Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a...

50
Social Monitoring Report Semestral Report October 2010 PRC: Hunan Roads Development III Project Prepared by Hunan University for Hunan Provincial Transportation Department and the Asian Development Bank.

Transcript of Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a...

Page 1: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

Social Monitoring Report

Semestral Report October 2010

PRC: Hunan Roads Development III Project

Prepared by Hunan University for Hunan Provincial Transportation Department and the Asian Development Bank.

Page 2: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

1

The Sixth Investigation Report on the External

Supervision of Jicha Highway’s Expropriation and

Relocation Work in Hunan Province

Hunan, China

October-2010

Page 4: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

2

The Organization and Staff of the Project Panel

Research Organization: Hunan University

Chief in Charge of the Project: Xian-zhong Long (Professor, PhD

Supervisor)

Members of the Project: Ze-liang Liu, Xiao-chun Chen, Jin-long

Li, Jian-qiang Guo, Hai-shu-Qiao, Xiang-bo Tian, Ying-chun Li, Li-

dan Zhou, Jian-hui Tang, Heping Zhong, Jing Wang, Bing Hu, Xiao

Huang, Min LI, Zhu-xia Gan, Ya Liu, Jing Zhou, Zhi Li, Shasha Liu

Page 5: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

1

I. 1 FOREWORD

A. 1.1 General situation of the project

The highway of Jishou-Chadong (also named Jicha Highway) project was

started in 2007. In this period, because of threat lot Weishaku, the project

changed the line section. And the land acquisition and resettlement work of

the 7.632 km’s altered line in C15, C16 Contract Section have been

completed in December 2009. The key engineering projects, the suspension

bridge in Ai village, also made a breakthrough. And it has been under

construction now. The construction will be completed by the end 2011 and will

be open to traffic.

Picture 1.1 A bridge fly north to south, Barriers change to flat

——Key to complete on schedule:the suspension bridge in Ai village

B. 1.2 The contents and the methods of monitoring

1. 1.2.1 Contents of monitoring

According to laws of national and provincial government, the main

contents of external monitoring including:

(1) Record the processes of immigration and allocation in Jicha highway

project;

(2) investigate the change of income and expend of families which are

influenced by this project;

(3) Investigation of affected people's income and livelihood restoration;

(4) Satisfactory degree comments on the external supervision setting and

the complaint process of relocation;

(5) Survey resettlement implementation of C15, C16 contract section to

change the line;

(6) The main funds flow while for expropriation and immigration work;

Page 6: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

2

(7) Survey on the participation of local people and public record

information.

During Jul. 29th-30th and Oct. 1st-5th, project team carried out the sixth

research on land acquisition and resettlement work of the highway. According

to the actual progress of external monitoring research plan and the demands

and memorandum of Asian Development Bank’s project inspection team in

April 2010, the emphasis of this time monitor are recovery of household

income of residents in affected acquisition and resettlement area, reroute part

of the progress of land acquisition and resettlement and the settlement of

remaining issues

2. 1.2.2 Methods of monitoring

(1) Investigation method

The main methods might be classified as follows:

①Inquiry Method. The project panel obtained exhaustive information from

the Highway Administration of Hunan Province, the Construction Coordination

Headquarters of Jishou County and that of Huahuan County, and other

relevant local organizations.

②Questionnaire. The investigation group took the form of filling in the

questionnaire. It classified to household level investigation and village level

investigation. Interviewees are classified to residents and director of village

committee respectively. The questionnaire’s content had basically reflected

the emphasis point of this investigation.

③The interview records. The investigation group interviewed with those

illiterates Face-to-face about the questionnaires and related affairs.

(2). Survey tools

① Digital Cameras. During the investigation, our members took photos of

the old houses of some relocated residents and their new home, as well as

photo of affected people’s living conditions.

Page 7: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

3

② Recording Pen. Considering the local residents are mainly ethnic

minorities, who received less education and could only dictate, members

record their dialogues for writing research reports.

C. 1.3 Fourth monitoring report on the Review and Feedback

Project team members were monitor for the fourth time about the

expropriation and relocation of Jicha highway on March 2009. In the report

analyzed the affected people on compensation for expropriation and

relocation payment and the rights of satisfaction survey, and also analyzed

the recovery of their income. During the enquiry, there are some problems

lead to project construction:first, public service damage caused by

excavating blast still exist; second, didn’t respect local people’s demand when

construction of highway facilities.

Feedback on problem solving:according to questions and suggestions

of report of external oversight bodies, project units to adopt the following

measures:(1)Timely communicate and consult with relevant staff,to

resolve the conflict with the local people.(2) In order to avoid the

recurrence of adverse effects,construction of the project side will account of

these circumstances during the next full,Response plans well in

advance.(3)Further improve the communication mechanism,Published a

complaints hotline, set up suggestion boxes.

D. 1.4 Brief Introduction of Monitoring Organizations

PPAC (Politics and Public Administration College) of Hunan University, as

the external supervisory organization, which has carried on four times of

monitoring to the Expropriation and Relocation Work of Jicha Freeway

Project, and has submitted the report. According to the schedule, the project

panel carried on the fourth fieldwork investigation in March 2009. During

March 10 to March 15 In 2010, we carried out a field survey on the land

acquisition relocation and resettlement program of 7 km changing line of C15,

C16 contract section.

During project implementation, we conduct periodic monitoring and

objective assessment on the implementation of land acquisition and

Page 8: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

4

resettlement program. We collect data and information through the site

investigation such as the implementation of the resettlement activities, and do

objective analysis of relevant data and information, then make further

implementation of the resettlement objective assessment to detect the

presence or potential problems, and put forward opinions and suggestions to

solve the problem. At last, this report will feedback to the Asian Development

Bank, the project implementing agency owners and immigration to promote

the work of the project in affected areas to improve and perfect action.

The External Monitoring Unit: Hunan University

The Principal Leader: Xian-zhong Long

Telephone Number: 0086-731-88823400 Fax Number: 0086-731-

88823400

Postal Code: 410082

E-mail: [email protected]

Page 9: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

5

II. 2 DESCRIPTIVE ANALYSES OF THE RESULTS

The sixth survey of the external monitoring took the farmer households

affected by the Jicha Highway project under its construction to investigate.

195 people in 32 affected villages were investigated (Including five villages in

Zhaiyang Town of Jishou City; four villages in Aizhai Town; five villages in

Panbi Town in Huayuan County; five in Mali Town; four in Erdao Town; one in

Longtan Town; three in Tuanjie Town; and five in Biancheng Town). The

panel from Hunan University used the form of face-to –face interview, so the

effective response rate was 100%, and quality of the returned questionnaires

was high. Meanwhile, the investigation team strictly controlled on the quality

of village and household questionnaire responses. In order to ensure the

authenticity of the survey results and seriousness, in addition to handwritten

signature and thumbprint, we also require stamp of the village committee or

town committee of the official seal.

