Appr Project New Airport 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title Report on Site Visit Resp. dept Projects Status Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 11 Site Survey Report To: Projects Engineer Station: New Airport 66/11kV 1. General: Information Project Site survey Site Survey Engineers Albert Kadala, Beatrice Muthoni Survey Date 21 st August 2014 Station Name & Contact New Airport 66/11 kV Region &Town Nairobi South, Nairobi Distance to Site(km) 13 km from Juja Control Station Coordinates 1*20’34.9”S, 36*54’47.5”E, 5321ft Access Road Airport South Road Station Voltage 66/11 kV Cable Trenches Available Notes: The substation is situated along Airport South Road. There is currently no communication to Control center. There is a PLC at site but it is not in service. The station is proposed for last mile fiber optic to be connected to Embakasi substation for onward routing to NCC using existing communication equipment.

Transcript of Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be...

Page 1: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 11

Site Survey Report

To: Projects Engineer

Station: New Airport 66/11kV

1. General: Information

Project Site survey

Site Survey Engineers Albert Kadala, Beatrice Muthoni

Survey Date 21st August 2014

Station Name & Contact New Airport 66/11 kV

Region &Town Nairobi South, Nairobi

Distance to Site(km) 13 km from Juja Control

Station Coordinates 1*20’34.9”S, 36*54’47.5”E, 5321ft

Access Road Airport South Road

Station Voltage 66/11 kV

Cable Trenches Available

Notes:

The substation is situated along Airport South Road. There is currently no communication to

Control center. There is a PLC at site but it is not in service. The station is proposed for last

mile fiber optic to be connected to Embakasi substation for onward routing to NCC using

existing communication equipment.

Page 2: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 2 en 01 No. of p. 11

2. Drawings

3. Equipment Room

Location 11kV room

Room type and Floor Stone building, concrete floor

Ceiling type Iron Sheets

L x W x H in meters 9x6.5x4M

AC Power 240/415 VAC

DC Power 110V for protection, 48V for scada and communication

Rectifier Available

Batteries Available

Power Distribution Board Available

Grounding System Substation earthing

Security Guard at the gate, Room secured with standard padlock

Page 3: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 3 en 01 No. of p. 11

4. RTU SIEMENS RTU available and in service. Station HMI for SAS is available but not powered.

5. Marshalling Cubicles Not Available

6. Communication Equipment Power line carrier available but out of service.

Proposed Adss fiber optic link to be installed to Embakasi sub station. New fiber optic terminal

equipment required to Embakasi for onward routing to NCC using existing equipment

7. Room layout

Communication room layout

.

Access Road Airport South road

RTU/SAS Available, Siemens RTU with station HMI available.

Marshalling Not Available

Cable Routes Available

Communication Eqpt PLC available but not powered. ADSS fiber optic proposed

Page 4: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 4 en 01 No. of p. 11

8. AC Supply 240/415VAC available

9. DC Supply 110V protection, 48V Scada and telecomms

10. Plant Interface 10.1 Signals list

Attached

10.2 Installation and adaptation works A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling

from all switch gear to the marshalling will need to be installed

11. Enclosures 9.1 Site Survey Report

9.2 Detailed plant drawings

9.3 Control Room layout

9.4 Equipment Room Layout

12. Notes distance from the site (km) 13 km from Juja Control Nearby buildings JKIA Nearby industries JKIA Type of soil Black Cotton Water availability Water available from borehole Special authority pass Permit to work Type of area Commercial Power supply 240VAC Pass issued by: Nairobi area control

Page 5: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 5 en 01 No. of p. 11

13. Photographic Report Siemens RTU installed at New airport Power line Carrier. Out of service Station HMI not powered Battery and charger room AC distribution board

Signal list

Airport 66/11kV Signal list

OBJECT  TYPE  SIGNAL  Indications  Alarms  Commands  Measurands 

Energy Meter Inputs 

66kV                   LINE 1  DPI  1L1 E/S  On/Off  1             

      1L3 ISO  On/Off  1             

                      

   AMI  Active Power, P            1    

      Reactive Power, Q           1    

      Voltage, U           1    

                       

   ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

                      

LINE 2  DPI  2L1 E/S  On/Off  1             

      2L3 ISO  On/Off  1             

                      

   AMI  Active Power, P            1    

      Reactive Power, Q           1    

      Voltage, U           1    

Page 6: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 6 en 01 No. of p. 11

                       

   ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

                      

LINE 3  DPI  3L1 E/S  On/Off  1             

      3L3 ISO  On/Off  1             

      3L5 CB  On/Off  1             

                      

   AMI  Active Power, P            1    

      Reactive Power, Q           1    

      Voltage, U           1    

                       

   DCO  3L5 CB  Open/Close        1       

                      

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

      SF6 LOW second step    1          

                      

   ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

                      

LINE 4  DPI  4L1 E/S  On/Off  1             

      4L3 ISO  On/Off  1             

      4L5 CB  On/Off  1             

                      

   AMI  Active Power, P            1    

      Reactive Power, Q           1    

      Voltage, U           1    

                       

   DCO  4L5 CB  Open/Close        1       

                      

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

      SF6 LOW second step    1          

                      

   ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

                       

66kV Busbar  DPI  ISO BC  On/Off  1             

                       

TX1 BAY  DPI  CB 1H5 On/Off  1             

      ISO 1H3 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

Page 7: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 7 en 01 No. of p. 11

      BPT‐Backup Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

      SF6 LOW second step    1          

                       

   DCO  CB 1H5  Open/Close        1       

                      

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

TX2 BAY  DPI  CB 2H5 On/Off  1             

      ISO 2H3 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

      SF6 LOW second step    1          

                       

   DCO  CB 2H5  Open/Close        1       

                      

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

TX1  DPI  TC Auto/Manual  1             

      TC Local/Remote  1             

                       

   SPI  TTA‐Temp Alarm     1          

      TTT TEMP TRIP     1          

      TBA BUCH AL     1          

      TBT BUCH TRIP     1          

      TOL OIL LEVEL ALARM    1          

      TGA TX GENERAL AL     1          

      TGT TX GEN TRIP     1          

      TBS TX OUT OF STEP    1          

                       

   DCO  TC Auto/Manual        1       

                       

   RCO  TC Raise/Lower        1       

                       

   AMI  Tap Position           1    

                       

TX2  DPI  TC Auto/Manual  1             

      TC Local/Remote  1             

Page 8: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 8 en 01 No. of p. 11

                       

   SPI  TTA‐Temp Alarm     1          

      TTT TEMP TRIP     1          

      TBA BUCH AL     1          

      TBT BUCH TRIP     1          

      TOL OIL LEVEL ALARM    1          

      TGA TX GENERAL AL     1          

      TGT TX GEN TRIP     1          

      TBS TX OUT OF STEP    1          

                       

