Sl. Cl. No., chapter no PART Query by Bidders … O… · ... Design / Detail Engineering ......
Transcript of Sl. Cl. No., chapter no PART Query by Bidders … O… · ... Design / Detail Engineering ......
MINUTES OF MEETING OF PRE-BID CONFERENCE HELD ON 05.05.2012 AT TCE, VIKHROLI AT MUMBAI
BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 - Design / Detail Engineering, Manufacturing, Testing, Third party inspection for import content, Packing & forwarding and Supply of Butane Pre Heater along with Mandatory spares, Commissioning and start-up spares, Maintenance tools and tackles, Supervision of erection, pre-commissioning, commissioning & performance guarantee test runs and Training of BPCL personnel for BPCL, Uran LPG Plant.
Sl. No
PART /VOL
Ref of
Page No.
Reference
Query by Bidders Comments by TCE/BPCL Cl. No., chapter no Para No.
Page 1 of 2
PRE BID DISCUSSIONS
1. Part-1 34 of 139
Bidder’s Qualification Criteria Technical Criteria shall read as : The bidder should have supplied / executed and completed in the previous ten years at least one Propane / Butane /LPG pre heater for not less than Rupees 48 lakhs.
2. Part-1 94 of 170
Clause 4.0 of SCC – Required Delivery Period
All the bidders requested for extension of delivery period. The suggestion was to change 5 months at site to 5 months at Ex-Factory
Required Delivery Period is changed from 5 months at site to 5 months at Ex-Factory. Now the clause shall read as “ Required Delivery period : Within 5 months at Ex-Factory from the placement of Fax / Letter of Intent.
3. Part-1 125 and 126 of 139
TCE.M4-907 Spares and Maintenance tools and tackles
This document is replaced with the following clause : Spares : Supply price shall be inclusive of price of Mandatory spares (listed in Part 2, Page 12 of 118) Supply price shall be inclusive of price of commissioning and startup spares Supply price shall be inclusive of price of Maintenance tools and tackles Recommended spares for 2 year trouble free operation shall be quoted separately and the price shall be valid for 6 months after contract delivery period.
4. Part-1 93 of 139
Clause 11.0 of SCC – Payment terms
All Bidders requested for BPCL to consider 10% advance payment.
Not acceptable. Payment terms remains same as given in the tender
5. Part-1 134 of 139
Schedule of Performance Guarantee
Updated Schedule of Performance Guarantee is attached herewith as Annexure-1
6. Part-1 135 to 139 of 139
Schedule of Price Updated Schedule of Price is attached herewith as Annexure-2
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 1 of 12
MINUTES OF MEETING OF PRE-BID CONFERENCE HELD ON 05.05.2012 AT TCE, VIKHROLI AT MUMBAI
BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 - Design / Detail Engineering, Manufacturing, Testing, Third party inspection for import content, Packing & forwarding and Supply of Butane Pre Heater along with Mandatory spares, Commissioning and start-up spares, Maintenance tools and tackles, Supervision of erection, pre-commissioning, commissioning & performance guarantee test runs and Training of BPCL personnel for BPCL, Uran LPG Plant.
Sl. No
PART /VOL
Ref of
Page No.
Reference
Query by Bidders Comments by TCE/BPCL Cl. No., chapter no Para No.
Page 2 of 2
7. Part-2 52 & 53 of 118
Piping and Valve Material Specification
Updated Piping specification (First 2 pages) is attached herewith as Annexure-3
General 8. There were no Technical queries from the
bidders. TCE/BPCL reiterated the following technical and scope parameters : For heater thermal design, Ambient air temperature is to be considered as 18 deg C at 60% RH and the Butane temperature at inlet of heater is -4 deg C and the outlet temperature shall be 15 deg C. Butane pre heater is to be mounted on the structures erected from the Ground. Columns of the pre heater from the ground is also part of the scope. Common header with branches at the inlet and outlet of 2 butane pre heaters with requisite valves is in the scope of the bidder (refer to Page 23 of 118)
9. Deviations presented in bidder’s proposal other than the deviation in the Schedule of Deviations Page 37 & 38 of 139, Part 1 will not be considered in evaluation and during the execution of the Job. Tender specification shall govern and shall be binding on the bidder.