Picture 2.1 The third team are investigating in a farmer’s home in Malichang Town

A. 2.1 The basic information on the respondents’ family

The investigation unit was researching the respondents’ basic situation,

including the sex ratio, nationality and the affected type. In the 195

respondents, there are 103 male, accounting for 52.8% of the total number;

and there are 92 female, by 47.2%; and Miao People are 85, by 43.6%; Tujia

are 67, by 34.4%; Han People are 43, by 22%. The affected type: only land

acquisition are 114 household, accounting for 58.5% of the total; and only

house demolition are 54, by 27.7%; and both land acquisition and house

demolition are 27, by 13.8%. If the relocated household is defined as severely

affected ones, then there are 75 seriously affected households, accounting for

38.5% of the total. As shown in the Table 2-1:

Page 10: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

6

T2-1 The summary of the basic information of the respondents

FREQUENCY

NUMBER PERCENTAGE%

EFFECTIVE

PERCENTAGE%

CUMULATIVE

PERCENTAGE%

Sex MALE 103 52.8 52.8 52.8

FEMALE 92 47.2 47.2 100

TOTAL 195 100

NATIONALITY MIAO 85 43.6 43.6 43.6

TUJIA 67 34.4 34.4 78.0

HAN 43 22.0 22.0 100

TOTAL 195 100

THE

AFFECTED

TYPE

LAND

ACQUISITION

ONLY

114 58.5 58.5 58.5

HOUSE

DEMOLITION

ONLY

54 27.7 27.7 86.2

BOTH

ACUISIION

AND

DEMOLITION

27 13.8 13.8 100

TOTAL 195 100

B. 2.2 The analysis of the survey of the compensation review and

confirmation situation

In the 195 respondents, farmer households affected by the land

acquisition who acquire the compensation less than 10,000 yuan accounts for

25.2%; who gain 10,000 to 50,000 accounts for 49.7%; 50,000 to 100,000

account for 17.9%, while who acquire more than 100,000 yuan only account

for 7.2%. As shown in the Table 2-2:

T2-2 Share of the compensation at all levels

FREQUENC

Y NUMBER

PERCENTAGE

%

EFFECTIVE

PERCENTAGE

%

CUMULATIVE

PERCENTAGE

%

Page 11: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

7

Less

than1000

0

10000 to

50000

50000 to

100000

100000

more than

Total

49

97

35

14

25.2

49.7

17.9

7.2

100.0

25.2

49.7

17.9

7.2

100.0

25.2

74.9

92.8

100.0

C. 2.3 The analysis of the land acquisition survey

Fatherly, the investigation team verified the various types of the land

expropriated of the farmers. As shown in the Table 2-3:

表 2-3 土地征用情况的交叉分析表

The situation of land use and compensation payment

Pct of Pct of

Category label

WATER FIELD

DRY LAND

ORCHARD

VEGETABLE LAND

FOREST

WOOD LAND

HOMESTEAD LAND

OTHERS

Code

1

2

3

4

5

6

7

8

Count

84

51

21

29

42

44

26

19

Responses

26.6

16.1

6.7

9.2

13.3

13.9

8.2

6.0

Cases

43.1

26.2

10.8

14.9

21.5

22.6

14.4

9.7

Total responses 316 100.0 163.2

0 missing cases; 195 valid cases

As shown in the above, in the 195 respondents, various types of the land

expropriated were chosen 316 times in total, including WATER FIELD were

87T; DRY LAND were 51T; WOOD LAND were 42T; ROADS WERE 26T;

OTHERS were 19T; and VEGETABLE LAND were 29T and FRUIT GARDEN

were 21. What’s more in the Table, the Pct of Cases calculation of all

Page 12: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

8

respondents choose the appropriate types of land were the proportion of the

total, for example, 84 people selected the WATER FIELD, they accounted for

43.1% of the number, the corresponding choice DRY LAND, 51 people,

26.2% of the total number. This shows that the farmers have been

expropriated for road construction is mainly WATER FIELD and DRY LAND.

It’s especially important for this part of the land compensation.

D. 2.4 The survey of the satisfaction to the compensation payment

We adopted the measure of monetary compensation for the main

compensation. This time we selected 195 households from affected areas,

and investigated cash compensation, timeliness of compensation payments,

compensation paid staff attitude.

(1) The aspect of cash compensation

In the aspect of cash compensation, there are 195 farmers selected the

fully in cash, accounting for100%.

(2) The aspect of timely compensation payment

In the aspect of timely compensation payment, there are 98 farmers

considered very timely, accounting for 50.3%; 65 people think more timely, for

33.3%; 29 think general in timely, for 14.9%; and only 3 think not timely, for

1.5%.

T2-4 the table of timely compensation payment

Very

satified More

satified Genaral

Not very satified

Very dissatified

Total

The number of

people(p

98 65 29 3 0 195

Percentage

(%) 50.3 33.3 14.9 1.5 0 100

(3) The aspect of the attitude of the staff working in compensation

In the aspect of the attitude of the staff working in compensation, there

are 104 people among the 195 respondents expressed the best to the staff,

accounting for 53.3%; and 56 expressed better, for 28.7%; and 30 chose the

general, for 15.4%; obviously, accounted for 97.4%, only 2.6% people

Page 13: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

9

considered the staff’s attitude were not good or worse. And we can conclude

that the farmer’s affected by the project were satisfied with the work of the

staff.

T2-5 the survey of the attitude of the staff

Best Better Good Not good Bad total

The number

of people(p

104 56 30 3 2 195

Percentage

(%) 53.3 28.7 15.4 1.5 1.1 100

E. 2.5 The survey analysis of the evaluation of the complaints procedure

In this process of land acquisition and resettlement, at all levels have

oversight telephone, and arranged for individual responsibility. Evaluation of

the complaints procedure in this survey can be seen from Table 2-6 are195,

that is, 91.3% of households that monitoring phone number and 18.7% of

households still do not understand.

T2-6 whether know the monitoring phone number

FREQUENCY

NUMBER

PERCENTAGE

%

EFFECTIVE

PERCENTAGE

%

CUMULATIVE

PERCENTAGE

%

YES

NO

TOTAL

178

17

195

91.3

8.7

100.0

91.3

8.7

91.3

100.0

In the survey of satisfaction to the complaint resolution, over 65% of the

families never had complaints, while more than 30% were quite satisfied on the

handling of complaints. We can see that the takeover of the project to do is

put in place; farmers can pay full attention to complaints, give top priority to

the interests of farmers.

In the survey of whether post the situation of implementation, such as

relocation area, grade and compensation standards, resettlement and

compensation funds, and other contents, 5 families did not answer this

question, and the remaining 190 valid respondents, a total of 165 people that

Page 14: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

10

these elements now post the implementation of all the valid accounts for

84.6% of respondents, only 25 were not sure.

T2-7 the table of post the situation of implementation

FREQUENCY

NUMBER

PERCENTAGE

%

EFFECTIVE

PERCENTAGE

%

CUMULATIVE

PERCENTAGE

%

YES

NO

TOTAL

Missing system

TOTAL

165

25

190

5

195

84.6

12.8

97.4

2.6

100.0

86.8

13.2

100.0

86.8

100.0

According to the survey, relevant departments actively promote the

resettlement policy, compensation standard and complaint channel through

the newspapers, radio, television, and bulletin board before the resettlement

plans implementation. According to a survey of 195 households showed that

most farmers can understand the resettlement policy.

F. 2.6 The analysis of survey of the affected population on the permission

responses

Upon the request, the survey was investigated in skills training, children

of compulsory education, job placement and the elderly insurance, and other

aspects of permissions for the affected farmers, and the respondents satisfied

with received permission. The results of this survey shown: most people are

very satisfied to obtain the permission, only a few of the villagers considered

that they have not fully enjoy the proper permissions government providing for

them. As follows:

(1) The aspect of skills training

In the aspect of the rights to "skills training", there are 112 people very

satisfied making up 57.4% of the total number; 80 people expressed more

satisfaction and general satisfaction for 41.0%; that is not satisfied with only

1.6%, and no one was very dissatisfied.

