Site Visit Report - Environmental Protection Agency · Sulphur Dioxide FTIR by MKS MG2030 Nitrous...
Transcript of Site Visit Report - Environmental Protection Agency · Sulphur Dioxide FTIR by MKS MG2030 Nitrous...
Site Visit Report
The site visit process is a sample on a particular day of an installation's compliance with some of its licence conditions. Where non-compliance against a particular condition has not been reported, this should not be construed to mean that there is full compliance with that condition of the licence.
Instructions and actions arising from the visit shall be addressed, or where applicable noted, by the licensee in order to ensure compliance, to improve the environmental performance of the installation and to provide clarification on certain issues.
The licensee shall take the actions specified to close out the non-compliances and observations raised in this Site Visit Report.
Licensee
Name of Installation Edenderry Power Limited
Licensee Edenderry Power Limited
Licence Register No. P0482-04
CRO Number 278071
Site Address Ballykilleen, Edenderry, Offaly
Site Visit Reference No. SV08119
Report Detail
Issue Date 03/01/2017
Prepared By David Matthews
Site Visit Detail
Date Of Inspection 28/09/2016 Announced No
Time In 13:00 Time Out 14:00
Visited by on behalf of the EPA Exova Ltd.
Licensee Personnel and Role See report.
Photo Taken No Samples Taken Yes Video Taken No
Site Visit Report - SV08119 - Edenderry Power Limited Page 1 of 42
Scope
This is a report on monitoring of emissions to atmosphere at this site. Please find the detailed technical report attached.
Media
Air.
Site Areas Inspected
See report.
Documents Inspected
See report.
Site Visit Report - SV08119 - Edenderry Power Limited Page 2 of 42
ISO/IEC 17025 Accredited Legal Entity, UKAS Accredited Testing Laboratory No. 4279Exova (UK) Ltd trading as Exova Catalyst & Exova Catalyst Ireland
Unit C5, Emery Court, The Embankment Business Park, Stockport, SK4 3GL
Exova Catalyst Ireland, Unit D8 North City Business Park, North Road, Finglas, Dublin 11T: +353 86 853 8247
E: [email protected] Exova Catalyst Ireland Contact: Nick Kenny (+353 86 853 8247)
EdenderryBallykillen
Edenderry Power Ltd
Co. Offaly
EPA Office of Environmental Enforcement
A1-1 Main Boiler
EMISSIONS REPORT(Prepared on behalf of the EPA by Exova Catalyst - EPA Contract No. OEE-14-DS)
-
-
EPA AIR EMISSIONS COMPLIANCE MONITORING
Stack Reference
Industrial Emissions Licence: P0482-04
Stack Emissions Testing Report Commissioned by
Installation Name & Address
Signature of Report Approver
Version 2
Donal O Faogain
3rd January 2017Report Date
TE1 TE2 TE3 TE4
Version
Team Leader
Deputy Regional Manager
TE1 TE2 TE3 TE4MM08 922
MCERTS Level 2
Patrick O'BrienReport Approved by
MM13 1259MCERTS Level 2
28th - 29th September 2016
Job Reference NumberP0482-04CAR-16-01
Dates of the Monitoring Campaign
Report Written by
Site Visit Report - SV08119 - Edenderry Power Limited Page 4 of 42
TITLE PAGE
CONTENTS
Summary of Sampling Deviations
EXECUTIVE SUMMARY
Monitoring Objectives
Monitoring Results
Monitoring Dates & Times
Process Details
Monitoring & Analytical Methods
Sampling Location
Plant Photos / Sample Points
APPENDIX 1 - Monitoring Personnel & List of Equipment
APPENDIX 2 - Raw Data, Sampling Equations & Charts
Opinions and interpretations expressed herein are outside the scope of Exova Catalyst Ireland's ISO 17025 accreditation.
9
3
5
6
8
4
2
7
CONTENTS
The testing performed fully meets the technical requirements in Irish EPA Guidance Note, AG2.
This test report shall not be reproduced, except in full, without the written approval of Exova Catalyst Ireland.
This version of the test report supersedes the previous version of the test report. Please destroy all previous versions to ensure no confusion arises from having multiple test reports in existence.
CAT-RT (Version BP)Page 2 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 5 of 42
Overall Aim of the Monitoring Campaign
Special Requirements
Target Parameters
Total Particulate Matter | Oxides of Nitrogen (as NO₂) | Nitrous Oxide | Sulphur Dioxide |
MONITORING OBJECTIVES
Executive Summary
Exova Catalyst Ireland were commissioned by EPA Office of Environmental Enforcement to carry out stack emissions testing at Edenderry Power Ltd on the A1-1 Main Boiler at Edenderry.
The aim of the monitoring campaign was to demonstrate compliance with a set of emission limit values (ELVs) as specified in the Site's Permit.
There were no special requirements.
A1-1 Main Boiler28th - 29th September 2016
(Page 1 of 7)
Edenderry Power Ltd, Edenderry
CAT-RT (Version BP)Page 3 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 6 of 42
where MU = Measurement Uncertainty associated with the Result
Parameter
Total Particulate Matter ¹
Oxides of Nitrogen (as NO₂) ¹ - -Nitrous Oxide ¹ - -Sulphur Dioxide ¹ - -Oxygen Dry
Water Vapour Stack Gas TemperatureStack Gas Velocity
¹
- -NOTE: VOLUMETRIC FLOW RATE & VELOCITY DATA TAKEN FROM THE PRELIMINARY VELOCITY TRAVERSE.
¹ Reference Conditions (REF) are: 273K, 101.3kPa, dry gas, 6% oxygen.
Limit485000
-
g/hr
g/hr
19135m³/hr
Limit+/-
Units
mg/m³mg/m³
8982-
0.18
% v/v
23.7
73.16
m/s
0.91163.1
0.95mg/m³mg/m³
4.5160015.29
325g/hr0.18
Edenderry Power Ltd, Edenderry
`
g/hr 151248.10+/-
Units Result
Concentration
MU
(Page 2 of 7)
-
200.0
% v/v21.3
417210
0.38
774532m³/hr
20067
Result LimitMU
A1-1 Main Boiler
-
Executive Summary
Mass Emission
50
Volumetric Flow Rate (REF)
398.4 -
2.88
MONITORING RESULTS
137893
9.42 -
°C
Volumetric Flow Rate (ACTUAL)
83449 5486
330.5
35523
CAT-RT (Version BP)Page 4 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 7 of 42
Parameter
R1 - -R1 -R1 - -R1 - -R1 - -R1 -R1
All results are expressed at the respective reference conditions.
