Skyscraper Floor and Cladding Cost Estimator … · Cost estimation is vital to the success and...
Transcript of Skyscraper Floor and Cladding Cost Estimator … · Cost estimation is vital to the success and...
Skyscraper Floor and Cladding Cost Estimator
Keith Oneil Newton
A project submitted to the faculty of Brigham Young University
in partial fulfillment of the requirements for the degree of
Master of Science
Richard J. Balling, Chair Paul W. Richards
Fernando S. Fonseca
Department of Civil and Environmental Engineering
Brigham Young University
December 2015
Copyright © 2015 Keith Oneil Newton
All Rights Reserved
ABSTRACT
Skyscraper Floor and Cladding Cost Estimator
Keith Oneil Newton
Department of Civil and Environmental Engineering BYU Master of Science
Cost estimation is vital to the success and financial viability of any construction project.
One of the greatest difficulties in the preliminary design phase of a project is providing an accurate cost estimation, and subsequently, an accurate budget. In the China Megastructures Study Abroad Program led by Dr. Richard J. Balling, the students take responsibility in performing basic cost estimation for a skyscraper design. This report describes the Skyscraper Floor and Cladding Cost Estimator (SFCCE), which is intended to (1) automate the design of a floor system given the position of megacolumns and the interior core and (2) provide a more accurate cost estimate of the floor system and exterior cladding. The SFCCE spreadsheet consists of four sheets and focuses on estimating the weight and cost of the floor system and exterior cladding. These values can then be subsequently used as inputs into a previously developed spreadsheet that performs the design and cost estimation of skyscraper belt trusses and outriggers. The SFCCE has been designed to accommodate skyscrapers with rectangular floor plans and cores. Keywords: automation, megastructures, skyscraper, cost estimation
ACKNOWLEDGEMENTS
My Masters Project was completed only through many hours of frustration and distress.
There were many times when I felt stuck and could not progress with certain ideas I wanted to
include in my project. Dr. Balling was always there to provide me with guidance and direction.
I want to express my gratitude for his hard work and patience throughout this project.
iv
TABLE OF CONTENTS
LIST OF TABLES .......................................................................................................................... v
LIST OF FIGURES ....................................................................................................................... vi
1 Introduction ............................................................................................................................. 1
2 Literature Review .................................................................................................................... 3
Automated Floor System Layout ..................................................................................... 3
Cost Estimation. ............................................................................................................... 6
Difficulties with High-Rise Cost Estimation ................................................................. 10
3 The Cost Estimation Spreadsheet (SFCCE) .......................................................................... 11
Floor System Tab ........................................................................................................... 11
3.1.1 Inputs....................................................................................................................... 12
3.1.2 Outputs .................................................................................................................... 12
Cladding Tab .................................................................................................................. 17
3.2.1 Inputs....................................................................................................................... 17
3.2.2 Output ..................................................................................................................... 17
Additional Tabs .............................................................................................................. 20
4 Assumptions and Limitations ................................................................................................ 21
Assumptions ................................................................................................................... 21
Limitations ..................................................................................................................... 22
Future Improvements ..................................................................................................... 25
5 Conclusions ........................................................................................................................... 27
References ..................................................................................................................................... 29
v
LIST OF TABLES
Table 1: Structural Design of Buildings (Nimtawat 2009) ............................................................. 3
Table 2: Building Efficiency (Langdon) ......................................................................................... 7
Table 3: Height Charge (Gossow 2000) ....................................................................................... 10
Table 4: Approximate Time of Construction ................................................................................ 15
Table 5: Weekly Crane Costs and Crane Capacity ....................................................................... 15
Table 6: Architectural Cladding Properties .................................................................................. 18
vi
LIST OF FIGURES
Figure 1: Typical Evolution of Solutions (Nimtawat 2009) ........................................................... 5
Figure 2: Increase of Building Costs in Relation to Height
and Size of Floor Plan (Van Oss 2007) ........................................................................... 8
Figure 3: Increase of Building Costs (de Jong 2008) ..................................................................... 9
Figure 4: Increase of Costs Due to Height (Van Oss 2007) ........................................................... 9
Figure 5: SFCCE Cell Color Legend ............................................................................................ 11
Figure 2-6: Screenshot of the Floor System Tab .......................................................................... 16
Figure 2-7: Screenshot of the Cladding Tab ................................................................................. 19
Figure 2-8: Screenshot of the Constants Tab ................................................................................ 20
Figure 2-9: Floor System of the “Guangzhou Group” .................................................................. 23
Figure 2-10: Floor System of the “Hong Kong Group” ............................................................... 24
Figure 2-11: Floor System of the “Shenzhen Group” ................................................................... 24
Figure 2-12: Floor System of the “Beijing Group” ...................................................................... 25
1
1 INTRODUCTION
The China Megastructures Study Abroad Program course offers students valuable design
and research experience of tall buildings. During the course, the students are divided into groups
and share responsibility for a culminating skyscraper design project. The students not only
design the architectural and structural elements of a skyscraper, they are also required to perform
basic cost estimation for their design. The manner in which cost estimation was carried out has
evolved significantly since the initial commencement of the course. At first, skyscraper cost was
estimated simply based on the average cost per square footage of the geographic location of the
building site. Cost estimation became a more involved procedure in subsequent years, leading to
the Skyscraper Floor and Cladding Cost Estimator (SFCCE).