Page 15: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

11

T2-8 the investigation of satisfaction to the authority of skills training

Very

satisfied More

satisfied General

Not very satisfied

Very dissatisfied

Total

The number of people(p)

112 62 18 3 0 195

Percentage(%) 57.4 31.8 9.2 1.6 0 100

(2)The aspect of children of compulsory education

In the aspect of children of compulsory education, there are 175 people

expressed very satisfied and more satisfied to this right, accounting for 89.8%;

16 people says no or not sure, accounting for8.2%; 4 people expressed not

satisfied or very dissatisfied, for 2.0%.

T2-9 the investigation of satisfaction to the authority of children of compulsory education

Very

satisfied More

satisfied Not

sure Not very satisfied

Very dissatisfied

Total

The number of people(p)

128 47 16 3 1 195

Percentage(%) 65.7 24.1 8.2 1.5 0.5 100

(3)The aspect of job placement

In the affected areas, due to the project giving the priority employment of

local labor, thus increase more jobs for the local residents. In the households

surveyed, there are 126 people expressed very satisfied to the job placement,

accounting for the 64.6%; 35 expressed more satisfied, accounting for 17.9%; 6

people expressed general satisfied or not quite understand, accounting for

3.1%; and 28 said not very satisfied or very dissatisfied, accounting for 14.4%.

T2-10 the investigation of satisfaction to the authority of job placement

Very

satisfied More

satisfied General

Not very satisfied

Very dissatisfied

Total

The number of people(p)

126 35 28 4 2 195

Percentage(%) 64.6 17.9 14.4 2.1 1.0 100

Picture 2.1 Employ local labor force for revetment construction in Lot 16

Page 16: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

12

(4)The aspect of rights of the elderly Insurance

In the aspect of rights of the elderly Insurance, 121 respondents

expressed very satisfied, accounting for the 62.1%; 44 expressed more

satisfied, accounting for 22.6%; 27 people expressed general satisfied,

accounting for 13.8%; and 2 said not very satisfied, accounting for 1.0%.

T2-11 the investigation of satisfaction to the authority of the elderly Insurance

Very

satisfied

More

satisfied General

Not very

satisfied

Very

dissatisfied Total

The number of

people(p) 121 44 27 2 1 195

Percentage(%) 62.1 22.6 13.8 1.0 0.5 100

G. 2.7 The comprehensive evaluation of efficiency, effectiveness, impact

and sustainability of the resettlement

After this survey that, the process of land acquisition and resettlement in

the project, various interests of affected farmers have been protected. Most

affected farmers are satisfied with the rights, transparency of compensation

and resettlement grant money. Payment of compensation and resettlement

costs of the efficiency of the working group has also been highly affected

residents. The relocation compensation panel upheld the release of “people

first” principle, and reflect the overall harmony demolition guidelines to

improve the government’s image and credibility. This fully protect the

fundamental interests of the affected people, effectively avoided negative

phenomena blocked by demolition work, ensured the smooth progress of the

Page 17: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

13

project, and provide a stable environment conducive to carried out in normal

conditions.

Page 18: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

14

III. 3. THE PROGRESS OF EXPROPRIATION AND RELOCATION

A. 3.1 The Working Schedule of Expropriation and Relocation

So far, Land acquisition and resettlement work are going smoothly. With

the cooperation of the local government and the support of the affected

residents, land acquisition and resettlement has been completed according to

plan. In addition to C15 and C16 standard to avoid the three slag area for

potential hazards, there were sections of 7.632km changed which led to delay

part of land acquisition and resettlement work, other work are implemented as

planned. The land acquisition and resettlement progress in the following table

Table 3-1 timetable of the progress of expropriation and relocation

item Finished time in

schedule actual Finished

time

A. expropriation General Engineering Changed line (C15,

C16)

1. distribute immigration manual 2005.5 2005.5

2.promulgate the compensation standard

2005.5~2005.6 2005.6

3. define the affected object 2005.7 2005.7

4.prepare and carry on the work of measuring

2005.8~2005.9 2006.12

5. publicize the measuring result and announce to the related people

2005.10~2005.11 2007.1

6. consult and confirm the compensation

2006.11~2006.12 2007.2

7. pay the compensation 2007.1~2007.2 2007.3

8. handle expropriation and land-use procedures

2007.2~2007.3 2007.4

B. resume production

1. make a detail resume plan, and consult with relative people

2006.12~2007.1 2007.3

2. reclaim the land 2007.3~2007.9 2007.12

C. house relocation

1. confirm the affected range 2005.4 2005.4

2. distribute immigration manual 2005.5 2005.5

3. promulgate the compensation standard

2007.1~2007.2 2007.2

4. carry on the investigation about relocation

2006.12~2007.1 2007.2

5. publicize the investigated result and announce to the related people

2007.1~2007.2 2007.3

6. consult with them and sign the 2007.2~2007.3 2007.5

Page 19: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

15

item Finished time in

schedule actual Finished

time agreement

7. choose the house site 2007.3~2007.4 2007.6

8. handle the house using procedures

2007.5~2007.6 2007.8

9.pay the compensation 2007.5~2007.6 2007.6

10. level the house site 2007.7~2007.8 2007.10

11. build the house 2007.8~2007.12 2008.3

12. move in the new house Before 2008.1 2008.4

13. dismantle the old house Before 2007.3 2007.6

D. resume special facility Before 2006.7 2007.1

From the above statistics show, with the exception of work by the economic

environment and the special circumstances of the individual household (two could

not find housing sites), the whole process of land acquisition and resettlement work

go well, including consultation and determine the compensation amount, payment of

land compensation, selection homestead, clearance for homestead land and other

more complicated procedures work, showing that the owner and the local

government did a good job in this regard.

B. 3.2 The practical implementation of land acquisition and resettlement

policy

The Implementation of resettlement policy of Jicha Freeway

specially paid attention to minority interests and regional economic

development. Wset Hunan is China's minority areas, freeway projects

across the residential areas of ethnic minorities, production and living

conditions of ethnic minorities is relatively backward, resettlement work

attached great importance to interests of minority groups, the

development of all social and economic benefits in project planning are

adapted to the ethnic minority beneficiaries, and in accordance with

national law and policy of the Asian Development Bank received higher

compensation. In which, directly affected by the project is a total of 25.1

million local residents, accounted for 45% of the total population. There

are 17.1 million people of ethnic minority beneficiaries, 68% of the total

number of beneficiaries (see Table 3-2).

Page 20: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

16

Table 3-2 Areas directly affected by the project beneficiaries of the situation

classification

beneficiary

total(*1000)

minority nationality

number of people(

*1000) percentage(%)

rural area 94 76 81

city 157 95 61

total 251 171 68

C. 3.3 Evaluation of resettlement implementation of the plan

1. 3.3.1 Actual implementation of the compensation comparison

with the compensation scheme

Land acquisition and resettlement compensation rates is in

accordance with the Tujia and Miao Autonomous Prefecture in western

Hunan resettlement compensation policies issued by the rural housing

construction and the latest implementation of the standards of

compensation rates, land acquisition and resettlement of the land

compensation standard is 16 times as AAOV, by macro-economic and

policy factors, housing demolition and resettlement compensation

program is much higher relatively to the initial standard.

Table 3-3 Compensation for permanent land acquisition before and after comparison

of the standard

land

types unit

Initial place

ment plan

The actual com

pensation change

paddy

field yuan/mu 18032 24400 35.31%↑

dry land yuan/mu 14504 16800 15.83%↑

forest yuan/mu 6698 7200 7.49%↑

Compared to the resettlement plan in paddy field,Actual compensation rose 3

5.31%;dry land resettlement program than the actual compensation rose 15.83%;c

ompared to the resettlement plan of forest,actual compensation rose 7.49%;The co

mpensation standard deviated from the plan at between 7.49% -35.31%.