10. In case of any further modifications, addendums to the tender, if any will be published in TCE’s website www.tce.co.in or BPCL’s website www.bharatpetroleum.in/tenderroom. Bidders are advised to check the website regularly till submission date for any such addendums.
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 2 of 12
TCE.6758A-B-300-
002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SCHEDULE OF PERFORMANCE GUARANTEE SHEET 1 OF 3
1.0 PERFORMANCE GUARANTEES & TESTS
1.1 The CONTRACTOR shall guarantee that materials and operation of the system
shall meet the requirements of this specification.
1.2 The CONTRACTOR shall guarantee satisfactory performance of the proposed
Butane pre heater with following parameters:
Sl. No. DESCRIPTION UNIT SPECIFICATION
Butane Pre heater
1
Outlet temperature at
the exit flange of
Butane pre heater at
the design flow rate
given in the data sheet
Deg C 15 Deg C + 2 Deg C
2 Power Consumption kW To be indicated by the
bidder in the bid
2.0 PERFORMANCE TESTS
2.1 The CONTRACTOR shall conduct the performance test of the Butane pre heater
after commissioning within the guarantee period.
2.2 It is the responsibility of the CONTRACTOR to conduct the performance test and
also arrange for all instruments with calibration certificates and equipment to
conduct the required guarantee tests.
2.3 After the system has been stabilized by the vendor during trial run, the vendor
shall conduct a performance guarantee test run for the complete system prior to
handing over the plant to the owner. The procedure for performance testing shall
be submitted to the owner / consultant for review and shall be mutually agreed.
2.4 CONTRACTOR shall furnish, after the award of Contract, the detailed test
procedure and suggested period of testing, for OWNER's review and approval.
3.0 BID EVALUATION
3.1 The BIDDER shall comply with the performance parameters wherever they are
specified in Data Sheets of this tender specification. No credit shall be given
during the Bid evaluation, if parameters better than those specified are offered
by the BIDDER.
Annexure 1 to MOM of Pre bid meeting for Butane Pre
Heater held on 03-05-2012. BPCL Tender NIT No. :
6758A_TCE/BPCL_RFQ_002
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 3 of 12
TCE.6758A-B-300-
002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SCHEDULE OF PERFORMANCE GUARANTEE SHEET 2 OF 3
3.2 BIDDER shall completely study all sections of this specification and indicate all
deviations in the Schedule of Deviations. If no deviations are indicated or except
for the deviations indicated in the Bid, it will be presumed that the Bid conforms
in all aspects to the specification and OWNER reserves the right to evaluate the
Bid without any further reference to the BIDDER. It is binding on the part of
BIDDER to supply the equipment in accordance with the specification except for
the deviations accepted by the OWNER. No extra claims on this account will be
accepted after the award of the Contract
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 4 of 12
TCE.6758A-B-300-
002
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SCHEDULE OF PERFORMANCE GUARANTEE SHEET 3 OF 3
SCHEDULE OF PERFORMANCE GUARANTEE
(TO BE FILLED BY BIDDER)
SUPPLIER shall furnish performance guarantee for Butane Preheater in respect
of all items listed in table below. Only the values indicated in the Table will be
considered for evaluation.
Also the values indicated in Table will be the basis for evaluation of the
performance test by the PURCHASER.
Values furnished by Bidder in this schedule shall alone be considered for Loading
during Bid Evaluation.
Sl. No Particulars Guaranteed value
1 Outlet temp of butane at the design flow rate given
in the data sheet
15 Deg C + 2 Deg C
2 Power Consumption at the design conditions kWhr
If the above guaranteed are not sustained on test, the contractor hereby
guarantees that he shall make good the deficiency in each every case by
altering and / or replacing the defective at no extra cost to the Purchaser.
