Reconfiguration of The Six Points Interchange
Community Update #1June 17, 2013
![Page 2: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/2.jpg)
Presentation Index
1. Project Description2. Project Timeline3. Schedule4. Build Toronto5. Existing Road Network6. Proposed Road Network/Plan7. Typical Cross Sections8. District Energy9. Next Steps
![Page 3: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/3.jpg)
Project Description
![Page 4: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/4.jpg)
Project Timeline
![Page 5: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/5.jpg)
Project Timeline
![Page 6: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/6.jpg)
Schedule
![Page 7: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/7.jpg)
Build Toronto
BUILD TORONTO is the real estate and development corporation created to generate value from the City’s real estate assets.
Build Toronto Mandate: To create value from the City’s underutilized real estate assets and generate a net financial return to the City.
Build Toronto Vision: To maximize value in a responsible, innovative and integrated manner, creating City Building opportunity and enhancing Toronto’s economic competitiveness.
Build Toronto Involvement at Six Points:• Completion of Soils and Geotechnical Investigation• Completion of Westwood Theatre demolition and site preparation• Planning future development within the reconfigured road network
![Page 8: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/8.jpg)
Existing Road Network
![Page 9: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/9.jpg)
Existing Road Network
![Page 10: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/10.jpg)
Proposed Road Network
![Page 11: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/11.jpg)
Proposed Plan
![Page 12: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/12.jpg)
Typical Cross Section-Dundas Street
![Page 13: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/13.jpg)
Typical Cross Section-Bloor Street West
![Page 14: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/14.jpg)
Typical Cross Section-Kipling Avenue
![Page 15: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/15.jpg)
Typical Cross Section-Dunbloor Road
![Page 16: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/16.jpg)
Typical Cross Section-Beamish Drive
![Page 17: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/17.jpg)
District Energy
![Page 18: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/18.jpg)
District Energy
![Page 19: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/19.jpg)
District Energy
![Page 20: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/20.jpg)
District Energy
![Page 21: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/21.jpg)
District Energy
![Page 22: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/22.jpg)
District Energy
![Page 23: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/23.jpg)
District Energy
![Page 24: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/24.jpg)
District Energy
![Page 25: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/25.jpg)
Next Steps
Completion of Soils and Geotechnical Investigation
Completion of Westwood Theatre Demolition and Site Preparation
Development of Traffic Management and Construction Staging Plans
Coordination of Utility Relocation Requirements
Continuation of the Detailed Design and Contract Tender Preparation
Next Community Update is planned for February, 2014
![Page 26: Six Points Reconfiguration - Community Update June, 2013](https://reader034.fdocuments.us/reader034/viewer/2022052621/557cf0acd8b42ae6078b5264/html5/thumbnails/26.jpg)
Next Steps
For comments and further information, please contact:
Mike LoganPublic Consultation UnitCity of [email protected]
Project Website: toronto.ca/involved/projects/6points