Table 3-4 Housing and structural comparison of the compensation standard

Page 21: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

17

category unit

Initial pla

cement pl

an

The actual

compensat

ion

change

brlck-concrete-structured Yuan /square meter

280 480—520 71.42%—85.71%↑

brick and-stud Yuan /square meter

220 400—430 81.82%—95.45%↑

shingle Yuan /square meter

160 300—320 87.5%—100%↑

simple structure Yuan /square meter

90 120—180 33.33%—100%↑

Compared to the resettlement plan including brick,Intervals of the actual comp

ensation rose 71.42% -85.71%;Brick wooden compared to resettlement plan, the act

ual compensation rose at 81.82% -95.45% range;Compared to the resettlement plans

shingle, the actual compensation rose 87.5% -100% range in;Simple structure comp

ared with resettlement plan, compensation rose 33.33% -100% range;The compensa

tion standard deviated from the plan at 33.33% -100%, respectively.

2. 3.2.2 Compared the implementation plan of rehabilitation

measures with practical recovery measures

Actual implementation of the restoration measures the progress of

restoration measures and plans remained the same. Project parties made a

very big effort, basically according to plan to make the resettlement of

immigrants recovery. Practical implementation of restoration measures are as

follows:

(1)Basically, timely resumption of temporary land, reclamation work

has been in progress. Construction side exit, it can recover as much as

possible that has been restored, and some land can not be restored, which

are basically the compensated in accordance with relevant policies.

( 2) For shooting houses and the local residents affected by the normal

production and life, Government and the owner have given it a high priority. Invited

Hunan University, Sichuan People's Armed Police Force of the relevant professional

bodies to assess the damage, after friendly consultations with the affected residents,

the extent of damage has been formed the compensation program.

Page 22: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

18

(3) Recovery work the pump has also been solved in time. Construction of a temporary

detour during construction have been retained, because it provide convenience for local residents’

production and living, and preserved.

3. 3.2.3 The overall implementation of the resettlement program

evaluation

Through the above comparative analysis of land acquisition and

resettlement work, Can be seen in the owner and the active cooperation of

local governments, the project resettlement plan is a better implementation, to

achieve the desired objectives. Specifically, land acquisition and resettlement

are not foreseen, although the progress of the factors, but in general are more

successful; actual extent of land acquisition and resettlement is less than

expected, compensation for land acquisition and resettlement policy fully

considered the interests of affected groups, in particular give special attention

to affected minorities’ interests of the area. Practical measures and the

original resettlement plant has been implemented the greatest degree ,

practice the concept of people-oriented, the affected groups are holding a

higher satisfaction.

Page 23: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

19

IV. 4. MONITORING AND EVALUATION ON RESETTLEMENT COSTS

A. 4.1 The proportion of cost distribution of resettlement work

The basic cost of land acquisition and relocation compensation include:

Permanent land acquisition, crop compensation, temporary land use fees,

housing compensation, compensation for trees and other ground attachments,

infrastructure compensation, training, monitoring costs(Including internal and

external monitoring)and so on.

Table 4-1 The proportion of the basic details of land acquisition and resettlement cost of the

project

Basic land

acquisition and

relocation projects

The actual

amount of

compensation

Percentage of

total costs

permanent land expropriation

93,623,777 34.14%

Young crops compensation

6,534,546 2.64%

Temporary land

charges 6,797,127 0.25%

Housing

Compensation 9,796,831 0.35%

Trees and other

ground attachments

compensation

19,414,822 7.07%

Infrastructure

Compensation 38,829,644 14.14%

training expense 1,400,000 0.51%

Monitoring fees

(including internal and

external monitoring)

1,000,000 0.36%

Survey and resettlement plans

400,000 0.14%

Land reclamation fees (to government)

23,214,186 8.45%

Page 24: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

20

Farmland use tax (to government)

9,561,303 3.48%

Forest vegetation

recovery payments (to

government)

14878216 5.42%

total 225,450,452 82.10%

In the basic project cost of land acquisition and resettlement, land

acquisition permanent cost as much as 34.14%, infrastructure compensation

of up to 14.14%,Lower reclamation, land occupation, vegetation restoration

costs as high as 17.35% of three. In the whole cost of land acquisition and

resettlement, the basic resettlement cost accounted for 82.10% of total costs.

B. 4.2 Costs of land acquisition and resettlement

Table 4-2 Comparison of land acquisition and relocation costs (million )

project The total cost of

the initial plan

Actual total

cost change

Land acquisition

and resettlement 258.36 316.35 22%↑

Advisory services /

training 50.85 52 2%↑

total 309.21 368.35 19.19%↑

According to the table:According to the table of,Advisory services,

training costs raised 2% more than the actual costs,The cost of the land

acquisition costs rose compared with 19.19% of the actual.

Table4-3 Costs of land acquisition and resettlement Details(does not contain C15,C16)

project unit compensatio

n price (yuan)

The number of affected

Compensation (Yuan)

The actual amount of

compensation

I. Basic fee 221,765,077 225,450,452

(A) Permanent

land acquisition

91,292,665

93,623,777

paddy field mu 25620 1448.7 37,115,694 38,143,765

dry land mu 17850 983.57 17,556,724 17,843,345

vegetable mu 26026 9.33 365,736 412,112

Page 25: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

21

project unit compensatio

n price (yuan)

The number of affected

Compensation (Yuan)

The actual amount of

compensation

field

Orchard

(trees

excluded)

mu 14640 347.9 5,093,256

5,123,853

woodland mu 9150 3142.7 28,755,705 29,587,456

Other land mu 11850 203.0 2,405,550 2,513,246

(B) crops compensation

6,471,607 6,534,546

(C) Temporary

land use fee 1 6,496,010

6,797,127

paddy field mu 5152 117.92 607,524 712,854

dry land mu 4144 851.48 3,528,533 3,712,543

vegetable field

mu 3091 134.23 414,905 415,965

林地 mu 2061 943.74 1,945,048 1,955,765

(D) Housing Compensatio

n 8,806,624

9,796,831

half-timbered Square meters

330 14641.2 4,831,596 5,121,652

Civil structure Square meters

310 8366.8 2,593,708 2634,567

Simple structure

Square meters

160 4459.5 713,520 785,890

Relocation subsidies

family 400 159 63,600 641,222

TOG 6 months

family 1800 159 286,200

287,400

66,81 water, electricity and

sanitation subsidies

family 2000 159 318,000

326,100

(E) trees and other ground attachments

compensation

19,414,822

19,414,822

(F) Compensatio

n infrastructure

38,829,644 38,829,644

1 Including restoration costs.

Page 26: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

22

project unit compensatio

n price (yuan)

The number of affected

Compensation (Yuan)

The actual amount of

compensation

(G) Training fee

1400000 1,400,000

For management

staff 200,000 200,000

For affected staff

1,200,000 1,200,000

(H) monitoring

fees

(including

internal and

external

monitoring)

1000000 1,000,000

Internal monitoring fee

250,000 250,000

External monitoring

costs 750,000 750,000

(I) investigation

and preparation costs of the resettlement

plan

400,000 400,000

(J) land reclamation

fees (to government)

23214186 23,214,186

paddy field Mu 10304 1448.7 14927404 14,927,404

dry land Mu 8288 983.57 8151828 8,151,828

vegetable field

Mu 14014 9.63 134954 134,954

(K) of forest vegetation recovery

payments (to government)

Mu 4000 2390.33 9,561,303 9,561,303

(L) cultivated land

occupation tax (to

government)

Mu 5333 2789.84 14878216 14878216

II. Vulnerable groups which

1,962,211 1,962,211

Page 27: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

23

project unit compensatio

n price (yuan)

The number of affected

Compensation (Yuan)

The actual amount of

compensation

need help at-risk personnel costs (1% of basic cost)

III. Management Fee (4% of basic cost)

7,848,842

7,941,825

Ⅳ.