SIGNATURE ___________________________
NAME ___________________________
COMPANY SEAL DESIGNATION ___________________________
DATE ___________________________
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 5 of 12
TCE.6758A-B-300-002
TATA CONSULTING ENGINEERS LIMITED SECTION: SOP
SCHEDULE OF PRICE Page 1 of 5
TCE FORM NO. 120 R3 FILE NAME: F120R3.DOC
ISSUE
R0
BID DOCUMENT NO: TCE.6758A-B-300-002
ITEM: Butane Pre Heater
PROJECT : BLENDING UNIT AT BPCL URAN
CLIENT : M/s. BHARAT PETROLEUM CORPORATION LIMITED
SUPPLIER’S BID REF _______________________________________ DT ______________
Sr. No. Description Form No
INDIGENOUS BIDDERS:
1. Price Schedule for Design / fabrication / assembly and supply of complete butane pre heater, supply of mandatory and commissioning spares, supply of special tools and tackles, Performance Guarantee, Installation Supervision and Commissioning assistance SP-1
2. Price Schedule for Recommended Spares for Two Years Operation & Maintenance SP-2
Annexure 2 to MOM of Pre bid meeting for Butane Pre
Heater held on 03-05-2012. BPCL Tender NIT No. :
6758A_TCE/BPCL_RFQ_002
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 6 of 12
TCE.6758A-B-300-002
TATA CONSULTING ENGINEERS LIMITED SECTION: SOP
SCHEDULE OF PRICE Page 2 of 5
TCE FORM NO. 120 R3 FILE NAME: F120R3.DOC
ISSUE
R0
SCHEDULE OF PRICE - INDIGENOUS (FORM SP-1)
BASIC PRICE FOR SUPPLY OF BUTANE PRE HEATER ( AS MENTIONED BELOW) INCLUDING DESIGN / DETAIL ENGINEERING, MANUFACTURING , TESTING, MANDATORY SPARES, COMMISSIONING & START-UP SPARES, MAINTENANCE TOOLS & TACKLES, SPECIAL TOOLS AND TACKLES AND THIRD PARTY INSPECTION CHARGES FOR IMPORT CONTENT IF APPLICABLE, PACKING & FORWARDING CHARGES FOR THE FOLLOWING TAGS IN STRICT COMPLIANCE WITH TECHNICAL SPECIFICATION AND VARIOUS ATTACHMENTS / ENCLOSURES / ANNEXURE MENTIONED THEREIN, DATA SHEETS, STANDARDS, SPECIFICATIONS AND TO THE SATISFACTION OF THE ENGINEER-IN-CHARGE.
SL. No
ITEM DESCRIPTION QUANTITY UNIT RATE (Rs) TOTAL AMOUNT (Rs)
A Design of complete butane pre heater, supply of butane pre heater, supply of mandatory and commissioning spares, Performance Guarantee including Packing and Forwarding
1 SET
B EXCISE DUTY @ % OF A
C CST @ _____ % OF ( A+B) OR MVAT @ ____% OF (A+B)
D FREIGHT CHARGES @ _________% OF "A"
E OCTROI @ _________% OF (A+B+C+D)
F OCTROI SERVICE @ _________% OF E
G TOTAL (A+B+C+D+E+F)
H LUMPSUM PRICE FOR SUPERVISION OF INSTALLATION, COMMISSIONING
I SERVICE TAX @ 12.36% OF H
NOTE:
1) NO TAXES AND DUTIES OTHER THAN THOSE INDICATED ABOVE SHALL BE PAYABLE.
2) BIDDER’S TO NOTE THAT SUPERVISION WILL BE IN THREE STAGES i.e. ERECTION / INSTALLATION, MECHANICAL / PRE COMMISSIONING AND COMMISSIONING / TESTING WITH TIME LAG. AT EVERY STAGE BIDDER WILL BE GIVEN ADVANCE INFORMATION BY BPCL/TCE. LUMPSUM PRICE SHALL INCLUDE TRAVEL CHARGES, LODGING AND BOARDING ETC
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 7 of 12
TCE.6758A-B-300-002
TATA CONSULTING ENGINEERS LIMITED SECTION: SOP
SCHEDULE OF PRICE Page 3 of 5
TCE FORM NO. 120 R3 FILE NAME: F120R3.DOC
ISSUE
R0
SCHEDULE OF PRICE - INDIGENOUS (FORM SP-2)
RECOMMENDED SPARES FOR TWO YEARS OPERATION & MAINTENANCE (Bidder to use photocopy of this proforma to furnish tag wise details)
SL. No
ITEM DESCRIPTION / TAG NO. QUANTITY UNIT RATE (Rs)
IN FIGURES AND WORDS AMOUNT (Rs)
IN FIGURES AND WORDS
NOTE:
1. Vendor's quoted prices in Form SP-1 of price schedule shall be exclusive of the cost of recommended spares for two years operation 2. Specify Firm Freight charges (payable extra) for two years spares @ ___________ % (applicable only in case of two years spares
ordered separately) 3. Cenvatable Service Tax extra @ _________ % shall be applicable on above freight charges for two years spares. 4. Excise Duty (ED) applicable extra on two years spares @ __________ %
5. Central Sales Tax (CST) against Form C applicable extra on two years spares @ __________ %
6. MVAT, if applicable extra on two years spares @ __________ %
7. OCTROI @___________%
8. OCTROI SERVICE CHARGES @__________% OF OCTROI. 9. The above quoted Price should be valid up to six months after contract delivery period. 10. Recommended spares for 2 years operations and maintenance will not be considered during price evaluation.