The SFCCE spreadsheet acts as a predecessor to the “5ex_Skyscraper_Formulas.xlsm”
spreadsheet previously developed by Dr. Richard J. Balling which assumes a value for the floor
and cladding weight. The purpose of the SFCCE spreadsheet is to obtain more accurate and
design specific weight values for the floor system and exterior cladding. The spreadsheet
automatically designs the floor slab and support beams in order to calculate the floor weight and
uses the building geometry to calculate the cladding weight. Costs are estimated based upon
material, labor, transportation, and equipment and craning costs.
2
3
2 LITERATURE REVIEW
Automated Floor System Layout
Any process that involves iteration and discernible patterns can, at least to a certain
extent, be automated. Optimizing a floor system is no different, and many studies indicate the
potential benefit for developing programs to streamline such tasks. Complicated automations
require the use of artificial intelligence (AI) to develop solutions. There are many subdivisions
that fit under the umbrella of AI including knowledge-based expert systems (KBES), case-based
reasoning (CBR), and genetic algorithms (GA) (Nimtawat 2009). Computer automation in
structural design is more valuable where more experiential data can be employed by the program
to produce optimal results. Table 1 shows various tasks of the structural design process, their
corresponding process characteristics, and the principal role of both the computer and the
engineer.
Table 1: Structural Design of Buildings (Nimtawat 2009)
4
Under the conceptual design stage, many design programs select the most appropriate
structural system for a particular building and also provide the basic architectural layout. A
program called HI-RISE, for example, uses KBES for the conceptual and preliminary design
phases of rectangular-shaped skyscrapers (Maher 1984). Many other programs exist that use
either KBES, CBR or GA to assist engineers with design (Nimtawat 2009).
The preliminary design stage focuses on establishing a layout of the structural members
in the system as well as the analysis of the members. There have been many attempts to automate
beam-slab layout design. Programs seek to create these layouts under basic design criterion. For
example, a system proposed by Tsakalis weighed in on mainly architectural and financial data to
form a design solution (Tsakalis 1994). Another program used by Syrmakezis, MAKE,
generated multiple beam-slab options for the floor system, which can then be selected by the user
(Syrmakezis 1996). Most of these programs are currently limited to rectangular floor plans of
high-rise buildings that use a uniform design throughout each story. These programs listed above
all rely on KBES, which also comes with its own limitations. The IF-THEN structure of the
program used to determine a solution do not encompass all possible solutions and their search
space has tighter bounds (Nimtawat 2009).
A different approach to floor system design, created by Bailey and Smith, uses a CBR
program coupled with CAD (Bailey 1994). The geometric models and topological data of
existing buildings can be utilized by the program to form solutions for new designs. The
weakness of CBR is that requires a generous amounts of previous design cases, but also a
complicated routine for acclimating the old design to the new one as a solution (Nimtawat 2009).
