Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project...

323
Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project - Resettlement Monitoring Report Prepared by Anhui Zhenhua Comprehensive Transport Research Institute of Anhui Communications Vocational and Technical College for the Anhui Provincial Government and the Asian Development Bank This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Transcript of Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project...

Page 1: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

Social Monitoring Report Project Number: 45021-002 August 2020

PRC: Anhui Intermodal Sustainable Transport Project - Resettlement Monitoring Report

Prepared by Anhui Zhenhua Comprehensive Transport Research Institute of Anhui Communications Vocational and Technical College for the Anhui Provincial Government and the Asian Development Bank This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 1 -

Anhui Intermodal Sustainable Transport

Development Project

External Resettlement Monitoring Report

(11th Report)

Anhui Communications Vocational & Technical College

August 2020

ADB-financed

Page 3: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 2 -

目录

Notes for the Updated Monitoring Report ......................................................................................................................... - 9 -

1 Overview ......................................................................................................................................................................... - 13 -

1.1 Project Overview ................................................................................................................................................... - 13 -

1.1.1 G206 Dongliu to Yaodu construction project overview .............................................................................. - 14 -

1.1.2 S319 Erba to Wuwei Section Project Overview........................................................................................... - 16 -

1.1.3 S367 Ma’anshan Northern Passage Road Project Overview....................................................................... - 17 -

1.1.4 G318 and S320 Yimu Highway Project overview ....................................................................................... - 18 -

1.1.5 Shuiyang River Inland Waterway Transport Project overview................................................................... - 19 -

1.2 Project Resettlement Impact Overview ................................................................................................................. - 20 -

1.2.1 G206 Dongliu to Yaodu Construction Project Impact Overview ............................................................... - 20 -

1.2.2 S319 Erba to Wuwei Section Construction Project Impact Overview .................................................... - 22 -

1.2.3 S367 Ma’anshan Northern Passage Road Impact Overview .................................................................... - 23 -

1.2.4 G318 and S320 Yimu Highway Project Impact Overview ......................................................................... - 24 -

1.2.5 Shuiyang River Transport Project Impact Overview ................................................................................... - 24 -

1.3 Project Resettlement Implementation Time .......................................................................................................... - 25 -

1.3.1 G206 Dongliu to Yaodu Construction Project Resettlement Implementation Time ................................. - 25 -

1.3.2 S319 Erba to Wuwei Section Construction Project Resettlement Implementation Time ......................... - 28 -

1.3.3 S367 Ma’anshan Northern Passage Road Resettlement Implementation Time ......................................... - 31 -

1.3.4 G318 and S320 Yimu Highway Project Resettlement Implementation Time............................................ - 34 -

1.3.5 Shuiyang River Integrated Transport Development Project Resettlement Implementation Time............ - 37 -

2 Resettlement Organization ............................................................................................................................................. - 44 -

2.1 G206 Dongliu to Yaodu Construction Project Resettlement Organization ................................................... - 44 -

2.2 S319 Erba to Wuwei Section Construction Project Resettlement Organization ........................................... - 45 -

2.3 S367 Ma’anshan Northern Passage Road Project Resettlement Organization.............................................. - 46 -

2.4 G318 and S320 Yimu Highway Project Resettlement Organization ............................................................. - 50 -

2.5 Shuiyang River Transport Construction Project Resettlement Organization ................................................ - 51 -

2.6 Organizational framework and personnel capacity analysis........................................................................... - 52 -

Page 4: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 3 -

3 Monitoring and evaluation of Resettlement Implementation Process......................................................................... - 55 -

3.1 Monitoring and evaluation of main content..................................................................................................... - 55 -

3.2 Methodology of Monitoring and Evaluation ................................................................................................... - 57 -

3.3 G206 Dongliu to Yaodu Construction Project Resettlement Monitoring and Evaluation Process .............. - 59 -

3.3.1 House Demolition and Resettlement................................................................................................... - 60 -

3.3.2 Permanent land acquisition .................................................................................................................. - 67 -

3.3.3 Temporary land occupation ................................................................................................................. - 67 -

3.3.4 Progress of land acquisition and demolition....................................................................................... - 69 -

3.3.5 Restoration and reconstruction of affected special facilities ............................................................. - 69 -

3.3.6 Restoration and improvement of water system .................................................................................. - 70 -

3.3.7 Vulnerable Groups Affected ................................................................................................................ - 73 -

3.3.8 Technical training ................................................................................................................................. - 74 -

3.4 S319 Wuwei to Erba Construction Project Resettlement Monitoring and Evaluation Process ................... - 77 -

3.4.1 House Demolition and Resettlement................................................................................................... - 78 -

3.4.2 State-owned Land Acquisition Area ................................................................................................... - 79 -

3.4.3 Permanent Land Acquisition ............................................................................................................... - 80 -

3.4.4 Temporary Land Acquisition............................................................................................................... - 80 -

3.4.5 Restoration and Reconstruction of the Affected Special Facilities ................................................... - 81 -

3.4.6 Vulnerable Groups Affected ................................................................................................................ - 82 -

3.5 S367 Ma’anshan Northern Passage Road Resettlement Monitoring and Evaluation Process ..................... - 82 -

3.5.1 House Demolition and Resettlement................................................................................................... - 84 -

3.5.2 Permanent Acquisition of Collective Land......................................................................................... - 86 -

3.5.3 Temporary Land Occupation ............................................................................................................... - 86 -

3.5.4 Pole Line and Other Infrastructure ...................................................................................................... - 87 -

3.5.5 Vulnerable Groups Affected ................................................................................................................ - 87 -

3.6 G318 and S320 Yimu Highway Project Resettlement Monitoring and Evaluation Process ........................ - 88 -

3.6.1 Housing Demolition and Resettlement ............................................................................................... - 91 -

3.6.2 Permanent Acquisition of Collective Land......................................................................................... - 93 -

Page 5: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 4 -

3.6.3 State Owned Land ................................................................................................................................ - 94 -

3.6.4 TemporaryLand Acquisition................................................................................................................ - 94 -

3.6.5 Infrastructure......................................................................................................................................... - 95 -

3.7 Shuiyang River Integrated Transport Construction Project Resettlement Monitoring and Evaluation Process- 95 -

3.7.1 house demolition and resettlement ...................................................................................................... - 96 -

3.7.2 Permanent Land Acquisition ............................................................................................................... - 98 -

3.7.3 Temporary Land Acquisition............................................................................................................... - 99 -

3.7.4 Infrastucture .......................................................................................................................................... - 99 -

4 Compensation standard for Resettlement...................................................................................................................... - 99 -

4.1 G206 Dongliu to Yaodu Project Compensation Standard ............................................................................ - 100 -

4.1.1 Land acquisition standard .................................................................................................................. - 100 -

4.1.2 Compensation Standard for House Demolition................................................................................ - 108 -

4.1.3 Grave relocation ................................................................................................................................. - 114 -

4.1.4 Affected individual businesses .......................................................................................................... - 114 -

4.2 S319 Wuwei to wuwei-erba Project Compensation Standard and Quantity ............................................... - 117 -

4.2.1 Quantity Standard of Land Acquisition ............................................................................................ - 117 -

4.2.2 Compensation Standard for Collective Land Acquisition ............................................................... - 117 -

4.2.3 Compensation Standard for House Demolition................................................................................ - 120 -

4.2.3.1 Compensation Standard for RuralHousing Demolition ................................................................ - 120 -

4.3 S367 Compensation Standard for Ma'anshan North Passage Project .......................................................... - 124 -

4.3.1 Compensation Standard for Land Acquisition ................................................................................. - 124 -

4.3.2 Compensation standard for rural housing demolition ...................................................................... - 126 -

4.3.3 Compensation for Accessories and Infrastructure............................................................................ - 129 -

4.3.4 Other cost standards ........................................................................................................................... - 130 -

4.3.5 Vulnerable Groups ............................................................................................................................. - 130 -

4.3.6 Women's Support Measures .............................................................................................................. - 131 -

4.4 Compensation Standard for G318 and S320 Yimu Highway Project .......................................................... - 131 -

4.4.1 Compensation Standards of Land Acquisition ................................................................................. - 131 -

Page 6: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 5 -

4.4.2 Compensation Standard for House Demolition................................................................................ - 136 -

4.4.3 Compensation Rates for Main Attachments and Infrastructure ...................................................... - 139 -

4.4.4 Affected Individual Businesses ......................................................................................................... - 140 -

4.4.5 Other Cost Standards.......................................................................................................................... - 141 -

4.4.6 Vulnerable Groups ............................................................................................................................. - 142 -

4.4.7 Women Support Measures ................................................................................................................. - 143 -

4.5 Compensation Standards for Shuiyang River Integrated Transport Construction Project ......................... - 143 -

4.5.1 Land Compensation Standards .......................................................................................................... - 143 -

4.5.2 Compensation Standards for the Acquisition of Flood Land Reclaimed by Households along the

River ............................................................................................................................................................. - 145 -

4.5.3 Compensation Standard for House Demolition................................................................................ - 146 -

4.5.4 Compensation Standard for Main Accessories and Infrastructure .................................................. - 147 -

4.5.5 Other Cost Standards.......................................................................................................................... - 147 -

4.5.6 Vulnerable Groups ............................................................................................................................. - 148 -

4.5.7 Women's Support Measures .............................................................................................................. - 149 -

5 Monitoring and evaluation mechanisms for resettlement .......................................................................................... - 150 -

5.1 G206 Dongliu to Yaodu monitoring and evaluation mechanisms for resettlement .................................... - 150 -

5.1.1 Internal Monitoring and Inspection ................................................................................................... - 150 -

5.1.2 Public Participation ............................................................................................................................ - 150 -

5.1.3 Grievance Redress Mechanism (GRM) ............................................................................................ - 152 -

5.1.4 Typical Cases ...................................................................................................................................... - 154 -

5.2 S319 Wuwei to Erba Monitoring and Evaluation Mechanisms for Resettlement....................................... - 156 -

5.2.1 Internal Monitoring and Inspection ................................................................................................... - 156 -

5.2.2 Public Participation ............................................................................................................................ - 156 -

5.2.3 Grievance Redress Mechanism(GRM) ............................................................................................. - 157 -

5.3 S367 Ma’anshan Northern Passage Road Construction Project Monitoring and Evaluation Mechanisms for

Resettlement ........................................................................................................................................................... - 159 -

5.3.1 Internal Monitoring and Inspection ................................................................................................... - 159 -

5.3.2 Public Participation ............................................................................................................................ - 159 -

Page 7: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 6 -

5.4 G318 and S320 Yimu Highway Project monitoring and evaluation mechanisms for resettlement ........... - 165 -

5.4.1 Internal Monitoring and Inspection ................................................................................................... - 165 -

5.4.2 Public Participation ............................................................................................................................ - 165 -

5.4.3 Grievance Redress Mechanism(GRM) ............................................................................................. - 167 -

5.5 Shuiyang River Transport Construction Project Monitoring and Evaluation Mechanisms for Resettlement- 170 -

5.5.1 Internal Monitoring and Inspection ................................................................................................... - 170 -

5.5.2 Public Participation ............................................................................................................................ - 170 -

5.5.3 Grievance Redress Mechanism(GRM) ............................................................................................. - 171 -

6 G206 Dongliu to Yaodu Investigation and Analysis of the Living Standards of the Affected Households .......... - 173 -

6.1 Distribution of survey samples ....................................................................................................................... - 173 -

6.2 Annual Per Capita Income of Affected Families .......................................................................................... - 174 -

6.3 property status of the investigated family ...................................................................................................... - 175 -

6.4 Living Conditions of the Investigated Family ............................................................................................... - 176 -

6.4.1 Basic Public Goods Such as Water and Electricity .......................................................................... - 176 -

6.4.2 House condition .................................................................................................................................. - 178 -

6.4.3 Living Environment ........................................................................................................................... - 182 -

6.5 Analysis of the Economic Income and Source of the Investigated Family ................................................. - 182 -

6.5.1 Economic Income of the Investigated Family .................................................................................. - 182 -

6.5.2 Income source analysis ...................................................................................................................... - 184 -

6.6 Subjective Evaluation of the Living Conditions of the Investigated Families ............................................ - 187 -

6.6.1 Evaluation of Own Production Conditions ....................................................................................... - 187 -

6.6.2 Evaluation of the Economic Situation of the Whole Village .......................................................... - 189 -

6.6.3 Assessment of current living environment ....................................................................................... - 190 -

6.6.4 Evaluation of Neighborhood Relationship ....................................................................................... - 191 -

6.6.5 Evaluation of current life satisfaction ............................................................................................... - 193 -

7 Basic Assessment and Suggestions ............................................................................................................................. - 195 -

7.1 Basic Assessment ............................................................................................................................................ - 195 -

7.2 Basic Suggestions ............................................................................................................................................ - 196 -

Page 8: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 7 -

8 Attachments .................................................................................................................................................................. - 197 -

Attachment 1: Project Location Diagram............................................................................................................. - 197 -

Attachment 2: G206 Project Approval of constrution land issued by Anhui provincial government ............. - 199 -

Attachment 3: Approval of Construction Land for Road S319 Erba to Wuwei Section Reconstruction Project - 200 -

Attachment 4: Notice on establishment of project resettlement office .............................................................. - 202 -

Attachment 5: Report on the Establishment of S319 Construction Headquarters in Wuwei County .............. - 205 -

Attachment 6: foundation file of anhui Jiaoyuan engineering project management limited company............ - 206 -

Attachment 7: Agreements On Land Acquisition ............................................................................................... - 207 -

Attachment 8: Agreements on Land Acquisition of Forest Farm for G205 Project.......................................... - 209 -

Attachment 9: Staff Meeting File of Forest Farm ............................................................................................... - 211 -

Attachment 10: Lease contract on mixing plant ground in lishan working area ............................................... - 212 -

Attachment 11: Rental Agreement on Temporary Land Use for Mixing Plant in S319 signed by Road and Port

Group ...................................................................................................................................................................... - 215 -

Attachment 12: housing lease contract of project management department in contract 01.............................. - 218 -

Attachment 13: Rental Contract of Project Management Department Signed by Road and Port Group ........ - 220 -

Attachment 14: Housing lease contract of project management department in contract 02 of G206 Project . - 225 -

Attachment 15: Housing lease contract of S319 Project ..................................................................................... - 228 -

Attachment 16: G206 Project housing lease contract of maintenance center .................................................... - 230 -

Attachment 17: G206 Compensation agreement for house demolition ............................................................. - 231 -

Attachment 18: Compensation agreement for power lines reconstruction project ........................................... - 235 -

Attachment 19: G206 Project Compensation agreement for communications trunk cables relocation project- 236 -

Attachment 20: G206 Project Water migration agreement ................................................................................. - 237 -

Attachment 21: G206 Project Forestry land compensation supplemental agreement....................................... - 238 -

Attachment 22: G206 Project Statistics of water conservancy project .............................................................. - 239 -

Attachment 23: G206 Project River restoration task decomposition table ........................................................ - 240 -

Attachment 24: Minutes of Meeting of Coordination Meeting for Pipeline Relocation of S319 Project. ...... - 245 -

Attachment 25: Approval of Construction Land Use for Nanling Yimu Highway Project .............................. - 248 -

Attachment 26: Notice on establishment of Nanling County project resettlement office ................................ - 249 -

Page 9: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 8 -

Attachment 27: Notice on establishment of Shuiyang River project resettlement office ................................. - 250 -

Attachment 28: Housing lease contract of Nanling Contract 01 ........................................................................ - 251 -

Attachment 29: Housing lease contract of Nanling Contract 02 ........................................................................ - 252 -

Attachment 30:Notification Concerning the Compensation Scheme of House Demolition On Collective Land in

Jishan Town, Gongshan Town.............................................................................................................................. - 254 -

Attachment 31: Agreement on the Compensation of Young Crops for Nanling Yimu Highway.................... - 255 -

Attachment 32:Compensation Agreement On Land Acquisition in Nanling .................................................... - 256 -

Attachment 33 Notice On Establishment of S367 Hanshan Section Reconstruction Project Resettlement Office- 257 -

Attachment 34 Agreement On Land Acquisition for S367................................................................................. - 258 -

Attachment 35: Compensation Standard for House Demolition On Collective Land and Above-Ground

Attachments, and Compensation Standard for Young Crops in Xuanzhou District ......................................... - 259 -

Attachment 36: Compensation Standard for House Demolition in the Collective Land Acquired Within the

Scope of Urban Planning Area of Xuancheng City............................................................................................. - 266 -

Attachment 37: Official Reply to the Construction Land for S367 Project ....................................................... - 282 -

Appendix 38: Ma An Shan Public Participation and Minutes for S367 project............................................. - 284 -

Appendix 39: Compensation Standard on Wuwei County of S319 approved by Wuhu City Government .... - 290 -

Appendix 40: House Demolition Agreement of S319 ........................................................................................ - 297 -

Appendix 41: The establishment of Nanling Organization................................................................................. - 299 -

Appendix 42: Permanent Agreement of Land Acquisition of S319 Project ...................................................... - 300 -

Appendix 43: Compensation of Demolition House and Resettlement Agreement of S367 ............................. - 302 -

Appendix 44:Acquisition Agreement of Land S367 ........................................................................................... - 304 -

Appendix 45: Compensation of Demolition House and Resettlement Agreement of Yimu Road ............... - 305 -

Appendix 46: Land Acquisition Agreement of Yimu Highway ...................................................... - 307 -

Appendix 47: Group Purchase Agreement of Huishang Century City .......................................................... - 308 -

Appendix:48: Demolition agreement of Non-residential house and operation house compensation for

reconstruction from Kedian to Mujiating section of Yimu Highway in Nanling County ................................ - 311 -

Appendix 49: Record Form of Resettlement House for Xiaohekouqiao Pottery Factory ................................ - 314 -

Appendix 50: Shuiyangjiang Waterway Dredging and Dam Project Approved by Xuancheng People's

Government ............................................................................................................................................................ - 315 -

Page 10: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 9 -

Appendix 51: Evaluation Report on New State-owned Land Acquisition for the Reconstruction Project from

Kedian to Mujiating Section of Yimu Highway in Nanling County .................................................................. - 316 -

Appendix 52: Resettlement Transition Fee for Demolition of Xuanzhou Port Wharf ..................................... - 320 -

Appendix 53: The transition fee for Vouchers resettlement of Xiaohekou Bridge ........................................... - 322 -

Notes for the Updated Monitoring Report

1.The duration of this monitoring report: July to December, 2019

2.For the quantity of land acquisition and demolition, see the table below:

G206 Dongliu-Yaodu Item Unit Planned Accumulated Completion Completion

Page 11: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 10

Section Construction

Engineering

Part Completion Proportion time

Permanent Land

Acquisition Mu 987.97 1010.336 102.26%

2015.12

Temporary land Mu 180.99 210.943 116.55%

Housing demolition

area ㎡ 2546.09 5096.04 200.15%

Compensation for

permanent land

Ten

thousa

nd

Yuan

2847.37 2936.2083 103.12%

Compensation for

temporary land

Ten

thousa

nd

Yuan

/ 776.0536 /

Compensation for

housing demolition

Ten

thousa

nd

Yuan

151.7 225.48 148.64%

S319 Erba to Wuwei

Section Construction

Project

Permanent Land

Acquisition Mu 500.18 304.7252 60.92%

Temporary land Mu 199 71.37 35.86%

Housing demolition

area ㎡ 9710.8 12277.83 126.43%

Compensation for

land

Ten

thousa

1345.2 1262.4127 93.85%

Page 12: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 11

nd

Yuan

2018.12

Compensation for

demolition

Ten

thousa

nd

Yuan

1259 1187.2951 94.30%

S367 Maanshan

City Northern

Passage Road

Permanent Land

Acquisition Mu 1440.33 1237.9531 85.95%

2018.12

Housing demolition

area ㎡ 19657 21217.29 107.94%

Compensation for

land

Ten

thousa

nd

Yuan

3998.65 4553.0259 113.86%

Compensation for

housing demolition

Ten

thousa

nd

Yuan

2070.96 3386.6326 163.53%

G318 and S320 Yimu

highway project

Permanent Land

Acquisition Mu 972.13 479.4 49.314% 2019.06

Housing demolition

area ㎡ 7645.3 6706.76 87.72% 2017.12

Compensation for

land

Ten

thousa

nd

Yuan

775.24 602.3045 77.69% 2017.12

Page 13: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 12

Compensation for

housing demolition

Ten

thousa

nd

Yuan

2259.96 2038.1347 90.18% 2019.06

Comprehensive

shipping development

project of Shuiyang

River

Permanent Land

Acquisition Mu 906.153 917.52 101.25% 2019.12

Housing demolition

area ㎡ 8063 8544.24 105.97% 2019.12

3.Updated the contents of "compensation and implementation time" and "monitoring and

evaluation" in the reporting period;1、Updated the resettlement progress of S319 project;

4.Update the resettlement progress of S319 project;

5.Update the progress of Shuiyangjiang project resettlement site;

6.Updated the complaint cases of the project;

7.Updated the basic evaluation and suggestions of the project;

8.Update the economic level survey and analysis of G206 project;

Page 14: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 13

1 Overview

1.1 Project Overview 1

The Wanjiang River Urban Belt is the most economically, socially, culturally and

technologically developed region in Anhui Province, and an integral part of the pan-Yangtze River

Delta economic circle. In January 2010, the State Council approved the Development Plan for the

Demonstration Area for Industry Shift to the Wanjiang River Urban Belt. The demonstration area

includes 59 counties (cities/districts) inclusive of Hefei and Wuhu Cities. According to the above

plan, infrastructure construction will be accelerated, an integrated transport system integrated with

the Yangtze River Delta established, regional energy supply level strengthened, and regional

information integration boosted in the Wanjiang River Urban Belt. The construction of the

expressway network will be accelerated and highway network structure improved with focus on

the interconnection of the demonstration area with surrounding areas.

ADB-financed Anhui Intermodal Sustainable Transport Project is composed of road network

reconstruction projects and Inland Waterway Transport (IWT) project. Of which, road network

reconstruction project include:

(1) Road S319 Erba to Wuwei Section: Upgrading of 30.60 km of the existing S319 road in

Jiujiang District (Wuhu City) and Wuwei County from Class II to Class I and adding 5.77 km of a

new road section. The subproject’s owner is Wuwei County Transport Bureau.

(2) S367 Ma’anshan Northern Passage Road: Upgrading of 46.87km of existing S367 within

Hexian County from Class IV to Class II. The owner is Ma’anshan Municipal Highway

Administration Bureau.

(3) Road G206 Dongliu to Yaodu Section: Construction of 15.714 km of a new Class I

highway section (G206) from Dongliu to Yaodu within Dongzhi County. The Owner is Chizhou

Municipal Highway Administration Bureau.

(4) G318 and S320 Yimu Highway: Upgrading of 22.36 km of G318 and S320 Yimu Road

1Resources: Resettlement Plan of the construction projects prepared by PMO in Anhui(Updated version)

Page 15: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 14

within Nanling County from Class II to Class I. The project owner is Nanling County Transport

Bureau.

Inland Waterway Transport Subproject includes:

(1) Shuiyang River Channel Improvement Project: 43.90 dredging, widening, and bank

protection of 43.90 km Shuiyang River channel waterway; construction of one 1000 dwt ship lock;

construction and installation of two low water rubber dams; construction of a new road overbridge

at Xiaohekou. The subproject’s owner is Anhui Provincial Port and Shipping Construction

Investment Group Co., Ltd. (APPSCIG).

(2) Shuiyangjiang xuanzhou Intermodal Port: construction of a new intermodal port on

northeast of Xuancheng industrial part in Xuancheng City, including construction of four

1,000-ton berths, road, storage yard and ancillary works in the rear. The subproject’s owner is

Anhui Provincial Port and Shipping Construction Investment Group Co., Ltd. (APPSCIG).

1.1.1 G206 Dongliu to Yaodu construction project overview

1) G206 Project Overview

Picture 1-1 G206 Project Diagram

Page 16: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 15

The G206 Dongliu to Yaodu Section Construction Project (the “Subproject”) assumes an

important traffic task, with An average daily traffic volume of 7,948 vehicles (estimated to be

30,115 cars in 2034). Since the existing highway is relatively low in grade and has a mixed traffic,

it has become a bottleneck for the economic and traffic development of this region. In order to

upgrade the highway network of Dongzhi County and its service level, improve the regional

investment environment, and promote the integration of Yaodu and Dongliu Towns, ADB plans to

grant a loan of US$200 million to the PRC for the Anhui Intermodal Sustainable Transport

Development Project. This Subproject is a component thereof.

The subproject starts from G206 pile No.K1275+100 in Xiayang Village, Dongliu Town, goes

through the Zhanggong Reservoir, Zhanggang Village (Exist to Dongliu in Anjing Expressway),

the right bank of the Yaodu River, Tongjiu Railway and Anjing Expressway, and ends at

K1293+820, being a Class-I highway with a full length of 15.714km, a design speed of 80

km/hour, a roadbed width of 34m and a carriageway pavement width of 28.5m.

2) G206 Project approval time and planned start time

Foreign Fund Project Management Office of Anhui Provincial Department of Transport

(APMO) has agreed to include this project into the construction plan in Year 2013 on October 23,

2012; ADB mission had a field visit to Dongzhi, and APMO held meetings and signed a

memorandum with ADB on April 9, 2013; the Feasibility Study Report (FSR) was approved by

Anhui Provincial Development and Reform Commission (PDRC) on July 9, 2013; the project’s

preliminary design was approved by Chizhou Municipal Development and Reform Commission

(MDRC) on August 8, 2013; Design institute has completed construction drawings design on

September 13, 2013. This project is scheduled to start from May 2014 to May 2017, with

construction period of approximately 3 years.

Land acquisition, house demolition, compensation and resettlement works for the project will

be publicized from Sept. 2013 land acquisition and resettlement will be started from, Feb. 2014,

and ended largely in April 2015, all resettlement houses will be built up for residence in Dec.

2015.

Page 17: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 16

1.1.2 S319 Erba to Wuwei Section Project Overview

Road S319 Erba to Wuwei Section Reconstruction Subproject (the Subproject)is a component

of the ADB-financed Anhui Intermodal Sustainable Transport Development Project. The

subproject is located in Jiujiang District of Wuhu City and Wuwei County, starting from ramp

entrance of connecting line to Wuwei County of Hefei-Wuhu Expressway, crossing Xihe River

from east to west, ending at the west bridgehead of Xihe Bridge. It is surrounded by various

zones&parks such as Wuwei County Economic Development Zone, Gaogou Town Industrial Park,

wucheng Industrial Parkin Wuwei County, etc. Along this subproject, which are key areas for

Wuwei County to rely on zones & parks, accelerate industry cluster, as well as undertake industry

transfer from the Yangtze River Delta. In recent years, with the rapid development of national

economy, increasing traffic volume, as well as affected by natural conditions, pavement damage

has occurred in various degrees; some heavily damaged road sections have threaten to traffic safety,

efficiency of operation in existing roadsis constantly lower, which has hindered the development

of transport and economy within regions in the future to some extent. Therefore, expansion works

on this road is very necessary for the purposes of reducing costs of routine maintenance,

improving service levels (fast, safe, comfortable) and traffic capacity of trunk highways as well as

decreasing negative influence on social aspect.

The subproject includes 30.80 km reconstruction project from existing Class II upgraded to

Class I, and newly construction of 5.456 km, totaling about 36.256 km. Reconstruction project will

only widen 0.75m on both sides of the existing subgrade. The existing subgrade section after

reconstruction will have the same width as the newly constructionsubgrade. The designed

standards are Class I highway, with a design speed of 80Km/h, dual way four lanes, and subgrade

width of 26.5 m. The construction works include: 1) road works; 2) bridges &culverts works; 3)

intersection works; 4) traffic engineering. The owner for the part of this subproject located within

Wuwei County is Wuwei County Transport Bureau; the owner for the other part located within

Jiujiang District is Jiujiang District Government.

The subproject is divided into three contracts, namely: No1-1:K0+000-K18+000;

No1-2:K18-K30+800; No1-3:K30+800-K36+256. All three contractors have mobilized

Page 18: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 17

successively from November 2014; overall works are expected to be completed around June 2017,

with 26 months of construction period as planned.

1.1.3 S367 Ma’anshan Northern Passage Road Project Overview

Figure 1-2 schematic diagram of S367 project

The project is located in the north of Ma’anshan, across He County, Hanshan County from the

east to west. The road starts from the joint of Jiangsu and Anhui, involving four towns, namely,

Shiyang Town, Shanhou Town in He County, Zhaoguan Town, Xianzong Town in Hanshan County,

total length is about 46.419km. Design speed 60km/h, subgrade width 12.0m, in compliance with

Class II highway standard.

This project will be constructed from June 2015 to May 2017, total construction period is 24

months.

Page 19: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 18

1.1.4 G318 and S320 Yimu Highway Project overview

Picture 1-3 Nanling Yimu Highway Project Diagram

Nanling County Yimu Highway Kedian to Mujiating Section Reconstruction Project starts

from Kedian Village, Jishan Town, Nanling County, runs through Nanling County Economic

Development Zone to Tongling westwards, ends at Yingtao Mount Nantong boundary of

Gongshan Town, total length 22.447km, of which Class I highway length 14.072km, biDirectional

four-lane, alignment is 30m; town road length is 8.375km, biDirectional six-lane + non-driveway,

acquisition alignment is 60m, it consists of a part of current G318 Xuannan Road Nanling Section

and S320 Nantong Road Nanling Section. S320 connects Nanling and the area in the west of

Tongling, G318 connects Nanling and Xuancheng, Taihu Region.

This project passes across Nanling County from east to west via Nanling county seat, there

are many fairs along the road, especially Nanling Industrial Park on both sides of the road in the

west of Wulihuandao, it is an east-west urban trunk road, also a necessary passage for daily ravel

of urban people.

According to the Resettlement Plan, land acquisition and resettlement would start from Sept.

2015 and end in June 2016; construction commenced officially from Dec. 2015, the whole line

will be completed for transport in Dec. 2017.

Page 20: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 19

1.1.5 Shuiyang River Inland Waterway Transport Project overview

Figure 1-3 Shuiyang River Transport Construction Project Diagram

Total length of Shuiyang River Integrated Transport Development Project is 43.9 km, in

compliance with Class Ⅳ channel standard, a new ship lock is built, a bridge is reconstructed.

Shuiyang River channel is divided into upper, middle, lower sections, upper section is Helixi to

Haitang Bay, the channel is rated as Class Ⅶ, middle section is Haitang Bay to Xidoumen, rated

as Class Ⅴ, lower section is below Xidoumen, is main part of Wushen Line channel, research

scope of this project is middle section.

Shuiyang River Haitang Bay-Xidoumen Section is about 49km long. In recent decades,

upstream soil erosion in Shuiyang River causes siltation in the navigation channel in successive

years, navigation mileage is shortened ontinuously. The channel could not meet transport

development demand. To meet eastward development strategy of Anhui Provincial Government,

Anhui Provincial Department of Transport decided to control Wushen Canal, open the waterway

transport between Yangtze River and Taihu water systems in 2004.

Page 21: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 20

This project is planned to start from June 2015 and end in Dec. 2017, construction period is

approximately 2.5 years. Land acquisition, house demolition, compensation and resettlement for

the project will start from Dec. 2014, end in Dec. 2016.

1.2 Project Resettlement Impact Overview

1.2.1 G206 Dongliu to Yaodu Construction Project Impact Overview

The main affects in resettlement of road G206 Dongliu to Yaodu section construction project

include collective land acquisition, state-owned land occupation, residential house demolition as

well as temporary land.

According to the Approval of construction land use for National Road G206 Dongliu

(Dongzhi) to Yaodu Section Reconstruction Project (WZD [2012] No.1226) approved by Anhui

Provincial Government, approved actual area of LA are 68.8640 hectares (approximately 1032.96

mu (including the former state-owned construction land of 2.0994 hectares), of which 42.5136

hectares of agricultural land (including 19.6241 hectares of arable land (294.36 mu)), 7.5005

hectares of construction land and 18.8499 hectares of unused land (including 12.5901 hectares of

state-owned unused land).

By the end of December 2015, the land acquisition, demolition and resettlement of g206

Dongliu Yaodu section construction project have been completed. Permanent land acquisition is

1010.336 mu, temporary land is 210.943 mu, and house demolition is 5096.04

Table 1-1 the Planned and Actual Impact of the Project

Items Unit Planned quantity

Cumulative

completed

quantity

Completion ratio

Permanent land

acquisition mu 987.97 1010.336 102.26%

Temporary land use mu 180.99 210.943 116.55%

Page 22: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 21

Housing demolition

area ㎡ 2546.09 5096.04 200.15%

Permanent land

compensation

Ten

thousan

d yuan

2847.37 2936.2083 103.12%

Temporary land

compensation

Ten

thousan

d yuan

/ 776.0536 /

Compensation for

house demolition

Ten

thousan

d yuan

151.7 225.48 148.64%

The housing demolition area includes 3194.73m2 of main house demolition, 1901.31m2 of

abandoned management house and temporary construction of auxiliary simple shed / house, so the

house demolition area is 200.15% of the planned resettlement area.

During the implementation of the project, 2 individual businesses will be affected. See table

1-2 for details. According to the survey, in the original resettlement plan, only two households

were regarded as ordinary affected households, and the breeding of both households was in the

wild, and there was no obvious breeding house. Therefore, in the resettlement plan, the chicken

farm and pig farm were regarded as ordinary affected households and were not listed as individual

industrial and commercial households.

Table 1-2 Impacts on Individual Businesses

Types of impacts Types of individual businesses Culture area(m2) Number

Individual businesses Pheasant farm 6000 About 10000

Pig farm 288 120

Page 23: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 22

1.2.2 S319 Erba to Wuwei Section Construction Project Impact

Overview2

The Resettlement Impact of the project mainly includes permanent land occupation,

demolition of rural residents' houses and demolition of non residential houses.

The land acquisition and demolition work for the reconstruction project of s319 Erjun Road

(Erba Wuwei) class I Highway in Wuwei County has been completed. The project collects

304.7152 mu of permanent land, 71.37 mu of temporary land, 12.624127 million yuan of land

compensation fee, 12277.83 mu of house demolition area and 11.872951 million yuan of house

demolition compensation fee.

T able 1-3 land acquisition and demolition quantity of S319 project

Item Unit Planned

quantity

Cumulative completed

quantity

Completion

ratio Remarks

Permanent land

acquisition mu 500.18 304.7252 60.92% Completed

Temporary land mu 199 71.37 35.86% Completed

Housing demolition

area ㎡ 9710.8

12277.83(Including

housing area of 2

Enterprises)

126.43% Completed

Land compensation

fee

Ten

thousand

yuan

1345.2 1262.4127 93.85% Completed

Compensation for

demolition

Ten

thousand

yuan

1259 1187.2951 94.30% Completed

The reason why the actual land acquisition data of the project is smaller than the data in the

resettlement plan: the Resettlement Impact of S319 project involves four towns, namely Dougou

Town, Fudu Town, Erba town and Tanggou Town, which have a total impact on Wuwei County. In

March 2013, the administrative division of Wuhu City was adjusted. Tanggou town and Erba town

2 Data source: Resettlement Plan of Road S319 Erba to Wuwei Reconstruction Project

Page 24: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 23

were divided into Jiujiang District of Wuhu City. 87.63 mu of land in Tanggou town and Erba

town of Jiujiang district is the auxiliary land of the highway, which does not need to be

expropriated; 107.8248 mu of land in Fudu town of Wuwei County has been expropriated before

the start of the project, when the new area of Chengdong is constructed, which does not need to be

repeatedly expropriated. Therefore, the actual land acquisition of the project is 304.7252 mu.

However, this part of the land that does not need to be repeatedly expropriated is occupied and

cultivated by the residents. Therefore, in the process of resettlement, compensation is still made

according to the compensation standard of the resettlement plan.

1.2.3 S367 Ma’anshan Northern Passage Road Impact Overview3

Main resettlement impacts of this project include permanent and temporary land occupation,

house demolition. The land acquisition and resettlement of this project involves He County and

Hanshan County, of which, He County involves 4 villages, 3 communities in Shiyang Town, 3

villages 1 community in Shanhou Town; Hanshan County involves 3 villages 1 community in

Zhaoguan Town, 1 village 1 community in Xianzong Town.

