Skyway 126 Wind Energyzeroemissionpeople.com/wp-content/uploads/projects...Skyway 126 Wind Energy...
Transcript of Skyway 126 Wind Energyzeroemissionpeople.com/wp-content/uploads/projects...Skyway 126 Wind Energy...
Skyway 126 Wind Energy
Design and Operations Report
Prepared by: M.K. Ince and Associates Ltd.
Prepared for: Cloudy Ridge Wind Park LP
June 14, 2013
June 14, 2013
Cloudy Ridge Wind Park LP
c/o WindWorks Power Corp.
346 Waverly Street
Ottawa, Ontario
K2P 0W5
Attention: Dr. Ingo Stuckmann
Reference: Skyway 126 Wind Energy, Design and Operations Report
Dear Dr. Stuckmann,
We are pleased to present a copy of the Design and Operations Report for Skyway 126 Wind Energy
project. This report was prepared to meet the requirements of the Renewable Energy Approval
regulations, O. Reg. 359/09, Section 13. It will be included as part of the Renewable Energy Approval
Application package to be submitted to the Ministry of the Environment for the Skyway 126 Wind
Energy project.
This report includes the following appendices:
Site Plan,
Cultural Heritage Assessment Report,
Shadow Flicker Report,
Radar and Radio Communications Impact Assessment Report,
Natural Heritage Environmental Effects Monitoring Plan, and
Archaeological Assessment Report.
Please feel free to contact us if you have any questions or concerns.
Sincerely,
M. K. INCE AND ASSOCIATES LTD.
Martin Ince, P. Eng.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. i June 14, 2013
Table of Contents
1 INTRODUCTION ............................................................................................................................................. 1
1.1 PROJECT OVERVIEW .......................................................................................................................................... 1 1.2 REGULATORY AND REPORTING REQUIREMENTS ....................................................................................................... 1
2 SITE PLAN ...................................................................................................................................................... 5
2.1 NATURAL HERITAGE FEATURES ............................................................................................................................ 6 2.2 CULTURAL HERITAGE AND ARCHAEOLOGICAL FEATURES............................................................................................ 6 2.3 WATER BODIES................................................................................................................................................. 7
3 FACILITY DESIGN PLAN ................................................................................................................................ 13
3.1 PERMANENT PROJECT STRUCTURES .................................................................................................................... 13 3.1.1 Wind Turbine Technologies ............................................................................................................... 13 3.1.2 Turbine Foundations .......................................................................................................................... 14 3.1.3 Lighting .............................................................................................................................................. 14 3.1.4 Interconnection Facilities ................................................................................................................... 15 3.1.5 Roads ................................................................................................................................................. 16
3.2 TEMPORARY FACILITIES .................................................................................................................................... 16 3.2.1 Crane Pad and Laydown areas .......................................................................................................... 16 3.2.2 Temporary Roads .............................................................................................................................. 16 3.2.3 Temporary Work Facility ................................................................................................................... 16 3.2.4 Temporary Sanitary Facilities ............................................................................................................ 17 3.2.5 Waste Management .......................................................................................................................... 17
3.3 CLEARED AREAS .............................................................................................................................................. 17 3.4 WATER TAKINGS ............................................................................................................................................. 17 3.5 SETBACKS ...................................................................................................................................................... 18
3.5.1 Noise Setbacks ................................................................................................................................... 18 3.5.2 Road and Railway Rights of Way Setbacks ........................................................................................ 22 3.5.3 Property Line Setbacks....................................................................................................................... 22
4 FACILITIES OPERATIONAL PLAN ................................................................................................................... 22
4.1 OPERATION .................................................................................................................................................... 22 4.2 MAINTENANCE ............................................................................................................................................... 22 4.3 ENVIRONMENTAL MONITORING ......................................................................................................................... 23 4.4 WASTE MANAGEMENT .................................................................................................................................... 23 4.5 NOISE ........................................................................................................................................................... 23 4.6 WATER TAKING AND STORMWATER MANAGEMENT .............................................................................................. 24
5 ENVIRONMENTAL EFFECTS MONITORING PLAN .......................................................................................... 24
5.1 PURPOSE AND OBJECTIVES OF THE ENVIRONMENTAL EFFECTS MONITORING PLAN (EEMP) .......................................... 24 5.2 ROLES AND RESPONSIBILITIES ............................................................................................................................ 25
5.2.1 Roles and Responsibilities for Implementation of the EEMP ............................................................. 25 5.3 SUMMARY TABLE ............................................................................................................................................ 27 5.4 PROJECT ENVIRONMENTAL IMPACTS ................................................................................................................... 37
5.4.1 Archaeological and Heritage Resources ............................................................................................ 37 5.4.2 Air ...................................................................................................................................................... 39 5.4.3 Public Health and Safety .................................................................................................................... 42 5.4.4 Water Bodies ..................................................................................................................................... 49 5.4.5 Land Use ............................................................................................................................................ 56 5.4.6 Birds ................................................................................................................................................... 61
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. ii June 14, 2013
5.4.7 Bats .................................................................................................................................................... 64 5.4.8 Natural Heritage Features and Significant Wildlife Habitat .............................................................. 66
6 EMERGENCY RESPONSE AND COMMUNICATIONS PLAN ............................................................................. 76
6.1 STATUS UPDATES ............................................................................................................................................ 76 6.2 EMERGENCY NOTIFICATION ............................................................................................................................... 77 6.3 PROTOCOL FOR RESPONDING TO PUBLIC INQUIRIES ............................................................................................... 77 6.4 CONTACT INFORMATION .................................................................................................................................. 77
7 CONCLUSIONS ............................................................................................................................................. 78
8 QUALIFICATIONS AND LIMITATIONS ........................................................................................................... 79
9 REFERENCES ................................................................................................................................................ 80
List of Tables TABLE 1-1: ONTARIO REGULATION 359/09 DESIGN AND OPERATIONS PLAN REPORT REQUIREMENTS ............................................... 2 TABLE 2-1: COMPONENTS DEPICTED IN THE SITE PLAN .............................................................................................................. 5 TABLE 2-2: NATURAL HERITAGE FEATURES.............................................................................................................................. 6 TABLE 2-3: CULTURAL HERITAGE FEATURES ............................................................................................................................ 7 TABLE 2-4: WATER BODIES SUMMARY ................................................................................................................................... 8 TABLE 3-1: WIND TURBINE SPECIFICATIONS .......................................................................................................................... 13 TABLE 3-2: TURBINE LIGHTING, COORDINATES AND HEIGHTS ................................................................................................... 14 TABLE 3-3: CABLING SPECIFICATIONS ................................................................................................................................... 15 TABLE 3-4: POINT OF RECEPTION DESCRIPTION AND LOCATIONS ............................................................................................... 18 TABLE 3-5: PARTICIPATING RECEPTOR DESCRIPTION AND LOCATIONS ......................................................................................... 21 TABLE 5-1: SUMMARY OF ENVIRONMENTAL EFFECTS MONITORING PLAN ................................................................................... 27 TABLE 5-2: ANTICIPATED ENVIRONMENTAL IMPACTS, PERFORMANCE OBJECTIVES AND MITIGATION MEASURES FOR SIGNIFICANT
NATURAL HERITAGE FEATURES ............................................................................................................................................ 67
List of Appendices Appendix I Site Plan Appendix II Cultural Heritage Assessment Report Appendix III Shadow Flicker Report Appendix IV Radar and Radio Communications Impact Assessment Appendix V Natural Heritage Environmental Effects Monitoring Plan Appendix VI Forms Appendix VII Archaeological Assessment Report
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 1 June 14, 2013
1 INTRODUCTION
1.1 Project Overview
Cloudy Ridge Wind Park LP (the Proponent) proposes to build the Skyway 126 Wind Energy project, a
10 MW Class 4 Wind Energy Generation Facility, on privately-owned agricultural lands within the
Municipality of Grey Highlands near the town of Badjeros. It will consist of five (5) REpower MM92
wind turbines of 2 MW each, located in five (5) proposed locations. The REpower MM92 has a sound
power level of 103.2 dB(A). The project turbines will be bounded to the north by South Line C, to the
east by Grey Road 9, to the South by Grey Road 9, and to the west by Road 57A. In addition, project
cabling will be constructed along South Line C, Road 63, and 4th Concession B Road. A Power Purchase
Agreement (PPA) has been acquired for the project under Ontario’s Feed-In Tariff (FIT) Program.
The Skyway 126 Wind Energy project will provide up to 10 MW of new, renewable electrical generation
capacity and will help the Province of Ontario to address potential future electricity shortfalls. The
promotion of wind energy within the Municipality of Grey Highlands will displace greenhouse gases, air
pollution, and toxic solid waste from traditional energy production methods in the Province of Ontario.
1.2 Regulatory and Reporting Requirements
The Green Energy and Green Economy Act, passed in the Province of Ontario in 2009, mandates a
Renewable Energy Approval (REA) process under the Environmental Protection Act, Ontario Regulation
359/09 for specified classes of renewable energy projects. The Skyway 126 Wind Energy project is
subject to this process, which will evaluate the project’s environmental impacts and propose measures to
mitigate or avoid them. This Design and Operations Report presents a site plan, details of the wind farm
design and an operations plan for the facility. The report also details mitigation measures for any
environmental impacts, how they will be monitored and contingency plans in the event that mitigation
measures fail. The report also includes a plan for managing emergency responses and communications.
The reporting requirements set out by O.Reg 359/09 are summarized with reference to specific sections of
the Design and Operations Report in Table 1-1. This checklist should be used for reference purposes
only and should not replace a full reading of the report.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 2 June 14, 2013
Table 1-1: Ontario Regulation 359/09 Design and Operations Plan Report Requirements
Required Documentation Requirement Met Location in Report
Set out a site plan of the Project Location at which the renewable energy project will be engaged in, including,
i) One or more maps or diagrams of:
A. All buildings, structures, roads, utility corridors, rights of way and
easements required in respect of the renewable energy generation
facility and situated within 300 metres of the facility,
Yes Site Plan in Appendix I
B. Any ground water and surface water supplies used at the facility, Yes Site Plan in Appendix I
C. Any things from which contaminants are discharged into the air, Yes Site Plan in Appendix I
D. Any works for the collection, transmission, treatment and disposal
of sewage
NA Site Plan in Appendix I , Section
3.2.4
E. Any areas where waste, biomass, source separated organics and
farm material are stored, handled, processed or disposed of,
Yes Site Plan in Appendix I
F. The Project Location in relation to any of the following within 125
metres: the portion of the Oak Ridges Moraine Conservation Plan
Area that is subject to the Oak Ridges Moraine Conservation Plan,
the area of the Niagara Escarpment Plan, the Protected
Countryside, the Lake Simcoe watershed,
Yes Site Plan in Appendix I
G. Any noise receptors or odour receptors that may be negatively
affected by the use or operation of the facility,
Yes Site Plan in Appendix I
ii) A description of each item diagrammed under the subparagraph i, Yes Section 2
iii) One or more maps or diagrams of land contours, surface water drainage
and any of the following, if they have been identified in complying with
this Regulation: properties described in column 1 of the Table to section
19, heritage resources, archaeological resources, water bodies,
significant or provincially significant natural features and any other
natural features identified in the Protected Countryside or in the portion
of the Oak Ridges Moraine Conservation Plan Area that is subject to the
Oak Ridges Moraine Plan.
Yes Not within plan areas.
iv) a description, map or diagram of the distance between the base of any
wind turbines and any public road rights of way or railway rights of way
that are within a distance equivalent to the length of any blades of the
wind turbine, plus 10 metres,
Yes Site Plan in Appendix I
v) a description, map or diagram of the distance between the base of any
wind turbines and all boundaries of the parcel of land on which the wind
turbine is constructed, installed or expanded within a distance equivalent
Yes Site Plan in Appendix I
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 3 June 14, 2013
Required Documentation Requirement Met Location in Report
to the height of the wind turbine, excluding the length of any blades, and
vi) a description, map or diagram of the distance between the base of each
wind turbine and the nearest noise receptor.
Yes Site Plan in Appendix I
Set out conceptual plans, specifications and descriptions related to the design of the renewable energy generation facility, including a
description of,
i) Any works for the collection, transmission, treatment and disposal of
sewage, including details of any sediment control features and storm
water management facilities
Yes Section 4.6, Section 3.2.4, Section
3.2.5
ii) Any things from which contaminants are discharged into the air, and Yes Section 3.1.1
iii) Any systems, facilities and equipment for receiving, handling storing and
processing any waste, biomass, source separated
Yes Section 3.2.5
Set out conceptual plans, specifications and descriptions related to the operation of the renewable energy generation facility, including a
description of,
i) In respect to any water takings,
A. A description of the time period and duration of water takings
expected to be associated with the operation of the facility
NA Not applicable
B. A description of the expected water takings, including rates,
amounts and an assessment of the availability of water to meet the
expected demand, and
NA Not applicable
C. An assessment of and documentation showing the potential of the
facility to interfere with existing uses of the water expected to be
taken.
NA Not applicable
ii) A description of the expected quantity of sewage produced and the
expected quality of that sewage at the Project Location and the manner in
which it will be disposed of, including details of any sediment control
features and storm water management features
NA None produced
iii) A description of any expected concentration of air contaminants
discharged from the facility,
Yes Section 3.5.1
iv) In respect of any biomass, source separated organics and farm material at
the facility,
A. The maximum daily quantity that will be accepted
NA None produced
B. The estimated annual average quantity that will be accepted, NA None produced
C. The estimated average time that it will remain at the facility, and NA None produced
D. The estimated average rate at which it will be used, and NA None produced
v) In respect of any waste generated as a result of processes at the Project Yes Section 3.2.5, Section 4.4
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 4 June 14, 2013
Required Documentation Requirement Met Location in Report
Location, the management and disposal of such waste, including
A. The expected types of waste to be generated
B. The estimated maximum daily quantity of waste to be generated,
by type,
Yes Section 3.2.5, Section 4.4
C. Processes for the storage of waste, and Yes Section 3.2.5, Section 4.4
D. Processes for final disposal of waste Yes Section 3.2.5, Section 4.4
Include an environmental effects monitoring plan in respect of an negative environmental effect that may result for negating in the
renewable energy project, setting out,
i) Performance objectives in respect to the negative environmental effects Yes Section 5
ii) Mitigation measures to assist in achieving the performance objectives
mentioned in subparagraph i,
Yes Section 5
iii) A program for monitoring negative environmental effects for the
duration of the time that the project is engaged in, including a
contingency plan to be implemented if any mitigation measures fail.
Yes Section 5
Include a response plan setting out a description of the actions to be taken while engaging in the renewable energy project to inform the
public, aboriginal communities and municipalities, local roads boards and Local Services Boards with respect to the project including,
i) Measures to provide information regarding the activities occurring at the
Project Location, including emergencies
Yes Section 6.2
ii) Means by which persons responsible for engaging in the project may be
contacted, and,
Yes Section 6.4
iii) Means by which correspondence directed to the persons responsible for
engaging in the project will be recorded and addressed.
Yes Section 6.3
If the Project Location is in the Lake Simcoe watershed, a description of whether the project requires alteration of the shore of Lake
Simcoe, the shore of a fresh water estuary of a stream connected to Lake Simcoe or other lakes or any permanent or intermittent stream and,
i) How the project may impact any shoreline, including the ecological
functions of the shoreline, and
NA Not within Lake Simcoe watershed
ii) How the project will be engaged in to,
A. Maintain the natural contour of the shoreline through the
implementation of natural shoreline treatments, such as planting f
natural vegetation and bioengineering, and
NA Not within Lake Simcoe watershed
B. Use a vegetative riparian area, unless the Project Location is used
for agricultural purposes and will continue to be used for such
purposes.
NA Not within Lake Simcoe watershed
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 5 June 14, 2013
2 SITE PLAN
The site plan is attached in Appendix I of this document. The site plan includes the components
described in Table 2-1 as required by Table 1-1 of O. Reg 359/09. Further description of each of the
items depicted can be found in the sections indicated in the table.
Table 2-1: Components Depicted in the Site Plan
Component (as described in O.Reg. 359/09) Section for Further Details
All buildings, structures, roads, utility corridors, rights of way and
easements required in respect of the renewable energy generation
facility and situated within 300 metres of the facility,
Section 3.1, Section 3.2
Any ground water and surface water supplies used at the facility, Section 3.4
Any things from which contaminants are discharged into the air, Section 3.1.1
Any works for the collection, transmission, treatment and disposal of
sewage Section 3.2.4
Any areas where waste, biomass, source separated organics and farm
material are stored, handled, processed or disposed of, Section 3.2.5
Any noise receptors or odour receptors that may be negatively
affected by the use or operation of the facility, Section 3.5.1
One or more maps or diagrams of land contours, surface water
drainage and any of the following, if they have been identified in
complying with this Regulation: properties described in column 1 of
the Table to section 19, heritage resources, archaeological resources,
water bodies, significant or provincially significant natural features
and any other natural features identified in the Protected Countryside
or in the portion of the Oak Ridges Moraine Conservation Plan Area
that is subject to the Oak Ridges Moraine Plan.
Section 2.1, Section 2.2,
Section 2.3
A description, map or diagram of the distance between the base of
any wind turbines and any public road rights of way or railway rights
of way that are within a distance equivalent to the length of any
blades of the wind turbine, plus 10 metres,
Section 3.5.2
A description, map or diagram of the distance between the base of
any wind turbines and all boundaries of the parcel of land on which
the wind turbine is constructed, installed or expanded within a
distance equivalent to the height of the wind turbine, excluding the
length of any blades, and
Section 3.5.3
A description, map or diagram of the distance between the base of
each wind turbine and the nearest noise receptor. Section 3.5.1
It is expected that limited water takings will occur during the construction phase in order to remove water
from foundation excavations, if perched groundwater exists. Further, at potentially all turbine locations
dewatering will be undertaken as needed to remove any accumulated precipitation. No on-site water will
be used at the facility. Additionally, no works for the collection, transmission, treatment and disposal of
sewage are included on the site plan as they will not be installed.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 6 June 14, 2013
2.1 Natural Heritage Features
The significant natural features listed in Table 2-2 and depicted on the Site Plan were identified as part of
the Natural Heritage Assessment. Table 2-2 outlines the distance of each feature to project components
within 120 m.
Table 2-2: Natural Heritage Features
Feature
ID Feature Location Relative to Project Location
WE02 Wetland 4 m to underground electrical cabling along Road 63.
WE03 Wetland 2 m to underground electrical cabling along 4th Concession B Road.
WE04 Wetland 4 m to underground electrical cabling along Road 63.
WO01 Woodland 10 m, 33 m, 54 m, 46 m and 46 m to T2 bladeswept area, laydown,
turbine, underground electrical cabling and cranepad, respectively.
40 m to both temporary and permanent project road to T2.
WO03 Woodland 4 m to underground electrical cabling along Road 63.
DWCA01 Deer Winter
Congregation
Area
8 m north of underground electrical cabling along 4th Concession B Road.
ABH01 Woodland
Amphibian
Breeding
Habitat
10 m, 33 m, 54 m, 46 m and 46 m to T2 bladeswept area, laydown,
turbine, underground electrical cabling and cranepad, respectively.
40 m to both temporary and permanent project road to T2.
GSWH Generalized
Significant
Wildlife
Habitat
10 m, 33 m, 56 m, 46 m and 46 m to T2 bladeswept area, laydown,
turbine, underground electrical cabling and cranepad, respectively.
40 m to both temporary and permanent project road to T2. 0 m to
underground electrical cabling along Road 63. < 1m (~ 0.25 m) to
underground electrical cabling along 4th Concession B Road.
For further information on these items please see the Natural Heritage Assessment Reports (Records
Review Report, Site Investigation Report, and Evaluation of Significance Report) and Environmental
Impact Study Report.
2.2 Cultural Heritage and Archaeological Features
The cultural heritage features listed in Table 2-3 and depicted on the Site Plan were identified as part of
the Cultural Heritage Assessment Report. Table 2-3 outlines the distance of each feature to project
components in the vicinity of the project. No archaeological features were identified on site as part of the
Archaeological Assessment Report.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 7 June 14, 2013
The Cultural Heritage Assessment Report and the response from the Ministry of Tourism, Culture and
Sport (MTCS) are included in Appendix II. The Archaeological Assessment Report and the response
from the MTCS are included in Appendix VII.
Table 2-3: Cultural Heritage Features
Feature ID Feature Location of Relative to Project Location
BHR 1 309167 Centre Line B Approximately 2800 m from Turbine 1
BHR 2 309366 Centre Line B Approximately 2700 m from Turbine 3
BHR 3 309766 Centre Line B Approximately 4900 m from Turbine 4
BHR 4 269252 South Line Approximately 600 m from Turbine 1
BHR 5 269377 South Line Approximately 700 m from Turbine 4
BHR 6 269504 South Line Approximately 1300 m from Turbine 4
BHR 7 269513 South Line Approximately 1700 m from Turbine 4
BHR 8 269547 South Line Approximately 1900 m from Turbine 4
BHR 9 358091 10th Line Approximately 1400 m from Turbine 5
BHR 10 673164 Road 67A Approximately 2500 m from Turbine 4
BHR 11 673211 Road 67A Approximately 2800 m from Turbine 4
CHL 1 Badjeros Post Office Village Approximately 500 m from Turbine 4
BHR 12 349655 Concession 4 Approximately 7700 m from Turbine 4
BHR 13 349485 Concession 4 Approximately 7200 m from Turbine 4
BHR 14 347442 Concession 4 Approximately 7000 m from Turbine 4
CHL 2 McIntyre United Church and Cemetery Approximately 6900 m from Turbine 4
BHR 15 349427 Concession 4 Approximately 6900 m from Turbine 4
BHR 16 349423 Concession 4 Approximately 6900 m from Turbine 3
BHR 17 349422 Concession 4 Approximately 6900 m from Turbine 4
CHL 3 McIntyre Pioneer Cemetery Approximately 6900 m from Turbine 3
BHR 18 633812 Road 63 Approximately 7000 m from Turbine 3
BHR 19 633683 Road 63 Approximately 5800 m from Turbine 3
2.3 Water Bodies
A Records Review and Site Investigation, described in the Water Bodies Assessment Report, were
undertaken to identify water bodies that exist within 120 m of the proposed project infrastructure. All nine
potential water bodies identified during the Records Review were confirmed during the Site Investigation.
