment 8: Agreements on Land Acquisition of Forest Farm for G205 Project
(1)Land acquisition agreement on permanent woodland of
Jinsishan forest farm
(2)Land acquisition agreement on temporary woodland of
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 210
Meicheng forest farm
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 211
Attachment 9: Staff Meeting File of Forest Farm
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 212
Attachment 10: Lease contract on mixing plant ground in lishan working area
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 213
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 214
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 215
Attachment 11: Rental Agreement on Temporary Land Use for Mixing Plant in S319 signed by Road and Port Group
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 216
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 217
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 218
Attachment 12: housing lease contract of project management department in contract 01
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 219
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 220
Attachment 13: Rental Contract of Project Management Department Signed by Road and Port Group
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 221
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 222
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 223
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 224
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 225
Attachment 14: Housing lease contract of project management department
in contract 02 of G206 Project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 226
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 227
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 228
Attachment 15: Housing lease contract of S319 Project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 229
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 230
Attachment 16: G206 Project housing lease contract of maintenance center
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 231
Attachment 17: G206 Compensation agreement for house demolition
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 232
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 233
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 234
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 235
Attachment 18: Compensation agreement for power lines reconstruction project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 236
Attachment 19: G206 Project Compensation agreement for communications trunk cables relocation project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 237
Attachment 20: G206 Project Water migration agreement
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 238
Attachment 21: G206 Project Forestry land compensation supplemental agreement
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 239
Attachment 22: G206 Project Statistics of water conservancy project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 240
Attachment 23: G206 Project River restoration task decomposition table
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 241
River Restoration Task Decomposition Table for G206 Dongliu to Yaodu Section
Construction Component
2015.1.20
No. Pile No.and place Existing problems Treatment opinions,
suggestions Deadline
Responsible
organizations
Contact person
for
coordination
1
Xiayang Village
K0+130-K0+220,
K0+330-K0+580,
K0+730-K0+980
Water system in the
section is destroyed,
should be restored Carry out temporary recovery for
Contract 1
Restored
properly
before the
Spring Festival
Project Office Road
and Bridge
Company
Wang Qianchun,
Han Xiuyu
2 Zhanggang Village
K2+70-K3+510
Water system in the
section is destroyed,
plus dredgingff 3 hilly
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 242
ponds
3
Seven places including
Xiaohuangni Lake,
Zetanwei
New station, water
gate reconstruction,
recovery of pond weirs
Reconstruction of outlet sluice
station at Zetanwei commenced
in 2014, construction of new inlet
sluice station commenced, the
rest design has been completed
Completed
before flood
season
Water Bureau
Ruan Zhonghua,
Ling Guoping 4
At Xiaohuangni Lake,
Guanshan Village
Recovery of excavated
Xiaohuangni Lake dam
before flood season
After capping beam is
completed, Contract 1 should be
restored timely according to
water level situation
Completed
before flood
season
Project Office Road
and Port Company
5
At the border of
viaduct and Quanshui
Lake dam in Zhaqiao
Recovery of the
excavated part
Construction scheduling of
Contract 1
Completed
before flood
season
Project Office Road
and Bridge
Company
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 243
Village
6 At Quanshui Lake in
Zhaqiao Village
Cofferdam in the lake
is not constructed
properly
Immediate organization of
construction for Contract 1
properly
At the end of
January
7
Lishan Avenue to
railway bridge in
Maotian Village
Sequential connection
of large area drainage
at Zetangwei
Temporary recovery of Contract 2 Before the
Spring Festival
Project Office Road
and Port Company
8 Near railway bridge in
Jiandong Village
Recovery of Shiyin
Group electric
pumping station
switch room, cable
facilities
Recovery of the sites selected in
towns and villages
Before spring
ploughing Yaodu Town
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 244
9
Railway bridge to
Mt.Daqing in Jiandong
Village
Sequential connection
of water system, road Temporary recovery of Contract 2
Before the
Spring Festival
Project Office Road
and Port Company
10
At south end of
Mt.Daqing in Maotian
Village
Tangfan Pond
drainage culvert
connection