Contingencies 39,244,212

39,244,212

(A) material unforeseen

costs (15% of basic cost)

29,433,159

29,433,159

(B) material unforeseen costs (5% of basic cost)

9,811,053

9,811,053

total 270,820,342 274,598,700

From the above data analysis, land acquisition costs rose, mainly due to:(1)

resettlement areas have complex geological conditions, climate impact(Wet stop

work),all kinds of water, electricity, roads, temporary pavement covers an large

area, made it difficult to restore project, , resulting in construction costs.(2)

industry specificity, stone, steel prices raised ,so as labor costs, resulting in overall

cost higher.( 3)The land acquisition and resettlement, the construction plans

unreasonable, and not enough detailed cost control, leading to land acquisition and

relocation costs are also slightly higher.

C. 4.3 Evaluation of resettlement compensation

Throughout the resettlement process, the resettlement compensation

costs have been a top priority,According to the actual situation have made

two major changes,due to factors such as policy changes and price

increases,The entire cost of resettlement compensation rate increased up to

nearly 20% compared to the original plan. Implementation of compensation

rates are as follows:

Page 28: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

24

Table 4-4 Compensation for land acquisition and resettlement rate of change

land types unit The actual compen

sation compensation Changes rates

paddy field Yuan / mu 24400 35.31%↑

dry land Yuan / mu 16800 15.83%↑

forest Yuan / mu 7200 7.49%↑

brick-

concrete-st

ructure

Yuan/square

meter 480—520 71.42%—85.71%↑

Brick

wooden Yuan/square

meter 400—430 81.82%—95.45%↑

shingle Yuan/square meter

300—320 87.5%—100%↑

simple stru

cture

Yuan/square meter

120—180 33.33%—100%↑

Various types of permanent land acquisition compensation standards

rose range is between 7.49% -35.31%,various types of housing and the

structure of compensation rises 33.33% -100% in between. They have carried

out various types of compensation detailed classification,Timely pay to

farmers, compensation costs rose with current policy and economic

environment changes, better safeguard the interests of the affected farmers.

Transparent, fair and timely payment of compensation can reduce the

resistance of farmer’s laborers; on the other hand speed up the progress of

land acquisition to protect the entire land acquisition and resettlement work

smoothly.

Page 29: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

25

Page 30: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

26

V. 5. THE CHANGES OF LIVING CONDITION AND THE RECOVERY OF

LIVING STANDARD IN AFFECTED HOUSEHOLD

A. 5.1The changes of living condition in affected household

1. 5.1.1 Incomes per capita

In the 225 surveyed families, In addition to increasing caused by

compensation for land requisition and removal, in recent years, also due to

migrant workers, the increase in start-up businesses, the income of affected

people increased fast. The proportion of low-income families declining and

middle-income and high income families is on the rise. The rate of the family

whose income is lower than 900 yuan every year accounting for the

investigated household has dropped from 10.26% to zero. Household income

of 6000-8000 yuan / year accounted for 48.72% of the total rose to 52.31%.

And the rate of the family whose income is more than 8000 every year has

increased from 9.78% to 28.44%. Generally speaking, all of their average

income has improved.

Table 11 Incomes per capita

Incomes per capita (Yuan per

year)

Before Expropriation

rate(%) 2010 rate(%)

<900 20 10.26 0 0

900-3000 38 19.48 22 11.28

3000-6000 25 12.82 43 22.05

6000-8000 95 48.72 102 52.31

>8000 17 8.72 28 14.36

Total 195 100 195 100

(Notes: The data in the table represent the income that is besides the

compensation of expropriation)

2. 5.1.2 Resource of income

Through the investigation, because of the financial crisis, labor demand of

coastal areas reduced. Many farmers reflected that the number of migrant

workers who return home has increase. Wage income is not a big proportion

Page 31: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

27

of the total income. Many of them started their own businesses depending on

their skills learned from outside and the government’s help, which made their

income increased. Therefore, local residents forestry, sideline production and

the income of business has a significant increase,despite the changes in

wage income. In addition, with the increasing importance for people's

livelihood, the government has increased the financial transfer payments to

the western region, the income has increased.

Table 5-2 resource of the income(unit: Yuan)

Item

Incomes per capita

Before Expropriatio

n 2010

increase(+)/reduce(-)

rate(%)

Wages(include work outside )

4,580 5385 805 17.58%

Agriculture and forestry 4,140 5586 1446 34.93%

Sideline production 1,233 2417 1184 96.03%

Business 4,867 6450 1583 32.53%

Transformed income 1,456 2354 898 61.68%

Total 16276 22892 6616 40.65%

3. 5.1.3 Life expenditure

With the rise of price and the improvement of living standard, the

expenditure in affected family has raised to some extent correspondingly. The

number of household’s income which less than 900 yuan / year down from the

27 to 4, reducing 11.80%,the number of households which the expenditures

were higher than 6000 yuan / year before land acquisition increased from

28.72% to 13.85%,Medium Expenditure (3000-6000 dollars) the number of

households increased by 6.68%.

Table 5-3 life expenditure per year

Incomes per capita (Yuan per year)

Before Expropriation

rate(%) 2008 rate(%)

<900 27 13.85 4 2.05

900-3000 56 28.72 37 18.97

3000-6000 85 43.58 98 50.26

>6000 27 13.85 56 28.72

Total 195 100 195 100

Page 32: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

28

4. 5.1.4 The change of the structure of expenditure per capita

With the growth of people's income, the affected families have

corresponding changes in the structure of expenditure. (Table 5-4)

Table 5-4 the structure of expenditure per capita

expenditure per capita(Yuan/year)

Before Expropriatio

n 2010

increase(+)/reduce(-)

rate(%)

Food 1,159 1645 486 +41.93%

Clothes 156 425 269 +172.44%

House 234 432 198 +84.62%

Facility 187 457 270 +144.39%

Communication 185 426 241 +130.27%

Education 165 124 41 -24.85%

Medical care 156 135 21 -13.46%

Other expend 246 524 278 +113.01%

Total 2,488 4168 1680 +67.52%

It can be found out from the table that of the investigated household in

food, clothes, house is has increased. The government has increase the input

in education, medical treatment and health care, which make peasants spend

less money in those aspects in some extent.