Table 1-4 completion ratio of land acquisition and demolition of S367 project

Item Unit Planned

quantity

Cumulative

completed

quantity Completion ratio Remarks

Permanent land

acquisition Mu 1440.33 1237.9531 85.95%

Completed

Housing demolition

area ㎡ 19657 21217.29 107.94% Completed

Land compensation

fee

Ten thousand

yuan 3998.65 4553.0259 113.86% Completed

Compensation for

demolition

Ten thousand

yuan 2070.96 3386.6326 163.53% Completed

The permanent land acquisition of the project is 1237.9531 mu, 85.95% of the resettlement

plan; the total area of house demolition is 21217.29m2, 107.94% of the resettlement plan. The land

3 Data source: Resettlement Plan for Yimu Highway Kedian to Mujiating Section Reconstruction Project

in Nanling County (Final Version) 2015

Page 25: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 24

compensation fee is 45.530259 million yuan, and the house demolition compensation is 33.866326

million yuan.1.2.4 G318 and S320 Yimu Highway Project Impact Overview4

1.2.4 G318 and S320 Yimu Highway Project Impact Overview

According to the design scheme of the project, the Resettlement Impact of the project

involves 2 towns, 10 villages and 49 village groups in Nanling County. The acquisition and

relocation of Yimu highway in Nanling County mainly involves Gongshan town and Jishan town.

In June 2019, the land acquisition and relocation work was completed. The permanent land

acquisition of the project is 479.4 mu, and the house demolition area is 6706.76 m2.

Table 1-5 completion ratio of land acquisition and demolition of Yimu Highway project

Item Unit Planned

quantity

Cumulative

completed

quantity

Completion

ratio Remarks

Permanent land

acquisition Mu 972.13 479.4 49.314% Completed

Housing

demolition area ㎡ 7645.3 6706.76 87.72% Completed

Land

compensation fee

Ten thousand

yuan 775.24 602.3045 77.69% Completed

Compensation for

demolition

Ten thousand

yuan 2259.96 2038.1347 90.18% Completed

1.2.5 Shuiyang River Transport Project Impact Overview

The shipping comprehensive development project of Shuiyangjiang is divided into

comprehensive wharf and waterway regulation project. Among them, the waterway regulation

project includes three subprojects: the construction of Xiaohekou bridge, sluice dam and waterway

dredging regulation project.

Main resettlement impacts of this project include permanent acquisition of collective land,

4 Data source: Resettlement Plan for Yimu Highway Kedian to Mujiating Section Reconstruction Project

in Nanling County (Final Version) 2015

Page 26: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 25

permanent occupation of state-owned land, temporary land occupation and rural house demolition.

The land acquisition and resettlement of this project involves 5 villages, 7 village groups in towns

of Xuanzhou District, Xuancheng City.

By the end of June, 2018, the land acquisition and demolition work of Shuiyangjiang

shipping comprehensive construction project was completed. The permanent land acquisition of

the comprehensive wharf project is 447.71 mu, and the house demolition is 4660.9 m2. The

permanent land acquisition of waterway regulation project is 491.01 mu, and the permanent land

acquisition of house demolition project is 3883.34 m2, 917.52 mu, and the house demolition area

is 8544.24 m2. The data of compensation for house demolition and land acquisition has not been

finalized due to multi department statistical accounting, and the next report will continue to

monitor.

Table 1-6 statistics of land acquisition and demolition of Shuiyangjiang shipping project

Permanent land acquisition (mu) Demolition area(m2) remarks

RAP plan Actual Completion ratio RAP plan Actual Completion

ratio Completed

Port engineering 499.5375 447.71 89.62% 5203 4660.9 89.58% Completed

Waterway

Engineering 406.6155 447.71 110.11% 2860 3883.34 135.78% Completed

Total 906.153 917.52 101.25% 8063 8544.24 105.97% Completed

1.3 Project Resettlement Implementation Time

1.3.1 G206 Dongliu to Yaodu Construction Project Resettlement

Implementation Time

In the stage of feasibility study, project owner has entrusted Hohai University to prepare the

resettlement plan based on project impacts. In the phase of project implementation, Dongzhi PMO

and project implementing agency have carried out a detailed project survey in December 2013,

Hohai University has updated the resettlement plan survey on the basis of detailed project survey

in February 2014.

Page 27: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 26

Resettlement external monitoring team has been to the field many times to conduct

investigation and interviews. We learned that the activities of LA, HD, Compensation and

resettlement were started in November 2013; (The research work of planning land acquisition and

resettlement programs, demolition area measurement, disbursement way, without access to land

and houses from the hands of affected households), Dongzhi county,the town Yaodu and Dongliu

held town and village levels meeting, inviting most of the affected households participate,fully

solicit the views of affected households on Land Acquisition and Resettlement Program of the

G206 Dongliu to Yaodu Road Section Construction Project (Draft), On this basis, revise and

improve the Program.

Issued Land Acquisition and Resettlement Program of the G206 Dongliu to Yaodu Road

Section Construction Project,November 19, 2013.

December 2013,Yaodu and Dongliu Town widely publicized land acquisition and

resettlement program;

April 2014, Dongzhi County held a land acquisition and resettlement mobilization meeting,

and Dongzhi television carried a report.

July 29, 2014, Magistrate, Sun Gexin in Chizhou city government Web site to promote the

importance of G206 Dongliu to Yaodu Road Section Construction Project, and answer the

questions the masses are concerned about, such as land acquisition and resettlement standards,

resettlement, compensation payment and other issues one by one. The successful implementations

of the project immigrant resettlement provide favorable conditions for the project.

Construction of the project began on September 25, 2014.

In early December 2014,land acquisition and demolition work basically competed.

June 30, 2015, land acquisition and resettlement compensation and resettlement work

basically finished.

Dec. 31, 2015, land acquisition and resettlement and compensation completely finished.

The staff of Monitoring Group learned that, the progress of resettlement implementation is

Page 28: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 27

shown in Table 1-7.

Table 1-7 Registration Form for Resettlement Implementation Progress

Implementation of Resettlement

Activities Approved by Implementation date Related documents

Project approval Anhui Provincial Development and

Reform Commission Jun. 8, 2012

WFGJCH 2012 No.

【599】

Official reply to preliminary

design

Chizhou Municipal Development and

Reform Commission Aug. 8, 2013

CFGSJ 【2013】

No.297

Official reply to construction

drawing

Chizhou Municipal Transportation

Bureau Mar. 4, 2014 CJJ 【2014】 No.8

Preliminary examination of land Anhui Provincial Department of Land

Resources Oct. 19, 2012

WGTZH 【2012】

No.1834

Official reply to land Anhui Provincial Peop le’s

Government Dec. 2012

WZD 【2012】

No.1226

Preparation of resettlement plan Apr. 2013 Prepared by Hohai

University

Approval of the Resettlement

Plan ADB

Preparation of the Resettlement

Plan (updated) Feb. 2014

Prepared by Hohai

University

Approval of the Resettlement

Plan (updated) ADB

Publicity of LAR Program Sept. 2013

LA implementation (LA

planning and preparation of

program)

In early Nov. 2013

HD implementation In late Nov. 2013

Measurement of LA, HD At the beginning of Nov.

2013

Households Registration Dec. 2013 in early

Engineering construction

tendering

Foreign Investment Office of

Provincial Department of Transport May 2014

Contractor’s mobilization Aug. 2014

Commence of project G206 Project OFFICE Sept. 26, 2014

Page 29: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 28

Implementation of Resettlement

Activities Approved by Implementation date Related documents

construction

Completion of HD In early Dec. 2014

Land acquisition completed 2014

Resettlement Date Main structures of new houses were completed in

June 2014.

New Houses Move-in Date In Aug. 2015, all resettlement apartments were built

up and resided.

Construction of farm irrigation

water systems was completed

Water system construction was completed in Oct.

2015

Notes: the project contractor has the required work surface during construction on site, so,

house demolition does not affect the construction.

1.3.2 S319 Erba to Wuwei Section Construction Project Resettlement

Implementation Time

In March 2012, Anhui Transport Survey &Consulting Design Institute(hereinafter called the

“Design Institute”) was entrusted by Wuwei County Transport Bureau (WCTB) to launch the

compilation of Feasibility Study Report on Class I Road S319 Erba to Wuwei Section

Reconstruction Project (hereinafter called the “FSR”).

In March 2012, under the strongly support by local PMO in Wuwei County, the design

institute carried out activities including field reconnaissance, site investigation and data collection;

and they has completed the draft of FSR and initially determine the contents and scope of this

project in July 2012.

During September 2012 to December 2012, immigration investigation team from Hohai

University has carried out a general survey on social economic conditions within project affected

areas and project resettlement impacts on the basis of the FSR.

During September 2012 to March 2013, the Resettlement Plan (RP) for this subproject was

completed based on the project’s FSR, survey data and public participation. The resettlement

impacts and risks of this subproject were analyzed and evaluated in this RP, and remedial measures

were also proposed.

Page 30: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 29

In March 2014, the Design Institute has completed the construction drawings design.

In Mar. 2014, House Compensation and Resettlement Scheme for Collective Land in

Chengdong New District, Wuwei County was issued. From Aug. To Oct. 2014, publicity was

carried out in Fudu Town and Dougou Town extensively;

In Apr. 2014, the County government held a land acquisition and resettlement mobilization

meeting, Wuwei television carried a report.

During April to May 2014, a detailed project survey on affected immigrants was conducted

by the Design Institute and Wuwei County PMO in accordance with construction drawings.

On the basis of the above survey,the final Resettlement Plan for Class I Road S319 Erba to

Wuwei Section Reconstruction Project based on Detailed Measurement Survey (the “final RP”)

was completed by immigration investigation teamof Hohai University in July 2014.

The successful implementations of the project immigrant resettlement provide favorable

conditions for the project.

This project was constructed from Aug., Sept. 2015.

LA and HD works were basically completed in early May 2015.

On Jun. 30, 2016, land acquisition and demolition, compensation and resettlement works

were basically completed.

On June 30, 2017, the land acquisition and demolition of S319 project and the relocation of

communication and power lines involved in the project were all completed. The housing

construction project of resettlement site - Chengdong new area was completed, and the supporting

auxiliary facilities project was in progress.

On June 30, 2018, some resettlers were resettled, some of them did not choose the existing

resettlement houses, and they were still waiting for their favorite houses.

On September 30, 2019, the relocated households were organized to select the resettlement

house number.

Page 31: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 30

Table 1-8 Registration Form for Resettlement Implementation Progress

No. Implementation stage of resettlement

activities Approved by

Implementation date or

period Remarks

1 Project approval

Anhui Provincial

Development and

Reform Commission

2013.9.17 WGFWZ [2013]

No.801

2 Official reply to preliminary design

Wuhu Municipal

Development and

Reform Commission

2014.1.10 WFGJT [2014]

No.16

3 Official reply to construction drawing Wuhu Municipal

Transportation Bureau 2014.7.12

WJGC [2014]

No.435

4 Preliminary examination of land Wuhu Provincial Land

and Resources Bureau 2013.5.29

WGT [2013]

No.200

5 Official reply to land Anhui Provincial

People’s Government 2014.1.22

WZD [2014]

No.53

6 Preparation of resettlement plan 2012.9-2013.3 Prepared by Hohai

University

7 Approval of the Resettlement Plan ADB-financed Project

Office 2013.5

8 Preparation of the Resettlement Plan

(updated) 2014.4-2014.6

Prepared by Hohai

University

9 Approval of the Resettlement Plan

(updated)

ADB-financed Project

Office 2014.7

10 Publicity of LAR Program 2014.8-2014.10

11 Measurement and registration of LA, HD 2014.11-2016.5

12 Signing and implementation of the

agreement on land acquisition 2014.11-2016.5

13

Signing and implementation of the

agreement on housing demolition and

relocation

2014.11-2016.5

14 Tendering for project construction Foreign Investment

Office of Provincial

Department of

02 Contract: 2014.4.28

03 Contract: 2014.7.18

Page 32: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 31

No. Implementation stage of resettlement

activities Approved by

Implementation date or

period Remarks

Transportation

15 Contractor’s mobilization 02 Contract: 2014.11 03

Contract: 2015.4

16 Commence of project construction Wuhu Municipal

Transportation Bureau

02 Contract: 2015.8.10

03 Contract: 2015.9.16

17 Construction time of centralized

settlements

2013.11.20 construction

started

18 Completion time of centralized settlements 2017.6.30

The housing

construction

project completed,

and the supporting

auxiliary facilities

project in

progress

Completion time of centralized settlements 2019.8.30

Supporting

facilities

completed

19 Centralized housing distribution and

selection 2019.9.30

20 Placement time Expected Dec. 2019

1.3.3 S367 Ma’anshan Northern Passage Road Resettlement

Implementation Time

The progress of project demolition and resettlement shall be implemented in accordance with

the overall progress plan of the project. The specific implementation time may be adjusted due to

the deviation of the overall progress of the project. The implementation progress of the project is

as follows:

Land Acquisition and Demolition Scheme for S367 Ma’anshan Northern Passage Road

Project was issued in Aug. 2015.

Page 33: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 32

At the end of Dec. 2015, land data for approval passed the examination of Ministry of Land

and Resources and were submitted to the State Council for approval.

Construction of this project uninvolved with LA and HD contract was commenced from Dec.

20, 2015.

Land requisition and house demolition statistics of the AHs in the restriction line was

completed in Jan. 2016.

In January 2016, we completed the works of land and housing demolition statistics of

households in the restriction line, land and housing measurement, attachments survey, statistics

and the acquisition on the ground.

By the end of December 2016, we completed the permanent land acquisition of Hanshan

county and about 75% of He county.

At the end of December 2016, there was no house demolition work in Xianxu town of He

county, and 50%in Zhaoguan town was completed.

By the end of June 2017, Hanshan county had completed 95% of pole line relocation, and all

the water pipelines had been relocated. In Hexian County, 80% of the relocation work had been

completed, and the relocation of water pipes had been basically completed.

On December 31, 2018, the land acquisition and demolition work was completed.

By the end of June 2019, the resettlement work has been completed.

Table 1-9 Resettlement Implementation Schedule for S367 Ma'anshan Northern Passage Road

No. Implementation stage of resettlement

activities Approved by

Implementation date or

period Remarks

1 Project approval

Maanshan Municipal

Development and Reform

Commission

Apr. 9, 2013 MFGM (2013)

No.27

2 Official reply to preliminary design

Anhui Provincial

Development and Reform

Commission

Oct. 17, 2014 WFGSJH (2014)

No.1030

Page 34: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 33

No. Implementation stage of resettlement

activities Approved by

Implementation date or

period Remarks

3 Official reply to construction drawing Maanshan Municipal

Transportation Bureau Aug. 5, 2015

MJ (2015)

No.198

4 Preliminary examination of land Maanshan Municipal Land

and Resources Bureau June 20, 2013

MGTZH (2013)

No.73

5 Official reply to land

Ministry of Natural

Resources of the People’s

Republic of China

Feb. 3, 2016 GTZH (2016)

No.51

6 Preparation of resettlement plan Hohai University May 2013

7 Approval of the Resettlement Plan ADB

8 Preparation of the Resettlement Plan

(updated) Hohai University Jan. 2015

9 Approval of the Resettlement Plan

(updated) ADB

10 Land acquisition plan and

scheme formulation Jan. 2016

11 House demolition Plan and

scheme formulation Jan. 2016

12 Publicity of LAR Program Jan. 2016

13 Measurement of LA, HD

completed June 2016

14 Households Registration May. 2016

15 Tendering for project construction Oct. 27, 2015

16 Contractor’s mobilization Dec. 2015

17 Commence of project construction At the end of Dec. 2015

18 Completion of land acquisition and

demolition An the end of 2018

19 Completion of all resettlement work At the end of June 2019

Page 35: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 34

1.3.4 G318 and S320 Yimu Highway Project Resettlement Implementation

Time

March 2012, Wuhu Municipal Highway Bureau entrusted China Highway Planning and

Design Institute in Anhui Province to prepare Feasibility Study Report on Nanling County Yimu

Highway Kedian to Mujiating Section Reconstruction Project.

Sept. 2012-Oct. 2012, immigration investigation team from Hohai University carried out 100%

investigation on social economic conditions within project affected areas, rural families affected

by land acquisition for the project, physical quantity affected by project demolition according to

the Feasibility Study Report, and carried out sampling survey on social economic conditions of the

affected households (sampling proportion is about 26%), survey contents include family members,

land acquisition impacts, family economy and expected mode of resettlement etc.

From July to December 2014, immigration investigation team from Hohai University carried

out additional investigation in the affected areas according to the changes of project design

construction drawing.

Dec. 2015 ADB approved the updated version of Resettlement Plan.

In June 2014, Land Acquisition and Demolition Scheme for G318 and S320 Yimu Highway

Project was issued.

In June 2014, publicity was carried out extensively in Jishan Town and Gongshan Town.

In Apr. 2014, Nanling County government held a land acquisition and demolition

mobilization meeting.

In early Mar. 2015, land acquisition and demolition work of Gongshan Town was basically

completed.

In Dec. 2015, land acquisition and demolition, compensation and resettlement in Gongshan

Town were basically completed. This project was constructed from Dec. 2015.

In June 2017, land acquisition was completed and demolition was in progress.

In December 2017, the land acquisition and demolition work was basically completed. Seven

Page 36: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 35

state-owned land assessments were completed and compensation agreements signed.

In June 2018, the resettlement work was completed.

In June 2019, the monitoring team learned that due to the design adjustment, the project does

not need to occupy the state-owned land of Qiangsheng Company, so it no longer needs to be

expropriated. The land acquisition work was completed.

Actual Resettlement Time of G318 and S320 Yimu Highway Project is shown in the table

below:

Table 1-10 Resettlement Implementation Time Table

No. Implementation stage of resettlement

activities Approved by

Implementatio

n date or

period

Remarks

1 Project approval Anhui Provincial Development and

Reform Commission

WFGWZ

No.2013-800

2 Official reply to preliminary design Wuhu Municipal Development and

Reform Commission 24 months

WFGJT

No.2014-62

3 Official reply to construction drawing Wuhu Municipal Transportation

Bureau

4 Preliminary examination of land Wuhu Provincial Land and Resources

Bureau

WGTM

No.2013-202

5 Official reply to land Anhui Provincial People’s

Government

6 Preparation of resettlement plan Hohai University Oct. 2012

7 Approval of the Resettlement Plan ADB

8 Preparation of the Resettlement Plan

(updated) Hohai University July 2015

9 Approval of the Resettlement Plan

(updated) ADB Dec. 2015

10 Publicity of LAR Program The governments of Jishan Town,

Gongshan Town

June

2014-Dec.

2014

Page 37: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 36

No. Implementation stage of resettlement

activities Approved by

Implementatio

n date or

period

Remarks

11 Measurement and registration of LA,

HD

The governments of Jishan Town,

Gongshan Town

Oct. 2014 –

Mar. 2015

12 Signing and implementation of the

agreement on land acquisition

The governments of Jishan Town,

Gongshan Town Dec. 2015

13

Signing and implementation of the

agreement on housing demolition and

relocation

The governments of Jishan Town,

Gongshan Town Dec. 2015

14 Tendering for project construction Dec. 2014

15 Contractor’s mobilization July 2015

16 Commence of project construction Dec. 2015

17 Construction time of centralized

settlements 2014-2016

18 Completion time of centralized

settlements Oct. 2015 Gongshan Town

19 Move-in time of centralized

settlements Feb. 2016 Gongshan Town

20 Move-in time of centralized

settlements

Resettlement

apartments

have been

built, HD is

being

negotiated

Jishan Town

21 Construction time of the self-built

decentralized resettlement apartments June 2015 Gongshan Town

22 Move-in time of decentralized

resettlement apartment Dec. 2015 Gongshan Town

23 Completed construction of the affected

infrastructures

Constructed

synchronously

with the

project

24 Completion of Demolition Dec.2017

Page 38: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 37

No. Implementation stage of resettlement

activities Approved by

Implementatio

n date or

period

Remarks

25 Completion of resettlement June 2018

26 Completion of land acquisition June 2019

1.3.5 Shuiyang River Integrated Transport Development Project

Resettlement Implementation Time

Oct. 30, 2006, Anhui Provincial Development and Reform Commission approved the

establishment of Wushen Canal Anhui Section Improvement Project according to the minutes of

meeting of the provincial government.

Nov. 20, 2007, Anhui Provincial Port and Shipping Construction Investment Group Co., Ltd.

Entrusted Anhui Survey and Design Institute of Water Conservancy and Hydropower to prepare

the Project Water and Soil Conservation Program.

Jan. 4, 2008, Anhui Provincial Port and Shipping Construction Investment Group Co., Ltd.

Entrusted Anhui Science and Technology Advisory Center to prepare environmental impact report

of the project, which passed assessment.

March 9, 2008, Anhui Provincial Port and Shipping Construction Investment Group Co., Ltd.

Entrusted Yangtze River Water Conservancy Committee Changjiang Institute of Survey, Planning,

Design and Research to prepare flood control assessment report for the project, which passes

review.

Dec. 3, 2008, Anhui Provincial Port and Shipping Construction Investment Group Co., Ltd.

Obtained letter of opinions on the preliminary examination of construction land from Anhui Land

and Resources Bureau.

According to the Memorandum of ADB Project Advisory Group (Dec. 12-15, 2011),

Shuiyang River channel will be improved according to “Class Ⅳ channel, Class Ⅲ water depth”

standard; research scope has been adjusted to Haitang Bay to Yanchi (Ganjiaguai); connecting line

Xiaocai River of Shuiyang River channel and main channel of Wushen Canal (Yanchi to Xigeng),

Page 39: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 38

old channel of Shuiyang River (Yanchi to Xidoumen in Jiangsu Province) were compared and

selected on the basis of sufficient study and communication; port work was added, so that this

project became integrated water transport development project.

March 2012, entrusted by the owner, Anhui Provincial Port and Shipping Construction Group

Co., Ltd. , Anhui Traffic Survey Design Institute Co., Ltd. Completed Feasibility Study Report on

Shuiyang River Integrated Transport Development Project (first draft).

Sept. 2012-Dec. 2012, immigration investigation team from Hohai University investigated

social economic conditions and resettlement impact within project affected areas according to the

Feasibility Study Report. And carried out sampling survey of 40 households (sampling proportion:

household proportion is 31.7%) on social economic conditions of the affected households,

investigation content includes family members, impacts of land acquisition, family economy and

expected mode of resettlement etc.

Nov. 28, 2012, the Request of Xuancheng Development and Reform Commission for the

Establishment of Shuiyangjiang xuanzhou Intermodal Port Project was approved by Anhui

Provincial Development and Reform Commission, Approval Document No.WFGWZH

[2012]1259. Sept. 7, 2013, Anhui Provincial Development and Reform Commission replied to the

Feasibility Study Report on Shuiyangjiang xuanzhou Intermodal Port Project for approval (Anhui

Development and Reform Commission Design Letter [2013] No.1031); April 14, 2014,

preliminary design report of Shuiyangjiang xuanzhou Intermodal Port Project was approved by

Anhui Provincial Development and Reform Commission in written form (Anhui Development and

Reform Commission Design Letter [2014] No.347); Sept. 2, 2014, Request of the Provincial Port

and Shipping Construction Investment Group Co., Ltd. Concerning the Construction Drawing

Design of Shuiyangjiang xuanzhou Intermodal Port Project for approval was approved by

Transport Department of Anhui Province in written form (WJJGH [2014] No.423).

Aug. 20, 2013, Letter of the Transport Department of Anhui Province Concerning the

Approval of Proposal for Shuiyang River Channel Improvement Project was approved by Anhui

Provincial Development and Reform Commission (WFGWZH [2013] No.932); Sept. 7, 2013,

Letter of the Transport Department of Anhui Province Concerning the Approval of Feasibility

Page 40: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 39

Study Report on ADB-financed Anhui Intermodal Sustainable Transport Infrastructure Project

Shuiyang River Channel Improvement Project was approved by Anhui Provincial Development

and Reform Commission (WFGWZH [2013] No.1030); Nov. 7, 2013, Letter of the Transport

Department of Anhui Province Concerning the Approval of Primary Design for ADB-financed

Anhui Intermodal Sustainable Transport Infrastructure Project Shuiyang River Channel

Improvement Project was approved by Anhui Provincial Development and Reform Commission

(WFGWZH [2013] No.1259).

From Jan. To June, 2014, entrusted by provincial PMO of this project —— Anhui Provincial

Department of Transport Anhui Provincial Port and Shipping Construction Investment Group Co.,

Ltd. , Anhui Xuancheng municipal government, Xuancheng Municipal Land and Resources

Bureau carried out detailed measurement and survey in Yangxian Township, Shuiyang Town,

Liqiao Town, Xuanzhou District, Xuancheng City involved in this project.

Dec. 2015, Integrated Shuiyang River Transport Improvement Project entered resettlement

publicity stage, project situation was publicized, compensation program data for land acquisition,

demolition were prepared for publicity. Real situation of the relocated households was investigated,

measurement and registration work was not carried out.

In Jan. 2016, PMO established Resettlement Organization.

In Jan. 2016, Land Acquisition and Demolition Scheme for Shuiyang River Integrated

Transport Development Project was issued.

In early Jan. 2016, pole line relocation scheme and agreement were signed.

In August 2016, land acquisition and demolition work officially began.

At the end of December 2016, the land acquisition and demolition of the comprehensive

wharf and Xiaohekou bridge were completed.

In June 2017, the construction of resettlement housing for Xuanzhou port comprehensive

wharf and Xiaohekou bridge project started. Land acquisition and demolition of gate dam project

and waterway project were in progress. On May 2, 2017, the people's Government of Yangxian

Town and Huishang Century City invested construction unit. Xuancheng Chuangyuan Real Estate

Page 41: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 40

Development Co., Ltd., signed a commercial housing group purchase agreement. It was agreed in

the agreement that 61 sets of commercial houses of A-03 and A-04 with construction area of 6161

㎡ will be purchased as resettlement houses in the first phase of Huishang century city.

In June 2018, the demolition work of gate dam project and channel dredging project was

completed. Xiaohekou bridge resettlement housing construction started. The channel dredging

project was relocated to Dongyun new village, and the resettlement was completed.

In June 2019, the developer of "Huishang No.1" residential area for centralized resettlement

of Xuanzhou port comprehensive wharf project went bankrupt. And the restructure was in progress.

The resettlement houses of Xiaohekou bridge had been handed over. The gate dam project

completed the water intake relocation and land acquisition.

In December 2019, the land acquisition and demolition work was completed.

Table 1-11 Implementation Schedule of Shuiyang River Channel Project

No. Implementation stage of resettlement

activities Approved by

Implementation date or

period Remarks

1 Project approval

Anhui Provincial

Development and Reform

Commission

Aug. 20, 2013

2 Official reply to preliminary design

Anhui Provincial

Development and Reform

Commission

Nov. 7, 2013

3 Official reply to construction drawing Transport Department of

Anhui Province Feb. 11, 2014 Xiaohekou Bridge

4 Preliminary examination of land

Anhui Provincial

Department of Land

Resources

Aug. 27, 2013

5 Official reply to land Anhui Provincial People’s

Government Sept. 30, 2014

6 Preparation of resettlement plan May 2013 Prepared by

Hohai University

7 Approval of the Resettlement Plan ADB

Page 42: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 41

No. Implementation stage of resettlement

activities Approved by

Implementation date or

period Remarks

8 Preparation of the Resettlement Plan

(updated) Nov. 2014

Prepared by

Hohai University

9 Approval of the Resettlement Plan

(updated) ADB

10 Publicity of LAR Program People’s Government of

Xuanzhou District Jan. 25, 2016 Xiaohekou Bridge

11 Measurement and registration of LA, HD Jan. 2016- Xiaohekou Bridge

12 Signing and implementation of the

agreement on land acquisition Jan. 2016- Xiaohekou Bridge

13

Signing and implementation of the

agreement on housing demolition and

relocation

Apr. 2016- Xiaohekou Bridge

14 Tendering for project construction

15 Contractor’s mobilization Oct. 2015 10 Xiaohekou Bridge

16 Commence of project construction Nov. 26, 2015 Xiaohekou Bridge

17 Completion of land acquisition and

demolition Dec. 2016

18 Group purchase of resettlement houses May 2017

19

Bankruptcy and reorganization of

developers of resettlement housing

estate

June 2019

20 Construction time of centralized

resettlement site 2012--

The resettlement

developer went

bankrupt and

reorganized , and

the completion

time is to be

determined

21 Completion time of centralized

resettlement site

22 Occupancy time of Centralized

Settlement

23 Self construction time of scattered

resettlement houses

24 Occupancy time of scattered resettlement

Page 43: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 42

No. Implementation stage of resettlement

activities Approved by

Implementation date or

period Remarks

houses

Table 1-12 Implementation schedule of Shuiyangjiang waterway project

No. Implementation stage of resettlement

activities Approved by

Implementation date

or period Remarks

1 Project approval

Anhui Provincial

Development and Reform

Commission

Aug. 20, 2013

2 Official reply to preliminary design

Anhui Provincial

Development and Reform

Commission

Nov. 7, 2013

3 Official reply to construction drawing Transport Department of

Anhui Province Feb. 11, 2014

4 Preliminary examination of land

Anhui Provincial

Department of Land

Resources

Aug. 27, 2013

5 Official reply to land Anhui Provincial People’s

Government Sept. 30, 2014

6 Preparation of resettlement plan May 2013 Prepared by

Hohai University

7 Approval of the Resettlement Plan ADB

8 Preparation of the Resettlement Plan

(updated) Nov. 2014

Prepared by

Hohai University

9 Approval of the Resettlement Plan

(updated) ADB

10 Publicity of LAR Program People’s Government of

Xuanzhou District Jan. 25, 2016 Xiao hekou bridge

11 Measurement and registration of LA, HD Jan. 2016----- Xiao hekou bridge

12 Signing and implementation of the

agreement on land acquisition Jan. 2016----- Xiao hekou bridge

13 Signing and implementation of the

agreement on housing demolition and

Apr. 2016----- Xiao hekou bridge

Page 44: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 43

No. Implementation stage of resettlement

activities Approved by

Implementation date

or period Remarks

relocation

14 Construction unit mobilization Oct. 2015 10 Xiao hekou bridge

15 Commencement of project construction Nov. 26, 2015 Xiao hekou bridge

16 Completion of land acquisition and

demolition Dec.2016

17 Commencement of resettlement housing

construction June 2018 Xiao hekou bridge

18 Completion of lock and channel dredging

demolition June 2018

lock and channel

dredging

19 Completion of Channel dredging

resettlement June 2018

lock and channel

dredging

Completion of resettlement June 2019 Xiao hekou bridge

20 Completion of land acquisition June 2019 Gate dam

Page 45: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 44

2 Resettlement Organization

2.1 G206 Dongliu to Yaodu Construction Project Resettlement

Organization

Foreign Fund Project Management Office of Anhui Provincial Department of Transport

(APMO) will be the executing agency (EA) for Anhui Integrated Sustainable Transport

Development Project; Dongzhi County PMO will be the EA for G206 subproject, and Chizhou

Municipal Highway Administration Bureau will be the implementing agencies (IA) of the

subproject (G206). The above agencies will be jointly in charge of implementation of resettlement

plan in details with each town government affected.

To ensure the smooth progress of Road G206 Dongliu to Yaodu Section Construction

Subproject, it was decided by Chizhou Municipal Highway Administration Bureau after office

meeting that a resettlement management office would be setup for this subproject, the list of

persons as follows:

Director: Yao Chengyu

Deputy Director: Han Xiuyu

Members: Xu Yong, Wen Fadong

Han Xiuyu will be responsible for specific leadership works for this resettlement project.

It was decided by Dongzhi County Government that resettlement coordination and

management office would be setup for this subproject, name list as follows:

Director: Shi Weimin (County Government’s Office)

Deputy Director: Xu Moyou (Yao Du Town Government)

Wang Qianchun (Dongown Government)

Han Xiuyu (County Transportation Bureau)

Regarding resettlement coordination and management, Mr. Xu Moyou is responsible for

Page 46: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 45

liaison and coordination in Yaodu Town; Mr. Wang Qianchun is responsible for liaison and

coordination in Dongliu Town.

Yaodu Town Resettlement Leading Group

Leader: Shi Weimin

Members: Xu Moyou, Ruan Zhihua, Zhang Yongjian, Zhao Shuang

Dongliu Town Resettlement Leading Group

Group head: Jiao Shiqing

Deputy Head: Wang Qianchun

Members: Zhu Guoping, Jiang Weihong, Zhang Kelong, Yu Fujin, Zhou Zhengdong, Wu

Zhongfa, Wang Faping, Deng Xin

The Leading Group comprises office, which is located in Dongliu Town Labor and Social

Security Station and Deng Xin serves concurrently as the director.

The office conference has decided that Han Xiuyu, deputy director of PMO serves

concurrently as the chief of local coordination department, is responsible for local environment

coordination and resettlement works.

The preparatory work for land acquisition and resettlement are adequate, with perfect

institutional settings, which ensure the implementation of land acquisition and resettlement work

smoothly.

2.2 S319 Erba to Wuwei Section Construction Project Resettlement

Organization

Project construction headquarters wasset up in project located areas ofwuwei County and

Jiujiang District, respectively.

Wuwei County established a headquarters headed by the standing deputy county mayor Jin

Ligang; Xu Yaguang, a member of standing committee of the chinesepeople’s Political

Consultative Conference (CPPCC) in Wuwei County, serves as vice executive chief, who will be

Page 47: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 46

in charge of local coordination department and responsible for leading works on resettlement

activities. The name list of Wuwei County Headquarters is shown as following:

Chief: Jin Ligang (member of county standing committee, deputy county mayor)

Political commissar: Zhao Yin (deputy director of the standing committee in Wuwei County)

Deputy Chief: Zhao Qiancheng (director-general of Wuwei County Transportation Bureau),

Xu Yaguang (member of the standing committee of CPPCC in Wuwei County), Jiang Ping (head

of Wuwei County Rural Highway Management Bureau)

Local Coordination Department: He Jiyou, Tang Xiaowei

A headquarters was jointly established by three projects in Jiujiang District including

downtown section of Tongjiang road, Erba (Chang’an) Interchange, as well as Road S319 Erba to

Wuwei Section Reconstruction Project(downtown section). Wang Yang, deputy director of

Engineering Department is in charge of local coordination department and responsible for

resettlement activities. The name list of this headquarters in Jiujiang District is listed as below:

Director: Wang Chunming

Deputy Director: Chen Ruisheng, Wang Yang

Local Coordination Department: Wang Yang (concurrently), Zheng Yutian, Xu Yadong

Thus it can be seen that, preparatory work for the project land acquisition and resettlement

work was sufficient, and institution settings were improved,which ensure the smooth

implementation of land acquisition and resettlement works.

2.3 S367 Ma’anshan Northern Passage Road Project Resettlement

Organization

In order to ensure smooth resettlement and achieve the expected result, an organization from

top to bottom must be set up in the project implementation process for planning, implementation,

coordination and monitoring of the resettlement activities.

This project adopts the management mechanism of unified dispatching at municipal level, the

Page 48: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 47

counties assume their respective responsibilities.

1) municipal government has established Project Construction Headquarters headed by

deputy mayor in charge, responsible for commanding and coordinating of the project construction,

Headquarters Office is located in the Municipal Highway Management Bureau. Municipal

Highway Management Bureau is the project owner.

2) the government of He County, Hanshan County should establish Project Construction

Headquarters at County Level, which should be headed by the leader of the County government in

charge, directors of relevant departments in the county are members, responsible for commanding

and coordinating of project construction in their jurisdictions.

3) Municipal Highway Management Bureau has established Project Management Office

(PMO for short). Responsible for commanding and coordinating of construction organization of

the project management organization in both counties.

4) Project Construction Headquarters in the counties should establish Project Site

Management Department at County Level (Site Management Department for short), responsible

for organization management of project construction in their jurisdictions, under unified

dispatching and instruction of PMO.

Site Management Department should govern Technical Contract Division, Comprehensive

Coordination Division, Safety and Environment Protection Division, Financial Audit Division etc

according to relevant requirements.

1) 2 directors in Site Management Department (1 person in He County, Hanshan County

each), also as deputy directors of PMO, responsible for comprehensive works of the Site

Management Department in their respective counties.

2) 6 persons in Technical Contract Division (4 persons in He County, 2 persons in Hanshan

County), responsible for engineering work, also responsible for measurement and payment audit of

construction, supervision, test organizations, submit withdrawal and reimbursement data for ADB

loan, review project progress report etc. Such persons should have technical title of highway

bridge above medium grade, with construction project management work experience in no less

Page 49: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 48

than one Class 2 highway.

3) 5 persons in Comprehensive Coordination Division (3 persons in He County, 2 persons in

Hanshan Count), responsible for local relocation coordination and resettlement, also responsible

for secretarial, general affairs, logistics, advertisement and security guard works. Such persons

should be familiar with the local work environment, with work experience in relocation,

coordination, office etc for 3 years and above.

4) 2 persons in Safety and Environment Protection Division (1 person in He County, Hanshan

County each), responsible for safe production, environmental protection monitoring etc. Such

persons should have relevant work experience.

5) 2 persons in Financial Audit Division (1 person in He County, Hanshan County each),

responsible for financial work, coordinate with audit work, such persons should have accounting

qualification.

The above-mentioned persons in Site Management Department should be assigned by

government of the counties, age should not exceed 50. Drivers, cooks, doorkeepers and other

workers should be assigned according to the requirements.