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 8 of 12
TCE.6758A-B-300-002
TATA CONSULTING ENGINEERS LIMITED SECTION: SOP
SCHEDULE OF PRICE Page 4 of 5
TCE FORM NO. 120 R3 FILE NAME: F120R3.DOC
ISSUE
R0
SCHEDULE OF PRICE - FOREIGN (FORM SP-1A)
BASIC PRICE FOR SUPPLY OF BUTANE PRE HEATER ( AS MENTIONED BELOW) INCLUDING DESIGN / DETAIL ENGINEERING, MANUFACTURING , TESTING, MANDATORY SPARES, COMMISSIONING & START-UP SPARES, MAINTENANCE TOOLS & TACKLES, SPECIAL TOOLS AND TACKLES AND THIRD PARTY INSPECTION CHARGES FOR IMPORT CONTENT IF APPLICABLE, PACKING & FORWARDING CHARGES FOR THE FOLLOWING TAGS IN STRICT COMPLIANCE WITH TECHNICAL SPECIFICATION AND VARIOUS ATTACHMENTS / ENCLOSURES / ANNEXURE MENTIONED THEREIN, DATA SHEETS, STANDARDS, SPECIFICATIONS AND TO THE SATISFACTION OF THE ENGINEER-IN-CHARGE.
SL. No
ITEM DESCRIPTION QUANTITY CURRENCY UNIT RATE
TOTAL AMOUNT
A Design of complete butane pre heater, supply of butane pre heater, supply of mandatory and commissioning spares
1 SET
B Third Part Inspection charges Lumpsum
C Firm Freight Charges up to Mumbai (India) Sea / Airports
D TOTAL (A+B+C)
E LUMPSUM PRICE FOR SUPERVISION OF ERECTION AND COMMISSIONING (Note 2)
F SERVICE TAX @ 12.36% OF E
NOTE:
1) NO TAXES AND DUTIES OTHER THAN THOSE INDICATED ABOVE SHALL BE PAYABLE.
2) BIDDER’S TO NOTE THAT SUPERVISION WILL BE IN THREE STAGES i.e. ERECTION / INSTALLATION, MECHANICAL / PRE COMMISSIONING AND COMMISSIONING / TESTING WITH TIME LAG. AT EVERY STAGE BIDDER WILL BE GIVEN ADVANCE INFORMATION BY BPCL/TCE. LUMPSUM PRICE SHALL INCLUDE TRAVEL CHARGES, LODGING AND BOARDING ETC
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 9 of 12
TCE.6758A-B-300-001
TATA CONSULTING ENGINEERS LIMITED SECTION: SOP
SCHEDULE OF PRICE Page 5 of 5
TCE FORM NO. 120 R3 FILE NAME: F120R3.DOC
ISSUE
R0
SCHEDULE OF PRICE - INDIGENOUS (FORM SP-2A)
RECOMMENDED SPARES FOR TWO YEARS OPERATION & MAINTENANCE (Bidder to use photocopy of this proforma to furnish tag wise details)
SL. No
ITEM DESCRIPTION / TAG NO. QUANTITY CURRENCY UNIT RATE
IN FIGURES AND WORDS AMOUNT
IN FIGURES AND WORDS
NOTE:
1. Vendor's quoted prices in Form SP-1A of price schedule shall be exclusive of the cost of recommended spares for two years operation 2. The above quoted price shall be FOB port of exit basis 3. Recommended spares for 2 years operations and maintenance will not be considered during price evaluation. 4. The above quoted price should be valid upto six months after contract delivery period.
