Smart Meter Interoperability and the Impact on early Rollout Programmes
Smart Grids Data Management
22nd-23rd November 2010
Ben NicaudieHead of Consulting, ElectraLink Limited
![Page 2: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/2.jpg)
Interoperability Questions
How did we get here? Why is change needed? What are the interim options? Who could govern the interim?
“Those who cannot remember the past are condemned to repeat it”George Santayana, Spanish philosopher
![Page 3: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/3.jpg)
How did we get here? Why is change needed?What are the interim options?Who could govern the interim?
![Page 4: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/4.jpg)
Many Industry Functions
• Change of Supply• Customer Billing• Energy Balancing and
Settlement• Change of Agent• Metering Services• Distribution Use of
System Billing
![Page 5: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/5.jpg)
Many Market Participants
![Page 6: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/6.jpg)
Inter - operabilityNetworks
A Highly Functional Solution
MeterMaintainer
Data Aggregator
DistributionOperator /
Transporter
Prepayment Infrastructure
ProviderSupplier
Data Collector
Consumer
MeteringSystem
![Page 7: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/7.jpg)
All using flat files
![Page 8: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/8.jpg)
Data Transfer Service
High VolumeGateway
Low VolumeGateway
Monitoring
Helpdesk
Remote UserSystems Primary Hub Secondary Hub
Managed Network
![Page 9: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/9.jpg)
An “Industrial Grade” Network
DTS (flat files)
Commercial data flows
(e.g. RGMA)
Web traffic (e.g. HTTP)
Web services (e.g. SOAP,
REST)
Any other application
protocol
ElectraLink Data Transfer Network
Authentication, Encipherment, Resilience, Reliability
Multi Protocol Label Switching (MPLS) NetworkConnectivity, Protocol Agnosticism
Physical layer e.g. Ethernet, fibre
![Page 10: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/10.jpg)
How did we get here? Why is change needed?What are the interim options?Who could govern the interim?
![Page 11: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/11.jpg)
The existing system can not talk to the meters
![Page 12: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/12.jpg)
With Smart Meters we need the Wide Area Network to talk and listen
ReadingsConfiguration
![Page 13: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/13.jpg)
Data
Data
XXT 0019.12
0001889.126 Head End
Head End
Customer A
Customer B
SMS
GPRS
Supplier to Meter Operations
![Page 14: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/14.jpg)
The answer - Centralised Comms
“Suppliers will have to use the DCC – a single entity – as that will aid switching and data management. It will control access to the data and secure communications, so it must be independent.”
![Page 15: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/15.jpg)
A Future Centralised Market
CPEMS
MGHHDC
NHHDA
HHDC
NHHDC
REGCOS
COA
MAPMAM
MAP
SH
GT
PP
IGTIGT
SU
GEN
SUP
PPMIP ECOES
ASP
MOP
DCC
DIST
NHHDR
DSM
scoges
ECOES
SET
![Page 16: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/16.jpg)
New investments for Suppliers leading early rollout
• Smart Meters• Head End systems• WAN Comms contracts• Smart Prepayment• All associated IT
![Page 17: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/17.jpg)
New problems for Suppliers leading early rollout
• New concept of “installing supplier”
• Stranded Assets• Negotiating Comms contracts• Dependencies on other Suppliers• Building Market share
![Page 18: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/18.jpg)
Ofgem’s timetable suggests 8-10 million interim meters by DCC Go-Live
20192018201720162015201320122011 2014
20192018201720162015201320122011 2014
Phase 2 Develop regulatory framework
Phase 3 Tender and award DCC licence
DCC Setup and procure service providers
Build and trialling of DCC services
Go-LiveDCC
Meter rollout profile
Delivery Timetable
![Page 19: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/19.jpg)
How did we get here? Why is change needed?What are the interim options?Who could govern the interim?
![Page 20: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/20.jpg)
Core Principles
1. Impact on the consumer
2. Privacy & Data Security
3. Speed and Cost of Implementation
4. Re-usability
5. Avoiding Scope Creep
6. Existing market arrangements
![Page 21: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/21.jpg)
Interim Options (1)
1. Supplier owned HEs non-standard interfaces to Central Service
2. Supplier owned HEs with standardised interfaces to Central Service
3. Centrally owned HEs providing Central Service
![Page 22: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/22.jpg)
Interim Options (2)
4. Installing Suppliers provide readings to a central store
5. Installing Suppliers provide Smart Meter Services direct to 3rd Parties
6. Suppliers Migrate Smart Meters to gaining Supplier’s HE on CoS
![Page 23: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/23.jpg)
Key Influencing Factors
• Industry has immature Smart Metering infrastructures
• Not all Suppliers have a Smart programme at all
• The industry needs to see interim as a step to DCC
![Page 24: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/24.jpg)
Supplier Meter Asset Provider
HH Data Aggregator
Distributor Meter Operator
HH Data Collector
SVAA
Meter Data Management
Site Meta Data Interval Data
Au
the
ntic
atio
n a
nd
Acc
ess
Co
ntr
ol
TranslationServices H/E
Smart Meters
XML Interoperability
Interim Interoperability Arrangements
Novated comms contracts from CoS
HE
HE
Smart Meters
Customer Changes Supplier1. Meter migrates to interim HE2. Comms contract novates to central body3. Translation service starts
HE
Enhancement A
Centralise all head ends
Enhancement B
Standardise interfaces
Enhancement C
Add legacy supportSimplify business processes
A Roadmap for Interim
![Page 25: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/25.jpg)
How did we get here? Why is change needed?What are the interim options?Who could govern the interim?
![Page 26: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/26.jpg)
The ideal regulatory framework
• A dedicated Smart Energy Code• Governing access to smart electricity
and gas meters• Defining commercial relationships
between DCC and its users • A code common to both gas and
electricity
![Page 27: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/27.jpg)
But this is highly complex...
![Page 28: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/28.jpg)
Existing regulatory frameworks
• The Master Registration Agreement• The Supply Point Administration
Agreement• The Uniform Network Code• The Balancing and Settlement Code• The Data Transfer Services Agreement
![Page 29: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/29.jpg)
Comparing frameworks
• The MRA and SPAA do not provide for data transfers service provision
• The UNC and BSC do cover data transfer but also a much wider area
• The DTSA is solely about metering-related data transfer, associated services and governance
![Page 30: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/30.jpg)
What would be needed?
• A transparent mechanism for cost recovery
• An obligation on gas and electricity Suppliers to join
• No restriction on the use of intellectual property by a future DCC
• Any user objections being ultimately resolved by Ofgem
![Page 31: Smart Interoperability for Early Rollout - Ben Nicaudie SMi Nov 2010](https://reader033.fdocuments.us/reader033/viewer/2022051820/55389ae0550346b82d8b488b/html5/thumbnails/31.jpg)
Interoperability Questions
How did we get here? Why is change needed? What are the interim options? Who could enforce this?