GA programs are capable of finding useful solutions in large search areas, and
subsequently, have become a more common technique to use for structural design automation. A
5
study by Anan Nimtawat and Pruettha Nanakorn focused on the automation of beam-slab floor
systems using a GA approach (Nimtawat 2009). In order for this to be accomplished, all gridline
positions connected columns had to be mapped out in binary. The beam-slab layout is described
by a chromosome string which is subject through multiple crossover and mutation processes.
Infeasible solutions were penalized. The code also placed a bias on layouts with fewer beam
segments and larger slab areas and there is a maximum allowable length placed on the slab
(Nimtawat 2009). The study examined how quickly the floor system converged upon a solution
when the population size was variable. The higher the population size, the less generations that
were required to come to a solution. Figure 1 shows the typical evolution of a beam system at
different generations.
Figure 1: Typical Evolution of Solutions (Nimtawat 2009)
6
The code was run on actual floor plans so that the calculated floor design could be
compared to the actual. The layouts provided by the code were found to be realistic solutions in
each applied case. Additional beam-slab problems were studied and tested by Nimtawat and
Nanakorn to further assess the usefulness of their code (Nimtawat 2010). The study concluded
that practical beam-slab layout designs can be produced through automation with the given
positions of columns and walls.
In a more recent study conducted by Eugenio Rodrigues, a similar GA approach is used
to automate floor systems. The algorithm expands upon this idea and attempts to incorporate
more design preferences from the architect such as maximum areas, space usage, multiple
stories, and overhangs. The study acknowledges that not all preferences can be quantified, and
the automation should serve as a guide and helper to the architect or engineer (Rodrigues 2014).
Cost Estimation.
Cost estimation is vital to the success and financial viability of any construction project.
One of the greatest difficulties in the preliminary design phase of a project is providing an
accurate cost estimation, and subsequently, an accurate budget. A project can quickly go over
budget if a cost estimate is too optimistic, but a contract bid can be lost if the estimate is too
conservative.
One of the most critical aspects of cost estimation is data collection. Cost models are
developed and built based off of previously completed projects (Heemstra 1992). Unfortunately,
this means that a suitable number of projects must already be constructed to develop an accurate
assessment of the costs. Depending on the building site, there is limited data to pull from and
make empirical comparisons. There are also numerous factors that influence cost; many of which
are difficult to include in cost models.
7
A recent study performed by Peter de Jong and Sanders van Oss indicates the tremendous
level of complexity that develops with the creation of cost models used to accurately portray
high-rise buildings (Van Oss 2007). The study was performed in the Netherlands, but its
findings are universally applicable although costs will differ slightly based upon area.
Building costs correlate with the gross floor area (GFA), while revenues correlate with a
building’s lettable area (LA). When designing a high-rise, building efficiency is important in
determining the practicality of such a project and is defined by the ratio of LA/GFA. Table 2
shows typical building efficiency ranges of buildings at varying number of floors.
Table 2: Building Efficiency (Langdon 2002)
Increased verticality is associated with a drop-off in building efficiency. One reason behind this
decrease of efficiency is the requirement for elevators. In high-rises, elevators can take up to
about 5% of the GFA. Building efficiency can improve by optimizing the dimensions of the
floor slab, structural columns, and the interior core (Sev 2008). Figure 2 compares both number
of floors and GFA per floor to cost.
8
Figure 2: Increase of Building Costs in Relation to Height
and Size of Floor Plan (Van Oss 2007)
The figure suggests that the most inefficient designs are those with a high number of stories but a
low GFA. This should be intuitive as the requirement for vertical transport does not change, but
the capacity for lettable area decreases.
It was concluded that building costs increase about 8% every ten floors (Van Oss 2007).
This can fluctuate slightly based upon location and time frame. The cost increase stems mainly
from the structural elements and the additional elevators. Figure 3 and Figure 4 illustrate the
increased costs among various components of the building as the number of stories increase.
9
Figure 3: Increase of Building Costs (de Jong 2008)
Figure 4: Increase of Costs Due to Height (Van Oss 2007)
The figures above confirm that the main cost increases originate from the structural and elevator
requirements. It should also be noted that the foundation is one of the least affected components
in relation to the number of stories.