Temporary recovery of Contract 2 At the end of
January
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 245
Attachment 24: Minutes of Meeting of Coordination Meeting for Pipeline Relocation of S319 Project.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 246
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 247
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 248
Attachment 25: Approval of Construction Land Use for Nanling Yimu Highway Project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 249
Attachment 26: Notice on establishment of Nanling County project resettlement office
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 250
Attachment 27: Notice on establishment of Shuiyang River project
resettlement office
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 251
Attachment 28: Housing lease contract of Nanling Contract 01
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 252
Attachment 29: Housing lease contract of Nanling Contract 02
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 253
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 254
Attachment 30:Notification Concerning the Compensation Scheme of House Demolition On Collective Land in
Jishan Town, Gongshan Town
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 255
Attachment 31: Agreement on the Compensation of Young Crops for
Nanling Yimu Highway
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 256
Attachment 32:Compensation Agreement On Land Acquisition in Nanling
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 257
Attachment 33 Notice On Establishment of S367 Hanshan Section
Reconstruction Project Resettlement Office
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 258
Attachment 34 Agreement On Land Acquisition for S367
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 259
Attachment 35: Compensation Standard for House Demolition On
Collective Land and Above-Ground Attachments, and Compensation Standard
for Young Crops in Xuanzhou District
Compensation Standard for House Demolition On Collective Land (Table 1)
Unit: Yuan/㎡
Category
Class House structure and standard
Basic
price
Composite
structure
1
Reinforced concrete beam, column, solid brick wall, flat roof or
tiled roof, flat roof ceiling, complete doors, windows, water,
electricity, kitchen, washroom, cement ground
900
2
Reinforced concrete beam, column, single, dual wall, flat roof or
tiled roof, simple ceiling, complete doors, windows, water,
electricity, kitchen, washroom, cement ground
850
Masonry-timber
structure
1
Load bearing brick wall, wooden roof truss, tiled roof, cement or
wooden floor, solid brick wall, flat roof ceiling, complete doors,
windows, water, electricity, kitchen, washroom, above two rooms
(including 2 storeys, storey height is above 2.8m) one-off design,
synchronous construction
800
2 Cement or timber purlin, cement or wooden floor, single, dual
wall, flat tile roofing, smooth ceiling, with utilities 730
3 Mixed bamboo and timber purlins, three-ply wood and simple
cement ground, single wall, flat tile roofing, smooth ceiling, with
utilities
650
Simple structure
1
Irregular roof truss, bamboo and wood base course, thatched, tile
or asbestos roof, adobe, broken brick and other simple walls,
simple ground, with electricity, eaves height above 2.2m
300
2 Irregular roof truss, bamboo and wood base course, thatched, tile
or asbestos roof, adobe, broken brick and other simple walls,
simple ground, with electricity, eaves height below 2.2 m
200
Compensation Standards for House Demolition On the Collective Land
Acquired and Temporary Relocation (Table 2)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 260
Category Subsidy standard Remarks
Transition subsidy for demolition
(relocation expense, transition
subsidy)
500 Yuan/person
One-off subsidy according to
the population registered on
the residence booklet
Compensation for
shutdown loss
Business
house
Calculate according to 20
Yuan/㎡/month for
building area of principal
room
Time should be calculated
according to three to six
months, no more than six
months at the most
Production
house
Calculate according to 10
Yuan/㎡/month for
building area of principal
room
Office house
Calculate according to 5
Yuan/㎡/month for
building area of principal
room
Note: 1. Business house and production house must have business license and tax
registration certificate before the release of demolition announcement, and only monetized
resettlement is possible. If residence is changed to business house or production house without
approval of the planning department, compensation and resettlement will be performed according
to residential houses uniformly.
2. For demolition of leased (borrowed) house, the owner of the leased (borrowed) house shall
terminate the lease relationship with the rental household. If rental households lease the houses of
the AHs for commercial production, processing and other production activities, the AHs shall be
responsible for the relocation, the demolition party will not compensate relocation cost of the
production facilities.
Compensation Standard for Young Crop on the Collective Land Acquired
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 261
(Table 3)
Unit: Yuan/mu
Category of land Paddy field Dry land Remarks
Compensation standard 1000 800
Notes: Compensation for young crops should be released to the owner of the young crops.
Compensation Standards for Demolition of House Attachments and Decoration
On the Collective Land Acquired (Table 4)
Name Specification Compensation
amount Remarks
Loft
Formal Eaves height above
1.8m 150 Yuan/㎡
With fixed wooden or
masonry stairs Common
Eaves height below 1.
8 m, 1.5 100 Yuan/㎡
Simple Eaves height below 1.
