SLIDE Final Report: Full Scale Wind Load Testing of Aluminum Screen Enclosures Forrest J. Masters,...

34
SLIDE Final Report: Full Scale Wind Load Testing of Aluminum Screen Enclosures Forrest J. Masters, PhD, PE, Associate Prof. of Civil Engineering, University of Florida Sungmoon Jung, PhD, Florida State University 1

Transcript of SLIDE Final Report: Full Scale Wind Load Testing of Aluminum Screen Enclosures Forrest J. Masters,...

SLIDE

1

Final Report:

Full Scale Wind Load Testing of Aluminum Screen Enclosures

Forrest J. Masters, PhD, PE, Associate Prof. of Civil Engineering, University of Florida

Sungmoon Jung, PhD, Florida State University

SLIDE

2

Presentation Outline• Specimen selection process• Full-scale testing

– Set up– Design load (FBC) vs. applied load– Key observations

• Material testing• Comparison of test and analysis• Implications to the code

SLIDE

3

Selection of the “Generic” Specimen

• AAF acquired 35 signed and sealed, site-specific plans from the St. Johns County Building Department and the City of Jacksonville.

• Ten designs with a mansard roof with approximate dimensions of 24 ft X 40 ft X 9 ft and a 48 in rise in the roof were selected, de-identified, and forwarded to Dr. Jung (FSU) to review

• A design with average structural performance was selected• In order to rank the candidate designs objectively, raking

criteria were used (performance of roof bracing, wall bracing, post, and other members)

SLIDE

4

Generic Specimen

SLIDE

5

Generic Specimen

SLIDE

6

Generic vs. AAF Specimens• AAF designed a second specimen (same size) following the 2010

AAF Guide to Aluminum Construction in High Wind Areas.• Significant differences between the “Generic” and the “AAF”

specimens– AAF has 8 additional 2 x 2 roof braces, whereas generic has none– AAF has 2 x 8 roof beams, whereas generic has 2 x 6 roof beams– AAF has 2 x 3 purlins, whereas generic has 2 x 2 purlins– AAF has a 5” super gutter, whereas generic has a 7” super gutter– AAF has a 2 x 3 + 1 x 2 eave rail, whereas generic has a 2 x 2 + 1 x 2 eave rail– AAF has 2 x 4 posts on the long wall, whereas generic has 2 x 5 posts– AAF does not have cable bracings on the side walls– Some AAF purlins require backing plates (at bracing bays)

SLIDE

7

AAF Specimen

SLIDE

8

AAF Specimen

SLIDE

9

Preparation for the Testing• Hartshorn Custom Contracting is fabricating both

specimens• AAF and FSU performed structural analysis to identify

high anticipated-to-allowable stress ratio and high tension. Visual Analysis and SAP2000 were used (sample results: next slide)

• The information was forwarded to IBHS to install strain gauges

SLIDE

10

High anticipated-to-allowable stress, moment (%)

High anticipated-to-allowable stress, buckling (%)

High tension (kips is shown)

SLIDE

11

High anticipated-to-allowable stress, moment (%)

High anticipated-to-allowable stress, buckling (%)

High tension (kips is shown)

SLIDE

12

Test Set Up• Tests were conducted at the IBHS Research Center• Generic specimen: assembled in April 23, tested in April

24• AAF specimen: assembled in April 25, tested in April 26• Both specimens used 18 ×14 × 0.013" fiberglass mesh

SLIDE

13

SLIDE

14

SLIDE

15

Sensors: Generic Sensors: AAF

(A: axial, M: moment, C: cable)

SLIDE

16

Experimental Procedure• Static pull tests (single point axial force) were conducted

before wind tests. Results were used for finite element model calibration.

• Wind tests: angle definition

SLIDE

17

Experimental Procedure (cont’d)• Wind tests

– Series I: 90 degree case over three wind speed intensities with and without turbulence (Runs 1 to 6)

– Series II: repeated most of Series I across a range of wind angles (Runs 7 to 24)

– Series III: gradually increased the wind speed for 0 degree and 90 degree wind angles (Runs 25 to 30)

– Series IV: tests at maximum wind speed for various scenarios (Generic: Runs 31 to 33, AAF: Runs 31 to 40)

SLIDE

Design vs. Applied Wind Loading• The following figures compare design wind loading (FBC) and

applied wind loading (IBHS)– FBC: 120 mph, exposure B were used for both specimens– IBHS: 90 mph, assumed a factor of 0.7 (includes gust effect, drag,

screen)

• In principle, no failure should have occurred in the test

0

2

4

6

8

10

12

0 5 10 15 20

Hei

ght (

ft)

Windward Pressure (psf)

IBHS (90 mph)

FBC (ASD)

FBC (LRFD)

IBHS pressure @ 33 ft = 14.5 psf

0

2

4

6

8

10

12

0 5 10 15 20H

eigh

t (ft

)

Leeward Pressure (psf)

IBHS (90 mph)

FBC (ASD)

FBC (LRFD)

IBHS pressure @ 33 ft = 14.5 psf

SLIDE

Key Observations During the Test• Screens/attachments began to fail at 80 mph

Generic, max V = 80 mph AAF, max V = 80 mph

SLIDE

Key Observations (cont’d)• Several screen attachments failed at 90 ~ 100 mph

Generic, max V = 90 mph

Failed screens and/or screen attachments (fully failed ones only), after all 90 mph tests