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 10 of 12
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: Write-up
TCE.6758A-300-PP-1551 PIPING MATERIAL SPECIFICATION GRADE : BE57C SHEET : 1 OF 3
SERVICE :-
PROPANE, BUTANE AND LPG
P-T
RA
TIN
G
TEMP. ºC -45 -29 CA (mm) :- 1.5
PR. kg/cm2 g 35.32 35.32 FLANGE FACING:- RF, 125 RA
NOM. PIPE SIZE NB 15 20 25 40 50 80 100 150 200 250 300 350
OUTSIDE DIA. mm 21.3 26.7 33.4 48.3 60.3 88.9 114.3 168.3 219.0 273.0 323.9 355.6
THICKNESS MM 3.73 3.91 4.55 5.08 3.91 5.49 6.02 7.11 6.35 6.35 6.35 7.92
NOM. PIPE SIZE NB 400
OUTSIDE DIA. mm 406.4
THICKNESS mm 7.92
LINE JOINT 40 NB & BELOW :- SW COUPLING
50 NB & ABOVE:- BUTT WELDED
ITEM
NOMINAL PIPE
SIZE RANGE
NB
MATERIAL
SPECIFICATION
DIMENSIONAL
STANDARD
REMARKS
PIPES
15 – 40 ASTM A 333 GR. 6 ASME B-
36.10 PE, SEAMLESS, SCH 80
50 – 150 ASTM A 333 GR. 6 ASME B-
36.10 BE, SEAMLESS, SCH 40
200 – 400 ASTM A 333 GR. 6 ASME B-
36.10 BE, SEAMLESS, SCH 20
NIPPLES 15 – 40 ASTM A 333 GR. 6 ASME B-
36.10 PBE, SEAMLESS, SCH 80
BW
F
ITT
ING
S
ELBOWS (90°/ 45°-1.5D), CAPS, REDUCERS (ECC. / CONC.), TEES (EQUAL / RED.)
50 – 350 ASTM A 420 GR. WPL 6 ASME B-16.9 BW (THK. TO MATCH PIPE THK.)
SW
FIT
TIN
GS
ELBOWS (90°/ 45°), TEES (EQUAL / RED.), COUPLING (FULL / HALF/RED.)
15 – 40 ASTM A 350 GR LF2
CLASS 1 ASME B-
16.11 SW
SWAGE (CONC. / ECC.)
15 – 80 ASTM A 350 GR LF2
CLASS 1 BS-3799 PBE (THK. TO MATCH PIPE THK.)
UNIONS 15 – 40 ASTM A 350 GR LF2
CLASS 1 BS-3799 SW
BRANCH CONNECTION 15 – 350 --- --- REFER BRANCH CONNECTION CHART
FLANGES
15 – 40 ASTM A 350 GR LF2
CLASS 1 ASME B-16.5 SW, 300, RF / 125 AARH, SCH 80
50 – 150 ASTM A 350 GR LF2
CLASS 1 ASME B-16.5 WN, 300, RF / 125 AARH, SCH 40
200 – 400 ASTM A 350 GR LF2
CLASS 1 ASMB B-16.5 WN, 300, RF / 125 AARH, SCH 20
BLIND FLANGES 15 – 400 ASTM A 350 GR LF2
CLASS 1 ASME B-16.5 300, RF / 125 AARH
STUD BOLTS 15 – 400 ASTM A 320 GR.L7 ASME B-
18.2.1
REV. NO. R1 PPD. BY: BSR JOB NO. CLIENT: BPCL, Uran ISSUE
DATE 04-05-12 CHD. BY: KR TCE. PROJECT: PMC SERVICES FOR R1
REV. BY BSR DATE: 30-03-12 6758A BLENDING UNIT AT URAN
TCE FORM NO. 087 R5 FILE NAME: 6758APP1551R0.DOC
ANNEXURE 3 TO MOM OF PREBID
MEETING FOR BUTANE PRE HEATER
HELD ON 03-05-2012
BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 11 of 12
SPECIFICATION NO. TATA CONSULTING ENGINEERS LIMITED SECTION: Write-up
TCE.6758A-300-PP-1551 PIPING MATERIAL SPECIFICATION GRADE : BE57C SHEET : 2 OF 3
ITEM
NOMINAL PIPE
SIZE RANGE
NB
MATERIAL
SPECIFICATION
DIMENSIONAL
STANDARD REMARKS
HEAVY HEX. NUTS
15 – 400 ASTM A 194 GR. 4 ASME B 18.2.2
GASKETS 15 – 400 SP. WND SS304 +
GRAFOIL ASME B 16.20 –
ASME B 16.5 4.5MM THK, SPIRAL, 300
THREADED FITTINGS :- CAPS
15 – 40 ASTM A 333 GR. 6 ASME B-16.11 SCREWED
TYPE OF VALVE
SIZE RANGE
MATERIAL PR.