B. 5.2 Production and living recovery of affected people

1. 5.2.1 The means of production

Through interviews with 195 respondents we learned that, before land

requisition and removal, 3.59% of households owned a threshing

machine, 12.31% of the farmers have tractors, 14.36% of households have

farm vehicle. As of the end of October 2010, in the respondent

household, with 12.31% households owned a threshing machine, 24.10 of

the farmers have tractors, 28.72% of households have farm vehicle,

others have varying degrees of improvement (see Table 5-5)

Table 5-5 the means of production

Page 33: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

29

Item

number of owned family All Quantity Rate of ownership

Before Expropriatio

n

March 2010

Before Expropriatio

n March 2010

Before Expropriatio

n

March 2010

Farm vehicle

28 56 30 64 14.36% 28.72%

Tractor 24 47 24 56 12.31% 24.10%

Reaper 7 24 8 27 3.59% 12.31%

Thresher 165 142 174 147 84.62% 72.82%

Water pump

52 88 86 120 26.67% 45.13%

Electromotor

42 85 58 102 21.54% 43.59%

Other items 31 63 42 85 15.90% 32.31%

It can be seen from the table that the number of owned thresher family

dropped to some extent, because some of them lost land or bought the

harvester after expropriation, they sold out it. In addition, with the

improvement of peasants’ living standard, and the workforce who worked

outside going back to the township, some peasants got rich on their own land,

and purchased some agricultural tools, it have improved the possession rate

of the means of production greatly. For instance, the family possession rate of

tractor has increased by 11.79% and the rate of agricultural vehicle has

increased to 14.36% than before.

2. 5.2.2 Family durable goods

Through 195 respondents we learned: before the expropriation, 78.97%

family have colorcast, and 61.03% have VCD, 26.67% have refrigerator, but

the rate of ownership of air condition and computer is low (less than 8%); In

October 2010, 94.87% families have colorcast, 86.15% have VCD, 94.36%

have mobile phone, and the number of the family that have air condition has

increased from 3.59% to 19.49%, and the computer owners rate increased

from 3.08% to 21.03%.

Page 34: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

30

Table 5-6 Family durable goods

Item

number of owned family

All Quantity Rate of family ownership

Before Expropri

ation

October 2010

Before Expropriat

ion

October 2010

Before Expropriati

on

October 2010

Car 7 25 9 37 3.59% 12.82%

Motorcycle 45 102 53 129 23.08% 52.31%

Bicycle 57 87 68 114 29.23% 44.62%

Color-cast 154 185 168 219 78.97% 94.87%

black and white TV

142 85 157 84 72.82% 43.59%

Mobile phone 91 184 128 190 46.67% 94.36%

Telephone 84 189 90 189 43.08% 96.92%

VCD 119 168 135 175 61.03% 86.15%

Recorder 19 45 46 65 9.74% 23.08%

Camera 32 64 39 78 16.41% 32.82%

Washer 74 142 82 152 37.95% 72.82%

Refrigerator 52 75 54 76 26.67% 38.46%

Air condition 7 38 9 40 3.59% 19.49%

Computer 6 41 8 46 3.08% 21.03%

Other Items 8 32 15 39 4.10% 16.41%

As can be seen from the table, home ownership and possession of

durable goods have been rapidly growing,The main reason is that the

income of the residents affected have been restored and grew. In addition, the

state introduced the policies and a series of measures such as "home

appliances to the countryside", "car to the countryside",Greatly increased

the purchasing power of project-affected residents. In addition, transportation

become convenient, many residents can buy a motorcycle.

Page 35: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

31

图 5.1 villager Zhang Lijun’s new house and the three-wheeled motorcycle

3. 5.2.3 Recovery of the scale and production of the fruit wood

After an investigation, land acquisition and resettlement activities made

the impact on the project area of fruit cultivation and production have to some

extent. Citrus, kiwi, pears and other fruits of this have declined. under the

skills training and technology guidance of the company of Jicha and local

government , fruit production has been restored and improved. As the

investigation time was when the fruit harvest season,Investigators talked

with the farmers and learned,Affected by climatic conditions this year, citrus

and other fruits obtained a good harvest, production has been further

restored.

Table 5-7 changes of scale and production of the orchard

Fruit Scale (hectare) Product (ton)

Before allocation

2010 reduce(%) Before

allocation 2010 reduce(%)

mandarin orange

18,810 17,750 5.64 194,596 187,600 3.59

kiwi fruit 1,780 1,710 3.93 6,178 5,890 4.66

pear 2,310 1,980 14.29 2,129 1,850 13.10

C. 5.3 Housing relocation and reconstruction

On the basis of the resettlement plan, 27379.9 square meters of houses

will be demolished, increased by 5.1% than the resettlement plan (the data in

Resettlement Plan was 26,056.9 square meters). Affected be demolition was

129 households, 18.5% less than the resettlement plan (the data in

Resettlement Plan was 159 households).

In the survey of 195 affected households, there are 68 households in the

demolition of housing. The investigation group on housing compensation,

whether paid in a timely manner, whether the implementation of preferential

policies for vulnerable groups, issues such as these farmers were about. The

results show that essentially all of the households on housing removal and

Page 36: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

32

resettlement of job were satisfied, only a very few of the farmers were not

satisfied due to personal demands not met. Details of the following table:

T5-8 the survey of satisfaction of housing reconstruction

Satisfaction

Object

Very satisfied More satisfied General

satisfied dissatisfied

Number Percentag

e

Numbe

r

Percentag

e Number

Percentag

e Number

Percenta

ge

Household

affected 24 35.29% 41 60.29% 2 2.95℅ 1 1.47%

D. 5.4 Contrast the old and new houses of affected farmers

The investigation showed that the affected farmers timely get

compensation and relocation funds for land acquisition,Most people have

built new houses, and most of the building are much larger than the original

house, with an area of about 30O square meters, living conditions are greatly

improved. Only a small number of affected households feel difficult to find

homestead to build houses, Therefore, the project side and the local

government need to strengthen cooperation to help these families find

homestead as soon as possible. In the first half of year 2010 Asian

Development Bank also concerned the situation on memo, And require

oversight bodies to track external monitoring, the investigators conducted a

special confirmation, Believe that this problem has received well attention in

the post-treatment. Overall, housing reconstruction has been carried out

fruitful, The following groups of pictures showed the contrast of houses before

and after the removal:

Picture 5.2 Relocatees Long Yuanlong’house before and after the removal

(Aizha-Paixiong Village)

Page 37: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

33

Picture 5.3 Relocatees Long Jinchang’house before and after the removal

(Aizha-Paixiong Village)

Picture 5.4 Relocatees Long Changbi’house before and after the removal

(Zhaiyang-Shuer Village)

Picture 5.5 Relocatees Shi Guangji’house before and after the removal

(Zhaiyang-Shuer Village)

Page 38: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

34

VI. 6. THE CONDITION OF THE RECOVERY OF THE AFFECTED PERSON’S

LIFE

A. 6.1 Infrastructure recovery

The project make some effect on road, drinking water facility and

telephone facility in some bid sections are damaged in certain degree, and

some bid sections take interim measures, such as changing its course,

looking for new source of water and setting telephone wire, etc., it have

basically solved problems of local villagers. According to the investigation,

The villagers think highly of construction, the rate of utilization open to the

traffic and electricity of the influencing area has already been up to 100%,

running water and telephone have already been basically popularized(Table

6-1). Especially with project completed, the resume of water and road system

work in succession bringing into schedule with temporary sidewalk

transformation, the infrastructure resumes work and has notable effect.

Table 6-1 road, the recovery of the water supply and electricity facility

Affected area

Rate of use (%)

Drinking water Road Telephone Electricity

Before Expropriatio

n

2010.10

Before Expropriati

on 2010.10

Before Expropriatio

n 2010.10

Before Expropriatio

n 2010.10

Jishou 73.4 94.5 95.8 100 93.7 99.8 100 100

Huayuan 76.4 92.4 98.2 100 93.4 98.5 100 100

Visited villages

72.9 90.5 95.4 100 100 97.9 100 100

B. 6.2 Remaining issues and the solutions

Investigation and settlement of the remaining problem are one of the

important contents of this investigation. Though the immigration allocation

plan has already made the detailed regulation on relevant policies and

measure, but because of the existence of some contingency and unavoidable

Page 39: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

35

factor, there will still be some leftover problems in the construction course of

project:

First, resume of temporary area reclaim, water and road system have

problems. Though it taken the effective measure in most bid sections, a few

questions exist, sidewalk without repair in time after construction, temporary

area recover or compensate not according request, it is not only influenced

the image of construction , and initiate the contradiction.