Page 50: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 49

Picture 2-1 S367 Resettlement Organization Management Organization Block Diagram

In order to ensure successful S367 Hanshan Section reconstruction work, the County

headquarters decided to establish S367 Hanshan Section Reconstruction Resettlement

Management Office (Attachment 32), specific list is given below:

Director: Li Dingguo

Deputy Director: Zhang Yunhai, Gu Congwen, Luo Weibao

Members: Shi Guang, He Chengbo, Jiang Jinfeng

Comrade Gu Congwen is responsible for resettlement coordination management in Zhaoguan

He County

He County Land

Acquisition And Re settlement

Bureau

Hanshan County

Hans han Cou nty Land

Acq uisition And Resettl ement Bureau

367 Provincial Highway Reconstruction Project

Construction Headquarters

He County Section Resettlement

Hanshan Section

Reconstruction Project

Resettlement Management Office

Anhui provincial government

ADB-financed Project Leading

S367 Northern Passage Road

(Ma'anshan Section) Reconstruction

Project Management Office

External independent

Ma’Anhui Provincial

The affected

Village

The affected

The affected household

Page 51: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 50

Town, Comrade Luo Weibao is responsible for resettlement coordination management in

Xianzong Town.

2.4 G318 and S320 Yimu Highway Project Resettlement Organization

Picture 2-2 Nanling County Yimu Highway Project Resettlement Organization Chart

In order to ensure successful resettlement for the project, Nanling County government

established Yimu Highway Reconstruction Project Site Office, Office organization and members

are as follows:

Director: Ling Xianhua (head of County Department of Transport Bureau)

Standing Deputy Director: Hou Qingran (head of County Highway Branch)

Deputy director: Tao Haibo (County Department of Transport)

Liu Dongan (County Highway Branch)

Zhan Lingsheng (County Relocation Office)

Lu Qin (County Environmental Protection Bureau)

Wang Changsong (County Tourism Investment Company)

Page 52: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 51

Pan Yun(Jishan Town)

Wang Jinping (Gongshan Town)

At the same time, to meet the requirements of Yimu Highway Reconstruction Project Site

Office, Nanling County Land House Acquisition Management Office was organized, special

persons were allocated for resettlement work on site, organization setup and personnel

arrangement are as follows:

Director: Ma Weidong (director of County Acquisition Office)

Standing Deputy Director: Tao Haibo (County Department of Transport)

Deputy director: Zhan Lingsheng (deputy director of County Acquisition Office)

Liu Dongan (County Highway Branch)

Pan Yun(Jishan Town)

Wang Jinping (Gongshan Town)

Members: Liu Jianjun, Hu Enhong, Yu Shoubao, Wang Tianxi

See Annex 40 for specific documents

2.5 Shuiyang River Transport Construction Project Resettlement

Organization

In order to ensure successful resettlement for the project, Shuiyang River Integrated Transport

Development Project Construction Headquarters established Resettlement Office, Office

organization setup and members are as follows:

Municipal Command Office: Leader in charge Song Huahui Transactor Wu Hao

District Command Office: Leader in charge Zhang Guoqing Transactor Zhong Gongwen

Yangxian Township: Leader in charge Jiang Jingbo Transactor Cheng Yan

Liqiao Town: Leader in charge Han Dong Transactor Su Yong

Page 53: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 52

Shuiyang Town: Leader in charge Ding Weiyin Transactor Wu Yi

Figure 2-3 S367 resettlement organization chart of shipping project on Shuiyang River

See Annex 40 for specific documents.

2.6 Organizational framework and personnel capacity analysis

Project Resettlement Organizations have been established, special persons are responsible for

resettlement-related works. Establishment of resettlement organization and personnel arrangement

are favorable to successful implementation of resettlement work for the project.

Before the project resettlement organizations were established, and after personnel of the

resettlement organizations reached their designated positions, external resettlement monitoring

project leaders, resettlement experts of Anhui Province Foreign Investment Office and Anhui

Jiaoyuan Engineering Project Management Co., Ltd. Provided special resettlement training for the

External Monitoring

Unit

Anhui Project

Offoce

Xuancheng Land and

Resources Bureau

Xuancheng Maritime

Bureau

(Command Office)

District Command Office

Shuiyang

Town

Liqaio Town

Yangxian

Country

Anhui Port and Waterway

Construction Investion Group Co.,Ltd

Project Design

Organiztion

Page 54: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 53

resettlement organizations and relevant personnel.

Main training content: get familiar with guarantee policy requirements of Asian Development

Bank, understand the features of voluntary resettlement and involuntary resettlement, and current

challenges of involuntary resettlement, utilize abundant examples in the training process, express

significance and challenges of the resettlement vividly, put forward specific working methods of

work personnel related to ADB project resettlement and the details to be noted. The training

enabled the workers in resettlement organizations to get familiar with and master ADB

resettlement security policies, solve problems in land acquisition and resettlement of the project

timely, increase understanding of resettlement personnel on land acquisition and resettlement, laid

solid foundation for more effective land acquisition and resettlement of ADB-financed project in

the future. For project resettlement training meetings, see the figure below.

Page 55: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 54

Picture 2-4 ADB Ⅱ Project Resettlement Training Meetings

Page 56: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 55

3 Monitoring and evaluation of Resettlement Implementation Process

In March 2014, the foreign funded project management office of Anhui Communications

Department carried out public bidding for the external supervision organization of resettlement.

Anhui Communications Vocational and Technical College submitted and won the bid and became

the external monitoring organization of resettlement of "Anhui multimodal transport sustainable

transport project loaned by ADB", who is responsible for regular monitoring of the entire ADB

loan project and submitting external monitoring report. In order to successfully complete the

external monitoring work and meet the requirements of the public institutions reform, Anhui

Communications Vocational and Technical College registered and established Anhui

Communications Institute Engineering Project Management Co., Ltd. to be responsible for the

external monitoring work.

In July 2014, the external monitoring unit signed an external monitoring contract with the

foreign funded project management office of Anhui Communications Department. Anhui

Communications Vocational and Technical College has been responsible for the external

monitoring of resettlement in many foreign-funded projects, such as the ADB I project and the

world bank loan project, and won good performance. In order to ensure the smooth

implementation of the resettlement work of this project, the foreign funded project management

office of Anhui Communications Department entrusted Anhui Communications Vocational and

Technical College to provide technical guidance for the external monitoring work of resettlement

of ADB II project before the external monitoring bidding.

3.1 Monitoring and evaluation of main content

A. Key Monitoring Indicators

(1) Progress: including preparation, implementation and resettlement for land acquisition,

demolition and immigration;

(2) Quality: including construction quality, satisfaction degree of immigrant resettlement

Page 57: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 56

during the process of land acquisition, demolition and relocation;

(3) Investment: including fund allocation and usage.

(4) Socio-economic indicators: per capita income, GDP, employment rate.

(6) Institutional indicators: staff composition, quality of personnel, rules and regulations,

equipment, completion rate of transaction handling.

(7) Immigration affected by LA and land occupation: Compensation funds in-position rate,

production arrangement modes, rate of change in income, employment rate, satisfaction degree of

resettlement;

(8) Residential houses: Compensation funds in-position rate, location of new houses, progress

of land acquisition in new location, resettlement satisfaction degree.

(9) Infrastructure: Compensation funds in-position rate, rate of functional recovery.

(10) Temporary occupation: restoration funds in-position rate, progress of land property

recovery.

B. Main indicators for evaluation

(1) Production and living conditions of immigrants

① Economic conditions: Household economy development before and after relocation,

including households’ means of production, possession of subsistence materials, assets, income.

② Environmental conditions: Living environment before and after resettlement, including

public facilities development and changes involved in transportation, education, health, business

services and so on.

③ Employment: Career change before and after migration, labor employment rate, provide

assistance to various people, especially for households in poverty, minority households.

④ Community development: It refers that the status of economic and environmental

development, interpersonal relationships, public opinion in local communities after immigrants are

properly resettled.

Page 58: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 57

(2) Infrastructure

Variations are existed in regions affected by the project before and after infrastructure

implementation.

C. Individual businesses and private shops

Changes are existed in business environment and status before and after resettlement for

individual businesses and private shops.

In addition to monitor the above-mentioned Indicators, resettlement external monitoring

agency also provide resettlement policy advertisement and service training for all participants of

the project, main training contents are Resettlement Plan for the project and the Safeguard Policy

Statement issued by the Asian Development Bank.

3.2 Methodology of Monitoring and Evaluation

The monitoring and evaluation activities would be on the basis of the available data provided

by the design institute and implementation agencies of resettlement; Random samples are required

for quick evaluation based on the all-round knowledge grasped. Some typical samples were

selected to establish evaluation index system for the affected persons and then marked with special

index co-efficiency under back-to-back way and then followed with careful analysis and

calculation.

Independent monitoring and evaluation agencies are involved in the following tasks:

(1) Investigation on the resettled persons’ living conditions

It is tasked to carry out comprehensive baseline survey for the project and collect samples

(there are all random samples at the initial period) selected to learn about such data as production

and living materials. This kind of survey has been conducted for one to two times a year to see

what changes to be happened on local production and living conditions generally in the manner of

periodical survey, random interviews and field visits, on the basis of which the obtained data could

be collated and analyzed and evaluated.

The investigation table designed for learning about the living conditions consists of various

Page 59: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 58

indicators for measuring production and living conditions. The dynamic changes on the same

indicator just reflects the local conditions on production and living by comparison of before and

after resettlement; furthermore, whether the indicator designed is suitable or not to properly see the

real changes of local production and living, which can be verified through baseline survey and also

be improved in accordance with the local facts to be sure of all-sided information collected to

truthfully show the current quantity and quality of local resettled persons’ living and production

conditions.

(2) Public Consultation

Independent monitoring evaluation institute participated the public consultation meeting held

at the local villages and towns. With these activities, the survey team has found out how well the

resettled persons participated in and has seen how the local transmigrates are cooperative in terms

of resettlement action plan.

(3) Transmigrants’ opinion

Independent monitoring evaluation team visited the resettlement offices at towns and villages

involved to learn about the local resettled persons’ comments, and they often talked to the

transmigrants who had utterances and submitted the ideas and requirements of affected population

and local communities and made out their proposal of improvement in order to make the

resettlement work more efficient while fulfilling.

(4) Other responsibilities

The following activities have been monitored by the external and separate monitoring

evaluation institute while fulfilling:

① Selection of resettlement spots;

② Reconstruction of demolished houses;

③ Production resettlement and renewal;

④ Support to vulnerable group;

⑤ Resettlement of individual businesses and private shops;

Page 60: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 59

⑥ Rehabilitation and reconstruction of special facilities;

⑦ Payment of compensation funds and quantity;

⑧ Relocation of affected people;

⑨ Employment;

⑩ Establishment of resettlement implementation organization;

○11Usage of collective land compensations and benefits for affected people;

○12 Labor employment and income growth.

○13 the use and effectiveness of the resettlement budget

○14 Operation of complaint mechanism

3.3 G206 Dongliu to Yaodu Construction Project Resettlement Monitoring

and Evaluation Process

The monitoring and evaluation team further inspected the house demolition, land acquisition

and the project resettlement from March to June and November to December 2015.

In the startup stage of resettlement works in G206 subproject, the staff from the Company has

conducted field investigations on this project with four times including in December 2013, January

2014, May 2014, September 2014, October 2015, January 2016 and April 2016 respectively.

Inception Report on External Resettlement Monitoring has been provided to ADB by the Company

in September 2014. The Report has systematically stated the monitoring organization, schedule

and TOR during the implementation of this project. Monitoring and Evaluation Group has

conducted a comprehensive site investigation on resettlement works of G206 Dongliu to Yaodu

Section Construction Project during September to October 2014, and compiled the baseline report

of this project resettlement; meanwhile, the first report of external resettlement monitoring during

these period has also been completed. In April, June, Sept., Dec. 2015, April 2016, Monitoring and

Evaluation Group has conducted a comprehensive site investigation on resettlement works of

G206 Dongliu to Yaodu Section Construction Project, completed External Resettlement

Monitoring Report. In September 2019, Anhui Communications Vocational and Technical College

Page 61: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 60

carried out the survey of living standards and wrote the 11th monitoring report.

By the end of December 2015, G206 Dongliu to Yaodu Section Construction Project had fully

completed the land acquisition, demolition and resettlement, actually completed the acquisition of

permanent land of 1010.38 mu(The actual land used for the project is 807.066 mu, and the land

occupied for the project is 203.27 mu, which will be used as reserved land after land acquisition),

completed proportion 102%; temporary land 201.94 mu, completed proportion 116.55%; areas of

house demolition 5096.04 ㎡, completed proportion200.15%; land compensation fee 37.1226

million Yuan was paid, completed proportion 130%; Among them, the compensation for

permanent land is 29.362083 million yuan ,completed proportion103.12%; Compensation for

temporary land use is RMB 776.0536, compensations for house demolition 2.2548 million Yuan

was paid, completed proportion 149%.

Table 3-1 Planned impact and actual impact of the project

Item Unit Planned

quantity

Cumulative

completed quantity

Completed

proportion

Permanent acquisition Mu 987.97 1010.336 102.26%

Temporary land Mu 180.99 210.943 116.55%

Housing demolition area ㎡ 2546.09 5096.04 200.15%

Compensation for

permanent land

Thousand

yuan 2847.37 2936.2083 103.12%

Compensation for

temporary land

Thousand

yuan / 776.0536 /

Compensation for house

demolition

Thousand

yuan 151.7 225.48 148.64%

3.3.1 House Demolition and Resettlement

Before December 31, 2014, the affected households have signed the house demolition

agreement, and before December 31, 2015, the resettlement work has been completed. See table

3-2 for the demolition situation.

Table 3-2 Housing Demolition Area

Page 62: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 61

Dongliu Town Yaodu Town Total

RAP Actual RAP Actual RAP Actual

Housing demolition area

(㎡) 1262.41 1684.98 1283.68 3411.06 2546.09 5096.04

Affected households number (hu) 8 10 6 17 14 27

Note: Through understanding of the personnel involved in the preparation of the resettlement

plan in Yaodu and Dongliu towns, the number of houses demolished in the two towns is less than

one. The GaoWeigui and Gao Guosheng conjoined rooms in JuYang village, Dongliu Town, were

counted by one household. Lin Maosheng and Lin Qinggen in Guanshan village of Yaodu town

were also conjoined houses, which were counted by one household; And another five were

abandoned houses and flood control management houses, which only need monetary

compensation and no resettlement.

In addition, the reasons for the increase of housing demolition area are: on the one hand, the

safety distance of the red line for land acquisition of the newly demolished houses is insufficient,

the lighting is insufficient, the houses are wet and not suitable for living, etc., which are voluntary

resettling households; on the other hand, the houses outside the red line of the road are impacted

by ramming during the construction process, and the house foundation and structure are damaged

to a certain extent, which need to be demolished and resettled, and the affected households shall

negotiate with the project office for settlement with no objection. See Annex 17 for housing

demolition agreement. The statistics of 6 households increased in house area demolition and the

increased area and reasons are as follows:

Table 3-3 increase of demolition area of relocated households.

Town NO. Name

Demolition

area(㎡) Reasons

Yaodu Town 1 Ye Longlin 117.31 Insufficient lighting wet

2 Zhu Wenbiao 78.10 Ramming

Page 63: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 62

Town NO. Name

Demolition

area(㎡) Reasons

3 Su Renguang 173.43 Insufficient safety distance

4 Liu Airong 69.82 Ramming

5 Su Renya 145.79 Insufficient safety distance

Subtotal 584.45

Dongliu 6 Ding Xiufen 64.19 Insufficient lighting wet

Subtotal 64.19

Total 648.64

The resettlement methods for the relocated households include centralized resettlement and

decentralized resettlement, all of which are monetary compensation and local self built new houses

allocated by the government. The 22 affected households had been completed and relocated before

December 31, 2015.

(1)Yaodu Town

The resettlement methods involved in the demolition of Yaodu town were to disperse the

resettlement according the villagers' personal wishes, and to coordinate the homestead by

themselves. In case of difficulties, village organizations can assist in the coordination. If the water

supply and power supply, cable television and other services of the resettled households needed to

be reopened due to demolition, the government should coordinate with the relevant departments to

properly solve the problem without any cost to the resettled households.

According to the on-site monitoring and inspection by the monitoring team, the new houses

of the relocated households in Yaodu town were completed and moved in before August 31, 2015.

According to the on-site investigation of the monitoring team, the living conditions of the residents

affected by the project had been improved, and the housing conditions had been greatly improved

compared with that before the demolition (see the pictures below for the comparison of the house

photos before and after the demolition). The residents of the house demolition had a relatively

satisfied attitude towards the compensation and resettlement of the demolition.

Page 64: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 63

1) Before and after the demolition of the house of Su Renya

2) Before and after the house demolition of Huang Hanlin

3) Before and after the house demolition of Lin Maocai

Page 65: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 64

4) Before and after the house demolition of Su Rencai

5) Before and after the house demolition of Su Rencai

6) Before and after the house demolition of Ye Longlin

Page 66: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 65

7) Before and after the house demolition of Zhang Guofeng

Figure 3-1 comparison of houses before and after demolition

(2) Dongliu town

The villagers involved in Dongliu town's demolition were resettled in a centralized way,

while respecting the individual's will to choose the resettlement way. The transitional housing for

the relocated households were provided by the village committee free of charge.

Four households in Zhanggang village of Dongliu town were relocated, and Zhu bingbin

household was resettled according to his own wish. His homestead was provided by the village

committee free of charge, and the compensation for the original homestead was also paid in full

according to the compensation standard. The other three households were resettled in Zhanggang

village by the village committee. By December 31, 2015, all resettlement houses had been

completed and reached living conditions, and residents had moved in. The relevant approval

documents of the resettlement site project are being processed. Since the land of the resettlement

site is owned by the collective, it cannot be listed for trading, but it can be traded between villagers

within the scope of the village.

Page 67: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 66

Figure 3-2 Housing construction in Zhanggang village, Dongliu town

There are 6 households to be relocated in Xiyang village, Dongliu town. The resettlement

site is located in the beautiful rural construction site to the east of Xiyang village. The village

committee provided the homestead free of charge, and the compensation for the original

homestead of the relocated households was paid in full according to the compensation standard.

The six self built resettlement houses in the JuYang village of Dongliu town were completed by

the end of June 2015 and moved in.

Figure 3-3 Current situation of centralized resettlement sites in Xianyang Village

The cost of water supply, power supply, road traffic and other infrastructure related to

Dongliu town resettlement site were borne by the village committee. The water, electricity and

cable TV of the relocated households without other relating account opening costs can be paid

directly through original accounts.

Page 68: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 67

Figure 3-4 Resettlement inspection meeting of monitoring group

Figure 3-5 Resettlement monitoring team on site inspection

3.3.2 Permanent land acquisition

The collective land acquisition of G206 project involves 2 towns and 6 administrative

villages in Dongzhi County, Chizhou City, Anhui Province. The permanent land acquisition of the

project is 1010.38 mu, the actual land acquisition of the project is 807.066 mu. The remaining

203.27 mu of land for the project is the original old road, beach and acquired construction land, so

no land acquisition area is required for this project.

3.3.3 Temporary land occupation

The temporary land of the project mainly involves four administrative villages in two

towns of Dongliu and Yaodu, affecting 47 households, and the rest are village collective land. The

actual temporary land for the project is 210.943 mu, including 173.673 mu in Yaodu town and

37.27 mu in Dongliu town. See table 3-4 for the temporary land acquisition. The temporary land

was mainly used for borrow area, spoil area and construction access road.

Page 69: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 68

Table 3-4 List of temporarily acquisition land

Town Address

Area

(mu) use

Affected

situation

Caption house

holds

People

number

Dongliu

Bichong

group

Xiayang

village

18.053

Spoil ground

and

construction

access road

14 58

Spoil ground

16.068 mu;

construction access

road1.985 mu

Zhoucun

group

Zhanggang

village

12.847 1#

Borrow area 10 41

Zhang

group

Zhanggang

village

6.370

Spoil ground

at level

crossing

17 54

Area of other plots

included in the

agreement;

Land group

Total 37.27 41 153

Yaodu

Gaunshan

village 84.24

Spoil ground

2#

Borrow area

2

Spoil ground

15.74mu;

2#

Borrow area68.5 mu

Maotian

village 89.433

3#

Borrow area

Spoil area

4

3#

Borrow area

76.44 mu;

Spoil area12.993 mu

Total 173.673 6

temporary land affected

6 households;

The rest is village

Page 70: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 69

Town Address

Area

(mu) use

Affected

situation

Caption house

holds

People

number

collective land

Actual land

acquisition grand total 210.943 47

The area of

compensation

temporary land is about

150 mu(including

Meicheng forest farm

and Jin Shangsi farm

forest)

RAP land

acquisition grand total 180.9mu

State owned land, no

compensation

3.3.4 Progress of land acquisition and demolition

The monitoring and evaluation team members learned from the inspection that the whole

land acquisition, demolition and resettlement work started in November 2013, and the housing

demolition and land acquisition work were completed on December 31, 2015. In December 2015,

all 22 households that need to be resettled after the completion of resettlement housing moved in.

3.3.5 Restoration and reconstruction of affected special facilities

(1) Compensation for power line reconstruction and demolition

Due to the construction needs of g206 Dongliu Yaodu section, 20 construction projects of

G206 Dongliu Yaodu section need to be reconstructed by Anhui Dongzhi Chengxing Power Co.,

Ltd., with the compensation amount of 2 million yuan.

On December 31, 2015, all pole lines of Anhui Dongzhi electric power management company

were relocated, rebuilt and completed.

Table 3-5 list of migration completion of pole line and water pipeline

Infrastructure impact type Planned quantity(chu) Actual quantity (chu)

Page 71: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 70

Infrastructure impact type Planned quantity(chu) Actual quantity (chu)

tap water 12 11

Power line Low voltage line 20 19

High voltage line 2 1

Communication optical cable 7 7

Total 41 38

(2) Communication optical cable migration (reinforcement compensation)

For the construction of the project, Chizhou line Bureau of Anhui transmission line

maintenance Bureau of China Telecom Co., Ltd. agreed to relocate or reinforce the national

defense trunk line within the red line of the project. Both parties signed compensation agreement,

and the line relocation was completed. Seven sites of G206 Dongliu Yaodu section construction

project, i.e. Kuanyang, Zhanggang, Daqingshan, Linhua plant and Chitou bridge, need to be

relocated and reinforced. At Daqingshan, the original three optical cable lines were translated, and

the rest four were locally reinforced and protected. The total compensation cost was 930000 yuan,

including 530000 buried optical cable lines and 400000 overhead optical cable lines, which were

used in a lump sum. On June 30, 2015, the relocation of seven telecommunication isopods was

completed.

(3) Tap water migration

On November 20, 2014, Dongliu Town People's government of Dongzhi County signed an

agreement with Dongzhi County Waterworks to reach an agreement on the pipeline rerouting,

renewal and sheath involved in stake No.K0+300-K4+080 within the red line of land acquisition

of Dongliu Kuanyang Zhanggang road construction project, and the water supply rerouting of

Dongzhi County G206 Dongliu Yaodu class I highway, Kuanyang Zhanggang section project

started from the date of signing the agreement on November 20, 2014 and was completed on

February 16, 2015. Before December 31, 2015, the relocation of water pipeline was completed.

3.3.6 Restoration and improvement of water system

For the affected infrastructure, the governments at all levels and the resettlement office shall,

in accordance with the compensation standards and procedures, formulate the corresponding

Page 72: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 71

specific recovery measures according to the specific conditions of the town (Village);

For the affected households to be resettled in a centralized way, unified planning was adopted,

and the cost of water supply and power supply, road traffic and other infrastructure construction in

the centralized resettlement site were borne by the village committee;

In the construction process of the project, the farmland irrigation water system was inevitably

damaged. The town government coordinated with the construction unit to take temporary measures

to ensure the normal production and life of the farmers. After the project was completed, it was

actively restored. If it cannot be restored, the scientific planning should be carried out again to

avoid the impact on the production and life of the farmers.

The large water system had been fully considered in the design of bridges and culverts in the

construction drawing, but the restoration of ponds and culverts within the red line was not fully

considered, and it was not considered outside the red line. Therefore, in January 2015, the county

government allocated 10 million yuan of special funds for the reconstruction of pump stations,

supporting transformation and new water conservancy facilities, totaling 14 (5 within the red line).

See Annex 22 for statistics of water system restoration project. The new gate dam is shown in the

figure below. On December 31, 2015, all reconstruction and reconstruction of water conservancy

facilities were completed.

(1) Comparison of demolition and construction of Zetanwei gate station

Page 73: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 72

(2) Comparison of demolition and construction of Da Qingshan gate station and weir

(3) Comparison of demolition and construction of Da Qingshan gate station and weir

(4) Comparison of demolition and construction of wuguitang culvert gate

Page 74: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 73

(5) Small water conservancy projects Dongliu town is responsible for the construction

Figure 3-6 built drawing of reconstructed and newly built water conservancy facilities

3.3.7 Vulnerable Groups Affected

Monitoring group learned from field investigation, vulnerable group is only involved in

Yaodu Town during this immigration, of which 2 households with low income and 3 people with

disabilities.. All vulnerable groups involved enjoy subsistence allowances. See details in Table 3-6.

Table 3-6 List of land acquisition Du Yao vulnerable situation

No. Belonging to Name Gender Age ID No. Type of

difficulties

1

Tiaokou Group

in Maotian

Village

Peng

Suping Male 39 342921197412063116

Low-income

household

2

Shiyin Group

in Jiandong

Village

Zhang

Guangrong Male 61 342829195301043000

Low-income

household

Zhang

Shuanglong Male 34 342921198011233318

Low-income

household

with

disabilities

3

Shiyin Group

in Jiandong

Village

Jiang

Zhongxiang Female 44 342829197012223323

With

disabilities

4 Shiyin Group

in Jiandong

Zhang

Hong Female 23 342921199111233328

With

disabilities

Page 75: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 74

No. Belonging to Name Gender Age ID No. Type of

difficulties

Village

Suffering from hepatitis E, Peng Suping is low-income household of Class B, safeguarding 4

persons with 560 yuan monthly subsistence allowances; his mother has grown old and frail, his

wife is a farmer, his son is in middle school. He enjoys the treatment of subsistence allowances.

The low-income household Zhang Guangrong is living with his second son Zhangshuang

Long, and his son has severe mental disability. Two persons are safeguarded by the subsistence

allowances with 280 yuan per month. They are enjoying the treatment of subsistence allowances.

Jiang Zhongyuan, with Grade I of visual disability, lives with the head of household her

husband Xu Xueyi. She is enjoying subsistence allowances.

Zhang Hong is the granddaughter of the household’s head Zhang Sijiu, who has Grade II of

intellectual disability. She is enjoying the subsistence allowances.

3.3.8 Technical training

The resettlement work at earlier stage guarantees the migrants to obtain the compensation

specified in the Resettlement Plan, production and living standards, living environment of the

affected households are restored or improved. With the support of relevant departments, migrant

training modes include centralized training and release of fortune and popular science data for

migrants. Seven phases of centralized skills training were provided in relevant administrative

villages in 2014, 2015 respectively, centralized training content: cereals & oils and cotton planting,

production technology, oil tea cultivation technology, 912 trainees; content of popular science data:

household service, edible fungus, vegetables, melon and fruit planting technology, 1520 copies of

data have been released, totally 3213 person-times trained.

Page 76: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 75

Picture3-7 Site of technical training

Page 77: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 76

Picture 3-8 Technical training data and content

Page 78: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 77

Figure 3-9 kick off meeting for external monitoring of resettlement in Dongzhi County

Figure 3-10 interview of resettlement monitoring and evaluation group

3.4 S319 Wuwei to Erba Construction Project Resettlement Monitoring

and Evaluation Process

In the start up stage of resettlement works in S319 subproject, the monitoring team from

AJEPM has conducted field investigation and interviews on this project’s resettlementin October

2014. Inception Report on External Resettlement Monitoring has been provided to ADB by

AJEPM in September 2014. In September 2014, AJEPM submitted the start report of external

monitoring on resettlement to ADB, which systematically described the monitoring organization,

monitoring work plan and outline during the implementation of the project.The Report has

systematically stated the monitoring organization, schedule and TOR during the implementation of

this project.

External Monitoring Group has conducted a comprehensive inspection on resettlement works

of Road S319 during 12 to 13 January 2015 along with APMO, Wuhu Municipal Transport Bureau,

etc. June 2015, External Monitoring Group conducted field investigation and interviews on the

resettlement progress, submitted the first External Monitoring Report. In Sept., Dec. 2015, and

April 2016, External monitoring agency conducted sampling survey on compensation standards,

compensation and living standards of the affected households.

The land acquisition and demolition work for the reconstruction project ofS319 Erjun Road

Page 79: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 78

(Erba Wuwei) class I Highway in Wuwei County has been completed. The permanent land

acquisition of the project is 304.7252 mu, and the temporary land occupation is 71.37 mu. The

housing demolition of the project involves 56 houses and 2 enterprises. The total demolition area

is 12277.83m2.

3.4.1 House Demolition and Resettlement

The project involves the houses of rural residents in Fudu community and Hualong co

mmunity of Dougou town. The house demolition involves 56 houses and 2 enterprises, wit

h a total demolition area of 12277.83 ㎡. The area of 56 households is 9947.91 ㎡, and t

he compensation amount is 6.43145 million yuan; the demolition area of the other two ent

erprises is 2329.92 ㎡, and the compensation amount is 5.4415 million yuan; the total de

molition area is 12277.83m2. Among them, there are 4 households in Dougou town with

an area of 461.44 ㎡, 52 households in Fudu town with an area of 11816.39 ㎡. Of the

56 households, 6 choose monetary compensation and 50 choose centralized resettlement, wi

th 110 resettlement houses.

Table 3-7 statistics of housing demolition area

Contents Towns

Number of relocated

households(hu)

Demolition area

(㎡)

Compensation for

demolition(yuan)

Dougou Town 4 461.44 509826.81

Fudu Town 52 11816.39 11363124.42

Total 56 12277.83 11872951.23

By December 30, 2019: among the 50 households of centralized resettlement, 24 households

have been fully resettled (38 resettlement houses), 17 households have not been fully resettled (54

resettlement houses should be resettled, 24 resettlement houses have been actually resettled), 9

households have not been resettled (18 resettlement houses), that is, 110 resettlement houses have

been resettled 62 sets, and 48 more need to be resettled. The main reasons for incomplete

resettlement and non resettlement are as follows: first, the housing resources of type C (90 ㎡)

Page 80: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 79

resettlement agreed by resettlement community (Chengdong new area) are insufficient; second,

some resettlement households have multiple resettlement houses, voluntarily give up the

resettlement housing resources of Chengdong new area, and they are required to be resettled in

different resettlement areas.

The resettlement community under construction includes Jingfuyuan, Linyu, Donglefu, etc. in

September 2019, the house number of the relocated households has been selected, and the

resettlement house is planned to be delivered centrally during the Spring Festival in 2020. During

the period of waiting for resettlement, the transition fees of resettlement households have been

paid in full on time, and most of the households who have not been allocated have also selected

1-2 sets of resettlement houses or other housing in Chengdong new area.

Figure 3-11 resettlement site of Chengdong new area

3.4.2 State-owned Land Acquisition Area

S319 mu of state-owned land as transferring land will be occupied permanently for the

subproject, affecting two enterprises (Changba Cotton Industry Co., Ltd. & Fangsu Edible Fungi

Co., Ltd. ) with 45 workers. Externalmonitoring group learned that, after consultation with

affected enterprises, Changba Cotton Industry Co., Ltd. was eliminated due to market factors, the

owner agreed only cash compensation; Fangsu Edible Fungi Co., Ltd. Agreed the resettlement

mode of relocation and cash compensation.

Page 81: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 80

Current Status of Wuwei Changba Cotton Industry Co., Ltd.

Interview in Wuwei Fangsun Edible Fungi Co., Ltd.

Figure 3-12 pictures of state owned land enterprises before demolition

See table 3-8 for state-owned land acquisition

Table 3-8 List of state owned land acquisition

Town Village Village

group Name of Enterprises Area(mu) Nature Aps Compensation (ten

thousand RMB)

Fudu

Town

Fudu

Community Changba

Changba Cotton Industry Co.,

Ltd. 5.7 Transfer 30

299.9393

Fudu

Town

Fudu

Community Changba Fangsun Edible Fungi Co., Ltd. 5 Transfer 15

244.2107

total 2329.92 45 544.15

3.4.3 Permanent Land Acquisition

The project actually completed 304.7252 mu of permanent land acquisition, 184 Mu less than

the resettlement plan. The reason is that other projects in Fudu town have been levied by the

government, and there is no need to levy repeatedly in this project. (The land requisition has been

used for the construction of the project, and the land acquisition standard is the same as the

compensation standard for land acquisition of the project)

See Annex 40 for land acquisition agreement

3.4.4 Temporary Land Acquisition

According to the final Resettlement Plan, this subproject will involve 199mu of temporary

Page 82: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 81

land for borrow pits and disposal sites in Fudu Town&Shijian Town of Wuwei County. Of which

9.87 mu in Shibei Village, Fudu Town is occupied for mixing station in Contract 02; 7.22 mu in

Wangfu Administrative Village Lingzhuang Natural Village of Wucheng Town is occupied for the

mixing station, reinforcement processing plant in Contract 03; 7.89 mu in Changba Village, Fudu

Town is occupied for temporary spoil grounds.

3.4.5 Restoration and Reconstruction of the Affected Special Facilities

S319 project involves the relocation and reconstruction of facilities such as water supply

pipelines, communication optical cables, high voltage rod lines and signs along the whole route.

To adhere to the principle of “minimum impact”, mobilization and coordination meetings on

demolition works of rod lines, pipelines and signs along the route were held by the Wuwei County

Headquarters on June 26 and November 13, 2014 as well as April 13, 2015. The meetings have

determined the contacts and responsible departments to negotiate with various property units

including power supply, China Mobile, China Telecom, China Unicom, Cable Television and

water supply companies. Currently, specific compensation rates and quantities are under

negotiation.

For the relocation of high and low voltage rod lines (K0 + 000 ~ K18 + 000) involved in

S319 project within Jiujiang District, Jiujiang District Construction Commission entrusted by

Wuhu Municipal Transport Bureau will sign an agreement with electrical contractor and be in

charge of relocation; for relocation of water supply pipelines within the scope of 35m from the

center line to both sides of the downtown section, Jiujiang District Resettlement Office will be

responsible for negotiation with the property owner of water supply together with Erba and

Tanggou Town Governments; the section from K7 + 000 ~ K18 +000 is relocated within the scope

of 18m from center line to both sides; weak current rods&lines and underground cables will be

executed by Wuhu Municipal Transportation Bureau in accordance with the document of GG

[2014] No.96, and the specific construction will be conducted bythe project construction office.

All need to remove the non-benchmark lines (K0 + 000 ~ K18 + 000) is responsible for the

Jiujiang.

External monitoring group learned that, relocation status of pole and pipe lines for S319 Erba

to Wuwei Section Reconstruction project (Urban Area Section) as of June 30, 2016 are as follows:

Page 83: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 82

the original 16 m wide pavement was widened to 25.5 m, the land in the widened construction

scope was already acquired in 2000, now becomes road shoulders and side ditches. Through

investigation, except Italian poplars, buried optical cables, tap water pipes and a number of

communication and power rod lines across highway, there are no house and other ancillary

facilities in the widened scope, personnel resettlement did not occur.

3.4.6 Vulnerable Groups Affected

According to the final report of the migration plan, the project involves 28 vulnerable groups,

including 7 households with five guarantees, 21 households with low guarantees and 3 disabled

people. After the field investigation, the external monitoring team learned that: Erba and Tanggou

did not involve vulnerable groups, Dougou and Fudu towns involved 16 vulnerable groups, 11

low-income households and 1 disabled person.

The external monitoring team learned that the low-income insurance households currently

enjoy the low-income insurance treatment, with the standard of 150 yuan / month.

3.5 S367 Ma’anshan Northern Passage Road Resettlement Monitoring and

Evaluation Process

External monitoring survey group learned that, since permanent land acquisition required for

construction was not approved at early stage of the project, land acquisition and demolition was

not carried out substantially for the project. In Feb. 2016, land use formalities required for project

construction was approved by the Ministry of Natural Resources, land acquisition and demolition

was started for the project from Apr. 2016. Since May 2016, typhoon in coastal areas of China

caused rainstorm and flood disasters in the districts of Anhui Province, delayed acquisition and

demolition seriously, so acquisition and demolition for this project proceeded slowly. At the end of

July 2016, land acquisition and demolition work was officially started. In June 2019, the land

acquisition, demolition and resettlement of the project were completed.

The S367 project involves Hanshan and Hexian counties.