5 m, above 1m 30 Yuan/㎡
Enclosing
wall
Simple enclosing
wall
Fence, bamboo
enclosing wall 30 Yuan/㎡
Masonry
enclosing wall 50 Yuan/㎡
Electricity meter 150
Yuan/piece
Water meter 200
Yuan/piece
Balcony
Self-enclosed
aluminum alloy
windows
200 Yuan/㎡ No compensation for those
already included into the
compensation area for
demolition Self-enclosed
plastic-steel
window
250 Yuan/㎡
Door Iron gate 30 Yuan/㎡
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 262
Name Specification Compensation
amount Remarks
Roller shutter
door 50 Yuan/㎡
Security door 450
yuan/piece
Outdoor
ground
Cement floor 40 Yuan/㎡
Masonry ground 25 Yuan/㎡
Decoration ground
Floor tiles, terrazzo
and other veneer 60 Yuan/㎡
Marble, granite
veneer 70 Yuan/㎡
Crushed material veneer 20
Yuan/㎡
Decoration ceiling
Three-ply board,
plastic pinch plate,
gypsum suspended
ceiling
30 Yuan/㎡
No compensation for roof
ceiling, suspended ceiling
etc
Decoration wall surface
Three-ply board,
plastic pinch plate
wainscot, latex paint
20 Yuan/㎡
White ceramic tile,
wall tile, dimension
stone and other veneer
30 Yuan/㎡ Internal wall
20 Yuan/㎡ Outside wall
Simple shed 20 Yuan/㎡
Stove
Single stove 200
Yuan/piece Including tiling on the
stove surface Double stove
400
Yuan/piece
Pool 50 Yuan/piece
Retaining wall Within 2 60 Yuan/㎡
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 263
Name Specification Compensation
amount Remarks
Above 2 85 Yuan/㎡
Bathtub 300/piece Including facing tile
Bath pot 500
Yuan/piece Including facing tile
Telephone replacement cost 30 Yuan/unit
One-off compensation 200 Yuan as replacement cost of CATV, tap water.
Air-conditioner Window type 100 Yuan/set Replacement cost
Split wall-hanging 150 Yuan/unit Replacement cost
Water heater
Solar energy 300 Yuan/unit Replacement cost
Indoor gas water
heater 100 Yuan/set Replacement cost
Electric water heater 100 Yuan/set Replacement cost
Kitchen ventilator 100 Yuan/set
Compensation Standard for Above-Ground Attachments On Collective Land
Within Recent Construction Scope in Xuanzhou District (Table 5)
Category Unit Standard Notes
Tomb
Yuan/coffin
Cement structure double coffin
and above 800
Unkown tombs are relocated
or buried by the affected unit
instead.
Cement structure single coffin,
earth grave structure double coffin
and above 600
Earth grave structure single coffin
400
Water well
Yuan/piece
Brickup water well 2000
No compensation for
abandoned well Pumping well 600
Hand-operated pumping well 500
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 264
Category Unit Standard Notes
Biogas digester
Yuan/piece
Cement concrete structure 2000,
brick-concrete 800
Masonry manure
pit
Yuan/piece 500
Dejecta cylinder Yuan/dan
50 Yuan if below 3 dans, 100
Yuan if above 3 dans (including 3
dans)
Greenhouse for
crop cultivation Yuan/
Bamboo frame 8 Top height above 2m
Steel frame 12
Fishpond Yuan/mu
2000 Intensive culture fish pond
(yield per mu above 250 kg)
1000 Extensive culture fish pond
(yield per mu below 250 kg)
Compensation Standard for Above-Ground Trees On the Collective Land
Acquired (Table 6)
Category Unit Compensation
standard Remarks
Tea garden
Yuan/mu
3000 Mature tea garden (tea garden over 3 years,
Including 3 years)
2000 Young tea garden (tea garden less than three
years)
Mulberry
field
Yuan/mu
3000
Mature mulberry field (mulberry field over 2
years,
Include 2 years)
2000 Young mulberry field (mulberry field less than 2
years)
Timber forest
(vast)
Yuan/mu
Immature forest 1000
Refers to general afforestation planted on land
for farm use Young forest 2000
Half-mature forest
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 265
Category Unit Compensation
standard Remarks
and above 1500
Economic
fruit forest
(vast)
Yuan/mu
Immature forest 2000
Refers to economic fruit forest planted on land
for farm use
Vegetative season
4000
Maturation stage
6000
Bamboo
forest
Yuan/mu
Sundry bamboo 1100
Moso bamboo 2200
Green
seedlings
(vast)
Yuan/mu
2000(diameter below
5cm)
Refers to the nursery stock planted on land for
farm use, diameter is measured at 1.3 m above the
ground.