Second, it is hard to stop in dispute that shaking bad local public facility

and resident's house when blow up construct. Because some bid section pass

through resident area, unavoidable noise pollution and damage that blow up

construct, Assessment damaged and compensation difference often become

origins that project side and influenced resident's dispute produce, local

people will adopt and hinder too drastic behaviors or resolve by force often

when it is difficult to clear up in the dispute.

Third, some unable to get rid of the poverty completely, that only live on

compensate fund and haven’t other peasant household of source of revenue.

Some peasant household will cause poor reason ascribe to expressway take

over the land for use, pull down or compensate style to be too little, and

employment authority is incomplete, therefore it is discontented to produce,

stimulate the contradiction, and then hinder the construction speed.

The detail determines the whole. So, in order to avoid the emergence of

this kind of problem, the project side must do well and prevent actively, fully

consider these situations in the course of design and operation, solve

influenced peasant households' poor problem through various routes, resume

public infrastructure, ensure resident's normal life order, meanwhile, should

also strengthen communication and exchange with the peasant, fully listen to

the peasant ' opinion.

Page 40: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

36

Fig. 6.1 recovery situation in the 16th bid section of project

C. 6.3 summaries

Through this investigate, the project produce loud influence to economic

income and life state of resident. In accordance with national laws and

regulations related to land and resettlement policy of ADB, the income

restoration and recovery public facility is the goal of land acquisition and

resettlement. Relevant department in line with " human-oriented " principle,

pay close attention to people's livelihood actively, pay energetically support at

policy, take a series of measures to instruct local masses how to develop

production actively, resume production, make income level of resident get

improvement of a certain degree, electricity, water, road and some other

public infrastructure receive recovery to a great extent and improve.

Page 41: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

37

VII. 7. IMMIGRATION AND ALLOCATION SITUATION ON C15, C16

CONTRACT SECTION RELOCATED

Because circuit of C15, C16 that design originally need across 4 tailing

dams (Fig. 7.1) that form by mine exploited, in order to get rid of the potential

safety hazard, after proving in detail, the related departments determine to

change its course to this section of circuits. C15 and C16 after changing its

course are about 7.632 kilometers. Relocating the road will take over 38.381

hectares of land for use, about 56% are the farmland, include 8.813 hectares

of paddy fields, dry land is 12.832 hectares.

Fig.7.1 tailing dams result in relocated

A. 7.1 Description analysis of the investigation result

The immigration and allocation of relocated implementation fully. Among

195 peasant households of this investigation, 45 are relocated the peasant

households that influenced by C15, C16 contract section. According to

investigating, because it is influenced by factors such as policy changing,

price rise, and compensation standard improve to some extent than the past,

mainly adopt the way of currency compensation. The investigation result

reveals, most people feel very satisfied to releasing pace, transparency of

compensate fund, satisfaction is up to 89.5%. At the same time, most

influenced peasant household corresponding enjoyed express that very

satisfied with authorities (skills training, child's compulsory education,

employment, the elderly's insurance authority), accounts for 80.5%.

B. 7.2 immigration allocation expenses are assessed

The expenses of expropriation and compensation mainly included land,

allowance for arrangement, food crops, temporary area, demolition of house,

etc.. According to investigation, most people feel very satisfied to releasing

pace, transparency of compensate fund, satisfaction is up to 87.4%.

Compensate expenses classify very careful, release in time, and meet

Page 42: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

38

peasant household's demands this time, it received by influenced peasant

household.

C. 7.3 Influenced crowd's incomes and livelihoods resume

Relocated influence 1 county (city), 2 town, 7 villages, take over 38.38

hectares of land for use for ever, according to the actual production of every

influenced village and living standard, and the economics and society

development plan which the local government pass, the project unit has set

up the following immigration and allocation goal:。Immigrants' level of

production is resumed after immigration allocation; the per capita income

resumes the standard before immigration; Public infrastructure, natural

environment and traffic condition influenced, etc. should be improved to some

extent after immigrant. The project take the flexible measure on compensation

and allocated method to influenced people, include cash compensation or

adjust land, a lot of schemes that the recovery of collective economy or

individual economy resumes, etc., make great efforts to make income and

livelihood of the influenced crowd in the project district resumed.

1. 7.3.1 Influenced economic income situations of crowd

Through investigate, because influenced peasant household got

compensation, and make the family income improved greatly. Compared with

the same period last year, influenced residents' per capita income rise to

12890 Yuan from 9344 Yuan. And it finds, influenced residents' source of

revenue and structural proportion to have changes obviously, because the

project has hired some local surplus labors, and offered some work positions

to local in construction, so salary income and incomes (including shifting

income other, concede the land to forestry replenish and run enterprise)

proportion relatively raise obviously, and the proportion of agricultural income

from sideline occupations obviously drops (as shown in Table 7-2).

Table 7.2 source of revenue of form and structure

Item Incomes per capita

Increase satuation

Rate(%)

Page 43: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

39

Before Expropriatio

n 2010.10

changed(±)

Rate(%)

Before Expropriatio

n

2010.10

salary income(including working outside)

2558 3670 1112 43.5 27.37 28.4

Agriculture and forestry

2193 2425 232 10.6 23.47 18.8

Sideline production 1150 1585 435 37.8 12.31 12.3

Business 1436 2058 622 43.3 15.37 15.9

Transformed income 2007 3180 1173 58.4 21.48 24.6

Total 9344 12918 3574 38.2 100 100

(Note:date is not including compensation)

2. 7.3.2 Expenditure situation of life

Table 7.3 Pay the structural situation per capital (unit: Yuan)

expenditure per capita(Yuan/year

After Expropriatio

n

Before Expropriatio

n

increase(+)/reduce(-

rate(%)

Food 1680 2078 398 23.69

Clothes 600 873 273 45.50

House 584 865 281 48.12

Facility 520 680 160 30.77

Communication 600 947 347 57.83

Education 354 436 82 23.16

Medical care 300 358 58 19.33

Other expend 842 980 138 16.39

Total 5480 7209 1729 31.55

Influenced by factors such as income level and price-level, etc., the

corresponding change took place in the life expenditure and structure in the

same period influenced the crowd, it can find out on table, investigated

peasant households increase to some extent in expenditure such as food,

clothes, inhabiting, traffic through the above form. Meanwhile, because the

government strengthened the input in education, medical treatment and

health care, the expenditure growth of education culture and medical

treatment and health care that make reduces to some extent.

3. 7.3.3 Infrastructure recovery

Table 7.4 the recovery of the road, water supply and electricity facility

Affected

area

Rate of use (%)

Drinking water Road Telephone Electricity

Page 44: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

40

Before

Expropriati

on

2010.1

0

Before

Expropriati

on

2010.1

0

Before

Expropriati

on

2010.1

0

Before

Expropriati

on

2010.1

0

Tuanjie

Town 70.5 91.2 92.7 100 90.7 98.5 100 100

Bianche

ng Town 72.4 90.4 94.5 100 93.4 96.3 100 100

According the investigated at Tuanjie and Biancheng town of Huayuan,

and under help and support of relevant departments, a lot of local public

infrastructure have been all resumed, especially the recovery results of road

and electricity are obvious, make the life state of local masses obviously

improved. The picture below is recovery and operating position of the

sidewalk.