   DCO  TC Auto/Manual        1       

                       

   RCO  TC Raise/Lower        1       

                       

   AMI  Tap Position           1    

                       

11 KV                      

INCOMER 1  DPI  CB INC1 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

      SF6 LOW second step    1          

                       

   DCO  CB INC 1 Open/Close        1       

                      

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

   ITI  Energy, KWHR               1 

      Energy, KVARHR               1 

                       

INCOMER 2  DPI  CB INC2 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      BYF‐Bay Faulty     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      Lockout relay operated     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

      SF6 LOW second step    1          

                       

   DCO  CB INC 2 Open/Close        1       

                      

   AMI  Volts, kV           1    

Page 9: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 9 en 01 No. of p. 11

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

   ITI  Energy, KWHR               1 

      Energy, KVARHR               1 

                       

11kV BUSBAR  DPI  ISO BC  On/Off  1             

                       

   DCO  ISO BC  Open/Close        1       

                       

   SPI  Busbar protection     1          

      Busbar supervision     1          

                       

   AMI  Volts, kV           1    

      Frequency, F           1    

                       

11kV Feeders                      

Industrial  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Airport 1  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

KPC  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

Page 10: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 10 en 01 No. of p. 11

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

IMARA DAIMA  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

AIRPORT 2  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

OSERIAN  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

ATHI  DPI  CB On/Off  1             

                       

Page 11: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project New Airport 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 11 en 01 No. of p. 11

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Station  DPI  Station Remote/Supervisory  1             

                       

   SPI  48 DC Battery Alarm    1          

      48 DC Charger Alarm    1          

      48V Charger A Fail Alarm    1          

      48V Charger B Fail Alarm    1          

      RTU Alarm     1          

      Communications Alarm    1          

      110V DC Battery Alarm    1          

      110V DC Charger Alarm    1          

      110V DC Charger A Fail Alarm    1          

      110V DC Charger B Fail Alarm    1          

      Smoke in Control Room     1          

                       

   AMI  48V DC1           1    

      48V DC2           1    

      110V DC1           1    

      110V DC2           1    

                    

Total  30  101  18  43  26 

Page 12: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project DARA 11KV SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 9

Site Survey Report

To: Projects Engineer

Station: Dara 11 kV

1. General: Information

Project Site survey

Site Survey Engineers Albert Kadala, Beatrice Muthoni

Survey Date 20/08/2014

Station Name & Contact Dara 11 kV S/Stn

Region &Town Nairobi South

Distance to Site(km) 12.5km from Juja NCC

Station Coordinates 1*18’6.7”S, 36*49’54.9”E, 5444ft

Access Road Lusaka Road

Station Voltage 11 kV

Cable Trenches Available

Notes:

All the switchgear has been recovered from the station. New switch gear yet to be installed.

Page 13: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project DARA 11KV SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 2 en 01 No. of p. 9

2. Drawings

DARA Substation SLD

3. Equipment Room

Location 11kV room

Room type and Floor Stone room and concrete floor

Ceiling type Concrete slab ceiling

L x W x H in meters 10.5 x 5 x 4

AC Power 240VAC

DC Power None

Rectifier None

Batteries None

Power Distribution Board 415VAC

Grounding System Substation earth

Security Secured with standard padlock and electric fence

Access Road Lusaka road

RTU/SAS None

Page 14: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project DARA 11KV SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 3 en 01 No. of p. 9

4. RTU

No RTU at the station

.

5. Marshalling Cubicles

No marshalling cubicles at the station

6. Communication Equipment

No communication equipment at the station

7. Room layout

.

8. AC upply

415 VAC

Marshalling None

Cable Routes available

Communication Eqpt None, proposed radio to Ngong hills repeater

Page 15: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project DARA 11KV SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 4 en 01 No. of p. 9

9. DC Supply

No DC supply

10. Plant Interface

10.1 Signals list

Attached

10.2 Installation and adaptation works

RTU, Marshalling cubicle and communication equipment need to be installed. Full wiring

to be done from the Panels to the Marshalling cubicle and to the RTU. Radio communication

to Ngong Hills repeater is proposed. If this is adapted a tower and antenna need to be

installed complete with radio and coax and configuration to Ngong repeater

11. Enclosures

9.1 Site Survey Report

9.2 Detailed plant drawings

9.3 Control Room layout

9.4 Equipment Room Layout

9.4

12. Notes

distance from the site (km) 12.5 km from NCC Nearby buildings Car and General Nearby industries Car and General Type of soil Cabro Water availability Not available Special authority pass Substation key, limitation of access Type of area Commercial Power supply 240VAC Pass issued by: Nairobi Area control

Page 16: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project DARA 11KV SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 5 en 01 No. of p. 9

13. Photographic Report

Equipment room photos

Cable trenches

AC distribution board

Page 17: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project DARA 11KV SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 6 en 01 No. of p. 9

DARA SIGNAL LIST

DARA 11kV Signal list 

OBJECT  TYPE  SIGNAL  Indications  Alarms  Commands  Measurands 

Energy Meter Inputs 

LINE 1  DPI  INC 1  CB On/Off  1             

                       

   DCO  INC 1 CB  Open/Close        1       

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   AMI  Active Power, P            1    

      Reactive Power, Q           1    

      Voltage, U           1    

                       

   ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

                       

LINE 2  DPI  INC 2 CB  On/Off  1             

                       

   DCO  INC 2 CB  Open/Close        1       

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   AMI  Active Power, P            1    

      Reactive Power, Q           1    

      Voltage, U           1    

                       

   ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

                       

11kV Feeders                      

NRBW2  DPI  CB On/Off  1             

                       

Page 18: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project DARA 11KV SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 7 en 01 No. of p. 9

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

KRWS2  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

INDU2  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

INDU1  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

Page 19: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project DARA 11KV SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 8 en 01 No. of p. 9

      Energy, KVARHR              1 

                       

BUS COUPLER  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

EAI  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

KRWS1  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

CATH  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

Page 20: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project DARA 11KV SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 9 en 01 No. of p. 9

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

GNGN  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Station  DPI  Station Remote/Supervisory  1             

                       

   SPI  48 DC Battery Alarm     1          

      48 DC Charger Alarm     1          

      48V Charger A Fail Alarm    1          

      48V Charger B Fail Alarm    1          

      RTU Alarm     1          

      Communications Alarm    1          

      110V DC Battery Alarm    1          

      110V DC Charger Alarm    1          

      110V DC Charger A Fail Alarm    1          

      110V DC Charger B Fail Alarm    1          

      Smoke in Control Room     1          

                       

   AMI  48V DC1           1    

      48V DC2           1    

      110V DC1           1    

      110V DC2           1    

                    

Total  12  55  11  19  20 

Page 21: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 12

Site Survey Report

To: Projects Engineer

Station: Industrial 66/11 kV

1. General: Information

Project Site surveys

Site Survey Engineers Albert Kadala, Beatrice Muthoni

Survey Date 19th August 2014

Station Name & Contact Industrial 66/11 kV

Region &Town Nairobi South

Distance to Site(km) 14.7 km from Juja

Station Coordinates 1*18’50”S, 36*51’3.9”E

Access Road Enterprise Road

Station Voltage 66/11 kV

Cable Trenches Available, from switchyard to new station building

Notes:

New station building is under construction and far from completion. All equipment will be

transferred to the new building once complete. Survey was carried out on the existing system

and building. Cable trenches from the switchyard to the new building are constructed.