3000(diameter below
5-10cm)
4000(diameter below
10-15cm)
5000(diameter below
15-20cm)
6000(diameter above
20cm)
Note: scattered trees, compensation price of each tree should be converted with reference to
technical standard density of forestry industry for vast afforestation.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 266
Attachment 36: Compensation Standard for House Demolition in the
Collective Land Acquired Within the Scope of Urban Planning Area of
Xuancheng City
Compensation Standard for House Demolition On the Collective Land
Acquired (Table 1)
Unit: Yuan/㎡
Category Class House structure and standard Basic
Price
Composite
structure
1
Reinforced concrete beam, column, solid brick wall, flat roof
or tiled roof. Plane ceiling, complete doors, windows, water,
electricity, kitchen, washroom, cement ground.
950
2
Reinforced concrete beam, column, single, dual wall, flat
roof or tiled roof. Simple ceiling door/window, water,
electricity, kitchen, washroom complete, cement ground.
900
Masonry-timber
Structure
1
Load bearing brick wall, wooden roof truss, tiled roof,
cement or wooden floor, solid wall body, flat roof ceiling,
complete doors, windows, water, electricity, kitchen,
washroom, two storeys and above (including two storeys,
storey height is above 2.8 m) one-off design, synchronous
construction.
830
2
Cement or timber purlin, cement or wooden floor, single,
dual wall, flat tile roofing, smooth ceiling, with water,
electricity utilities.
760
3
Mixed bamboo and timber purlins, trinity mixture fill or
simple cement ground, single wall, flat tile roofing, with
water, electricity utilities.
680
Simple
Structure
1
Irregular roof truss, bamboo and wood base course, thatch,
tile or asbestos tiled roof, adobe, broken brick or other simple
walls. Simple ground, with electricity, cornice height above
2.2m.
320
2 Irregular roof truss, bamboo and wood base course, thatch,
tile or asbestos tiled roof, adobe, broken brick or other simple
walls. Simple ground, with electricity, cornice height below
220
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 267
Category Class House structure and standard Basic
Price
2.2 m.
Note: with respect to loft, basement, open floor, spring layer etc that were constructed
together with the house at one time, execute 50% of this standard for the part of storey height
1.5-2.2m, execute 25% of this standard for the part of storey height below 1.5m.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 268
Housing Location Value (Table 2)
Unit: Yuan/㎡
Location
category
Scope
Residence
Office,
production
storage
house
Classification areas
Category
1
Zhongshanxi
Road-Jingting
Road-Daocha
River-Wanxi
River-Meixi
Road-Zhaotingzhong
Road
1800 1200
Class 1: Lingxi Road-Aofeng
Road-Wanxi River-Zhongshan
Road
1710 1140 Class 2: area of Category 1
deducting the area of Class 1
Category
2
Shuiyangjiang
Avenue-Wangan
Railway (excluding
Category 1 area
1470 980
Class 1: Wanlingxi
Road-Yourong Road-Jixian
Road-Xiegong Road-Shuangta
Road-Wangan
Railway-Tonggong
Road-Wanxinan
Road-Xiangshan
Road-Shuiyangjiangnan
Avenue-Jiutong
Road-Meiyuan Road-Jingde
Road-Meixi Road (excluding
Category 1 area)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 269
1390 930
Class 2: ① Meiyuan
Road-Jiutong
Road-Shuiyangjiang
Avenue-Jingde Road ②
Meiyuan Road-Baocheng
Road-Jialexiang-Shitao
Road-Qushan Road-Shuangta
Road-Xiegong Road-Jixian
Road-Yourong Road-Wanlingxi
Road-Meixi Road-Jingde Road
③ Xiegong
Road-Shuiyangjiang
Avenue-Wangan
Railway-Wanxi River-Shuangta
Road ④ Xiangshan
Road-Wanxinan
Road-Tonggong Road-Wangan
Railway-Shuiyangjiangnan
Avenue
1310 880
Class 3: the area in Category 2
deducting the areas of Class 1
and Class 2
Category
3
Xuanhang
Expressway-Fengcui
