SNF/HLW Repository Acceptance
Presented by Steve Gomberg
Office of Systems Analysis and Strategy DevelopmentOffice of Civilian Radioactive Waste Management
April 13, 2005
Office of Civilian Radioactive Waste Management
DOE SNF and HLW Inventory
RW planning to accept 7,000 MTHM as part of the allocation for Yucca Mountain– 2333 MTHM is DOE SNF
• Naval reactors• INL/ICP• Savannah River Site• Hanford
– 4667 MTHM is DOE HLW• Savannah River Site• Hanford• ICP• West Valley Demonstration Project (conditional)
Office of Civilian Radioactive Waste Management
Draft License Application Inventory
Repository design and operations, and preclosure and postclosure analyses support receipt and emplacement– DOE SNF and HLW to be received in several configurations
• Standard canisters• Naval SFCs• Commercial-origin SNF• Canistered HLW glass• Vitrified plutonium glass waste form
– Analyses are based on 34 different SNF groups– Borosilicate HLW glass with increased waste loadings– Co-emplacement strategies within drifts– Co-disposal within waste packages
Office of Civilian Radioactive Waste Management
Acceptance Planning
Memorandum of Agreement between EM and RW sets responsibilities and conditions for acceptance, transportation, and disposal of DOE SNF and HLW– Current version is Revision 1– Draft Revision 2 is currently awaiting signature by EM– A similar agreement addresses acceptance of naval SNF by RW
Most significant changes to MOA include– MOA revised to cover only EM SNF and HLW– Complete rewrite of quality assurance responsibilities– Documents RW responsibility to acquire all transportation casks– Clarifies overall acceptance process
Office of Civilian Radioactive Waste Management
Key Documents between Offices
Waste Acceptance System Requirements Document– Revision 4 is current version– Draft revision 5 has been on hold for several years– Plan to reevaluate WASRD requirements after MOA is signed
Integrated Acceptance Schedule– LA design is loosely based on IAS Revision 0– A revision consistent with accelerated cleanup is planned
Integrated Interface Control Document– Revision 2 of IICD is under preparation– RW has received input and comments from EM and NNPP
Quality Assurance Requirements Document– An EM-specific QA program document, the Waste Custodian Quality
Assurance Requirements (WCQARs), is under development