Date(s)Mass Emission
g/hr
08:25 - 08:4523.0
Velocity & Volumetric Flow Rate
MONITORING DATE(S) & TIMES
mins
08:50 - 09:4929/09/201629/09/2016
% v/v
g/hr
200.0
08:48 - 09:48
A1-1 Main Boiler28th - 29th September 2016
Executive Summary
SamplingTimes
Concentration
29/09/2016
Sampling
20067
Units
Edenderry Power Ltd, Edenderry
60
(Page 3 of 7)
Water Vapour
mg/m³
60
DurationUnits
Total Particulate Matter 48.1mg/m³
% v/v60
08:50 - 09:49
4.51
60
8344973.2 60
Oxides of Nitrogen (as NO₂)Nitrous Oxide
08:50 - 09:49
08:50 - 09:49
29/09/201629/09/2016
Sulphur Dioxide 330.5
6008:50 - 09:490.18
g/hrg/hr
mg/m³ 29/09/2016
Oxygen
137893
mg/m³29/09/2016
CAT-RT (Version BP)Page 5 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 8 of 42
Standard Operating Conditions
Value
Feedstock (if applicable)
Edenderry Power Ltd, Edenderry
Power GenerationCapacity (of 100%) and Tonnes / HourContinuous or Batch Process
Solid FuelOn
Continuous
Abatement SystemAbatement System Running Status
Plume Appearance
Electrostatic Precipitator
Parameter
A1-1 Main Boiler28th - 29th September 2016
Normal operating conditions
Peat and biomass
FuelVisible
(Page 4 of 7)Executive Summary
PROCESS DETAILS
Process Status
CAT-RT (Version BP)Page 6 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 9 of 42
2.68 mg/m³
CAT
Yes
Yes
CAT-TP-05 0.1 % v/vCAT-TP-05 YesEN 14790EN 14789 CAT-TP-21 Yes
TGN M22 FTIR by Gasmet Technologies Oy DX4000
Dry Zirconia Cell by Horiba PG-250
CAT
0.15 mg/m³
CAT-TP-22(b)
CATOxygen
FTIR by MKS MG2030Sulphur DioxideNitrous Oxide
YesTGN M22
Water VapourYes 1.2 m/s
0.1 %
CAT
ANALYSIS LABORATORIES
TGN M22FTIR by MKS MG2030
YesYes
(with short name reference as appears in the table above)
Exova Catalyst (CAT)
FTIR by MKS MG2030
YesCAT Yes
CATYesCAT-TP-22(b)
CAT
ISO 17025 Accreditation Number: 4279
CATCAT-TP-22(b)
Yes
Yes
CAT-TP-22(b)
0.02 %
CAT-TP-41
(Average)
Yes
Analytical
GravimetricWater Vapour
Yes
Velocity & Vol. Flow Rate
TGN M22
(Page 5 of 7)
Testing ISOStandard
CAT-TP-01 Gravimetric
MCERTS17025
Testing
0.09 mg/m³Yes
Analytical LOD
Edenderry Power Ltd, Edenderry
Analysis
Total Particulate Matter EN 13284-1
Lab
Yes
ISOLab
Technical
CAT-TP-03
A1-1 Main Boiler
0.51 mg/m³
28th - 29th September 2016
Analysis17025
Analysis
Monitoring
CAT
ParameterProcedure
Oxides of Nitrogen (as NO₂)
TechniqueProcedure
Executive Summary
Testing
CAT
EN 16911-1 (MID)
MONITORING & ANALYTICAL METHODS
Pitot Tube and ThermocoupleYes
SUMMARY OF SAMPLING DEVIATIONS
1Total Particulate Matter
Deviation
Due to the restricted access, it was not possible to sample at all of the sample points on the available sampling lines.
SUMMARY OF SAMPLING DEVIATIONS
Parameter Run
CAT-RT (Version BP)Page 7 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 10 of 42
Duct Characteristics Location of Sampling Platform
Platform Details
Sampling Location / Platform Improvement Recommendations
-
-
Sufficient working area to manipulate probe and operate the measuring instruments
Type3.40
Parameter
There are no obstructions present which hamper insertion of sampling equipment
(Page 6 of 7)
Permanent
Safe Access Available
Value
Platform has 2 levels of handrails (approx. 0.5m & 1.0m high)
Executive Summary
cm
Inside / Outside
Yes
-
Units
Sample Port Size
Circular
Value
Vertical
Yes
Width
All platforms should be designed in accordance with the requirements in EPA Guidance Note AG1 and EN 15259.
General Platform Information
Permanent / Temporary Platform
-
m²m
Yes
9
Platform has vertical base boards (approx. 0.25m high)YesYes
SUITABILITY OF SAMPLING LOCATION
Outside
Irish EPA Technical Guidance Note AG1 / EN 15259 Platform Requirements
Port Depth
YesYes
Platform has chains / self closing gates at top of ladders
Value
m
9.08
Orientation of Duct
Area
4" BSP
Easy Access Available
Depth
EN 15259 Homogeneity Test Requirements
Sampling Plane Validation Criteria (from EN 15259)
-
-
-
-
-
--m/s
Maximum Angle of Swirl Yes
--Units
-
-
-
No Local Negative Flow
Mean Velocity> 5 Pa Yes
- --8 -°
--
There is no requirement to perform a EN 15259 Homogeneity Test on this Stack.
267.0
- Compliant
Yes
All platforms should be designed in accordance with the requirements in EPA Guidance Note AG1 and EN 15259.
Criteria in EN 15259
0.001.10
-
Ratio of Above : 1 Yes< 15°
-
-
< 3 : 10.00
--
Traverse 1
m/s-
Lowest Gas Velocitym/s
-
22.64-
-
Required
--23.69
Pa
-
Yes
Highest Gas Velocity
--
Lowest Differential Pressure
24.82
--
0.00
-
0.00
CAT-RT (Version BP)Page 8 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 11 of 42
Photo 2
PLANT PHOTOS
(Page 7 of 7)
Photo 1
Photo 4Photo 3
Executive Summary
SAMPLE POINTS
where = isokinetic point sampled at
= isokinetic point not sampled at
= combustion gases sample point= non-isokinetic sample point
Line B
Line A
B1
A1
B2
B3
B4
B5
B6
A2A3A4A5
A6
CAT-RT (Version BP)Page 9 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 12 of 42
APPENDIX 1 - Stack Emissions Monitoring Personnel, List of Equipment & Methods and Technical Procedures Used
APPENDIX 2 - Summaries, Calculations, Raw Data and Charts
APPENDIX CONTENTS
APPENDICES
CAT-RT (Version BP)Page 10 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 13 of 42
Bioaerosols Temperature Logger -Electronic Refrigerator -
StopwatchServomex 4900
-CAT 19.1
Position
CAT 3.27SELECT Horiba Model (2)
MM13 1259 TE1 TE2 TE3 TE4Technician James Magann MCERTS Level 2 MM13 1330 TE1
-
Digital Manometer (2)
Box Thermocouples (2)Box Thermocouples (1)
-
Equipment Type
-
-
-
MKS MG2030
CAT 21S.46
CAT 7.15
Miscellaneous Items
Digital Temperature Meter
Heated Probe (3) -CAT 6.44
Eco Physics CLD 822Mh
Stack Thermocouple (1)
Gasmet Sampling SystemCAT 5.13Heated Probe (2)
500g / 1Kg Check WeightsLast Impinger ArmCallipers
- 20m Heated Line (1)
Bernath 3006 FID --
- 1m Heated Line (2)
CAT 11.53SELECT Logger 2 -
Dual Channel Heater Controller -CAT 17.1-
ABB AO2020-URAS26
MCERTS Number
Equipment Type
Control Box DGM (2)
-
Donal O Faogain MCERTS Level 2
Mass Flow Controller (2) CAT 6.45 -
Stack Thermocouple (3)Stack Thermocouple (2)
Equipment I.D.
STACK EMISSIONS MONITORING PERSONNEL
APPENDIX 1
15m Heated Line (1)
JCT JCC P1 Cooler
CAT 13.22
Mass Flow Controller (1)
Extractive Sampling
LIST OF EQUIPMENT
-
-
Umbilical (2) Servomex 5200MP
-
CAT 17.1 CAT 25.12
Tubes Kit Thermocouple -
CAT 20.124
Heated Probe (1)
--
-
CAT 3.62-
Mass View (2)
CAT 12.66
CAT 19.9-
M&C PSS
BarometerUmbilical (1)
Hioki 5031 (mA)
Technical Endorsements
Team Leader
Equipment Type
CAT 4.695
5m Heated Line (1) -
Site BalanceMass View (1) CAT 25.11
20m Heated Line (2)
Oven Box (1)
CAT 20.124
-
S-Pitot (1)
L-Pitot-
Equipment I.D.Digital Manometer (1)Horiba PG-250
MCERTS Accreditation
Single Channel Heater ControllerLaboratory Balance CAT 1.18 / 1.18aTape Measure CAT 16.94
Equipment I.D.