Road-Shuiyang River
(excluding the areas
of Category 1 and
Category 2)
1170 780
Class 1: ① Shuiyangjiangnan
Avenue-Xiangyang
Avenue-Xuanhang
Expressway-Qingxi
Road-Hongyue Avenue-Yuhe
Road-Xuanhang
Expressway-Xingye
Road-Hongyue Avenue-Meixi
Road-Wenchang
Road-Shuiyangjiangxi Avenue
② Wangan
Railway-Shuiyangjiangdong
Avenue-Shuiyang River
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 270
1030 690
Class 2: ① Xuanhang
Expressway-Guiling
Road-Hongyue Avenue-Xingye
Road ② Xuanhang
Expressway-Yuhe
Road-Hongyue Avenue-Qingxi
Road ③ Xiangyang
Avenue-Shuiyangjiang
Avenue-Yushan
Road-Xuanhang Expressway
④ Jingtingshan Mountain
South Landscape Coordination
Area (according to general
planning of Jingtingshan
Mountain)
830 560
Class 3: the area of Category 3
area deducting the areas of
Class 1 and Class 2
Category
4
Within Qingyijiang
Avenue (excluding the
areas of Category 1,
Category 2 Category
3)+ Shuangqiao Group
development land
scope
630 420
Class 1: ①construction land
scope of Xuanzhou Economic
Development Zone (road
network enclosure scope)②
Fengcui Road-Xuanhang
Expressway-Xuannantong
Expressway ③ Rixin
Road-Qingyijiangxi
Avenue-Fenggong
Avenue-Wushapu
Road-Chuangxin Road ④
Houde Road-Wenjing
Road-Xingzhi Road-Shengyu
Road ⑤ Shuangqiao Group
Wanlingdong Road-Niwan
Road-Aofengdong Road-Liren
Street ⑥ Xiadu Group
construction land scope
520 350
Class 2: the area in Category 4
area deducting the areas of
Class 1 and Class 3
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 271
410 280
Class 3: Shuiyang
River-Qingyijiangnan
Avenue-Lingyang
Road-Aofengdong Road-Niwan
Road-Wanlingdong
Road-Kuaisudong
Road-Qingyijiangbei
Avenue-Shoude
Road-Changyan
Road-Zhaotingbei
Road-Xuannantong
Expressway
Category
5
Outside Qingyijiang
Avenue, within the
scope of urban
planning area
300 200
Class 1: ①town construction
land scope of Tianhu
Neighborhood ② town
construction land scope of Jinba
Neighborhood③town
construction land scope of
Xiangyang Town ④ Wutunxi
Road-West Outer
Ring-Wutundong Road
(including town construction
land scope of Sunbu Town)⑤
town construction land scope of
Wuxing Township ⑥town
construction land scope of
Guquan Town ⑦ Qingyijiangxi
Avenue-Qingbo
Road-Changqiao Road-Qixiu
Road
120 80
Class 2: the area in Category 5
area deducting the area of Class
1
Note: non-residential housing should be identified according to the purpose
indicated on the property ownership certificate.
Compensation Standard for Ancillary Facilities of the House (Table
3)
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 272
Item
Compensation
amount (unit
price)
Remarks
Power supply
Electricity
meter
380
Yuan/household
1.5 to 20A (included), single-phase,
separate account
2000
Yuan/household
20A to 60A, three-phase, separate
account
150
Yuan/household
Single-phase time-sharing electricity
meter
600
Yuan/household
Three-phase time-sharing electricity
meter
60
Yuan/household Submeter
Transformer
(including
affiliated
pipeline)
6000 Yuan/unit Up to 315KVA (included), relocation
subsidy
7000 Yuan/unit 315 to 630KVA (included), relocation
subsidy
8000 Yuan/unit Above 630KVA, relocation subsidy
Water supply
Main water
meter
(separate
account)
700 Yuan/piece Retail private investor, one meter per
household
Submeter 50 Yuan/piece
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 273
Item
Compensation
amount (unit
price)
Remarks
Gas supply Pipe gas 2700
Yuan/household One meter per household
Communication
CATV 100
Yuan/household Replacement cost
Telephone,
broadband
network
8 Yuan/door Replacement cost
Air-conditioner
Split 200 Yuan/unit Replacement cost
Window type 150 Yuan/unit Replacement cost
Central
air-conditioner100 Yuan/KW
Calculate according to rated cooling
input power