These water bodies were carried forward to the Water Bodies Impact Assessment Report. Table 2-4 below
summarizes the findings from the Site Investigation conducted at the Skyway 126 Wind Energy project,
and a description of the features carried forward to the Water Bodies Impact Assessment Report.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 8 June 14, 2013
Table 2-4: Water Bodies Summary
Unique
Identifier
UTM Coordinates
(NAD83 Zone 17)
Location relative to
proposed infrastructure
Water Bodies Descriptions
Northing Easting
WA01 557138 4901998
WA01 was identified as a
permanent or intermittent
stream within 120 m of the
Project Location, crossing
cabling infrastructure (>0.1
m from Project Location)
adjacent to Road 63.
The water body is an intermittent stream surrounded by riparian deciduous
woodland [WOD according to Ecological Land Classification (ELC; Lee et al.,
1998)]. Property access was not granted for properties on which WA01 is
present within 120 m of the Project Location; however the stream crossing is
present within the road and road allowance, and therefore sufficient data could
be collected from Road 63.
WA01 passes under Road 63 through an existing culvert, and is approximately
0.5 m in width. Stream flow is in an eastward direction. In-stream cover is
approximately 90% and consists of riparian vegetation present within the
stream channel. Riparian vegetation included grasses, forbs, shrubs (willow
and seedling balsam poplar), and trees (white willow, balsam poplar, and red
maple). Undercut banks are not present. Canopy cover is 40% partly open, and
60% open within 120 m of the Project Location. No fish or other aquatic
wildlife was observed. Water chemistry tests could not be conducted due to a
lack of property access.
WA02 556873 4903649
WA02 was identified as a
natural or artificial pond
within 120 m of the Project
Location, or more
specifically, 15 m east of
cabling infrastructure
adjacent to Road 63 at its
closest point.
The water body is a pond surrounded by a Mixed Swamp/Swamp Thicket
[SWM/SWT according to ELC (Lee et al., 1998)]. The pond is nearly
rectangular in shape, moderately-sized, and is within close proximity to
agricultural property, suggesting that it could be an artificial dugout pond, and
therefore would not qualify as a water body according to REA regulations.
Property access was not granted and the landowner was not consulted with
regards to the pond’s origin. Due to this uncertainty, it will be assumed that the
pond is of natural origin.
WA02 is an isolated pond, however it is possible that water is able to enter the
pond during the spring melt from the adjacent wetland (within approximately
15 m of the pond). An outflow is not present. The pond is absent of biotic
and/or abiotic cover. Substrate is not visible from the roadside. Fish were not
observed, though habitat is possible due to potential inflows from adjacent
swamp. Canopy cover is completely open. Potential pollution sources include
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 9 June 14, 2013
Unique
Identifier
UTM Coordinates
(NAD83 Zone 17)
Location relative to
proposed infrastructure
Water Bodies Descriptions
Northing Easting
runoff from Road 63 and agricultural fields. Water chemistry tests could not be
conducted due to a lack of property access.
WA03 556686 4906850
WA03 was identified as a
natural or artificial pond
within 120 m of the Project
Location, present 31 m
south of cabling
infrastructure adjacent to 4th
Concession B at its closest
point.
The water body is a pond surrounded by a Mixed Swamp [SWM according to
ELC (Lee et al., 1998)]. The pond is small, and is within close proximity to
agricultural property, suggesting that it could be an artificial dugout pond and
therefore would not qualify as a water body according to REA regulations.
Property access was not granted and the landowner was not consulted with
regards to the pond’s origin. Due to this uncertainty, it will be assumed that the
pond is of natural origin.
WA03 is an isolated pond, however it is likely that water is able to enter the
pond during the spring melt from the adjacent wetland (abuts the pond). An
outflow is not present. Pond is covered (approximately 90%) with floating
vegetation. Substrate is not visible from the roadside. Fish were not observed,
though habitat is possible due to potential inflows from adjacent swamp.
Canopy cover is completely open. Potential pollution sources include runoff
from 4th Concession B and agricultural fields. Water chemistry tests could not
be conducted due to a lack of property access.
WA04 557044 4906912
WA04 was identified as a
natural or artificial pond
within 120 m of the Project
Location, present 77 m
south of cabling
infrastructure adjacent to 4th
Concession B at its closest
point.
The pond’s presence was confirmed during the Site Investigation from vantage
points along 4th Concession B relatively distant to the feature, and could not be
observed close to the feature due to the presence of a thicket swamp and tall
hedgerow blocking views. Therefore air photo interpretation was utilized to
analyze the water bodies as an alternative method of study.
The water body is edged by residential Rural Property [CVR_4 according to
ELC (Lee et al., 1998)] on its east side, Swamp Thicket [SWT according to
ELC (Lee et al., 1998)] on its north side and Mixed Swamp [SWM according
to ELC (Lee et al., 1998)] on its west and southern side. WA04 is
approximately 400 m length by approximately 240 m in width. It is palustrine,
downstream from a large swamp (with intermittent or permanent inflow) and
upstream from the Mad River via an intermittent or permanent outflow greater
than 120 m from the Project Location. The feature’s large size and topographic
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 10 June 14, 2013
Unique
Identifier
UTM Coordinates
(NAD83 Zone 17)
Location relative to
proposed infrastructure
Water Bodies Descriptions
Northing Easting
position indicate that it is likely the pond is of natural origin. Potential
pollution sources include runoff from 4th Concession B, adjacent rural lawns,
and agricultural fields in the vicinity of the stream. Water chemistry tests could
not be conducted due to a lack of property access.
WA05 557521 4907140
WA05 was identified
during the Records Review
as a permanent stream
within 120 m of the Project
Location, crossing cabling
infrastructure (>0.1 m from
Project Location) adjacent
to 4th Concession B Road.
The water body is permanent stream surrounded by Shallow Marsh [MAS
according to ELC (Lee et al., 1998)]. Property access was not granted for
property south of 4th Concession B, however property access was granted north
of the road.
The Mad River passes under 4th Concession B through an existing culvert, and
is approximately 10 m in width. Stream flow is in a northward direction. In-
stream cover is approximately 5% and consists of riparian vegetation, small
organic debris, and cobble. Undercut banks are present, comprising
approximately 50% of banks along the stream (indicating vulnerability to
erosion). Substrate consists of 80% cobble, 15% gravel, and 5% silt. Riparian
vegetation includes Red Osier Dogwood, Willow sp., Bur Reed, Yellow Pond
Lily, Water Shield, Speckled Alder, Meadowsweet, and riparian grasses.
Canopy cover is 5% partly open, and 95% open within 120 m of the Project
Location. Fish were observed within the stream channel (approximately 5-10
cm in length, species unknown). Potential pollution sources include runoff
from 4th Concession B and agricultural fields. Water chemistry tests were
performed indicating a pH of 7.5, water temperature of 18.8°C, and
conductivity of 363 µS/cm.
WA06 559144 4907635 WA06 was identified as a
permanent or intermittent
stream within 120 m of the
Project Location, crossing
cabling infrastructure (>0.1
m from Project Location)
adjacent to 4th Concession
B Road.
The water body is a permanent stream surrounded by riparian Coniferous
Swamp and Marsh [SWC and MA according to ELC (Lee et al., 1998)] to the
north of the stream crossing and Mixed Willow Organic Deciduous Thicket
Swamp Type [SWMO2-6 according to Ecological Land Classification (Lee et
al., 1998)] to the south of the stream crossing. Property access was not granted
for property north of 4th Concession B, however property access was granted
south of the road.
WA06 passes under 4th Concession B Road through an existing culvert, and is
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 11 June 14, 2013
Unique
Identifier
UTM Coordinates
(NAD83 Zone 17)
Location relative to
proposed infrastructure
Water Bodies Descriptions
Northing Easting
approximately 2 m in width. Stream flow is in a northward direction, at a
velocity of approximately 0.5 m/s. Undercut banks are not present. In-stream
cover is approximately 90% and consists of small organic debris and
vegetation. Substrate consists of muck (90%) and gravel (10%). Canopy cover
is 50% partly open and 50% open within 120 m of the Project Location. Fish
habitat is possible. Potential pollution sources include runoff from 4th
Concession B and agricultural fields. Water chemistry tests were performed
indicating a pH of 8.0, water temperature of 22°C, conductivity of 308 µS/cm,
and alkalinity of approximately 200 ppm.
WA07 559698 4907776 WA07 was identified as a
natural or artificial pond
within 120 m of the Project
Location, present 27 m
south of cabling
infrastructure adjacent to 4th
Concession B at its closest
point.
The water body is a pond surrounded mostly by Rural Property [CVR_4
according to ELC (Lee et al., 1998)] with a small portion on the eastern side
adjacent to Coniferous Swamp [SWC according to ELC (Lee et al., 1998)].
The pond is rectangular in shape, small, and is within close proximity to
agricultural property, suggesting that it could be an artificial dugout pond, and
therefore would not qualify as a water body according to REA regulations. The
landowner was not consulted with regards to the pond’s origin. Due to this
uncertainty, it will be assumed that the pond is of natural origin.
WA07 is an isolated pond, however it is possible that water is able to enter the
pond during the spring melt from the adjacent wetland (abuts the pond). The
pond is partially covered (approximately 40%) with floating vegetation. Banks
are not at risk for erosion. Substrate consists of muck (40%) and sand (60%).
Fish were not observed, though habitat is possible due to potential inflows
from adjacent swamp. Canopy cover is completely open. Potential pollution
sources include runoff from 4th Concession B, adjacent rural lawns, and
agricultural fields. Water chemistry tests were performed indicating a pH of
8.0, water temperature of 22°C, conductivity of 138 µS/cm.
WA08 560111 4907977 WA08 was identified as a
permanent or intermittent
stream within 120 m of the
Project Location, at no
point coming in contact
The water body is a permanent stream that is surrounded by Mixed Swamp
[SWM according to ELC (Lee et al., 1998)] for sections within 120 m of the
Project Location.
WA08 does not come into contact with project infrastructure, flowing
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 12 June 14, 2013
Unique
Identifier
UTM Coordinates
(NAD83 Zone 17)
Location relative to
proposed infrastructure
Water Bodies Descriptions
Northing Easting
with project infrastructure. northwestward from Hwy. 124 where it crosses beneath the road via a culvert
greater than 120 m from the Project Location. It is approximately 3 m in width
(5 m in width at bank full), and contains pools 8 cm in depth (25 cm at bank
full). In-stream cover is 100%, with small organic debris and dense vegetation.
Substrate consists of muck (100%). Riparian vegetation consists of grasses and
forbs such as Canada Bluejoint, Jewelweed, Joe-Pye Weed, Common
Arrowhead, and trees and shrubs such as Black Ash, Eastern White Cedar, and
Black Ash. Canopy cover is 80% partly open and 20% open for portions of the
stream within 120 m of the Project Location. No fish or other aquatic wildlife
was observed, but the stream could provide suitable habitat for fish. Potential
pollution sources include runoff from agricultural fields in the vicinity of the
stream, sediments/runoff from Hwy. 24 located upstream. Water chemistry
tests were performed indicating a pH of ~8.0, water temperature of 24°C, and
conductivity of 298 µS/cm.
WA09 559829 4907726 WA09 was identified as a
natural or artificial pond
within 120 m of the Project
Location, present 115 m
south of cabling
infrastructure adjacent to 4th
Concession B Road at its
closest point.
The water body is a pond surrounded by Coniferous Swamp [SWC according
to ELC (Lee et al., 1998)]. The pond is almost circular in shape, small, and is
within close proximity to agricultural property, suggesting that it could be an
artificial dugout pond and therefore would not qualify as a water body
according to REA regulations. The landowner was not consulted with regards
to the pond’s origin. Due to this uncertainty, it will be assumed that the pond is
of natural origin.
WA09 is an isolated pond, however it is possible that water is able to enter the
pond during the spring melt from the adjacent wetland (within 6 m of the
pond’s northern edge). The pond is partially covered (approximately 40%)
with floating and emergent vegetation (water shield, grasses and rushes).
Banks are not at risk for erosion. Substrate consists of muck (30%), gravel
(10%), and sand (60%). Fish were not observed, though habitat is possible due
to potential inflows from adjacent swamp. Canopy cover is completely open.
Potential pollution sources include runoff from 4th Concession B, adjacent rural
lawns, and agricultural fields. Water chemistry tests were performed indicating
a pH of 8.0, water temperature of 20°C, conductivity of 237 µS/cm.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 13 June 14, 2013
3 FACILITY DESIGN PLAN
The following sections provide technical descriptions of the project components as presented in the site
plan, including the wind turbine, foundations, roads and associated electrical transmission and distribution
components.
3.1 Permanent Project Structures
Skyway 126 Wind Energy project will have a nameplate capacity of 10 MW, consisting of five (5)
REpower MM92 wind turbine generators (constructed at five proposed locations), each rated at 2 MW
capacity, along with ancillary facilities. The location of all structures is noted on the Site Plan (see
Appendix I). Turbine details are provided below in Table 3-1.
The wind turbines will each require a transformer (either pad-mounted or within the turbine if possible) to
increase the voltage of generated electricity from 575 V to 34.5 kV. One substation within the wind
project area will serve as a collection point for the power generated at all turbines and will step up the
voltage to 44 kV. The substation will require an area of approximately 36 m x 32 m within a fenced work
area, which will also be used for construction trailers and equipment laydown.
The collection system, consisting of underground conductors and fibre optic cable, will largely follow
internal access road routes from the turbines to the substation. Connection from the substation will occur
along an 11.4 km 44 kV tapline to the Point of Common Coupling (PCC). At the PCC, the project will
connect to the expanded Hydro One grid at the M2 Feeder on 4th Concession B Road. Interconnection
facilities are described in greater detail in Section 3.1.4.
New access roads will connect the project to the existing road network, and internal roads within the
project area will provide access to each turbine for construction, operation and maintenance. Roads are
described in greater detail in Section 3.1.5.
3.1.1 Wind Turbine Technologies
The wind turbine model to be used at Skyway 126 Wind Energy project is the REpower MM92 turbine.
This turbine has a power rating of 2 MW and has three (3) blades. Each tower will be conical, made of
steel and approximately 4.6 m in diameter at the base. Table 3-1 outlines key technical specifications of
the REpower MM92 turbine; further information about this turbine model is included in the Wind Turbine
Specifications Report. The locations of the proposed turbines are shown in
Table 3-2.
Table 3-1: Wind Turbine Specifications
Specification Information
Make REpower
Model MM92
Name Plate Capacity 2 MW
Hub Height Above Grade 100 m
Rotor Diameter 92.5 m
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 14 June 14, 2013
Specification Information
Rotor Radius 46.25 m
Blade Length 45.2 m
Blade Swept area 6,720 m2
Operational Wind Speeds 3 – 24 m/s
Rotational Speed 7.8 – 15.0 RPM
Tower Diameter 4.6 m (bottom), 3.0 m (top)
Voltage 575 V
Sound Power Level 103.2 dB(A)
Ice detection and de-icing The turbine will be equipped with an ice detection system that
will stop the rotor until the icing drops off. No active de-icing
technology will be used (e.g. heaters).
Maintenance Schedule Quarterly maintenance
3.1.2 Turbine Foundations
At the base of each turbine will be a poured concrete foundation with reinforcing steel bars. The
foundation will contain a mounting ring to which the base of the tower will be attached. Exact
specifications of foundation design will depend on the results of a geotechnical investigation of the
proposed turbine locations. Typically foundations range from a diameter of 15 m to 25 m and are
approximately 2 m to 3 m in depth. Once backfilled, only 5-6 m of the foundation is expected to be
visible from the base of the turbine.
3.1.3 Lighting
While confirmation from Transport Canada is pending, it is expected that 3 of the 5 turbines will be lit for
aeronautical safety. Turbine coordinates and whether they are proposed to be lit or unlit is noted in
Table 3-2. The Department of National Defense (DND) has requested that turbines be lit with
incandescent as well as infrared lighting in order to ensure compatibility with night vision goggles.
Correspondence with the DND is ongoing with respect to this request.
Table 3-2: Turbine Lighting, Coordinates and Heights
Turbine Lighting* Easting
(m)
Northing
(m) Longitude Latitude
Ground
Elevation
(m)
Turbine
Height (m
AGL)
Total
Height
(m ASL)
T1 Yes 556214 4899665 80 17 45.28 W 44 14 52.99 N 524 146.25 670.25
T2 Yes 556263 4899421 80 17 43.17 W 44 14 45.06 N 521 146.25 667.25
T3 No 556746 4899891 80 17 21.21 W 44 15 00.16 N 520 146.25 666.25
T4 Yes 557106 4899922 80 17 04.96 W 44 15 01.06 N 520 146.25 666.25
T5 No 557083 4899692 80 17 06.09 W 44 14 53.62 N 519 146.25 665.25
* Note: Number and configuration of lit vs. unlit turbines is contingent on feedback from Transport
Canada
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 15 June 14, 2013
3.1.4 Interconnection Facilities
The proposed wind project will be connected to the Hydro One electrical distribution grid via turbine pad-
mounted transformers at the base of each turbine which are connected to the collection system and in turn
are connected to the substation. The project will connect to existing HONI M2 Feeder which is connected
to the Stayner Transformer Station (TS) near the town of Stayner.
The pad mount transformers will be located at the base of the wind turbines and will step-up the voltage
from 575 V to 34.5 kV. The transformer design has not been finalised at the time of reporting; however
the footprint dimensions are expected to be approximately 3 m x 3 m. The transformers will not have
acoustic barriers. They will be placed on small concrete pads or within the tower base if possible.
A total of 1.8 km of buried electrical cabling will be used to connect the project to the substation. The
voltage of these collector lines will be 34.5 kV. The routing of the collection system is shown in
Appendix I. The specifications of the cabling used will be finalised upon completion of the detailed
electrical design, however expectations are outlined in Table 3-3. At the three locations where cabling is
required to cross water courses, directional drilling or a similar technology such as punch and bore will be
used. These techniques may also be used where required to avoid existing utilities, tile drainage, etc. At
all other locations trenching (or ploughing) will be used to bury cabling.
Three water bodies (WA01, WA05, and WA06) cross Road 63 and 4th Concession B Road will be crossed
by underground electrical cabling using high pressure directional drilling (HPDD), or similarly
appropriate technology, such as punch and bore.
Table 3-3: Cabling Specifications
Cabling Component Dimensions Notes
Trench for buried cable ~1 m depth x 1 m width
Cable burial depth ~1 m
Water crossing drilling depth ~1 m below stream bed Low enough to prevent scouring
of cable by stream bed.
Electrical cabling conduit ~150 mm diameter
Communication conduit ~32 mm diameter
The substation will include a main transformer to step up the voltage from 34.5kV to 44 kV, to match the
local distribution grid voltage level. The substation will also contain a breaker, disconnect switches,
meters, protection and controls, and communications systems. The substation will require an area of
approximately 36 m x 32 m, which will include a small control building, approximately 3 m x 5 m. A
grounding grid will be buried at the site of the substation. The transformer foundation is designed to also
act as a spill trap for secondary spill containment, filled with aggregate with ~35% interstitial space to
accommodate oil in the event of an accidental oil spill and prevent release into the environment.
Connection to Hydro One’s existing distribution grid will be carried out via an 11.4 km tap line between
the substation and the PCC at the existing 44 kV M2 Feeder on 4th Concession B Road, within the
municipal road allowance.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 16 June 14, 2013
3.1.5 Roads
Approximately 3.3 km of non-paved gravel surface roads will be constructed to allow access to each
individual wind turbine site. Approximately 2.3 km are permanent roads and 1.0 km are temporary roads
(to be removed at the end of construction). The roads will be 5 m in width and their construction will
reach a depth of 0.5 m consisting of 0.4 m of aggregate with 0.1 m of gravel on the surface. Both
permanent and temporary roads will be constructed with the same specifications. Temporary (1.0 km) and
permanent (2.3 km) project roads, including turning radii, will be developed on privately owned
agricultural lands with three proposed entrances from municipal roads. No active intermittent or
permanent streams are proposed to be crossed by newly constructed roads.
3.2 Temporary Facilities
Temporary facilities for waste disposal, sanitary requirements and indoor work needs will be provided.
Crane pads may also be temporary, as they may be removed following the completion of construction,
depending on landowner wishes. Temporary laydown areas will be located adjacent to each turbine.
Temporary construction roads may also be removed, depending on landowner wishes. Temporary
facilities are described in greater detail below.
3.2.1 Crane Pad and Laydown areas
Crane pads and laydown areas are also required near the base of each turbine. The crane pad will consist
of an area of 25 m x 45 m, which will be 0.5 m deep. The bottom 0.4 m will be filled with aggregate and
the top 0.1 m surface will be gravel. The laydown area will simply be leveled as necessary in a 92 m
diameter area beside the turbine. No aggregate or gravel will be used for the laydown areas, unless
weather conditions dictate otherwise.
Following completion of construction works the crane pads may be removed and restored for agricultural
use, if requested by the landowner.
3.2.2 Temporary Roads
Approximately 1.0 km of project roads will be constructed to provide temporary access to turbines during
the construction phase, and will be removed during site rehabilitation at the conclusion of construction
activities for agricultural production, if requested by the landowner. Permanent project roads will be
constructed along alternate routes to provide access for construction and to the turbines throughout the
project life.
3.2.3 Temporary Work Facility
Office trailers of approximately 3 m x 12 m will be brought onto the site for meetings, crew breaks, and
storage of computers and drawings. The trailer will be removed upon the completion of construction. The
trailer will be located within the substation area.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 17 June 14, 2013
3.2.4 Temporary Sanitary Facilities
During construction and decommissioning temporary bathroom and washing facilities will be required.
Portable toilets and washing facilities will be brought in by a contractor, emptied, cleaned and resupplied
as necessary. No on-site water will be used for any of the temporary sanitary facilities; all water will be
brought in. The temporary sanitary facilities will be located within the substation area or crane pads as
necessary. Sanitary waste from temporary employee sanitary facilities will be handled by an appropriate
licensed contractor.
3.2.5 Waste Management
Waste materials for the REpower MM92 are limited to oils and solvents which will be replaced during
regular maintenance, and physical parts that must occasionally be replaced. These waste materials will not
be stored on site, but will be brought off-site immediately.
Procedures relating to the management, monitoring, and mitigation measures for petroleum, oils, and
lubricants are contained in the Environmental Effects Monitoring Plan (Section 5 of this report).
3.3 Cleared Areas
As project infrastructure will be located almost entirely on agricultural areas, up to 4.8 hectares of
agricultural area will be removed from production. Wooded and hedgerow areas are not expected to be
cleared. Project components of the project have been designed to be located within areas presently
vegetated.