Table 3-9 summary of land acquisition and demolition of S367 project

Page 84: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 83

contents

towns

Land

acquisition

area

(mu)

Compensation

for land

acquisition

(ten thousand

yuan)

Relocated households(hu)

Demolition

area

(㎡)

Demolition

compensation

(ten thousand

yuan)

Compensation

for

appurtenances

and structures

only(hu)

Compensation

for

appurtenances

and structures

(ten thousand

yuan))

Within

the red

line

Outside

the red

line

subtotal

He County 958.694 3625.2244 100 43 143 17589.49 2546.8864 22 20.0184

Hanshan

County 279.2591 927.8015 25 5 30 3627.8 839.7462 0 0

total 1237.9531 4553.0259 125 48 173 21217.29 3386.6326 22 20.0184

The permanently expropriated land in Hanshan county is 279.2591 mu, and the compensation

for land acquisition is 9.278015 million yuan, including 30.8918 mu, 1.13613 million yuan,

24.83673 mu, 8.141912 million yuan in Xianxu Town, Zhaoguan town. The project involves 30

households of house demolition, including 7 households within 5m outside the red line, with a

total area of 3627.8m2, all of which are monetary compensation, with a compensation amount of

8.397462 million yuan.

The main reason for the demolition within 5m outside the red line of Hanshan county project

is that the houses outside the red line of land acquisition along the road are close to the road.

Considering the factors such as ensuring the operation safety after the completion of the road, the

residents took the initiative to require the demolition. Referring to the relevant practices of land

acquisition and relocation of other highways (such as S226 and S105) in Hanshan County, the 16th

executive meeting of the people's Government of Hanshan county decided on June 22, 2018 to

demolish the main houses of households along the project within 5 meters (including 5 meters)

from the red line of highway construction land.

The permanent land acquisition of the project in Hexian county is 958.694 mu, with the

compensation amount of 36.25224 million yuan, including 561.786 mu in Shanhou Town, with the

compensation amount of 22.353622 million yuan, and 396.908 mu in Shiyang Town, with the

compensation amount of 13.898622 million yuan. The project involves the demolition of 143

houses, with a total area of 17589.49 ㎡, and a total compensation of 25468864 yuan. Shanhou

town involves 83 households of house demolition (including 19 households within 3 meters

Page 85: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 84

outside the red line), with demolition area of 9938.33 ㎡ , compensation amount of RMB

13.514535 million; only 22 households of accessory and structure compensation, compensation

amount of RMB 201.84 million, total compensation amount of RMB 13.714719 million.

In Shiyang Town, Hexian County, 60 households (including 24 households within 3 meters

outside the red line) are involved in house demolition. The demolition area is 7651.16 ㎡, and the

compensation amount is 11954329 yuan. The main reason for the demolition within 3 meters

outside the red line of land acquisition of Hexian county project is that the residential houses are

close to the red line of land acquisition. Considering the factors such as ensuring the operation

safety after the completion of the road, the residents took the initiative to require the demolition.

Figure 3-13 Ma'anshan data collection by monitoring group

3.5.1 House Demolition and Resettlement

1) Demolition

The demolition of this project does not involve the demolition of non residential houses. They

are all rural residential houses.

See Annex 41 for the agreement on compensation and resettlement for house demolition.

Hanshan project involves 30 households of house demolition, including 7 households within 5m

outside the red line, with a total area of 3627.8m2, all of which are monetary compensation, with a

compensation amount of 8.397462 million yuan.

The permanent land acquisition of the project in Hexian county is 958.694 mu, with the

compensation amount of 36.25224 million yuan, including 561.786 mu in Shanhou Town, with the

compensation amount of 22.353622 million yuan, and 396.908 mu in Shiyang Town, with the

Page 86: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 85

compensation amount of 13.898622 million yuan. The project involves the demolition of 143

houses, with a total area of 17589.49 ㎡, and a total compensation of 25468864 yuan. Shanhou

town involves 83 households of house demolition (including 19 households within 3 meters

outside the red line), with demolition area of 9938.33 ㎡, compensation amount of RMB

13.514535 million; only 22 households of accessory and structure compensation, compensation

amount of RMB 201.84 million, total compensation amount of RMB 13.714719 million. Shiyang

town involves 60 houses to be demolished (including 24 houses to be demolished within 3 meters

outside the red line), with an area of 7651.16 ㎡ and a compensation of 11.954329 million yuan.

The main reason for the demolition within 3 meters outside the red line of land acquisition of

Hexian county project is that the residential houses are close to the red line of land acquisition.

Considering the factors such as ensuring the operation safety after the completion of the road, the

residents took the initiative to require the demolition. The main reason is as shown in Figure 3-24.

Figure 3-14 residential houses along the widening section

Page 87: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 86

2) Resettlement

Of the 143 households involved in house demolition in the Hexian project, 83 households in

Shanhou town were all monetary compensation; 4 households in 60 households in Shiyang town

were property right replacement resettlement, of which 3 households were concentrated in the

resettlement site of Daima in Shiyang community, 1 household was relocated in other places, and

the others were monetary compensation.

Figure 3-15 centralized resettlement site of Daima in Shiyang community

3.5.2 Permanent Acquisition of Collective Land

The permanently expropriated land in Hanshan county is 279.2591 mu, and the compensation

for land acquisition is 9.278015 million yuan, including 30.8918 mu, 1.13613 million yuan,

24.83673 mu, 8.141912 million yuan in Xianxu Town, Zhaoguan town.

The permanent land acquisition of the project in Hexian county is 958.694 mu, with the

compensation amount of 36.25224 million yuan, including 561.786 mu in Shanhou Town, with the

compensation amount of 22.353622 million yuan, and 396.908 mu in Shiyang Town, with the

compensation amount of 13.898622 million yuan.

3.5.3 Temporary Land Occupation

The temporary land occupation of the project is rural collective land, and all of them are

unused land. The property right belongs to the village collective, so the project does not affect the

population. Compensation shall be made according to the compensation standard.

Page 88: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 87

3.5.4 Pole Line and Other Infrastructure

The whole line units of the project are divided into mobile, Unicom, telecom, national

defense and township waterworks. Compensation shall be made according to the compensation

standard.

3.5.5 Vulnerable Groups Affected

The affected population of the project is all Han nationality. According to the survey, the main

vulnerable groups of the project are low-income and five guarantee households. According to the

survey, 55 households and 164 people are vulnerable groups. In the whole process of resettlement,

PMO, implementing agencies and local governments paid special attention to the resettlement of

vulnerable groups. In addition to living and production resettlement for vulnerable groups

according to the project implementation plan, it also provides some help to improve production

and living conditions. Mainly as follows:

Five guarantees

The village collective reserves the compensation, provides the allowance to the five

guarantees every month, and provides the free medical treatment;

Low security households

1) Two family members in each household have access to technical training opportunities, at

least one of them is female. Meanwhile, priority should be given to arranging employment

opportunities related to project construction, providing them with employment related information,

etc.

2) Local governments pay pensions.

In addition to the above vulnerable groups, the households seriously affected by land

acquisition (the land loss rate is more than 10%) will also enjoy the following measures:

1) More than 10% of the seriously affected households will be given priority to the

employment opportunities for the construction and operation of the project, and participate in

various agricultural and non-agricultural technical training for the farmers who have been

Page 89: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 88

requisitioned for the project.

2) If possible, the replaceable land will be given priority.

Figure 3-16 Ma'anshan household survey by resettlement monitoring group

3.6 G318 and S320 Yimu Highway Project Resettlement Monitoring and

Evaluation Process

Field investigation was conducted for ADB-financed Anhui Nanling County Yimu Highway

Project in Sept. 2014. Inception Report on External Resettlement Monitoring has been provided to

ADB by the Company in September 2014. The Report has systematically stated the monitoring

organization, schedule and TOR during the implementation of this project.

According to Nanling County Yimu Highway Project Resettlement Plan (before updating),

resettlement work would start from March 2014, end in Dec. 2014, so Nanling County Project

Office started publicity of resettlement policies and compensation standards into households

related to the project from May 2014. Nanling County Project Office completed land acquisition

setting-out, house measurement and registration from May to Dec. 2014; and signed compensation

Page 90: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 89

agreement with the affected households. Meanwhile, Anhui Jiaoyuan Engineering Project

Management Co., Ltd. Entered the project site for investigation and visits, focus on the

resettlement progress. Dec. 2015, resettlement plan of this project based on detailed investigation

was approved by ADB. From November to December 2015, April, October and December 2016,

the resettlement monitoring team conducted an investigation on the resettlement progress of Yimu

road in Nanling County.

The monitoring evaluation group learned from this investigation that, Nanling Yimu Highway

project acquired permanent land 654.71 mu as of Jun. 30, 2016, completed proportion 94.02%;

acquired temporary land 353.5 mu, completed proportion 37.81%; Areas of house demolition 3813

㎡, completed proportion 55.45%; land compensation fee 13.51 million Yuan was paid, completed

proportion 81.63%; compensations for house demolition 2.515 million Yuan was paid, completed

proportion 18.98%.

Figure 3-17 monitoring team visit

Figure 3-18 resettlement training and field discussion

Page 91: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 90

Figure 3-19 data collection of Yimu road by monitoring team

Figure 3-20 interview survey of resettlement monitoring group

The acquisition and relocation of Yimu highway in Nanling County mainly involves

Gongshan town and Jishan town. In June 2019, the land acquisition and relocation work was

completed. Permanent land acquisition is 479.4 mu, accounting for 49.314% of the planned

number of immigrants; house demolition area is 6706.76 m2, accounting for 87.72% of the

Page 92: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 91

planned number of resettlement.

Table 3-10 summary of land acquisition and demolition of Yimu highway

contents

towns

Land acquisition

area(mu)

Compensation for land

acquisition

(ten thousand yuan)

Number of

demolition

households

(hu)

Demolition area

(㎡)

Compensation for

demolition

(ten thousan yuan)

Gongshan Town 337.86 976.8163 15 3127.13 16.7045

Jishan Town 141.54 1061.3184 23 3579.63 585.6

Total 479.4 2038.1347 38 6706.76 602.3045

The reason why the number of land acquisition and demolition is less than that of the

resettlement plan: in other projects of Jishan Town, the government has completed the land

acquisition and demolition of some land houses, so it is not necessary to repeat the expropriation.

3.6.1 Housing Demolition and Resettlement

The demolition area of Gongshan town is 3127.13 ㎡, and 15 households are involved in the

demolition, of which 14 households are resettled in Daitang community, one household is

monetary compensation, and the compensation amount for demolition is 167045 yuan.

The demolition area of Jishan town is 3579.63 ㎡ , involving 23 households in total,

including 13 households and 10 non residential houses (individual businesses), with the

compensation amount of 1981762 yuan.

All the 10 households of non residential house demolition are property right replacement,

while resettlement, the part of business area is compensated by 600 yuan / m2, see the following

table for the specific compensation amount.

Table 3-11 list of affected individual businesses

No. Self employed householder Area(㎡) Compensation amount(yuan)

1 Yuan yuxia 57.45 34470

2 Wang jianhui 62.11 37266

3 Wang yifa 62.11 37266

Page 93: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 92

No. Self employed householder Area(㎡) Compensation amount(yuan)

4 Zheng aiying 63.00 37800

5 He hongxiang 63.36 38016

6 Fan hunyin 55.08 33048

7 Hu shiwen 63.00 37800

8 Huang jinlin 94.20 56520

9 Yi changshou 82.93 49758

10 Zhangshun 66.98 20094

Total 670.22 382038

See Annex 43 for the agreement on compensation and resettlement for house demolition.

According to the relevant staff of Jishan Town, the resettlement sites of Jishan town include

Qilin villa, Meiyuan New Village Phase II and Chengbei phase II for the relocated households to

choose from.

Kylin Villa

Page 94: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 93

Meiyuan New Village Phase II

Chengbei phase II

Figure 3-21 resettlement community

3.6.2 Permanent Acquisition of Collective Land

The land acquisition and demolition work in Nanling County involves Jishan town and

Gongshan town. In Gongshan Town, 337.86 mu of land is permanently expropriated, and the

amount of land compensation is 9.768163 million yuan. Jishan town permanently expropriates

141.54 mu of land, and the amount of land compensation is 10.613184 million yuan. The part of

collective land within the red line of Jishan town has been expropriated by other projects from

2005 to 2013, so it does not need to be expropriated again.

See Annex 44 for land acquisition agreement.

Page 95: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 94

3.6.3 State Owned Land

In June 2019, a total of 7 state-owned land acquisition projects were finally determined. In

December 2017, 7 state-owned land assessments were completed and compensation agreements

were signed, and compensation funds were issued.

No. Name of Affected Unit Compensation(ten thousand yuan)

1 China National Gas Corporation 59.4655

2 Peng Zhenhua 13.9842

3 Zhenyun logistics company 250.7895

4 South bus station 62.3403

5 PetroChina gas station 158.6962

6 Wuhu Hongshun Real Estate Development Co., Ltd 105.3729

7 Wuhu Tengxin Industry Co., Ltd 1.5455

3.6.4 TemporaryLand Acquisition

353.5 mu of temporary land for the project:

Lot 01 mixing plant is located in Mingtai glass plant, No. 18 Huashan Road, Nanling

Economic Development Zone, covering an area of about 30 mu; small prefabrication plant is

located in Nanling Development Zone, covering an area of about 10 mu; borrow pit is located in

the south side of Nanling Development Zone, covering an area of about 100 mu; waste dump is

located in LUOJIACHONG, Dagang village, Jishan Town, Nanling County, covering an area of

about 60 mu;

Lot 02 mixing plant is located in Gongyi village, Gongshan Town, Nanling County, covering

an area of about 60 mu; small prefabrication plant is located in Gongshan Town, Nanling County,

covering an area of about 15 mu; borrow pit is located in Gongyi village, Gongshan Town,

Nanling County, covering an area of 50 mu; spoil heap is located in Gongyi village, Gongshan

Town, Nanling County, covering an area of about 15 mu; lot 02 road or other infrastructure is

located in Gongshan Town, Nanling County, covering an area of about 10 mu.

Page 96: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 95

3.6.5 Infrastructure

The project has a total impact on walls, fences, cement floors, poles, wires, street lights,

junction boxes, transformers, graves, wells, trees, etc. All of them are compensated according to

the compensation standard.

3.7 Shuiyang River Integrated Transport Construction Project

Resettlement Monitoring and Evaluation Process

Nov. And Dec. 2015, Anhui Jiaoyuan Engineering Project Management Co., Ltd.

Resettlement Monitoring Group carried out field investigation on the ADB-financed Anhui

Shuiyang River Integrated Transport Construction Project, provided training for resettlement work

of this project.

Picture 3-22 Shuiyang River Resettlement Training Meeting

Picture 23- Baseline Survey on Living Standards of the Farmers Affected by Shuiyang River

Integrated Transport Project

In December 2016, the external monitoring team went to the water Yangjiang project site to

Page 97: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 96

investigate and interview the progress of resettlement work, and completed the external monitoring

report of resettlement in this period. From June to July 2016, the rainstorm and flood disaster

weather in Anhui Province led to no significant progress in the relocation work. By the end of

November 2016, the land acquisition and demolition of Xuanzhou port comprehensive wharf and

Xiaohekou bridge project were completed. In December 2016, land acquisition and demolition

work for waterway regulation began.

By the end of June 2018, the permanent land of 917.52 Mu has been expropriated for the

Shuiyangjiang shipping comprehensive construction project; the house demolition area is 8544.24

m2.

Table 3-12 statistics of land acquisition and demolition of Shuiyangjiang shipping project

Port engineering

Permanent land acquisition

(mu) Demolition area(m2)

RAP plan Actual RAP plan Actual

499.5375 447.71 5203 4660.9

Waterway

Engineering

Xiaohegou

bridge

406.6155

37.13

2860

925.61

Gate dam 353.4 772.78

Channel

dredging 79.28 2184.95

Subtotal 406.6155 447.71 2860 3883.34

合计 906.153 917.52 8063 8544.24

3.7.1 house demolition and resettlement

As of December 2016: 8544.24 ㎡ of houses demolished in the project. 4660.9 ㎡ of port

engineering demolition; 3883.34 ㎡ of channel engineering house demolition, including 925.61

m2 of Xiaohekou bridge demolition, 772.78 m2 of gate dam demolition, 2184.95 m2 of channel

dredging demolition. The resettlement is as follows:

1) Resettlement of Xuanzhou port comprehensive Wharf Project

Page 98: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 97

Xuanzhou port comprehensive wharf project involves demolition of 28 residential houses

(including 1 smoke pit), with demolition area of 4660.99 ㎡. 26 of these relocated households

choose the way of property right replacement for resettlement, and 2 households choose monetary

compensation for resettlement. A total of 60 houses with an area of 5780 ㎡ need to be resettled

in the way of property right replacement. The local government plans to place the resettlement

houses in the "Huishang No.1" community.

As of June 30, 2019, the monitoring team learned that the developer responsible for the

construction of "Huishang No.1" had gone bankrupt and was being restructured; the resettlement

community could not be completed on schedule, and the 26 relocated households to be resettled

were still in the transitional period; the government of Yangxian Township had paid the transitional

fee for the first half of 2019.

2) Arrangement of Xiaohekou Bridge

The Xiaohekou bridge project involves the demolition of 11 houses. One of the relocated

households chose to resettle 10 old workers' dormitories with monetary compensation. The

property right of the houses belongs to the pottery factory under the county economic and

Information Commission. Xuanzhou District Economic and Information Commission has built 10

new resettlement houses in the pottery factory and continued to place the original households in

the resettlement houses. The auxiliary facilities of the original demolished houses have been

compensated to each household in currency. The resettlement housing construction project was

started on May 10, 2018, delivered in June 2019, and the transition fee has been issued.

3) Gate and dam project placement

The demolition of the project involves three houses, a shipyard, a water intake of a water

plant and a slaughterhouse. Among the three households, one house is shifted, two houses are built

on their own and one house is compensated with money. The demolition area is 772.78 ㎡, and

the compensation amount is 1042619 yuan. The shipyard has been closed for many years, and it

does not have the conditions to continue its business. The compensation amount is 5603238 yuan.

The water intake of the waterworks does not meet the requirements of the health code after the

completion of the shiplock The relocation of the water intake is carried out and the cost is paid by

Page 99: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 98

the project owner. The relocation of the water intake has been completed. At present, the advance

payment of 4.43 million yuan has been paid, and the final cost will be settled according to the

actual situation after the government audit. After receiving monetary compensation, the

slaughterhouse improved its operation conditions and continued its production and operation.

4) Demolition and resettlement of waterway dredging project

The demolition involves 23 houses and 2 ship building factories in Liqiao town. 23

households have been demolished, among which 13 households have chosen monetary

resettlement and 10 households have chosen non local resettlement. The demolition area is

2184.95 ㎡, and the compensation amount is 2483099 yuan. The resettlement of non local

resettlement is chosen in the new rural resettlement site of Dongyun village. Two ship repair and

construction plants are monetary compensation, with the compensation amount of 3.06 million

yuan.

Figure 3-25 resettlement site of Dongyun New Village

3.7.2 Permanent Land Acquisition

The three sub items of the project involve collective land and state-owned land acquisition.

The land acquisition of the project involves 5 villages and 7 villagers' groups in Yangxian

Township, Liqiao town and Shuiyang Town, Xuanzhou District, Xuancheng City, Anhui Province.

A total of 917.52 mu of land is permanently expropriated for the project, including 447.708 mu of

port works and 469.81 mu of waterway works.

Page 100: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 99

3.7.3 Temporary Land Acquisition

Temporary land for construction refers to the land temporarily borrowed during the

construction period of the project, including the land occupied by borrow areas, production and

living areas and temporary roads during the construction period. The temporary land occupation of

the project is mainly the temporary land occupation of the dumping site, which does not involve

the temporary land occupation of the borrow area. Compensation shall be made according to the

compensation standard.

3.7.4 Infrastucture

The project affects 350kv high-voltage line, 10kV line, irrigation and drainage station,

transformer, etc., and compensates according to the compensation standard.

4 Compensation standard for Resettlement

According to the regulations and policy requirements of the Chinese government and the

Asian Development Bank, the principle of compensation and rights and interests of the project is

formulated. The goal is to ensure that the resettlers receive adequate compensation and assistance

measures, at least to ensure that their living standards are restored to the level before the project

starts. The resettlement principles of the project can be seen in table 4-1.

Table 4-1 The project resettlement principles

Principles

1 If possible, avoid involuntary resettlement

2 The compensation and rights that the affected people get can be maintained as their living

standards before the "no project" state, and may also improved.

3 Regardless of legal rights or not, the affected people will receive resettlement compensation

and assistance.

4 If the land of each person after land acquisition is not enough to sustain his / her livelihood,

the loss of land shall be compensated in cash or material, as well as other income generating

activities.

5 The affected people have a full understanding of the qualifications, compensation methods

and standards, livelihood and income recovery plan, project schedule, and participate in the

Page 101: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 100

Principles

implementation of the resettlement plan.

7 The implementing agencies and independent / third parties will monitor the operation of

compensation and land acquisition and resettlement.

8 Vulnerable groups receive special assistance or treatment to ensure that they live better, and

all affected groups should have the opportunity to benefit from the project. Each resettling

family has two family members who have received skills training, at least one is a female.

9 The resettlement plan is consistent with the overall plan of the affected cities (districts,

counties) and towns.

10 The resettlement costs will fully cover all affected areas in full.

4.1 G206 Dongliu to Yaodu Project Compensation Standard

4.1.1 Land acquisition standard

G206 Dongliu to Yaodu Permanent land required for the project has received the approval of

Anhui Provincial Government (see Attachment 1). Approved land area 1032.96 mu, the approved

land quantity exceeds permanent land quantity in the resettlement action plan and actually

acquired land quantity.

It is learned through investigation that, after procedures of submission for approval on land

are completed, each villager and household affected by land acquisition have signed resettlement

grant agreements (Attachment 4), the compensations for appendages on the expropriated land,

crop compensation fees and resettlement subsidies owned by individuals have been directly

transferred to the account provided by the farmers in the form of cash.

The situation of social insurances for households with less than 0.3mu arable land per capita

after land acquisition are not involved in the project land acquisition.

4.1.1.1 Quantity and Compensation Standard for Collective Land Acquisition

Table 4-2 Compensation standard for permanent collective land acquisition

Region Farmland Construction Land and Unutilized Land

Page 102: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 101

Updated

Planned

Actual

Executed

Received

By

household

Updated

Planned

Actual

Executed

Received

By household

Zhaqiao, Maotian,Jiandong

Villages in yaodutown 36800 36800 36800 18400 18400 18400

Guanshan Village in Yaodu Town 32780 32780 32780 16390 16390 16390

Dongliu Town 32780 32780 29651 16390 16390 16390

In accordance with the stipulations in the Notice of the Anhui Provincial Government on

Adjusting Compensation Rates for Land Acquisition of Anhui Province (APG [2012] No.67), and

Work Scheme for Land Acquisition of G206 Dongliu to Yaodu Construction Project in Dongzhi

County(DLZ[2013] No.31), Agreement for Compensation on Land Acquisition have been reached

after consultation among Town’s Government, Village Committee and villagers affected land

acquisition. According to the compensation standards indicated in above mentioned two

documents, the land is provided. The compensation standards are:

(I) Agricultural land:

(1) the compensation standard of 32,780 Yuan/mu will be used in Xiayang, Zhanggang,

Villages in Dongliu Town and Guanshan Village in Yaodu Town, of which it has paid

29,651yuan/mu to each household (i.e.land compensation (70%) with the standard of

7,301yuan/mu + resettlement subsidy with the standard of 22,350 Yuan/mu);

(2) the compensation standard in Zhaqiao, Maotian, Jiandong Villages in Yaodu Town is

36,800 Yuan/mu. Of which, each household has received 32,960 Yuan/mu (i.e.land compensation

fee(70%) with the standard of 8960 Yuan/mu + resettlement subsidy of 24,000 Yuan/mu);

30% of land compensation will be allocated to collective-economic organization in village

level, which will be used for public welfare organizations and safeguard for land-lost peasants in

village level within the region of land acquisition and resettlement.

Withdrawal and Retention are on the basis of “Notice of Issuance of Work Scheme for Land

Acquisition of G206 Dongliu to Yaodu Construction Project in Dongzhi County” (DLZ [2014]

No.1). During the actual implementation, full compensation amount of land acquisition have been

Page 103: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 102

paid to farmers with two time appropriation and without withdrawal and retention in any forms by

Yaodu Town according to farmers’ requirements.

(II) Compensation standard for young crops is 700 Yuan/mu.

(III) Annual rent of temporary land is 1390 Yuan/mu.

(IV) according to the Resettlement Plan and WZ [2012] No.67 Document, the compensation

standards for unused land and construction land take a half of compensation rate for agricultural

land.

To summrize the above-mentioned indicators, compensation standards for permanent

acquisition of collective land meet the compensation standards of the project in the resettlement

plan, and meet policy requirements in China.

4.1.1.2 Area and Compensation Standards for State-owned Land Acquisition

Township Dongliu Town Yaodu Town

Permanent occupation

planned compensation standard 32780yuna/mu 36800yuan/mu

Permanent occupation

executive compensation standard 36800yuan/mu 36800yuan /yuan

Compensation for the woodland acquired for the Subproject is based on the Notice of the

Anhui Provincial Government on Adjusting Compensation Rates for Land Acquisition of Anhui

Province (APG [2012] No.67) (May 19, 2012), whose Article 2 writes, “If land of a state-owned

agricultural (forest, livestock or fish) farm is acquired, the compensation rates for land acquisition

of the area in which such farm is located shall apply. If such farm spans more than one area, the

highest rate of such areas shall apply. “It is stipulated that the compensation rate for state-owned

farmland is 36,800 Yuan/mu in Yaodu Town, and that for state-owned construction land and

unused land 18,400 Yuan/mu; the compensation rate for state-owned farmland is 32,780 Yuan/mu

in Dongliu Town, and that for state-owned construction land and unused land 16,390 Yuan/mu; the

compensate rate for temporary land is 1,390 Yuan/mu rent per year; Temporary land will be

restored to woodland after completion, which the charge of vegetation restoration will be paid by

Page 104: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 103

property owner to provincial finance in accordance with the standard of 6yuan/m2 to be used for

vegetation restoration of temporary land..

Monitoring Group County learned from Dongzhi County Forestry Bureau that, two parties

have signed an agreement on permanent land acquisition, actual compensation amount of

permanent land acquisition in state-owned woodland is 3,509,952 yuan with compensation rate

executed in deed is 16,000 Yuan/mu as of Oct. 2014. The compensation standards for temporary

forest land acquisition is also compensated in accordance with the compensation standard for

permanent forest land requisition of 16,000 Yuan/mu, and make a clear definition in the Agreement

for temporary land acquisition that, if the forest land acquired for this project temporarily will be

used for commercial exploitation in the future, the compensation fund should make up any

difference as the compensation rate during land acquisition. The forest farm is responsible for the

cutting works of trees in woodland acquired, and the timbers owned by the forest farm. Given the

forest farm may be used for commercial development in the future, involving compensation again,

and the discrepancy of compensation amount this time have no impact on the forest farm;

meanwhile taking into account Dongzhi County Government having actual difficulties in

counterpart fund, two forest farm have agreed by Staff Meeting held (meeting documents

Attachment 6) that the compensation rates for permanent and temporary land are carried out in

accordance with the standard of 16,000 Yuan/mu, and signed Agreements of Land Acquisition of

their own accord.

Since Dongzhi government paid compensation to 2 Forest farms according to the

compensation standards lower than the compensation standards in the Resettlement Plan, External

monitoring agency disclosed this issue in previous monitoring report, which arounsed the attention

of Anhui PMO, Anhui PMO obliged Dongzhi PMO to compensate according to the compensation

standards in the Resettlement Plan, supplement the difference. On March 18, 2015, G206 Dongliu

to Yaodu Section Construction Project Coordination Office signed additional compensation

agreement with Meicheng Forestry, Jin Sishan Forestry, executive compensation standards of the

original compensation agreement were adjusted to 36800 yuan/mu. Of Dongliu Town eventual

implementation compensation standard is 36,800 yuan/mu, higher than the RAP original

compensation standards 32,780 Yuan/mu, Woodland compensation standards of Yaodu Town36800

Page 105: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 104

Yuan/mu, which is the same with the RAP standards.

Through the interviews with the heads of two woodland and Dongzhi County Forestry Bureau,

Monitoring Group learned that Jinsishan and Meicheng Forest Farms are enterprise-style

management public institutions with its expenses paid by its earning and carrying out the principle

of “one-level accounting, two-levels management”; salaries for staff are paid according to the

wages standard of public institutions, which do not directly relate to the income of woodland.

Dongzhi County Forestry Bureau has a positive attitude to the issue of woodland acquired by this

project, and fully understands local government’s difficulties in counterpart funds; they will fully

cooperate with woodland acquisition works and process relevant approvals submission actively.

Jinsishan Forest Farm which has the area of 35,000mu, 128 employees and approximately

annual income of 10million yuan, its main revenue includes timbers felling, selling of seeding

cultivation as well as subsidies for national public welfare forest. Farm income is used for wages,

social insurance and routine office expenses. The woodland area of 105.319 mu in Jinsishan Forest

Farm are acquired for permanent land acquisition of this project, which land lost rate is 0.3%;

115,440 Yuan was paid in total during land acquisition, which is about one-tenth of annual income.

This compensation fund from land acquisition will be used as surplus of forest farm, not for the

purposes of payments for salaries and insurances, etc. Therefore, there is very limited impact on

forest farm’s income and living levels of staff.

Founded in 1958, Meicheng forest farm now has operating area of 26000mu, 138 employees

and annual revenues of around 9 million yuan, which main income are selling of seeding

cultivation as well as subsidies for national afforestation. The forest’s annual income essentially

keeps balance with its expenditures. The woodland area of 64.20 mu in Meicheng Forest Farm are

acquired for permanent land acquisition of this project, which land lost rate is 0.25%; 1.6 million

yuan was paid in total during land acquisition, which is about one-ninth of its annual income. This

compensation fund from land acquisition will be used uniformly, not for the purposes of payments

for salaries or welfares, etc. Salaries for staff are paid according to the wages standard of public

institutions, which do not directly relate to the income of woodland. Land acquisition has no

impact on living levels of staff in Meicheng forest farm.

Page 106: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 105

To sum up the above-mentioned monitoring, compensation standards for G206 permanent

acquisition of state-owned land did not meet the compensation standards in the Resettlement Plan

approved by ADB at the beginning. After disclosed by the external monitoring agency, ADB

experts put forward feedback requirement, Anhui Provincial PMO obliged Dongzhi government to

compensate relevant fees, finally the compensation standards of the project for Permanent

state-owned land acquisition meet the compensation standards in the Resettlement Plan.

4.1.1.3 Area and Compensation Standards for Temporary Land Acquisition

According to the applicable state and provincial provisions, compensation for temporary land

occupation includes compensation fees young crops and ground attachments, and land reclamation

costs. Land will be occupied by borrow areas and spoil grounds during project construction.

All land temporarily occupied (180.9mu) is state-owned land. The borrow areas are located

on state-owned hilly land, and the spoil grounds are located on state-owned wasteland, involving

no compensation. Monitoring Group learned on-site that actual project temporary land is 201.943

mu, of which the area of temporary land for borrow pits involved compensation increases 150mu,

this is the reason about an increase of about 7 million cost.

4.1.1.4 Renting of Houses and Construction Grounds for this Project

This project is divided into two sections by public bidding organized by APMO, It needs to

rent grounds of 53.55mu according to construction needs, of which 11mu for mixing plant,

approximately 2.55mu for residential area in Contract 01, as well as 40mu for residential area in

total in Contract 02.

The mixing plant located in Lishan work area belonging to Dongzhi Highway Sub-bureau is

rent by Contract 01 as their mixing plant for 2 years with annual rent of 30,000 Yuan and paid

every year. The maintenance work area in Lishan has 11mu of temporary land acquisition.

Page 107: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 106

Picture 4-1 Mixing plant in Lishan Work Area

Dongzhi County Fangjin Furniture Factory located nearby Erjing Highway in Zhaqiao Village

in Dongzhi County was rent by Contract 01 as residential area, with construction area of

approximately 1700m2 and rent of 25,000 yuan/month, paid monthly.

The land for the second phase (about 40mu) of Dongzhi County Domestic Sewage Treatment

Plant was rent by Contract 02 used for residential construction of project manager’s department,

with annual rent 25,000 Yuan, two years and paid in a lump sum.

Dongliu Maintenance Branch Center including office building, dormitory building and dining

hall belonged to Anjing (Anhui-Jingdezhen) Expressway is leased out to Dongzhi County Urban

Management Investment Co., Ltd. (DCUMI) by Anhui Provincial Expressway Holding Group Co.,

Ltd. (APEHG). The rental area is about 2600m2,a payment of 100,000 Yuan per month for 3 years.

On behalf of Dongzhi County Government, DCUMI is responsible for external financing and

project management, and has directly authorized the right to use the rental site to G206 Project

Management Office in Dongzhi. Mixing plant of 01 Contract is the original mixing plant of

Chizhou Highway Bureau conservation work area without hardened, the land is hardened in

Contract 01. Mixing plant of 02 Contract is the original construction site of water plant without

smooth, two sections respectively hardening the land, after the end of the project, the site can still

be used, does not require restitution.

No additional collective land or state-owned land are increased for Dongzhi PMO, residential

areas for two contractors, mixing plant, which all use existing ground. The saving of land

resources is maximized, and income of original property unit is increased. After completion of this

project, the property unit could continue to use them, and reducing the cost of the restoration for

Page 108: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 107

temporary works.

4.1.1.5 Land Restoration Measures and Compensation Payment

After field investigations, Monitoring and Evaluation Goup learned that land compensation

rates are divided into three types of collective land acquisition, temporary land use as well as using

of state-owned land in accordance with the nature of highway construction land demands.

The compensation standard for collective land acquisition is decided in accordance with land

management laws and regulations including the Notice of Adjusting on Compensation Standards

for Land Acquisition issued by Anhui Provincial Government (WZ [2012] No.67) and the Notice

of Compensation Standards for Ground Attachments such as Young Crops and Housing

Expropriated in Dongzhi County Announced by Chizhou County Government “(CZ [2012] No.90).

According to the Approval of construction land use for National Road G206 Dongliu (Dongzhi) to

Yaodu Section Reconstruction Project (WZD [2012] No.1226) approved by Anhui Provincial

Government. Procedures of Land submission for approval are completed; compensations for land

acquisition are in place partly; each villager and household affected by land acquisition have

signed agreements on land acquisition and resettlement; the compensations for attachments and

young crops owned by individuals on the occupied land as well as resettlement subsidies have

been paid to individuals. Compensation is uniformly paid to town level by headquarters, then town

level will directly deposit into the accounts of individuals and village collective organization.

Compensation has been fully paid.

Regarding the resettlement subsidies for farmland acquisition, it shall be paid to land

contractor if the farmland belongs to farmers; and it shall be paid to collective economic

organization if it belongs to village collective land. Regarding the resettlement subsidies for

construction land and unused land acquisition, of which, the subsidies for unused land shall be

paid to village collective economic organization; for construction land shall be paid depending on

land use. Following the principle of “managed by village finance, deposited in special account, and

used for special purposes”, land compensations are used for public welfare and social security

within the scope of village groups affected by land acquisition.

Page 109: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 108

4.1.2 Compensation Standard for House Demolition

4.1.2.1 Compensation Standard for Rural Housing Demolition

The executable file of compensation standards for demolition is the Notice of Announcement

on Compensation Standards for Young Crops and Housing Attachments on Land Occupied in

Dongzhi County and Other Places issued by Chizhou Municipal Government (CZ[2012] No.90).

The Notice refines and improves the compensation standards in the RP, in favor of implementation

of compensation works smoothly, fairly and impartially. Specific criteria are detailed as follows:

(1) Compensation Standards for Main House Demolition

Type Structure COMPENSATION

STANDARDS in RAP

Compensation

Standards Executed Remarks

Main House

Frame structure 735 Yuan/m2 735 Yuan/m2

Masonry concrete

structure 645 Yuan/m2 645 Yuan/m2

Masonry timber

structure 510 Yuan/m2 510 Yuan/m2

(2) Compensation Standards for Outbuildings and structures

Type Features

COMPENSATION

STANDARDS in

RAP

Compensation

Standards

Executed

Outbuildings

Masonry concrete, the area are calculated

completely if the height of eaves are no

less than 2.2m; the area is reduced by half

if the height of eaves are less than 2.2m.

/ 260 Yuan/m2

Masonry bricks, the area is calculated

completely if the height of eaves are no

less than 2.2m; the area is reduced by half

if the height of eaves are less than 2.2m.

/ 140 Yuan/m2

Earth bricks, the area is calculated

completely if the height of eaves are no

less than 2.2m; the area is reduced by half

if the height of eaves are less than 2.2m.