Page 22: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 2 en 01 No. of p. 12

2. Drawings

66kV

66kV

W57 W58

1L7

1L1

1L5

2L7

2L1

2L5

TX123MVA

TX245MVA

Local TX

Local TX

VillaFranca

NewMSA rd

N/South1

N/South2

RollMills

PFC Kencell EAO Kampalard

PFCDara 1 Dara 2

Inc 1 Inc 2

Single Line Diagram

3. Equipment Room

Location Nairobi Industrial area

Room type and Floor Stone building, concrete floor

Ceiling type Iron sheet

L x W x H in meters New building under construction

AC Power 240VAC available

DC Power 30VDC available, 48VDC available but not in service

Rectifier Available

Batteries Available

Power Distribution Board Available

Grounding System Substation earthing

Security Security guard at the gate, room secured with standard padlock

Page 23: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 3 en 01 No. of p. 12

4. RTU

RTU560 installed in old existing building but it is not in service. The RTU will need to be

migrated to the new equipment room when station building is complete

RTU available with following cards: 13No. 23BE23, 4No. 23AE23, 2No. 560PSU01, 1No.

560CMU05, 1No. 560RTC01, 1No. 23BA22, 48No. DC48V command relays

5. Marshalling Cubicles

Available with 80No. DC36V double pole and 126No. DC36V Single point indication relays

available in the marshalling.

6. Communication Equipment

Radio communication to Ngong Hills repeater site had been installed

The radio is not available at the station but radio cabinet is available.

36 ft tower complete with antenna and coax available. The coax will not be able to reach the new

building when equipments are migrated. Excavation work will be necessary and a longer coax

required.

A new radio and a coax from the tower to the new building will need to be installed to get

communication to Ngong Hills site which is connected to Juja Control

7. Room layout

.New station building is still under construction. There will be sufficient space to mount Scada

and communication cabinets in the new room.

Access Road Enterprise road

RTU/SAS RTU 560 installed

Marshalling Available

Cable Routes Available

Communication Eqpt Radio Not available, communication tower complete with

antenna and coax available

Page 24: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 4 en 01 No. of p. 12

8. AC Supply

240VAC available

9. DC Supply

30VDC for protection available, 48VDC for communication available but not in use

10. Plant Interface

10.1 Signals list

Attached

10.2 Installation and adaptation works

New wiring will need to be done from the RTU to the relay panels to the switchyard as equipment

are to be moved from the old room to new building. Excavation may be required for coax path if the

existing Communication tower is to be used. It is situated further from the new building

Enclosures

9.1 Site Survey Report

9.2 Detailed plant drawings

9.3 Control Room layout

9.4 Equipment Room Layout

11. Notes

distance from the site (km) 14.7 km from Juja control Nearby buildings HEMA House Nearby industries Crown industries Type of soil Black cotton Water availability In process of installation Special authority pass Permit to work Type of area Industrial area Power supply 240VAC Pass issued by: Nairobi area control

Page 25: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 5 en 01 No. of p. 12

12. Photographic Report

RTU 560 installed but not in service

Marshalling cubicle

Radio communication cabinet with radio missing

AC distribution board

30V DC supply

48V Dc supply out of service

Page 26: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 6 en 01 No. of p. 12

Signal list

INDUSTRIAL 66/11kV Signal list 

OBJECT  TYPE  SIGNAL  Indications  Alarms  Commands  Measurands 

Energy Meter Inputs 

66kV                      LINE   DPI  W57  On/Off  1             

      W58  On/Off  1             

                       

   AMI  Volts, kV W57           1    

      Volts, kV W58           1    

      Active Power, P W57           1    

      Active Power, P W58           1    

      Reactive Power, Q W57           1    

      Reactive Power, Q W58           1    

                       

   ITI  Energy, KWHR Imp W57              1 

      Energy, KWHR Imp W58              1 

      Energy, KVARHR Imp W57              1 

      Energy, KVARHR ImpW58              1 

                       

66kV Busbar  DPI  ISO BC 1H2  On/Off 1             

                       

TX1 BAY  DPI  ES 1L1  On/Off  1             

      CB 1L5 On/Off  1             

      ISO 1L7 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

      SF6 LOW second step    1          

                       

Page 27: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 7 en 01 No. of p. 12

   DCO  CB 1L5  Open/Close        1       

                       

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

   ITI  Energy, KWHR               1 

      Energy, KVARHR               1 

                       

TX2 BAY  DPI  ES 2L1  On/Off  1             

      CB 2L5 On/Off  1             

      ISO 2L7 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

      SF6 LOW second step    1          

                       

   DCO  CB 2L5  Open/Close        1       

                       

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

   ITI  Energy, KWHR               1 

      Energy, KVARHR               1 

                       

TX1  DPI  TC Auto/Manual  1             

      TC Local/Remote  1             

                       

   SPI  TTA‐Temp Alarm     1          

      TTT TEMP TRIP     1          

      TBA BUCH AL     1          

      TBT BUCH TRIP     1          

      TOL OIL LEVEL ALARM    1          

      TGA TX GENERAL AL    1          

      TGT TX GEN TRIP    1          

      TBS TX OUT OF STEP    1          

                       

   DCO  TC Auto/Manual        1       

                       

   RCO  TC Raise/Lower        1       

                       

   AMI  Tap Position           1    

                       

TX2  DPI  TC Auto/Manual  1             

      TC Local/Remote  1             

Page 28: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 8 en 01 No. of p. 12

                       

   SPI  TTA‐Temp Alarm     1          

      TTT TEMP TRIP     1          

      TBA BUCH AL     1          

      TBT BUCH TRIP     1          

      TOL OIL LEVEL ALARM    1          

      TGA TX GENERAL AL    1          

      TGT TX GEN TRIP    1          

      TBS TX OUT OF STEP    1          

                       

   DCO  TC Auto/Manual        1       

                       

   RCO  TC Raise/Lower        1       

                       