10
Difficulties with High-Rise Cost Estimation
Several costs that are associated with high rises are typically not accounted for in these
cost models. For example, there are greater requirements for a tall building’s plant and
distribution system, and the ability to supply adequate pressure up through the higher vertical
distances is increasingly cumbersome. The extra wind loading inevitably leads to heavier frames.
The movement of materials and the use of labor can be more difficult as well. There are also
amplified risks attached to large buildings with regards to enhanced safety measures and liability
concerns (de Jong 2008).
The credibility of any cost model generally stems from historical data that can be
compared easily based upon location, floor size, and other similar characteristics. The problem
with high-rise buildings is that there is a limited pool of data to use for an accurate cost
comparison. Cost models attempt to rectify these additional costs by implementing a “height
charge” factor to account for the more elaborate costs as shown in Table 3 (de Jong 2008).
Table 3: Height Charge (Gossow 2000)
These factors, however, are subjectively placed. One problem associated with using these height
factors is that some elements in a building are affected by the larger heights dramatically, while
others are not affected at all.
11
3 THE COST ESTIMATION SPREADSHEET (SFCCE)
This spreadsheet consists of four tabs: Floor System, Cladding, Constants, and W-Shapes.
The first two tabs require user input before any calculations can be performed. The spreadsheet
outputs include the weight and cost of the floor system and cladding as well as a graphical
representation of the floor system layout. The spreadsheet is formatted to be user-friendly, and
the cells designating inputs and outputs are color coded as indicated by Figure 5. The latter two
tabs of the spreadsheet store material properties and unit cost values which are referenced in
several of the calculations.
Figure 5: SFCCE Cell Color Legend
Floor System Tab
A screenshot of this tab, Figure 2-6, is provided at the end of the section. The figure
designates a number of inputs (shown in red) and outputs (shown in green), which are discussed
in greater detail in the following subsections.
12
3.1.1 Inputs
The first user input indicates the number of megacolumns in the structure (a). Once a
number has been entered, the corresponding number of rows for the ‘x’ and ‘y’ coordinate nodes
automatically appears (b). The user can then enter the coordinates of each megacolumn, bearing
in mind that the coordinates must be input in a sequential counter-clockwise order and form a
rectangular area in order for the building layout to be graphed correctly and the calculations to be
valid. The length and width of the concrete core are also input by the user (c).
The user may also input the type of occupancy to modify live loads (d). Currently, the
spreadsheet allows for residential, office, school, retail, and restaurant live loads. If other loads
types are desired, they can be manually added to the data validation table.
The last user input is the approximate number of miles away from the nearest
manufacturing plant (e). This information is used to calculate the transportation costs of all of
the materials.
3.1.2 Outputs
After the user fills out all the necessary inputs, the spreadsheet performs several
calculations and calculates the floor live load (a), floor dead load (d), and total floor cost (c).
However, the dead load cannot be adequately estimated until the floor slab and the structural
members supporting the floor slab are designed. Therefore, one of the first tasks accomplishes is
to design and graph the floor system (b).
Floor Live Load
The floor live load is the simplest output to determine. After the user selects the type of
floor occupancy, the corresponding live load appears.
13
Floor System Graph
Once the user inputs the number of megacolumns and the corresponding nodal coordinates,
they are automatically added as data points on the graph. The megacore is also included based
upon the user-defined dimensions. The starting and ending coordinates for each beam are then
determined. The girder beams have a starting node at each megacolumn and an end node at the
closest point on the megacore. The perimeter beams span from megacolumn to megacolumn, and
the intermediate beams span along the girders at an equal spacing to make sure that the slab does
not span more than twenty feet. There are a maximum of three intermediate beams that will act
as point loads on the girders. If more intermediate beams are required, an error message appears
explaining that the analysis cannot be performed with the current inputs.
Floor Dead Load
Once the nodes of each beam in the system are determined, their associated lengths are
calculated by the distance formula. They are then analyzed as simply supported members. The
perimeter and intermediate beams are stressed with uniform live and dead loads acting on the
slab while the girder beams are stressed with the point loads from each of the intermediate beams
in the floor system. Once the reactions and moments are calculated, the spreadsheet optimizes
beam shapes with a simple loop in Visual Basic to ensure that the provided elastic section
modulus ‘S’ of a given shape is larger than the required elastic section modulus calculated by the
formula below.