/ 80 Yuan/m2

The houses have simple walls at four sides,

tile-roofed and the height of eaves is less / 60 Yuan/m2

Page 110: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 109

Type Features

COMPENSATION

STANDARDS in

RAP

Compensation

Standards

Executed

than 1.5m.

Pigsty,

toilet:

Masonry bricks and cement ground Toilet: 80

Yuan/m2;

live-stock shed: 30

Yuan/m2

60 Yuan/m2

Masonry concrete and cement ground 80 Yuan/m2

Floors Cement 18 Yuan/m2 18 Yuan/m2

Masonry / 10 Yuan/m2

Walls Masonry / 26 Yuan/m2

Notes: compensation standards in the Resettlement Plan are not listed completely in this table,

actual standards are universal compensation standards for domestic fund projects, more specific

and perfect than the standards in the plan.

(3) Relocation compensation standard for attachments

Items Standard

in RAP

Executive

standards Remarks

Pot and stove

Single stove / 80 yuan/piece

Compensation based on single

stove

Twin stoves / 120 yuan/piece

Triple stoves / 140 yuan/piece

Cooking

bench board / 100 Yuan/m2

Air-conditioner

Cabinet type / 220 yuan/set

Subsidies for relocation and

installation

Split type / 180 yuan/set

Window

type / 100 yuan/set

Water heater

Solar power / 100 yuan/piece

Electrical

energy / 80 yuan/piece

Coal, gas / 80 yuan/piece

Communications Telephone / / Relocation compensation in

Page 111: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 110

Items Standard

in RAP

Executive

standards Remarks

Cable

television / /

accordance with

communications department

and television station

Sanitary

equipment

Bathtub / 150 yuan/piece

Pedestal pan / 100 yuan/piece

Squatting

pan / 80 yuan/piece

Wash basin / 50 yuan/piece

Outdoor facility

Weld mesh

screen / 70 yuan/m2

Subsidies

Rolling door / 100 yuan/m2

Self-made

security door / 180 yuan/piece

Iron gate in

courtyard / 150 yuan/piece

Others

Al-alloy

doors&

windows

/ 120 yuan/m2

Subsidies

Timber

doors &

windows

/ 70 yuan/m2

PVC

DOORS &

WINDOWS

/ 140 yuan/m2

Kitchen

ventilator / 80 yuan/piece Demolished by themselves

Pool / 50 yuan/piece

Compensations

Coal pool / 50 yuan/piece

Rain shed / 50 yuan/m2

Glass fiber

reinforced

plastics

/ 80 yuan/m2

Page 112: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 111

Items Standard

in RAP

Executive

standards Remarks

appentice

Notes: for other activities outside of the scope of compensation, the compensation will be

calculated as per quality.

(4) Compensation rate for interior decoration

Items Standard in

RAP

Executive

standards Remarks

Suspended

ceiling

Wallpaper

ceiling / 18 Yuan/m2

Compensation shall be not

calculated

Fiberboard,

pinch / 15 Yuan/m2

Plaster / 28 Yuan/m2

Plywood / 25 Yuan/m2

Wall

surface

Ceramic tile / 25 Yuan/m2

Wall cloth / 22 Yuan/m2

Plywood / 25 Yuan/m2

Spraying

Painting,

ceramic,

plastics

/ 12 Yuan/m2

Interior

floor

Wood floor / 60 Yuan/m2

Floor tile / 40 Yuan/m2

Terrazzo / 20 Yuan/m2

Marble / 60 Yuan/m2

Granite / 70 yuan/m2

Painted ground / 8 Yuan/m2

Others

Skirting / 10 yuan/m Compensation calculated as per

actual measurements for

undecorated suspended ceilingand

and floor tile or floor Line / 10 yuan/m

Page 113: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 112

Items Standard in

RAP

Executive

standards Remarks

Door surround / 55 yuan/piece

Compensations

Window

surround / 45 yuan/piece

Screen / 50 yuan/piece

Screen window / 45 yuan/piece

(5) Compensation standards for attachments such as scattered trees, garden plant

Diameter of trees

(cm)

General tree Fruit trees

Standard in RAP Executive

standards

Standard in

RAP Executive standards

2.0~10.0 / 5yuan/tree / 8 yuan/tree

11.0~15.0 / 15 yuan/tree / 30 yuan/tree

16.0~20.0 / 20 yuan/tree / 40 yuan/tree

Above 21.0 / 35 yuan/tree / 50 yuan/tree

Grape

/ Bearing no fruit: 15

yuan/tree

/ Bearing fruit: 70

yuan/tree

Moso bamboo / 10 yuan/tree

Tea trees in tea garden / 18 yuan/tree

Notes: 1. The measurement of trunk diameter is calculated at the place of 1m from the

ground, 1 yuan will be increase for additional 1 cm if the tree is higher than 21 cm.

2, the trees transplanted and fell down are all owned by original owner.

3, 1500 yuan/mu for taking full responsibility for a large-scale woods; 500 yuan/mu for taking full

responsibility for mixed bamboo forest; 300 Yuan/mu for taking full responsibility for shrub

wood.

(6)Compensation standards for other attachments

Items Type Standard in RAP Executive standards

Page 114: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 113

Items Type Standard in RAP Executive standards

Well

Tractor-ploughing well

within 5 m depth or

pressurized well 1200 yuan/well 500 Yuan/well

Deep well(above 5m) 1200 yuan/well

Pole Concrete pole(above 5m) / 150 yuan/piece

Wooden pole / 20 yuan/piece

Tombs Single coffin

1500 yuan/set 1000

Double coffin 1500

Plastic shed Steel frame / 8 Yuan/m2

Bamboo frame / 5yuan/m2

Dung depositary Outdoor / 80 yuan/piece

For better implementation of demolition work, the compensation standards for wells and

tombs of different sizes are detailed according to detailed implementation rules of the policies in

China. After investigation and detailing, the compensation standards are no lower than

replacement price of the project. All compensation standards for housing demolition are no less

than the compensation standards listed in the Resettlement Plan.

4.1.2.2 Relocation Compensation and Temporary Transition Subsidies

The compensation for relocated households involved in this project, shall be implemented in

strict accordance with the provisions of compensation standards stated in the document filed (CZ

[2012] No.90), and be paid in a lump sum in cash to the accounts provided by farmers after

agreement signed. According to on-site investigation, Monitoring Group learned that actual

situation of relocation compensation and temporary transition subsidies for affected households are

shown in the table below.

Table 4-3 Relocation Compensation and Temporary Transition Subsidies

Compensation

Items

Relocation

subsidies(yuan/household)

Compensation for

homestead

(yuan/household)

Temporary transition

subsidies (calculated as 6

months)

Scheduled 1000 4000 5 yuan/m2

Page 115: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 114

Compensation

Items

Relocation

subsidies(yuan/household)

Compensation for

homestead

(yuan/household)

Temporary transition

subsidies (calculated as 6

months)

Executive

standards 1000 4000 5 yuan/m2

Others Reward 10% of housing compensation

In addition to compensation for house demolition according to the standard, each relocated

household will received transition subsidy of 5 Yuan/m2 per household per month for 6 months of

transition period; and relocation subsidy of 1000 Yuan/household, with housing plot for free to

build resettlement housing; Dongliu Town also provides 4000 Yuan to each household as

compensation for housing plot; no transition resettlement will be provided to those AHs only

affected by demolition of attached facilities, without demolition of main house. If the relocation

could be completed within specified time, affected households can be rewarded as 10% of housing

compensation amount; while all relocated households have enjoyed 10% bonus.

4.1.3 Grave relocation

Number demolition grave, affecting households and the number of statistics in the following

table:

Town Quantity

Number of households and persons Unit

Price(Yuan) Compensation(Yuan)

Household Number of

people

Yaodu 131 131 576 1000 131000

Dongliu 31 31 166 1000 31000

Subtotal 162 162 742 / 162000

4.1.4 Affected individual businesses

Monitoring Group after the investigation learned that affected individual businesses are two

households including pheasant farm and pig farm along the whole alignment, located in Xiayang

and Zhanggang Villages respectively.

(1) Pheasant farm

Page 116: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 115

The villager Xu Haizhou in Bichong Group of Xiayang Village is breeding pheasant. The

relocation of pheasant farm is affected by the project, and the houses need to be demolished and

resettled. Total compensation for chicken farm is 237167 Yuan, see Table 4-4.

Table 4-4 Compensation list for relocation of pheasant farm

No. Contents Compensation(Yuan) Remarks

1 Replacement of

management houses 24000 120m2×200 Yuan/m2

2 Migration costs 7795 Calculated by county animal

husbandry bureau

3 Replacement of

pheasant farm 205372 Negotiation

4 Subtotal 237167

An Agreement on compensation for farm relocation was signed between Xu Haizhou and

Dongliu Town Government on December 12, 2013, and then the relocation and compensation

were carried out. Pheasant farm was relocated to new site, and Xiayang Village Committee in

Dongliu Town is responsible for water supply, power supply and road for pheasant farm after

relocation to meet the requirements of the farm.

Monitoring Group learned that, pheasant farm resumed the breeding works in May 2014..

Production status in the pheasant farm before and after relocation is shown in Table 4-5.

Table 4-5 Comparison of pheasant farm before and after relocation

Breeding area(mu) Annual amount of adult

pheasants(10000)

Annual amount of

eggs(10000)

Before 9 1.0 4.5

After 15 1.5 7

The situation of pheasant farm has changes a lot due to improved environment for cultivation

after relocation of pheasant farm. The main changes include: the area of cultivation has been

expanded from original9 mu to existing 15mu;, about 15,000 adult pheasants with 70000 eggs

produced annually after relocation, while there are only about 10000 adult pheasants with 45000

eggs in previous year.

Page 117: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 116

Picture 4-2 Management houses in pheasant farm before and after relocation

Picture 4-3 Environment improvement in pheasant farm after relocation

Xu Haizhou expanded the scale of farming with increase of egg quantity after the relocation

of pheasant farm affected by the project. Meanwhile, Xu’s family has moved to resettlement site

and their living conditions were improved. The head of this household is very satisfied with the

situation of demolition, relocation and compensation.

(2) Pig farm

An agreement on compensation for pig farm was signed between a self-employed

businessman Hu Baowei and Dongliu Town Government on December 30, 2013, totaling 151,200

yuan of compensation expense, as shown in Table 4-6.

Table 4-6 Compensation for pig farm

No. Contents Compensation Remarks

Page 118: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 117

No. Contents Compensation Remarks

1 Replacement of hog

house 115200 288m2×400 yuan/m2

2 Loss of pigs 36000 120 pigs ×300 yuan/pig

Subtotal 151200

Monitoring Group learned that the original self-employed household would like to switch to

another job. Before career changes, there are about 100 giant pigs in the previous year and about

240 piglets sold out annually with normal annual value of production of 100,000 Yuan. Currently,

3 persons in this household have employed in Zhanggang Restaurant with family annual income of

120,000 Yuan. No reemployment problems for staffs are involved in the pig farm.

4.2 S319 Wuwei to wuwei-erba Project Compensation Standard and

Quantity

4.2.1 Quantity Standard of Land Acquisition

According to the final Resettlement Report, there are land acquisition of412.55mu inthis

subproject, of which, permanent collective land of 401.85mu, and state-owned land of 10.7mu.

Permanent land required by this subproject was approved by Anui Provincial Government (in the

file of WZD[2014] No.52), with land of 16.905 hectares (253.587 mu) approved.

The compensation standards of land acquisition are classified as three types: collective land,

state-owned land and temporary land in accordance with the various demands for land use of road

construction.

The compensations for attachmentson the acquiredland, crop compensation fees and

resettlement subsidies owned by individuals will be directly transferred to the account provided by

the farmers in the form of cash.The situation of social insurances for householdswith less than

0.3mu arable land per capita after land acquisition are not involved in the project land acquisition.

4.2.2 Compensation Standard for Collective Land Acquisition

Compensation standards in this subproject are carried out in accordance with the stipulations

Page 119: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 118

in the Notice on Adjustment on Standards of Land Acquisition Compensations in Anhui

(WZ[2015]No.24) issued by Anhui Provincial Government. Agreements on compensations of land

acquisition are negotiated among town government, villager committee and affected villagers,

please see compensation standards for collective land in Table 4-7:

Table 4-7 Compensation Standards for Collective Land Acquisition in this Project

Unit: Yuan/mu

No. Area Town

Farmland Construction Land and

Unutilized Land

Standard in

RAP

Executive

standards

Standard in

RAP

Executive

standards

1 Wuwei

County

Fudu Town,

Dougou Town 33000 38280 16500 19140

2 Wucheng Town 35420 40260 17710 20130

In addition, compensation standardfor young cropsis 800 yuan/mu.

With respect to the compensation agreement for land acquisition and resettlement of the AH,

Zhang Yifan, see Attachment 33.

To sum up the above-mentioned monitoring, compensation standards of collective land

permanently acquired for the project are higher than the compensation standards in the

resettlement plan.

4.2.2.1 Compensation Standard for State Owned Land Acquisition

The houses to be demolished shall be compensated according to the compensation standard

for houses, and the land area to be expropriated shall be compensated according to the

compensation standard for construction land.

4.2.2.2 Compensation Standards for Temporary Land Acquisition

According to the notice on Strengthening the Management of Temporary Land Use (wtzz

[2010] No. 119) issued by the Land and Resources Department of Anhui Province, the

compensation standard for temporary land use shall refer to the unified annual output value of the

land expropriated or the compensation standard for young crops to compensate the farmers or

Page 120: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 119

affected villages. In this project, the compensation for temporary land occupation is based on the

unified annual output value standard, i.e. Fudu town is 1500 yuan / mu / year. The temporary land

occupation period of the project is 2 years.

After the expiration of the temporary land occupation period of the project, Wuwei County

Transportation Bureau and the project contractor are responsible for the restoration of the land, and

the restoration cost is included in the general budget of the project.

For land reclamation agreement and temporary land use permit, see Annex 3

4.2.2.3 Renting of Houses and Construction Grounds

Construction of S319 project is divided into three contracts. All contracts need rent land used

for precast yard, mixing plant and construction site of project management department. In line

with the principle of land conservation and contributing to the development of local economy,

shutdown or abandoned factories are rent as precast yard and construction site of project

management department required in these three contracts. On the one hand, land resources and

cost of project land construction are saved; on the other hand, shutdown enterprises and

personnel’s incomes have been increased, which are benefit for the production and development of

the enterprises in the future. S319 project involves 30 mu land within the factory, office building

and civil housing of 2680 ㎡ in total, with a rent of 40,560 yuan/year. The rent will be paid once

per year in the form of cash or paying to account. For example, it is stipulated in the clause of “4.3

payment method” of Lease Contract for Project Residence Area in Contract NO1-1 that: the rent

shall be paid to the Party A (Wang Yalin) by the Party B (Project Management Department of

Contract NO1-1) before 30 working days prior to the expiration of each rent period.

4.2.2.4 Land Restoration Measures and Compensation Payment

After field investigations, Monitoring and Evaluation Goup learned that land compensation

rates are divided into three types of collective land acquisition, temporary land use as well as using

of state-owned land in accordance with the nature of highway construction land demands. The

compensation standard for collective land acquisition is decided in accordance with land

management laws and regulations including the Notice of Adjusting on Compensation Standards

for Land Acquisition issued by Anhui Provincial Government (WZ [2015] No.24), the standards

specified in the document WZM [2012] No.254 issued by Wuhu Municipal Government and a

Page 121: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 120

delivery report (MECG [2014] No.35) issued by the Office of Wuhu Municipal Government, in

accordance with the official reply of Anhui provincial government (WZD [2014] No.52).

Procedures of Land submission for approval of S319 project are completed; compensations for

land acquisition are in place partly; each villager and household affected by land acquisition have

signed agreements on land acquisition and resettlement; the compensations for attachments and

young crops owned by individuals on the occupied land as well as resettlement subsidies have

been paid to individuals.

4.2.3 Compensation Standard for House Demolition

4.2.3.1 Compensation Standard for RuralHousing Demolition

The relocation of S319 project and the resettlement of small and medium-sized enterprises

comprehensive industrial park in Wuwei County are both in the Chengdong new area of Wuwei

County. Wuwei County has established the Chengdong new area headquarters to be responsible for

the resettlement work in this area. The compensation standard for rural housing shall be

implemented together with the compensation and resettlement plan for collective land and housing

in Wuwei Chengdong new area from 2014 to 2015 issued by the headquarters of Chengdong new

district of Wuwei County on December 1, 2014. The compensation scheme can be divided into

property right exchange and currency compensation, which can be selected by the expropriated: if

the property right is exchanged, it shall be implemented according to the principle of "one levy and

one compensation"; if currency compensation is selected, it shall be 35 m2 per capita For the

boundary, the replacement price of the house plus the market evaluation price (higher than the

replacement price of the house) shall be implemented. Its implementation is as follows:

Table 4-8 compensation standards for demolition of residential buildings and ancillary

facilities

Unit:yuan/㎡

Impact

types type unit RAP standards Executive Standards

Housing

compensaframe ㎡ / 1380

Page 122: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 121

Impact

types type unit RAP standards Executive Standards

tion Brick and

concrete ㎡ 1180 1180

Brick and

tile ㎡ 930 930

Civil

Engineeri

ng

㎡ 380 380

Other

compensa

tion

Relocation

subsidy

yuan/h

u 200

For monetary

compensation, the legal

construction area of the

house to be expropriated

is 4 yuan / m2 once; for

property right control, the

subsidy is twice according

to the above standard.

Temporar

y

resettleme

nt subsidy

yuan/

㎡.mo

nth

According to the legal building

area of the house area, the

temporary resettlement subsidy

is 2.5 yuan / m2. Month for

every 50 M2 (including 50 m2)

of legal building area, and 2 yuan

/ m2. Month for the part

exceeding 50 m2. If the property

right is exchanged, the temporary

resettlement subsidy for one year

shall be paid in advance to the

expropriated household for one

year. Until 4 months after the

resettlement and the transition

period is more than 18 months,

the temporary resettlement

subsidy fee and the second

relocation fee shall be paid

according to the double standard.

One time relocation fee and

4-month temporary resettlement

subsidy are paid for monetary

compensation.

For monetary

compensation (including

existing house

resettlement), the

temporary resettlement

fee for 4 months shall be

subsidized at the rate of 4

yuan / m2 per month; for

the option of property

right exchange, the

subsidy shall be 4 yuan /

m2 per month within 18

months and temporarily

paid for one year; from 18

months to 24 months, it

shall be 6 yuan / m2 per

month, and for more than

24 months, it shall be 8

yuan / m2 per month from

the date of exceeding the

month until four months

after resettlement.

Page 123: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 122

4.2.3.2 relocation compensation and temporary transition subsidy

In order to encourage the expropriated to move actively, s319 did not set up incentive

measures for the PMO. The expropriated households who completed the relocation within the

specified time and signed the housing expropriation compensation and resettlement agreement will

be rewarded in terms of resettlement area and relocation time. For example, for the resettlement

area award, on the basis of "one demolition and one compensation", it is allowed to purchase 45

square meters per capita at the cost price; if currency compensation is selected, the compensation

standard will be appropriately increased to the market evaluation price; for the resettlement time

award, 100, 150, 200 yuan / m2 will be given to the expropriated households who move within the

specified time limit, sign the expropriation compensation agreement and hand over the house for

demolition.

The external monitoring team understands that the compensation standards for demolished

houses are not lower than the compensation standards in the final report of the resettlement plan.

Housing demolition and resettlement standards

The project involves the demolition of rural residential houses on collective land, with an area

of 8733.8 m2, affecting 63 households and 240 people. The affected areas are Fudu community of

Fudu town and Hualong community of Dougou town. There are some problems in the demolished

rural houses, such as imperfect indoor supporting facilities, obsolete structure and poor lighting

and ventilation conditions, and the supporting conditions around the residential areas are also poor.

The relocation and resettlement activities of the project will provide opportunities for the relocated

households to improve their living conditions and environment. According to the investigation,

after fully soliciting the wishes of the land expropriated farmers, no resettlement plan has been

provided for the county project office and the project implementation organization, including

property right exchange and currency compensation:

Property right exchange

Page 124: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 123

Property rights exchange standard and price difference settlement

The resettlement site of the project is located in the resettlement site of Chengdong new

district, crossing Changba and Xuqiao villages of Fudu community in Fudu town. The resettlement

community covers an area of 108 mu, with a total construction area of about 180000 m2, of which

the construction area of phase I project is about 100000 m2. The land acquisition for the

resettlement project of Chengdong new area was completed in December 2012. The resettlement

project only involves collective land acquisition, not housing demolition. The construction of

resettlement community began in July 2013, with 1900 houses planned to be built for resettlement.

The house type design of the resettlement site includes: type A (about 135 ㎡); type B (about 110

㎡); type C (about 90 ㎡); type D (about 70 ㎡); type E (about 48 ㎡).

Figure 4-4 Resettlement site in Chengdong new district of Wuwei County (phase I)

Figure 4-5 Effect drawing of centralized resettlement point

Monetary compensation

The housing area within 35 ㎡ per capita shall be settled according to the market evaluation

price (the estimated market price is 1800 yuan / ㎡), and the houses exceeding 35 ㎡ per capita

shall be settled according to the house replacement price. The replacement price standard is 1300 /

㎡ for frame, 1180 yuan / ㎡ for brick concrete, 930 yuan / ㎡ for brick and tile, and 380 yuan /

㎡ for civil engineering.

4.2.4 Affected Individual Businesses

Page 125: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 124

According to the investigation team, there are no individual businesses affected by s319

project.

4.3 S367 Compensation Standard for Ma'anshan North Passage Project

4.3.1 Compensation Standard for Land Acquisition

4.3.1.1 Compensation Standard for Collective Land Acquisition

According to the spirit of land management law of the people's Republic of China, guiding

opinions on improving land acquisition compensation and resettlement system, land management

law of the people's Republic of China implemented by Anhui Province, and notice of the people's

Government of Anhui Province on adjusting land acquisition compensation standard of Anhui

Province (WZ [2012] No. 67), the project and Shiyang Town, Shanhou town and Zhaoguan of

Hanshan County . The compensation standards for land acquisition of towns and xianzhuzhen are

the same, see table 4-9 and table 4-10 for details.

Table 4-9 multiple and standard of compensation for collective land acquisition of the project

(resettlement plan)

N

o.

Distric

t Area

Unifie

d

annua

l

output

value

standa

rd

(yuan

/ mu)

Agricultural land Construction land and unused land

Land

compensat

ion

multiple

Multiple

of

resettleme

nt

compensat

ion

Compensat

ion

standard

for land

acquisition

(yuan /

mu)

Land

compensat

ion

multiple

Multiple

of

resettleme

nt

compensat

ion

Compensat

ion

standard

for land

acquisition

(yuan /

mu)

1

Hexia

n

county

Shiyan

g

town、

Shanho

u town

1565 7 14 32865 5 5.5 16433

2 Hansh

an

Shaogu

an 1566 7 14 32886 5 5.5 16443

Page 126: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 125

county town、

Xianzo

ng

town

Table 4-10 multiple and standard of compensation for collective land acquisition of the project (actual

implementation standard)

No. District Area

Unified annual

output value

standard (yuan

/ mu)

Agricultural land

Construction

land and unused

land

Land

compensation

multiple

Multiple of

resettlement

compensation

1 Hexian

county

Shiyang

town、

Shanhou

town

1800 7 14 37800 5 5.5 18900

2 Hanshan

county

Shaoguan

town、

Xianzong

town

1780 7 15 39160 5 6 19580

4.3.1.2 compensation standard for temporary land occupation

According to the impact analysis of the project, the impact of temporary land occupation of

the project is all unused land, and the compensation standard is 1500 yuan / mu / year. According

to the construction design, the temporary occupation period of the project is 2 years. See table 4.11

for compensation standard of temporary land occupation.

Table 4-11 compensation standard for temporary land occupation

Type Unit Hexian

county

Hanshan

county Remarks

Land for borrow piand spoil yuan/mu.year 1500 1500 Calculated by 2

Page 127: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 126

years

General temporary land

occupation yuan/mu.year 1500 1500

Calculated by 2

years

4.3.2 Compensation standard for rural housing demolition

The compensation standard for the demolition of rural residential houses of the project is

determined according to the replacement price of the demolished houses. See Annex 34 for the

calculation of relocation and replacement price of rural housing in Hexian county and Hanshan

county. See table 4-12 and table 4-13 for the compensation standard of rural housing demolition in

this project. The resettled homestead will be obtained before the demolition, and the site selection

of homestead will be determined by the villagers and the affected immigrants. After the project

affected farmers get compensation, they can fully use the compensation money to build new

houses. The three connections and one leveling of the homestead will be carried out by the

construction company, and the cost will be included in the project budget by.

Table 4-12 compensation standard for demolition of rural housing and auxiliary facilities in

Hexian County

Type Structure

type Unit

Price (yuan )

Remarks RAP

compensation

standard

Actual

implemented

standard

House

compensation

Framework ㎡ 1220 1342

Masonry

timber

structure

㎡ 965 1062

Masonry tile ㎡ 765 842

Earth-timber ㎡ 305 336

Other

compensation

Moving

subsidy hu 500 500-1000 One off subsidy

Page 128: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 127

Type Structure

type Unit

Price (yuan )

Remarks RAP

compensation

standard

Actual

implemented

standard

Transition

subsidy ㎡·month 6 6

According to the

actual transition time,

generally no more

than 18 months, 8

yuan / m2 / month

compensation

standard will be paid

for more than 18

months

Temporary resettlement transition fee shall be paid at 6 yuan per square meter per month

(calculated from the date of relocation). The temporary resettlement transition fee of 6 months

shall be paid in one time to the person who chooses monetary compensation and the person who

chooses homestead resettlement; the temporary resettlement transition fee of the person who

chooses property right exchange shall be paid to 4 months after the house is delivered. The person

to be expropriated shall complete the relocation within the relocation period stipulated in the

expropriation compensation agreement or determined by the expropriation compensation decision.

The resettlement transition will be solved by itself.

Payment method of compensation and resettlement. If the expropriated person chooses the

method of homestead resettlement or monetary compensation, the two sides of the expropriation

shall reach a consensus through consultation and conclude the agreement of house expropriation

and resettlement and the agreement of land expropriation, and the expropriated person shall

complete the house relocation and deliver the house to be demolished, the expropriated person

shall pay the compensation and resettlement money in one time. If the expropriated person chooses

to change the property right, the account shall be calculated according to each other and the

original price difference shall be found between each other Then, the relocation compensation and

resettlement fee will be directly converted into the purchase price, and the difference will be

settled according to the prices of different types of resettlement houses selected by the

Page 129: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 128

expropriated. If the compensation is greater than the purchase price, the surplus part shall be

immediately paid to the person to be expropriated after all the relocated households have

completed the relocation and the house has been completely delivered and demolished; if the

compensation is less than the purchase price, the difference part shall be settled and settled by the

person to be expropriated once the resettlement house is selected.

Table 4-13 compensation standard for demolition of rural residential houses and auxiliary

facilities in Hanshan County

Type Structure

type Unit

Price (yuan )

Remarks RAP

compensation

standard

Actual

implemented

standard

House

compensation

Framewor

k ㎡ 1400 2160

Masonry

timber

structure ㎡ 1075 1530

Masonry

tile ㎡ 885 1400

Earth-tim

ber ㎡ 380 600

Other

compensation

Moving

subsidy hu 6 6

Transition

subsidy ㎡·

month 4 4

According to the actual transition

time, generally no more than 18 months, 8

yuan / m2 / month compensation standard

will be paid for more than 18 months

Relocation compensation standard:

(1) If monetary compensation is selected, the relocation compensation shall be paid

according to the standard of 6 yuan / m2 of the main building area of the house to be demolished;

(2) If the homestead is selected for resettlement, two relocation compensation shall be paid

according to the standard of 6 yuan / m2 of the main building area of the house to be demolished

Page 130: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 129

(3) If the area of the house to be expropriated is less than 50 square meters, it shall be

calculated as 50 square meters

Compensation standard for temporary resettlement:

(1) If monetary compensation is selected, temporary resettlement compensation for six

months shall be paid at one time according to the standard of 4 yuan / m2 per month for the main

building area of the house to be demolished.

(2)If the homestead is selected for resettlement, temporary resettlement compensation shall

be paid according to the standard of 4 yuan / m2 per month for the main building area of the house

to be expropriated, and the actual number of transitional months shall not exceed 18 months; if the

homestead cannot be obtained in time, it shall be taken as the main building area of the house to be

demolished after the overdue period

Standard resettlement compensation of 8 yuan / m2 per month for the building area of the

house

(3) The number of months of actual transition refers to the number of months of actual

temporary transition from the date when the relocated households have moved to the date when the

houses have been built and capped.

4.3.3 Compensation for Accessories and Infrastructure

According to the principle of replacement price, determine the compensation standard for the

affected accessories and infrastructure of the city and county within the scope of the project. See

table 4-14 for details.

Table 4-14 compensation standards for accessories and infrastructure

Accessories Unit RAPstandard

(yuan/unit) Hexian county Hanshan county

Pole

Cement Stick 200 200 300

Wood Stick 60 60 100

Tomb tomb 600 600(mud single)1100(mud double) 600(mud)/800(cement)

Page 131: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 130

Accessories Unit RAPstandard

(yuan/unit) Hexian county Hanshan county

1200(brick single)2400(brick double)

Public restroom 160 60-80/m2 200

Vegetable shed ㎡ 12 8000-10000/mu 12

Motor-pumped well eye 2500 2500 2500

Enclosing wall m 60 60 60(stone)/80(brick)

Pigsty ge 600 60/80/m2 300/m2

Tree ke 15 18-84 20/40/50

Fruit tree ke 20 37-130 20/50

4.3.4 Other cost standards

See table 4-15 for other expense standards.

Table 4-15 resettlement tax standard of the project

No. Tax name Standard

1 New construction land use fee 10000Yuan/mu(15yuan/㎡)

2 Cultivated land reclamation fee 30000yuan/mu

3 Land occupation tax 1333.34yuan/mu(yuan 元/㎡)

4 Land acquisition management fee 850yuan/mu

5 Water conservancy fund 500yuan/mu

6 Survey and design cost 1% of basic cost

7 External monitoring and evaluation fee 1% of basic cost

8 Technical training cost 0.5% of basic cost

9 Administrative expenses 2% of basic cost

10 Unforeseen expenses 10% of basic cost

4.3.5 Vulnerable Groups

In addition to the aforementioned land acquisition compensation policies, vulnerable groups

affected by the project can also enjoy other preferential policies:

(1) Provide vocational training for the labor force in the vulnerable groups' families, and

Page 132: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 131

provide various employment information and guidance to increase employment opportunities;

(2) In the process of project construction, priority should be given to recruiting the labor force

of vulnerable groups to do some non-technical work;

(3) Cooperate with the social labor and social security departments of counties and cities to

set up a special support fund to provide assistance, which will be paid from the resettlement

management fees.

4.3.6 Women's Support Measures

In addition to the policy of land acquisition compensation, women also enjoy special support

policies

(1) Priority is given to employment opportunities, and 30% of women have access to

non-technical employment opportunities.

(2) Priority will be given to agricultural and non-agricultural technical training. 12000 people

will receive agricultural and non-agricultural technical training in this project, including at least

6000 women (50%)

(3) Affected women have access to relevant information during the resettlement process and

can participate in fair consultation and resettlement.

(4) During the implementation of resettlement, a special women's forum was held to

introduce relevant policies of resettlement, so as to improve women's awareness.

(5) The compensation agreement must be signed by both husband and wife.

4.4 Compensation Standard for G318 and S320 Yimu Highway Project

4.4.1 Compensation Standards of Land Acquisition

4.4.1.1 Compensation Standard for Collective Land Acquisition

Nanling County Project Office announced and publicized the land acquisition scheme at early

stage of land acquisition.In the Project Resettlement Plan, compensation standards for permanent

acquisition of collective land should execute WZ (2012) No.67 document, actually executed

Page 133: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 132

compensation standards also follow WZ (2012) No.67 document, compensations are paid to the

households affected by land acquisition according to the standards in the table below, the rest

money is used for public welfare of village collective and social security for landless

peasants.With respect to the compensation standards for permanent acquisition of collective land,

see the table below.

Table 4-16 Compensation Standards for Collective Landland Acquisition

Unit:Yuan/mu

Region

Farmland Construction land and unused land

Planned

compen

sation

standar

ds

Actual compensation

standards

Pl

anned

compe

nsatio

n

standa

rds

Actual compensation standards

Distribu

tion to

househo

lds

Land lost farmers

fund and village

collective land

social welfare

total

Distrib

ution

to

househ

olds

Land lost farmers

fund and village

collective land social

welfare

total

Jishan

Town 36300 32800 3500 36300 18150 15675 2475 18150

Gongsha

n Town 32130 28917 3213 32130 16065 13770 2295 16065

Take an example of Jishan Town, compensation methods for collective land acquisition are as

follows:

Agricultural land:land compensation 11550 Yuan/mu(30% of the land compensation fund is

Page 134: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 133

used to pay for the land lost farmers' fund and the social welfare of rural collective land, and 70%

is paid directly to the households affected by land acquisition), resettlement subsidies 24750

Yuan/mu are paid to bank cards of the households affected by land acquisition directly.Total land

compensation and resettlement subsidies are 36300 Yuan/mu, the amount paid to the households

affected by land acquisition is 8085+24750=32800 Yuan/mu, the rest payment is used for public

welfare of village collective and pension insurance of landless peasants affected by land

acquisition.

Construction land and unused land:land compensation 8250 Yuan/mu(of which 30% is used

unified for security fund of landless peasants, i.e.2475 Yuan, 70% is paid to the units or individuals

affected by land acquisition, i.e.5775 Yuan), resettlement subsidies 9900 Yuan/mu.Total land

compensation and resettlement subsidies are 18150 Yuan/mu, payment to the households affected

by land acquisition is 5775+9900=15675 Yuan/mu, which is paid directly to the units or

individuals affected by land acquisition via bank card.

In the Resettlement Plan, compensation standard for young crops in the acquired cultivated

area follows unified annual production value standard, i.e.1650 Yuan/mu in Jishan Town, 1530

Yuan/mu in Gongshan Town.According to the monitoring, crops on the cultivated area are

basically mulberry and green seedlings etc, compensations are given to the attachments in actual

compensation process, hardly involving any category of common young crops. Compensation

standards for attachments meet the compensation standards in the Resettlement Plan.

It may be seen from the above-mentioned monitoring result that:compensation standards for

permanent land acquisition of Nanling County Yimu Highway meets ADB standards in the

Resettlement Plan.

Page 135: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 134

Picture 4-6 Announcement On Land Acquisition Program in Jishan Town

4.4.1.2 Compensation Standards and Quantity of Temporary land

According to the Notice of Anhui Provincial Office of Land and Resources Concerning the

Enhanced Temporary Land Management (WGTZ (2010) No.119), compensation for temporary

land should take reference to unified annual value of production or young crops compensation

standard for local land acquisition to the households or affected village groups, compensation for

temporary land occupation should comply with unified annual production value standard, i.e.1650

Yuan/mu. Year in Jishan Town, 1530 Yuan/mu. Year in Gongshan Town. Temporary land

occupation period in this project is 2 years. During actual implementation, temporary land

compensation standard in both Jishan Town and Gongshan Town is 2000 Yuan/mu. After

temporary land occupation period for this project expires, Nanling County Department of

Transport and project contractor are responsible for land restoration, restoration costs are included

in general estimate of the project.

It may be seen from the monitoring that: temporary land compensation standards for the

project are higher than the resettlement scheduled, and in compliance with relevant domestic

policies, benefits of the affected households are guaranteed.

Page 136: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 135

4.4.1.3 Renting of Office Grounds for This Project

Nanling Yimu Highway Construction Project is divided into two contract sections, office of

Contract 01 rents the whole fourth floor, dormitory on the fifth floor and kitchen and dining room

on the first floor of the office building of Anhui Mingtai Glass Technology Co., Ltd. , contract has

been signed, tenancy is 3 years, rent is 200,000 RMB per year, rent of every year should be paid

before Aug. 20 in advance. Contract 02 rents about 25 mu land of Anhui Nantian Building

Material Technology Co., Ltd. , as well as the office on the third floor as PMO command land,

tenancy is 2 years, 200,000 RMB per year. For rental agreement, see the Attachment27、28.

Picture 4-7 Site of Contract 01 Project Management Department

Picture 4-8 Site of Contract 02 Project Management Department

Picture 4-9 the Site Leased for Contract 02 Project

Page 137: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 136

It may be seen from the monitoring that: temporary land of PMO for this project does not use

new land, but utilizes the houses and land of plant buildings, which increases the income of local

enterprises. And after the construction is completed, the hardened land may be reused by the

factories, which may reduce expenditure of the enterprises.