1m Heated Line (3)
Control Box DGM (1)
CAT 23.3
Instrumental Analysers
S-Pitot (2) -
-
CAT 14.53
Name
CAT 3.27
Oven Box (2)CAT 19.4 1m Heated Line (1)
METHODS & TECHNICAL PROCEDURES USED
Velocity & Vol. Flow Rate
Nitrous Oxide CAT-TP-22(b)CAT-TP-22(b)
CAT-TP-21
EN 16911-1 (MID) CAT-TP-41
CAT-TP-22(b)CAT-TP-22(b)
Oxides of Nitrogen (as NO₂)
EN 14790EN 14789
Water VapourSulphur Dioxide
Parameter
Total Particulate MatterWater VapourOxygen
EN 13284-1
Technical ProcedureStandard
CAT-TP-01
TGN M22TGN M22TGN M22TGN M22
CAT-TP-05
CAT-RT (Version BP)Page 11 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 14 of 42
General Stack Details
Stack Gas Composition & Molecular Weights
CO₂ (Estimated)
O₂
Moisture (H₂O)
Where: p = M / 22.41
pi = r x p
Calculation of Stack Gas Densities
Stack Diameter / Depth, D
0.84
Value
3.40
101.2
Average Stack Gas Temperature, Ta
-0.414
-
Units
Pa
m²
PRELIMINARY STACK SURVEY: CALCULATIONS
°C
Average Stack Static Pressure, Pstatic
Stack Area, A
292.5
9.08mStack Width, W
163.1
Average Barometric Pressure, Pb
m
Stack Details (from Traverse)
APPENDIX 2
0.05
Average Stack Gas Pressure
21.3395.43
-
Volume
Average Pitot Tube Calibration Coefficient, Cp
ppm kg/m³Conc
0.06438-0.9543 28.01
1.9635
kg/m³
kPakPa
0.00118
Conc
MWet
r% v/vFraction
DensityDry
0.17145
4.51 32.00
Conc
0.2133
3.550.06
N₂1.4277
Molar Conc
1.1927375.0718.02
0.0006
p pi
MassComponent
--
0.0451-
0.8037
% v/v
44.01
-1.2498
Calculation of Stack Gas Densities
Where: P STD = sum of component concentrations, kg/m³ (not including water vapour)
P STW = sum of all wet concentrations / 100 x density, kg/m³ (including water vapour)
P Actual = P STD x (TSTP / (PSTP)) x ((Pstatic + Pb) / Ta)
P ActualW (at each sampling point) = P STW x (Ts / Ps) x (Pa / Ta)
Calculation of Stack Gas Volumetric Flowrate, Q
Gas Volumetric Flowrate (from Traverse)
Average Wet Density (Actual), P ActualW
kg/m³
ResultUnits
kg/m³
m³/hr
Total Pressure
kg/m³
kPa
1.258Dry Density (STP), P STD
Determinand
417210
kg/m³
m³/hr
Result
°C
m³/hr
REF ¹
Oxygen (Dry)
0.723
Dry Density (Actual), P Actual
m³/hrGas Volumetric Flowrate (STP, Dry)
21.33
Units
Gas Volumetric Flowrate (Actual)
-0.0
Actual
4.5
101.3163.1100.8
Temperature
%
Units
0.00
0.784
Wet Density (STP), P STW
Gas Volumetric Flowrate REF ¹
%
Gas Volumetric Flowrate (STP, Wet)
Moisture
379499
Duct gas flow conditions
482402774532
1.161
6.0
CAT-RT (Version BP)Page 12 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 15 of 42
Parameter Parameter
Date of Survey Initial Pitot Leak CheckTime of Survey Final Pitot Leak CheckAtmospheric Pressure Orientation of DuctAverage Stack Static Pressure Pitot Tube, Cp
Result of Pitot Stagnation Test Number of Lines AvailableAre Water Droplets Present? Number of Lines UsedDevice Used
0.725
279.0
Wet Density
Pa 0.84
S-Type Pitot with KIMO MP 200 (500Pa)
-414 -22
29/09/2016
Value
-
Units
-
(1 of 1)
Depth
-
Velocity
Units
APPENDIX 2
∆P Temp°
162.0
48.0
288.02.1
0.723
-
-
Traverse
0.723
101.2
Pass
∆P
-
Sampling Line A
0.7235163.0163.0
-418.0
2.0
0.723
0.723
287.0
2.90
4.0293.0
24.00
23.570.09
23.72
1
0.723163.00.50
163.0 1.0
0.723
kg/m³Point
162.0
24.20
282.0
304.023.72
23.17
2.63
20.725
0.77
Temp
5.0
°C
299.0
2.0
°
282.0279.0
m/s°C-409.0
162.0
305.0
Mean
0.28
163.0
4.03
163.1
23.4924.20
23.24
0.723
PRELIMINARY STACK SURVEY: VELOCITY TRAVERSE TO EN 16911-1 (MID)
Swirl
Vertical
Pass
0.725
m/sPa
0.725
m
23.966.0
kg/m³STATIC (Units: Pa)
Value
6.0
Sampling Line B
Pa
163.0300.0
83.12
-
0.722
2.0
08:25 - 08:45
4.0
23.3823.82
163.0 0.723
5.09 23.1724.30 4.0 164.0
24.8224.16
23.47
284.0
163.0
10
0.723
24.07
164.0
2.246
164.03.0
295.0 164.0
301.0 0.7220.722
0.7220.722
5.0
71.0
164.0
5.0267.0
307.0279.0
164.00.722
321.0 163.04.0293.0
3.31
22.64
305.0
289.4 163.1
0.723
295.6
Pass
1.16
23.2423.82
3.0
0.72323.12
163.0
162.0
kPa
-
Wet Density
-
VelocitySwirl
No
- - --
--
- ----
-
-
---
-
-
-
-
-
-
--
-
-
-- --
- -
-- - ---
--
--
--
-
-
--
-
-
- -
-
---
-
----
-
----
-------
--
CAT-RT (Version BP)Page 13 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 16 of 42
3.548- 0.047
u(φO₂,d) 0.138
u(φCO₂,w) 0.002
5.667
(1 of 1)
Standard uncertainty associated with the local velocities
u(Cf)
u(cal) 8.908
u(φO₂,w)
-Pa
m/s
-
u(φCO₂,d) 0.002
-u(M) 0.00011
0.241u(v)
APPENDIX 2
u(φH₂O) 1.088
-
u(ρ) 0.00390
Standard Uncertainty on the coefficient of the Pitot Tube
PRELIMINARY STACK SURVEY: VELOCITY TRAVERSE TO EN 16911-1 (MID) - MEASUREMENT UNCERTAINTY
Performance characteristics (Uncertainty Components)
Standard uncertainty associated with the stack temperature
Standard uncertainty associated with the mean velocity
- Resolution- Calibration
- Water Vapour- Oxygen, wet- Carbon Dioxide, wet
- φCO₂,w- Oxygen, dry- Carbon Dioxide, dry
u(fit) 22.118
Standard Uncertainty associated with the mean local dynamic pressures u(∆pi)
Standard uncertainty associated with the mean velocity (95% Confidence) m/sUc,rel(v) 0.74
0.175
UnitsValueUncertainty
- Atmospheric Pressure
u(drift) 0.083
Ku(pc) 175.738
0.119
u(Tc) 2.225
u(k) 0.005Pa
u(res) 0.00087
31.111
0.089Uc(v)
Standard uncertainty associated with the mean velocity (95% Confidence), relative
Standard uncertainty associated with the absolute pressure in the duct
- Drift- Lack of Fit- Overall corrections to dynamic measurementsStandard uncertainty associated with the molar mass of the gas- φO₂,w
%
- Static PressureStandard uncertainty associated with the density in the duct
u(vi)
Pau(patm) 175.692u(pstat) 4.007
- u²(a)/a²- u²(qV,w)/q²V,w
-35523.0 m³/hr
- u²(qV,w)
Uc,rel(v) 0.74Standard uncertainty associated with the volume flow rate (95% Confidence)Standard uncertainty associated with the mean velocity (95% Confidence), relative
- u(qV,w)Standard uncertainty associated with the volume flow rate (95% Confidence), relative
0.00053-
Uc(qV,w)
0.00055- 328479425- 18124.0
Uc,rel(qV,w) 4.59
%
%
CAT-RT (Version BP)Page 14 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 17 of 42
Sample Runs
- -
- -
- -
- -
- -
- -
- -
- -
Blank Runs
- -
APPENDIX 2
20067.5
mg/m³ 48.10
Run 1
Maximum
Mean
1512.2
1.03 1.03±% v/v
Parameter Units
Run 1
Water Vapour
Concentration
Mass Emission
19.62% v/v
g/hr 20067.5
1512.2
Parameter Units
Uncertainty ±g/hr
Edenderry Power Ltd, Edenderry
Mean
19.62
TOTAL PARTICULATE MATTER: RESULTS SUMMARY
A1-1 Main Boiler
Parameter
48.10
Blank 1
Uncertainty
Uncertainty ±mg/m³ 2.88 2.88
Units
- -
General Sampling Information
FORMAT: Number Used / Number Required
FORMAT: Number Used / Number Required
Reference Conditions
Reference Conditions are: 273K, 101.3kPa, dry gas, 6% oxygen.
mg/m³ 0.09
A1, A2, A3, A4, A5, A6, B1, B2, B3, B4, B5, & B6
2 / 2Number of Sampling Points Used 10 / 10
TitaniumFilter Housing Material TitaniumProbe Material
Standard
NOTE: Where the Balance Uncertainty / Limit of Detection is higher than the Blank concentration, the Balance Uncertainty / Limit of Detection concentration has been reported.