3.4 Water Takings
Based on the findings of a preliminary dewatering assessment, at the foundation excavation locations
temporary water takings of no more than 50,000 L/day will be required during construction. Temporary
water takings will potentially be required only during the construction phase, in order to remove water
from foundation excavations, if perched groundwater is present. Further, at potentially all turbine
locations dewatering will be undertaken as needed to remove any accumulated precipitation.
Dewatering of the foundation excavations will occur through a combination of gravity drainage and/or
sump pumps, and possibly perimeter drainage ditches, depending on the time of year and conditions
encountered. The dewatering discharge will be directed to the ground surface, where it will re-infiltrate or
become surface runoff. Silt and erosion control measures will be employed as necessary, potentially
including a sump pit composed of clear stone and filter fabric surrounding the pump inlet.
Given the distances between the excavation locations and nearby natural features and adjacent users, no
impacts to surface water features or groundwater users are anticipated. This is in part due to the depth and
duration of the excavation, and the soil types present. Furthermore, it is not expected that migration of
contaminants will occur as a result of the dewatering. Flow rates will be monitored using a flow meter on
the dewatering discharge pipe, to ensure the permitted dewatering rate is not exceeded. If gravity drainage
is used for dewatering, a weir will be constructed in the outflow channel and daily flow rates will be
calculated based on daily flow measurements at the weir.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 18 June 14, 2013
3.5 Setbacks
3.5.1 Noise Setbacks
One-hundred and sixteen (116) noise receptors are located within 2,000 m of the turbines. This includes
three (3) participating receptors associated with Skyway 126 Wind Energy project. A list of all receptors
surrounding the Project was compiled by M. K. Ince and Associates Ltd. using 2012 Ontario Parcel data,
current (2013) Grey County GIS data, satellite and aerial photography, and site visits. Assessed parcel
boundaries were used to add receptors for vacant lots (as opposed to ownership parcels). Vacant lots were
modeled as points at locations consistent with local development patterns (required by the Noise
Guidelines for Wind Farms, Ministry of the Environment, October 2008).
The acoustical characteristics surrounding the project area are consistent with that of a Class 3 Area as
defined by NPC 232 and required by Noise Guidelines for Wind Farms (Ministry of the Environment,
2008). All receptors have been classified as lying in a Class 3 Area.
The turbine Sound Power Level for the REpower MM92, as defined in O. Reg 359/09, is 103.2dB(A).
There are a total of 5 turbines in the Skyway 126 Wind Energy project. Adjacent projects result in
numerous additional turbines being located within 3 km of the noise receptors being considered. Based on
the number of turbines within 3 km of the noise receptors being considered, the sound power level of
those turbines, and the setbacks of the turbines from the receptors, Section 55 of O. Reg 359/09 requires a
noise assessment be performed.
Table 3-4 gives setback distances and coordinates for all noise receptors within 2,000 m of the Skyway
126 Wind Energy project. The nearest non-participating receptor is 559 m from the project location; as
such, an Environmental Noise Impact Assessment has been prepared for this project. This report is
included with the REA Application documents. For some receptors shown in the table, turbines from
adjacent projects may be closer than the distances shown to the Skyway 126 Wind Energy turbines.
All noise receptors within 2,000 m of the proposed turbine locations and the participating receptors are
detailed in Table 3-4 and Table 3-5, respectively.
Table 3-4: Point of Reception Description and Locations
Point of
Reception ID Description
UTM Coordinates (NAD 83) Distance to Nearest
Turbine (m)
Nearest
Turbine Easting Northing
R001 Non-Participating 557140 4901724 1802 T4
R002 Non-Participating 555895 4901021 1393 T1
R003 Non-Participating 556637 4900511 630 T3
R004 Non-Participating 556770 4900556 665 T3
R005 Non-Participating 557374 4900732 853 T4
R006 Non-Participating 557393 4900730 857 T4
R007 Non-Participating 557439 4900737 880 T4
R008 Non-Participating 558183 4901237 1700 T4
R009 Non-Participating 558523 4901148 1874 T4
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 19 June 14, 2013
Point of
Reception ID Description
UTM Coordinates (NAD 83) Distance to Nearest
Turbine (m)
Nearest
Turbine Easting Northing
R010 Non-Participating 557199 4900671 755 T4
R011 Non-Participating 557214 4900677 763 T4
R012 Non-Participating 557271 4900691 787 T4
R014 Non-Participating 557318 4900741 846 T4
R015 Non-Participating 555813 4900135 618 T1
R016 Non-Participating 557291 4900650 751 T4
R017 Non-Participating 557271 4900643 740 T4
R018 Non-Participating 557252 4900638 731 T4
R019 Non-Participating 557340 4900525 647 T4
R020 Non-Participating 557338 4900640 755 T4
R021 Non-Participating 557334 4900669 781 T4
R022 Non-Participating 557346 4900483 610 T4
R023 Non-Participating 557231 4900632 721 T4
R024 Non-Participating 557397 4900632 767 T4
R025 Non-Participating 557404 4900587 729 T4
R026 Non-Participating 557413 4900541 691 T4
R027 Non-Participating 557717 4900680 974 T4
R028 Non-Participating 557451 4900368 564 T4
R029 Non-Participating 558696 4900898 1866 T4
R030 Non-Participating 558601 4900891 1782 T4
R031 Non-Participating 558310 4900944 1579 T4
R032 Non-Participating 558228 4900917 1500 T4
R033 Non-Participating 558155 4900792 1363 T4
R034 Non-Participating 557547 4899281 620 T5
R035 Non-Participating 556720 4898854 728 T2
R036 Non-Participating 556651 4898828 709 T2
R037 Non-Participating 557680 4898910 984 T5
R038 Non-Participating 557723 4898682 1196 T5
R039 Non-Participating 557160 4898289 1405 T5
R040 Non-Participating 556863 4898801 863 T2
R041 Non-Participating 556757 4898782 808 T2
R042 Non-Participating 556925 4898376 1237 T2
R043 Non-Participating 557774 4901023 1288 T4
R044 Non-Participating 557731 4900836 1107 T4
R045 Non-Participating 556953 4900616 711 T4
R046 Non-Participating 555636 4899682 578 T1
R047 Non-Participating 555565 4899362 700 T2
R048 Non-Participating 555565 4899273 714 T2
R049 Non-Participating 555594 4899091 746 T2
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 20 June 14, 2013
Point of
Reception ID Description
UTM Coordinates (NAD 83) Distance to Nearest
Turbine (m)
Nearest
Turbine Easting Northing
R050 Non-Participating 555603 4898987 790 T2
R051 Non-Participating 555443 4899248 838 T2
R052 Non-Participating 555395 4899541 828 T1
R053 Non-Participating 555751 4900258 752 T1
R054 Non-Participating 555707 4898543 1039 T2
R055 Non-Participating 555684 4898792 855 T2
R056 Non-Participating 555477 4898680 1080 T2
R057 Non-Participating 555328 4898876 1082 T2
R058 Non-Participating 555364 4898777 1106 T2
R059 Non-Participating 555321 4898727 1170 T2
R060 Non-Participating 555339 4898684 1182 T2
R061 Non-Participating 555337 4898506 1302 T2
R062 Non-Participating 554686 4898243 1968 T2
R063 Non-Participating 554589 4898230 2054 T2
R064 Non-Participating 554471 4898386 2069 T2
R067 Non-Participating 558980 4899596 1899 T5
R068 Non-Participating 558586 4899432 1525 T5
R069 Non-Participating 558630 4899442 1567 T5
R070 Non-Participating 558378 4899134 1410 T5
R071 Non-Participating 558639 4898804 1792 T5
R072 Non-Participating 557832 4898264 1613 T5
R073 Non-Participating 557097 4898219 1463 T2
R074 Non-Participating 555687 4898456 1124 T2
R075 Non-Participating 557663 4897761 2016 T5
R076 Non-Participating 557493 4897923 1816 T5
R077 Non-Participating 557431 4897963 1764 T5
R079 Non-Participating 557797 4898409 1468 T5
R080 Non-Participating 558562 4898318 2019 T5
R083 Non-Participating 558841 4899705 1749 T4
R084 Non-Participating 557327 4897892 1816 T5
R085 Non-Participating 555399 4898600 1192 T2
R086 Non-Participating 555767 4898674 897 T2
R087 Non-Participating 557533 4897983 1767 T5
R088 Non-Participating 557330 4900702 812 T4
V001 Vacant 557624 4898592 1226 T5
V002 Vacant 558988 4899375 1931 T5
V003 Vacant 556581 4898821 679 T2
V004 Vacant 557466 4900747 900 T4
V005 Vacant 557291 4900805 902 T4
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 21 June 14, 2013
Point of
Reception ID Description
UTM Coordinates (NAD 83) Distance to Nearest
Turbine (m)
Nearest
Turbine Easting Northing
V006 Vacant 557873 4899203 929 T5
V007 Vacant 557656 4899000 898 T5
V009 Vacant 556541 4898653 817 T2
V010 Vacant 557359 4900892 1002 T4
V011 Vacant 555544 4899454 702 T1
V012 Vacant 555397 4898466 1289 T2
V013 Vacant 555413 4899667 801 T1
V014 Vacant 555378 4899888 865 T1
V015 Vacant 555174 4900000 1093 T1
V016 Vacant 555115 4899899 1124 T1
V017 Vacant 555412 4900166 946 T1
V018 Vacant 555341 4900148 998 T1
V019 Vacant 554674 4900573 1788 T1
V020 Vacant 557122 4901799 1877 T4
V021 Vacant 557383 4900650 779 T4
V022 Vacant 558385 4901050 1705 T4
V023 Vacant 558579 4901102 1887 T4
V024 Vacant 559095 4899608 2014 T4
V026 Vacant 557761 4898528 1347 T5
V027 Vacant 556433 4898674 766 T2
V029 Vacant 557185 4900610 693 T4
V030 Vacant 557180 4898896 802 T5
V033 Vacant 557383 4900675 802 T4
V034 Vacant 557411 4900675 812 T4
V035 Vacant 556744 4897739 1749 T2
V036 Vacant 557347 4900426 559 T4
Table 3-5: Participating Receptor Description and Locations
Description
UTM Coordinates (NAD83) Distance to Nearest
Turbine (m) Nearest Turbine
Easting Northing
P001 556244 4900103 439 T1
P002 556645 4900430 548 T3
P003 557026 4900331 417 T4
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 22 June 14, 2013
3.5.2 Road and Railway Rights of Way Setbacks
All turbines have been sited farther than the blade length (being 46.25 m) plus 10 m from public road and
railway rights of way, as required by the REA regulations. Please see the Site Plan (Appendix I) for a
depiction of the turbines and the locations of the rights of way.
3.5.3 Property Line Setbacks
All turbines have been sited farther than a distance equal to the height of the wind turbine, excluding
blade length from any parcel boundary, unless the adjacent parcel is also participating in the project, as
required by REA regulations. The nearest distance between a turbine and a non-participating property line
is 129 m. Please see the Site Plan (Appendix I) for a detailed depiction of the turbine locations and
property lines.
4 FACILITIES OPERATIONAL PLAN
The operation phase of the project will include the steps outlined below. This phase is expected to be
carried out continuously over the anticipated project life of 20 to 25 years.
4.1 Operation
The Skyway 126 Wind Energy project will be monitored and controlled remotely via computer.
Dedicated supervisory control and data acquisition (SCADA) systems will be used to capture real-time
turbine feedback and monitor and control the operation of individual turbines. Operation of the turbine
will stop automatically under extreme weather conditions such as icing or wind speeds above the
turbine’s operational limit. On-site personnel are only required for maintenance activities (Section 4.2).
Data collected using turbine mounted meteorological instruments will provide feedback to operators via
the SCADA system. Discrepancies noted between operational factors (power output, rotational speed,
etc.) and expected levels will be investigated internally. Site visits will be scheduled as necessary.
During operation, the turbine blades will turn at a rate between 7.8 to 15 revolutions per minute. The
turbines will not operate in cases of mechanical breakdown, extreme weather conditions and during
periods of maintenance.
4.2 Maintenance
The wind turbines will be subject to periodic inspection and maintenance, including routine oil changes,
motor maintenance, and lubricant and fluid replacement. To ensure proper operational output and safety
the wind turbines will be maintained by certified technicians according to the schedules recommended by
equipment manufacturers.
In general, each turbine is expected to be serviced quarterly. Maintenance service activities may include
structural inspections, braking system checks, oil and hydraulic fluid analyses, cable connections and
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 23 June 14, 2013
voltage level checks. The electrical system will be maintained annually or in compliance with industry
standards such as the 5 year substation maintenance. These regular maintenance activities will be
performed by a small crew (2-4 people) accessing the site using a pick-up truck. Periodically, major
components of the wind turbines such as blades, gearboxes or generators may require replacement. Major
component replacement will be performed with similar equipment and methods to those used in the
construction phase, including cranes and oversized vehicles for transportation. If crane pads are removed
following construction, they will be reconstructed as necessary for this activity.
In the winter months a contractor will be hired to clear access roads after snow falls. Limited salt and sand
will be applied to roads as necessary.
At the end of the useful life of the wind turbines, typically 20-25 years, the old wind turbines will be
either refurbished or decommissioned. The project site, including roads, will be maintained during the
operations phase of the project. Regular grounds-keeping will be undertaken to ensure access to the site
year-round.
4.3 Environmental Monitoring
Monitoring activities, including post-construction bird and bat mortality monitoring, will be carried out at
the wind project during its operation. These activities are described in the Environmental Effects
Monitoring Plan in Section 5 of this report.
4.4 Waste Management
Waste associated with scheduled maintenance will consist of oils, lubricants and solvents, and soiled rags.
These will be collected, brought off-site and disposed of according to relevant regulations. There will be
no on-site storage of wastes during operation.
Currently, there are programs in place to facilitate the recycling of turbine parts and it is expected that
over the lifetime of the project these programs will be strengthened and expanded. In the event that
refurbishment or recycling is not feasible, scrap turbine parts will be disposed of according to applicable
regulations at the time.
Details of the possible effects of waste as well as procedures for managing, temporarily storing, disposing
of, and monitoring waste can be found in the Environmental Effects Monitoring Plan, Section 5 of this
report. Section 5.4.4.1 outlines procedures relating to the management, mitigation measures, and
monitoring for petroleum, oils, and lubricants.
4.5 Noise
During operation the turbines will create noise, largely composed of aerodynamic noise associated with
the passing of air over the rotating blades of the turbine. The noise emission from the turbines and a
description of the nearest receptors are described in Section 3.5.1. A complaints and monitoring system
will be set up as described in Section 6.3. Noise mitigation will also occur through operational
monitoring and maintenance activities, as discussed in Section 4.2, to ensure turbines are operating at
maximum efficiency.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 24 June 14, 2013
4.6 Water Taking and Stormwater Management
No water taking, sewage management, or biomass equipment processes will occur at the facility during
the operations phase of the project. The only stormwater management during the operations phase of the
project will be related to any ongoing post-construction erosion and sedimentation controls, discussed
further in the EEMP (Section 5).
5 ENVIRONMENTAL EFFECTS MONITORING PLAN
The Environmental Effects Monitoring Plan (EEMP) has been developed by M.K. Ince and Associates
Ltd. (MKI) to describe the environmental protection measures required for all activities associated with
the Skyway 126 Wind Energy project and the monitoring protocols necessary to ensure that mitigation
measures are effective and adequate. Please refer to Table 5-1 for a summary of the EEMP. This plan
should be considered a supporting document to the rest of the Design and Operations Report and fulfills
the requirements outlined by O. Reg. 359/09 under the Green Energy Act.
This plan is applicable to all employees of Cloudy Ridge Wind Park LP working on any phase of the
project and provides guidance to their contractors and subcontractors on environmentally safe standards
for project activities during construction, operation and environmental monitoring, and decommissioning.
The Skyway 126 Wind Energy project is anticipated to be operational by the end of 2014. Environmental
monitoring procedures will be implemented throughout the construction, operation and decommissioning
phases of the project.
5.1 Purpose and Objectives of the Environmental Effects Monitoring Plan (EEMP)
This Environmental Effects Monitoring Plan has been prepared to provide the required protection
measures for all project activities associated with Skyway 126 Wind Energy project.
The purpose of the Environmental Effects Monitoring Plan is to:
Ensure that Cloudy Ridge Wind Park LP’s commitments to minimizing environmental effects are
met;
Provide a description of the environmental considerations related to the construction, operation
and decommissioning of the project;
Provide concise and clear instructions for implementing mitigation measures for the protection of
environmental resources, and minimizing potential adverse environmental effects;
Provide instructions for ongoing monitoring of the efficacy of mitigation measures, and
contingency plans in the event that they fail;
Ensure that the project operations meet all provincial, federal and municipal requirements; and
Provide a reference document for planning and/or conducting construction, operation,
maintenance or decommissioning activities that may have an impact on the environment.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 25 June 14, 2013
The Environmental Effects Monitoring Plan is intended to be a supporting document of the REA
application that provides guidelines for the protection of valued ecosystem processes and components
during construction, operation, maintenance and decommissioning activities.
5.2 Roles and Responsibilities
5.2.1 Roles and Responsibilities for Implementation of the EEMP
The EEMP document will be maintained by the Project Manager and individual Plan Holders. The
responsibilities for implementation of the plan and monitoring are outlined below.
Project Manager
The Project Manager is an employee of the proponent, Cloudy Ridge Wind Park LP, who is the primary
party responsible for all aspects of the Project, including environmental, health and safety performance.
Specific environmental responsibilities of the Project Manager are as follows:
Ensure adequate plans and resources are in place to achieve minimal environmental impacts;
Ensure compliance with relevant regulations, authorizations, permits and protocols;
Review incident reports as they are submitted and advise on the proper course of action to be
taken to deal with unexpected environmental conditions or events;
Ensure ongoing communication with appropriate regulatory agencies and other interested parties
on behalf of the proponent; and
Facilitate compliance with the EEMP as outlined in this document.
Site Supervisor
Cloudy Ridge Wind Park LP will designate a Site Supervisor to oversee all operations at the site. The
responsibilities of the Site Supervisor are as follows:
Review and approve EEMP revision requests;
Conduct a review of the EEMP on as needed basis and update as required;
Ensure regulatory authorities review changes of a substantive nature;
Ensure EEMP document control and revisions;
Provide the primary contact with Project Manager, and regulatory authorities with regard to
EEMP implementation and compliance issues; and
Ensure that all construction sub-contractors are aware of and comply with all the requirements of
this document.
Construction Manager
The Construction Manager is defined as the person responsible for day to day coordination of
construction activities on behalf of the contractor retained by Cloudy Ridge Wind Park LP, hereafter
referred to as the Contractor. The responsibilities of the Construction Manager are as follows:
Familiarize themselves and their personnel with the EEMP;
Provide training for all current personnel, and future personnel arriving on the site including sub-
contractors, tradespeople, and suppliers, to introduce and explain the EEMP;
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 26 June 14, 2013
Distribute copies of the EEMP to appropriate locations and personnel;
Ensure EEMP revisions are distributed and revision control record updated;
Familiarize themselves and their personnel with the EEMP revisions;
Suggest changes to improve the quality of the EEMP to the Project Manager or Site Supervisor;
Comply with all requirements of the EEMP; and
Ensure personnel and subcontractors comply with EEMP.
In the event that this plan presents a conflict with a requirement, term or condition of relevant regulatory
acts, regulations, permits or control orders, those regulatory requirements will take precedence.
Training Requirements
The Construction Manager will advise all construction personnel (including subcontractors) of the
appropriate measures outlined in the EEMP and ensure that proper training or instruction of individuals is
provided in the following areas:
All personnel will be instructed by the Construction Manager (or designate) in the correct and
sanitary method of garbage disposal in designated disposal locations;
Hazardous materials and POLs (Petroleum, Oils and Lubricants) will be used only by personnel
who are trained and qualified in the handling of these materials, and only in accordance with
manufacturer’s instructions and government regulations. The Workplace Hazardous Materials
Information System (WHMIS) program will be implemented and all employees involved with
hazardous materials will be appropriately trained. WHMIS training is the responsibility of the
Contractor.
All workers will receive a brief environmental orientation from the Construction Manager or
his/her designate prior to initiating work at the site.
Project personnel will be trained in the use of on-site firefighting equipment (e.g. fire
extinguishers) and locations of such equipment will be known to all personnel.
Enforcement and Compliance
The Project Manager will be responsible for day-to-day field monitoring and for ensuring that the EEMP
is implemented and complied with. The Site Supervisor and Construction Manager will liaise with the
Project Manager and assist in ensuring that compliance with the EEMP and other permits is achieved. The
Site Supervisor and Construction Manager have the authority to make recommendations to improve
inadequate environmental measures, or, if need be, to make recommendations to management to have the
work, or a portion of work, suspended.
In circumstances where insufficient environmental protection results in an immediate threat to the
environment, the MOE will be notified and consulted immediately. While awaiting response, interim
measures may be implemented under the supervision of the Site Supervisor. Where danger to the
environment is not an immediate threat, the necessary remedies will be implemented within 48 hours
from receipt of notification of the circumstances. Failure to meet this requirement can result in suspension
of the work, or a portion of the work, through the issuance of an Environmental Suspension Order by the
MOE. After an Environmental Suspension Order has been issued, work may recommence when the
measures are completed to correct the noncompliance.
Specific issues/requests raised by Provincial and Federal regulatory bodies will be discussed with the
Project Manager for consideration of changes to the work, and beneficial environmental effects resulting
from the changes. Additionally, issues raised by such other bodies will be considered for future
incorporation into the EEMP.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 27 June 14, 2013
5.3 Summary Table
Table 5-1: Summary of Environmental Effects Monitoring Plan
Potential Effects
(Reference Section)
Project Phase Performance
Objectives
Mitigation Measures Monitoring Plan and
Contingency Measures
Impacts to Archaeological
Resources (Section 5.4.1.1).
A Stage 2 Archaeological
Assessment identified no
archaeological resources on site;
however, a low risk remains that
resources may be uncovered or
damaged by equipment during
construction, major maintenance
or decommissioning activities.
Construction,
Operation,
Decommissioning
Minimize impacts to
potential
archaeological
resources.
Employees will be briefed on
response procedures if artifacts
are found.
Any finds will be reported to
the MTCS and local
Aboriginal Communities;
work may stop.