   AMI  Tap Position           1    

                       

                       

11 KV                      

INCOMER 1  DPI  CB INC1 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

      SF6 LOW second step    1          

                       

   DCO  CB INC 1 Open/Close        1       

                       

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

   ITI  Energy, KWHR               1 

      Energy, KVARHR               1 

                       

INCOMER 2  DPI  CB INC2 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      BYF‐Bay Faulty     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      Lockout relay operated     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

      SF6 LOW second step    1          

                       

   DCO  CB INC 2 Open/Close        1       

                       

Page 29: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 9 en 01 No. of p. 12

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

   ITI  Energy, KWHR               1 

      Energy, KVARHR               1 

                       

11kV BUSBAR  DPI  ISO BC  On/Off  1             

                       

   DCO  ISO BC  Open/Close        1       

                       

   SPI  Busbar protection     1          

      Busbar supervision     1          

                       

   AMI  Volts, kV           1    

      Frequency, F           1    

                       

11kV Feeders                      

New Msa Rd  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Villa Franca  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

PFC1  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

Page 30: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 10 en 01 No. of p. 12

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Nairobi south 1  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Roll Mills  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Kencell  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Nairobi south 2  DPI  CB On/Off  1             

Page 31: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 11 en 01 No. of p. 12

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

East Africa Oxygen  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Kampala rd  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Dara 1  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

Page 32: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Industrial 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 12 en 01 No. of p. 12

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Dara 2  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

PFC 2  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step    1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

Station  DPI  Station Remote/Supervisory  1             

                       

   SPI  48 DC Battery Alarm    1          

      48 DC Charger Alarm    1          

      48V Charger A Fail Alarm    1          

      48V Charger B Fail Alarm    1          

      RTU Alarm     1          

      Communications Alarm    1          

      110V DC Battery Alarm    1          

      110V DC Charger Alarm    1          

      110V DC Charger A Fail Alarm    1          

      110V DC Charger B Fail Alarm    1          

      Smoke in Control Room     1          

                       

   AMI  48V DC1           1    

      48V DC2           1    

      110V DC1           1    

      110V DC2           1    

                    

Total  29  107  21  42  36 

Page 33: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project Substation NamePrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 4

Site Survey Report

To: Projects Engineer

Station: KAREN 66/11KV SUBSTATION –

1. General: Information

Project Station Voltage 66/11kV

Site Survey Engineers Metrine Jelagat Cable Trenches

Survey Date 30/07/2014

Station Name & Contact Karen Substation

Region &Town Nairobi West

Distance to Site(km)

Station Coordinates

Access Road Ngong Rd

Notes:

Give a description of Substation and attach the SLD.

Station Voltage and general status of substation. Take pictures of station. Comment on

status of cable trenches etc.

Page 34: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project KAREN SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. metrine Rev. ind. Page 2 en 01 No. of p. 4

2. Drawings

Comment on drawing(s) and collect copies of same. If station is new get station layout

drawings.

3. Equipment Room

4. RTU

Indicate if RTU/SAS exists and check model, and spare capacity.

.

5. Marshalling Cubicles

Indicate if Marshalling cubicles are available. Access cable routes and status of

Where possible, all signals shall be brought to the marshalling cubicle. Access need for

items like transducers etc.

Location 66kV panels

Room

RTU/SAS RTU560 – IEC103

Room type and Floor Blocks/stones Marshalling

Ceiling type none Cable Routes See Drawing/Photo

L x W x H in meters Communication Eqpt Radio

AC Power 415v/240v

DC Power 48VDC,110VDC

Rectifier

Batteries 48VDC Avail

Power Distribution Board

Grounding System

Security Room secure

Access Road

Page 35: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project KAREN SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. metrine Rev. ind. Page 3 en 01 No. of p. 4

6. Communication Equipment

Indicate if any communication equipment exist in the station and necessary capacity installed and spare.

If no Equipment exists, indicate possible equipment and media. Since this shall be accessed on viability

give all the options possible and nearest terminal communication link. Limit to Fibre, Radio and

PLC(Least preferred)

Indicate if Tele-protection is required.

Indicate if fibre required length of fibre and line voltage.

7. Room layout

Get the room layout. Indicate if space is available for proposed new equipment.

8. AC Supply

Check the AC distribution board and available spare capacity.

9. DC Supply

Indicate if 48 VDC and 110 VDC is available in the status and spare capacity.

10. Plant Interface

10.1 Signals list

Make a table based on Standard Signal list to indicate no required

10.2 Installation and adaptation works

. Indicate any challenges expected

Page 36: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project KAREN SUBSTATION Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. metrine Rev. ind. Page 4 en 01 No. of p. 4

11. Enclosures

9.1 Site Survey Report

9.2 Detailed plant drawings

9.3 Control Room layout

9.4 Equipment Room Layout

9.4

12. Notes

distance from the site (km)

In town Type of area Urban

Nearby buildings Apartments, Slum Nearby industries Samsung, Heineken Power supply 240VAC Type of soil Loamy soil Water availability Special authority pass

Permit of work Pass issued by:

RCC

It is important to note if there other challenges expected in works. Also if available indicate any near

future rehabilitation works are planned.

Indicate strategic position of the sub-station and its importance to the region.

13. Photographic Report

Attach Relevant Photographs

Page 37: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project Kikuyu 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

No. of p. 12

Site Survey Report

To: Projects Engineer

Station: Kikuyu Substation 66/11kV

1. General: Information

Project Site survey

Site Survey Engineers Metrine Jelagat/Tony Angatia

Survey Date 12th September 2014

Station Name & Contact Kikuyu S/S 66/11 kV

Region &Town Nairobi North, Nairobi

Distance to Site(km) 40 km from Juja Control via Waiyaki way

Station Coordinates 1.2326830S, 36.662070E

Access Road Waiyaki Way

Station Voltage 66/11 kV

Cable Trenches Available

Notes:

The substation is situated at Kikuyu town accessed via waiyaki way.

The substation has two 66/11KV, 23MVA transformers with an indoor 11kv switchboard. The 11kV switchboard has ABB type HD4 breakers with 2 incomers, 1 Bus Section switch and 6 feeders.

The control room accommodates the 11kV switchboard, the transformer and 66kV line protection panels and tap changer control panels.