47mm Glass Fibre
0.09
Parameter
EN 13284-1
Sample Point I.D.'s
Number of Sampling Lines Used
CAT-TP-01
Value
Filter Size and MaterialIn Stack
Technical Procedure
Concentration
Positioning of Filter
CAT-RT (Version BP)Page 15 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 18 of 42
Absolute pressure of stack gas, Ps
Volume of water vapour collected, Vwstd
Volume of gas metered dry, Vmstd
Moisture content, Bwo & Rwv
Bwo as a percentageReported Water Vapour, checked with Tables in EN 14790, RwvVolume of gas metered wet, Vmstw
Volume of gas metered at Oxygen Reference Conditions, Vmstd@X%O₂ & Vmstw@X%O₂
755.9
- 0.91
NoIED & Incinerates Hazardous Material? (Yes = no positive O₂ correction)
Bwo = Vwstd / (Vmstd + Vwstd) 0.1962
3.56
0.86
m³
m³
Average pressure drop across orifice, ∆H
Total mass collected in impingers (silica trap)
mmHg
g
759.0mmHg
62.5
Run 1
-1.6189
g
TOTAL PARTICULATE MATTER: ISOKINETIC SAMPLING CALCULATIONS
Test Units
Total mass collected in impingers (liquid trap)104.7
Stack static pressure, Pstatic
Ps = (Pb + (Pstatic / 13.6)
Barometric pressure, Pb
282.1
mmH₂O
0.3515
Volume of gas sample through gas meter, Vm m³Gas meter correction factor, Yd
177.4g
% v/v
1.7916
-
Vmstw = (Vmstd)(100/(100 - Rwv))
% wet oxygen measured in gas stream, ACT%O₂w
% v/v 6.00% dry oxygen measured in gas stream, ACT%O₂d
O₂ Reference Factor dry (O₂REFd) = (21 - REF%O₂) / (21 - ACT%O₂d)V = (V ) / (O₂ ) m³ 2.0834
-
APPENDIX 2
mmH₂O
% oxygen reference condition, REF%O₂
1.4401
0.935015.3
Vwstd = (0.001246)(Vlc)
Average dry gas meter temperature, Tm °C
Total mass of liquid collected, Vlc
% v/v% v/v
m³
Vmstd = ((0.3592)(Vm)(Pb + (∆H/13.6))(Yd)) / (Tm + 273)
-41.7
m³
% v/v
O₂ Reference Factor wet (O₂REFw) = (21 - REF%O₂) / (21 - ACT%O₂w)
19.6219.62
4.52
Molecular weight of dry gas stream, Md
CO₂ (Estimated)
O₂
Molecular weight of stack gas (wet), Ms
Total flow of stack gas: Actual (Qa), Wet (Qstw), Dry (Qstd), Wet@O₂REF (QstwO₂), Dry@O₂REF (QstdO₂)
Percent isokinetic, %I
g/gmol 28.19N₂
Pitot tube velocity constant, Kp
-34.97
0.3592
m³
g/gmol 26.19
-
0.06
15199.7
°C
Ms = Md(1 - (Rwv/100)) + 18(Rwv/100)
Average stack gas temperature, Ts
m³/min
Average square root of velocity heads, √∆P
m³/min
103.0
m/s
Area of stack, As m²
5.97
Qstw = ((Qa)(Ps)(Cf)) / ((Ts) + 273)Conversion factor (K/mm.Hg), Cf
Vs = ((Kp)(Cp)(√∆P)(√Ts + 273)) / (√(Ms)(Ps)) 27.90
mm
min 60%
Average of velocity heads, ∆Pavg mmH₂O
Total sampling time, q
9.08
m³/min 7557.010932.2
QstdO₂ = ((Qa)(Ps)(Cf)(1 - (Rwv/100))) / ((Ts) + 273) / (O₂REFd)
m³/minQa = (60)(As)(Vs)
4.52
Velocity of stack gas, Vs
Velocity pressure coefficient, Cp
41.676.45
28.00
166.0
-
Nozzle diameter, Dn
% v/v 4.58
0.83
Vmstw@X%oxygen = (Vmstw) / (O₂REFw) m³ 2.0834
% v/vMd = 0.44(%CO₂)+0.32(%O₂)+0.28(%N₂)
% v/v
1.5820Vmstd@X%oxygen = (Vmstd) / (O₂REFd)
QstwO₂ = ((Qa)(Ps)(Cf)) / ((Ts) + 273) / (O₂REFw)
%I = (4.6398E⁶)(Ts+273)(Vmstd) / (Ps)(Vs)(An)(q)(1 - (Rwv/100))
% v/v
mm²
Qstd = ((Qa)(Ps)(Cf)(1 - (Rwv/100))) / ((Ts) + 273)
95.42
√mmH₂O
Nozzle area, An
m³/min
Total
8301.4
9401.4
CAT-RT (Version BP)Page 16 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 19 of 42
Sample Runs
Filter I.D. Number
Probe Rinse I.D. Number
Where: ISO stands for Manual Isokinetic Sampling Train
Blank Runs
Start Probe Rinse Mass
0.00534
Sampling Device
47-36467
Sampling Times
Average Volume Sampled (REF)
Total Mass on Filter
mg/m³0.09
Units
PR-47-36467g
g
1.5820
0.07075-
ISO
TOTAL PARTICULATE MATTER: SAMPLING DETAILS
2.980592.97525
76.09
-
End Probe Rinse Mass
48.10
Blank Dates
Balance Uncertainty / LODCalculated Concentration
29/09/2016
1.5820
Start Filter Mass
Run 1
Parameter Units
End Filter Mass
-
Parameter
Blank 1
Total Mass Collected
-
mg/m³
m³
Sampling Dates
g0.148970.21972
Total Mass in Probe Rinse
08:48 - 09:48
APPENDIX 2
-
gg
-Volume Sampled (REF) m³
mg
g
29/09/2016
Filter I.D. Number
Probe Rinse I.D. Number
0.14688Total Mass on Filter
Average Volume Sampled (REF)-
3.09039
mg -0.10
0.09Calculated Concentration
1.5820
g
Balance Uncertainty / LOD
Start Filter Mass
-0.06
0.14699
-g
47-36466
PR-47-36466
mg/m³
m³
gEnd Filter Mass
mg/m³
Total Mass in Probe Rinse
Start Probe Rinse Mass
g
End Probe Rinse Mass
-0.00011
0.00001g
3.09038
Total Mass Collectedg
CAT-RT (Version BP)Page 17 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 20 of 42
Sample Runs
MU Acceptable
95 - 115
Post-Sampling Leak Rate
Leak Test Results
Yes
Isokinetic Variation
Yes
Run 1
TOTAL PARTICULATE MATTER: QUALITY ASSURANCE
Run 1
%
l/min 0.13
Are Water Droplets Present
l/minLeak Test Acceptable -Allowable Leak Rate
Units Run 1
Mean Sampling Rate l/min 25.23
Measurement Uncertainty (MU)
Silica Gel (Concurrent Water Vapour) Units
Allowable Isokinetic Range %
Allowable MU
(PAGE 1 OF 2)
%
103.0
- No
- Yes
Water Droplets
%
Units
%
5.2
0.50
%
Isokineticity Acceptable
20
APPENDIX 2
Isokinetic Criterion Compliance
Units
Pre-Sampling Leak Rate l/min 0.11
Run 1
Less than 50% Faded
Units
Yes
Run 1
MU (Concurrent Water Vapour)
Test Conditions Units
Allowable Weighing Uncertainty
180
0.25
Weighing Uncertainty Criteria
160Post-Conditioning Temperature
Run 1
± mg/m³
Weighing Uncertainty Acceptable
Yes
ELV [Daily ELV for IED] mg/m³ 50.00
Ambient Temperature Recorded? -
0.16
166
-
Units
Yes
Units Run 1
Run 1
°C
mg/m³ 2.50
Filter Temperatures
°C
Overall Weighing Uncertainty± mg
Pre-Conditioning Temperature °C
Overall Weighing Uncertainty
Maximum Filter Temperature
CAT-RT (Version BP)Page 18 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 21 of 42
Blank Runs
Method Deviations
1
wx
- - - - -
Units Blank 1
APPENDIX 2
mg/l
Run Number
Post-Sampling Leak Rate l/min 0.12
Yes0.50
Validity of Blank vs ELV
Leak Test Acceptable
TOTAL PARTICULATE MATTER: QUALITY ASSURANCE
Due to the restricted access, it was not possible to sample at all of the sample points on the available sampling lines.