Water heater
Solar energy 3 50 Yuan/piece
Subsidies for relocation and
installation Electricity 100 Yuan/piece
Gas 100 Yuan/piece
Outdoor ground
Cement 40 Yuan/㎡
Masonry 25 Yuan/㎡
Enclosing wall
Hollow 50 Yuan/㎡
Masonry 60 Yuan/㎡
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 274
Item
Compensation
amount (unit
price)
Remarks
Simple earth,
fence 10 Yuan/㎡
Kitchen range
Single stove
stove 200 Yuan/piece
Add 50 Yuan for every increase of
one,
Productive
stove 700 Yuan/piece
Sanitary
facilities
Bathtub 500 Yuan/set
Water closet 300 Yuan/piece
Squatting pan 200 Yuan/piece
Wash basin 80 Yuan/piece
Septic tank 100 Yuan/m³
Biogas
digester 2000 Yuan/set
Abandoned pool subsidy 500
Yuan/set
Other
Exterior balcony
PVC, plastic-steel
door window
180 Yuan/㎡ Subsidy for self-enclosure
Exterior
balcony
aluminum
alloy
160 Yuan/㎡ Subsidy for self-enclosure
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 275
Item
Compensation
amount (unit
price)
Remarks
door/window
Exterior
balcony
wooden doors
and windows
50 Yuan/㎡ Subsidy for self-enclosure
Iron gate 30 Yuan/㎡
Roller shutter
door 50 Yuan/㎡
Burglar mesh 30 Yuan/㎡
Security door 450 yuan/piece
Common
wooden door 300 Yuan/frame
Finished suit
door 700 Yuan/frame
Boiler 3 Yuan/kg Subsidies for relocation and
installation
Kitchen
ventilator 100 Yuan/piece
Subsidies for relocation and
installation
Water pool, 50 Yuan/piece
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 276
Item
Compensation
amount (unit
price)
Remarks
coal pool
Brick water
well
2000
Yuan/piece
Pressure well 500 Yuan/piece
Fire pool, bath
pool 100 Yuan/m³
Canopy, cover
for protect
rains
20 Yuan/㎡
Insulation
layer
30 Yuan/㎡ Simple
60 Yuan/㎡
Note: for unlisted ancillary facilities, compensation should be given with reference to
similar facilities in the table, or compensation should be given according to the
replacement price in combination with the degree of newness.
Compensation Standard for House Decoration (Table 4)
Name
Compensation
amount
(unit price)
Remarks
Ground Painted ground 15 Yuan/㎡
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 277
Name
Compensation
amount
(unit price)
Remarks
Terrazzo, artificial
stone 40 Yuan/㎡ Various floor tile grounds
Floor tile 60 Yuan/㎡
Laminate wood
flooring 40 Yuan/㎡
Wood floor
80 Yuan/㎡ General wood flooring
140 Yuan/㎡ No paint, solid wood flooring
without planing
Dimension stone
ground 100 Yuan/㎡
Marble (granite) material,
excluding artificial stone
Indoor
decoration
Calcium plastic,
ceramic simulating
wall surface
20 Yuan/㎡
Three-ply board,
ceramic tile wainscot 30 Yuan/㎡
Soft/hard enveloped
wooden wainscot 50 Yuan/㎡
Plastic sprayed wall
surface 15 Yuan/㎡
Fine and smooth surface,
without the sense of
concave-convex
Latex paint wall
surface 15 Yuan/㎡
Wallpaper 25 Yuan/㎡
Unmovable fixed wall
cabinet 300 Yuan/㎡
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 278
Name
Compensation
amount
(unit price)
Remarks
Fiber, calcium plastic,
plasterboard 30 Yuan/㎡ Hard ceiling
Wood suspended
ceiling 50 Yuan/㎡ Hard ceiling
Subsidy Standard for Transplanting of Trees (Table 5)
Category
Diameter
(measured at 1.3 m
from the ground)
Compensation
amount (unit price)Remarks
General
Trees
2cm-5cm 10 Yuan/tree 1. This standard is only applicable to
trees in house sites;
2. Landscape trees should be
compensated with reference to the
standard for fruit tree;
3. No compensation for the flowers
and grass, nursery stock, trees planted
after the announcement was released.
5cm-10cm 30 Yuan/tree
Above 10cm 50 Yuan/tree
Fruit
tree
2cm-5cm 50 Yuan/tree
5cm-10cm 100 Yuan/tree
Above 10cm 200 Yuan/tree
Moving Cost Standard
I. Cash compensation
1. Residential housing: standard is 8 Yuan/㎡, no lower than 500 Yuan, moving cost
is given at one time.