SLIDE

Key Observations (cont’d)• Generic specimen lost one corner post at 90 mph

SLIDE

Key Observations (cont’d)• AAF specimen lost two corner posts at 100 mph• The failure was due to the unbalanced loading (& failed

attachment)

SLIDE

Summary of the Tests80 mph

Gen

eric

AAF

Partial failure of screen attachments

Partial failure of screen attachments

90 mph

Structural failure of the corner post, and failure of four screens and/or attachments

Failure of two screens and/or attachments

100 mph

• Unable to load @ 90 deg. (no screen at the corner due to the damage)

• 100 mph @ 270 deg. and 0 deg., no substantial damage

Structural failure of two corner posts

Retr

ofit

Retr

ofit

SLIDE

24

Material Testing• Material testing was conducted to confirm the material

performance

SLIDE

25

Material Testing (cont’d)• Specified: 6005-T5 (E = 10,100 ksi, = 35.0 ksi, = 38.0

ksi)• Actual performance: E = 9,300 ksi, = 27.8 ksi, = 34.0

ksi– and are estimated statistically– : N = 12, mean = 32.3 ksi, standard deviation = 1.2 ksi– : N = 12, mean = 37.5 ksi, standard deviation = 0.9 ksi

SLIDE

26

Model Calibration• Using the results from pull tests, three different

modeling assumptions were compared

Model A: baseline Model B: boundary conditions prevent rotation

Model C: Model B + frame end-releases are fixed except purlins and corner bracings

SLIDE

27

Model Calibration (cont’d)• Finite element results

were compared to sensor readings

• Model C was chosen for further analysis

• Sample results on the right: axial forces, AAF, pull 01

-6.0E-2

-3.0E-2

0.0E+0

3.0E-2

6.0E-2

9.0E-2

-6.0E-2 -3.0E-2 0.0E+0 3.0E-2 6.0E-2 9.0E-2

Axia

l Ana

lysi

s (ki

ps)

Axial Experiment (kips)

Model A

Model B

Model C

Perfect

Correlation

SLIDE

28

Comparison of Design vs. Test• For 80 mph and 90 mph tests,

test results (x-axis) were compared to the analysis results (y-axis)

• Analysis used FBC loading. Therefore, in principle, all test results should be lower than analysis results.

• Marked notable locations (a sample comparison is shown on the right) -1.5E+0

-1.0E+0

-5.0E-1

0.0E+0

5.0E-1

1.0E+0

-1.5E+0 -1.0E+0 -5.0E-1 0.0E+0 5.0E-1 1.0E+0

Axia

l Ana

lysi

s (k

ips)

Axial Experiment (kips)

80 mph

90 mph

Perfect

Correlation

Data Higher Than AnalysisData Lower Than Analysis

SLIDE

29

Summary of Notable Members: Generic

• One corner bracing exceeded the allowable stress• High moment correlated well with screen attachment

failure

A-5M-7

A-6

M-9

M-10

M-11

M-12

A-13

A-14

A-15

M-17

A-16

M-18

M-19

M-20M-21

M-8

0.0

0.2

0.4

0.6

0.8

1.0

1.2

A-15 (0) M-17 (0) M-18 (0) A-1 (90) A-2 (90) M-17(90)

M-21(90)

Actu

al to

Allo

wab

le S

tres

s Ra

tio

Max

Avg

SLIDE

30

Summary of Notable Members: AAF• Two posts exceeded the allowable stress (one of which

actually failed during the testing)

A-5

A-4

M-7

A-6

M-9

M-10

A-11

A-12

A-13A-14

M-17

M-18

M-19

M-20M-21

M-8

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

A-6 (0) M-8 (0) M-9 (0) A-4 (90) M-9 (90) M-18(90)

M-21(90)

Actu

al to

Allo

wab

le S

tres

s Ra

tio

Max

Avg

SLIDE

31

Implications to the Code• Although the wind loading did not exceed the design

loading, failures were observed:– Screens began to fail at 80 mph– Some screen attachments failed at 90 to 100 mph– Some of the failed screen attachments fluttered while attached

to the structural member, contributing failure of it– One vertical post failed due to the unbalanced loading (one side

had screen but the other side lost the screen)

SLIDE

32

Implications to the Code (cont’d)• The failure of screen attachments and unbalanced

loading have direct implications on the rule on removing the screen (Rule 61G20-1.002). If some screens are cut but not others, unbalanced loading may accelerate the failure of the post. Code changes should be considered to either require removal of all screens above the chair rail, or, devise a more secure fastening of screen attachments to prevent partial failure and unbalanced loading.

SLIDE

33

Implications to the Code (cont’d)• The tensile ultimate strength and tensile yield strength

of the aluminum extrusions, based on the testing of coupons harvested from the specimens, were lower than the specified values. To ensure that the aluminum meets or exceeds the specified performance levels, the building code should require that material certification be submitted to the building official.

SLIDE

34

Implications to the Code (cont’d)• The tested specimens received very thorough

inspection and quality control. However, it is well known that the real-world plan review and inspection may not reach such a level, and therefore, likely experience much more severe failure due to the hurricane. The code requirement on this issue would greatly reduce potential failure of screen enclosures due to the hurricane.