Impacts to Cultural Heritage
Resources (Section 5.4.1.2)
Potential impacts to the structural
integrity of several resources were
identified in relation to vibrations
caused by construction activities.
Visual impacts to one cultural
heritage landscape (Badjeros
Union Cemetery) were identified.
Construction,
Operation,
Decommissioning
Minimize impacts to
cultural heritage
resources.
If buried electrical cabling will
be within 50 m of identified
heritage resources (including
built heritage resources and
those resources within cultural
heritage landscapes), a pre-
construction assessment will be
undertaken and vibration limits
for construction will be
established. With respect to
visual impacts, an appropriate
visual barrier will be
constructed to minimize visual
impacts on the views from the
Badjeros Union Cemetery in
consultation with the South
Line Cemetery Board and the
A professional engineer will
monitor vibration from
construction activities and
ensure limits are not
exceeded if underground
construction is to occur
within 50 m of the identified
heritage resource.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 28 June 14, 2013
Potential Effects
(Reference Section)
Project Phase Performance
Objectives
Mitigation Measures Monitoring Plan and
Contingency Measures
Municipality of Grey
Highlands.
Dust (Section 5.4.2.1)
Construction and maintenance
vehicles will potentially create
dust during project construction,
operation and decommissioning.
Construction,
Operation,
Decommissioning
Minimize air quality
impacts during
construction and
operation.
Dust suppression using sprayed
water as necessary.
Public concerns will be
addressed as outlined in
Section 6.3. Additional soil
wetting and restrictions in
speed limits will be enforced
as necessary to limit dust
emissions.
Noise (Section 5.4.2.2)
Construction equipment and
activities produce noise in a
limited nature and duration, above
the levels typical in a rural
agricultural area. Turbine
operation will produce noise,
largely composed of aerodynamic
noise. Local residents may
experience an increase in noise
levels in proximity to the turbines
during turbine operation.
Construction,
Operation,
Decommissioning
Minimize noise
impacts during
construction,
maintenance and
decommissioning.
Meet turbine setback
requirements.
Abide by municipal noise
regulations during construction.
Turbines are sited to meet
regulatory setback criteria.
Monitoring and maintenance
of construction equipment;
operational turbine noise
monitoring program
according to MOE
guidelines will be
implemented, including
public complaint response
protocol.
Vehicle Emissions (Section
5.4.2.3)
Vehicular emissions have the
potential to degrade local air
quality over a limited temporal
and spatial scale.
Construction,
Decommissioning
Minimize the
vehicular emission of
greenhouse-gases
and harmful
compounds from the
construction process.
Trips to and from the
construction site will be
minimized to the extent
possible. A traffic management
plan will be developed, as
described in Construction Plan
Report.
All construction vehicles
will be maintained in proper
working order as required.
Fires (Section 5.4.3.1)
Fires could result in terrestrial
Construction,
Operation,
To prevent fires
resulting from
project activities, and
Training for all persons on site;
fire prevention protocol will be
Emergency response plan,
including notification, fire
control, and extinguishing,
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 29 June 14, 2013
Potential Effects
(Reference Section)
Project Phase Performance
Objectives
Mitigation Measures Monitoring Plan and
Contingency Measures
habitat alteration, and wildlife
mortality. Fire-fighting chemicals
and spilled materials could enter
aquatic habitat and adversely
affect biota and habitat. Fires
could adversely affect air quality
and could pose risks to human
health and safety.
Decommissioning to safely contain,
manage and
extinguish any fires
in the Project
Location regardless
of origin.
put in place. will implemented.
Construction Danger (Section
5.4.3.2)
General risks that members of the
general public could be injured if
they were enter the site, due to the
presence of heavy machinery and
construction equipment.
Construction may present a
hazard to low flying aircraft.
Construction Minimize the risk of
injuries to the
general public during
the construction
phase and during
major maintenance.
Signage will be put in place
warning of danger; NAV
Canada will be notified of
construction.
Project employees will
monitor construction
perimeter and halt work as
necessary.
Ice Throw (Section 5.4.3.3)
Blade ice on a rotating turbine can
be thrown and present a hazard to
the public.
Operation Ensure that the
project is operated in
a manner that
minimizes the risk of
ice throw.
Turbine ice detection
technology.
Automatic shut-down of
wind turbines when ice
detected on blades. Remote
notification of icing events
for O&M staff.
Blade Failure (Section 5.4.3.4)
The turbines are at a very low risk
of experiencing blade failure
which could result in blade throw.
Operation Ensure that the
project is operated in
a manner that
minimizes the risk of
blade throw.
Turbine designed for 20-year
service life and certified for
specific wind conditions.
Site suitability analysis
conducted by the manufacturer.
Regular maintenance and
upkeep.
The SCADA system will
remotely alert turbine
operators in the event of
mechanical failures.
Notifications of emergency
personnel will be
undertaken.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 30 June 14, 2013
Potential Effects
(Reference Section)
Project Phase Performance
Objectives
Mitigation Measures Monitoring Plan and
Contingency Measures
Aeronautical Safety (Section
5.4.3.5)
The maximum height of the
turbines is 146.25 metres AGL.
As such they may present a
hazard to low-flying aircraft.
Operation Ensure that the
project is operated in
a manner that does
not pose risks to
aeronautical
navigation.
Lighting will be installed on
turbines as required by
Transport Canada.
Remote notifications of
failure of lighting; NAV
Canada will be notified as
necessary.
Shadow Flicker (Section 5.4.3.6)
Flickering frequencies between
2.5 and 20 Hz (cycles per second)
can cause annoyance (Burton et
al., 2001). The expected shadow
flicker over the course of a year is
16 hours and 24 minutes at the
most impacted receptor.
Harding et al. (2008) and Smedley
et al. (2010) report that there is a
possible risk of seizures in 1.7
people in 100,000 when they
encounter spin speeds greater than
3 Hz (60 RPM).The maximum
shadow flicker frequency is 0.75
Hz (well below the 2.5-3.0 Hz
threshold).
Shadow flicker from the Project is
not expected to cause adverse
health effects due to the low
frequency of the flicker. Nuisance
impacts are expected to be
minimal.
Operation To minimize
nuisance impacts
from shadow flicker
to the fullest extent
possible.
Turbines are sited in a location
distant from nearby receptors.
Shadow flicker study
completed to ensure shadow
flicker frequency and duration
is below acceptable levels.
Public concerns will be
addressed as they arise, as
described in Section 6.
Human Health (Section 5.4.3.7) Operation Minimize risks to Abide by all regulated setbacks. Public concerns will be
addressed as they arise, as
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 31 June 14, 2013
Potential Effects
(Reference Section)
Project Phase Performance
Objectives
Mitigation Measures Monitoring Plan and
Contingency Measures
A number of health and medical
agencies agree that when sited
properly, wind turbines are not
causally related to adverse effects.
In Ontario, properly sited means
wind turbines cannot be closer
than 550m from non-participating
receptors and cannot be louder
than 40 dBA at non-participating
receptors. No net effects from
impacts to human health are
anticipated.
human health. described in Section 6.
Electric and Magnetic Fields
(Section 5.4.3.8)
On a daily basis people around the
world are exposed to ELF EMF as
a result of using electricity. There
is no conclusive evidence of any
harm caused by exposure at levels
found in Canadian homes and
schools, including those located
just outside the boundaries of
power line corridors (Health
Canada, 2012).
Operation Minimize public
health and safety risk
due to electric and
magnetic fields.
The substation will be fenced to
restrict access to the facility.
Public concerns will be
addressed as they arise, as
described in Section 6.
Spills and Leaks (Section
5.4.4.1)
The potential exists for the
uncontrolled release of petroleum,
oils and lubricants (POLs) due to
accidental spillage or leakages.
This could lead to adverse effects
on terrestrial and aquatic habitat
Construction,
Operation,
Decommissioning
Prevent or contain all
leaks and spills from
POLs
Storage, fuelling and disposal
protocols will be followed.
Emergency spill response
will be followed; MOE
Spills Action Centre will be
called as necessary.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 32 June 14, 2013
Potential Effects
(Reference Section)
Project Phase Performance
Objectives
Mitigation Measures Monitoring Plan and
Contingency Measures
and species, on soil and
groundwater quality, and on
human health and safety.
Impacts due to Erosion and
Sedimentation (Section 5.4.4.2)
Clearing, grading, excavating and
potential soil and root compaction
during construction, major
maintenance activities and
decommissioning may increase
erosion and concomitant impacts
to nearby wetlands and water
bodies, including reduced water
quality, sedimentation, and
impacts to aquatic organisms and
habitat.
Construction,
Decommissioning
To ensure erosion
control measures
employed during
construction and
decommissioning are
effective at the time
of major works and
remain effective until
permanent
restorative measures
effectively eliminate
impacts due to
erosion and
sedimentation.
Erosion control measures will
be installed everywhere
grading, excavation, drilling,
soil stockpiling or vegetation
clearing is to occur within 120
m of water bodies, wetlands,
and woodlands.
Capture and removal of
captured sediment;
inspection for structural
integrity after major
precipitation events; post-
construction surveys;
repairs, reseeding and
replanting as required.
A post-construction erosion
control survey will be
undertaken to evaluate long-
term control measures.
Impacts to Fish and Fish
Habitat (Section 5.4.4.3)
Negative impacts to fish and fish
habitat are possible from water
crossing construction; spills and
leaks; riparian vegetation
disturbance; and
geomorphological change.
Construction To avoid any
harmful alteration,
disruption or
destruction (HADD)
of fish habitat.
Follow DFO Operational
Statements for all construction
works in or near water bodies;
where not possible, approval
from DFO will be sought on
designs.
Monitoring for frac-out
specified in DFO
Operational Statements;
monitoring of pits to ensure
lubricants are contained;
monitoring to ensure no
entry into riparian zone;
other monitoring of erosion
control measures as
specified elsewhere.
Impacts as a Result of Frac-Out
(Section 5.4.4.4)
Directional drilling (or a similar
technology such as punch and
Construction Minimise the risk of
a frac-out occurring,
and be prepared to
react appropriately to
contain the damage if
Follow DFO Operational
Statement for High-Pressure
Directional Drilling (or punch
and bore as applicable).
Follow DFO Operational
Statement for High-Pressure
Directional Drilling (or
punch and bore as
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 33 June 14, 2013
Potential Effects
(Reference Section)
Project Phase Performance
Objectives
Mitigation Measures Monitoring Plan and
Contingency Measures
bore) will be used to cross cabling
under three water courses to
minimise the impacts on these
features. A frac-out – excessive
drilling pressure resulting in
drilling mud propagating towards
the surface – can alter water
quality.
one does occur. applicable).
Impacts from Products for
Snow Removal (Section 5.4.4.5)
The excessive use of salt and sand
for site maintenance can cause
saline and sediment-laden runoff
into watercourses and may cause
blockages in drainage structures.
Operation Minimize the use of
de-icing salts and
sand.
Salt and sand use will be used
only as required after
ploughing.
None proposed.
Traffic (Section 5.4.5.1)
The effects of increased road
traffic during project construction
and decommissioning are
expected to be minor and short
lived. Nearby roads that may
experience increased traffic levels
include Highway124, and Grey
Road 9
Construction,
Decommissioning
Minimize
disturbance to local
residents from traffic
issues.
The number of trips needed to
bring equipment to site will be
minimized as much as possible.
Permits for oversized vehicles
will be obtained from the
Ministry of Transportation,
Grey County and the
Municipality of Grey Highlands
as necessary.
In the event that the
proposed transportation
routes are inconveniencing
local residents and alternate
routes are available and
practical these will be
considered.
Impacts due to Change of Land
Use (Section 5.4.5.2)
Project infrastructure will be
located entirely on agricultural
areas. Several hectares (4.8 ha) of
agricultural area will be removed
from production. Woodland or
Construction,
Operation
Minimize direct and
indirect impacts of
the land use changes.
Project infrastructure has been
located to minimize vegetation
clearing as much as possible;
amount of agricultural area
removed from production by
the project has been minimized
to the extent possible; where
Any planned works within
vegetated areas will be
clearly marked and
monitored daily to ensure
that no work occurs outside
the marked area.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 34 June 14, 2013
Potential Effects
(Reference Section)
Project Phase Performance
Objectives
Mitigation Measures Monitoring Plan and
Contingency Measures
hedgerow area is not expected to
be cleared.
possible, new roads follow
tracks previously used in
farming activities; crane pads
may be returned to agricultural
use immediately following
construction, if requested by the
landowners.
Waste (Section 5.4.5.3)
Solid waste, if not properly
controlled and disposed, can be
unsightly and cause human safety
and health concerns. Uncontrolled
hazardous waste can contaminate
soils, surface- and groundwater,
and can be toxic to local
vegetation, fish and wildlife, if
ingested in sufficient quantities.
Construction,
Operation,
Decommissioning
Minimize waste
generated on site as
much as possible.
Designated and controlled
temporary on-site storage;
waste handled in accordance
with provincial and federal
requirements; containment
facilities at least 120 m from
natural features; waste on site
will be separated for reuse and
recycling as much as possible.
Waste containers during
construction and
decommissioning will be
checked daily to ensure that
all waste is property
contained. Emergency spill
response will be followed;
MOE Spills Action Centre
will be called as necessary.
Telecommunications (Section
5.4.5.4)
Wind turbines have the potential
to interfere with radio
communication signals.
Operation Ensure siting of wind
turbines minimizes
impacts to
telecommunications
systems.
Desktop research and
consultation with relevant
stakeholders that have
infrastructure within specified
consultation zones was
undertaken to avoid or mitigate
potential effects to radio
communication systems.
Potential impacts to analog
and digital broadcast
television reception are
possible; the Proponent will
explore potential
troubleshooting in the event
of complaints.
Visual Landscape (Section
5.4.5.5)
The wind farm may have either a
positive or negative effect on the
local landscape, depending on the
observer.
Operation The wind turbines
will be visible to
local residents
however
disturbances related
to lighting of
Lighting will be designed to
ensure the minimal number of
turbines are lit according to
Transport Canada guidelines;
lights will be made to blink in
unison at night to minimize
None proposed.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 35 June 14, 2013
Potential Effects
(Reference Section)
Project Phase Performance
Objectives
Mitigation Measures Monitoring Plan and
Contingency Measures
turbines will be
minimized as much
as possible.
light pollution.
Bird Mortality (Section 5.4.6.1)
Wind turbines present a risk of
collision mortality risk to birds.
Operation Ensure bird
mortalities are kept
below MNR
requirements.
Bird studies were conducted as
part of the Natural Heritage
Assessment to reduce or avoid
project impacts. Project
infrastructure has been sited
beyond 120 m of any
significant bird habitat.
Post-construction mortality
surveys will be conducted as
per the EEMP; mitigation
measures will be considered
in consultation with the
MOE and MNR in the event
mortality surpasses MNR
thresholds.
Bird Disturbance (Section
5.4.6.2)
Breeding behaviour has the
potential to be impacted.
Avoidance of the wind farm may
result in habitat fragmentation for
some species. Effects of
construction on resident bird
species is expected to be
temporally and spatially limited,
and reversible in nature.
Construction and
Decommissioning
Minimize
behavioural
disturbance to birds.
Turbines have been sited away
from potential significant bird
habitat.
Construction activities will be
restricted to the proposed areas.
Wooded and hedgerow area is
not expected to be cleared. If
necessary, tree-clearing will be
restricted between May and
July (breeding season).
No post-construction
behavioural monitoring or
contingency plans are
proposed; if tree-clearing
during breeding season is
unavoidable then a trained
biologist will search the area
before clearing begins to
ensure that no bird nests are
present in any work areas.
Bird Habitat Loss (Section
5.4.6.3)
Clearing of vegetation will reduce
available habitat for birds.
Construction Minimize loss of
habitat and avoid
destruction of active
nests.
Wooded and hedgerow area is
not expected to be cleared. If
necessary, tree-clearing will be
restricted between May and
July (breeding season).
If tree-clearing during
breeding season is
unavoidable then a trained
biologist will search the area
before clearing begins to
ensure that no bird nests are
present in any work areas.
Bat Mortality (Section 5.4.7.1) Operation Ensure bat Bat studies were conducted as Post-construction mortality
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 36 June 14, 2013
Potential Effects
(Reference Section)
Project Phase Performance
Objectives
Mitigation Measures Monitoring Plan and
Contingency Measures
Wind turbines present a risk for
bat mortality, which may occur as
a result of direct collision or
barotrauma – internal injuries
caused by rapid pressure
reductions undetected by
echolocation.
mortalities are kept
below MNR
requirements.
part of the Natural Heritage
Assessment to reduce or avoid
project impacts. Project
infrastructure has been sited
beyond 120 m of any
significant bird habitat.
surveys will be conducted as
per the EEMP; mitigation
measures will be considered
in consultation with the
MOE and MNR in the event
mortality surpasses MNR
thresholds.
Bat Disturbance (Section
5.4.7.2)
It is possible that bats inhabit
areas of the project that were not
considered significant for
breeding or hibernating. Wind
farm construction has the
potential to affect these local
individuals.
Construction and
Decommissioning
Minimize
behavioural
disturbance to bats.
Construction activities will be
restricted to the proposed areas;
use of construction lighting will
be kept to a minimum;
aeronautical lighting will be
kept to the minimum required
by Transport Canada;
construction will not be
undertaken near the habitat
between May and July.
Pre-construction behavioural
monitoring will be
undertaken to confirm
significance of habitat. If
found significant, three years
of post-construction
behavioural monitoring will
be undertaken.
Bat Habitat Loss (Section
5.4.7.3)
Clearing of woodlands during the
construction phase may remove
potential bat habitat.
Construction Minimize the loss of
bat habitat.
Wooded and hedgerow area is
not expected to be cleared. If
necessary, cleared areas will be
minimized to the extent
possible.
No monitoring or
contingency measures are
proposed.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 37 June 14, 2013
5.4 Project Environmental Impacts
5.4.1 Archaeological and Heritage Resources
A Stage 1 and 2 Archaeological Assessment for the Skyway 126 Wind Energy project, contained within
contained within Part of Lots 54, 55, 56, 57, 58, 59, & 60 Concession 3 S.D.R (Geographic Township of
Osprey), Town of Badjeros, County of Grey, was undertaken to identify and assess archeological
resources potentially affected by the proposed project.
The Stage 1 Archaeological Assessment used literature and data reviews, including the Ontario Ministry
of Tourism, Culture and Sport (MTCS) Archaeological Sites Database, to determine that there was
potential for archaeological resources to exist on the site. The Stage 2 Archaeological Assessment
undertook field surveys and identified no archaeological resources on site. The assessments concluded
that no further study is required. The MTCS reviewed the findings and were satisfied with the
conclusions. The Archaeological Assessment Report and MTCS acceptance letter can be found in
Appendix VII. Note that since this report was produced, T6 has been removed from the project. Further,
Substation 1 (S1) and Substation (S3) have also been removed. Thus, considerations in the Assessment
regarding Lot 60 Concession 3 S.D.R. are no longer relevant to the project. This change does not affect
the conclusions of the Archaeological Assessment Report. A Cultural Heritage Assessment Report was
conducted in compliance with O.Reg 9/06 to identify and assess cultural heritage resources and
landscapes potentially affected by the proposed project. The study identified 19 built heritage resources
(BHR). Three cultural heritage landscapes (CHL) were identified. Several resources were identified as
having the potential to be impacted by sub-grade construction activities conducted within 50 m. The study
recommended the maximum acceptable vibration levels be determined for BHRs including resources
within CHLs prior to construction. It also recommended vibration levels be monitored throughout the
construction process by a qualified engineer to ensure these levels are not exceeded. These mitigation
measures will be undertaken as recommended. The study further recommended that an appropriate visual
barrier be constructed to minimize visual impacts on the views from the Badjeros Union Cemetery, in
consultation with the South Line Cemetery Board and the Municipality of Grey Highlands. Finally, as a
general recommendation, the study suggested that transportation of heavy equipment through the villages
of McIntyre and Badjeros be avoided to the extent practicable. No other negative project related impacts
were identified. The MTCS was satisfied with the conclusions. The Cultural Heritage Assessment Report
and the response from the MTCS can be found in Appendix II of the Design and Operations Report.
5.4.1.1 Impacts to Archaeological Resources
Potential Effects
Where the Stage 2 assessment identified no archaeological resources on-site, it remains possible that
archaeological resources may be uncovered during construction or might be damaged by equipment or
construction activities. The risk of such damage is considered very low since no archeological resources
were identified within the project area.
Objectives
Minimize impacts to potential archaeological resources.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 38 June 14, 2013
Mitigation Measures
The Stage 2 assessment, aimed at identifying on-site archaeological resources for development to avoid,
did not identify any resources. No additional mitigation measures are proposed at this time.
Monitoring Plan and Contingency Measures
A contingency plan and associated measures have been developed for unexpected discoveries. Project
employees will be briefed on how to respond in the event that archaeological artifacts reveal themselves
during construction. If artifacts are encountered during construction, the work in the area will cease and
the MTCS and local Aboriginal Communities will be notified immediately. In the event human remains
are uncovered, the MTCS and the Registrar or Deputy Registrar of the Cemeteries Regulation Unit of the
Ministry of Consumer and Commercial Relations will be contacted.
Net Effects
The Stage 1 and Stage 2 Archaeological Assessments did not identify any archaeological resources
contained within the Project Location. The MTCS approved the Report’s conclusion that no further
assessment was necessary. Contingency measures have been developed to deal with the unlikely
discovery of on-site archaeological artifacts. The preventative measures to date and accompanying
responsive measures serve to identify and preserve artifacts, if found. Therefore, no net effects from
impacts to archaeological features are anticipated.
5.4.1.2 Impacts to Cultural Heritage Resources
Potential Effects
According to the MTCS there are several ways in which new development can potentially impact heritage
resources. Among these potential identified impacts, wind turbines can potentially create shadows that
alter the appearance of heritage resources; change the surrounding environment or context of a heritage
site; or obstruct significant views. Vibrations associated with construction work have the potential to
negatively affect the structural integrity of the resources.
Potential impacts to the structural integrity of several resources and one cultural heritage landscape were
identified in relation to vibrations caused by construction activities.
Objectives
Minimize impacts to cultural heritage resources.
Mitigation Measures
Potential negative impacts to the structural integrity of seven properties have been identified in relation to
construction activities (269377 South Line C, BHR 5; 349427 4th Concession B Road, BHR 15; 349423
4th Concession B Road, BHR 16; 349422 4
th Concession B Road, BHR 17; 633683 Road 63, BHR 19;
Village of Badjeros Post Office, CHL 1; and McIntyre Church and Cemetery, CHL 2).