Fig. 7.2 Sidewalk recovery will be completed soon

4. 7.3.4 The satisfaction investigation that measure on income and

livelihood resume

According to investigation result on 45 peasant household of district, all

people certainly understand to income and livelihood resume, and most

peasant households hold a satisfactory attitude (account for 95.6%) to the

situation of implementing of the policy, only specific peasant household

unsatisfied (account for 4.4%),because their demand interests is not been

satisfied before.

Table 7.5 situation of measure on income and livelihood resume

Satisfied investigated

Very satisfied satisfied normal unsatisfied

people

Rate peopl

e Rate

people

Rate peopl

e Rate

All investigated (45

households) 21

46.7%

15 33.3% 7 15.6%

2 4.4%

fragile colony(11

households) 6

54.5%

4 36.4% 1 9.1% 0 0%

Page 45: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

41

D. 7.4 Relocation and reconstruction of the building

1. 7.4.1 Method and measure of Relocation and reconstruction of

the building

Relocated project have 68 family (279 people) influence house, distribute

among 7 administrative villages originally. With Expropriation, 14354.84 square

meters of house will be removed. In order to lighten the influence to the

maximum extent, the project side has taken the following measures:

(1)House of peasant remove and rebuild by oneself, old building

materials of house use according to his will.

(2)While rebuilding the house, fully consider development need in local

folkways and customs, actual demand and future need. Building construction

will go on according to the opinion of the relocated household.

(3)Make the reasonable compensation standard according to the

replacement price and quantity of removal area, relevant department make

the plan that the compensation will be paid according to progress of building

construction by stages.

(4)Adopt and place the principle nearby. According to the actual

conditions of each village, the relocated household will be placed in the

original village.

(5)Relevant departments offer help for the relocated household in

sanctioning and choosing the residence base, meanwhile, the project team

increases input, guarantee the recovery of infrastructure such as water

supply, power supply and hygiene.

2. 7.4.2 Measure offered for fragile colony and implementing the

situation

According to immigrant's plan, as to the removal of the fragile colony, this

project will offer extra financial help and material to support. Especially for

fragile colony, such as solitary old man, disabled person, Households headed

by women, executive body will offered the essence while rebuilding and

moving in the house in village. According to the investigation, special measure

Page 46: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

42

which the relocation household of fragile colony made in the project team

already has been implemented.

Table 7.6 Special measure to the relocation fragile colony

Kind of the fragile colony Qualification standard right to the house lost(the

measure suggested)

Implement

situation

5 protect door Confirmed by the

village official side

New house offered by

village Done

Lonely obvious Offer the workforce of

building new room Done

Households headed by

women (have children or

not)

Bereft of one's spouse,

divorce or live apart

Offer the workforce of

building new room Done

Disabled person Confirmed by

government

Offer the workforce of

building new room Done

Old over 70 years old Offer the workforce of

building new room Done

Poor family

The annual income per

capita is lower than 865

yuan,comfirm by

poverty alleviation

Offer the workforce of

building new room Done

Close to the poverty but

influence seriously

Under the help of

poverty alleviation, fix

with measuring in detail

The minimum limit standard

house Done

Live in the simple house Only have one simple

room

The minimum limit standard

house Done

3. 7.4.3 Influenced people's satisfaction to the rebuilt house

Among the 45 household investigated, 32 needs to allocate the house, 7

of these 32 peasant households are fragile colonies. Through investigate,

majority square to project and measure of government satisfied with

influenced people(Table 7.7), and the project and the support measure which

the government promised has all already been put into effect.

Table 7.7 Satisfaction situation on house rebuild

Satisfaction

Target

Very

satisfied

satisfied normal unsatisfied

peopl Rate peopl Rate peopl Rate peopl Rat

Page 47: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

43

e e e e e

Investigated

(32

household)

including:

fragile

colony(7perso

n)

17

4

53.1

57.1

14

2

43.7

28.6

1

1

3.1℅

14.3

0

0

0℅

0℅

Fig.7.2 outlook of new house of household influenced by relocated (Dengwen Si and

Shengqian Zhang)

Note:Left belong to Dengwen Si,Right belong to Shentqian Zhang, both of

them in Biancheng town, Huayuan county

7.5 Summary

The time started of relocate circuit is relatively late, expropriation and

allocation arrange work summarizing and using before for reference. So C15,

C16 of Jicha expressway relocate place policy and measure have greater

flexibility, can adapt to the complicated and changeable removal state. The

project team carries out according to relevant regulations and policy strictly,

pay close attention to the people's livelihood, the policy carries out the result

prominently. The determination of the compensation standard is

comparatively rational in the course of immigration allocation, and

compensate and pay very in time, the transparency is very high too, the

person influenced has got enough compensation and aid in the course of

soliciting moving, having resumed incomes, produced and lived to a certain

extent, the life state of the especially fragile colony is obviously improved, it is

obvious project team in relocate, take over the land for use, pull down and

place course maintain legitimate rights and interests to take over the land for

use peasants this time.

Page 48: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

44

Page 49: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

45

VIII. 8. SUGGESTIONS FOR THE PROBLEMS EXISTED IN LAND

EXPROPRIATION, RESIDENT REMOVAL AND RESETTLEMENT

A. 8.1 Problems Existed in Land Expropriation, Resident Removal and

Resettlement

Through investigation, the work of expropriation and relocation draw to an end

entirely, people's living standard has got certain improvement. There still some

problem need be solving too.

1. The treatment of some leftover problems will be further strengthened. First,

some houses fracture influence by blow out, and cause certain damage, the noise is

too big, too frequent, residents are discontented, demand to compensate. Second,

influenced by the climate and geological condition and the phenomenon of caving in

constructing, bring the inconvenience to the masses safely. Third, relocated in route,

allocated more people, two residents can’t find the residence base, some masses'

psychology is unwilling to accept to move. Fourth, compensation standard same as 3

year ago, expropriation is difficult, the mass work difficulty is done.。

2. Influenced regional resident's employment to assist efforts to await and

strengthen. Consider factors such as the property safety and labor cost, project does

not hire the local workforce in principle in some bid sections, all workers bring by

oneself; Having signed the labor service contract in because other parts of bid

sections, the group has long-term cooperation with constructing partly, have taken the

team of skilled worker that uses for a long time, has not hired the local workforce by

oneself, so the local surplus labor's employment problem can't get maximum

settlement.。

B. 8.2 Suggestions

To the preceding question, set up improving from the following

respects:

1. Optimize the construction environment, link in many ways, reduce and hinder

workers, construction phenomenon by force. To the noise phenomenon, fully

consider resident's life, control the time of blowing out strictly, as to the thing that the

Page 50: Social Monitoring Report - Asian Development Bank€¦ · This social monitoring report is a document of the borrower. ... In preparing any country program or strategy, financing

46

house shatters etc., unified and coordinated and asking professional personnel to

decrease definitely the assessment, give appropriate compensation, and try to receive

local masses' understanding. Choose by base as to residence, until masses finish,

consult, respect immigrant will, realize paid and voluntary expropriation of land under

pull down. The contradiction appearing in constructing at the same time, obtain the

support of the government to the maximum extent, solve within shortest time.。

2. Do well and survey and study, find out workforce's basic situation, try hard to

solve local peasants' employment problem. Does a good job of immigration allocation

regional surplus labor situation know the real situation, investigate situation analysis

to go on surplus labor, do a good job of thought of the operation team, try hard to

create more employment opportunities for the local.