0.12
- Yes
Blank 1
-
Leak Test Results
(PAGE 2 OF 2)
Units
Allowable Blank
l/minExpected Sampling Rate
5.0
Acetone / Water Rinse Value
mg/m³
(x = deviation applies to the associated run, wx = deviation also applies to the concurrent water vapour run)
2.7
Pre-Sampling Leak Rate
10
Allowable Leak Rate
Nature of Deviation
Acetone / Water Rinse Blank Units Blank
l/min
25.00
Allowable Blank
mg/l
-
YesBlank Acceptable
Blank Acceptable
l/min
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
CAT-RT (Version BP)Page 19 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 22 of 42
Sampled Volume (Actual)Sampled Gas TemperatureSampled Gas PressureSampled Gas HumidityLeakMass of ParticulateUncollected Mass
Sampled Volume (Actual)Sampled Gas TemperatureSampled Gas PressureSampled Gas HumidityLeakMass of ParticulateUncollected Mass
Sampled Volume (STP)LeakMass of Particulate
0.143
Measured Quantities
-
0.50≤1%
Measured Quantities Symbol
288.3
uVm m³
L 0.520.0
≤2%0.52
Symbol UnitsUncertainty in Measurement Units Sensitivity Coefficient
%
76.093
kPaHm
mg
APPENDIX 2
TOTAL PARTICULATE MATTER: MEASUREMENT UNCERTAINTY CALCULATIONS
Value Standard uncertainty
0.0324
UCM
0.5ρm 100.8
%
m
1.0
33.40
um
Run 1
76.09
Symbol
%
K 2.01.6189
mg/m³
-uL %
1.4401
-
Run 1 Requirement of Standard
Run 1
2.00 ≤2%0.69
%
Measured Quantities
Units Run 1
uTm
Uncertainty as a Percentage
%
uHm
uUCM mg -
Units
Run 1
Vm
% v/v
uρm
% 0.18
Lr mg
m³
<5% of ELV
Tm
L
Vm
0.63
≤1%% 1.00
0.14
1.00
≤1%
-0.10
Mass of ParticulateUncollected Mass
Sampled Volume (STP)LeakMass of ParticulateUncollected Mass
O₂ Correction FactorStack Gas O₂ ContentMU for O₂ Correction
Combined uncertainty
Expanded uncertainty (95% confidence), without Oxygen CorrectionExpanded uncertainty (95% confidence), with Oxygen CorrectionExpanded uncertainty (95% confidence), estimated with Method DeviationsReported Uncertainty
Expanded uncertainty (95% confidence), without Oxygen CorrectionExpanded uncertainty (95% confidence), with Oxygen CorrectionExpanded uncertainty (95% confidence), estimated with Method DeviationsReported Uncertainty
Measured Quantities
% v/v 4.52-
mg
2.88
Oxygen Correction Part of MU Budget
-0.0365
Run 1
Units
- 0.91
mg/m³
76.093
Units Run 1
mg/m³
3.03
mg/m³
Parameter Units
0.03%
mg/m³
0.0885
mg/m³ 1.253
2.88mg/m³
% 6.06.0
Overall MU For O₂ Measurement
5.2
0.63
%
%
-0.06
Lr mg
2.48
2.88
Measured Quantities
0.1431
mg/m³
UCM
Run 1
0.63
Uncertainty in Result
mg/m³ 1.26
% 6.0
mg/m³
CAT-RT (Version BP)Page 20 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 23 of 42
Sample Runs
- -
- -
- -
General Sampling Information
NOTE: Dilution performed to achieve correct span value
Span Gas Type Synthetic Air (5 Grade)
Run 1
Value
Standard EN 14789Technical Procedure CAT-TP-21
Probe Material Stainless SteelFiltration Type / Size
Parameter
Span Gas Expiry Date 14/09/2021Span Gas Start Pressure (bar) 100Gas Cylinder Concentration (% v/v) 21.22
Parameter
Span Gas Reference Number
Span Gas Uncertainty (%) 2
180°C
MeanUnits
11.0256
Uncertainty ±% v/v 0.38 0.38
0.1µm Glass Fibre
Concentration % v/v 4.51 4.51
Heated Line TemperatureHeated Head Filter Used Yes
Edenderry Power Ltd, EdenderryA1-1 Main Boiler
APPENDIX 2
OXYGEN: RESULTS SUMMARY
FORMAT: Number Used / Number Required
FORMAT: Number Used / Number Required
Span Gas Uncertainty (%) 2Zero Gas Type
Number of Sampling Lines Used 1 / 1
Nitrogen (5 Grade)
Number of Sampling Points Used 1 / 1
Sample Point I.D.'s A2
CAT-RT (Version BP)Page 21 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 24 of 42
Graphical Trend of Data
OXYGEN: DATA TREND
APPENDIX 2
COVER ME WITH CHART/S
0.0
1.0
2.0
3.0
4.0
5.0
6.0
08:5
0
08:5
2
08:5
4
08:5
6
08:5
8
09:0
0
09:0
2
09:0
4
09:0
6
09:0
8
09:1
0
09:1
2
09:1
4
09:1
6
09:1
8
09:2
0
09:2
2
09:2
4
09:2
6
09:2
8
09:3
0
09:3
2
09:3
4
09:3
6
09:3
8
09:4
0
09:4
2
09:4
4
09:4
6
09:4
8
Conc
entr
atio
n (%
v/v
)
Oxygen Oxygen
- Run 1
CAT-RT (Version BP)Page 22 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 25 of 42
Sampling Details
Quality Assurance
Zero Drift 0 0 0
Zero Drift 0 0 0
Zero Drift 0 0 0
Zero Down Sampling Line (Post)
% v/v
CAL
2 Zero Down Sampling Line (Pre) % v/v
CAL
3
N/A
- 08:50 - 09:49
Parameter Units Run 1
Sampling Times
Average Temperature
Span Gas Value
-0.06
Zero Down Sampling Line (Pre) % v/v
Conditioning Unit Temperature Units Run 1
Instrument Range % v/v 25
CAL
1 Zero Down Sampling Line (Pre) % v/v
°C N/A
YesZero Drift Acceptable
Temperature Acceptable - N/A
Units Run 1
Allowable Temperature < °C
0.06Zero Down Sampling Line (Post) % v/v 0.00
Zero Down Sampling Line (Post)
% v/v
OXYGEN: SAMPLING DETAILS & QUALITY ASSURANCE
% v/v 5.00
% v/v
% v/v
-Allowable Zero Drift ± % v/v 0.25
Zero Drift
Sampling Dates - 29/09/2016
% v/v
APPENDIX 2
Span Drift 0 0 0
Span Drift 0 0 0
Span Drift 0 0 0
Method Deviations
1
x
- - -
- - -
- - -
Span Drift Acceptable - Yes
Test Conditions Units Run 1
Run Ambient Temperature Range °C 14 - 19
Run 1
Span Down Sampling Line (Post) % v/v
% v/v
Span Drift Units
Run Number
% v/v
CAL
3
(x = deviation applies to the associated run)
There are no deviations associated with the sampling employed.