14
Where = Allowable bending moment stress = 30 ksi
M = Bending moment in steel member
= Elastic section modulus
1
The spreadsheet uses the Allowable Strength Design (ASD) instead of Load Reduction
Factor Design (LRFD) in order to be consistent with the values provided in the constants tab.
After the beam shapes are optimized in the floor system, the total steel weight and cost can then
be calculated.
Total Floor Cost
The total cost is the calculated sum of material, labor, transportation, and equipment and
craning costs. The material costs are calculated by using the total weight of steel and concrete
and multiplying by their corresponding unit material cost. Labor costs are influenced by a
significant number of factors, which typically range from 30% - 40% of the material costs. The
spreadsheet assumes a conservative value of 40% of the total concrete and steel cost for labor. A
constant value of 6 cents per ton per mile is used as an estimate for shipping costs. The total
transportation costs are then determined by using the total weight, the total shipping distance,
and the cost per ton per mile.
The equipment and craning costs are influenced by both the total floor area and the
number of stories. The first step of approximating the equipment and craning costs is to estimate
the time of construction. The spreadsheet calculation uses simple ratios between the user defined
floor area and that of the Pearl River Tower in Guangzhou, China. Similarly, it uses a ratio for
15
the number of stories (input on the Cladding Tab). These ratios are then used to approximate the
number of weeks of construction as indicated in Table 4. Once a timetable is established, the
appropriate number of cranes to procure to complete construction is estimated. Table 5 shows the
approximate cost of operation per week of several different crane sizes and is derived from an
existing table from C&S Crane & Rigging Inc. The table also indicates the allowable lift capacity
of each crane at a specified radius with 25 ft., 50 ft., and 100 ft. options. The spreadsheet takes
into account the tonnage of the floor system and the floor area to approximate the number of
cranes. The number of cranes required can then be multiplied by the weekly operation rate to
estimate the equipment and craning costs.
Table 4: Approximate Time of Construction
Table 5: Weekly Crane Costs and Crane Capacity
16
Figure 2-6: Screenshot of the Floor System Tab
17
Cladding Tab
A screenshot of this tab, Figure 2-7, is provided at the end of the section. The figure
designates a number of inputs (shown in red) and outputs (shown in green), which are discussed
in greater detail in the following subsections.
3.2.1 Inputs
The first few inputs on this tab are the story height and the number of stories (a). These
parameters, along with the floor system dimensions input from the previous tab are used to
calculate the total surface area of the building (a). Although the total surface area is calculated
by default, it is delineated as an input because the value may be overridden by the user. In such
cases, the user may opt to use the surface area pulled from the skyscraper model if more complex
geometry is to be accounted for such as tapered buildings.
The user also has the ability to choose between three typical architectural cladding
panels: precast concrete, glass fiber reinforced concrete (GFRC), and thinshell (b). The
percentage between concrete cladding panels and exterior glass curtain walls can also be input by
the user (c).
Again, the last user input is the approximate number of miles away from the nearest
manufacturing plant (d). This information is used to calculate the transportation costs of all of
the materials.
3.2.2 Output
18
The cladding tab has two main outputs: the dead load (b), and total floor cost (a).
A list of the cladding options and their associated properties, courtesy of Willis Construction Co.
Inc., is provided in Table 6. This table is used to calculate the desired outputs.
Table 6: Architectural Cladding Properties
Dead Load
The weight of the selected cladding option (in psf) is multiplied by the total surface area
to determine the dead load. This value was found to be quite close to the estimated value in Dr.
Balling’s “5ex_Skyscraper_Formulas.xlsm” spreadsheet when architectural precast cladding was
selected. The other options, because they are much lighter, reduce the total dead weight
substantially.
Total Floor Cost
The total cost is the calculated sum of material, labor, transportation, and equipment and
craning costs. The labor and material cost are analogous to the weight calculation and are
determined by multiplying the cost (in psf) by the total surface area. Calculating the
transportation costs is the same as the calculations for the floor system. A constant value of 6
cents per ton per mile is used as an estimate for shipping costs. The total transportation costs are
then determined by using the total weight, the total shipping distance, and the cost per ton per
mile. The equipment and craning costs for cladding are based off of a simple linear interpolation
of story heights and corresponding craning costs; with user input between 8 and 120 stories, it
determines a value between $800/ton and $1300/ton.