There exists a SCADA equipment in the station but it is not terminated to the process, the cables have been done from the RTU/MC and lie in the trenches

Page 38: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

2. Drawings

Page 39: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

Page 40: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

3. Equipment Room

Location Scada room

Room type and Floor Stone building, concrete floor

Ceiling type Iron Sheets

L x W x H in meters 2.5x1.7x4M

AC Power 240/415 VAC

DC Power 30V for protection, 110V for Tap changer panel, 48V for scada

and communication

Rectifier Available

Batteries Available

Power Distribution Board Available

Grounding System Substation earthing

Security Guard at the gate, station controller

Access Road Waiyaki way to Kikuyu township

RTU/SAS Available, RTU560 installed but terminations to switchgear not

done

Marshalling Available

Cable Routes Available

Communication Eqpt Radio Mast available at the station, a radio cabinet available

but no radio, a coax from the mast to the radio cabinet

available

Page 41: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

4. RTU

It is proposed to use the existing RTU in the station. Average length of cables shall be 15 meters and shall all be for bottom entry. The existing transducers are mounted in the11kv panels and 66kv tap changer control panels. These are for local metering.

5. Marshalling Cubicles

The marshalling cabinet is located in the scada room as shown in the layout drawing and is of an average cable route of 15 meters from the switchgear.

6. Communication Equipment

There is no existing Telecommunication equipment for the SCADA Network.

A communication mast however exists and a UHF Radio is proposed for this station.

This would communicate with Ngong Hills UHF Repeater station as there is no direct propagation path to Juja Rd NCC.

The new radio equipment would be installed in the communications cabinet in the control room. See room layout drawing. The distance from the new RTU is about 5 meters.

7. Room layout (not to scale)

Communication room layout

.

8. AC Supply

Page 42: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

A 415V AC distribution board is located about 15meteres from the proposed RTU position Spare MCB way is available in the AC distribution board.

9. DC Supply

There exists a 48v DC system. This is located in the battery room as shown in the room layout. The system is located in the battery room shown in the room layout diagram

10. Plant Interface 10.1 Signals list

Attached

10.2 Installation and adaptation works There is an RTU 560 with a marshalling cubicle mounted in the scada room. The RTU has cables terminated but left in the trenches and not terminated to the process. It is proposed that in the implementation of the scada , the available materials shall be used

11. Enclosures Site Survey Report

Photographic represenation

Control Room/ Equipment room layout

12. Notes distance from the site (km) 40 km from Juja Control Nearby buildings Kikuyu Town Nearby industries Steel Rolling Mills Type of soil Red Soil Water availability Water available from a neighboring borehole Special authority pass Permit to work Type of area Commercial Power supply 240VAC Pass issued by: Nairobi area control

Page 43: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

13. Photographic Report

14. RTU & MC Radio cabinet and mast

Battery and charger room

AC distribution board

Signal list

Kikuyu 66/11kV Signal list

OBJECT TYPE SIGNAL Indications Alarms Commands Measurands

Energy Meter Inputs

66kV Karen DPI ISO 1L7 0N/OFF 1

CB 1L5 0N/Off 1

ISO 1L3 0N/OFF 1

ES 1L1 ON/OFF 1

DCO CB 1L5 Open/Close 1

ISO 1L7 Open/Close 1

ISO 1L3 Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

ITI Energy, KWHR Imp 1

Energy, KVARHR Imp 1

Page 44: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

Limuru DPI ISO 2L7 0N/OFF 1

CB 2L5 0N/Off 1

ISO 2L3 0N/OFF 1

ES 2L1 ON/OFF 1

DCO CB 2L5 Open/Close 1

ISO 2L7 Open/Close 1

ISO 2L3 Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

ITI Energy, KWHR Imp 1

Energy, KVARHR Imp 1

TX1 BAY DPI CB 1H5 On/Off 1

ISO 1H3 On/Off 1

SPI MPT-Main Prot. Trip 1

BPT-Backup Prot. Trip 1

Protection Faulty 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

SF6 LOW first step 1

SF6 LOW second step 1

DCO CB 1H5 Open/Close 1

AMI Volts, kV 1

Active Power, P 1

Reactive Power, Q 1

Amps 1

TX2 BAY DPI CB 2H5 On/Off 1

ISO 2H3 On/Off 1

SPI MPT-Main Prot. Trip 1

BPT-Backup Prot. Trip 1

Protection Faulty 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

SF6 LOW first step 1

SF6 LOW second step 1

DCO CB 2H5 Open/Close 1

AMI Volts, kV 1

Active Power, P 1

Reactive Power, Q 1

Amps 1

Page 45: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

TX1 DPI TC Auto/Manual 1

TC Local/Remote 1

SPI TTA-Temp Alarm 1

TTT TEMP TRIP 1

TBA BUCH AL 1

TBT BUCH TRIP 1

TOL OIL LEVEL ALARM 1

TGA TX GENERAL AL 1

TGT TX GEN TRIP 1

TBS TX OUT OF STEP 1

DCO TC Auto/Manual 1

RCO TC Raise/Lower 1

AMI Tap Position 1

TX2 DPI TC Auto/Manual 1

TC Local/Remote 1

SPI TTA-Temp Alarm 1

TTT TEMP TRIP 1

TBA BUCH AL 1

TBT BUCH TRIP 1

TOL OIL LEVEL ALARM 1

TGA TX GENERAL AL 1

TGT TX GEN TRIP 1

TBS TX OUT OF STEP 1

DCO TC Auto/Manual 1

RCO TC Raise/Lower 1

AMI Tap Position 1

11 KV

INCOMER 1 DPI CB INC1 On/Off 1

SPI MPT-Main Prot. Trip 1

BPT-Backup Prot. Trip 1

Protection Faulty 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

SF6 LOW first step 1

SF6 LOW second step 1

DCO CB INC 1 Open/Close 1

AMI Volts, kV 1

Active Power, P 1

Reactive Power, Q 1

Amps 1

Page 46: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

ITI Energy, KWHR 1

Energy, KVARHR 1

INCOMER 2 DPI CB INC2 On/Off 1

SPI MPT-Main Prot. Trip 1

BPT-Backup Prot. Trip 1

BYF-Bay Faulty 1

Protection Faulty 1

TCF-Trip Circuit Faulty 1

Lockout relay operated 1

SCF-Spring Charge Fail 1

SF6 LOW first step 1

SF6 LOW second step 1

DCO CB INC 2 Open/Close 1

AMI Volts, kV 1

Active Power, P 1

Reactive Power, Q 1

Amps 1

ITI Energy, KWHR 1

Energy, KVARHR 1

11kV BUSBAR DPI ISO BC On/Off 1

DCO ISO BC Open/Close 1

AMI Volts, kV 1

11kV Feeders

KABETE DPI CB On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

SF6 LOW first step 1

DCO CB Open/Close 1

AMI Amps 1

ITI Energy, KWHR 1

Energy, KVARHR 1

DPI CB On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

S PARE SCF-Spring Charge Fail 1

Page 47: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

SF6 LOW first step 1

DCO CB Open/Close 1

AMI Amps 1

ITI Energy, KWHR 1

Energy, KVARHR 1

UTHIRU DPI CB On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

SF6 LOW first step 1

DCO CB Open/Close 1

AMI Amps 1

ITI Energy, KWHR 1

Energy, KVARHR 1

KIKUYU DPI CB On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

SF6 LOW first step 1

DCO CB Open/Close 1

AMI Amps 1

ITI Energy, KWHR 1

Energy, KVARHR 1

MUGUGA DPI CB On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

SF6 LOW first step 1

DCO CB Open/Close 1

AMI Amps 1

ITI Energy, KWHR 1

Energy, KVARHR 1

STEEL MILLS DPI CB On/Off 1

Page 48: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Kikuyu 66/11 kV Substation Prep. Date 12-09- Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 12