Nature of Deviation
Span Down Sampling Line (Post) % v/vSpan Down Sampling Line (Pre) % v/v
4.824.84
% v/v
Allowable Span Drift ± % v/v 0.25
CAL
2 Span Down Sampling Line (Pre) % v/vSpan Down Sampling Line (Post) % v/v
CAL
1 Span Down Sampling Line (Pre)
% v/v 0.02
CAT-RT (Version BP)Page 23 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 26 of 42
% rangeDependence on voltage 0.02 % full scale/10VLosses in the line (leak) 1.60 % of value
0.01 %vol
% of full scale
%vol%vol
Atmospheric pressure dependence
Combined interference 0.56
Uncertainty of calibration gas 2.00
Standard deviation of repeatability at zero use rep at span %volStandard deviation of repeatability at span level
N/A %vol6.0 %
0.02
Atmospheric pressure dependence 0.30 % of value/kPaVolume or pressure flow dependence 0.20
Ambient temperature dependence
Combined interference (from MCERTS Certificate) 0.08 %vol
RUN 1 Units
-0.07 % full scale/10K
Lack of fit 0.00 %volDrift -0.14 %volVolume or pressure flow dependence 0.00
Ambient temperature dependence -0.01 %vol
Deviation from linearity% full scale
Span drift 0.41 % full scale
0.03 % of valueZero drift -1.24
Number of readings in measurement 60 -Repeatability at zero 0.04Repeatability at span level 0.04 % full scale
Range Used 25.0 %volCal gas conc. 21.2 %vol
Performance characteristics
4.51 %vol
% full scale
secondsResponse time 60
Performance characteristics RUN 1 Units
Measured concentrationTGN M2 Allowable MULimit value
% of value
Performance characteristic RUN 1 Units
APPENDIX 2
OXYGEN: MEASUREMENT UNCERTAINTY CALCULATIONS
k =
%volCombined uncertainty
Expanded uncertainty (no O₂) - at 95% Confidence 8.50 % of ValueResult of Compliance with Uncertainty Requirement in M2 COMPLIANT -
Expanded uncertainty 1.96 0.38 %vol
RUN 1 Units
Requirement for SRM is that Uncertainty should be 0.5%vol absolute or 6% relative whichever is the lower, on a dry gas basis. Ref EA TGN M2.
Combined interference (from MCERTS Certificate) 0.08Dependence on voltage 0.00 %volLosses in the line (leak) 0.04 %volUncertainty of calibration gas 0.05 %vol
RUN 1 UnitsMeasurement uncertainty Result 4.51
0.20 %vol
CAT-RT (Version BP)Page 24 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 27 of 42
Sample Runs
- -
- -
- -
- -
- -
General Sampling Information
Sample Cell Temperature (°C)
±g/hr
Yes
Value
101.8Sample Cell Pressure (mbar)
Technical Procedure CAT-TP-22(b)
191
200.02
Uncertainty
APPENDIX 2
OXIDES OF NITROGEN (AS NO₂): RESULTS SUMMARY
Edenderry Power Ltd, Edenderry
Sampling System Path Length (m)
A1-1 Main Boiler
9.42
Standard TGN M22
Heated Head Filter Used
9.42
Mass Emission g/hr 83448.7
Parameter
Stainless Steel
83448.7
mg/m³ 200.02
Uncertainty ±mg/m³
5486.4 5486.4
5.11
Analysis Areas (Wave Number Limits) 1875 - 2138 & 2700 - 2950
Units Run 1
Concentration
Mean
Parameter
Probe MaterialFiltration Type / Size 0.1µm Glass Fibre
FORMAT: Number Used / Number Required
FORMAT: Number Used / Number Required
References Used in Analytical Algorithm Application
Reference Conditions
Reference Conditions are: 273K, 101.3kPa, dry gas, 6% oxygen.
Concentration of References
20, 40, 60, 81.3, 100, 200, 300, 398, 500, 1000, 1500, 2058
Number of Sampling Points Used
180°C
Nitrogen (5 Grade)
12.0059
Gas Cylinder Concentration (ppm)Check Gas Start Pressure (bar)
Instrument Specific
Sample Point I.D.'s A3
Yes
150
Number of Sampling Lines Used 1 / 1
411.5Check Gas Uncertainty (%)
1 / 1
Check Gas Type NO
Type of Reference
09/08/2018
Heated Line TemperatureHeated Head Filter Used
2Zero Gas Type
Check Gas Reference NumberCheck Gas Expiry Date
CAT-RT (Version BP)Page 25 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 28 of 42
Graphical Trend of Data
APPENDIX 2
OXIDES OF NITROGEN (AS NO₂): DATA TREND
COVER ME WITH CHART/S
0.0
50.0
100.0
150.0
200.0
250.0
08:5
0
08:5
2
08:5
4
08:5
6
08:5
8
09:0
0
09:0
2
09:0
4
09:0
6
09:0
8
09:1
0
09:1
2
09:1
4
09:1
6
09:1
8
09:2
0
09:2
2
09:2
4
09:2
6
09:2
8
09:3
0
09:3
2
09:3
4
09:3
6
09:3
8
09:4
0
09:4
2
09:4
4
09:4
6
09:4
8
Conc
entr
atio
n (m
g/m
³)
Oxides of Nitrogen (as NO₂) At Reference Conditions
- Run 1
CAT-RT (Version BP)Page 26 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 29 of 42
Lack of FitZero DriftSpan DriftSensitivity to Atmospheric PressureSensitivity to Sample Gas PressureSensitivity to Ambient TemperatureSensitivity to Electrical VoltageInterferentsStandard Deviation of Repeatability at ZeroStandard Deviation of Repeatability at SpanUncertainty of Certified Reference Material
Combined Uncertainty
Expanded Uncertainty (ppm)Expanded Uncertainty (%age of Reading)
RUN 1 Measured (ppm) 84.34Oxides of Nitrogen (as NO₂) NOx (as NO₂) NOx (as NO₂) Range (ppm) 80Source of Uncertainty Value (±%) Probability Distribution
OXIDES OF NITROGEN (AS NO₂): MEASUREMENT UNCERTAINTY CALCULATIONS
APPENDIX 2
Divisor Conversion Factor ui | ppm0.75 rectangular √3 0.843427963 0.3650.50 rectangular √3 0.8 0.2312.00 rectangular √3 0.8 0.924N/A rectangular √3 N/A 0.000N/A rectangular √3 N/A 0.0000.34 rectangular √3 0.32 0.063-0.08 rectangular √3 0.2 -0.008-3.20 rectangular √3 0.8 -1.4780.10 normal 1 0.8 0.080N/A normal 1 N/A 0.0002.00 normal 2 0.843427963 0.843
- normal - - 1.987
- t-distribution (k=2) - - 3.973- t-distribution (k=2) - - 4.71
CAT-RT (Version BP)Page 27 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 30 of 42
Sample Runs
- -
- -
- -
- -
- -
General Sampling Information
Parameter Value
5.11Sample Cell Temperature (°C)
Uncertainty
Uncertainty ±g/hr 398.4
Yes
0.18
0.95
Mass Emission
Sampling System Path Length (m)
101.8
g/hr 73.2
±mg/m³
TGN M22Technical Procedure
191
Filtration Type / Size
398.4
Sample Cell Pressure (mbar)
Analysis Areas (Wave Number Limits) 2000 - 2222 & 2540 - 2590
Standard
0.1µm Glass Fibre
0.95
73.2
Stainless SteelProbe Material
Heated Head Filter Used
mg/m³ 0.18Concentration
Run 1Units
CAT-TP-22(b)
APPENDIX 2
NITROUS OXIDE: RESULTS SUMMARY
Mean
Edenderry Power Ltd, EdenderryA1-1 Main Boiler
Parameter
FORMAT: Number Used / Number Required
FORMAT: Number Used / Number Required
References Used in Analytical Algorithm Application
Reference Conditions
Reference Conditions are: 273K, 101.3kPa, dry gas, 6% oxygen.