It is important to note that a number of potential BHRs have been grouped under the CHL 1. According to
the Ministry of Culture, a landscape involves a grouping(s) of individual heritage features such as
structures, spaces, archaeological sites and natural elements, which together form a significant type of
heritage form, distinctive from that of its constituent elements or parts.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 39 June 14, 2013
The mitigation measures for the BHRs and CHLs will be the same. It was recommended that any below-
grade construction of Project activities be prohibited within a 50 m buffer zone of the heritage resources.
Alternative mitigation measures include re-routing the cabling outside the 50 m buffer of the identified
resource, or building overhead cabling to minimize vibrations. In the event that this is not feasible due to
other project constraints, it was recommended that the maximum acceptable vibration levels be
determined prior to construction and monitored throughout the construction process by a qualified
engineer to ensure these levels are not exceeded.
Potential visual impacts to the Badjeros Union Cemetery have been identified in relation to project
operation. It was recommended that the proponent work with the South Line Cemetery Board and the
Municipality of Grey Highlands to install an appropriate visual barrier around the Badjeros Union
Cemetery to protect views from within the cemetery (e.g., fencing, shrubbery or trees). The Cultural
Heritage Assessment Report and the response from the MTCS are included in Appendix II.
Monitoring Plan and Contingency Measures
If below-grade construction works are to be undertaken within 50 m of the potentially impacted building,
a professional engineer will be present to ensure that maximum vibration levels are not exceeded. If levels
are exceeded work will immediately be ceased and alternate equipment or methods will be used to ensure
that the remaining works can be completed without exceeding vibration limits. If members of the public
have any concerns in this regard communication as described in Section 6.3 will be undertaken.
Net Effects
The Cultural Heritage Assessment Report was undertaken and identified construction activities have the
potential to negatively affect the structural integrity of seven properties and one cultural heritage
landscape. The mitigation measures recommended will be followed during the construction phase.
Therefore, no net effects from impacts to cultural heritage features are anticipated.
5.4.2 Air
Local air quality is presently impacted by limited vehicular emissions, and dust and noise from existing
farming operations. Additional dust, noise, and vehicular emissions during the construction process and
during project operations and decommissioning will further impact local air quality. Potential effects,
mitigation measures, and the net effects of construction, operations and decommissioning activities to this
feature are described below.
5.4.2.1 Dust
Potential Effects
Construction and maintenance vehicles will potentially create dust during project construction and
operation.
Objectives
Minimize air quality impacts during construction and operation.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 40 June 14, 2013
Mitigation Measures
Dust suppression including wetting gravel or topsoil piles, limiting vehicle speeds on gravel or dirt roads,
and project scheduling will mitigate the amount of dust created and its impact on local residents and
businesses. When required, water trucks will be hired to spray gravel and topsoil piles to suppress dust
during project construction. No on-site water will be used for dust control. Furthermore, the proponent
will monitor concerns raised by the public regarding dust.
Monitoring Plan and Contingency Measures
The proponent will monitor concerns raised by the public regarding dust and noise. Additional soil
wetting and restrictions in speed limits will be enforced as necessary to limit dust emissions.
Net Effects
Minor dust creation will likely occur in limited geographical and temporal contexts. Dust suppression
methods and project scheduling will mitigate the creation of dust and its associated impacts. Therefore, no
net effects from the impact of dust creation are anticipated.
5.4.2.2 Noise
Potential Effects
Construction equipment and activities produce noise above the levels typical in a rural agricultural area.
Nearby residents are not expected to be affected by noise during construction, maintenance and
decommissioning activities due to the limited nature and duration of these activities.
During operation the turbines will create noise, largely composed of aerodynamic noise associated with
the passing of air over the rotating blades of the turbine. Local residents may experience an increase in
noise levels in proximity to the turbines during turbine operation.
Objectives
Minimize noise impacts during construction, maintenance and decommissioning.
Ensure noise levels due to wind turbine operation are below 40 dB(A) at all noise receptors.
Mitigation Measures
To mitigate noise disturbance, all construction activities will adhere to the Municipality of Grey
Highlands noise curfew as per bylaw 2004-13. As such, construction activities involving the operation of
machinery or mechanical equipment will not be undertaken outside the hours of 7:00 a.m. to 9:00 p.m. on
any given day to minimize disruption to local residents and businesses. Turbine erection equipment may
however be operated during day and night. In cases of urgent necessity, authorization to work outside
typical hours may be sought from the Municipality.
The noise emissions from the turbines and a description of the nearest receptors are described in Section
3.5.1. Based on the number of turbines within 3 km of the noise receptors, the sound power level of those
turbines, and the setbacks of the turbines from the receptors, Section 55 of O. Reg 359/09 requires a noise
assessment be performed. An Environmental Noise Impact Assessment has been prepared for this project.
This report is included with the REA Application documents. The report concludes that all noise levels at
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 41 June 14, 2013
points of reception in the vicinity of the Skyway 126 Wind Energy are predicted to not exceed the most
restrictive MOE noise level limit of 40 dB(A).
A complaints and monitoring system for the construction phase will function as described in Section 5 of
the Construction Plan Report. Post-construction noise monitoring will ensure turbines do not exceed 40
dB(A) at any noise receptor.
Monitoring Plan and Contingency Measures
Construction equipment will be monitored for proper functioning by the operators. Any noise beyond
typical operating limits will be addressed through prompt repairs or replacement of equipment until any
problems can be remedied. Any complaints arising from the public will be dealt with promptly.
An operation-phase noise monitoring program will be established to ensure that noise levels do not
exceed acceptable limits. This monitoring program will consist of the following components:
A program which provides local residents with the means and opportunity to file a noise
complaint with the wind project operator.
An operator whose responsibility it will be to record noise complaints received and respond to
complaints within a reasonable period of time.
The exact details of any post-construction monitoring will be finalized in cooperation with the MOE.
Noise complaints received by the project proponent will be provided to the MOE. A protocol for
responding to noise and other complaints will be developed in accordance with the guidelines proposed in
Section 6.3.
Net Effects
Nearby residents are not expected to be seriously affected by noise during construction, maintenance and
decommissioning activities due to the limited nature and duration of these activities. During operation the
turbines will create noise, and local residents may experience an increase in noise levels in proximity to
the turbines during turbine operation. An operation-phase noise monitoring program according to MOE
requirements will be established to ensure that noise levels do not exceed acceptable limits. Therefore, net
effects are anticipated to be limited.
5.4.2.3 Vehicular Emissions
Potential Effects
Vehicular emissions have the potential to degrade local air quality. Emissions will occur over a limited
temporal and spatial scale.
Objectives
Minimize the vehicular emission of greenhouse-gases and harmful compounds from the construction
process.
Mitigation Measures
To minimize emissions, construction activities will occur in as efficient a manner as possible. Trips to and
from the construction site will be minimized to the extent possible. All construction vehicles will be
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 42 June 14, 2013
maintained in proper working order as required. A traffic management plan will be developed, as
described in Section 5 of the Construction Plan Report.
Net Effects
Although temporally limited, vehicular emissions may contribute to a degradation of local air quality
during construction and operational maintenance.
5.4.3 Public Health and Safety
Public Health and Safety may be affected as a result of construction and decommissioning activities and
the operation of the project. Potential effects could arise as a result of fires, construction dangers, ice
throw, blade failure, aeronautical dangers, shadow flicker, human health issues, or from electric and
magnetic fields. These impacts may occur during construction, operations and decommissioning phases.
Potential effects, mitigation measures, and the net effects of construction, operations and
decommissioning activities on Public Health and Safety are described below.
5.4.3.1 Fires
Potential Effects
Fires could result in terrestrial habitat alteration and potentially in the direct mortality of wildlife. Fire-
fighting chemicals and spilled materials could enter aquatic habitat and adversely affect biota and habitat.
Fires would also adversely affect air quality and could pose risks to human health and safety.
Objectives
To prevent fires resulting from project activities, and to safely contain, manage and extinguish any fires in
the Project Location regardless of origin.
Mitigation Measures
The following measures will be implemented to minimize the potential for causing a fire and the potential
environmental effects in the event of a fire.
Personnel Training
All persons working on the site will be trained in the use of on-site fire-fighting equipment, fire
prevention and response, including emergency services phone numbers (see Section 6) and locations of
on-site fire-fighting equipment.
Prevention:
All flammable waste will be disposed of on a regular basis.
There will be no smoking within 50 m of flammable product storage or usage. Areas for disposal
of smoking material will be clearly posted.
Fire-fighting equipment, sufficient to suit on-site fire hazards, will be maintained in proper
condition and to the manufacturer’s standards. For details on manufacturer’s specifications for
fire safety, please refer to Appendix B of the Wind Turbine Specifications Report.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 43 June 14, 2013
Monitoring Plan and Contingency Measures
Upon report of any fire the following will occur:
Notification of nearby personnel will happen immediately and will include:
o Where the fire is located,
o What happened ,
o How many people are injured (if any),
o What type of injuries occurred (if any).
Immediate steps will be taken by on-site personnel to extinguish the fire using appropriate
equipment.
Notification of the Project Manager and Site Supervisor.
In the event that the fire cannot be contained, the local Fire Department will be contacted at
9-1-1.
In case of related medical emergencies, emergency medical assistance will be requested from
9-1-1.
Relevant emergency contact information will be kept at each turbine location, as described in Section 6.
Net Effects
Activities related to the construction and operation of the project could unexpectedly result in a fire.
Preventative measures for fire safety outlined in the contingency plan are design to prevent, control,
extinguish or otherwise respond to fires in such a manner that any impacts due to fires should have no net
effects on Human Health and Safety.
5.4.3.2 Construction Danger
Potential Effects
During periods of construction there is a risk that members of the general public could be injured if they
were to come on site, due to the presence of heavy machinery and construction equipment. Construction
of wind turbines presents a hazard to low flying aircraft.
Objectives
Minimize the risk of injuries to the general public during the construction phase and during major
maintenance.
Mitigation Measures
During construction and decommissioning or during major maintenance, signage will be installed along
roads leading into the construction areas warning of the construction taking place and the associated
danger. At the perimeter of the work areas project employees will prohibit the entrance of members of
the general public into areas where construction work is underway. The Construction Manager will
ensure a clean and safe jobsite at all times. Transport Canada and NAV Canada will be advised of
construction dates in advance of construction and “notices to airmen” (NOTAMs) will be issued advising
of aeronautical obstructions.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 44 June 14, 2013
Monitoring Plan and Contingency Measures
Project employees will actively monitor the work areas to monitor for any unauthorized access. If any
members of the public enter areas where there is potential danger work will be stopped as required until
the individual is escorted from the area and it is safe to resume construction.
Net Effects
Construction equipment required on site may pose a hazard for members of the public, if any were to
enter the site. The mitigation measures are designed to prohibit the entrance of members of the general
public into areas where construction work is underway. To ensure aviation safety, relevant agencies will
be advised and NOTAMs will be issued of construction dates in advance. Therefore, no net effects from
construction dangers are anticipated.
5.4.3.3 Ice Throw
Potential Effects
During the winter months in Ontario, ice builds up on stationary structures such as transmission towers,
communications towers and buildings. Similarly, during certain conditions ice can build up on wind
turbine rotor blades. At times ice can fall from the blades to the ground. From a stationary turbine ice fall
is not a public safety concern as the ice falls within a very small distance from the turbine. From a
rotating turbine, blade ice can be thrown and can present a hazard to the public. Ice throw only presents a
hazard during the few days a year that weather conditions lend themselves to ice accretion.
Objectives
Ensure that the project is operated in a manner that minimises the risk of ice throw.
Mitigation Measures
The turbines are equipped with passive ice-shedding equipment. The turbines will monitor for weight
imbalances in the rotor or power curve anomalies and differentials between heated and unheated
anemometers. If the temperature measured by the built-in turbine meteorological equipment falls within
the range when ice build-up is possible, and any of the sensors indicate potential icing, the turbines will
automatically stop. In the event of any shut-down due to icing, a manual re-start will be required. Under
such circumstances local operations staff will ensure all ice has been shed prior to start-up.
Access roads will be signed at the entry road to the turbines to restrict entry (in accordance with
landowner wishes), warn of the potential of ice-shedding, and caution O&M personnel to remain clear of
turbines experiencing icing. The risk of ice throw affecting a non-participating residence is very low. As
the nearest non-participating landowner is located 559 m from the nearest turbine, no additional
mitigations measures are recommended for ice throw.
Monitoring Plan and Contingency Measures
Turbine operators will be informed remotely of any icing event. Standard operation will resume when
temperatures indicate ice will have melted, or other operational metrics suggest that ice is no longer
present. The decisions to restart will occur with a combination of input from remote turbine operators
monitoring telemetry and local personnel. In the event of any shut-down due to icing, a manual re-start
will be required.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 45 June 14, 2013
Net Effects
The risk of a public safety effect from ice throw is remote, but will be further reduced through appropriate
monitoring with redundant sensors, mechanical safety measures, and signage. Therefore no net effects
from the impact of ice throw are anticipated.
5.4.3.4 Blade Failure
Potential Effects
The turbines are at a very low risk of experiencing blade failure which could result in blade throw. The
study by Garrad Hassan (2007) entitled Recommendations for Risk Assessment of Ice Throw and Blade
Failure in Ontario cites recent international studies of such events which suggest blade failure events are
very rare. The main causes of blade failure include human interference with control systems, lightning
strike and manufacturing defects. The study demonstrates that the probability of blade failure and blade
loss is very low and the associated safety risks to those outside of the area immediately under the turbine
are very low.
Objectives
Ensure that the project is operated in a manner that minimises the risk of blade throw.
Mitigation Measures
Turbines and designed and certified to operate in specific wind conditions. Turbines are designed for a
20-year service life. The suitability of each project site for a given turbine model is analysed and
confirmed by the turbine manufacturer prior to installation. Regular mechanical maintenance and upkeep
will be performed as required by the manufacturer. Access roads will be signed at the entry road to the
turbines to restrict entry. The risk of blade failure affecting a non-participating residence is very low. As
the nearest non-participating landowner is located 559 m from the nearest turbine, and due to the
intermittent nature of vehicular and pedestrian traffic, no additional mitigations measures are
recommended for blade failure.
Monitoring Plan and Contingency Measures
The SCADA system will alert turbine operators in the event of any mechanical failure, including blade
failure. Notifications of emergency personnel will be undertaken as necessary.
Net Effects
Given the very low probability of blade failure and blade loss, with an appropriate maintenance schedule
no net effects from blade failure are anticipated.
5.4.3.5 Aeronautical Safety
Potential Effects
The turbines reach a maximum height of 146.25 metres from the base of the tower to the tip of the highest
blade. As such they may present a hazard to low-flying aircraft. The nearest airstrip for which records
were found in MKI’s desktop analysis is located at Collingwood Airport (CNY3), approximately 30 km
northeast of the Project Location. NAV Canada evaluated the proposed project and had no objection to
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 46 June 14, 2013
the project. Communications with NAV Canada remain open and any new information will be addressed
as it arises.
The turbines will be equipped with night-time lighting as required by Transport Canada, to ensure that the
towers are visible by aircraft at night. Lighting will be designed to ensure the minimal number of turbines
is lit according to Transport Canada guidelines (December 2011), requiring only single lighting fixtures
for use during the night. Lights will be made to blink in unison at night to minimize light pollution. Wind
farm lighting is only required every 0.9 kilometres and on boundary turbines, and lighting would be
aimed 5 degrees above the horizon. See Section 3.1.3 for details on the proposed lighting plan presented
to Transport Canada.
Objectives
Ensure that the project is operated in a manner that does not pose risks to aeronautical navigation.
Mitigation Measures
Lighting on Skyway 126 Wind Energy project turbines will comply with Transport Canada regulations.
Monitoring Plan and Contingency Measures
The SCADA system will monitor the status of lighting systems and alert operators in the event of
aeronautical lighting failure. In the event of lighting failure for any reason, NAV Canada will be alerted
and NOTAMs will be issued to ensure continued aeronautical safety.
Net Effects
As lighting and safety features will be in compliance with Transport Canada regulations, no net effects
from impacts to aeronautical safety are anticipated.
5.4.3.6 Shadow Flicker
Potential Effects
As described in the Shadow Flicker Report (see Appendix III), shadow flicker occurs when the blades
from a wind turbine pass between an observer and the sun. As a wind turbine rotates, the shadow cast by
the blades can cause a “flicker” for an observer. Research indicates that flickering frequencies between
2.5 and 20 Hz (cycles per second) can cause annoyance and may even trigger epileptic problems for a
certain portion of the population (Burton et al., 2001). Harding et al. (2008) and Smedley et al. (2010)
report that there is a possible risk of seizures in 1.7 people in 100,000 when they encounter spin speeds
greater than 3 Hz (60 RPM).
The purpose of the Shadow Flicker Report was to model and analyze expected shadow flicker for 116
residences and vacant lots in the Project Location. Results of the study suggest that:
The maximum worst-case annual SF for any residence is 56 hours 42 minutes, over the course of
127 days.
The anticipated annual SF for the most impacted non-participating residence is 16 hours 24
minutes.
The worst case maximum SF in one day for any residence is 51 minutes
The worst case maximum annual SF days for any residence is 127 days.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 47 June 14, 2013
The maximum shadow flicker frequency is 0.75 Hz (which is the maximum rotation speed of the
proposed turbines and well below the 2.5 to 3.0 Hz threshold).
As such, shadow flicker from the Project is not expected to cause adverse health effects due to the low
frequency of the flicker.
Objectives
To minimize health and nuisance impacts from shadow flicker to the fullest extent possible.
Mitigation Measures
Based on the spin rates of the turbines proposed for this project, it is expected that no health effects will
require monitoring or contingency measures.
Monitoring and Contingency Measures
If residents have concerns about shadow flicker and nuisance they can contact the proponent through the
complaint resolution protocol described in Section 6.3. Additional contingency measures to address
concerns may include installation of curtains or planting of trees to screen shadows.
Net Effects
Shadow flicker from the Project is not expected to cause adverse health effects due to the low frequency
of the flicker. Nuisance impacts are expected to be minimal. Nevertheless, contingency measures are
available if negative impacts are confirmed. Therefore no net effects are anticipated.
5.4.3.7 Human Health
Potential Effects
Wind power has been harnessed as a source of power around the world. Debate is ongoing with respect to
the relationship between reported health effects and wind turbines, specifically in terms of audible and
inaudible noise. As a result, minimum setback distances have been established world-wide to reduce or
avoid potential complaints from, or potential effects to, people living in proximity to wind turbines
(Knopper and Ollson 2011).
Many studies have been conducted world-wide to examine the relationship between wind turbines and
possible human health effects (e.g., audible/inaudible noise, shadow flicker, electromagnetic fields
(EMF)). A number of health and medical agencies agree that when sited properly, wind turbines are not
causally related to adverse effects (e.g., Chatham-Kent Public Health Unit, 2008; Australian Government,
National Health and Medical Research Council, 2010; Ontario CMOH, 2010; Australian Government,
2011; Massachusetts Department of Environmental Protection (MassDEP) and Massachusetts Department
of Public Health (MDPH), 2012). In Ontario, properly sited means wind turbines cannot be closer than
550m from non-participating receptors and cannot be louder than 40 dBA at non-participating receptors.
Objective
Minimize risks to human health.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 48 June 14, 2013
Mitigation Measures
The Project is fully in compliance with the maximum noise level (40 dBA) from any non-participating
residence and vacant lot as required by the Ontario Ministry of Environment.
Monitoring and Contingency Measures
Residents with concerns about health effects can contact the proponent through the complaint resolution
protocol described in Section 6.3. More specifically, an operation-phase noise monitoring program will
be established to ensure that noise levels do not exceed acceptable limits, as detailed in Section 5.4.2.2.
Science and medical experts around the world will continue to publish findings in this field. The
proponent is committed to keeping informed on the issue of human health.
Net Effects
No net effects from impacts to human health from the project are anticipated.
5.4.3.8 Electric and Magnetic Fields
Power frequency or extremely low frequency (ELF) electric and magnetic fields (EMF) are invisible lines
of force that you cannot see or feel that surround electrical equipment, power cords, wires that carry
electricity and outdoor power lines. On a daily basis people around the world are exposed to ELF EMF as
a result of using electricity. Power frequency or ELF EMF can come from a number of Project related
components, including transformers (installed either adjacent to or within the base of each turbine tower),
the project substation, the collector lines and existing Hydro One distribution grid.
The relationship between ELF EMF and possible human health is well studied (e.g., NIEHS 2002, WHO
2007). Health Canada (2012) has stated:
“Health Canada does not consider that any precautionary measures are needed regarding
daily exposures to EMFs at ELFs. There is no conclusive evidence of any harm caused by
exposures at levels found in Canadian homes and schools, including those located just
outside the boundaries of power line corridors”.
Potential Effects
Health Canada (2012) has stated:
“There is no conclusive evidence of any harm caused by exposures at levels found in
Canadian homes and schools, including those located just outside the boundaries of power
line corridors”.
Objective
Minimize risks to human health.
Mitigation Measures
The substation will be fenced to restrict access to the facility and typical EMF beyond the fences and
walls built to enclose transformer stations are likely indistinguishable from background levels. The level
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 49 June 14, 2013
of EMF from the substation and nacelles are negligible as it relates to public health compared to daily
exposure levels.
Monitoring and Contingency
Residents with concerns about EMF can contact the proponent through the complaint resolution protocol
described in Section 6.3.
Net Effects
Based on currently-available information, electro-magnetic fields and interference from project related
components are not considered a health concern, and no net effects on human health and safety are
anticipated.
5.4.4 Water Bodies
A Water Bodies Assessment was undertaken to identify water bodies that exist within 120 m of proposed
project infrastructure. The report identified nine water bodies within the defined area and reported that
three water crossings on Road 63 and 4th Concession B Road will be necessary using High Density
Directional Drilling (HPDD) or similar technology. Potential impacts to these water bodies include spills
of chemicals or hazardous materials, erosion and sedimentation, and frac-out during directional drilling,
as well as impacts from salt from snow clearing during operation.
5.4.4.1 Spills and Leaks
Potential Effects
The potential exists for the uncontrolled release of petroleum, oils and lubricants (POLs) due to accidental
spillage or leakages. This could lead to adverse effects on terrestrial and aquatic habitat and species, on
soil and groundwater quality, and on human health and safety.