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

SF6 LOW first step 1

DCO CB Open/Close 1

AMI Amps 1

ITI Energy, KWHR 1

Energy, KVARHR 1

Station DPI Station Remote/Supervisory 1

SPI 48 DC Battery Alarm 1

48 DC Charger Alarm 1

RTU Alarm 1

Communications Alarm 1

30V DC Battery Alarm 1

30V DC Charger Alarm 1

110V DC Chargerl Alarm 1

110V DC Battery 1

AMI 48V DC1 1

30V DC1 1

110V DC2 1

Total 26 78 21 43 20

Page 49: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project Limuru 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

en 01 No. of p. 6

Site Survey Report

To: Projects Engineer

Station: Limuru Substation 66/11kV

General: Information

Project Site survey

Site Survey Engineers Metrine Jelagat

Survey Date 12th September 2014

Station Name & Contact Limuru S/S 66/11 kV

Region &Town Nairobi North, Nairobi

Distance to Site(km) 60 km from Juja Control

Station Coordinates 1.1109900S, 36.6458490E , 2254.5m ASL

Access Road Waiyaki Way

Station Voltage 66/11 kV

Cable Trenches Available

Notes:

The substation has 3no 66kV lines, 1 66kV bus-section switch, two 23MVA transformer with an indoor and one 5MVA transformer. All equipment is included in the siemens scada system, except one 23 MVA transformer which is still under construction with no scada .It has an 11kv switchgear board located in an adjacent control room. The board has Siemens type breakers with 3 incomers and 9 feeders.

There is a Siemens SCADA equipment in this station.

There is a PLC at site but it is not in service. An ADSS fiber optic cable is also under

installation to link Limuru S/S to Nairobi North S/S.

A fibre terminal equipment is proposed for the communication in this station.

Page 50: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Limuru 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 6

Drawings

UPLANDS MUTHAIGA LOCAL TX2LIMURU TOWN

LOCAL TX 1 BATA

TX3 TX2

1L7

1L5

1L3

1L1

NGEMA/MAAI MAHIU KIKUYU

1H3

1H0

2L7

2L5

2L3

2L1

2H3

2H0

BC

WELBCK SPARE SPARE

BC

TX1

BC

INC3 INC1 INC2

3L7

3L5

3L3

3L1

NAIROBI NORTH

5 MVA

Under construction

Page 51: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Limuru 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 6

quipment Room

RTU SIEMENS RTU available and in service. Station HMI for SAS is available but not powered.

Marshalling Cubicles Not Available

Communication Equipment Power line carrier available but out of service.

An Adss fiber optic link is being installed to Nairobi North sub station. New fiber optic terminal

equipment required to Nairobi North for onward routing to NCC using existing equipment

Room layout

Location Old control room

Room type and Floor Stone building, concrete floor

Ceiling type Iron Sheets

L x W x H in meters 9x6.5x4M

AC Power 240/415 VAC

DC Power 110V for protection, 48V for scada and communication

Rectifier Available

Batteries Available

Power Distribution Board Available

Grounding System Substation earthing

Security Guard at the gate, Room secured with standard padlock

Access Road Waiyaki way

RTU/SAS Available, Siemens RTU with station HMI available.

Marshalling Not Available

Cable Routes Available

Communication Eqpt PLC available but not powered. ADSS fiber optic proposed

Page 52: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Limuru 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 6

Communication room layout

.

AC Supply 24all 0/415VAC available

DC Supply 110V protection, 48V Scada and telecomms

Plant Interface 1.1 Signals list

Except for a new transformer being installed in the station, the rest of the equipment is monitored

on the siemens scada platform. Details of the transformer not available

Page 53: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Limuru 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 6

1.2 Installation and adaptation works

A new transformer is under construction, and it shall be required that it is added to the existing scada system via the siemens SCMS

A fiber optic terminal equipment is proposed to be installed at the station. The siemens Scada system

shall then be connected to NCC via Nairobi North s/s

Enclosures Site Survey Report

Photographs

Control Room layout

Equipment Room Layout

Notes distance from the site (km) 55 km from Juja Control Nearby buildings Limuru Shopping centre Nearby industries Bata Shoe Company Type of soil Red Soil Water availability Water available Special authority pass Permit to work Type of area Commercial Power supply 240VAC Pass issued by: Nairobi area control

Photographic Report Siemens RTU installed at Limuru

Page 54: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Limuru 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 6

Power line Carrier. Out of service Station HMI not powered Battery and charger room

Page 55: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project Machakos 33/11 kV Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 8

Site Survey Report

To: Projects Engineer

Station: Machakos 33/11 kV

1. General: Information Project Site surveys

Site Survey Engineers Albert Kadala, Beatrice Muthoni

Survey Date 22 August 2014

Station Name & Contact Machakos 33/11 kV

Region &Town Machakos

Distance to Site(km) 35 km from Nairobi

Station Coordinates Machakos town

Access Road Makutano - kitui road

Station Voltage 33/11 kV

Cable Trenches Available

Notes:

The station is undergoing renovation; a new station building is under construction.

Page 56: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Machakos 33/11 kV Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 2 en 01 No. of p. 8

2. Drawings

3. Equipment Room

Location Building under construction

Room type and Floor Concrete

Ceiling type Concrete slab

L x W x H in meters 10.5 x 5 x 4 meters

AC Power Not yet available

DC Power Not yet available

Rectifier Not yet available

Batteries Not yet available

Power Distribution Board Not yet available

Grounding System Not yet available

Security Room is secured,

Access Road Makutano - kitui road

RTU/SAS Not available

Marshalling Not available

Page 57: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Machakos 33/11 kV Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 3 en 01 No. of p. 8

4. RTU Not available

.

5. Marshalling Cubicles Not available

6. Communication Equipment Not available.

ADSS last mile fiber link to be installed to Embakasi substation. New FO terminal equipment

required to Embakasi for onward routing to NCC using existing communication equipment.

7. Room layout

.