4.4.2 Compensation Standard for House Demolition

In Nanling County, demolition should be completed for 22 households in Gongshan Town,

and should be completed for 23 households in Jishan Town. Demolition was completed for 21

households in Gongshan Town, the remaining 1 household signed agreement for demolition and

resettlement, yet demolition was not performed, 6 households signed agreement for demolition and

resettlement in Jishan Town, of which demolition was completed for 1 household, demolition of

the rest households will be performed according to the project progress

Compensation standards for house demolition in Gongshan Town follow GZ (2014)No.56

document, compensation standards in Jishan Town follow NZ (2013) No.72 document, as shown

in the table below.

Table 4-17 Compensation Standards for Houses

Structure type Unit Jishan Town Gongshan Town

Planned Actual Planned Actual

Masonry concrete

structure Yuan/㎡

Masonry

concrete

structur of

three-story

and above

three-story

e:920,

Five-story

and above

960

Masonry

concrete

structur of

three-story

and above

three-story

e:920 Yuan/㎡,

Masonry

concrete

structur of

three-story

and above

three-story

e:920,

Masonry

concrete

structure

below

three-story:88

0

Three-story

and

four-story:92

0 Masonry

concrete

structure

below

three-story:88

0

Masonry

concrete

structure

below

three-story:88

0 Yuan/㎡

One-story

and

two-story:88

0

Masonry timber Yuan/㎡ Masonry Two-story 700 700

Page 138: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 137

Structure type Unit Jishan Town Gongshan Town

Planned Actual Planned Actual

timber of

two-story and

above

two-story:860

and above

860

One-story

masonry

timber:840

One-story:84

0

Makeshift Yuan/㎡ 180

Class 1 200

180

180 for

below

2.2m;200 for

above 2.2m Class 2 180

Movin

g

subsid

y

Residential Yuan/household·tim

es 250 500 250 500

Non-residenti

al Yuan/㎡ 8 8 8 8

Transition subsidy Yuan/

㎡·month 3 5 3 3

Relocation incentive

fees

(move out within 10

days)

Yuan/㎡ / / / 20

Relocation incentive

fees

(move out within 20

days)

/ 100 / /

Relocation incentive

fees

(move out within 40

days)

/ 50 / /

Cash compensation for resettlement will be given to the property owner according to the

replacement price of the houses;Compensation for homestead will follow compensation standards

for construction land in the Notice of the Anhui Provincial Government on Adjusting

Page 139: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 138

Compensation Rates for Land Acquisition of Anhui Province (WZ [2012] No.67).

Property swap in Gongshan Town will adopt “unified construction and repurchase” mode, the

affected towns should construct resettlement communies, the AHs will repurchase the resettlement

house after compensation for demolition is settled according to the replacement price, resettlement

standards are as follows:

1)if original per capita residential area of the APs is less than or equal to 30 ㎡, resettlement

according to per capita 30 ㎡;

2)if original per capita residential area of the APs is larger than 30 ㎡ yet less than 45 ㎡,

resettlement according to the effectgive area of the APs house.

3)if original per capita residential area of the APs is larger than 45 ㎡, resettlement according

to per capita 45 ㎡ in principle.

If original residential area of the APs is small, resettlement area is inconvenient for residence

after convertion, resettlement area needs to be added, the AHs should submit application to the

town government for approval, then each AH may add resettlement area of 10 ㎡ according to the

preferential price determined by the government (1.4 times of the average price of the resettlement

sites), if area of the demolished house exceeds the area of the resettlement house, the excessive

part will be compensated through market assessment.

It may be seen from the monitoring that:Gongshan Townadopts property swapmode for

demolition, the rights and interests of households of the AHs are guaranteed.

Picture 4-10 Gongshan Town Compensation Standard for House Demolition announcement

Page 140: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 139

Picture 4-11 Announcement On the Resettlement Scheme of Jishan Town

4.4.3 Compensation Rates for Main Attachments and Infrastructure

For the Compensation Standards Executed for main attachments and infrastructure in the

project and the compensation standards in the Resettlement Plan, see the table below,

Compensation standards for other attachmentss in house demolition, see the Attachment.

Table 4-18 Comparison Table of Compensation Rates for Main Attachments and Infrastructure

Types of Impact Planned compensation standards Actual compensation

standards

Walls (m2) Masonry (dry): 20 Yuan/m2, Masonry

(mortar): 30 Yuan/m2 The same as the plan

Fencing (m) Earth, fence: 15 Yuan/m2 The same as the plan

Floors (m2) Cement floors 25 Yuan/m2 Cement floors 25 Yuan/m2;

Masonry floors 15 Yuan/m2

Tombs (piece)

Earth grave: 200 Yuan/grave (one-grave

one-coffin); 300 Yuan/grave (one-grave

two-coffin or above two coffins)

Cement structure grave: 300 Yuan/grave

(one-grave one-coffin); 400 Yuan/grave

(one-grave two-coffin or above two coffins)

Earth grave: 400 Yuan/grave

(one-grave one-coffin); 500

Yuan/grave (one-grave

two-coffin or above two

coffins)

Cement structure grave: 500

Yuan/grave (one-grave

one-coffin); 600 Yuan/grave

Page 141: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 140

Types of Impact Planned compensation standards Actual compensation

standards

(one-grave two-coffin or

above two coffins)

Well (piece) 150 Yuan/well Pressure well 150 Yuan/well

Deep well 1000 Yuan/well

Trees (tree)

General trees: circumference below 10 cm:

10 Yuan/tree; 11-20 cm: 30 Yuan/tree; 21-30

cm: 50 Yuan/tree; 31-40 cm: 60 Yuan/tree;

41-50 cm: 70 Yuan/tree; 51-60 cm: 80

Yuan/tree; 61-70 cm: 90 Yuan/tree; above 71

cm: 100 Yuan/tree.

Fruit trees: circumference below 10 cm: 50

Yuan/tree; 11-20 cm: 100 Yuan/tree; 21-30

cm: 250 Yuan/tree; 31-40 cm: 350 Yuan/tree;

41-50 cm: 450 Yuan/tree; above 51 cm: 500

Yuan/tree.

The same as the plan

Pole (piece)

According to the signed agreement, property

units should be responsible for their

relocation during construction, will not be

compensated

The same as the plan

Electric wires (m)

According to the signed agreement, property

units should be responsible for their

relocation during construction, will not be

compensated

The same as the plan

Road lamp (piece)

According to the signed agreement, property

units should be responsible for their

relocation during construction, will not be

compensated

The same as the plan

Transformer (unit) Relocation subsidies: 6000 Yuan/unit. The same as the plan

Cross-connecting

boxes (piece)

According to the signed agreement, property

units should be responsible for their

relocation during construction, will not be

compensated

The same as the plan

Compensation standards for attachments meet the compensation standards in the

Resettlement Plan.

4.4.4 Affected Individual Businesses

The affected individual industrial and commercial households involved in the Yimu highway

Page 142: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 141

project in Nanling County are mainly concentrated in Jishan town. While the houses are

demolished and resettled, compensation is given to the operating area. See the table below for the

specific compensation standards.

Table 4-19 list of affected individual businesses

NO. Individial business

householder

Area

(㎡)

Compensation standard

(yuan/㎡)

Compensation amount

(yuan)

1 Yuan yuxia 57.45 600 34470

2 Wang jianhui 62.11 600 37266

3 Wang yifa 62.11 600 37266

4 Zheng aiying 63.00 600 37800

5 He hongxiang 63.36 600 38016

6 Fan chunyin 55.08 600 33048

7 Hu shiwen 63.00 600 37800

8 Huang jinlin 94.20 600 56520

9 Yi changshou 82.93 600 49758

10 Zhangshun 66.98 300 20094

Total 670.22 382038

4.4.5 Other Cost Standards

See 4-20 for Other Expense Standards.

Table 4-20 resettlement tax standard of the project

Table 4-20 resettlement tax standard of the project

NO. Item Charging

standard Basis Accept objects

1 Land occupation

tax

17500yuan/mu

(26.25yuan/

㎡)

WZC [2008] No. 367

Collection by

Land and

Resources Bureau

2 Cultivated land

reclamation fee 8yuan/㎡ Wcz [2001] No. 1061

Land and

Resources Bureau

3 Land acquisition 2.8% of the total WJF [2002] No. 47 Land and

Page 143: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 142

NO. Item Charging

standard Basis Accept objects

management fee basic cost Resources Bureau

4

New

construction land

use fee 16yuan/㎡

Ministry of Finance, Ministry of

Land and Resources, people's

Bank of China

Notice on adjusting the policy of

paid use fee of new construction

land (CZ [2006] No. 48)

Land and

Resources Bureau

5 Survey and

design cost

3% of the total

basic cost

Design

Department

6 Administrative

expenses

5% of the total

basic cost

Resettlement

implementation

agency

7 Technical

training cost

3% of the total

basic cost

8

External

monitoring and

evaluation fee

2% of the total

basic cost

9

Internal

monitoring and

evaluation fee

0.5% of the total

basic cost

10

Water

conservancy

fund

500yuan/mu

Notice of the people's

Government of Anhui Province

on printing and distributing the

administrative measures for

raising and using local water

conservancy construction funds

of Anhui Province (WZ [2012]

No. 54)

11 Unforeseen

expenses

0% of the basic

resettlement

cost

4.4.6 Vulnerable Groups

In addition to the aforementioned land acquisition compensation policies, vulnerable groups

affected by the project can also enjoy other preferential policies:

Page 144: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 143

(1) Provide vocational training for the labor force in the vulnerable groups' families, and

provide various employment information and guidance to increase employment opportunities;

(2) In the process of project construction, priority should be given to recruiting the labor force

of vulnerable groups to do some non-technical work;

(3) Cooperate with the social labor and social security departments of counties and cities to

set up a special support fund to provide assistance, which will be paid from the resettlement

management fees.

4.4.7 Women Support Measures

In addition to the policy of land acquisition compensation, women also enjoy special support

policies.

(1) Priority is given to employment opportunities, and 30% of women have access to

non-technical employment opportunities.

(2) Priority will be given to agricultural and non-agricultural technical training. 12000 people

will receive agricultural and non-agricultural technical training in this project, including at least

6000 women (50%)

(3) Affected women have access to relevant information during the resettlement process and

can participate in fair consultation and resettlement.

(4) During the implementation of resettlement, a special women's forum was held to

introduce relevant policies of resettlement, so as to improve women's awareness.

(5) The compensation agreement must be signed by both husband and wife.

4.5 Compensation Standards for Shuiyang River Integrated Transport

Construction Project

4.5.1 Land Compensation Standards

4.5.1.1 Collective Land Compensation Standards

Page 145: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 144

Actual amounts for Shuiyang River Integrated Transport Project comply with the Notice of

the Anhui Provincial Government on Adjusting Compensation Rates for Land Acquisition of

Anhui Province (WZ [2015] No.24). Actual amount standards are higher than the compensation

standards in the Resettlement Plan. For the Resettlement Plan and Actual Compensation Standards

Executed, see the table below.

Table 4-21 Compensation Standards of Collective Land Acquisition for the Project

Unit: Yuan/mu

Region

Unified

annual

production

value standard

Farmland Construction Land and Unutilized Land

Compensation

standards for land

acquisition in the

Resettlement Plan

Actual

Compensation

Standards

Executed

Compensation

standards for land

acquisition in the

Resettlement Plan

Actual

Compensation

Standards

Executed

Shuiyang

Town 1610 37030 42320 18515 21160

Yangxian

Township,

Liqiao Town

1550 34100 39820 17050 19910

Compensation Standards Executed for permanent land acquisition of Shuiyang River

Integrated Transport Project are higher than the compensation standards in the Resettlement Plan.

With respect to young crop compensation standard for the cultivated area acquired, see Table

4-12.

Table 1-6 Young Crop Compensation Standards for Collective Land Acquired

Unit: Yuan/mu

Lands Paddy field Dry land

Compensation standards in the Resettlement Plan 900 800

Actual standards 1000 800

Actual Compensation Standards Executed for young crop involved with Shuiyang River

Integrated Transport Project are no lower than the compensation standards in the Resettlement

Plan.

Page 146: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 145

4.5.1.2 Compensation Standard for Permanent Occupation of State Owned Land

The permanently occupied state-owned land of the project includes state-owned agricultural

land, construction land and unused land. The compensation for expropriation of state-owned forest

land of the project shall be implemented in accordance with the notice of the people's Government

of Anhui Province on adjusting the compensation standard for expropriation of land in Anhui

Province (WZ [2012] No. 67 (May 19, 2012). The second article of the circular stipulates: "the use

of state-owned agricultural (forestry, animal husbandry and fishery) land shall be carried out in

accordance with the compensation standard for land acquisition of agricultural (forestry, animal

husbandry and fishery) sites in rural (town and street) areas (districts). If there are multiple areas

(districts) around the agricultural (forestry, animal husbandry and fishery) site, the highest standard

of the surrounding areas (districts) shall prevail."

4.5.1.3 Compensation Standard for Temporary Land Use

According to the regulations of the state and Anhui Province on the temporary land

occupation, the compensation for the temporary land occupation includes the compensation for

young crops / ground accessories and the compensation for land reclamation. In the construction

process of this project, temporary land occupation of borrow area and dumping site is involved.

Earthwork (such as gravel, stone and other construction materials) required for construction shall

be purchased from Xuanzhou Industrial Park, so no land occupation and compensation are

involved. The temporary land occupation of the dumping site is all the unused ponds of the village

collective. After the coordination of the project office, the owner unit has reached a preliminary

agreement with the village collective for the temporary land occupation, which will be

compensated by 1200 yuan / mu / year. According to the construction design, the occupation

period of the temporary land occupation of the project is 2 years, so the compensation period is

also 2 years, that is, during the 2 years, the collective economic organization of the temporary land

occupation village can obtain 2400 yuan / mu compensation fund.

4.5.2 Compensation Standards for the Acquisition of Flood Land Reclaimed by

Households along the River

(1) with respect to the compensation for flood land for which agricultural tax was paid in the

Page 147: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 146

past, in compliance with the Notice of the Anhui Provincial Government on Adjusting

Compensation Rates for Land Acquisition of Anhui Province (WZ [2015] No.24) if the farmers

could provide original evidences or copy of evidences for payment of agricultural tax.

(2) compensation for “Erduowei” flood land along the river should take reference to flood

land acquisition standard of Shuiyang River Kaika and Shuiyang River Road Closed Section,

compensation standard is 15,000 RMB/mu, a lump sum for the town.

(3) ony compensation for young crops is given to the flood land outside “Erduowei”.

Such compensation standards meet domestic and ADB policies, are favorable to land

acquisition work for the project, could increase activeness of the households affected by land

acquisition, guarantee the rights and interests of households affected by land acquisition.

4.5.3 Compensation Standard for House Demolition

1. Compensation for house acquisition out of the scope of urban planning areas should be

given according to the Notification of the People’s Government of Xuanzhou District Concerning

Adjustment of the Compensation and Resettlement Standard for Collective Land House

Acquisition, and the Compensation Standard for Above-Ground Attachments and Young Crops in

Xuanzhou District(XQZM (2016) No.18).for specific standard, see Attachment 34.

2. Compensation for house acquisition within the scope of urban planning areas should be

given according to the Notification of Xuancheng Municipal People’s Government Office

Concerning Further Normalization of Compensation and Resettlement for House Acquisition On

Collective Land Within the Scope of Urban Planning Area (XZB (2015) No.11).for specific

standard, see Attachment 35.

Table 4-22 compensation standard for demolition of rural residential houses and auxiliary facilities

Affected

type

Structure

type Unit

Plan

compensation

standard(yuan/

㎡)

Actual

compensation

standard

Remarks

Housing Brick

concrete

㎡ 850 850-900

Page 148: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 147

compensation structure

Brick wood

structure ㎡ 750 800

Simple

structure ㎡ / 300

Other

compensation

Housing

relocation

subsidy

yuan/hu 8yuan /㎡ 500yuan/person

Transitional

living

allowance

yuan/

㎡·month 6yuan/㎡

6 yuan / m2

within 18 months;

12 yuan / m2 after

18 months

The monetary compensation is

calculated and issued for 6

months, the property right

replacement is calculated and

issued for 4 months based on

the existing housing

resettlement, and the

outstanding housing is

calculated and issued for 18

months at 6 yuan / month per

square meter

4.5.4 Compensation Standard for Main Accessories and Infrastructure

For the compensation standard for above-ground attachments and compensation standard for

house demolition involved with Shuiyang River Integrated Transport Construction Project, see

Attachment 34. Agreement for the relocation of pole lines was signed in early May 2016. In Jul. 28,

Municipal Guidance Office held a promotion meeting for the relocation of pole lines, land

acquisition and demolition of Shuiyang River Integrated Transport Development Project, defined

to complete land acquisition and demolition, and relocation of pole lines completely before Aug.

20.

According to the principle of replacement price, determine the compensation standard for the

accessories and infrastructure of the project, which shall not be lower than the resettlement plan

standard in the implementation process.

4.5.5 Other Cost Standards

See 4-23 for other expense standards.

Page 149: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 148

Table 4-23 resettlement tax standard of the project

No Item Charging

standard Basis

1 Land occupation tax 2yuan/㎡ Measures of Anhui Province for the implementation of land

occupation tax (wcrch [2008] No. 367)

2 New construction

land use fee 28yuan/ ㎡

ircular of the Ministry of finance, the Ministry of land and

resources, the people's Bank of China on the adjustment of the

policy on the paid use fee of the newly added construction land

(November 7, 2006) (CZ [2006] No. 48)

3 Cultivated land

reclamation fee 8yuan/㎡

Detailed rules for the implementation of the management of

collection and use of cultivated land reclamation fees in Anhui

Province (wcz [2001] No. 1061)

4 Land acquisition

management fee

4% of total land

acquisition cost

5 Survey and design

cost

3% of total land

acquisition cost

6 External monitoring

and evaluation fee

1% of total land

acquisition cost

7 internal monitoring

and evaluation fee

0.5% of total land

acquisition cost

8 Water conservancy

fund 500yuan/mu

Notice of the people's Government of Anhui Province on printing

and distributing the administrative measures for raising and using

local water conservancy construction funds of Anhui Province (WZ

[2012] No. 54)

9 Administrative

expenses

5% of total land

acquisition cost

10 Technical training

fee

1% of total land

acquisition cost

11 Contingency

(reserve)

10% of the basic

resettlement cost

4.5.6 Vulnerable Groups

In addition to the aforementioned land acquisition compensation policies, vulnerable groups

affected by the project can also enjoy other preferential policies:

Page 150: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 149

(1) Provide vocational training for the labor force in the vulnerable groups' families, and

provide various employment information and guidance to increase employment opportunities;

(2) In the process of project construction, priority should be given to recruiting the labor force

of vulnerable groups to do some non-technical work;

(3) Cooperate with Xuanzhou District Social Labor Security Department of Xuancheng City

to set up a special support fund of 200000 yuan to provide help.

4.5.7 Women's Support Measures

In addition to the policy of land acquisition compensation, women also enjoy special support

policies.

(1) Priority is given to employment opportunities, and 30% of women have access to

non-technical employment opportunities.

(2) Priority will be given to agricultural and non-agricultural technical training. 3000

agricultural and non-agricultural technical training will be conducted in this project, of which at

least 1500 (50%) women will be trained.

(3) Affected women have access to relevant information during the resettlement process and

can participate in fair consultation and resettlement.

(4) During the implementation of resettlement, a special women's forum was held to

introduce relevant policies of resettlement, so as to improve women's awareness.

(5) The compensation agreement must be signed by both husband and wife.

Page 151: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 150

5 Monitoring and evaluation mechanisms for resettlement

5.1 G206 Dongliu to Yaodu monitoring and evaluation mechanisms for

resettlement

5.1.1 Internal Monitoring and Inspection

Resettlement organizations have been available. Coordination Office entrusted by Anhui

Provincial Department of Transport (APDOT) through Dongzhi County Government, is

responsible for the project implementation and resettlement works. County government established

a resettlement leading group, and set up resettlement offices at county, town and village level.

Personnel and equipments have been mobilized.

During the implementation, resettlement offices at town level would collect implementation

information on the basis of individual, family and unit and submit to the County (District) Office;

after that, the information was forwarded to Coordination Office by County (District) Resettlement

Offices; Coordination Office reports the information to Foreign Investment Project Management

Office of the Transport Department of Anhui Province; APMO will regularly the resettlement

works at all levels and inspect the materials submitted and implementation progress. Thus, the

resettlement works at all levels will be incorporated in the monitoring mechanism.

5.1.2 Public Participation

In the stage of implementation, the various governments and affected enterprises and

individuals along the alignment would share the following activities concerning resettlement work:

(1) Compartmentalizing of the compensation scope and defining of compensation standard

(2) Determination of compensation agreement

(3) Selection of resettlement types

(4) Selection of new resettlement spots

(5) Redistribution of land

(6) Relocation and Resettlement for affected individual businesses;

Page 152: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 151

(7) Investigation and coordination on grievance;

(8) Monitoring and evaluation on resettlement work.

As learned, the main Items concerning the public participation activities are summarized as

below:

Table 5-1 public participation

Purpose Mode Time Unit Participants Topics

Announcement on

compensation scheme

for land acquisition

Focus group and

field guidance

and advertisement

Nov.

2013

Relevant town

government in

Dongzhi County

All Affected

Persons(APs)

Compensation, type and policy

of payment

Preparatory works of

land acquisition and

demolition at earlier

stage

Focus group Nov.

2013

Relevant town

government in

Dongzhi County

All Affected

Persons(APs)

County and town levels

headquarters have setup, which

have held twice mobilization

meetings on land acquisition

and demolition for this project.

Preparatory works of

land acquisition and

demolition at earlier

stage

Focus group and

field guidance

and advertisement

Nov.

2013

PMO of

G206Dongliu to

Yaodu Section

Construction

Project

All Affected

Persons(APs)

Establishment of office staff,

issue the documents of land

acquisition and demolition,

carry out implementation.

Announcement and

implementation on

compensation scheme

for land acquisition

Focus group and

field guidance

and advertisement

Nov.

2013

Relevant town

government in

Dongzhi County

All Affected

Persons(APs)

Compensation, type and policy

of payment

Resettlement and

resettlement housing

construction

Consultative

Meeting

Dec.

2013

Maotian Village in

Yaodu Town Affected persons

Listen to the views of the

affected people for the time of

the resettlement sites and

housing construction

Resettlement questions Focus group April

2014

Zhanggang

Village, Dongliu

Town

Affected persons,

Village

government

officials

Demolition and resettlement of

relocated residents had no

objection

Part of the resettlement

housing construction

time

Into the

household

interviews

May

2014

Xiayang and

Zhaqiao Village Affected persons

Respect the wishes of the

individual affected households,

according to the individual

preparation time building

Page 153: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 152

Purpose Mode Time Unit Participants Topics

Woodland

compensation Focus group

Oct.

2014

Meicheng

Forestry, Jin

Sishan Forestry

Forestry center

grows, workers’

representatives

Executive compensation

standard is not less than the

ADB policy Compensation

Standard

5.1.3 Grievance Redress Mechanism (GRM)

Stage 1: If any AP is dissatisfied with resettlement activities, he/she may file an oral or

written appeal to the village committee orally or in writing; if the complainant are not satisfied

with settlement decision, they could appeal at Dongzhi County Transportation Bureau (DCTB)

after receiving decisions; if they are still not satisfied with DCTB’s decision, they could provide

complain to Dongzhi County PMO after receiving decision; Stage 4: If the AP is dissatisfied with

the disposition of Stage 3, he/she may file an appeal to the Wuwei PMO after receiving such

disposition; Stage 5: If the AP is dissatisfied with the disposition of Stage 4, he/she may file an

appeal to the Anhui PMO after receiving such disposition; the AP may also bring a suit in a civil

court in accordance with the Administrative Procedure Law of the PRC at any point in the process.

Project Coordination Office establishes a complaints hotline, and posts the notice of the

complaints hotline in each village, so that the affected households in the resettlement process in a

timely manner to reflect emerging issues and in a timely manner for the Project Coordination

Office to solve problems for the affected households. Complaint Hotline Post published as the

pictures shown below.

Page 154: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 153

Picture 5-1 publication of Complaint Hotline and setting of report box

Monitoring and Evaluation Group learned that some village resettlement offices received

some complaints and questions, which have been settled after careful investigation and on-site

processing, such as water system, road system damage problems reflected by affected households.

Of which, affected households in Fangshan Group informed that the domestic water is affected by

water system destruction. Resettlement Office asked the staff in each township water station

together with technicians to fully check the water system and find out problems, then provide the

inspection results to County Transportation Bureau, in order to timely take measure. County

Transport Bureau makes special arrangements on County and Town Governments. Totaling 6

locations (4 locations within the red line) of water facilities are identified to be transformed, newly

Page 155: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 154

built and rebuilt after field investigation, including: transformation of a drainage and irrigation

station, 4 locations of sluices at entrance and exit, one staunch, and taking into account the small

water system problems. As of June 30, 2016, Water restoration project is basically completed,

residents live, production water is not affected by adverse effects.

5.1.4 Typical Cases

Case 1: During the process of house demolition within the scope affected by the project,

there are 27 house-demolished households, of which actual affected are 22 households, involving

main houses and outbuilding; In addition, Yaodu town involves the demolition of five houses, all

of which are for management auxiliary use only for seasonal use. As the five households have

corresponding housing facilities in other locations, there is no need for resettlement. But the owner

of the house complained that it would be demolished.

Solution: demolish the house according to the requirements of the owner, and compensate the

house in the compensation process. See Table 5-1 for the housing situation and demolition

compensation. The situation of some demolished houses is shown in Figure 5-2.

Table 5-1 Demolition and compensation status for discarded houses

Location Head of

household Compensation(Yuan) Type of Housing

Guansha n

Village

Ding

Longquan 2698

Outbuilding abandoned many years, no

one lives there

Zhaqiao

Village

Village

collective 185307

Fishing lake management room belongs

to village collective

Maotian

Village Hu Mingsheng 348160

Original duck shed, abandoned many

years

Maotian

Village Zhao Zhenzhu 30448

Outdated fishing lake management

shed, no one live there

Jiandong

Village Li Qing 5574

Abandoned house in farmland, no one

live there

Compensation Subtotal 572187

Page 156: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 155

(a) Fishing lake management room belongs to Zhaqiao village collective

(b) Zhao Zhenzhu’s fishing lake management shed

(c) Ding Longquan’s outbuilding without living (d) Li Qing’s broken house located in farmland

Picture 5-2 Original pictures of demolished houses for the purposes of production and management

Case 2: March 19, 2015 one side of the construction of access roads is arable land at Dongliu

Town, due to heavy rains, resulting in the loss of topsoil sidewalk slope covered with a small

amount of farmland, and choked ditches, so farmers through the complaint hotline complained to

the Project Coordination Office.

Solution: March 20, 2015, by field investigation, Coordination Office, the construction team

and other relevant persons of Xiayang Village jointly propose solutions: I. The construction team

complete refurbishment sidewalk slope and clear ditches work before March 22; II. And the

affected households responsible for clean-up arable land, the construction team paid to the affected

Page 157: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 156

households for the costs of clean-up, there is no objection. Construction team complete the

renovation of slope and gutter clear in a specified time, and timely payment of arable land mud

clean-up costs, without bad influence.

5.2 S319 Wuwei to Erba Monitoring and Evaluation Mechanisms for

Resettlement

5.2.1 Internal Monitoring and Inspection

Resettlement organizations have been established for S319 Wuwei Section. Wuwei County

Transportation Bureau entrusted by Anhui Provincial Department of Transport (APDOT) through

Wuwei County Government, is responsible for the project implementation and resettlement works.

The governments at all levels are responsible for the project implementation and relevant

resettlement, conducting the internal monitoring work as well as completion of Internal

Monitoring Report. County government established a resettlement leading group, and set up

resettlement offices at county, town and village level. Personnel and equipments have been

mobilized.

5.2.2 Public Participation

Great importance is given to aps’ participation of and consultation at the preparation and

implementation stages of S319 project. During the implementation, public participation will be

further carried out. PMO has issued a booklet of resettlement information to aps. The group

learned the records on public participation shown as below:

Table 5-2 Records of Public Participation

Purpose Mode Time Unit Participants Topics

Training

program

Village

meeting

Dec. 2014 –

Dec. 2015

Officials fromwuwei

PMO, WCTB, county

land and resources

bureau, town and

village

All APs Discussing training

needs

M&E Sampling

survey, FGD

and

Dec. 2014 –

Jun. 2017

Aexternal Resettlement

Monitoring Agency,

officials of town and

All APs

1) Resettlement

progress and impacts

2) Payment of

Page 158: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 157

Purpose Mode Time Unit Participants Topics

interview village compensation

3) Information

disclosure

4) Livelihood

restoration and house

reconstruction

M&E

Informal

discussion

and

interview

Jan.

2016-Apr.

2016

External

Resettlement

Monitoring Agency,

Cadres of the

towns/townships,

villages

All APs

1) Resettlement

progress and

impacts 2)

Livelihood

recovery and house

reconstruction 3)

information

disclosure

M&E

Informal

discussion

and

interview

Dec.2016

External

Resettlement

Monitoring Agency,

Cadres of the

towns/townships,

villages

All APs

Resettlement

progress and

situation

Resettlement Meeting Sept.,2019 Wuwei County

Project Office

Households

to be

resettled

Resettlement house

selection

5.2.3 Grievance Redress Mechanism(GRM)

S319 Erba to Wuwei Section Reconstruction Project Field Office established S319 Erba to

Wuwei Section Reconstruction project Resettlement Management Office. Personnel and

equipments have been mobilized.

Project Coordination Office establishes a complaints hotline, and posts the notice of the

complaints hotline in each village, so that the affected households could reflect emerging issues in

the resettlement process in a timely manner and the Project Coordination Office could solve

problems for the affected households in a timely manner.

Stage 1: If any AP is dissatisfied with resettlement activities, he/she may file an oral or

written appeal to the village committee orally or in writing; Stage 2: If any AP is dissatisfied with

Page 159: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 158

the disposition of Stage 1, he/she may file an oral or written appeal to the township government

orally or in writing; if any complainant still feels dissatisfied with the decision of Wuwei County

Transport Bureau, the complainant may file a complaint at Dongzhi County Project Office after

receiving the decision, if the complains are still not resolved, they may be submitted to Anhui

Provincial PMO, or an appeal may be lodged to justice department according to Civil Procedure

Law.

Case 1: on Nov. 25, 2015, Ji Changtian from Jicun appealed to the Resettlement Management

Office that the construction team of Contract 03 caused dead of some fish in his pond during

construction, and he asked for compensation of his loss.

Transaction situation: the headquarters coordinated the Project Department of the Fifteenth

Bureau to compensate his loss 500 Yuan.

Case 2: on Dec. 8, 2015, Zhang Zhiqing from Makan appealed to the Resettlement

Management Office that the construction team of Contract 03 affected the rest of pregnant women

during nighttime construction, asked to take corresponding measures.

Transaction situation: the headquarters compensated him 3000 Yuan to find another place for

rest.

Case 3: the S319 project of Wuwei County adopted the construction of bilateral widening,

which was the main road from Wuwei County to Wuhu City. The traffic flow is large, and the road

construction brings hidden dangers to the traffic safety.

Transaction situation: the project headquarters of Wuwei County strictly required the

construction unit to add security facilities such as warning pile guardrail on the basis of the

procurement contract, and invited the traffic police department to add vehicle speed measuring

device in the construction section to prevent the accident risk caused by too fast speed.

Page 160: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 159

5.3 S367 Ma’anshan Northern Passage Road Construction Project

Monitoring and Evaluation Mechanisms for Resettlement

5.3.1 Internal Monitoring and Inspection

S367 Ma’Anshan Northern Passage Road Construction Project Resettlement Organization

Municipal Project Office asked the counties (refer to Hanshan County in this monitoring report,

resettlement related work has not been carried out in He County, the same below) to establish and

allocate special persons for specific resettlement work; deputy director of the Site Department

should be in charge of resettlement related work; deputy town chief of the towns along the line

should be responsible for resettlement related work, and should dispatch personnelfamiliar with

such work and the leaders of relevant administrative villages to coordinate with resettlement work,

classify resettlement-related data for archiving.

To enable the people along the line to further understand relevant ADB policies, promote

successful proceeding of resettlement work, Hanshan County headquarters issued the Resettlement

Plan for Maanshan City Northern Passage Road Project, ADB Security Policies etc and issued to

the villages; relevant resettlement personnel in the town communicated with some AHs for the

compensation standards for acquisition and demolition.

According to the Resettlement Plan for Maanshan City Northern Passage Road Project, in

combination with specific conditions in the counties, Implementation Scheme of Compensation

and Resettlement for House Demolition for S367 Maanshan Section (Northern Passage Road)

Reconstruction Project was formulated in the counties, provided reliable basis for acquisition and

demolition later. Relevant image data were collected timely according to the work progress.

Permanent land acquisition data in the restriction line have been collected, image data of housing

demolition and resettlement sites etc will be collected at next step.

5.3.2 Public Participation

During the feasibility study in the project preparation stage, Ma'anshan PMO has repeatedly

solicited suggestions and opinions from relevant government departments, affected towns, villages

and affected households on the resettlement work of the project.

Page 161: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 160

Since August 2012, under the guidance of technical assistance consulting experts, Academy

of Jiangsu Transportation Sciences Co., Ltd., Ma'anshan project office, Hexian County, Hanshan

County Transportation Bureau and the investigation team of Hehai University have carried out a

series of socio-economic surveys and public consultation (30% of women participated). During the

preparation of the project, the PMO, the implementing agencies and the Design Institute conducted

extensive consultation on the land acquisition and resettlement of the project. See Annex 37 for the

minutes of public participation. The migration information booklet was issued in December 2012.

With the continuous progress of project preparation and implementation, the project

implementation agency will also carry out further public participation. See table 5-3 for details of

public participation arrangements.

The resettlement plan was opened. Before January 31, 2015, the resettlement plan would be

made public in the project office of Ma'anshan City, the office of Transportation Bureau of He

county and Hanshan County, as well as on the website of Ma'anshan municipal government, and

the announcement would be published in the main local newspapers so that the resettlement

householders could consult and put forward their opinions.

Resettlement information book. The main part of the resettlement plan was compiled into

resettlement information manual, which was released to the resettling people before May 31, 2013.

The main contents of the information book include: project overview, project impact,

compensation policy, implementation agency, appeal channel, etc.

Table 5-3 project public participation plan

Purpose Mode Time Unit Participants Topics

Release of

resettlement

plan or

information

book

Release

information

book

May,2013 Ma anshan

project office

Transporta

tion

Bureau of

Hexian

county and

Hanshan

County,

township

governme

nt and

Officially inform

the immigration

plan and its main

contents

Page 162: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 161

Purpose Mode Time Unit Participants Topics

village

committee

Release of

resettlement

plan

website June,2013 ADB

Anhui and

Ma'anshan

PMO

resettlement plan

website open

Announcement

of land

acquisition

Village

bulletin

board and

villagers'

meeting

Feb.,2015

Ma'anshan PMO,

Transportation

Bureau, land and

Resources

Bureau, township

and village cadres

of He county and

Hanshan County

All APs

Announcement of

land acquisition

area,

compensation

standard and

resettlement way,

etc

Announcement

of

compensation

and

resettlement

plan for land

acquisition

Village

bulletin

board and

villagers'

meeting

Feb.,2015

Ma'anshan PMO,

Transportation

Bureau, land and

Resources

Bureau, township

and village cadres

of He county and

Hanshan County

All APs

Compensation fee

and payment

method

Physical

quantity

review

field

investigatio

n

Mar.,2015

Ma'anshan PMO,

Transportation

Bureau, land and

Resources

Bureau, township

and village cadres

of He county and

Hanshan County

All APs

1)Check the

leakage and make

up the deficiency,

and confirm the

final impact

2)List of land

occupied by

immigrants and

assets lost

3)Prepare

compensation

agreement basic

contract

Determine

revenue

villagers'

meeting

Before

implementa

Ma'anshan PMO,

Transportation All APs Discuss the final

income recovery

Page 163: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 162

Purpose Mode Time Unit Participants Topics

recovery plan

and its

implementatio

n

(many

times)

tion Bureau, land and

Resources

Bureau, township

and village cadres

of He county and

Hanshan County

plan and the use

plan of

compensation

funds

training plan Villagers

meeting

2014.12~

2015.12

Human resources

and Social

Security Bureau,

township and

village cadres

All APs Discuss training

needs

monitor

Villagers

participate

in the

meeting

2014.12-20

17.7

township and

village cadres All APs

1) Resettlement

progress and

impact2) Payment

of compensation

3) Information

open

4)Recovery of

production and

life, resettlement

of demolished

houses

monitor

Villagers

participate

in the

meeting

2015.11.02

Project

officeCounty and

township

resettlement

personnel

Part of

APs

Resettlement

training

At present, the vulnerable groups of the affected households of the project have been

investigated, and relevant assistance measures have been formulated (such as technical training,

employment arrangement of the project, life assistance, etc.)