19
Figure 2-7: Screenshot of the Cladding Tab
20
Additional Tabs
The constants tab is pulled directly from the “5ex_Skyscraper_Formulas.xlsm”
spreadsheet. This tab contains the relevant properties and cost values for concrete and steel that
are used in the floor system and cladding calculations. The W-Shapes tab is essentially an
abridgment of the AISC database; it includes W36 shapes or smaller while excluding shapes that
are slender in bending. See Figure 2-8 for a screenshot of this tab.
Figure 2-8: Screenshot of the Constants Tab
21
4 ASSUMPTIONS AND LIMITATIONS
Assumptions
The spreadsheet makes several assumptions that are acknowledged and addressed in this
section. The first key assumption was that the deflection of a beam would not control the design
due to the rigidity of the floor slab. Under this assumption, deflection calculations were not
required or performed. Subsequently, bending moment was the governing stress for beam design
in the floor system.
Each beam was modeled as a simply supported member, an assumption used to simplify
calculations. The steel members in a megastructure, however, will typically employ fixed
connections. For example, the wide-flange spandrel beams of the Pearl River Tower are
connected to the exterior columns at each floor to form moment frames for the lateral force
resisting system of the structure (Tomlinson 2014).
The max span of a 10 inch floor slab was assumed to be 20 feet. The spreadsheet does not
allow for dynamic input on the thickness of the slab, nor does it calculate the necessary amount
of reinforcement to include in the slab.
The girder beams in the spreadsheet were modeled with point loads from the intermediate
beams. The point loads were assumed to be significantly larger than the weight of the girders
themselves; therefore, the self-weight was neglected in the moment calculations. Superposition
22
of both the point loads and the uniform self-weight load could have been employed to be more
precise in determining the beam shapes.
There are two section modulus properties: the elastic section modulus (S) and the plastic
section modulus (Z). The former is used for materials up to the yield point; the latter is used for
materials after elastic yielding has occurred up until the formation of a plastic hinge. This
spreadsheet assumes structural failure of a member once any yielding has occurred and compares
the allowable elastic section modulus with the required. If the plastic section modulus was used
instead, the beams would have a higher capacity and smaller shapes could be used in the analysis
of the floor system.
Limitations
Although the spreadsheet makes great strides towards finding more precise weights and
costs, it is not without its flaws and limitations. The spreadsheet is only applicable to skyscrapers
with rectangular floor systems and rectangular cores. This proved to be one of the most
significant drawbacks. Groups in the most recent China Megastructures study abroad program,
had many unique designs which the spreadsheet was incapable of. As shown in Figure 2-9,
Figure 2-10, and Figure 2-11, the floor systems for each group were comprised of various shapes
that were incompatible with the current functionality of the spreadsheet. These floor systems
had to be manually graphed and evaluated, indicating the need for a much more general graphing
function that can support various shapes. It was evident that the concrete core would also need to
support multiple shapes.
The spreadsheet also restricts the quantity of megacolumns to a maximum number of
twenty. This seemed like a reasonable cap in the initial setup of the spreadsheet; yet, it still
23
presented an obstacle for one of the groups as shown in Figure 2-12. The floor system in
question had a rectangular shaped floor plan and a rectangular core, but it also had 24
megacolumns along its perimeter. There were not enough nodes available to automatically
design the floor system. The limitations of the spreadsheet were considerably more apparent as
the spreadsheet continued to develop.
The spreadsheet relied on Visual Basic coding to optimize the steel shapes used in the floor
system. The code requires going back and forth between both Visual Basic and Excel programs
through multiple iterations and causes a slight lag time. If the calculations were designed
entirely in one program, the results would be produced much quicker.
Figure 2-9: Floor System of the “Guangzhou Group”
24
Figure 2-10: Floor System of the “Hong Kong Group”
Figure 2-11: Floor System of the “Shenzhen Group”
25
Figure 2-12: Floor System of the “Beijing Group”
Future Improvements
The most significant improvement of the spreadsheet would enable the user to input node
coordinates for megacolumns without restrictions on the shape of the floor system or the
concrete core.