2. Non-residential housing: moving cost is given at one time according to 10 Yuan/㎡
for the certified building area of the house; if there is any large-scale equipment,
calculate according to the freight transport price at that time.
II. Property swap
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 279
1. Subsidy should be released according to the above-mentioned provisions for
resettlement in existing housing;
2. Moving cost will be paid twice for resettlement in forward delivery housing
according to the above-mentioned provisions.
Standard for Temporary Resettlement Cost of Residential Housing
(Table 6)
Unit: Yuan/㎡ · month
Location Category 1
area
Category 2
area
Category 3
area
Category 4
area
Category 5
area
Subsidy
standard 10 9 8 7 6
1. For cash compensation, subsidy will be released for 6 months according to the
above-mentioned provisions.
2. For property swap:
(1) with respect to resettlement in existing housing, subsidy will be released for 4
months according to the above-mentioned provisions.
(2) with respect to resettlement in forward delivery housing, if the APs arrange
transition by themselves, and are resettled in 18 months, subsidy will be released for
the duration from the month moving out to the time of resettlement according to the
above-mentioned standards; if the APs are not resettled in more than 18 months, the
acquisition party should pay transition subsidy according to twice of the standard
from the overdue month untill the time of resettlement.
Transition subsidy should still be paid for 4 months according to the standard since
resettlement is realized.
(3) Transition subsidy will not be paid if house acquisition department provides
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 280
transitional housing; If resettlement is not realized after 18 months, transition subsidy
should be paid according to the standard from the overdue month until 4 months after
the resettlement is realized.
Subsidy Standard for Shutdown Loss of Non-Residential Housing
(Table 7)
Unit: Yuan/㎡•month
Location standard Category 1
Area
Category 2
Area
Category 3
Area
Category 4
Area
Category 5
Area
Business house 35 30 25 20 15
Office house 12 11 10 9 8
Production house 16 15 14 13 12
Storage house 9 8 7 6 5
Note: shutdown loss of non-residential housing should be calculated
according to the certified area, and should be paid for 6 months according
to the above-mentioned standards.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 281
Additional Area Comparison Table for Transregional Resettlement (Table 8)
Unit: ㎡
Incentive Standard for House Demolition
If the APs sign compensation and resettlement agreement for the house
demolition, and hand over the housing at the house demolition incentive stage,
maximum incentive should not exceed 100 Yuan/㎡ based on the incentive area
calculated according to these provisions.
Location
category
standard
Category 1
area
Category 2
area
Category 3
area
Category 4
area
Category 5
area
Category 1 area 0 +10% +20% +30% +50%
Category 2 area -- 0 +5% +10% +20%
Category 3 area -- -- 0 +5% +10%
Category 4 area -- -- -- 0 +5%
Category 5 area -- -- -- -- 0
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 282
Attachment 37: Official Reply to the Construction
Land for S367 Project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 283
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 284
Appendix 38: Ma An Shan Public Participation and Minutes
for S367 project
Date September 9, 2012
Place
Land and Resources Bureau of Shanhou Town, He County
Organizer He county Transportation Bureau
Participants
He County Transportation Bureau, Shanhou Town Land Bureau, Hehai
University
Topic Resettlement impact and compensation as well as resettlement policies of
Shanhou Town
Main content
(1) Implementing《the Notice of the People’s Government of Anhui Province
Adjusting on the Compensation Standards for Land Acquisition》(Wan Zheng
[2012] 67).
(2) The resettlement is decided by the affected villages through the villagers'
meeting.
Date September 9, 2012
Place Xianzhang Town, Hanshan County
Organizer
Hanshan County Transportation Bureau
Participants
Hanshan County Transportation Bureau, Hehai University, design unit,
Xianzhang Town, affected villages
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 285
Topic
Affected scope of the project, attitudes of affected villagers, house
demolition and resettlement plan
Main content
1) The project affects Jianghuai Village of Xianzou Town, and the affected
villagers supported the project; 2) House demolition and resettlement is
collectively planned by the village , and houses built by the affected
households
Date September 17, 2012
Place Land and Resources Bureau of Hanshan County
Organizer
Hanshan County Transportation Bureau
Participants
Hanshan County Transportation Bureau, Hohai University, Hanshan County
Land and Resources Bureau
Topic
Resettlement impact and compensation and resettlement policies of Hanshan
County
Main content
(1) Implementing《the Notice of the People’s Government of Anhui Province
Adjusting on the Compensation Standards for Land Acquisition》(Wan Zheng
[2012] 67).
