Slatina CHP:
CHP fired by biomass with wood chips drying system
V međunarodna konferencija o OIESava Centar, Beograd. 12.10.2017.
GGE 2
Slatina CHP: CHP fired by biomass
Investment: 26 Million EURO
Contractual period: 14 years
Expected timeframe:
─ project implementation start : June 2018
─ invoicing start: 2018, 4Q
GGE 3
Slatina CHP: CHP fired by biomass
General info:
GGE invested into “woodchip drying plant” in connection with 5,0 MW CHP
plant, located in northern part of Croatia (Municipality of Slatina, closed to
Vitorvitica). The plant will produce heat energy in order to dry the woodchips
and electrical energy which will be distributed into electrical grid.
• CHP size: 5 MWe / 12 MWth
• Location: Norhern part of Croatia (Municipality of Slatina)
GGE 4
Slatina CHP: CHP fired by biomass
General info:
GGE bought existing SPV company, which had all needed documentation for the Feed in tarriffapproval and permits for construction. Legal due diligence was already done, no negativeissues were found. Due to GGE philosophy to use BAT and plants with highest possibleefficiency, we gone through process of changing Construction permit of CHP plant, add newpermit for Drying plant and totally changed previous project in order to get 50% of total plantefficiency and get 20% of bonus on Feed-in tariff.
Received documentation:
- Construction permits for CHP, Drying plant and 35kV l=2,1km cable
- Contract with HERO
- Contract with HROTE
- Cntract with HEP
- Contract with Hrvatske šume
- Grid contract period: 14 years
- Feed in tarriff: 192 €/MWh
GGE 5
Slatina CHP: CHP fired by biomass
Technical facts:
• Number of working hours: 8.000
• Woodchip consumption p.a.: 60.000 t
• Boiler cpacity: 27 t/h, 72bar
• Generator max power: 5,7 MWe
• Selfconsumption: 0,6 MWe
• Termal max power: 12 MWth
• Woodchip logistics
‒ Supplier: Hrvatske Šume
‒ Long term supply contracts
‒ supplier radius: 150 km
GGE 6
Slatina CHP: new CHP on biomass
Activity 2016 2017 2018
Building permit
Feasibility study
Legal Due Diligence
Design
Buying Energy 9
Getting turnkey offers
Sign the turnkey contract
Construction
Equipmet delivery
Connection to the grid
Installation
Commissoning
Operating Permit
Feed-in-tariff approval
1 august 2016 30 november 2016 30 June 2018
Biomass Plant Slatina
GGE 8
Dryer Plant - building design drawings
GGE 9
Power Plant - building design drawings
GGE 10
GGE Heat & Powergorenje · energetika ljubljana
Resavska 23/6B, 11000 BeogradSrbija (Serbia)
Tel: +381 (0) 11 785 00 95 (local 205)GSM:
SRB: +381 (0) 63 252 492+381 (0) 60 545 00 94
CG: +382 (0) 68 052 492sinisa.janjusevic@gge.siwww.gge.co.mewww.ggesrbija.rswww.gge.si
S poštovanjem,Siniša Janjušević______________