The Visual Basic for Applications (VBA) code runs much slower than originally
anticipated. The existing code requires storing variables from excel, running an iteration, and
then rewriting the new variables into Excel. This process introduces a substantial amount of lag
associated with performing multiple iterations but can be effectively nullified if the W-shape
database was stored in VBA as an array and all required calculations were executed directly from
the code. Only the final results would be written in Excel.
The original assumption that deflection would not govern became very questionable as
the project developed. It simplified calculations, but with such large spans, deflection checks
26
would certainly be required to produce sensible results. It would also be beneficial in future
versions to indicate which failure criterion governs for each beam: deflection or bending
moment.
The slab thickness, in future versions, should act as a dynamic input. The design thickness
was set to ten inches, with a constant maximum span of twenty feet. This leads to a
tremendously heavy floor design that is overly conservative. It would be far more beneficial for
the user to input a desired thickness, which can be linked to a corresponding maximum span.
27
5 CONCLUSIONS
The SFCCE spreadsheet acts as a predecessor to the “5ex_Skyscraper_Formulas.xlsm”
and can be a valuable tool to provide a preliminary cost estimate for both the floor system and
the exterior cladding of a high-rise structure. The spreadsheet automates the initial design of the
concrete slab and optimizes beam shapes according to ASD loading. The total steel and concrete
material used in the floor system is calculated and the average weight (in force/area) is provided
as an output. In addition to material costs, the spreadsheet incorporates transportation, labor, and
equipment and craning costs. Although the spreadsheet produces reasonable results; it is not
without its limitations. The spreadsheet is capable of evaluating only rectangular shaped floor
plans with rectangular cores. This weakness in the spreadsheet means that a vast number of
possible skyscraper designs are incapable of being analyzed. There is an inherent need to
improve upon the existing spreadsheet to include any floor-print, regardless of the complexity of
shape.
28
29
REFERENCES
Bailley SF, Smith IFC. Case-based preliminary building design. J Comput Civ Eng 1994;8:455–
68. De Jong, Peter, H. Wamelink. (2008) Delft University of Technology “Building cost and eco-
cost aspects of tall buildings.” CTBUH Journal De Jong, Peter, Sander van Oss.”High rise costs” Architecture, Real Estate & Housing. Delft
University of Technology Gossow, V. (2000) Schlüsselfertiger Hochbau. Wiesbaden: Vieweg Heemstra, F. J. “Software cost estimation” (Oct 1992) Vol 34 No 10. Twente University Langdon, D. and Watts, S. (2002). Costs of building a 48-storey tower in Central London.
Building, no. 6 Maher ML. HI-RISE: a knowledge-based expert system for the preliminary structural design of
high rise buildings. PhD thesis, Department of Civil Engineering, Carnegie-Mellon University; 1984.
Nimtawat, Anan, Pruettha Nanakorn. “Automated layout design of beam-slab floors using a
genetic algorithm” (Nov 2009) Vol 87, Issues 21-22 Nimtawat, Anan, Pruettha Nanakorn. “A genetic algorithm for beam-slab layout design of
rectilinear floors”. (Nov 2010) Vol 32 Issue 11 Rodrigues, Eugenio. “Automated Floor Plan Design: Generation, Simulation, and Optimization”
University of Coimbra (2014) Sev, Aysin, Aydan Ozgen. “Space Efficiency in High-Rise Office Buildings” (2008) Tomlinson, Richard, William Baker, Luke Leung, Shean Chien, and Yue Zhu. (2014)“Case
Study: Pearl River Tower, Guangzhou” CTBUH Journal Issue 2
30
Syrmakezis CA, Mikroudis CA, Rouva S. Development of the VK.Expert system for computer-aided preliminary design of reinforced concrete buildings. Inf Process Civ Struct Eng Des 1996:45–51.
Tsakalias GE. KTISMA: a blackboard system for structural model synthesis of asymmetrical
skeletal reinforced concrete buildings. Artif Intell Object Oriented Approaches Struct Eng 1994:15–21.
Van Oss, Sander. (2007) “Higher is more expensive”. Architecture, Real Estate & Housing. Delft
University of Technology
31