(2) The resettlement is decided by the affected villages through the villagers'
meeting.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 286
Date September 19, 2012
Place
Jianghuai Village, Xianzu Town, Hanshan County
Organizer Hanshan County Transportation Bureau
Participants
Hanshan County Transportation Bureau, Hehai University, Xianzhang Town
of Hanshan County, and representatives of affected villagers
Topic Consultation on land acquisition and restoration plan
Main content
1) The compensation for land acquisition directly compensated to the affected
households without any land adjustment;
2) Some affected households hope to use the opportunities to do some small
businesses related to tourism, such as catering, car wash services,
farmhouses, etc.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 287
Date September 17, 2012
Place He county Land and Resources Bureau
Organizer He county Transportation Bureau
Participants
He county Transportation Bureau, Hehai University, He county Land and
Resources Bureau
Topic Resettlement impact of He County and compensation and resettlement
policies
Main content
(1) Implementing《the Notice of the People’s Government of Anhui Province
Adjusting on the Compensation Standards for Land Acquisition》(Wan Zheng
[2012] 67).
(2) The resettlement is decided by the affected villages through the villagers'
meeting.
Date September 19, 2012
Place zhongshan Village, Shiyang Town, He County
Organizer
He county Transportation Bureau
Participants
He County Transportation Bureau, Hehai University, Shiyang Town of He
County, and representatives of villagers
Topic Negotiation of Demolition and resettlement and income restoration
Main content
1) The compensation for land acquisition are directly compensated to the
affected households without any land adjustment.
2) Some affected households hope to use the opportunities to do some small
businesses related to tourism, such as catering and car wash services.
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 288
3) subsidies can be provide to the villagers through the restoration of
temporary land occupation.
4) House demolition will be planned by the village collectively and the
affected households will build their own houses
Date
December 8, 2014
Place Taodian Village, Shanhou Town, He County
Organizer He county Transportation Bureau
Participants
He county Transportation Bureau, Hehai University, Taodian staff,
representatives of affected villagers
Topic Negotiation of Demolition and resettlement and income restoration
Main content
1) The compensation for land acquisition are directly compensated to the
affected households without any land adjustment.
2) Some affected households hope to use the opportunities to do some small
businesses related to tourism, such as catering and car wash services.
3) subsidies can be provide to the villagers through the restoration of
temporary land occupation.
4) House demolition will be planned by the village collectively and the
affected households will build their own houses
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 289
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 290
Appendix 39: Compensation Standard on Wuwei
County of S319 approved by Wuhu City Government
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 291
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 292
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 293
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 294
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 295
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 296
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 297
Appendix 40: House Demolition Agreement of S319
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 298
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 299
Appendix 41: The establishment of Nanling Organization
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 300
Appendix 42: Permanent Agreement of Land Acquisition of S319 Project
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 301
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 302
Appendix 43: Compensation of Demolition House and Resettlement Agreement of S367
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 303
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 304
Appendix 44:Acquisition Agreement of Land S367
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 305
Appendix 45: Compensation of Demolition House and Resettlement Agreement of Yimu Road
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 306
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 307
Appendix 46: Land Acquisition Agreement of Yimu Highway
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 308
Appendix 47: Group Purchase Agreement of Huishang Century
City
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 309
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 310
Appendix 47: Notification of winning the bid for the Resettlement House of
Xiaohekouqiao Pottery Factory
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11
Anhui Communications Vocational&Technical College - 311
Appendix:48: Demolition agreement of Non-residential house and operation house compensation for reconstruction
Kedian to Mujiating section of Yimu Highway in Nanling County
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 312
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 313
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 314
Appendix 49: Record Form of Resettlement House for Xiaohekouqiao Pottery
Factory
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring
Report (11th Report)
Anhui Communications Vocational&Technical College - 315
Appendix 50: Shuiyangjiang Waterway Dredging and Dam Project
Approved by Xuancheng People's Government
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 316
Appendix 51: Evaluation Report on New State-owned Land Acquisition for the Reconstruction Project from Kedian to
Mujiating Section of Yimu Highway in Nanling County
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 317
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 318
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 319
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 320
Appendix 52: Resettlement Transition Fee for Demolition of Xuanzhou
Port Wharf
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 321
ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)
Anhui Communications Vocational&Technical College - 322
Appendix 53: The transition fee for Vouchers resettlement of Xiaohekou
Bridge