Objectives
Prevent or contain all leaks and spills from POLs during construction, operation or decommissioning.
Mitigation Measures
The following protection measures are intended to minimize the potential for any petroleum, oil and
lubricants (POLs) spills on soil, vegetation, surface water, and groundwater.
Storage and disposal of POLs:
The transportation of POLs will be conducted in compliance with the Transportation of
Dangerous Goods Act.
There will be no permanent on-site storage of POLs for fueling or vehicle maintenance purposes,
with the exception of small double-walled CSA approved fuel tanks for refuelling equipment and
machinery during the construction period.
Where possible, vehicle maintenance will be performed off site, at a nearby commercial fuelling
station, in order to minimize the amount of lubricants and oils stored on site.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 50 June 14, 2013
POLs will be stored in compliance with applicable provincial and federal regulations, codes and
guidelines. During maintenance, POLs will be stored within the base of the tower for the duration
of each visit and as such will be well-removed from any water bodies or wetlands. Upon
completion of turbine maintenance activities, all POLs will be removed from the site.
On-site POL storage will be in a ventilated, lockable steel container. The container will be
equipped with galvanized steel drip trays for the collection of spilled substances.
The on-site POL storage container shall be located on level terrain, at least 120 m from any water
body, watercourse or wetland.
Spill decks will be used for transferring products to smaller containers.
Fire extinguishers will be located near POL storage areas.
A spill kit, including absorbent material, will either be stored in the base of the tower or will be
brought to the site during maintenance visits.
POL storage areas will be identified by signs.
Smoking will not be permitted within 50 m of any POL storage area. “No Smoking” signs will be
displayed at all POL storage sites and refuelling areas. On-site signage will indicate the location
of smoking areas.
Equipment Fuelling:
Only equipment that is not easily transported will be refueled on site. All other vehicles and equipment
will be refueled at a commercial fuelling station.
When refuelling equipment, operators will:
o use designated fuelling locations;
o use drip trays;
o use leak free containers and reinforced rip and puncture proof hoses and nozzles;
o be in attendance for the duration of the procedure; and
o seal all storage container outlets except the outlet currently in use.
Fuelling must be done at least 120 m from a wetland, water body or watercourse.
The Contractor will make daily inspections of hydraulic and fuel systems on machinery and leaks
will be repaired immediately. All leaks will be reported to the MOE, Spills Action Centre at
1-800-268-6060.
Servicing of equipment will not be allowed within 120 m of a wetland, watercourse or water
body.
Fuelling attendants will be trained in the requirements under the contingency response plan
below.
POL Waste Disposal
Waste POLs will be stored in a ventilated, lockable steel container. The container will be
equipped with galvanized steel drip trays for the collection of spilled substances.
Waste solvents and oils will be stored separately.
All used oil and petroleum products will be removed as required and disposed in an acceptable
manner in accordance with government regulations, and requirements, including but not limited
to O. Reg 347/09 S. 17.2. Waste oil will be collected separately and offered for recycling or
stored for collection by an appropriate special waste collection and disposal company.
Greasy or oily rags or materials subject to spontaneous combustion will be deposited, and kept, in
an appropriate receptacle. This material will be removed from the work site on a regular basis and
will be disposed in an approved existing waste disposal facility.
POL waste disposal will be the responsibility of the Contractor.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 51 June 14, 2013
Servicing and Inspections
Regular scheduled inspections of oil and hydraulic systems will be made during the semi-annual
maintenance visits. Any leaks found will be repaired immediately. All leaks will be reported to
the Ontario Ministry of Environment, Spills Action Centre at 1-800-268-6060. As turbine
systems will be monitored remotely by cell phone or satellite communication, technicians will
determine when additional unscheduled inspections are required. These are typically performed
every 2 to 3 months at each turbine.
Equipment will not be serviced within 120 m of a wetland, watercourse, water body, or seepage
area.
Emergency Response
Even with the implementation of the above mitigation measures, there is a possibility of accidents
resulting in the release of hazardous materials into the environment. In the event that a spill occurs, action
will be taken as outlined in the contingency measures below.
Monitoring Plan and Contingency Measures
If it is safe to do so, the individual who discovers the leak or spill will immediately attempt to stop and
contain the leak or spill.
Any spill or leak must be reported immediately to the Construction or Operations Manager.
The Construction or Operations Manager will immediately report the spill to the Ontario Ministry of
Environment, Spills Action Centre which can be reached at 1-800-268-6060. A Spill Report Form
(provided in Appendix VI) shall be filled out and will include:
A description of the source, including the name of the owner or operator;
The nature, extent, duration and environmental impact of the release;
The cause or suspected cause of the release; and
Any remedial action taken or to be taken to prevent a recurrence of the leak or spill.
The site Contractor will have the full authority to take appropriate action without unnecessary delay. The
Spill Report Form in will be filled out by the Contractor immediately following the discovery of the spill
or leak and forwarded to the Project Manager.
The Contractor will assume the overall responsibility for coordinating the clean-up and maintaining this
contingency plan current and up-to-date. The Contractor will, in consultation with the regulatory
authorities (if warranted):
Deploy on-site personnel to contain the spilled material using a dyke, pit, or absorbent material;
Assess site conditions and environmental impact of various cleanup procedures;
Choose and implement an appropriate cleanup procedure;
Deploy on-site personnel to mobilize pumps and empty drums (or other appropriate storage) to
the spill site;
Dispose of all contaminated debris, cleaning materials, and absorbents by placing in an approved
disposal site.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 52 June 14, 2013
Spill Cleanup Resource List:
Throughout the operational life of the project, the following resources will be available at an appropriate
location in readiness to respond to accidental releases of fuels and/or hazardous materials:
Absorbent materials (e.g. sorbent pads, Sorb-All, peat moss).
Small equipment such as shovels, rakes, tool kit, sledgehammer, buckets, stakes, tarpaulins, one
empty drum, and protective equipment.
Section 6 of this report contains the contact list for spill response.
Net Effects
Various measures are in place to prevent or contain all leaks and spills from POLs during construction,
operation and decommissioning. The preventative measures are designed for safe storage, use, and waste
disposal of petroleum, oils, and lubricants. Furthermore, mitigation measures through the development of
an emergency response plan will serve to immediately control spills and leaks. No net effects are
anticipated from spills and leaks
5.4.4.2 Impacts due to Erosion and Sedimentation
Potential Effects
Due to the clearing, grading, excavating and potential soil and root compaction during construction, major
maintenance activities and decommissioning, stormwater patterns may change throughout the life of the
project. These changes may increase erosion and concomitant impacts to nearby wetlands and water
bodies, including reduced water quality, sedimentation, and impacts to aquatic organisms and habitat.
Three water crossings by HPDD or a similar technology such as punch and bore will be constructed. The
construction works associated with these crossings have the potential to further contribute to the potential
effects. Impacts specific to the crossings are further discussed in Section 5.4.4.3 and 5.4.4.4.
Objectives
To ensure erosion control measures employed during construction and decommissioning are effective at
the time of major works and remain effective until permanent restorative measures effectively eliminate
impacts due to erosion and sedimentation.
Mitigation Measures
Where grading, excavation, drilling, soil stockpiling or vegetation clearing is to occur within 120 m of
water bodies, siltation fences will be installed in order to prevent movement of sediment toward water
bodies. Where necessary, ditches and catchment areas will be established to supplement the siltation
fences. These ditches will be routed away from nearby water bodies and terminate in locations such that
no sediment will be able to enter water bodies. Areas with temporarily cleared vegetation will have native
plants replanted to permanently effect erosion control. Temporarily stockpiled soil will also be
surrounded with silt fencing in order to further prevent erosion. Upon the completion of backfilling and
the subsequent disposition of excess soil elsewhere within the properties by the property owners (outside
of 120 m from the water bodies), replanting with native vegetation will be undertaken in areas that are not
going to be used for agricultural purposes. For excavation within municipal road easements, following
backfilling reconditioning of the surface will be undertaken in consultation with the municipality; gravel,
asphalt or native plants and grasses will be used as appropriate.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 53 June 14, 2013
Further risk and mitigation measures related to water crossings by cabling are discussed in Section
5.4.4.3 and Section 5.4.4.4.
Monitoring Plan and Contingency Measures
Sediment captured through the use of siltation fences and ditches, where necessary, will be captured and
transported by truck 120 m away from aquatic features. During construction silt fences will be inspected
after major precipitation events. Damaged sediment control features will be immediately repaired.
One year after construction a survey will be undertaken to ensure that long-term erosion control measures
have been effective. This will include an inspection of drainage facilities such as ditches, culverts and
water retention areas for structural integrity and any excessive amount of silt collection. Seeded or
replanted areas will be inspected to ensure that re-vegetation measures were successful and re-seeding or
replanting will occur where necessary.
If erosion control measures are found to be less than fully effective during this survey, reseeding or
replanting of problem areas will take place. Should there be residual effects noted during post-
construction monitoring, advice on contingency measures will be sought out and applied.
Net Effects
Short-term (e.g. silt fencing, catchment areas, and geotextiles) and long-term mitigation measures (e.g.
surveying, replanting of native vegetation) are expected to fully mitigate sedimentation and erosion
generated through the construction process. Therefore, no net effects from erosion and sedimentation are
anticipated.
5.4.4.3 Impacts to Fish and Fish Habitat
Potential Effects
Impacts to fish and fish habitat are possible from the activities associated with the construction of water
crossings by cabling. Fish and fish habitat have the potential to be harmed by spills and leaks, and erosion
and sedimentation, or as a result of various construction activities, as discussed in Section 5.4.4.1 and
Section 5.4.4.2. Additional potential impacts specific to the construction of water crossings include
disturbance to riparian vegetation and disturbance of the banks and streambed during the construction
process, all of which could result in disturbance or damage to fish or fish habitat.
Objectives
To avoid any harmful alteration, disruption or destruction (HADD) of fish habitat.
Mitigation Measures
Where cabling will cross under water bodies by way of directional drilling, the Department of Fisheries
and Oceans (DFO) Operational Statement for High-Pressure Directional Drilling (HPDD) will be
followed. In the unlikely event that this Operational Statement is not able to be used, approval from the
DFO will be sought on alternative design processes. In the event that a different technology is used, such
as punch and bore, the applicable operational statement will be followed. Measures to be implemented are
described below. The measures listed below are numbered identically to the HPDD Operational
Statement; please refer to the Operational Statement for a comparison between the DFO recommended
measures and how the measures are being implemented as shown below.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 54 June 14, 2013
1. Existing trails or roads will be used wherever possible as access routes to avoid disturbance to the
riparian vegetation.
2. The drill path will be designed to an appropriate depth below the watercourse to minimize the risk of
frac-out and to a depth to prevent the line from becoming exposed due to natural scouring of the
stream bed. The drill entry and exit points are far enough from the banks of the watercourse to have
minimal impact on these areas. Please see Section 5.4.4.4 for further discussion of impacts from
frac-out and proposed mitigation, monitoring and contingency measures.
3. No riparian vegetation will be removed for cabling water crossings.
4. No machinery will ford watercourses.
5. Machinery will be operated on land above the ordinary high water mark and in a manner that
minimizes disturbance to the banks of the watercourse.
i) Machinery is to arrive on site in a clean condition and is to be maintained free of fluid leaks.
ii) Machinery will be washed, refueled and serviced and fuel and other materials for the
machinery will be stored away from the water to prevent any deleterious substance from
entering the water.
iii) Emergency spill kits will be kept with equipment in case of fluid leaks or spills from
machinery.
iv) Banks will be restored to original condition if any disturbance occurs.
6. A dugout/settling basin will be constructed at the drilling entry/exit site to contain drilling mud to
prevent sediment and other deleterious substances from entering the watercourse. The drilling mud
will be reclaimed and will not enter any water body.
7. The watercourse will be monitored to observe signs of surface migration (frac-out) of drilling mud
during all phases of construction.
Monitoring Plan and Contingency Measures
During HPDD the stream bed will be continually monitored for signs of frac-out. Please see Section
5.4.4.4 for further details on mitigation, monitoring and contingency measures for frac-out.
Operators will monitor the pits at the terminals of the drilling to ensure all drilling lubricants are
contained. In the event that drilling lubricant escapes the pits, drilling will be halted and the liquid
contained and removed. The pits will be emptied as necessary with the liquid reclaimed by the drilling
contractor as appropriate. Drilling will resume only once it is clear no further spills of drilling lubricant
will occur.
Net Effects
The Water Bodies Assessment Report identified that seven water bodies within the Project Location is
supportive of fish or fish habitat (WA02, WA03, WA05-09). The water crossing for cabling where Road
63 crosses WA01, and where 4th Concession B Road crosses WA05 and WA06 will be constructed using
HPDD, or a similar technique such as punch and bore. By following the relevant DFO Operational
Statement no net effects to fish and fish habitat are anticipated
5.4.4.4 Impacts as a Result of Frac-Out
Potential Effects
Directional drilling (or a similar technology such as punch and bore) will be used to cross cabling under
water bodies to minimise the impacts on these features. However there is a possibility that frac-outs can
occur. A frac-out is when excessive drilling pressure results in drilling mud propagating towards the
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 55 June 14, 2013
surface. The effects of frac-out include the alteration of water quality, largely through increases in
turbidity and changes in water chemistry.
Objectives
Minimize the risk of a frac-out occurring, and be prepared to react appropriately to contain the damage if
one does occur.
Mitigation Measures
Mitigation measures to avoid frac-out, and ensure preparedness in the event of a frac-out, follow the DFO
Operational Statement for HPDD (In the event that a similar technology such as punch and bore is used,
the applicable operational statement will be followed). The drill path will be designed to an appropriate
depth (approximately 1 m) below the watercourse to minimize the risk of frac-out and to a depth to
prevent the line from becoming exposed due to natural scouring of the stream bed. The drill entry and exit
points will be located at an appropriate distance from the banks of the watercourse to minimize
geomorphological impacts.
Monitoring Plan and Contingency Measures
During HPDD (or punch and bore as applicable) the stream bed will be continually monitored for signs of
frac-out. Material and equipment needed to contain and clean up drilling mud releases on site will be
kept readily accessible in the event of a frac-out. A frac-out response plan will be prepared by the drilling
contractor and in the event of frac-out will be implemented. In this event, work will immediately be
halted, and the drilling mud contained to prevent its further migration into the watercourse. All applicable
authorities will be notified, including the closest DFO office in the area. Clean-up activities will be
prioritized relative to the risk of potential harm. Drilling mud within the pits will be immediately pumped
out by the contractor so no further mud enters the watercourse.
Should frac-out be experienced, an alternate drilling location will be attempted, with the course adjusted
suitably to further ensure the integrity of the stream bed during the drill. An additional metre below the
surface (for a total of at least 2 m below the stream bed) will be planned. Further, an offset of several
metres up or downstream as appropriate will be selected as the new drilling location. Consultation with
the DFO will be undertaken as necessary prior to the repetition of the drill. Equipment will be double-
checked to ensure proper functioning prior to commencing the drill. For the repetition of the drill all
above mitigation and monitoring procedures will again be followed.
Monitoring and contingency measures to be implemented if a frac-out occurs despite these mitigation
measures are included in the EEMP included within the Design and Operations Report.
Net Effects
Where cabling will cross under water bodies by way of directional drilling, the Department of Fisheries
and Oceans (DFO) Operational Statement for High-Pressure Directional Drilling (HPDD) will be
followed. During HPDD the stream bed will be continually monitored for signs of frac-out, and an
immediate response plan will be followed in case of frac-out occurring. As a result of these measures, no
net effects from the impacts of frac-out are anticipated.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 56 June 14, 2013
5.4.4.5 Impacts from Products for Snow Removal
Potential Effects
Snow removal and application of sand and/or salt will be required during the winter months to maintain
safe conditions for maintenance activities. Excessive salt use can cause saline runoff into watercourses.
Excessive sand use can contribute to sediment-laden runoff into watercourses and may cause blockages in
drainage structures.
Objectives
Minimize the use of de-icing salts and sand.
Mitigation Measures
The following protection measures will be implemented to minimize the potential environmental effects
of snow removal, sanding and de-icing.
A professional service provider will be used for snow and ice removal on roads. The contractor
will follow the Best Management Practices as described in Environment Canada’s Best
Management Practices for Salt Use on Private Roads, Parking Lots and Sidewalks.
The use of sand, salt and combinations thereof, will be minimized to that which is necessary to
ensure the safety of the maintenance staff. Sand application will be the primary means of
maintaining safe driving conditions. Salt will only be used as necessary.
Prior to salt application, as much snow as possible will be removed from the road through
ploughing.
Salt application will be targeted to areas requiring treatment in order to minimize the volume of
salt used and the amount of salt lost to adjacent areas.
Snow removed from access roads and site surfaces will not be dumped within the 120m of a
wetland, water body, or other environmentally sensitive area.
Monitoring Plan and Contingency Measures
No monitoring or contingency measures are proposed.
Net Effects
No net effects from the impacts of product for snow removal are anticipated.
5.4.5 Land Use
Project activities, from site preparation to transportation to infrastructure assembly, through operation and
decommissioning, have the potential to affect ecological, social, and economic land use patterns. Land
use change is traditionally understood in reference to the removal of agricultural land from production, or
installing infrastructure on lands designated for natural protection. The concept of land use change in the
present document also includes consideration of the socio-economic uses of forested land, such as timber
or firewood harvesting. Potential impacts on land use include increased traffic congestion, removal of
vegetative and agricultural lands, waste generation, as well as impacts on telecommunications and the
visual environment.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 57 June 14, 2013
5.4.5.1 Traffic
Potential Effects
Increased traffic can be expected on routes near the project area during construction and decommissioning
of the wind farm. Some trucks used will be oversized to bring turbine equipment to the site. This has the
potential to cause traffic delays. Construction equipment and vehicles that may be used on site have been
detailed in the Construction Plan Report. The effects of increased road traffic are expected to be minor
and short lived. Nearby roads that may experience increased traffic levels include Highway 124, and Grey
Road 9.
Objectives
Minimize disturbance to local residents from traffic issues.
Mitigation Measures
The number of trips needed to bring equipment to site will be minimized as much as possible. Permits for
oversized vehicles will be obtained from the Ministry of Transportation, County of Grey, and
Municipality of Grey Highlands as necessary. Traffic control plans, road user agreements, and other
municipal agreements will be developed, acquired, and implemented to minimize impact on public roads
after REA submission.
Monitoring Plan and Contingency Measures
Nearby residents with concerns about traffic impacts can contact the proponent as described in Section
6.3. In the event that the proposed transportation routes are inconveniencing local residents and alternate
routes are available and practical these will be considered as a contingency measure.
Net Effects
Increased traffic can be expected on routes near the project area. Although the number of trips needed to
bring equipment to site will be minimized through the development of a traffic management plan, traffic
congestion for limited time periods may occur along stretches of some roads (e.g. during transportation of
tower and turbines). No net effects are anticipated.
5.4.5.2 Removal of Agricultural Land and Vegetation Clearing
Potential Effects
Construction of project infrastructure will require clearing of vegetation within the Project Location and
removal of 4.8 hectares of agricultural land from production. Project infrastructure will be located almost
entirely on agricultural areas. No woodland or hedgerow area is expected to be cleared. Objectives
Minimize direct and indirect impacts of the land use changes.
Mitigation Measures
All lands which can be restored post-construction (e.g. construction pad areas) may be restored, thus
minimizing the longer-term impact of vegetation removal. On decommissioning of the project, all project
lands will be returned to their prior condition as nearly as possible.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 58 June 14, 2013
The amount of agricultural land removed from production by the project has been minimized to the extent
possible. Where possible, new roads follow tracks previously used in farming activities. If requested by
the landowner, crane pads will be returned to agricultural use immediately following construction, or they
will be removed as part of the process of project decommissioning.
Monitoring Plan and Contingency Measures
Any planned works within vegetated areas will be clearly marked and monitored daily to ensure that no
work occurs outside the marked area. The return of the crane pad areas to agricultural use, whether
immediately following construction or at project decommissioning, will be undertaken in cooperation
with the land owner, and any concerns regarding land use changes will be addressed through the process.
Net Effects
Temporary changes to land usage patterns during construction and operation will be short-term, and
should have no permanent effects. Cleared areas will be minimized, and re-vegetated at the earliest
opportunity where necessary. Upon decommissioning all project lands will be returned to their original
condition as nearly as possible. No long-term net effects from changes in land use are anticipated.
5.4.5.3 Waste
Potential Effects
Solid waste, if not properly controlled and disposed, can be unsightly and cause human safety and health
concerns. Uncontrolled hazardous waste can contaminate soils, surface- and groundwater, and can be
toxic to local vegetation, fish and wildlife, if ingested in sufficient quantities.
Objectives
Minimize waste generated on site as much as possible.
Mitigation Measures
Waste on site will be separated for reuse and recycling as much as possible. The construction contractor
will ensure the safe disposal of any waste materials.
Additionally, the following protection measures will minimize the potential environmental effects of solid
waste disposal:
The Contractor will designate and use areas for the transfer and limited temporary storage of
hazardous materials and special wastes. These sites will be properly labeled and appropriately
controlled, and will be located a minimum of 120 m from a wetland, water body, or other
environmentally sensitive area.
All waste will be handled in accordance with relevant provincial and federal requirements,
including but not limited to O Reg 347/09 S. 17.2.
Waste material will not be dumped on-site.
Waste and debris will be prevented from entering any water bodies, wetlands, watercourses or
other environmentally sensitive area. This shall include at a minimum proper waste management
and containment facilities at least 120 m from a wetland or water body.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 59 June 14, 2013
Waste disposal and storage facilities and areas will be properly protected from the elements in
accordance with all applicable legislation and regulation such that run-off will not form nor enter
any watercourses, water bodies or wetlands.
Materials will be reused and recycled as much as possible. Waste will be disposed of safely at an
appropriate disposal location.
Waste generation specific to construction and decommissioning is discussed in greater detail in the
Construction Plan Report and the Decommissioning Plan Report.
Monitoring Plan and Contingency Measures
Waste containers during construction and decommissioning will be checked daily to ensure that all waste
is property contained. In the event of a spill, the individual who discovers the leak or spill will
immediately attempt to stop and contain the leak or spill. Any spill or leak must be reported immediately
to the Construction or Operations Manager.
The Construction or Operations Manager will immediately report the spill to the Ontario Ministry of
Environment, Spills Action Centre which can be reached at 1-800-268-6060. A Spill Report Form
(provided in Appendix VI) shall be filled out and will include:
A description of the source, including the name of the owner or operator;
The nature, extent, duration and environmental impact of the release;
The cause or suspected cause of the release; and
Any remedial action taken or to be taken to prevent a recurrence of the leak or spill.