Note: in April 2016, the Ministry of land and resources has issued the reply on the

construction land for the reconstruction project of Ma'anshan section (Northern passage) of the

comprehensive transportation infrastructure project loaned by ADB (GZH [2016] No. 51), see

Annex 36.

Page 164: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 163

During the implementation of the resettlement plan, the resettlement agencies at all levels

shall register and manage the complaint data and processing result data, and report to the project

office of Ma'anshan City in written form once a month. Ma'anshan PMO will regularly check the

registration of complaint handling.

In order to fully record the complaints of the affected population and the handling of related

problems, Ma'anshan PMO and the project implementation agency formulated the registration

form of complaints and grievances of the affected population. See table 5-2 for the format sample.

Table 5-4 resettlement complaint and appeal registration form

Accepting unit: Time: Location:

Name of

complainant

Complaining

content Solution required

Proposed

solutions Actual handling

complainant

(signature)

recorder

(signature)

Note: 1) The recorder shall truthfully record the contents and requirements of the complaint.

2) The grievance process should not be disturbed or obstructed.

3) The proposed solution shall be replied to the complainant within the specified time.

The resettlement agencies of the project will arrange the main person in charge to receive and

handle the complaints and grievances of the affected population. See table 5-5 for names and

contact numbers of offices at all levels and their responsible persons.

Table 5-5 Information on complaint and grievance institutions and personnel of the affected

population

Relevant unit Contact person Telephone

Anhui provincial project office Wufei 0551-63756191

Page 165: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 164

Ma'anshan PMO He changshenf 0555-2471127

Hexian Transportation Bureau Director Miao 0555-5313006

Transportation Bureau of Hanshan County Director Huang 0555-4314354

Case 1:

Complaint content: local residents of K15 + 231.5 passage bridge in Shiyang community,

Shiyang town complained that construction road is too close to the specified distance which will

be harmful to the growth of trees,and asked for compensation.

Transaction situation: After the study of the PMO, it was agreed that the number involved the

villagers' requirements, the number of felling and compensation. The villagers were satisfied with

the result.

Case 2:

Complaint content: Lu changcui, the householder of Dongxing village, Zhaoguan Town,

Hanshan County, whose house is 5 meters away from the red line of land acquisition, asked to be

demolished because the house was higher than the road surface and inconvenient to travel .

Transaction situation: The county and town governments studied and decided not to dismantle,

but repaired the part from the front of the gate to the road, and gave 35000 yuan as compensation.

The householder was satisfied with this treatment. The repaired pavement as shown in the figure.

Figure 5-3 pavement repaired at the gate of Lu changcui in Hanshan County

Page 166: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 165

5.4 G318 and S320 Yimu Highway Project monitoring and evaluation

mechanisms for resettlement

5.4.1 Internal Monitoring and Inspection

Resettlement organizations have been set up for Yimu Highway in Nanling County. Transport

Department of Anhui Province authorized Nanling County Transport Bureau to be responsible for

overall implementation and corresponding resettlement of this project via the people’s government

of Nanling County, the town governments are responsible for the project implementation and

relevant resettlement, conducting the internal monitoring work as well as completion of Internal

Monitoring Report. County government established a resettlement leading group, and set up

resettlement offices at county, town and village level. Personnel and equipments have been

mobilized.

During the implementation, resettlement offices at town level would collect implementation

information on the basis of individual, family and unit and submit to the County (District) Office;

County (District) Relocation & Resettlement Office reports the information to Nanling County

Department of Transport; Nanling County Department of Transport Relocation & Resettlement

Office reports the information to the Foreign Investment Office of the Transport Department of

Anhui Province; APMO will regularly the resettlement works at all levels and inspect the materials

submitted and implementation progress. Thus, the resettlement works at all levels will be

incorporated in the monitoring mechanism.

5.4.2 Public Participation

In the stage of implementation, the various governments and affected enterprises and

individuals along the alignment would share the following activities concerning resettlement work:

(1) Compartmentalizing of the compensation scope and defining of compensation standard

(2) Determination of compensation agreement

(3) Selection of resettlement types

(4) Selection of new resettlement spots

Page 167: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 166

(5) Redistribution of land

(6) Relocation and Resettlement for affected individual businesses;

(7) Investigation and coordination on grievance;

(8) Supervision and evaluation on resettlement work.

Supervision and evaluation team learned from the inspection that, the main items concerning

the public participation activities are summarized in the table below:

Table 5-6 registration form of public participation

Purpose Mode Unit Time Participants Subject

Announcement

on

compensation

scheme for

land

acquisition

Focus group

and field

guidance and

advertisement

Relevant

township,

town

governments

in Nanling

County

May 2014

All Affected

Persons(APs),

as well as

cadres of towns

and villages etc

Compensation,

type and policy of

payment

Preparatory

works of land

acquisition and

demolition at

earlier stage

Focus group

and field

guidance and

advertisement

Project

construction

Management

Office

June 2014

All Affected

Persons(APs),

as well as

cadres of towns

and villages etc

Establishment of

office staff, issue

the documents of

land acquisition

and demolition,

carry out

implementation.

Announcement

and

implementation

on

compensation

scheme for

land

acquisition

Focus group

and field

guidance and

advertisement

Relevant

township,

town

governments

in Nanling

County

Nov.

2014

All Affected

Persons(APs),

as well as

cadres of towns

and villages etc

Compensation,

type and policy of

payment

Resettlement

and

resettlement

housing

construction

Consultative

Conference

Nanling

County Jan. 2015

Affected

persons, as well

as cadres of

towns and

villages etc

Listen to the

affected people’s

view on the time

of resettlement

sites and housing

construction

Page 168: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 167

Purpose Mode Unit Time Participants Subject

Resettlement Consultative

Conference

Jishan

Town,

Nanling

County,

Gongshan

Town

Dec. 2015

External

monitoring

group, Affected

persons,

township, town,

village cadres

etc

Listen to the

affected people’s

view on the time

of resettlement

sites and housing

construction

Resettlement

Focus group

and field

guidance and

advertisement

Relevant

township,

town

governments

in Nanling

County,

external

monitoring

group

Jan. 2016

All Affected

Persons(APs),

township, town,

village cadres

etc

Information

disclosure,

including the

selection of

resettlement

mode, selection

of resettlement

sites and

distribution of

house sites,

construction of

resettlement

apartments etc

Resettlement Consultative

Conference

External

monitoring

group

Apr. 2016

Affected

persons as well

as township,

town, village

cadres etc

Impact survey

before and after

the resettlement

of the already

resettled aps

Resettlement Household

survey

External

monitoring

group

Dec.,2016

Affected

persons as well

as township,

town, village

cadres etc

Sample survey on

living standards

of the affected

people

5.4.3 Grievance Redress Mechanism(GRM)

Nanling Yimu Highway Project Coordination Office established complaints mechanism, and

propagandized the complaints process and procedures in the form of poster, so that the affected

households could reflect emerging issues in the resettlement process in a timely manner and the

Project Coordination Office could solve problems for the affected households in a timely manner.

The poster is shown in Fig.5-4 below. At the same time, Resettlement Office established

Page 169: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 168

resettlement complaint standing book to archive and solve the problems reflected by farmers

timely. Resettlement complaint Record standing book is shown in Fig.5-5.

Picture 5-3 Resettlement Complaint Procedure and Flow Chart Poster

Picture 5-4 Resettlement Complaint Record Standing Book

Case 1:

Complaint content: Five households along the line of Gongshan town are less than 1m away

from the red line of the road. After the completion of the road, frequent vehicle traffic brings

Page 170: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 169

certain safety hazards to residents' travel, and traffic noise, dust and other negative impacts on

Residents' lives. In addition, the way of centralized resettlement was adopted in Gongshan town.

Once the houses were demolished, the demolished households can get higher economic income

Benefit and improve the quality of life. The five households asked the PMO to demolish the

houses and resettle them.

Transaction situation: The appeal requirements of 5 households attracted the attention of

Nanling County Government and Gongshan town government. The government department

carried out a special study and agreed that the five households, like other relocated households in

the red line of the road, would enjoy the policy of demolition and resettlement, and all of them

would be demolished and resettled in the Datang community together with other relocated

households.

Case 2:

Complaint content: on January 8, 2016, there were no K30 + 215, K30 + 300, k29 + 850

culverts in the construction drawing of Yimu road in Gaoling village, Gongshan Town, which led

to the covering of these culverts in the construction, and the villagers could not get water for

irrigation in the fields. Therefore, they applied to the people's Government of Gongshan town to

install culvert pipes in K30 + 215, K30 + 300, k29 + 850 sections.

Transaction situation: it was agreed to install culvert pipes to ensure villagers' irrigation.

Case 3:

Complaint content: Bao Zhengsheng said that his old house was in disrepair for a long time,

and his family worked in Beijing for a long time, resulting in the collapse of the old house. He

wanted to rebuild the house, but the Yimu road will be rebuilt immediately, which will affect the

basic road surface, and he asked to be resettled according to the transitional households in this

resettlement.

Transaction situation: the people's Government of Gongshan Town, after investigation and

verification, reflected the truth of the situation, and the town government decided to give

transitional resettlement. He was very satisfied.

Page 171: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 170

5.5 Shuiyang River Transport Construction Project Monitoring and

Evaluation Mechanisms for Resettlement

5.5.1 Internal Monitoring and Inspection

Resettlement organizations have been set up for Shuiyang River Transport Project.

Xuancheng City the governments at all levels are responsible for the project implementation and

relevant resettlement, conducting the internal monitoring work as well as completion of Internal

Monitoring Report. County government established a resettlement leading group, and set up

resettlement offices at county, town and village level. Personnel and equipments have been

mobilized.

5.5.2 Public Participation

Great importance is given to aps’ participation of and consultation at the preparation and

implementation stages of this project. During the implementation, public participation will be

further carried out. PMO has issued a booklet of resettlement information to aps. The group

learned the records on public participation shown as below:

Table 5-7 Records of Public Participation

Purpose Mode Time Unit Participants Subject

Training

program

Village

meeting

Dec. 2014 –

Dec. 2015

Officials from

Xuanzhou District

PMO, Xuancheng

Municipal

Transportation Bureau,

County Land and

Resources Bureau,

towns and villages

All APs Discussing

training needs

Monitoring

Sampling

survey, FGD

and

interview

Dec. 2014 –

Jun. 2017

External Resettlement

Monitoring Agency,

officials of town and

village

All APs

1) Resettlement

progress and

impacts

2) Payment of

compensation

3) information

disclosure

Page 172: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 171

Purpose Mode Time Unit Participants Subject

4) Livelihood

recovery and

house

reconstruction

Monitoring Field survey Apr. 2016 External monitoring

group

External

monitoring

group and the

affected

persons

Investigation of

the properties

related to vital

interests of the

APs after

resettlement, yet

sufferred from

loss

Monitoring Field survey Dec.,2016 External monitoring

group

The affected

persons

Survey the living

standards of the

affected people

after resettlement

Monitoring Field survey Apl.,2020 External monitoring

group

The affected

persons

Survey the living

standards of the

affected people

after resettlement

5.5.3 Grievance Redress Mechanism(GRM)

Case 1: Due to the shutdown of the construction of Huishang Century City, the resettlement

house of Xuanzhou port comprehensive wharf project, the relocated households were not able to

get the resettlement house within the agreed time (Huishang century city was originally scheduled

to hand over the house on December 31, 2018).

Transaction situation: The local government actively communicated and coordinated with

Anhui Huishang group and Xuancheng Chuangyuan Real Estate Development Co., Ltd.

(developer). Considering that Huishang group was still in the period of internal structure

integration, Xuancheng Chuangyuan Real Estate Development Co., Ltd. was unable to determine

the specific delivery time of Huishang shijicheng project. According to the agreement, the people's

Government of Yangxian township issued the temporary resettlement extension transition fee to

December 31, 2018 (it had been issued to June 30, 2018, and the transition fee from July 1, 2018

Page 173: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 172

to December 31, 2018 will be issued to January 2019). From January 2019, Xuancheng

Chuangyuan Real Estate Development Co., Ltd. bore the temporary resettlement delay transition

fee. If the company fails to pay on time, the people's Government of Yangxian township will

deduct the future generations from the purchase price to pay, so as to effectively protect the

legitimate rights and interests of the relocated households. External monitoring units will continue

to pay attention to resettlement.

Page 174: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 173

6 G206 Dongliu to Yaodu Investigation and Analysis of the Living

Standards of the Affected Households

The resettlement work of each sub project of Anhui multimodal transport sustainable

transportation project loaned by ADB has been basically completed. Since the project involves

relatively scattered affected residents, the external monitoring plan starts this period of monitoring

report. In each report, 1 to 2 sub projects are selected to investigate the restoration of economic

and living standards affected by resettlement, and make analysis reports. This report is an

investigation report on G206 Dongliu Yaodu section project.

6.1 Distribution of survey samples

During December 2013-January 2014, April-May 2014, random samples were made by the

Monitoring and Evaluation Group for investigation on land-affected and house-demolished

families, totaling 46 families, that is, 36 land-affected households, 7 house-demolished families,

and 5 households with land-affected and house-demolished families. The above-mentioned

samples were carried out with baseline investigation and filed.

From April 2020 to may 2020, the survey objects of the affected households are 44 affected

households along the road, including 34 affected by land acquisition, 5 affected by house

demolition, and 5 affected by land acquisition and demolition. The sample distribution is shown in

table 6-1:

Table 6-1Household sample distribution of living standard basic survey

Village(town、street) Number of households

affected

Number of households

investigated Sample

proportion 2013 2019

Xiayang 53 8 8 15.09%

Zhanggang 156 9 9 5.77%

Gaungshan 205 13 13 6.34%

Mantian 206 14 14 6.80%

Among them, there are 53 affected households in Kuanyang village, 8 in this survey; 156 in

Page 175: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 174

Zhanggang village, 9 in this survey; 205 in Guanshan village, 13 in this survey; 206 in Maotian

village, 14 in this survey. The distribution and basic characteristics of the family members selected

in this survey are relatively uniform and representative, which can truly reflect the basic living

standards of the affected households.

6.2 Annual Per Capita Income of Affected Families

In April 2020, the testing team members investigated the annual per capita income of 2017,

2018 and 2019 of the affected households who established the archives.

Table 6-2 annual per capita income of affected families

No. Name Affected type annual per capita income (yuan)

2014.12 2015.12 2016.12 2017 2018 2019

1 Lin guocai Land acquisition 20000 21050 22166 23000 23000 24000

2 Zhang

shouyuan Land acquisition 25000 26312 27707 28000 29000 29000

3 Hu demo Land acquisition 15000 15787 16624 17000 17000 20000

4 Ding longquan Demolition 50000 52625 55414 56000 57000 57000

5 Ye longlin Demolition 40000 42100 44331 46000 46000 47000

6 Zhang guofeng Demolition 15000 16874 17223 18000 20000 21000

7 Hu dekui Land acquisition、Demolition 20000 21056 22166 23000 23000 24000

8 Liu airong Land acquisition、Demolition 15000 15789 16624 17000 18000 20000

9 Su rencai Land acquisition、Demolition 15000 15442 17588 18000 20000 21000

10 Su renguang Land acquisition 20000 21009 22623 23000 24000 24000

From the above monitoring results, it can be seen that the construction of G206 Dongliu

Yaodu project has little negative impact on the family income of local residents. The main reasons

are as follows: the resettlement progress of the project is relatively fast, the period of influence on

the affected households is relatively short, the affected households have enough time to engage in

Page 176: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 175

the original work, and the impact on family income is relatively small. The households affected by

the project are less dependent on the land and the amount of land is small.

6.3 property status of the investigated family

In order to fully reflect the economic situation of the investigated family, this survey took the

investigated family property as an important content. In the survey, 12 kinds of durable consumer

goods or important production materials were selected. Compared with the types of basic living

standard survey, pad and air conditioning projects were increased, DVD / VCD indicators were

reduced, and the rest were basically consistent, trying to reflect the economic level of the

investigated families. See table 6-3 for the specific situation of the average amount of durable

consumer goods owned by the affected households.

On the whole, in April 2020, the survey found that the lowest distribution of indicators was

pad and air conditioner. With the gradual improvement of living standards, the surveyed

households have gradually used pad, and the number of air conditioner is gradually increasing;

broadband ownership is 0.84 per household, computer ownership is 1.84 per household, and

telephone and mobile phone ownership are 4.42 per household. The possession of broadband,

mobile phone, TV and computer is relatively high, which shows that the information between

villagers and society is unobstructed, which has a positive role in promoting the social

development of rural collective. At the same time, with the development of mobile phone network,

the possession of TV has declined. The number of refrigerators and washing machines per

household is 1.21. It can be seen from the data comparison of the two surveys that the ownership

of broadband and computers of residents has greatly increased in 2019 and 2013, on the one hand,

the reason is that the information consumption cost has been greatly reduced; on the other hand,

the income level of residents has been greatly improved, affected by the convenience of the

improvement of communication and the improvement of income level, cars, motorcycles / electric

bikes The quantity of non necessities has also been greatly increased.

Table 6-3 average household ownership of durable consumer goods of affected households

Xiayang Zhanggang Guanshan Maotian Population

Page 177: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 176

Property name 2013 2019 2013 2019 2013 2019 2013 2019 2013 2019

broadband 0.71 0.75 0.82 0.89 0.73 0.85 0.71 0.86 0.74 0.84

Computer 1.43 1.75 1.55 1.89 1.46 1.85 1.43 1.86 1.46 1.84

Pad / 0.38 / 0.33 / 0.54 / 0.43 / 0.43

M-phone 3.86 4.00 4.46 4.50 3.73 4.00 4.07 5.00 4.00 4.42

TV set 3.36 3.50 0.36 1.11 3.27 3.08 2.86 3.00 2.58 2.73

Air conditioner / 0.50 / 0.33 / 0.46 / 0.57 / 0.48

refrigerators 1.07 1.00 1.27 1.11 1.00 1.00 1.21 1.57 1.14 1.20

washing machine 1.00 1.00 1.27 1.00 1.00 1.00 1.21 1.23 1.12 1.07

bike 1.71 1.75 1.27 1.33 1.55 1.54 1.64 1.43 1.55 1.50

motorcycles / electric bike 1.36 1.75 1.36 1.56 1.55 1.77 1.43 1.71 1.44 1.70

car 0.21 0.25 0.91 1.00 0.18 0.46 0.57 0.64 0.46 0.59

Agricultural machinery 0.36 0.38 0.82 0.78 0.46 0.38 0.72 0.86 0.59 0.61

6.4 Living Conditions of the Investigated Family

6.4.1 Basic Public Goods Such as Water and Electricity

6.4.1.1 Domestic Water

The domestic water is mainly from three aspects: tap water, well water, pond water, etc. in

fact, there is no use of lotus pond water, so it will not be shown in the table. See table 6-4 for

details.

Table 6-4 domestic water situation of investigated households (%)

Xiayang Zhanggang Guanshan Maotian total

Year 2013 2019 2013 2019 2013 2019 2013 2019 2013 2019

Tap

water 16.9 87.5 12.56 88.89 32.7 84.62 12.39 85.71 19.39 86.36

Well

water 83.1 25 87.44 22.22 67.3 23.07 87.61 14.26 80.61 20.44

total 100 112.5 100 111.11 100 107.69 100 105.39 100.00 106.81

Page 178: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 177

Figure 6-1 domestic water sources in 2013 and 2019 (%)

Figure 6-2 source of domestic water (%)

In general, 19.39% of households use tap water in 2013, and 80.61% use well water. With the

policies of better rural construction and other policies, all rural areas have access to tap water. In

2020, the proportion of total use of tap water has increased significantly, to 86.36%. There are

problems in living habits. Some residents still use well water at the same time, and the proportion

of total use of well water has decreased significantly to 20.44%, totaling 100% The reason why the

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

80.00

90.00

100.00

2013 2019

Tap water Well water

Page 179: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 178

ratio is more than 100 is that some families use tap water and well water at the same time.

6.4.1.2 Domestic Electricity

According to the analysis of three indicators, the household electricity consumption of the

investigated households is all guaranteed, and there are no households with no electricity.

Sufficient electricity can ensure the daily production and living needs of the residents. See table

6-5 for the specific situation of domestic power consumption in the sample village.

Table 6-5 household electricity consumption (%)

Xiayang Zhanggang Guanshan Maotian Population

2013 2019 2013 2019 2013 2019 2013 2019 2013 2019

Guaranteed 100 100 100 100 100 100 100 100 100 100

Yes, but no

guarantee

0 0 0 0 0 0 0 0 0 0

No 0 0 0 0 0 0 0 0 0 0

6.4.2 House condition

6.4.2.1 HouseType

81.64% of the total families are buildings. Compared with 63.6% in 2013, the proportion of

buildings has increased, because the productivity development level along the line is high, the

family living standard is good, and the housing conditions are good. See table 6-6 for details.

Table 6-6 investigated family buildings (%)

Xiayang Zhanggang Guanshan Maotian Population

2013 2019 2013 2019 2013 2019 2013 2019 2013 2019

Bungalow 37.5 12.5 33.33 11.11 46.15 23.08 28.57 21.43 36.40 18.36

Building 62.5 87.5 66.67 88.89 53.85 76.92 71.43 78.57 63.60 81.64

total 100.00 100.00 100.00 100.00 100.00 100.00 100.00100.00 100.00 100.00

Page 180: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 179

Figure 6-3 house types of surveyed households in 2013 and 2019 (%)

Figure 6-4 proportion of total house types of surveyed households (%)

The distribution structure of sample villages of bungalows and buildings is basically

consistent with the overall sample. The proportion of buildings in all sample villages is more than

75%. The proportion of buildings and bungalows in Xiyang village is 87.5:12.5, that in Zhanggang

village is 88.89:11.11, that in Guanshan village is 76.92:23.08, and that in Maotian village is

78.57:21.43.

6.4.2.2 House Structure

Page 181: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 180

From the perspective of housing structure, in 2013, 86.96% of the households in the overall

sample were brick and concrete houses, with the proportion of brick and wood houses ranking

second, 8.69%, and the proportion of civil houses and simple houses was 2.17%, respectively, with

a high overall living level; in 2019, the survey showed that the proportion of frame structure

houses was 31.82%, the proportion of brick and concrete structure houses was 67.02%, the

proportion of simple houses was 1.16%, and the proportion of brick and wood houses and civil

structure houses was 0. See table 6-7 for details.

Table 6-7 house types of the investigated households (%)

Xiayang Zhanggang Guanshan Maotian Population

2013 2019 2013 2019 2013 2019 2013 2019 2013 2019

Frame 0.00 50.00 0.00 44.44 0.00 38.46 0.00 7.14 0.00 31.82

Brick 62.50 43.60 88.89 55.56 100.00 61.54 86.67 92.86 86.96 67.02

Brick and

wood 12.50 0.00 11.11 0.00 0.00 0.00 13.33 0.00 8.69 0.00

Civil

Engineering 12.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.17 0.00

Simple 12.50 6.40 0.00 0.00 0.00 0.00 0.00 0.00 2.17 1.16

Total 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00

Page 182: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 181

Figure 6-5 house structure of the surveyed households in 2013 and 2019

Figure 6-6 house structure of the investigated families in each village

The characteristic distribution of each sample village is slightly different. Before the

demolition, there was no frameless structure in the investigation sample. After the demolition,

31.82% of the houses were rebuilt as frame structures. From the perspective of brick and concrete

houses, the highest proportion is Maotian village, which is 92.86%. The house type is mainly

frame and brick and concrete structure, and very few families have civil structure houses and brick

and wood structure houses. There are basically no civil and simple houses. The overall living

Page 183: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 182

conditions are good.

6.4.3 Living Environment

The target of this analysis design is the distance from the place where we live to the nearest

hospital, school, shopping center and bus station and the time needed. Table 6-8 shows the distance

and time of the nearest public facilities in the residence of the investigated family. There is

basically no change between the survey results and the base survey in 2019. But after the new road

is built, the road condition is greatly improved, the travel is more convenient, and the time is

shortened. It is more convenient for residents to travel.

Table 6-8 the distance between the nearest public facilities in the residence of the investigated

family (km)

Bus

station

Towns at or above the

county level

Market

town

Primary

school

Middle

school Hospital

Xiayang 7.5 9 4 0.8 1 1

Zhanggang 9 14 1 1 1 1

Guanshan 8 8 1 1 1 1

Maotian 6 7 1 1 1 1

6.5 Analysis of the Economic Income and Source of the Investigated

Family

6.5.1 Economic Income of the Investigated Family

According to the survey and statistics, before the land acquisition of each village involved in

the project, there are 5892.11 mu of cultivated land, with an average per capita cultivated land of

1.11 mu / person. 294.36 mu of cultivated land is expropriated for the project, with an impact rate

of 4.9%. After land acquisition, the per capita cultivated land is 1.052 mu / person. The vast

majority of people affected by land acquisition will lose only part of their land. According to the

socio-economic survey, the situation of cultivated land before and after land acquisition in the

affected villages was compared and analyzed. Among the six affected villages, none of them lost

Page 184: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 183

more than 25% of the land. The highest loss rate was 20.62% (Tiaokou group, Maotian village,

Yaodu town), and the lowest loss rate was 1.53% (huatuple, Maotian village, Yaodu town). In

general, the level of land loss in the villages affected by the project is very low. The agricultural

production and operation status of the investigated family is not affected by the land acquisition of

the project.

From the perspective of the income level of the surveyed households, the average income

level of the surveyed households was 69792 yuan in 2013 and 81100 yuan in 2019. The income of

the investigated families all increased.

Table 6-9 annual average income of families (yuan)

Village Xiayang Zhanggang Guanshan Maotian Average annual income per household

Year 2013 2019 2013 2019 2013 2019 2013 2019 2013 2019

Income

(yuan) 45575 59000 57400 68800 87700 96000 73429 87800 69792.07 81100.00

Figure 6-7 average income of each village household surveyed in 2013 and 2019 (yuan)

Page 185: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 184

Figure 6-8 average income of each village investigated (yuan)

6.5.2 Income source analysis

According to the survey, the construction industry, commerce and service industry are the

first income sources, followed by industry and food planting. This income structure shows that

along the G206 Dongliu Yaodu section, farmers' household income is no longer dominated by

agricultural production. Construction industry, commerce and service industry are the main

sources of farmers' income. See table 6-10 and 6-11 for the specific data of the income

composition of farmers' households in each village.

Table 6-10 distribution of income sources of surveyed households in 2013 and 2019 (yuan)

Food / crop

cultivation

Fishing or

poultry

keeping

Industry construction

industry

commerce and

service industry

Other

industry total

Xiayang

2013 9200 63 14625 4812 14375 2500 45575

2019 9300 0 20000 10700 17000 2000 59000

Zhanggang

2013 12818 0 15136 14545 13091 1818 57408

2019 14000 0 18000 19500 14400 2900 68800

Guanshan 2013 11950 0 13350 43600 16800 2000 87700

Page 186: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 185

Food / crop

cultivation

Fishing or

poultry

keeping

Industry construction

industry

commerce and

service industry

Other

industry total

2019 13000 0 15500 46000 18900 2600 96000

Maotian 2013 12214 0 13929 31143 13286 2857 73429

2019 12800 0 16000 35000 19500 4500 87800

Pupolation

2013 11728 11 14110 27108 14507 2331 69794

2019 12375 3 14884 33700 16531 3128 80622

Figure 6-9 income sources of households surveyed in 2013 and 2019 (yuan)

Page 187: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 186

Figure 6-10 proportion of average income sources of households in the overall survey

for 2013 and 2019 (%)

Table 6-11 proportion of household income sources (5%)

Food / crop cultivation Fishing or poultry

keeping

Industry construction

industry

commerce and

service industry

Other

industry

2013 16.80 0.02 20.22 38.84 20.79 3.34

2019 15.35 0.00 18.46 41.80 20.50 3.88

Page 188: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 187

Figure 6-11 proportion of average income sources of households surveyed in 2013, 2019 (yuan)

6.6 Subjective Evaluation of the Living Conditions of the Investigated

Families

6.6.1 Evaluation of Own Production Conditions

The evaluation of self production conditions can be divided into five grades: very good, good,

general, poor and very poor. Generally speaking, the majority of people hold "general", "good" and

"very good" opinions, and they do not hold a poor and very poor evaluation attitude towards their

own production conditions. Therefore, these two items are omitted in the following chart. With the

economic development, the proportion of residents who hold a "good" attitude towards their own

production conditions has increased, indicating that the residents are satisfied with the current

production conditions. See table 6-11for the specific situation.

Table 6-11 evaluation of the investigated families on their own production conditions (%)

Village Very good Good General total

Xiayang 2013 37.5 25 37.5 100

2019 37.5 37.5 25 100

Zhanggang 2013 0 100 0 100

2019 33.33 66.67 0 100

0

5

10

15

20

25

30

35

40

45

Grain crop Poultry Industry Architecture Business and

Service

Other

2013年 2019年

Page 189: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 188

Guanshan 2013 0 40 60 100

2019 30.77 38.46 30.77 100

Maotian 2013 21.4 28.6 50 100

2019 28.57 35.72 35.71 100

Population 2013 13.50 45.41 41.09 100.00

2019 31.72 42.92 25.36 100.00

Figure 6-12 evaluation of production conditions of investigated families in each village (%)

Page 190: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 189

Figure 6-13 overall evaluation of production conditions of the surveyed families (%)

6.6.2 Evaluation of the Economic Situation of the Whole Village

The evaluation of their own economic situation is also divided into five grades, which belong

to the whole village: first-class, middle-class, middle-class, middle-class, and low-class. According

to the survey in April 2020, 97.73% of them are above average. See table 6-12 for details.

Table 6-12 evaluation of the economic status of the investigated families in the whole village (%)

Superior Upper-middle Middle Below-middle Inferior total

Xiayang 2013 12.5 12.5 62.5 12.5 0 100

2019 25 25 37.5 12.5 0 100

Zhanggang 2013 9.1 90.9 0 0 100

2019 33.33 66.67 100

Guanshan 2013 30 10 60 0 0 100

2019 38.46 28.57 32.97 100

Maotian 2013 0 28.6 64.3 7.1 0 100

2019 28.57 21.43 50 100

Population 2013 13.08 32.33 50.10 4.49 0 100.00

2019 31.82 33.44 32.47 2.27 0.00 100.00

Page 191: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 190

Figure 6-14 evaluation of the economic situation of the investigated families in each village

Figure 6-15 evaluation of the overall economic status of the surveyed families

6.6.3 Assessment of current living environment

From the overall point of view, the assessment of the current living environment of the

surveyed families is generally good and good. Among them, the very poor level. With the

improvement and construction of national environmental requirements, the residents' environment

has been greatly improved. At present, there are no poor residents in the residential environment

assessment, so the list is no longer reflected. The overall evaluation is good. See table 6-13 for

Page 192: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 191

details.

Table 6-13 assessment of current living environment of surveyed families (%)

Very good Good General Total

Xiayang 2013 25 50 25 100

2019 50 25 25 100

Zhanggang 2013 0 100 0 100

2019 55.56 44.44 0 100

Guanshan 2013 40 30 30 100

2019 46.15 30.77 23.08 100

Maotian 2013 21.4 28.6 50 100

2019 28.57 35.71 35.72 100

Population 2013 23.50 46.72 29.78 100.00

2019 43.18 34.09 22.73 100.00

Figure 6-16 evaluation of living environment of surveyed families in each village

6.6.4 Evaluation of Neighborhood Relationship

In the evaluation of neighborhood relationship, the poor evaluation of each sample village is 0,

and the poor proportion is the lowest. See table 6-14 for details.

Page 193: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 192

Table 6-14 evaluation of neighborhood relationship of surveyed families (%)

Very good Good General Poor total

Xiayang 2013 25 50 12.5 12.5 100.00

2019 50 25 12.5 12.5 100.00

Zhanggang2013 18.2 36.4 36.4 9 100.00

2019 44.44 33.33 22.22 0.00 100.00

Guanshan 2013 20 40 30 10 100.00

2019 30.77 46.15 15.38 7.69 100.00

Maotian 2013 21.4 42.9 28.6 7.1 100.00

2019 28.57 42.86 21.43 7.14 100.00

Population 2013 20.97 41.98 27.75 9.29 100.00

2019 36.36 38.64 18.18 6.82 100.00

Figure 6-17 evaluation of the relationship between themselves and their neighbors

Page 194: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 193

Figure 6-18 the overall evaluation of the relationship between themselves and their neighbors

The evaluation of the relationship with the neighborhood has greatly improved the overall

quality of the residents compared with the previous ones because of the higher and higher cultural

education they have received. Among the sample villages surveyed in 2020, the highest proportion

was 12.5% in Kuanyang village, 7.69% in Guanshan village, 0% in Zhanggang village and 7.14%

in Maotian village. It is believed that 70% of them have a good relationship with their neighbors. It

can be seen that the investigated family has a good neighborhood relationship.

6.6.5 Evaluation of current life satisfaction

Overall, in 2019, 65.91% of the respondents were satisfied with their current life, 25% of

them were generally satisfied, and the overall evaluation was relatively high. In the overall sample,

7.69% of them were not satisfied with their current living conditions. In the sample survey

households, there were no samples that were very dissatisfied with their life satisfaction.

According to the survey, the dissatisfaction of the sample families is mainly caused by the high

level of material living and the high pressure of life. The main factors that lead to the high pressure

of life are the high cost of education for children, the large expenditure of human relationship, and

the great uncertainty of income. The overall satisfaction in 2019 is higher than that in 2013. See

table 6-16 for details.

Table 6-15 evaluation of life satisfaction of surveyed families (%)

Page 195: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 194

Very satisfied Satisfied General satisfied Dissatisfied Total

Xiayang 2013 12.50 37.50 25.00 25.00 100.00

2019 25.00 37.50 25.00 12.50 100.00

Zhanggang 2013 9.00 27.30 45.50 18.20 100.00

2019 33.33 44.44 11.11 11.12 100.00

Guanshan 2013 10.00 30.00 40.00 20.00 100.00

2019 23.08 46.15 23.08 7.69 100.00

Maotian 2013 7.20 35.70 35.70 21.40 100.00

2019 21.43 35.71 35.71 7.14 100.00

Population 2013 9.33 32.63 37.07 20.97 100.00

2019 25.00 40.91 25.00 9.09 100.00

Figure 6-19 evaluation of the family's life satisfaction

Page 196: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 195

Figure 6-20 evaluation of the overall satisfaction of the surveyed families to their lives

In 2019, 25%, 37.5%, 25% and 12.5% of Panyang village were very satisfied, general

satisfied and dissatisfied with life; 33.33%, 44.44%, 11.11% and 11.12% of Zhanggang village

were very satisfied, general satisfied and dissatisfied with life; Guan Shan village was very

satisfied and satisfied with life 23.08%, 46.15%, 23.08% and 7.69% respectively were very

satisfied, satisfied, general satisfied and dissatisfied with life in Maotian village, 21.43%, 35.7%,

35.7% and 7.14% respectively.

7 Basic Assessment and Suggestions

7.1 Basic Assessment

1) The implementation agencies of each subproject of multimodal transport sustainable

transportation project can carry out the work in accordance with the resettlement action plan, and

pay attention to the policy publicity and public participation of resettlement. The resettlement

action plan has been well implemented.

2) The resettlement work of G206, S367 and Yimu road has been completed.

3) S319 resettlement is planned to be completed during the Spring Festival in 2020.

4) The land acquisition of Shuiyangjiang shipping comprehensive development project has

been completed, but the resettlement of relocated households has not been completed.

Page 197: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 196

5) According to the economic survey and analysis of G206 affected households, the negative

impact of G206 project construction on the affected households is relatively small, and the

economic income, living environment, etc. are increased or improved.

7.2 Basic Suggestions

1) The sub project implementation organization that has completed the resettlement work

shall prepare the resettlement summary report in time, so as to summarize the resettlement

summary report of the whole multimodal transport project.

2) The implementation agency shall continue to pay attention to the living standard and

income recovery of the affected households after resettlement, and ensure that the living standard

and income of the affected households are not lower than the level before the implementation of

the project.

3) The implementation organization of the second military road of S319 in Wuwei County

should properly settle the relocated households as soon as possible, and prevent and timely deal

with the problems that may occur during the period of waiting for the completion of the

resettlement community.

4) The construction of 319 phase II project may involve the households affected by land

acquisition and demolition. It is suggested that the external monitoring of resettlement of phase II

construction project be combined with the construction project of S319 Erba Wuwei section for

external monitoring.

5) The relocation households of the comprehensive wharf of Shuiyangjiang shipping

comprehensive development project have not completed the resettlement. The project

implementation agency actively coordinates with the local government to promote the construction

progress of "Huishang No.1" resettlement site. Resettle the relocated households as soon as

possible.

