SMITH PLAYGROUND: PHASE 2Improvements to
November 6, 2019Boston Parks and Recreation
![Page 2: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/2.jpg)
AGENDA
PROJECT TEAM INTRODUCTION1
EXISTING CONDITIONS/RECENT IMPROVEMENTS2
PRESENTATION3
LISTENING & DISCUSSION4
CLOSING REMARKS & NEXT STEPS5
1
![Page 3: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/3.jpg)
PROJECT TEAMCathy Baker-EclipseProject [email protected] or 617-961-3058
Stantec Planning & Landscape ArchitectureKevin Beuttell, Project Manager
Conor NewmanOffice of Neighborhood [email protected]
![Page 4: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/4.jpg)
PROJECT SCHEDULE & FUNDING
NOV. 2019Community Meeting 1
JAN. 2020Community Meeting 2
FEB. 2020Community Meeting 3
WINTER & SPRING 2020Design Development + Construction Documents
SUMMER 2020Bidding
FALL 2020 – FALL 2021ConstructionEstimated cost of Construction:$4,500,000
FALL 2021Anticipated Park Opening
![Page 5: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/5.jpg)
PARKDESIGN
Safety Guidelines+Regulatory Guidelines
City of BostonPriorities
Parks + RecreationGoals
CommunityInput
PARKDESIGN
![Page 6: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/6.jpg)
CITY OF BOSTON PRIORITIES
• Expanding walkable access to parks
• Addressing equity
• Climate resilience
• Health
• Housing and community building
![Page 7: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/7.jpg)
PARK & RECREATION GOALS
• Preserve And Protect Existing Trees
• Expand Usable Park Area
• Improve Universal Access
• Enhance Park Visibility
• Improve Access to Parks
• Design Flexible, Multi-functional Park Spaces
![Page 8: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/8.jpg)
COMMUNITY MEETING PROCESS
• Meeting #1Project Introduction + Overview
• Meeting #2 (Winter 2019)Design Alternatives
• Meeting #3 (Winter 2020)Preview Final Proposed Design
![Page 9: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/9.jpg)
CAMBRIDGE
• William E. Smith Playground
• Established in 1890’s• 14-acre park• Currently includes
athletic courts, hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways.
Project Overview: Locus
SMITH FIELD
WATERTOWN
ALLSTON
BRIGHTON
BROOKLINE
![Page 10: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/10.jpg)
Project Overview
PARK c.2017
HockeyBasketball
Playground
Little League
Multi-purpose Fields
Softball
![Page 11: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/11.jpg)
Project Overview
MASTER PLAN
![Page 12: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/12.jpg)
Project Overview
MASTER PLAN
![Page 13: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/13.jpg)
Master Plan
LOOKING EAST
![Page 14: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/14.jpg)
Master Plan
LOOKING SOUTHWEST
![Page 15: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/15.jpg)
Project Overview
PHASE 1 OPENING
![Page 16: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/16.jpg)
Project Overview
PHASE 1
![Page 17: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/17.jpg)
• Weak organic subsoils• Drainage challenges
Project Overview
PHASE 1 TAKEAWAYS
![Page 18: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/18.jpg)
Project Overview
PHASE 2
![Page 19: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/19.jpg)
Design
BALL FIELDS
![Page 20: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/20.jpg)
Design
BALL FIELD AMENITIES
![Page 21: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/21.jpg)
Design
BALL FIELD AMENITIES
![Page 22: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/22.jpg)
Design
DOG PARK
![Page 23: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/23.jpg)
Design
DOG PARK
Small Dogs3,640 sf
Large Dogs13,600 sf
![Page 24: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/24.jpg)
Design
DOG PARK
![Page 25: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/25.jpg)
Design
PLAYELEMENTS
![Page 26: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/26.jpg)
Project Overview
MASTER PLAN
![Page 27: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/27.jpg)
Park that is FUN and filled with energy, excitement, discovery and contemplation
Master Plan
PLAY & INCLUSIVEDESIGN
![Page 28: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/28.jpg)
![Page 29: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/29.jpg)
Design
PLAY ELEMENTS
![Page 30: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/30.jpg)
![Page 31: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/31.jpg)
Design
PLAY ELEMENTS
![Page 32: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/32.jpg)
Design
PLAY ELEMENTS
![Page 33: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/33.jpg)
LISTENING & DISCUSSION
Help us build great parks. Let us know what matters to you.
![Page 34: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/34.jpg)
Project Overview
PHASE 2
![Page 35: SMITH PLAYGROUND: PHASE 2 · 06/11/2019 · hockey/bike polo rink, athletic fields, pump track, tot lot, amphitheater, sculpture and pathways. Project Overview: Locus. SMITH FIELD.](https://reader033.fdocuments.us/reader033/viewer/2022050521/5fa4952c899d82071049f4a4/html5/thumbnails/35.jpg)
THANK YOU!
For questions, maintenance requests or concerns regarding any of our
parks contact 311
November 6, 2019Boston Parks and Recreation