The site Contractor will have the full authority to take appropriate action without unnecessary delay. The
Spill Report Form in will be filled out by the Contractor immediately following the discovery of the spill
or leak and forwarded to the Project Manager.
The Contractor will assume the overall responsibility for coordinating the clean-up and maintaining this
contingency plan current and up-to-date. The Contractor will, in consultation with the regulatory
authorities (if warranted):
Deploy on-site personnel to contain the spilled material using a dyke, pit, or absorbent material;
Assess site conditions and environmental impact of various cleanup procedures;
Choose and implement an appropriate cleanup procedure;
Deploy on-site personnel to mobilize pumps and empty drums (or other appropriate storage) to
the spill site;
Dispose of all contaminated debris, cleaning materials, and absorbents by placing in an approved
disposal site.
Spill Cleanup Resource List:
Throughout the operational life of the project, the following resources will be available at an appropriate
location in readiness to respond to accidental releases of fuels and/or hazardous materials:
Absorbent materials (e.g. sorbent pads, Sorb-All, peat moss).
Small equipment such as shovels, rakes, tool kit, sledgehammer, buckets, stakes, tarpaulins, one
empty drum, and protective equipment.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 60 June 14, 2013
Net Effects
No net effects from the impact of waste are anticipated.
5.4.5.4 Telecommunications
Potential Effects
The tower and blades of wind turbines can interfere with radio communication as described in the Radar
and Radio Communications Impact Report detailed in Appendix IV.
Objectives
Ensure siting of wind turbines to minimize impacts to telecommunications systems.
Mitigation Measures
Industry Canada’s Spectrum database was searched for radiocommunication systems near the Project
Location. Rogers Communications Partnership and Bayshore Broadcasting Corporation were identified as
operators of communications infrastructure within the consultation zones recommended by the Radio
Advisory Board of Canada and the Canadian Wind Energy Association. These parties have been
contacted and informed of the proposed turbine locations to determine whether any concerns arise with
respect to the Skyway 126 Wind Energy project. Early in discussions, Rogers identified potential impacts
to its operations; however, the turbine locations were adjusted in consultation with Rogers to mitigate
these impacts. Bayshore Broadcasting Corporation has indicated that it has no concerns. A complete list
of correspondence with public agencies is provided in Appendix B of the Radar and Radio
Communications Impact Report.
The potential exists for impacts to households with satellite or over-the-air television systems and these
impacts will be confirmed and resolved should any concerns arise. Further details are included in the
Radar and Radio Communications Impact Report found in Appendix IV.
Monitoring Plan and Contingency Measures
Potential impacts to analog and digital broadcast television reception are possible and if so will be
mitigated. For instance, if nearby residents experience degraded reception the project proponents will
examine and troubleshoot the issues to ensure adequate reception is restored. Net Effects
If any impacts to television reception are identified they will be mitigated by the proponent. No net effects
on telecommunications are anticipated to result from the project.
5.4.5.5 Visual Landscape
Potential Effects
The wind farm will be a visible feature within the local landscape. Depending on the observer, the
turbines will have either a positive or negative effect on the local landscape.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 61 June 14, 2013
Objectives
The wind turbines will be visible to local residents; however, disturbances related to lighting of turbines
will be minimized as much as possible.
Mitigation Measures
Lighting will be designed to ensure the minimal number of turbines is lit according to Transport Canada
guidelines (December 2011), requiring only single lighting fixtures for use during the night. Lights will
be made to blink in unison at night to minimize light pollution.
Monitoring Plan and Contingency Measures
No monitoring or contingency is proposed.
Net Effects
The project will have an effect on the local landscape until decommissioning. Effects from lighting will
be minimized where possible. Upon decommissioning, the project area will be restored. No long-term net
effects are anticipated.
5.4.6 Birds
No significant bird habitats were identified within the Project Location, as determined through an
extensive natural heritage assessment. However, it is likely that birds inhabit areas of the project that were
not considered significant but these areas will have fewer species, fewer individuals and/or more common
species. Specific areas of inhabitation may include those delineated as generalized significant wildlife
habitat. This section discusses potential impacts to the general bird population of the area from
construction, operation and decommissioning activities.
In addition to the natural heritage reporting requirements under O. Reg. 359/09, the Skyway 126 Wind
Energy project will be in compliance with the requirements under the Endangered Species Act (2007) as
outlined in the Ministry of Natural Resources’ (MNR) Approvals and Permitting Requirements
Document. Details pertaining to Species at Risk are not described within this report.
5.4.6.1 Bird Mortality
Potential Effects
Although it is expected that many resident birds will become habituated to the wind turbines, the turbines
do present a mortality risk to birds. Breeding and courtship behaviour of some birds may result in
collision with the turbines during the operation of the wind farm. Collision mortality also may occur
during spring and fall migration, particularly during take-off and landing and in poor weather conditions.
Post-construction mortality surveys at wind facilities in North America suggest that bird mortality is
occurring as a result of interactions with turbines. A review of post-construction monitoring studies at 46
wind farms across the United States found most wind farms reported fewer than 4 bird mortalities per
megawatt per year (NWCC, 2010). Most mortalities noted occurred during bird migration periods though
were highly varied regionally (NWCC, 2010). Data from the MNR suggests that operational wind farms
in Ontario average roughly 2.5 bird deaths per turbine per year (OMNR, 2011b).
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 62 June 14, 2013
Objectives
Ensure bird mortalities are kept below MNR requirements. Current requirements are14/turbine/year at
individual turbines or turbine groups; 0.2 raptors/turbine/year (all raptors) across a wind power project;
0.1 raptors/turbine/year (provincially tracked raptors across a wind power project); and 2 raptors/wind
power project (<10 turbines).
Mitigation Measures
Turbines have been sited away from natural heritage features based on the results of the Natural Heritage
Assessment Reports. Post-construction bird monitoring will be implemented. Should bird mortality
thresholds be crossed during operation, mitigation measures such as increasing cut-in speeds of wind
turbines or halting operation of problem turbines at specific times of the year will be considered as
appropriate. Any mitigation measures utilized will be established with the cooperation of the MOE and
MNR.
Monitoring Plan and Contingency Measures
Post-construction follow-up monitoring surveys will be conducted in accordance with the Natural
Heritage Environmental Effects Monitoring Plan detailed in Appendix V.
Net Effects
Bird mortality is a possible impact of the project, and will be carefully monitored to ensure levels are
below MNR requirements. Should bird mortality thresholds be exceeded during operation, mitigation
measures will be considered. As a result of these measures net effects on bird populations will be
minimized.
5.4.6.2 Bird Disturbance
Potential Effects
During the construction and decommissioning phases the presence of humans and machinery and the
associated noise will likely cause birds to avoid the areas under construction. Breeding behaviour has the
potential to be impacted. Although it is expected that many resident birds will become habituated to the
wind turbines, there may be some behavioural impacts during construction, operation, and
decommissioning. Avoidance of the wind farm may result in habitat fragmentation for some species.
Effects of construction on resident bird species is expected to be temporally and spatially limited, and
reversible in nature.
Objectives
Minimize breeding and behavioural disturbance to birds.
Mitigation Measures
Project infrastructure has been sited beyond 120 m of any significant bird habitat. Construction activities
will be restricted to the proposed areas. Woodland and hedgerow areas are not expected to be cleared.
However, minor fragmented clearing may be necessary (e.g. of standalone trees that do not constitute
woodland or hedgerow area). If clearing must occur, it will be avoided during the breeding season (May
and July) to the extent practical. If tree-clearing activities are unavoidable during this period, then a
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 63 June 14, 2013
trained biologist will search the area in advance to ensure that no bird nests are present in any work areas.
If an active nest is found of a federally (i.e. Migratory Birds Convention Act) or provincially (i.e. Fish and
Wildlife Conservation Act) protected species within the proposed construction area a mitigation plan will
be developed to prevent negative impacts to those species. The mitigation plan will be discussed with
Environment Canada or the MNR as applicable prior to implementation.
Monitoring Plan and Contingency Measures
No post-construction behavioural monitoring or contingency plans are proposed. If tree clearing during
breeding season is unavoidable then a trained biologist will search the area in advance to ensure that no
bird nests are present in any work areas.
Net Effects
Although no significant bird habitat was identified within the Project Location, generic habitat for birds
likely exists. While measures to mitigate behavioural disturbance to breeding birds will be implemented,
including giving consideration to restricting construction activities during the breeding season, project
activities may temporarily disturb birds to a limited extent. No long term net effects to bird breeding and
behaviour are anticipated.
5.4.6.3 Habitat Loss
Potential Effects
No clearing of woodland or hedgerow areas are expected to occur. However, minor fragmented clearing
may be necessary (e.g. of standalone trees that do not constitute woodland or hedgerow area). Although
not expected, clearing may reduce available habitat for birds and impact active nests during breeding
season.
Objectives
Minimize loss of habitat and avoid destruction of active nests.
Mitigation Measures
Project infrastructure has been sited beyond 120 m of any significant bird habitat. Woodland and
hedgerow areas are not expected to be cleared. However, minor fragmented clearing may be necessary
(e.g. of standalone trees that do not constitute woodland or hedgerow area). If clearing must occur, it will
be avoided to the extent practical during the breeding season (May and July). If tree-clearing activities are
unavoidable during this period, then a trained biologist will search the area in advance to ensure that no
bird nests are present in any work areas. If an active nest is found of a federally (i.e. Migratory Birds
Convention Act) or provincially (i.e. Fish and Wildlife Conservation Act) protected species within the
proposed construction area a mitigation plan will be developed to prevent negative impacts to those
species. The mitigation plan will be discussed with Environment Canada or the MNR as applicable prior
to implementation.
Monitoring Plan and Contingency Measures
No post-construction behavioural monitoring or contingency plans are proposed.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 64 June 14, 2013
Net Effects
Although no significant bird habitat was identified within the Project Location, generic habitat for birds
likely exists. Habitat loss is not expected as a result of direct impacts from this project. No net effects on
bird populations due to impacts of habitat loss are anticipated.
5.4.7 Bats
No significant bat maternity colonies or hibernacula were identified during pre-construction surveys, as
determined through an extensive natural heritage assessment. However, it is likely that bats inhabit areas
of the project that were not considered significant but these areas will have fewer species, fewer
individuals and/or more common species. Specific areas of inhabitation may include those delineated as
generalized significant wildlife habitat.
In addition to the Natural Heritage reporting requirements under O. Reg. 359/09, the Skyway 126 Wind
Energy project will be in compliance with the requirements under the Endangered Species Act (2007) as
outlined in the Ministry of Natural Resources’ (MNR) Approvals and Permitting Requirements
Document. Details pertaining to Species at Risk are not described within this report. This section
discusses potential impacts to the general bat population of the area from construction activities.
5.4.7.1 Mortality
Potential Effects
There is an increasing need to protect bat species as their populations are declining across North America
due to White Nose Syndrome. Bats are less equipped to avoid turbine blades because their navigational
systems depend on echolocation which detects objects in their flight path. The potential effects of a wind
farm on bat species include mortality, which may occur as a result of direct collision or barotrauma –
internal injuries caused by rapid pressure reductions undetectable by echolocation. A review of post-
construction monitoring studies at 46 wind farms across the United States found most wind farms
reported fewer than 10 bat mortalities per megawatt per year (NWCC, 2010). Most mortalities noted
occurred during bat migration periods though were highly varied regionally (NWCC, 2010). Data from
the MNR suggests that operational wind farms in Ontario average roughly 4-14 bat deaths, per year per
turbine (OMNR, 2011a).
Objectives
Ensure bat mortalities are kept below MNR requirements. The current requirement is 10 bats/turbine/year.
Mitigation Measures
Project infrastructure has been sited beyond 120 m of any significant bat habitats. Construction activities
will be restricted to the proposed areas. Woodland and hedgerow areas are not expected to be cleared.
Use of construction lighting will be kept to a minimum. Aeronautical lighting will be kept to the
minimum required by Transport Canada.
Monitoring Plan and Contingency Measures
Post-construction follow-up monitoring surveys will be conducted in accordance with the Natural
Heritage Environmental Effects Monitoring Plan detailed in Appendix V. Should bat mortality
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 65 June 14, 2013
thresholds be exceeded during operation, mitigation measures such as increasing cut-in speeds of wind
turbines or halting operation of problem turbines at specific times of the year will be considered. Any
mitigation measures utilized will be established with the cooperation of the MOE and MNR.
Net Effects
Although no significant bat habitat was identified within the Project Location, generic habitat for bats
likely exists. Despite mitigation measures for construction and decommissioning activities, resident bats
may experience disturbances. During operation, bat mortality will be carefully monitored to ensure it
remains below MNR requirements. Should bat mortality thresholds be exceeded during operation,
mitigation measures established with the cooperation of the MOE and MNR will be considered. As a
result of these measures net effects on bat populations will be minimized.
5.4.7.2 Disturbance
Potential Effects
Wind farm construction has the potential to affect local bat species. During the construction phase the
presence of humans and machinery and the associated noise will likely cause bats to avoid the areas under
construction. Breeding behaviour has the potential to be impacted. Lighting used during construction
also has the potential to impact bat behaviour.
It has also been shown that many bats habituate to the presence of wind turbines, and this reduces the
potential for significant displacement during operation. Aeronautical lighting may impact bat behaviour.
For some species habitat fragmentation due to the presence of turbine and access roads may impact
behaviour.
Objectives
Minimize breeding and behavioural disturbance to bats.
Mitigation Measures
Project infrastructure has been sited beyond 120 m of any significant bat maternity habitats. Construction
activities will be restricted to the proposed areas. Use of construction lighting will be kept to a minimum.
Aeronautical lighting will be kept to the minimum required by Transport Canada.
Monitoring Plan and Contingency Measures
No post-construction behavioural monitoring or contingency plans are proposed.
Net Effects
Disturbance to bats is expected to be limited in scope and duration. Net effects of the project in terms of
disturbance to bats are expected to be minimal.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 66 June 14, 2013
5.4.7.3 Habitat Loss
Potential Effects
No clearing of woodland or hedgerow areas are expected to occur. Although not expected, clearing may
reduce available habitat for bats.
Objectives
Minimize the loss of bat habitat.
Mitigation Measures
Project infrastructure has been sited farther than 120 m from significant bat habitat. Cleared areas have
been minimized to the extent possible.
Monitoring Plan and Contingency Measures
No post-construction monitoring or contingency plans are proposed.
Net Effects
Although no significant bat habitat was identified within the Project Location, generic habitat for bats
likely exists. Habitat loss is not expected as a result of direct impacts from this project. No net effects on
bat populations due to impacts of habitat loss are anticipated.
5.4.8 Natural Heritage Features and Significant Wildlife Habitat
Significant Natural Heritage Features and Wildlife Habitat were identified during Natural Heritage
Assessment surveys. Table 5-2 below summarizes the impacts to these features and habitats and presents
mitigation measures for each. Many of the impacts and mitigation measures presented below are also
presented elsewhere within this report. However, Table 5-2 below specifically addresses impacts to
individual features. Please refer to the Natural Heritage Assessment and Environmental Impact Study
Report for further details.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 67 June 14, 2013
Table 5-2: Anticipated Environmental Impacts, Performance Objectives and Mitigation Measures for Significant Natural Heritage Features
Natural
Feature
ID
Distance to
Project
Components
within 120 m
Function Potential Negative Effect(s) Performance
Objective Mitigation Measures Residual
Effects
Direct Indirect
WETLANDS
WE02 4 m to
underground
electrical
cabling along
pre-existing
Road 63.
Functions as wildlife
habitat, storage of
carbon, cleaning air,
hydrological
cycling, nutrient
cycling (OMNR,
2005) absorbing of
spring runoff from
the agricultural
fields.
Construction/
Decommissioning of
electrical cabling within
the right-of-way of Road
63:
No encroachment onto
feature.
Potential for erosion
and/or sedimentation from
construction activities, but
these impacts will be
short term and highly
localized.
Minimal risk of
contamination to soils
from spills and leaks
anticipated.
Dust generation from
construction activities will
be short-term and highly
localized.
Localized
displacement of
wildlife
inhabiting
WE02 due to
construction
noise.
Maintain form
and function
of wetland.
Ensure
minimal
disturbance to
wildlife using
habitat.
Construction activities will be limited to designated construction area. Areas
for construction will be, at a minimum, 4m from the edge of the wetland. The
wetland boundary will be demarcated in the field by a qualified biologist
using OWES methodology (50% wetland vegetation rule).
All workers will be notified of wetland significance. Daily visual monitoring
of work area by constructor manager will occur to ensure compliance
(construction only occurring within demarcated area).
Silt fencing will be erected 4m from the edge of the wetland boundary. Use of
erosion and sedimentation control measures such as silt fences or erosion
control blankets will be applied when construction is within 30m of the
wetland. Erosion and sediment fencing will be inspected daily to ensure they
are functioning and maintained as required. If erosion and sediment control
measures are not functioning properly, alternative measures will be
implemented and prioritized above other construction activities. Inspection
will continue until vegetation has become established and the disturbed areas
are stabilized.
The size and exposure time of disturbed (trenched) areas for burial of
underground electrical cables will be minimized to the shortest extent
possible.
All disturbed areas will be re-vegetated as soon as possible to pre-
construction conditions. Erosion and sediment control measures such as
erosion blankets will be used until re-vegetation in the next growing season.
All natural areas will be restored using native species.
Implement dust suppression when needed such as wetting gravel or topsoil
piles, and limiting vehicle speeds on gravel or dirt roads
No residual
effects
anticipated.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 68 June 14, 2013
Natural
Feature
ID
Distance to
Project
Components
within 120 m
Function Potential Negative Effect(s) Performance
Objective Mitigation Measures Residual
Effects
Direct Indirect
All equipment used on site will be maintained in good working order. Safe
storage of petroleum, oils and lubricants will be ensured. Where possible,
vehicle maintenance will be performed off site, at a nearby commercial
fuelling station, in order to minimize the amount of lubricants and oils stored
on site. Storage and disposal of petroleum, oil and lubricants (POL), and
equipment fuelling is not allowed within 120m of any significant natural
feature, watercourse or water body. In the event of an accidental spill, the
MOE Spills Action Centre will be contacted and emergency spill procedures
implemented immediately. Any fuel storage and activities with the potential
for contamination will occur in properly protected and sealed areas.
WE03 2 m to
underground
electrical
cabling along
4th
Concession
B Road
Functions as wildlife
habitat, storage of
carbon, cleaning air,
hydrological
cycling, nutrient
cycling OMNR,
2005) absorbing of
spring runoff from
the agricultural
fields.
Construction/
Decommissioning of
electrical cabling within
the right-of-way of Road
63 and 4th
Concession B:
No encroachment onto
feature.
Potential for erosion
and/or sedimentation from
construction activities, but
these impacts will be
short term and highly
localized.
Minimal risk of
contamination to soils
from spills and leaks
anticipated.
Dust generation from
construction activities will
be short-term and highly
localized.
Localized
displacement of
wildlife
inhabiting
WE03 due to
construction
noise.
Maintain form
and function
of wetland.
Ensure
minimal
disturbance to
wildlife using
habitat.
Construction activities will be limited to designated construction area. Areas
for construction will be, at a minimum, 2 m from the edge of the wetland. The
wetland boundary will be demarcated in the field by a qualified biologist
using OWES methodology (50% wetland vegetation rule).
All workers will be notified of wetland significance. Daily visual monitoring
of work area by constructor manager will occur to ensure compliance
(construction only occurring within demarcated area).
Silt fencing will be erected 2m from the edge of the wetland boundary. Use of
erosion and sedimentation control measures such as silt fences or erosion
control blankets will be applied when construction is within 30m of the
wetland. Erosion and sediment fencing will be inspected daily to ensure they
are functioning and maintained as required. If erosion and sediment control
measures are not functioning properly, alternative measures will be
implemented and prioritized above other construction activities. Inspection
will continue until vegetation has become established and the disturbed areas
are stabilized.
The size and exposure time of disturbed (trenched) areas for burial of
underground electrical cables will be minimized to the shortest extent
possible.
All disturbed areas will be re-vegetated as soon as possible to pre-
construction conditions. Erosion and sediment control measures such as
No residual
effects
anticipated.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 69 June 14, 2013
Natural
Feature
ID
Distance to
Project
Components
within 120 m
Function Potential Negative Effect(s) Performance
Objective Mitigation Measures Residual
Effects
Direct Indirect
erosion blankets will be used until re-vegetation in the next growing season.
All natural areas will be restored using native species.
Implement dust suppression when needed such as wetting gravel or topsoil
piles, and limiting vehicle speeds on gravel or dirt roads
All equipment used on site will be maintained in good working order. Safe
storage of petroleum, oils and lubricants will be ensured. Where possible,
vehicle maintenance will be performed off site, at a nearby commercial
fuelling station, in order to minimize the amount of lubricants and oils stored
on site. Storage and disposal of petroleum, oil and lubricants (POL), and
equipment fuelling is not allowed within 120m of any significant natural
feature, watercourse or water body. In the event of an accidental spill, the
MOE Spills Action Centre will be contacted and emergency spill procedures
implemented immediately. Any fuel storage and activities with the potential
for contamination will occur in properly protected and sealed areas.
Adherence to Fisheries and Oceans Canada, Ontario Operational Statement
for Maintenance of Riparian Vegetation in Existing Rights-of-Way.
WE04 4 m to
underground
electrical
cabling along
pre-existing
Road 63.
Functions as wildlife
habitat, storage of
carbon, cleaning air,
hydrological
cycling, nutrient
cycling (OMNR,
2005) absorbing of
spring runoff from
the agricultural
fields.
Construction/
Decommissioning of
electrical cabling within
the right-of-way of Road
63 and 4th
Concession B:
No encroachment onto
feature.
Potential for erosion
and/or sedimentation from
construction activities, but
these impacts will be
short term and highly
localized.
Minimal risk of
Localized
displacement of
wildlife
inhabiting
WE04 due to
construction
noise.
Maintain form
and function
of wetland.
Ensure
minimal
disturbance to
wildlife using
habitat.
Construction activities will be limited to designated construction area. Areas
for construction will be, at a minimum, 4m from the edge of the wetland. The
wetland boundary will be demarcated in the field by a qualified biologist
using OWES methodology (50% wetland vegetation rule).