Page 198: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 197

8 Attachments

Attachment 1: Project Location Diagram

Page 199: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 198

Page 200: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 199

Attachment 2: G206 Project Approval of constrution land issued by Anhui provincial government

Page 201: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 200

Attachment 3: Approval of Construction Land for Road S319 Erba to Wuwei Section Reconstruction Project

Page 202: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 201

Page 203: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 202

Attachment 4: Notice on establishment of project resettlement office

(1) Otice on establishment of Chizhou Municipal project

resettlement office

(2) Notice on establishment of Dongzhi County project

Page 204: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 203

resettlement office

(3) Assignment of responsibilities in G206 PMO

Page 205: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 204

Page 206: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 205

Attachment 5: Report on the Establishment of S319 Construction

Headquarters in Wuwei County

Page 207: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 206

Attachment 6: foundation file of anhui Jiaoyuan engineering project

management limited company

Page 208: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 207

Attachment 7: Agreements On Land Acquisition

G206 Project Compensation for land acquisition agreement

Page 209: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 208

S319 Project compensation agreement

Page 210: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 209

Attachment 8: Agreements on Land Acquisition of Forest Farm for G205 Project

(1)Land acquisition agreement on permanent woodland of

Jinsishan forest farm

(2)Land acquisition agreement on temporary woodland of

Page 211: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 210

Meicheng forest farm

Page 212: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 211

Attachment 9: Staff Meeting File of Forest Farm

Page 213: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 212

Attachment 10: Lease contract on mixing plant ground in lishan working area

Page 214: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 213

Page 215: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 214

Page 216: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 215

Attachment 11: Rental Agreement on Temporary Land Use for Mixing Plant in S319 signed by Road and Port Group

Page 217: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 216

Page 218: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 217

Page 219: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 218

Attachment 12: housing lease contract of project management department in contract 01

Page 220: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 219

Page 221: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 220

Attachment 13: Rental Contract of Project Management Department Signed by Road and Port Group

Page 222: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 221

Page 223: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 222

Page 224: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 223

Page 225: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 224

Page 226: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 225

Attachment 14: Housing lease contract of project management department

in contract 02 of G206 Project

Page 227: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 226

Page 228: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 227

Page 229: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 228

Attachment 15: Housing lease contract of S319 Project

Page 230: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 229

Page 231: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 230

Attachment 16: G206 Project housing lease contract of maintenance center

Page 232: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 231

Attachment 17: G206 Compensation agreement for house demolition

Page 233: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 232

Page 234: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 233

Page 235: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 234

Page 236: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 235

Attachment 18: Compensation agreement for power lines reconstruction project

Page 237: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 236

Attachment 19: G206 Project Compensation agreement for communications trunk cables relocation project

Page 238: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 237

Attachment 20: G206 Project Water migration agreement

Page 239: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 238

Attachment 21: G206 Project Forestry land compensation supplemental agreement

Page 240: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 239

Attachment 22: G206 Project Statistics of water conservancy project

Page 241: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 240

Attachment 23: G206 Project River restoration task decomposition table

Page 242: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 241

River Restoration Task Decomposition Table for G206 Dongliu to Yaodu Section

Construction Component

2015.1.20

No. Pile No.and place Existing problems Treatment opinions,

suggestions Deadline

Responsible

organizations

Contact person

for

coordination

1

Xiayang Village

K0+130-K0+220,

K0+330-K0+580,

K0+730-K0+980

Water system in the

section is destroyed,

should be restored Carry out temporary recovery for

Contract 1

Restored

properly

before the

Spring Festival

Project Office Road

and Bridge

Company

Wang Qianchun,

Han Xiuyu

2 Zhanggang Village

K2+70-K3+510

Water system in the

section is destroyed,

plus dredgingff 3 hilly

Page 243: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 242

ponds

3

Seven places including

Xiaohuangni Lake,

Zetanwei

New station, water

gate reconstruction,

recovery of pond weirs

Reconstruction of outlet sluice

station at Zetanwei commenced

in 2014, construction of new inlet

sluice station commenced, the

rest design has been completed

Completed

before flood

season

Water Bureau

Ruan Zhonghua,

Ling Guoping 4

At Xiaohuangni Lake,

Guanshan Village

Recovery of excavated

Xiaohuangni Lake dam

before flood season

After capping beam is

completed, Contract 1 should be

restored timely according to

water level situation

Completed

before flood

season

Project Office Road

and Port Company

5

At the border of

viaduct and Quanshui

Lake dam in Zhaqiao

Recovery of the

excavated part

Construction scheduling of

Contract 1

Completed

before flood

season

Project Office Road

and Bridge

Company

Page 244: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 243

Village

6 At Quanshui Lake in

Zhaqiao Village

Cofferdam in the lake

is not constructed

properly

Immediate organization of

construction for Contract 1

properly

At the end of

January

7

Lishan Avenue to

railway bridge in

Maotian Village

Sequential connection

of large area drainage

at Zetangwei

Temporary recovery of Contract 2 Before the

Spring Festival

Project Office Road

and Port Company

8 Near railway bridge in

Jiandong Village

Recovery of Shiyin

Group electric

pumping station

switch room, cable

facilities

Recovery of the sites selected in

towns and villages

Before spring

ploughing Yaodu Town

Page 245: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 244

9

Railway bridge to

Mt.Daqing in Jiandong

Village

Sequential connection

of water system, road Temporary recovery of Contract 2

Before the

Spring Festival

Project Office Road

and Port Company

10

At south end of

Mt.Daqing in Maotian

Village

Tangfan Pond

drainage culvert

connection

Temporary recovery of Contract 2 At the end of

January

Page 246: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 245

Attachment 24: Minutes of Meeting of Coordination Meeting for Pipeline Relocation of S319 Project.

Page 247: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 246

Page 248: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 247

Page 249: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 248

Attachment 25: Approval of Construction Land Use for Nanling Yimu Highway Project

Page 250: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 249

Attachment 26: Notice on establishment of Nanling County project resettlement office

Page 251: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 250

Attachment 27: Notice on establishment of Shuiyang River project

resettlement office

Page 252: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 251

Attachment 28: Housing lease contract of Nanling Contract 01

Page 253: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 252

Attachment 29: Housing lease contract of Nanling Contract 02

Page 254: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 253

Page 255: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 254

Attachment 30:Notification Concerning the Compensation Scheme of House Demolition On Collective Land in

Jishan Town, Gongshan Town

Page 256: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 255

Attachment 31: Agreement on the Compensation of Young Crops for

Nanling Yimu Highway

Page 257: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 256

Attachment 32:Compensation Agreement On Land Acquisition in Nanling

Page 258: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 257

Attachment 33 Notice On Establishment of S367 Hanshan Section

Reconstruction Project Resettlement Office

Page 259: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 258

Attachment 34 Agreement On Land Acquisition for S367

Page 260: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 259

Attachment 35: Compensation Standard for House Demolition On

Collective Land and Above-Ground Attachments, and Compensation Standard

for Young Crops in Xuanzhou District

Compensation Standard for House Demolition On Collective Land (Table 1)

Unit: Yuan/㎡

Category

Class House structure and standard

Basic

price

Composite

structure

1

Reinforced concrete beam, column, solid brick wall, flat roof or

tiled roof, flat roof ceiling, complete doors, windows, water,

electricity, kitchen, washroom, cement ground

900

2

Reinforced concrete beam, column, single, dual wall, flat roof or

tiled roof, simple ceiling, complete doors, windows, water,

electricity, kitchen, washroom, cement ground

850

Masonry-timber

structure

1

Load bearing brick wall, wooden roof truss, tiled roof, cement or

wooden floor, solid brick wall, flat roof ceiling, complete doors,

windows, water, electricity, kitchen, washroom, above two rooms

(including 2 storeys, storey height is above 2.8m) one-off design,

synchronous construction

800

2 Cement or timber purlin, cement or wooden floor, single, dual

wall, flat tile roofing, smooth ceiling, with utilities 730

3 Mixed bamboo and timber purlins, three-ply wood and simple

cement ground, single wall, flat tile roofing, smooth ceiling, with

utilities

650

Simple structure

1

Irregular roof truss, bamboo and wood base course, thatched, tile

or asbestos roof, adobe, broken brick and other simple walls,

simple ground, with electricity, eaves height above 2.2m

300

2 Irregular roof truss, bamboo and wood base course, thatched, tile

or asbestos roof, adobe, broken brick and other simple walls,

simple ground, with electricity, eaves height below 2.2 m

200

Compensation Standards for House Demolition On the Collective Land

Acquired and Temporary Relocation (Table 2)

Page 261: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 260

Category Subsidy standard Remarks

Transition subsidy for demolition

(relocation expense, transition

subsidy)

500 Yuan/person

One-off subsidy according to

the population registered on

the residence booklet

Compensation for

shutdown loss

Business

house

Calculate according to 20

Yuan/㎡/month for

building area of principal

room

Time should be calculated

according to three to six

months, no more than six

months at the most

Production

house

Calculate according to 10

Yuan/㎡/month for

building area of principal

room

Office house

Calculate according to 5

Yuan/㎡/month for

building area of principal

room

Note: 1. Business house and production house must have business license and tax

registration certificate before the release of demolition announcement, and only monetized

resettlement is possible. If residence is changed to business house or production house without

approval of the planning department, compensation and resettlement will be performed according

to residential houses uniformly.

2. For demolition of leased (borrowed) house, the owner of the leased (borrowed) house shall

terminate the lease relationship with the rental household. If rental households lease the houses of

the AHs for commercial production, processing and other production activities, the AHs shall be

responsible for the relocation, the demolition party will not compensate relocation cost of the

production facilities.

Compensation Standard for Young Crop on the Collective Land Acquired

Page 262: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 261

(Table 3)

Unit: Yuan/mu

Category of land Paddy field Dry land Remarks

Compensation standard 1000 800

Notes: Compensation for young crops should be released to the owner of the young crops.

Compensation Standards for Demolition of House Attachments and Decoration

On the Collective Land Acquired (Table 4)

Name Specification Compensation

amount Remarks

Loft

Formal Eaves height above

1.8m 150 Yuan/㎡

With fixed wooden or

masonry stairs Common

Eaves height below 1.

8 m, 1.5 100 Yuan/㎡

Simple Eaves height below 1.

5 m, above 1m 30 Yuan/㎡

Enclosing

wall

Simple enclosing

wall

Fence, bamboo

enclosing wall 30 Yuan/㎡

Masonry

enclosing wall 50 Yuan/㎡

Electricity meter 150

Yuan/piece

Water meter 200

Yuan/piece

Balcony

Self-enclosed

aluminum alloy

windows

200 Yuan/㎡ No compensation for those

already included into the

compensation area for

demolition Self-enclosed

plastic-steel

window

250 Yuan/㎡

Door Iron gate 30 Yuan/㎡

Page 263: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 262

Name Specification Compensation

amount Remarks

Roller shutter

door 50 Yuan/㎡

Security door 450

yuan/piece

Outdoor

ground

Cement floor 40 Yuan/㎡

Masonry ground 25 Yuan/㎡

Decoration ground

Floor tiles, terrazzo

and other veneer 60 Yuan/㎡

Marble, granite

veneer 70 Yuan/㎡

Crushed material veneer 20

Yuan/㎡

Decoration ceiling

Three-ply board,

plastic pinch plate,

gypsum suspended

ceiling

30 Yuan/㎡

No compensation for roof

ceiling, suspended ceiling

etc

Decoration wall surface

Three-ply board,

plastic pinch plate

wainscot, latex paint

20 Yuan/㎡

White ceramic tile,

wall tile, dimension

stone and other veneer

30 Yuan/㎡ Internal wall

20 Yuan/㎡ Outside wall

Simple shed 20 Yuan/㎡

Stove

Single stove 200

Yuan/piece Including tiling on the

stove surface Double stove

400

Yuan/piece

Pool 50 Yuan/piece

Retaining wall Within 2 60 Yuan/㎡

Page 264: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 263

Name Specification Compensation

amount Remarks

Above 2 85 Yuan/㎡

Bathtub 300/piece Including facing tile

Bath pot 500

Yuan/piece Including facing tile

Telephone replacement cost 30 Yuan/unit

One-off compensation 200 Yuan as replacement cost of CATV, tap water.

Air-conditioner Window type 100 Yuan/set Replacement cost

Split wall-hanging 150 Yuan/unit Replacement cost

Water heater

Solar energy 300 Yuan/unit Replacement cost

Indoor gas water

heater 100 Yuan/set Replacement cost

Electric water heater 100 Yuan/set Replacement cost

Kitchen ventilator 100 Yuan/set

Compensation Standard for Above-Ground Attachments On Collective Land

Within Recent Construction Scope in Xuanzhou District (Table 5)

Category Unit Standard Notes

Tomb

Yuan/coffin

Cement structure double coffin

and above 800

Unkown tombs are relocated

or buried by the affected unit

instead.

Cement structure single coffin,

earth grave structure double coffin

and above 600

Earth grave structure single coffin

400

Water well

Yuan/piece

Brickup water well 2000

No compensation for

abandoned well Pumping well 600

Hand-operated pumping well 500

Page 265: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 264

Category Unit Standard Notes

Biogas digester

Yuan/piece

Cement concrete structure 2000,

brick-concrete 800

Masonry manure

pit

Yuan/piece 500

Dejecta cylinder Yuan/dan

50 Yuan if below 3 dans, 100

Yuan if above 3 dans (including 3

dans)

Greenhouse for

crop cultivation Yuan/

Bamboo frame 8 Top height above 2m

Steel frame 12

Fishpond Yuan/mu

2000 Intensive culture fish pond

(yield per mu above 250 kg)

1000 Extensive culture fish pond

(yield per mu below 250 kg)

Compensation Standard for Above-Ground Trees On the Collective Land

Acquired (Table 6)

Category Unit Compensation

standard Remarks

Tea garden

Yuan/mu

3000 Mature tea garden (tea garden over 3 years,

Including 3 years)

2000 Young tea garden (tea garden less than three

years)

Mulberry

field

Yuan/mu

3000

Mature mulberry field (mulberry field over 2

years,

Include 2 years)

2000 Young mulberry field (mulberry field less than 2

years)

Timber forest

(vast)

Yuan/mu

Immature forest 1000

Refers to general afforestation planted on land

for farm use Young forest 2000

Half-mature forest

Page 266: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 265

Category Unit Compensation

standard Remarks

and above 1500

Economic

fruit forest

(vast)

Yuan/mu

Immature forest 2000

Refers to economic fruit forest planted on land

for farm use

Vegetative season

4000

Maturation stage

6000

Bamboo

forest

Yuan/mu

Sundry bamboo 1100

Moso bamboo 2200

Green

seedlings

(vast)

Yuan/mu

2000(diameter below

5cm)

Refers to the nursery stock planted on land for

farm use, diameter is measured at 1.3 m above the

ground.

3000(diameter below

5-10cm)

4000(diameter below

10-15cm)

5000(diameter below

15-20cm)

6000(diameter above

20cm)

Note: scattered trees, compensation price of each tree should be converted with reference to

technical standard density of forestry industry for vast afforestation.

Page 267: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 266

Attachment 36: Compensation Standard for House Demolition in the

Collective Land Acquired Within the Scope of Urban Planning Area of

Xuancheng City

Compensation Standard for House Demolition On the Collective Land

Acquired (Table 1)

Unit: Yuan/㎡

Category Class House structure and standard Basic

Price

Composite

structure

1

Reinforced concrete beam, column, solid brick wall, flat roof

or tiled roof. Plane ceiling, complete doors, windows, water,

electricity, kitchen, washroom, cement ground.

950

2

Reinforced concrete beam, column, single, dual wall, flat

roof or tiled roof. Simple ceiling door/window, water,

electricity, kitchen, washroom complete, cement ground.

900

Masonry-timber

Structure

1

Load bearing brick wall, wooden roof truss, tiled roof,

cement or wooden floor, solid wall body, flat roof ceiling,

complete doors, windows, water, electricity, kitchen,

washroom, two storeys and above (including two storeys,

storey height is above 2.8 m) one-off design, synchronous

construction.

830

2

Cement or timber purlin, cement or wooden floor, single,

dual wall, flat tile roofing, smooth ceiling, with water,

electricity utilities.

760

3

Mixed bamboo and timber purlins, trinity mixture fill or

simple cement ground, single wall, flat tile roofing, with

water, electricity utilities.

680

Simple

Structure

1

Irregular roof truss, bamboo and wood base course, thatch,

tile or asbestos tiled roof, adobe, broken brick or other simple

walls. Simple ground, with electricity, cornice height above

2.2m.

320

2 Irregular roof truss, bamboo and wood base course, thatch,

tile or asbestos tiled roof, adobe, broken brick or other simple

walls. Simple ground, with electricity, cornice height below

220

Page 268: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 267

Category Class House structure and standard Basic

Price

2.2 m.

Note: with respect to loft, basement, open floor, spring layer etc that were constructed

together with the house at one time, execute 50% of this standard for the part of storey height

1.5-2.2m, execute 25% of this standard for the part of storey height below 1.5m.

Page 269: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 268

Housing Location Value (Table 2)

Unit: Yuan/㎡

Location

category

Scope

Residence

Office,

production

storage

house

Classification areas

Category

1

Zhongshanxi

Road-Jingting

Road-Daocha

River-Wanxi

River-Meixi

Road-Zhaotingzhong

Road

1800 1200

Class 1: Lingxi Road-Aofeng

Road-Wanxi River-Zhongshan

Road

1710 1140 Class 2: area of Category 1

deducting the area of Class 1

Category

2

Shuiyangjiang

Avenue-Wangan

Railway (excluding

Category 1 area

1470 980

Class 1: Wanlingxi

Road-Yourong Road-Jixian

Road-Xiegong Road-Shuangta

Road-Wangan

Railway-Tonggong

Road-Wanxinan

Road-Xiangshan

Road-Shuiyangjiangnan

Avenue-Jiutong

Road-Meiyuan Road-Jingde

Road-Meixi Road (excluding

Category 1 area)

Page 270: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 269

1390 930

Class 2: ① Meiyuan

Road-Jiutong

Road-Shuiyangjiang

Avenue-Jingde Road ②

Meiyuan Road-Baocheng

Road-Jialexiang-Shitao

Road-Qushan Road-Shuangta

Road-Xiegong Road-Jixian

Road-Yourong Road-Wanlingxi

Road-Meixi Road-Jingde Road

③ Xiegong

Road-Shuiyangjiang

Avenue-Wangan

Railway-Wanxi River-Shuangta

Road ④ Xiangshan

Road-Wanxinan

Road-Tonggong Road-Wangan

Railway-Shuiyangjiangnan

Avenue

1310 880

Class 3: the area in Category 2

deducting the areas of Class 1

and Class 2

Category

3

Xuanhang

Expressway-Fengcui

Road-Shuiyang River

(excluding the areas

of Category 1 and

Category 2)

1170 780

Class 1: ① Shuiyangjiangnan

Avenue-Xiangyang

Avenue-Xuanhang

Expressway-Qingxi

Road-Hongyue Avenue-Yuhe

Road-Xuanhang

Expressway-Xingye

Road-Hongyue Avenue-Meixi

Road-Wenchang

Road-Shuiyangjiangxi Avenue

② Wangan

Railway-Shuiyangjiangdong

Avenue-Shuiyang River

Page 271: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 270

1030 690

Class 2: ① Xuanhang

Expressway-Guiling

Road-Hongyue Avenue-Xingye

Road ② Xuanhang

Expressway-Yuhe

Road-Hongyue Avenue-Qingxi

Road ③ Xiangyang

Avenue-Shuiyangjiang

Avenue-Yushan

Road-Xuanhang Expressway

④ Jingtingshan Mountain

South Landscape Coordination

Area (according to general

planning of Jingtingshan

Mountain)

830 560

Class 3: the area of Category 3

area deducting the areas of

Class 1 and Class 2

Category

4

Within Qingyijiang

Avenue (excluding the

areas of Category 1,

Category 2 Category

3)+ Shuangqiao Group

development land

scope

630 420

Class 1: ①construction land

scope of Xuanzhou Economic

Development Zone (road

network enclosure scope)②

Fengcui Road-Xuanhang

Expressway-Xuannantong

Expressway ③ Rixin

Road-Qingyijiangxi

Avenue-Fenggong

Avenue-Wushapu

Road-Chuangxin Road ④

Houde Road-Wenjing

Road-Xingzhi Road-Shengyu

Road ⑤ Shuangqiao Group

Wanlingdong Road-Niwan

Road-Aofengdong Road-Liren

Street ⑥ Xiadu Group

construction land scope

520 350

Class 2: the area in Category 4

area deducting the areas of

Class 1 and Class 3

Page 272: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 271

410 280

Class 3: Shuiyang

River-Qingyijiangnan

Avenue-Lingyang

Road-Aofengdong Road-Niwan

Road-Wanlingdong

Road-Kuaisudong

Road-Qingyijiangbei

Avenue-Shoude

Road-Changyan

Road-Zhaotingbei

Road-Xuannantong

Expressway

Category

5

Outside Qingyijiang

Avenue, within the

scope of urban

planning area

300 200

Class 1: ①town construction

land scope of Tianhu

Neighborhood ② town

construction land scope of Jinba

Neighborhood③town

construction land scope of

Xiangyang Town ④ Wutunxi

Road-West Outer

Ring-Wutundong Road

(including town construction

land scope of Sunbu Town)⑤

town construction land scope of

Wuxing Township ⑥town

construction land scope of

Guquan Town ⑦ Qingyijiangxi

Avenue-Qingbo

Road-Changqiao Road-Qixiu

Road

120 80

Class 2: the area in Category 5

area deducting the area of Class

1

Note: non-residential housing should be identified according to the purpose

indicated on the property ownership certificate.

Compensation Standard for Ancillary Facilities of the House (Table

3)

Page 273: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 272

Item

Compensation

amount (unit

price)

Remarks

Power supply

Electricity

meter

380

Yuan/household

1.5 to 20A (included), single-phase,

separate account

2000

Yuan/household

20A to 60A, three-phase, separate

account

150

Yuan/household

Single-phase time-sharing electricity

meter

600

Yuan/household

Three-phase time-sharing electricity

meter

60

Yuan/household Submeter

Transformer

(including

affiliated

pipeline)

6000 Yuan/unit Up to 315KVA (included), relocation

subsidy

7000 Yuan/unit 315 to 630KVA (included), relocation

subsidy

8000 Yuan/unit Above 630KVA, relocation subsidy

Water supply

Main water

meter

(separate

account)

700 Yuan/piece Retail private investor, one meter per

household

Submeter 50 Yuan/piece

Page 274: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 273

Item

Compensation

amount (unit

price)

Remarks

Gas supply Pipe gas 2700

Yuan/household One meter per household

Communication

CATV 100

Yuan/household Replacement cost

Telephone,

broadband

network

8 Yuan/door Replacement cost

Air-conditioner

Split 200 Yuan/unit Replacement cost

Window type 150 Yuan/unit Replacement cost

Central

air-conditioner100 Yuan/KW

Calculate according to rated cooling

input power

Water heater

Solar energy 3 50 Yuan/piece

Subsidies for relocation and

installation Electricity 100 Yuan/piece

Gas 100 Yuan/piece

Outdoor ground

Cement 40 Yuan/㎡

Masonry 25 Yuan/㎡

Enclosing wall

Hollow 50 Yuan/㎡

Masonry 60 Yuan/㎡

Page 275: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 274

Item

Compensation

amount (unit

price)

Remarks

Simple earth,

fence 10 Yuan/㎡

Kitchen range

Single stove

stove 200 Yuan/piece

Add 50 Yuan for every increase of

one,

Productive

stove 700 Yuan/piece

Sanitary

facilities

Bathtub 500 Yuan/set

Water closet 300 Yuan/piece

Squatting pan 200 Yuan/piece

Wash basin 80 Yuan/piece

Septic tank 100 Yuan/m³

Biogas

digester 2000 Yuan/set

Abandoned pool subsidy 500

Yuan/set

Other

Exterior balcony

PVC, plastic-steel

door window

180 Yuan/㎡ Subsidy for self-enclosure

Exterior

balcony

aluminum

alloy

160 Yuan/㎡ Subsidy for self-enclosure

Page 276: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 275

Item

Compensation

amount (unit

price)

Remarks

door/window

Exterior

balcony

wooden doors

and windows

50 Yuan/㎡ Subsidy for self-enclosure

Iron gate 30 Yuan/㎡

Roller shutter

door 50 Yuan/㎡

Burglar mesh 30 Yuan/㎡

Security door 450 yuan/piece

Common

wooden door 300 Yuan/frame

Finished suit

door 700 Yuan/frame

Boiler 3 Yuan/kg Subsidies for relocation and

installation

Kitchen

ventilator 100 Yuan/piece

Subsidies for relocation and

installation

Water pool, 50 Yuan/piece

Page 277: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 276

Item

Compensation

amount (unit

price)

Remarks

coal pool

Brick water

well

2000

Yuan/piece

Pressure well 500 Yuan/piece

Fire pool, bath

pool 100 Yuan/m³

Canopy, cover

for protect

rains

20 Yuan/㎡

Insulation

layer

30 Yuan/㎡ Simple

60 Yuan/㎡

Note: for unlisted ancillary facilities, compensation should be given with reference to

similar facilities in the table, or compensation should be given according to the

replacement price in combination with the degree of newness.

Compensation Standard for House Decoration (Table 4)

Name

Compensation

amount

(unit price)

Remarks

Ground Painted ground 15 Yuan/㎡

Page 278: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 277

Name

Compensation

amount

(unit price)

Remarks

Terrazzo, artificial

stone 40 Yuan/㎡ Various floor tile grounds

Floor tile 60 Yuan/㎡

Laminate wood

flooring 40 Yuan/㎡

Wood floor

80 Yuan/㎡ General wood flooring

140 Yuan/㎡ No paint, solid wood flooring

without planing

Dimension stone

ground 100 Yuan/㎡

Marble (granite) material,

excluding artificial stone

Indoor

decoration

Calcium plastic,

ceramic simulating

wall surface

20 Yuan/㎡

Three-ply board,

ceramic tile wainscot 30 Yuan/㎡

Soft/hard enveloped

wooden wainscot 50 Yuan/㎡

Plastic sprayed wall

surface 15 Yuan/㎡

Fine and smooth surface,

without the sense of

concave-convex

Latex paint wall

surface 15 Yuan/㎡

Wallpaper 25 Yuan/㎡

Unmovable fixed wall

cabinet 300 Yuan/㎡

Page 279: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 278

Name

Compensation

amount

(unit price)

Remarks

Fiber, calcium plastic,

plasterboard 30 Yuan/㎡ Hard ceiling

Wood suspended

ceiling 50 Yuan/㎡ Hard ceiling

Subsidy Standard for Transplanting of Trees (Table 5)

Category

Diameter

(measured at 1.3 m

from the ground)

Compensation

amount (unit price)Remarks

General

Trees

2cm-5cm 10 Yuan/tree 1. This standard is only applicable to

trees in house sites;

2. Landscape trees should be

compensated with reference to the

standard for fruit tree;

3. No compensation for the flowers

and grass, nursery stock, trees planted

after the announcement was released.

5cm-10cm 30 Yuan/tree

Above 10cm 50 Yuan/tree

Fruit

tree

2cm-5cm 50 Yuan/tree

5cm-10cm 100 Yuan/tree

Above 10cm 200 Yuan/tree

Moving Cost Standard

I. Cash compensation

1. Residential housing: standard is 8 Yuan/㎡, no lower than 500 Yuan, moving cost

is given at one time.

2. Non-residential housing: moving cost is given at one time according to 10 Yuan/㎡

for the certified building area of the house; if there is any large-scale equipment,

calculate according to the freight transport price at that time.

II. Property swap

Page 280: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 279

1. Subsidy should be released according to the above-mentioned provisions for

resettlement in existing housing;

2. Moving cost will be paid twice for resettlement in forward delivery housing

according to the above-mentioned provisions.

Standard for Temporary Resettlement Cost of Residential Housing

(Table 6)

Unit: Yuan/㎡ · month

Location Category 1

area

Category 2

area

Category 3

area

Category 4

area

Category 5

area

Subsidy

standard 10 9 8 7 6

1. For cash compensation, subsidy will be released for 6 months according to the

above-mentioned provisions.

2. For property swap:

(1) with respect to resettlement in existing housing, subsidy will be released for 4

months according to the above-mentioned provisions.

(2) with respect to resettlement in forward delivery housing, if the APs arrange

transition by themselves, and are resettled in 18 months, subsidy will be released for

the duration from the month moving out to the time of resettlement according to the

above-mentioned standards; if the APs are not resettled in more than 18 months, the

acquisition party should pay transition subsidy according to twice of the standard

from the overdue month untill the time of resettlement.

Transition subsidy should still be paid for 4 months according to the standard since

resettlement is realized.

(3) Transition subsidy will not be paid if house acquisition department provides

Page 281: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 280

transitional housing; If resettlement is not realized after 18 months, transition subsidy

should be paid according to the standard from the overdue month until 4 months after

the resettlement is realized.

Subsidy Standard for Shutdown Loss of Non-Residential Housing

(Table 7)

Unit: Yuan/㎡•month

Location standard Category 1

Area

Category 2

Area

Category 3

Area

Category 4

Area

Category 5

Area

Business house 35 30 25 20 15

Office house 12 11 10 9 8

Production house 16 15 14 13 12

Storage house 9 8 7 6 5

Note: shutdown loss of non-residential housing should be calculated

according to the certified area, and should be paid for 6 months according

to the above-mentioned standards.

Page 282: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 281

Additional Area Comparison Table for Transregional Resettlement (Table 8)

Unit: ㎡

Incentive Standard for House Demolition

If the APs sign compensation and resettlement agreement for the house

demolition, and hand over the housing at the house demolition incentive stage,

maximum incentive should not exceed 100 Yuan/㎡ based on the incentive area

calculated according to these provisions.

Location

category

standard

Category 1

area

Category 2

area

Category 3

area

Category 4

area

Category 5

area

Category 1 area 0 +10% +20% +30% +50%

Category 2 area -- 0 +5% +10% +20%

Category 3 area -- -- 0 +5% +10%

Category 4 area -- -- -- 0 +5%

Category 5 area -- -- -- -- 0

Page 283: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 282

Attachment 37: Official Reply to the Construction

Land for S367 Project

Page 284: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 283

Page 285: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 284

Appendix 38: Ma An Shan Public Participation and Minutes

for S367 project

Date September 9, 2012

Place

Land and Resources Bureau of Shanhou Town, He County

Organizer He county Transportation Bureau

Participants

He County Transportation Bureau, Shanhou Town Land Bureau, Hehai

University

Topic Resettlement impact and compensation as well as resettlement policies of

Shanhou Town

Main content

(1) Implementing《the Notice of the People’s Government of Anhui Province

Adjusting on the Compensation Standards for Land Acquisition》(Wan Zheng

[2012] 67).

(2) The resettlement is decided by the affected villages through the villagers'

meeting.

Date September 9, 2012

Place Xianzhang Town, Hanshan County

Organizer

Hanshan County Transportation Bureau

Participants

Hanshan County Transportation Bureau, Hehai University, design unit,

Xianzhang Town, affected villages

Page 286: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 285

Topic

Affected scope of the project, attitudes of affected villagers, house

demolition and resettlement plan

Main content

1) The project affects Jianghuai Village of Xianzou Town, and the affected

villagers supported the project; 2) House demolition and resettlement is

collectively planned by the village , and houses built by the affected

households

Date September 17, 2012

Place Land and Resources Bureau of Hanshan County

Organizer

Hanshan County Transportation Bureau

Participants

Hanshan County Transportation Bureau, Hohai University, Hanshan County

Land and Resources Bureau

Topic

Resettlement impact and compensation and resettlement policies of Hanshan

County

Main content

(1) Implementing《the Notice of the People’s Government of Anhui Province

Adjusting on the Compensation Standards for Land Acquisition》(Wan Zheng

[2012] 67).

(2) The resettlement is decided by the affected villages through the villagers'

meeting.

Page 287: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 286

Date September 19, 2012

Place

Jianghuai Village, Xianzu Town, Hanshan County

Organizer Hanshan County Transportation Bureau

Participants

Hanshan County Transportation Bureau, Hehai University, Xianzhang Town

of Hanshan County, and representatives of affected villagers

Topic Consultation on land acquisition and restoration plan

Main content

1) The compensation for land acquisition directly compensated to the affected

households without any land adjustment;

2) Some affected households hope to use the opportunities to do some small

businesses related to tourism, such as catering, car wash services,

farmhouses, etc.

Page 288: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 287

Date September 17, 2012

Place He county Land and Resources Bureau

Organizer He county Transportation Bureau

Participants

He county Transportation Bureau, Hehai University, He county Land and

Resources Bureau

Topic Resettlement impact of He County and compensation and resettlement

policies

Main content

(1) Implementing《the Notice of the People’s Government of Anhui Province

Adjusting on the Compensation Standards for Land Acquisition》(Wan Zheng

[2012] 67).

(2) The resettlement is decided by the affected villages through the villagers'

meeting.

Date September 19, 2012

Place zhongshan Village, Shiyang Town, He County

Organizer

He county Transportation Bureau

Participants

He County Transportation Bureau, Hehai University, Shiyang Town of He

County, and representatives of villagers

Topic Negotiation of Demolition and resettlement and income restoration

Main content

1) The compensation for land acquisition are directly compensated to the

affected households without any land adjustment.

2) Some affected households hope to use the opportunities to do some small

businesses related to tourism, such as catering and car wash services.

Page 289: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 288

3) subsidies can be provide to the villagers through the restoration of

temporary land occupation.

4) House demolition will be planned by the village collectively and the

affected households will build their own houses

Date

December 8, 2014

Place Taodian Village, Shanhou Town, He County

Organizer He county Transportation Bureau

Participants

He county Transportation Bureau, Hehai University, Taodian staff,

representatives of affected villagers

Topic Negotiation of Demolition and resettlement and income restoration

Main content

1) The compensation for land acquisition are directly compensated to the

affected households without any land adjustment.

2) Some affected households hope to use the opportunities to do some small

businesses related to tourism, such as catering and car wash services.

3) subsidies can be provide to the villagers through the restoration of

temporary land occupation.

4) House demolition will be planned by the village collectively and the

affected households will build their own houses

Page 290: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 289

Page 291: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 290

Appendix 39: Compensation Standard on Wuwei

County of S319 approved by Wuhu City Government

Page 292: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 291

Page 293: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 292

Page 294: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 293

Page 295: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 294

Page 296: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 295

Page 297: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 296

Page 298: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 297

Appendix 40: House Demolition Agreement of S319

Page 299: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 298

Page 300: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 299

Appendix 41: The establishment of Nanling Organization

Page 301: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 300

Appendix 42: Permanent Agreement of Land Acquisition of S319 Project

Page 302: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 301

Page 303: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 302

Appendix 43: Compensation of Demolition House and Resettlement Agreement of S367

Page 304: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 303

Page 305: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 304

Appendix 44:Acquisition Agreement of Land S367

Page 306: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 305

Appendix 45: Compensation of Demolition House and Resettlement Agreement of Yimu Road

Page 307: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 306

Page 308: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 307

Appendix 46: Land Acquisition Agreement of Yimu Highway

Page 309: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 308

Appendix 47: Group Purchase Agreement of Huishang Century

City

Page 310: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 309

Page 311: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 310

Appendix 47: Notification of winning the bid for the Resettlement House of

Xiaohekouqiao Pottery Factory

Page 312: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11

Anhui Communications Vocational&Technical College - 311

Appendix:48: Demolition agreement of Non-residential house and operation house compensation for reconstruction

Kedian to Mujiating section of Yimu Highway in Nanling County

Page 313: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 312

Page 314: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 313

Page 315: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 314

Appendix 49: Record Form of Resettlement House for Xiaohekouqiao Pottery

Factory

Page 316: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring

Report (11th Report)

Anhui Communications Vocational&Technical College - 315

Appendix 50: Shuiyangjiang Waterway Dredging and Dam Project

Approved by Xuancheng People's Government

Page 317: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 316

Appendix 51: Evaluation Report on New State-owned Land Acquisition for the Reconstruction Project from Kedian to

Mujiating Section of Yimu Highway in Nanling County

Page 318: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 317

Page 319: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 318

Page 320: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 319

Page 321: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 320

Appendix 52: Resettlement Transition Fee for Demolition of Xuanzhou

Port Wharf

Page 322: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 321

Page 323: Social Monitoring Report Project Number: 45021-002 August ... · Social Monitoring Report Project Number: 45021-002 August 2020 PRC: Anhui Intermodal Sustainable Transport Project

ADB-financed Anhui Intermodal Sustainable Transport Development Project External Monitoring Report (11th Report)

Anhui Communications Vocational&Technical College - 322

Appendix 53: The transition fee for Vouchers resettlement of Xiaohekou

Bridge