Concentration of References
180°CYes
Heated Line Temperature
1 / 1
12.0059Check Gas Expiry Date 09/08/2018
Check Gas Type
411.5
NO
150
Number of Sampling Lines Used
Heated Head Filter Used
Check Gas Reference Number
Check Gas Uncertainty (%)
Sample Point I.D.'s A3
Type of Reference
1 / 1Number of Sampling Points Used
Gas Cylinder Concentration (ppm)2
Check Gas Start Pressure (bar)
Instrument Specific 10, 20, 40, 60, 81.3, 100, 200, 300, 398, 500, 1000, 1500, 2058
CAT-RT (Version BP)Page 28 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 31 of 42
Graphical Trend of Data
COVER ME WITH CHART/S
NITROUS OXIDE: DATA TREND
APPENDIX 2
0.0
0.0
0.0
0.1
0.1
0.1
0.1
0.1
0.2
0.2
0.2
08:5
0
08:5
2
08:5
4
08:5
6
08:5
8
09:0
0
09:0
2
09:0
4
09:0
6
09:0
8
09:1
0
09:1
2
09:1
4
09:1
6
09:1
8
09:2
0
09:2
2
09:2
4
09:2
6
09:2
8
09:3
0
09:3
2
09:3
4
09:3
6
09:3
8
09:4
0
09:4
2
09:4
4
09:4
6
09:4
8
Conc
entr
atio
n (m
g/m
³)
Nitrous Oxide At Reference Conditions
- Run 1
CAT-RT (Version BP)Page 29 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 32 of 42
Lack of FitZero DriftSpan DriftSensitivity to Atmospheric PressureSensitivity to Sample Gas PressureSensitivity to Ambient TemperatureSensitivity to Electrical VoltageInterferentsStandard Deviation of Repeatability at ZeroStandard Deviation of Repeatability at SpanUncertainty of Certified Reference Material
Combined Uncertainty
Expanded Uncertainty (ppm)Expanded Uncertainty (%age of Reading)
APPENDIX 2
0.82 rectangular √3 0.000772911 0.00040.50 rectangular √3 0.1 0.02892.00
NITROUS OXIDE: MEASUREMENT UNCERTAINTY CALCULATIONS
RUN 1 Measured (ppm) 0.08Nitrous Oxide N₂O N₂O Range (ppm) 10Source of Uncertainty Value (±%) Probability Distribution Divisor Conversion Factor ui | ppm
rectangular √3 0.1 0.1155N/A rectangular √3 N/A 0.0000N/A rectangular √3 N/A 0.00000.46 rectangular √3 0.04 0.01060.10 rectangular √3 0.0 0.00123.00 rectangular √3 0.1 0.17320.00 normal 1 0.1 0.0000N/A normal 1 N/A 0.00002.00 normal 2 0.000772911 0.0008
- normal - - 0.2104
- t-distribution (k=2) - - 0.4209- t-distribution (k=2) - - 544.51
CAT-RT (Version BP)Page 30 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 33 of 42
Sample Runs
- -
- -
- -
- -
- -
General Sampling Information
CAT-TP-22(b)
330.51
Run 1
Edenderry Power Ltd, Edenderry
Stainless SteelFiltration Type / Size
330.51
APPENDIX 2
SULPHUR DIOXIDE: RESULTS SUMMARY
Uncertainty ±g/hr 8981.7
A1-1 Main Boiler
Parameter
±mg/m³ 15.29
Sample Cell Pressure (mbar)
Units
8981.7
Parameter
Standard TGN M22
g/hr
Technical Procedure
Heated Head Filter Used
Mean
5.11
Yes
Mass Emission
0.1µm Glass Fibre
Analysis Areas (Wave Number Limits) CHOOSE: 1050 - 1250, 1100 - 1366 or 1200 - 1366
Probe Material
15.29
Concentration mg/m³
Uncertainty
191Sample Cell Temperature (°C)
Value
137892.9137892.9
101.8
Sampling System Path Length (m)
FORMAT: Number Used / Number Required
FORMAT: Number Used / Number Required
References Used in Analytical Algorithm Application
Reference Conditions
Reference Conditions are: 273K, 101.3kPa, dry gas, 6% oxygen.
Check Gas Expiry Date
Check Gas Type SO₂
2
Check Gas Reference Number
Gas Cylinder Concentration (ppm) 100.9
1 / 1
Sample Point I.D.'s
180°CHeated Head Filter Used
Check Gas Start Pressure (bar) 150
Yes
Type of Reference Concentration of References
09/08/2018
Check Gas Uncertainty (%)
A3
12.0059
Heated Line Temperature
Number of Sampling Lines Used
Instrument Specific 4, 8, 12, 16, 100, 200, 300, 403, 600, 1200, 1800, 2460
Number of Sampling Points Used 1 / 1
CAT-RT (Version BP)Page 31 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 34 of 42
Graphical Trend of Data
SULPHUR DIOXIDE: DATA TREND
COVER ME WITH CHART/S
APPENDIX 2
0.0
50.0
100.0
150.0
200.0
250.0
300.0
350.0
400.0
08:5
0
08:5
2
08:5
4
08:5
6
08:5
8
09:0
0
09:0
2
09:0
4
09:0
6
09:0
8
09:1
0
09:1
2
09:1
4
09:1
6
09:1
8
09:2
0
09:2
2
09:2
4
09:2
6
09:2
8
09:3
0
09:3
2
09:3
4
09:3
6
09:3
8
09:4
0
09:4
2
09:4
4
09:4
6
09:4
8
Conc
entr
atio
n (m
g/m
³)
Sulphur Dioxide At Reference Conditions
- Run 1
CAT-RT (Version BP)Page 32 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 35 of 42
Lack of FitZero DriftSpan DriftSensitivity to Atmospheric PressureSensitivity to Sample Gas PressureSensitivity to Ambient TemperatureSensitivity to Electrical VoltageInterferentsStandard Deviation of Repeatability at ZeroStandard Deviation of Repeatability at SpanUncertainty of Certified Reference Material
Combined Uncertainty
Expanded Uncertainty (ppm)Expanded Uncertainty (%age of Reading)
SULPHUR DIOXIDE: MEASUREMENT UNCERTAINTY CALCULATIONS
RUN 1 Measured (ppm) 100.17Sulphur Dioxide SO₂ SO₂ Range (ppm) 100
APPENDIX 2
Source of Uncertainty Value (±%) Probability Distribution Divisor Conversion Factor ui | ppm0.90 rectangular √3 1.001724947 0.5210.50 rectangular √3 1 0.2892.00 rectangular √3 1 1.155N/A rectangular √3 N/A 0.000N/A rectangular √3 N/A 0.000
-0.46 rectangular √3 0.4 -0.1060.10 rectangular √3 0.2 0.012-2.80 rectangular √3 1 -1.6170.23 normal 1 1 0.225N/A normal 1 N/A 0.0002.00 normal 2 1.001724947 1.002
- normal - - 2.317
- t-distribution (k=2) - - 4.633- t-distribution (k=2) - - 4.63
CAT-RT (Version BP)Page 33 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 36 of 42
Sample Runs
- -
- -
- -
General Sampling Information
Units Run 1 Mean
Concentration % v/v 23.04 23.04
5.11
Edenderry Power Ltd, Edenderry
Yes
3200 - 3401
Sampling System Path Length (m)
WATER VAPOUR: RESULTS SUMMARY
TGN M22
APPENDIX 2
Standard
Sample Cell Temperature (°C)
0.79 0.79
Parameter Value
101.8
Uncertainty % v/v
Heated Line Temperature
A1-1 Main Boiler
Parameter
Probe Material
180°C
Check Gas Type
191
Heated Head Filter Used0.1µm Glass Fibre
Stainless SteelFiltration Type / Size
C₃H₈Check Gas Reference Number 12.0059
Sample Cell Pressure (mbar)
Technical Procedure CAT-TP-22(b)Analysis Areas (Wave Number Limits)
FORMAT: Number Used / Number Required
FORMAT: Number Used / Number Required
References Used in Analytical Algorithm Application
A3
10, 20, 30, 40
Check Gas Expiry Date
Sample Point I.D.'s
83.63Check Gas Uncertainty (%)
Number of Sampling Lines Used 1 / 1
Check Gas Start Pressure (bar) 150Gas Cylinder Concentration (ppm)
Concentration of References
Number of Sampling Points Used 1 / 1
2
Instrument Specific
Type of Reference