All workers will be notified of wetland significance. Daily visual monitoring
of work area by constructor manager will occur to ensure compliance
(construction only occurring within demarcated area).
Silt fencing will be erected 4 m from the edge of the wetland boundary. Use
of erosion and sedimentation control measures such as silt fences or erosion
control blankets will be applied when construction is within 30m of the
wetland. Erosion and sediment fencing will be inspected daily to ensure they
are functioning and maintained as required. If erosion and sediment control
measures are not functioning properly, alternative measures will be
implemented and prioritized above other construction activities. Inspection
No residual
effects
anticipated.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 70 June 14, 2013
Natural
Feature
ID
Distance to
Project
Components
within 120 m
Function Potential Negative Effect(s) Performance
Objective Mitigation Measures Residual
Effects
Direct Indirect
contamination to soils
from spills and leaks
anticipated.
Dust generation from
construction activities will
be short-term and highly
localized.
will continue until vegetation has become established and the disturbed areas
are stabilized.
The size and exposure time of disturbed (trenched) areas for burial of
underground electrical cables will be minimized to the shortest extent
possible.
All disturbed areas will be re-vegetated as soon as possible to pre-
construction conditions. Erosion and sediment control measures such as
erosion blankets will be used until re-vegetation in the next growing season.
All natural areas will be restored using native species.
Implement dust suppression when needed such as wetting gravel or topsoil
piles, and limiting vehicle speeds on gravel or dirt roads
All equipment used on site will be maintained in good working order. Safe
storage of petroleum, oils and lubricants will be ensured. Where possible,
vehicle maintenance will be performed off site, at a nearby commercial
fuelling station, in order to minimize the amount of lubricants and oils stored
on site. Storage and disposal of petroleum, oil and lubricants (POL), and
equipment fuelling is not allowed within 120m of any significant natural
feature, watercourse or water body. In the event of an accidental spill, the
MOE Spills Action Centre will be contacted and emergency spill procedures
implemented immediately. Any fuel storage and activities with the potential
for contamination will occur in properly protected and sealed areas.
WOODLANDS
WO01 10 m, 33 m,
54 m, 46 m
and 46 m to
T2 bladeswept
area, laydown,
turbine,
underground
electrical
Functions in total
area, woodland
interior, native
diversity dominant,
water protection and
proximity to other
significant
Construction/
Decommissioning of
Turbine 1 and associated
components including:
foundation, cranepad,
blade swept area, laydown
area access road and
Displacement of
wildlife
inhabiting W001
due to
construction
noise.
Maintain form
and function
of woodland.
Ensure
minimal
residual
disturbance to
Construction activities will be limited to designated construction area.
Areas for construction will be demarcated with silt fencing and placed, at a
minimum, 30m from the woodland edge as defined by the drip line (outer
edge of the canopy). All workers will be notified of woodland significance.
Daily visual monitoring of work area by constructor manager will occur to
ensure compliance (construction only occurring within demarcated area).
Silt fencing will be erected 30 m from the edge of the woodland boundary,
No residual
effects
anticipated.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 71 June 14, 2013
Natural
Feature
ID
Distance to
Project
Components
within 120 m
Function Potential Negative Effect(s) Performance
Objective Mitigation Measures Residual
Effects
Direct Indirect
cabling and
cranepad,
respectively.
40 m to both
temporary and
permanent
project road to
T2
woodlands/habitats. electrical cabling:
No encroachment onto
feature.
Potential for erosion
and/or sedimentation from
construction activities, but
these impacts will be
short term and highly
localized.
Minimal risk of
contamination to soils
from spills and leaks
anticipated.
Dust generation from
construction activities will
be short-term and highly
localized.
wildlife using
habitat.
where possible. Erosion and sediment fencing will be inspected daily to
ensure they are functioning and maintained as required. If erosion and
sediment control measures are not functioning properly, alternative measures
will be implemented and prioritized above other construction activities.
All disturbed areas will be re-vegetated as soon as possible to pre-
construction conditions. Erosion and sediment control measures such as
erosion blankets will be used until re-vegetation in the next growing season.
All natural areas will be restored using native species.
Implement dust suppression when needed such as wetting gravel or topsoil
piles, and limiting vehicle speeds on gravel or dirt roads
All equipment used on site will be ensured to be in good working order. Safe
storage of petroleum, oils and lubricants will be ensured. Where possible,
vehicle maintenance will be performed off site, at a nearby commercial
fuelling station, in order to minimize the amount of lubricants and oils stored
on site. Storage and disposal of petroleum, oil and lubricants (POL), and
equipment fuelling is not allowed within 120m of any significant natural
feature, watercourse or water body. In the event of an accidental spill, the
MOE Spills Action Centre will be contacted and emergency spill procedures
implemented immediately. Any fuel storage and activities with the potential
for contamination will occur in properly protected and sealed areas.
Operation of Turbine 1;
use of access road for
maintenance:
Use of road salt during
winter months may
increase salinity of water
bodies, wetlands and soil
associated with WO01.
Indirect effects
from operation
(i.e. noise,
vehicle
movement)
could
temporarily
disturb wildlife
living in this
habitat.
Use of access road will be restricted for maintenance vehicles only when
required.
Minimize use of road salt; use of licensed contractor for winter road clearing
and maintenance.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 72 June 14, 2013
Natural
Feature
ID
Distance to
Project
Components
within 120 m
Function Potential Negative Effect(s) Performance
Objective Mitigation Measures Residual
Effects
Direct Indirect
WO03 4 m to
underground
electrical
cabling along
4th
Concession
B Road
Functions in total
area, woodland
interior, native
diversity dominant,
water protection and
proximity to other
significant
woodlands/habitats.
Construction/
Decommissioning of
electrical cabling within
the right-of-way of Road
63 and 4th
Concession B:
No encroachment onto
feature.
Potential for erosion
and/or sedimentation from
construction activities, but
these impacts will be
short term and highly
localized.
Minimal risk of
contamination to soils
from spills and leaks
anticipated.
Dust generation from
construction activities will
be short-term and highly
localized.
Localized
displacement of
wildlife
inhabiting
WO03 due to
construction
noise.
Maintain form
and function
of wetland.
Ensure
minimal
disturbance to
wildlife using
habitat.
Construction activities will be limited to designated construction area.
Areas for construction will be demarcated by a qualified biologist with silt
fencing and placed, at a minimum, 4 m from the woodland edge as defined by
the drip line (outer edge of the canopy). All workers will be notified of
woodland significance. Daily visual monitoring of work area by constructor
manager will occur to ensure compliance (construction only occurring within
demarcated area).
Silt fencing will be erected 4 m from the edge of the woodland boundary.
Erosion and sediment fencing will be inspected daily to ensure they are
functioning and maintained as required. If erosion and sediment control
measures are not functioning properly, alternative measures will be
implemented and prioritized above other construction activities. Inspection
will continue until vegetation has become established and the disturbed areas
are stabilized.
The size and exposure time of disturbed (trenched) areas for burial of
underground electrical cables will be minimized to the shortest extent
possible.
All disturbed areas will be re-vegetated as soon as possible to pre-
construction conditions. Erosion and sediment control measures such as
erosion blankets will be used until re-vegetation in the next growing season.
All natural areas will be restored using native species.
Implement dust suppression when needed such as wetting gravel or topsoil
piles, and limiting vehicle speeds on gravel or dirt roads
All equipment used on site will be maintained in good working order. Safe
storage of petroleum, oils and lubricants will be ensured. Where possible,
vehicle maintenance will be performed off site, at a nearby commercial
fuelling station, in order to minimize the amount of lubricants and oils stored
on site. Storage and disposal of petroleum, oil and lubricants (POL), and
equipment fuelling is not allowed within 120m of any significant natural
feature, watercourse or water body. In the event of an accidental spill, the
No residual
effects
anticipated.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 73 June 14, 2013
Natural
Feature
ID
Distance to
Project
Components
within 120 m
Function Potential Negative Effect(s) Performance
Objective Mitigation Measures Residual
Effects
Direct Indirect
MOE Spills Action Centre will be contacted and emergency spill procedures
implemented immediately. Any fuel storage and activities with the potential
for contamination will occur in properly protected and sealed areas.
WILDLIFE HABITAT
DWCA01 8 m north of
underground
electrical
cabling along
4th
Concession.
DWCA01 has been
identified as an area
of coniferous swamp
where deer annually
congregate in large
numbers during the
winter months.
Movement in the
area is not
constrained by snow
depth.
Construction/
Decommissioning of
electrical cabling within
the right-of-way of 4th
Concession B:
No encroachment onto
feature.
Localized
displacement of
deer inhabiting
DWCA01due to
construction
noise.
Maintain form
and function
of habitat.
Ensure
minimal
disturbance to
wildlife using
habitat.
As DWCA01 is located within the WE03/WO03, areas for construction will
be demarcated using the mitigation measures for WE03 and WO03. All
workers will be notified of habitat significance. Daily visual monitoring of
work area to ensure compliance (construction only occurring within
demarcated area).
No construction between Dec 1st through April 15th when the snow depth is
greater than 20cm or there is evidence of yarding. In years where
environmental conditions are not favourable for yarding, MNR will be
contacted to determine if construction activities may proceed between Dec 1st
and April 15th.
Mitigation measures detailed for WE03 and WO03 will also be applied (see
above)
No residual
effects
anticipated.
ABH01 10 m, 33 m,
54 m, 46 m
and 46 m to
T2 bladeswept
area, laydown,
turbine,
underground
electrical
cabling and
cranepad,
respectively.
40 m to both
temporary and
Wetland, lake or
pond within or
adjacent to (within
120 m) to a
woodland that
provide amphibian
breeding habitat.
Woodlands with
permanent ponds or
those containing
water in most years
until mid-July are
most likely to be
Construction/
Decommissioning of
Turbine 1 and associated
components including:
foundation, cranepad,
blade swept area, laydown
area access road and
electrical cabling:
Potential for erosion
and/or sedimentation from
construction activities, but
these impacts will be
short term and highly
Displacement of
amphibians
using ABH01
due to
construction
noise.
Maintain form
and function
of woodland.
Ensure
minimal
residual
disturbance to
wildlife using
habitat.
As ABH01 occupies the same location as WO01, the same mitigation
measures detailed above for WO01 will be applied for ABH01.
In addition to these mitigation measures, construction is to take place outside
of the sensitive April-June breeding period for this habitat.
Should construction be unavoidable in April- June a trained biologist will
accompany construction crews to monitor amphibian movements within
vicinity (120m) of the amphibian breeding habitat and where possible prevent
mortality. Specifically, the biologist will search the area for amphibians and
usher them to areas outside of the construction zone according to MNR
recommended best practices. As amphibians can be sensitive, no handling or
collection will occur. There will be no collection or capturing of amphibians.
No residual
effects
anticipated.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 74 June 14, 2013
Natural
Feature
ID
Distance to
Project
Components
within 120 m
Function Potential Negative Effect(s) Performance
Objective Mitigation Measures Residual
Effects
Direct Indirect
permanent
project road to
T2
used as breeding
habitat.
localized.
Minimal risk of
contamination to soils
from spills and leaks
anticipated.
Dust generation from
construction activities will
be short-term and highly
localized.
Operation of Turbine 1;
use of access road for
maintenance:
Use of road salt during
winter months may
increase salinity of water
bodies, wetlands and soil
associated with ABH01.
Indirect effects
from operation
(i.e. noise,
vehicle
movement)
could
temporarily
disturb
amphibians
using this
habitat.
Use of access road will be restricted for maintenance vehicles only when
required.
Minimize use of road salt; use of licensed contractor for winter road clearing
and maintenance.
Post-construction monitoring to ensure ongoing use of habitat by amphibians
during breeding season (April-June).
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 75 June 14, 2013
5.4.8.1 Environmental Effects Monitoring
Specific mitigation and monitoring measures for potential environmental impacts to natural heritage
features that require monitoring are addressed in the Natural Heritage Environmental Effects Monitoring
Plan detailed in Appendix V. The mitigation and associated monitoring measures are relevant to the
significant natural features identified in Table 5-2. Information presented in the NHEEMP will serve to
verify that mitigation measures are effective for meeting performance objectives. If performance
objectives are not being met, as indicated by monitoring, contingency measures will be used to ensure that
remedial action is taken to comply with identified performance objectives. By providing adequate and
detailed information in the NHEEMP, the REA regulatory requirement to describe how the
Environmental Effects Monitoring Plan (EEMP) addresses any negative environmental effects to natural
features, provincial parks and conservation reserves can be fulfilled.
5.4.8.2 Generalized Significant Wildlife Habitats
As specified in Appendix D to the Natural Heritage Assessment Guide for Renewable Energy Projects,
candidate Significant Wildlife Habitat identified within 120 m of underground lines (with the exception of
winter deer yards) is not required to be delineated or evaluated. Instead, it is treated as Generalized
Significant Wildlife Habitat (GSWH).
Construction activities for the burial of underground electrical lines will occur along pre-existing
roadways in the road right-of-way. Construction of underground lines would involve the temporary
removal of surface materials (including vegetation) and soils, followed by the replacement of this
material. The area affected by the underground burial of electrical taplines will be minimized.
Burial of underground electrical taplines > 0.1-4 m from WO03/WE02, WO03/WE03 and WO03/WE04
may result in erosion from excavation and re-filling of trenches. These impacts will be short-term and
highly localized. Moreover, control measures such as the use of silt fences, minimizing the size and
exposure time of disturbed areas, and erosion control blankets will be used where appropriate. It is
anticipated that impacts to any GSWH within features are extremely unlikely. Sedimentation and erosion
impacts will be minimized as all construction areas within close proximity to water bodies will occur
within pre-existing road right-of-ways. See Section 5.4.4.2 for a full description of the Sedimentation &
Erosion Control Plan. No impacts from operation are anticipated. See Section 5.4.4.2 for specific erosion
control measures for the features listed above, which will minimize any potential impacts to GSWH
located within these areas.
Additionally, there is some potential for improper storage or disposal of oils, gasoline, grease or other
materials used in construction vehicles, turbines or maintenance vehicles which may result in spills or
leaks, contaminating soils or groundwater. Please see the Section 5.4.4.1 for a full description of the
Spills & Leaks Control Plan for Skyway 126 Wind Energy project.
Localized wildlife disturbance due to construction activities, in the form of noise and dust, are expected
but will be controlled by limiting construction activities for the proposed area along with clear delineation
to keep construction workers out of the GSWH areas. Dust will be kept to a minimum by regularly
wetting the roads.
No residual impacts are anticipated for the GSWH areas along the underground electrical cable route
when the above mitigation measures, as described in the Environmental Effects Monitoring Plan, are
taken into account.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 76 June 14, 2013
6 EMERGENCY RESPONSE AND COMMUNICATIONS PLAN
The following section lists key organizations and/or individuals that may be contacted during emergency
situations and regarding regulatory issues, followed by the Project Contact List. This list will be posted in
the base of each turbine, and it will be carried by construction and maintenance personnel during the
construction, operation, and decommissioning phases of the project.
Agency Area, Contact Person Phone Number
Emergency Contacts
Ambulance/Police/Rescue 9-1-1
Fire Emergency Response 9-1-1
Environmental Emergencies and Spills
Ministry of Environment, Spills Action
Centre
Ontario 1-800-268-6060
Local Hospitals with Emergency Services
Collingwood General & Marine Hospital 705-445-2550
Regulatory and Municipal Contacts
Ministry of Natural Resources Midhurst District Office 705-725-7500
Ontario Ministry of Tourism and Culture Walkerton – Janine Dunlop, Regional Advisor
– Citizenship, Culture & Health Promotion
519-881-1081
Ministry of Transportation Owen Sound 519-376-7350
Ontario Ministry of Environment London District Office 519-873-5000
Workplace Safety and Insurance Board Kitchener 519-576-4130
Toll Free 1-800-265-2570
Project Contacts
Cloudy Ridge Wind Park LP TBA (Project Manager)
When contacting emergency agencies, the location of the project and contact information of the personnel
on site should be given. The project address is:
269294 South Line C, RR1,
Badjeros, ON, N0C 1A0
6.1 Status Updates
The Community Liaison Committee will be updated on all significant project milestones. In addition,
status updates will be sent by mail or e-mail to the Municipality of Grey Highlands and the County of
Grey. These updates will also be posted on the project website.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 77 June 14, 2013
6.2 Emergency Notification
Emergencies can be triggered by various events, such as POL and waste spills and leaks, fires, or ice
throw. In case of emergencies, the appropriate emergency response bodies will be contacted. Details
regarding emergency notification can be found in the Environmental Effects Monitoring Plan in Section 5
of this report.
6.3 Protocol for Responding to Public Inquiries
The protocol for responding to public inquiries will be as follows:
A log will be kept of all public inquiries. These records will be kept on hand by Cloudy Ridge
Wind Park LP for at least 2 years.
The project operator will respond to all public inquiries within a reasonable time period.
The project operator will record all responses and actions taken in the log.
The project operator will engage appropriate agencies or authorities (for example the Ministry of
Environment for noise issues).
6.4 Contact Information
All relevant contact information for Cloudy Ridge Wind Park LP, including postal address, phone
number, and e-mail address, will be posted on the project website for public reference and sent to any
nearby Municipalities and Aboriginal communities. This communication pathway will remain open for
the lifetime of the project.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 78 June 14, 2013
7 CONCLUSIONS
The Skyway 126 Wind Energy project, proposed by the Cloudy Ridge Wind Park LP, will have a
nameplate capacity of 10 MW, consisting of five (5) REpower MM92 wind turbines of 2 MW each.
Turbines will be built in five proposed locations. The project will be constructed on privately-owned
agricultural lands near the community of Badjeros, within the Municipality of Grey Highlands. The
Skyway 126 Wind Energy project has received a Power Purchase Agreement (PPA) under Ontario’s
Feed-In Tariff (FIT) Program. This wind energy project is subject to the Renewable Energy Approval
(REA) process per Ontario Regulation 359/09 under the Environmental Protection Act. Environmental
studies carried out under the REA process will ensure that the Skyway 126 Wind Energy project produces
clean, emissions-free electricity while minimizing negative environmental effects.
This Design and Operations Report presented the site plan, details of the wind farm design and an
operations plan for the facility. The report also detailed mitigation measures for any environmental
impacts, how they will be monitored and contingency plans in the event that mitigation measures fail. A
plan for managing emergency responses and communications was also discussed within this report. It has
provided information that may be relevant to stakeholders and the public or in relation to authorizations
that may from other provincial ministries or approval agencies. Further details on the project will be
found in the documents compiled with the complete REA application.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 79 June 14, 2013
8 QUALIFICATIONS AND LIMITATIONS
M. K. Ince & Associates Ltd. (MKI) has prepared this report in accordance with its proposal and
information provided by its Client. The information and analysis contained herein is for the sole benefit of
the Client and save for regulatory review purposes may not be relied upon by any other person.
MKI’s assessment was made in accordance with guidelines, regulations and procedures believed to be
current at this time. Changes in guidelines, regulations and enforcement policies can occur at any time
and such changes could affect the conclusions and recommendations of this report.
The reports, maps and related documents may rely on information provided to MKI by the Client. This
information may include but is not limited to manufacturer and construction specifications and other
related information. Maps are created using a Geographic Information System (GIS) that compiles
records, information, and data from various sources which may contain errors. While we have referred to
and made use of reports, maps and geospatial data and specifications prepared by others, we assume no
liability for the accuracy of the information contained within.
Maps and documents made available by MKI are not legal surveys and are not intended to be used as
such. No original surveying is included as part of these maps. If any contradictions exist between this
document and relevant municipal, provincial or federal laws, regulations, codes, or policies, the text of the
laws, regulations, codes or policies will be the legal authority.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 80 June 14, 2013
9 REFERENCES
Australian Government. (2010). Wind turbines and health: a rapid review of evidence. National Health
and Medical Research Council, 1-11.
Australian Government. (2011). The social and economic impact of rural wind farms. Community Affairs
References Committee, 1-131.
Burton, T., D. Sharpe, N. Jenkins and E. Bossanyi (2001). Wind energy handbook. West Sussex,
England: John Wiley and Sons.
Chatham-Kent Public Health Unit. (2008). The health impact of wind turbines: a review of the current
white, grey and published literature. Chatham-Kent Municipal Council, Chatham Ontario, 1-26.
Garrad Hassan Canada. 2007. Recommendations for risk assessment of ice throw and blade failure in
Ontario.
Harding, P., Wilkins, A. (2008). Wind turbines, flicker, and photosensitive epilepsy: characterizing the
flashing that may precipitate seizures and optimizing guidelines to prevent them. Epilepsia 49
(6):1095-1098.
Health Canada. (2012). Electric and Magnetic Fields from Power Lines and Appliances. Catalogue #
H13-7/70-2012E-PDF, ISBN # 978-1-100-21395-8.
Knopper, L.D. and Ollson, C.A. (2011). Health effects and wind turbines: A review of the literature.
Environmental Health, 10:78. http://www.ehjournal.net/content/10/1/78
Massachusetts Department of Environmental Protection (MassDEP) and Massachusetts Department of
Public Health (MDPH). (2012). Wind turbine health impact study: report of independent expert
panel, 1-164.
Ministry of Environment. (2008). Noise Guidelines for Wind Farms: Interpretation for Applying MOE
NPC Publications to Wind Power Facilities. Government of Ontario, 1-18.
National Institute of Environmental Health Sciences. (2002). EMF: Electric and magnetic fields
associated with the use of electric power. NIEHS/DOE EMF Rapid Program, 1-65.
National Wind Coordinating Collaborative (NWCC). Wind Turbine Interactions with Birds, Bats, and
their Habitats: A Summary of Research Results and Priority Questions Spring 2010.
http://www.nationalwind.org
Ontario's Chief Medical Officer of Health. (2010). The potential health impact of wind turbines. Chief
Medical Officer of Health (CMOH) report. Toronto, ON: Queen's Printer for Ontario; 2010. p. 1-
14.
Smedley, A.R.D., Webb, A.R., Wilkins, A.J. (2010). Potential of wind turbines to elicit seizures under
various meteorological conditions. Epilepsia 51 (7):1146-1151.
Skyway 126 Wind Energy Design and Operations Report
M.K. Ince and Associates Ltd. 81 June 14, 2013
World Health Organization. (2007). Environmental Health Criteria 238: Extremely Low Frequency
Fields. WHO Press, Geneva, Switzerland. Available on line: http://www.who.int/peh-
emf/publications/elf_ehc/en/index.html