8. AC Supply Not available

9. DC Supply Not available

Cable Routes Available

Communication Eqpt Not available

Page 58: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Machakos 33/11 kV Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 4 en 01 No. of p. 8

10. Plant Interface 10.1 Signals list

Attached

10.2 Installation and adaptation works

A new RTU, Marshalling cabinet and Fiber optic terminal equipment will need to be installed.

Wiring from the panels yet to be installed to the Marshalling cubicle and from the

Marshalling to the RTU will be required.

11. Enclosures

9.1 Site Survey Report

9.2 Detailed plant drawings

9.3 Control Room layout

9.4 Equipment Room Layout

9.4

12. Notes

distance from the site (km) 35 km from nairobi

Nearby buildings Thika motor dealers

Nearby industries Thika motor dealers

Type of soil Clay soil

Water availability No water

Special authority pass LOA, PTW

Type of area Commercial

Power supply Not yet installed

Pass issued by: NRCC

Page 59: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Machakos 33/11 kV Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 5 en 01 No. of p. 8

13. Photographic Report Substation building

Substation building

Communication room and Equipment rooms

SIGNAL LIST

Machakos 33/11kV Signal list

OBJECT  TYPE  SIGNAL  Indications  Alarms  Commands  Measurands 

Energy Meter Inputs 

33kV                      LINE 1  DPI  X708 ISO  On/Off  1             

                       

   AMI  Active Power, P            1    

      Reactive Power, Q           1    

      Voltage, U           1    

                       

   ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

                       

TX1 BAY  DPI  CB VPR1 On/Off  1             

      ISO X709 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail     1          

      SF6 LOW first step     1          

Page 60: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Machakos 33/11 kV Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 6 en 01 No. of p. 8

      SF6 LOW second step     1          

                       

   DCO  CB VPR1  Open/Close        1       

                       

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

TX2 BAY  DPI  CB VWVE13 On/Off  1             

      ISO X710 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail     1          

      SF6 LOW first step     1          

      SF6 LOW second step     1          

                       

   DCO  CB VWVE13  Open/Close        1       

                       

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

TX1  DPI  TC Auto/Manual  1             

      TC Local/Remote  1             

                       

   SPI  TTA‐Temp Alarm     1          

      TTT TEMP TRIP     1          

      TBA BUCH AL     1          

      TBT BUCH TRIP     1          

      TOL OIL LEVEL ALARM     1          

      TGA TX GENERAL AL     1          

      TGT TX GEN TRIP     1          

      TBS TX OUT OF STEP     1          

                       

   DCO  TC Auto/Manual        1       

                       

   RCO  TC Raise/Lower        1       

                       

   AMI  Tap Position           1    

                       

TX2  DPI  TC Auto/Manual  1             

      TC Local/Remote  1             

                       

   SPI  TTA‐Temp Alarm     1          

      TTT TEMP TRIP     1          

      TBA BUCH AL     1          

      TBT BUCH TRIP     1          

Page 61: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Machakos 33/11 kV Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 7 en 01 No. of p. 8

      TOL OIL LEVEL ALARM     1          

      TGA TX GENERAL AL     1          

      TGT TX GEN TRIP     1          

      TBS TX OUT OF STEP     1          

                       

   DCO  TC Auto/Manual        1       

                       

   RCO  TC Raise/Lower        1       

                       

   AMI  Tap Position           1    

                       

11 KV                      

FEEDER 1  DPI  CB FTU110 On/Off  1             

      ISO Y6066 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail     1          

      SF6 LOW second step     1          

                       

   DCO  CB FTU110 Open/Close        1       

                       

   AMI  Volts, kV           1    

      Amps           1    

                       

   ITI  Energy, KWHR               1 

      Energy, KVARHR               1 

                       

FEEDER 2  DPI  CB KFE13 On/Off  1             

      ISO Y6064 On/Off  1             

      CB OSM1 On/Off  1             

      ISO Y6065 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail     1          

      SF6 LOW second step     1          

                       

   DCO  CB KFE13 Open/Close        1       

                       

   AMI  Volts, kV           1    

      Amps           1    

                       

   ITI  Energy, KWHR               1 

      Energy, KVARHR               1 

                       

Station  DPI  Station Remote/Supervisory  1             

                       

   SPI  48 DC Battery Alarm     1          

      48 DC Charger Alarm     1          

      48V Charger A Fail Alarm     1          

      48V Charger B Fail Alarm     1          

Page 62: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Machakos 33/11 kV Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 8 en 01 No. of p. 8

      RTU Alarm     1          

      Communications Alarm     1          

      110V DC Battery Alarm     1          

      110V DC Charger Alarm     1          

      110V DC Charger A Fail Alarm    1          

      110V DC Charger B Fail Alarm    1          

      Smoke in Control Room     1          

                       

   AMI  48V DC1           1    

      48V DC2           1    

      110V DC1           1    

      110V DC2           1    

                    

Total  16  49  8  21  6 

Page 63: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project Mombasa road substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 10

Site Survey Report

To: Projects Engineer

Station: Mombasa Road Substation

1. General: Information

Project Site survey

Site Survey Engineers Albert Kadala, Beatrice Muthoni

Survey Date 21/08/2014

Station Name & Contact Mombasa road

Region &Town Nairobi South

Distance to Site(km) 18 km from Juja control

Station Coordinates 1*20’23.6”S, 36*52’26.9”E, 5403ft

Access Road Mombasa road

Station Voltage 66/11kV

Cable Trenches Available

Notes:

A new 11 kV board has been installed at the station. Installation works is in progress.

Page 64: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Mombasa road substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 2 en 01 No. of p. 10

2. Drawings

Single line diagram

3. Equipment Room

Location 11kV room

Room type and Floor Concrete building

Ceiling type Galsheet mabati roof

L x W x H in meters 13.5 x 7.5 x 5meters

AC Power 415 VAC

DC Power 110VDC, 30VDC

Rectifier Available

Batteries Available

Power Distribution Board Available with spare capacity

Grounding System Substation earth

Security Room secured with standard paddlock

Access Road Mombasa road

RTU/SAS Available. To use existing Embakasi RTU

Marshalling Available, wiring in progress

Cable Routes Available

Communication Eqpt Available, with connection to Juja control

Page 65: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Mombasa road substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 3 en 01 No. of p. 10

4. RTU

Available in Embakasi, wiring in progress

.

5. Marshalling Cubicles

Available. Wiring in progress

6. Communication Equipment

Fiber optic terminal available, fiber connection to Juja available

7. Room layout

.