Check Gas Reference Number 12.005909/08/2018
CAT-RT (Version BP)Page 34 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 37 of 42
Graphical Trend of Data
COVER ME WITH CHART/S
APPENDIX 2
WATER VAPOUR: DATA TREND
0.0
5.0
10.0
15.0
20.0
25.0
30.0
08:5
0
08:5
2
08:5
4
08:5
6
08:5
8
09:0
0
09:0
2
09:0
4
09:0
6
09:0
8
09:1
0
09:1
2
09:1
4
09:1
6
09:1
8
09:2
0
09:2
2
09:2
4
09:2
6
09:2
8
09:3
0
09:3
2
09:3
4
09:3
6
09:3
8
09:4
0
09:4
2
09:4
4
09:4
6
09:4
8
Conc
entr
atio
n (%
v/v
)
Water Vapour Water Vapour
- Run 1
CAT-RT (Version BP)Page 35 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 38 of 42
Lack of FitZero DriftSpan DriftSensitivity to Atmospheric PressureSensitivity to Sample Gas PressureSensitivity to Ambient TemperatureSensitivity to Electrical VoltageInterferentsStandard Deviation of Repeatability at ZeroStandard Deviation of Repeatability at SpanUncertainty of Certified Reference Material
Combined Uncertainty
Expanded Uncertainty (% v/v)Expanded Uncertainty (%age of Reading)
APPENDIX 2
WATER VAPOUR: MEASUREMENT UNCERTAINTY CALCULATIONS
RUN 1 Measured (% v/v) 23.04Water Vapour H₂O H₂O Range (%v/v) 20Source of Uncertainty Value (±%) Probability Distribution Divisor Conversion Factor ui | % v/v
0.40 rectangular √3 0.230438471 0.05320.50 rectangular √3 0.2 0.05772.00 rectangular √3 0.2 0.2309N/A rectangular √3 N/A 0.0000N/A rectangular √3 N/A 0.0000
-0.37 rectangular √3 0.08 -0.0172-0.10 rectangular √3 0.0 -0.00231.80 rectangular √3 0.2 0.20780.05 normal 1 0.2 0.0100N/A normal 1 N/A 0.00002.00 normal 2 0.230438471 0.2304
- normal - - 0.3952
- t-distribution (k=2) - - 0.7904- t-distribution (k=2) - - 3.43
CAT-RT (Version BP)Page 36 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 39 of 42
Sampling Details
Quality Assurance
0 00 0
Method Deviations
1
- - -
- - -
- - -
Value
M22 FTIR SAMPLING DETAILS & QUALITY ASSURANCE
Background / Zero Calibration Check
AU0.0050
CAL
1
29/09/2016Sampling Date
Parameter Units
Nature of Deviation
(x = deviation applies to the associated run)
°C 14 - 18⁰C
Run Number
AU -0.00390.0004
Allowable Energy in Cell ± AUMaximum Energy in Cell
-
APPENDIX 2
Run 1
Sampling Times
Test Conditions Units
Minimum Energy in Cell
(PAGE 1 OF 2)
Run 1
Run Ambient Temperature Range
- 08:50 - 09:49
Units
- - -
Interference Check
PWater Vapour
P
DAY 1
Oxides of Nitrogen (as NO₂)
Nitrous Oxide
Sulphur DioxideP
Target Parameter
P
where "P" = Pass and "F" = Fail
CAT-RT (Version BP)Page 37 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 40 of 42
Difference 0 0 0 0 0
0
Difference 0 0 0 0Drift
NOTE: Drift correction will be automatically applied to the data if the maximum check gas drift is between 2 - 5%.
ppm
Check Gas Check - Post Test
Allowable DriftYes
- Yes
Yes
%
Yes4.2
0.2 2.50.8 0.4
120120200Yes
Response Time from ASC, ASC T₉₀ s0
120
Check Gas Value 83.686.6
C₃H₈
200Yes
100.9
ppm
120
Yes Yes
(PAGE 2 OF 2)
1.3
120
REACTIVE GAS CHECK
120
Check Gas Reading - Post Test ppm
Check Gas Check - Pre Test
102.4
1200
120
ppm 99.5-1.4
3.1 0.4 2.0
103.7 99.5 86.6
Units CO
± ppm 5.120.6
Yes
101.4
Check Gas Acceptable
2.0 0.3
Allowable Difference
ppm
± % 5.0 5.0 5.0 5.0Yes
405.4 98.9408.4 104.2 101.4
29/0
9/20
16
86.8
10.1Yes
SO₂C₃H₈CO SO₂
5.0
Units
CAL
1
NO
-Drift Acceptable
Check Gas Reading - Pre Test
Yes
Check Gas Reading on Analyser
200
120
200
Response Time, T₉₀
411.598.9
SO₂
-2.0
-
1200
(performed against decreasing H₂O)
3.0
0
SO₂
405.4
200Reverse Response Time, RT₉₀
ss
Allowable Response Time
12.0059
M22 FTIR SAMPLING DETAILS & QUALITY ASSURANCE
12.0059 12.0059
60
12.0059 12.0059
CAL
1 100.9
-6.1
APPENDIX 228
/09/
2016
sResponse Time Acceptable
ppm
-
System Lag Time [ASC T₉₀ - T₉₀] s
Yes
NO
Yes
60
Check Gas Reference Number
103.7
CAT-RT (Version BP)Page 38 of 38
Edenderry Power LtdEdenderryA1-1 Main Boiler
Job Number: P0482-04CAR-16-01, Version 2Sample Date/s: 28th - 29th September 2016
Industrial Emissions Licence: P0482-04
Site Visit Report - SV08119 - Edenderry Power Limited Page 41 of 42
Summary
See report.
FOLLOW-UP ACTIONS
You are required to complete the instructions and actions, as outlined in this report, within the specified timeframe. Where required, you shall respond to actions specified in Compliance Investigations within the required timeframe. The licensee shall maintain documentary evidence, for review by the EPA, that the prescribed corrective actions were completed within the required timeframe.
You are not required to respond directly to items contained in this EPA site visit report; where an issue requires a direct response, the EPA will generate a Compliance Investigation through the EDEN system. You will receive notification when a Compliance Investigation instruction or action is generated.
Please note that this Site Visit Report will be made available for public viewing via the EPA’s Licence Enforcement Access Portal within one day of the issue date and will be published on the Licence Details Page of the EPA’s website, www.epa.ie, that relates to your licence 60 calendar days after the issue date.
You may if you choose submit, within 45 calendar days of the issue date of this Site Visit Report, a Licensee Public Response that will be published alongside the Site Visit Report. This Response, should you wish to avail of it, provides you with an opportunity to inform the public about how you are implementing the actions set out in the report, activities underway, timescales and target completion dates. Please be aware that the content of your Licensee Public Response must be factual and should not breach the EPAs stated online publication standards.
If you wish to submit a Licensee Public Response to an EPA Site Visit Report, you should do this by clicking on the ‘Make a Response’ link on the Site Visits page in EDEN. A .pdf document containing your response can be attached and submitted from here.
Please note that you are required to comply with the conditions of your licence at all times, and where noncompliance occurs you must restore compliance within the shortest possible time. These actions will be verified during subsequent EPA visits.
Please quote the above Inspection Reference Number in any future correspondence in relation to this Report.
Site Visit Report - SV08119 - Edenderry Power Limited Page 42 of 42