Slide 1 Test Assurance – Ensuring Stakeholders get What They Want Paul Gerrard Gerrard Consulting...
-
Upload
charleen-clarke -
Category
Documents
-
view
213 -
download
1
Transcript of Slide 1 Test Assurance – Ensuring Stakeholders get What They Want Paul Gerrard Gerrard Consulting...
Slide 1
Test Assurance – Ensuring Stakeholders get What They Want Paul GerrardGerrard ConsultingPO Box 347MaidenheadBerkshireSL6 2GU UK
e: [email protected]: http://gerrardconsulting.comt: 01628 639173
Slide 2
Why Test Assurance? Most projects need to be kept ‘honest’ Sponsors and business- Need someone ‘on the inside’ on their side- Need translations from technical, evasive
spin to lay persons’ language Testing is rarely done well - project
needs support from someone capable and bias-free
Risks arising need someone to prod the project into action (who else will do this?)
Slide 3
Objectives of the role Primary objective: Support- To provide advice, leadership and direction to the
project team to improve the effectiveness of testing and in particular test reporting
Secondary objective: Assurance- To provide independent assurance to the
management board on the thoroughness, completeness and quality of testing
Optional Excluded from scope is any responsibility for the
delivery of testing - specifically excluded to avoid any conflicts of interest
Slide 4
Support Information Provision- Including specific points of expertise or experience
Decision Support- To support the decision making process, where points of
technique, documentation, reporting or appropriate (not always 'best') practice may be suggested to the team
Advisory- To advise on process for traceability, coverage, sign-off
for assurance purposes Risk Awareness- To identify risks that must be addressed by test phases
Review support- Critical reviews of coverage, documentation, plans,
results while under development.
Slide 5
Assurance Test Audit- Independent audit of test records and
process to include checks for traceability, coverage, consistency, accuracy etc.
Test Phase report- Phase report to document the audit,
identify areas for correction, interpretation Sign-Off- See later.
Slide 6
Assessment of Testing as a whole Can the system can be used in a realistic business
environment, processing realistic data? Does the system meets performance, availability
and reliability objectives? Can the system can be supported by operations
staff so that exceptions can be handled? Can the system can be installed, started, stopped,
backed up and restored from a range of failure scenarios?
Have all outstanding product risks of concern have been addressed
Have each of the test phases achieved their target level of coverage so that the project can be confident in their assessment?
Slide 7
Process and Coverage Assurance Is the process sound; will it achieve the
test phase objectives? Was the process followed, exit criteria met,
waived appropriately? Did the appropriate, responsibility people
perform sign-offs? What process was used to design tests;
were coverage targets set? Were the targets met in test planning and
execution?
Slide 8
Product Risk Assurance What risks drove the test planning,
prioritisation? Were risks addressed through the
testing? Are there risks, not tested that are
outstanding?
Slide 10
Interventions - Assurance
Test Assurance Notes: Where anomalies or uncertainties in the planning, scope or approach to testing are detected, or where a new risk to be addressed by testing appears, an Assurance Note is a challenge to the project to clarify the purpose of that aspect of the project.
Test Audit: Independent audit of test records and process to include checks for traceability, coverage, consistency, accuracy etc.
Test Phase report: Phase report to document the audit, identify areas for correction, interpretation.
Sign-Off: see slides that define precisely what Assurance Sign-off means (and doesn't mean).
Slide 12
Sign-Off by stakeholders and other participants Indicates that the signatories:- Have read and understood it what they have signed- Have approved a deliverable, outcome or process- Made their decision in a transparent fashion- Commit to a defined course of action – usually to ‘accept’
and/or implement- Have reached a consensus view- Have based their decision on their (or delegated)
judgements- Agree that their views have been taken into consideration
Signatories must be recognised authorities Sign-off is usually irreversible – once signed, cannot
be undone Not granted lightly.
Slide 13
Test Assurance Sign-Off (is different) The test approach, plan, specifications, scripts,
logs, incident reports have been reviewed and test lead has been interviewed/consulted
The following have been ‘assured’:- Objectives and acceptance/exit criteria- The test design approach enables objectives to be met- Coverage target(s) ensure that enough information will
be gathered to make the acceptance/exit decision- The exit criteria have been met or…
The remaining anomalies have been waived by the business And… the right people have been involved
- The test records indicate that the phase process has been followed and are a true reflection.
Slide 14
The politics of assurance Who will pay for the assurance function?- Would your department employ a critic?
Can the Assurance Manager stay independent?- Or will he go native with the development group?
Can the Assurance Manager speak the language of business?- Are you a techy at heart – unable to see beyond code, bugs,
incident reports? If you made a recommendation, would the
development organisation attack you, or the problem? Assurance Managers sign-off – do they take
responsibility for the release? Do Test Assurance Management skills exist yet? If you ‘did’ assurance, would it be a career limiting
move?