RATING TYPE OF ENDS
SPECIFICATION OR
TAG NUMBER
REMARKS
NB BODY TRIM ANSI
GLOBE VALVE 15 – 40 A350 GR
LF2 CLASS 1
SS 304 800 SW, 800, B-
16.11 T63
DMN. STD :- API-602 Note 1
GLOBE VALVE 50 – 250 ASTM A352
GR. LCB SS 304 300
FLGD, 300, B-16.5, RF /125
AARH T33
DMN. STD :- BS-1873
Note 2 for valves greater than 100 NB
GLOBE VALVE 300 – 400 ASTM A352
GR. LCB SS 304 300
FLGD, 300, B-16.5, RF /125
AARH T33
DMN. STD :- B-16.34, Note 2
CHECK VALVE 15 – 40 A350 GR
LF2 CLASS 1
SS 304 800 SW, 800, B-
16.11 C63
DMN. STD :- API-602
PISTON LIFT TYPE
CHECK VALVE 50 – 400 ASTM A352
GR. LCB SS 304 300
FLGD, 300, B-16.5, RF /125
AARH C33
DMN. STD :- BS-1868
SWING TYPE
BALL VALVE 15 – 40 A350 GR
LF2 CLASS 1
SS 304 800 SW, 800, B
16.11 B63
DMN. STD :- ISO-17292, Note 1
BALL VALVE 50 - 100 A352 GR.
LCB SS 304 300
FLGD, 300, B-16.5, RF /125
AARH B33 DMN. STD ISO 17292
BALL VALVE 150 - 400 A352 GR.
LCB SS 304 300
FLGD, 300, B-16.5, RF /125
AARH B33
DMN. STD ISO 17292
Note 2
TYPE OF SPECIALITY
SIZE RANGE
NB
MATERIAL PR. RATING
ANSI
TYPE OF ENDS
SPECIFICATION OR
TAG NUMBER
REMARKS BODY TRIM & INT
STRAINER 15 – 40 A350 GR
LF2 CLASS 1
INT: SS304 800 SW SY63 Y-TYPE
STRAINER 50 – 150 ASTM A352
GR. LCB INT: SS304 300 WN, RF SY33 Y – TYPE
STRAINER 200 – 400 A 350 GR
LF2 CLASS 1
INT: SS304 300 WN, RF SY33 Y – TYPE
NOTES:-
1. With 100 mm pipe piece on each side of the valve.
2. With Gear Operator with adequate torque
3. All ball valves shall be full bore, trunion mounted, fire safe design(API-607) and with anti static feature.
4. 20% of valve casting shall under go radiographic examination. All cast steel valves shall be subjected to radiography as per ASME B 16.34.
5. Valves shall be tested with API 598/ BS EN 12266-1 a applicable.
6. Valves shall be provided with extended stem wherever required considering insulation.
7. Valve stems shall be of Forged construction. Castings are not acceptable.
REV. NO. R1 PPD. BY: BSR JOB NO. CLIENT: BPCL, Uran ISSUE
DATE 04-05-12 CHD. BY: KR TCE. PROJECT: PMC SERVICES FOR R1
REV. BY BSR DATE: 30-03-12 6758A BLENDING UNIT AT URAN
TCE FORM NO. 087 R5 FILE NAME: 6165APP1551R0.DOC
MOM OF PREBID MEETING FOR BUTANE PREHEATER HELD ON 03-05-2012 BPCL TENDER NIT NO: 6758A_TCE/BPCL_RFQ_002 Page 12 of 12