8. AC Supply

415 VAC

Page 66: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Mombasa road substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 4 en 01 No. of p. 10

9. DC Supply

110VDC, 48VDC, 30VDC

10. Plant Interface

10.1 Signals list

Attached

10.2 Installation and adaptation works

New 11kV panel installed. Wiring in progress

11. Enclosures 9.1 Site Survey Report

9.2 Detailed plant drawings

9.3 Control Room layout

9.4 Equipment Room Layout

9.4

12. Notes

distance from the site (km) 18 km from juja Nearby buildings Embakasi sub Nearby industries Lab and allied Type of soil Black cotton Water availability Water tank available Special authority pass Limitation of access Type of area Industrial Power supply Available Pass issued by: Nairobi area

Page 67: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Mombasa road substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 5 en 01 No. of p. 10

13. Photographic Report

11kv board

Marshalling cubicle work in progress

AC distribution board

Page 68: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Mombasa road substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 6 en 01 No. of p. 10

SIGNAL LIST

Mombasa Road 11kV Signal list 

OBJECT  TYPE  SIGNAL  Indications  Alarms  Commands  Measurands 

Energy Meter Inputs 

LINE 1  DPI  INC 1  CB On/Off  1             

                      

   DCO  INC 1 CB  Open/Close       1       

                      

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                      

   AMI  Active Power, P            1    

      Reactive Power, Q           1    

      Voltage, U           1    

                       

   ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

                      

LINE 2  DPI  INC 2 CB  On/Off  1             

                      

   DCO  INC 2 CB  Open/Close       1       

                      

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                      

   AMI  Active Power, P            1    

      Reactive Power, Q           1    

      Voltage, U           1    

                       

   ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

                      

11kV Feeders                      

SPARE  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

Page 69: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Mombasa road substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 7 en 01 No. of p. 10

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

IMARA DAIMA  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

AIRPORT  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

NMG  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

MSA RD  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

Page 70: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Mombasa road substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 8 en 01 No. of p. 10

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

BUS COUPLER  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

LABELS  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

MASAI RD  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

LAB & ALLIED  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

Page 71: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Mombasa road substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 9 en 01 No. of p. 10

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

POLYTHENE  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

SAFE PAK  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

                       

Station  DPI  Station Remote/Supervisory  1             

                       

   SPI  48 DC Battery Alarm    1          

      48 DC Charger Alarm    1          

      48V Charger A Fail Alarm    1          

      48V Charger B Fail Alarm    1          

      RTU Alarm     1          

      Communications Alarm    1          

      110V DC Battery Alarm    1          

      110V DC Charger Alarm    1          

      110V DC Charger A Fail Alarm    1          

      110V DC Charger B Fail Alarm    1          

      Smoke in Control Room     1          

Page 72: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Mombasa road substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 10 en 01 No. of p. 10

                       

   AMI  48V DC1           1    

      48V DC2           1    

      110V DC1           1    

      110V DC2           1    

                    

Total  14  63  13  21  24 

Page 73: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 17

Site Survey Report

To: Projects Engineer

Station: Muthurwa 66/11kV

1. General: Information

Project Site Survey

Site Survey Engineers Metrine Jelagat & Tony Angatia

Survey Date 17th September 2014

Station Name & Contact Muthurwa 66/11 kV

Region &Town Nairobi South, Nairobi

Distance to Site(km) 13.3 km from Juja rd NCC

Station Coordinates Latitude : 1.287117°S , 36.835619°E, 2389m

Access Road Landhies Road

Station Voltage 66/11 kV

Cable Trenches Available

Notes:

Muthurwa substation is a 66/11kV station with 3 No. 66 kV incomers from Juja and Nairobi

south. The station has 2 No. 45 MVA transformers with 15 No. feeders and 2 No. 11kV

incomers.

The station has already installed a Sicam (siemens) RTU but with no communication to the

control centres

Page 74: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 2 en 01 No. of p. 17

2. Drawings

Single Line Diagram

NB: All isolators are motorised while CB are SF6

Station Layout

Page 75: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 3 en 01 No. of p. 17

3. Equipment Room

Location 11kV room

Room type and Floor Stone building, concrete floor

Ceiling type Concrete

L x W x H in meters 25*6.6*4.46 m

AC Power 240/415 V ac

DC Power 110V

Rectifier Available

Batteries Available for protection panels

Power Distribution Board Available

Page 76: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 4 en 01 No. of p. 17

4. RTU

Siemens SICAM 1703 ACP CP 6014 gateway available

5. Marshalling Cubicles

Available

Grounding System Substation earth mat

Security Guard at the gate, room secured with standard padlock

Access Road Landhies Rd

RTU/SAS Siemens SICAM 1703 ACP CP 6014 gateway available

Marshalling Available

Cable Routes Available

Communication Equipment Not Available

Page 77: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 5 en 01 No. of p. 17

6. Communication Equipment

Not Available

7. Room layout

8. AC Supply

240/415V

9. DC Supply

110 V DC

10. Plant Interface

10.1 Signals list

Muthurwa  66/11kV Signal list

OBJECT  TYPE  SIGNAL  Indications  Alarms  Commands  Measurands 

Energy Meter Inputs 

Page 78: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 6 en 01 No. of p. 17

66kV                   LINE 1  DPI  1L1 E/S  On/Off  1             

      1L3 ISO  On/Off  1             

1L5 CB   On/Off                    1 

1L7 ISO  On/Off                    1 

SPI  MPT‐Main Prot. Trip     1 

BPT‐Back up  Prot. Trip     1 

   TCF‐Trip Circuit Faulty     1 

   SCF‐Spring Charge Fail    1 

SF6 LOW 1ST Step  1 

SF6 LOW 2ND Step  1 

Bay Faulty  1 

Master Trip Operated 1 

DC Source Fail  1 

Remote/Local  1 

Auto Reclose Operated  1 

Auto Reclose Lockout  1 

21 Relay Fail  1 

AMI  Active Power, P            1 

   Reactive Power, Q           1 

   Voltage, U           1 

   Current, I                       1    

DCO  1L3 ISO  Open/Close                   1 

1L5 CB   Open/Close                   1

1L7 ISO  Open/Close                  1

ITI  Energy, KWHR Imp              1 

   Energy, KVARHR Imp              1 

LINE 2  DPI  2L1 E/S  On/Off  1             

   2L3 ISO  On/Off  1 

2L5 CB   On/Off                    1 

2L7 ISO  On/Off                    1 

SPI  MPT‐Main Prot. Trip     1 

BPT‐Back up  Prot. Trip     1 

   TCF‐Trip Circuit Faulty     1 

   SCF‐Spring Charge Fail    1 

SF6 LOW 1ST Step  1 

SF6 LOW 2ND Step  1 

Bay Faulty  1 

Master Trip Operated 1 

DC Source Fail  1 

Remote/Local  1 

Auto Reclose Operated  1 

Auto Reclose Lockout  1 

21 Relay Fail  1 

                      

   AMI  Active Power, P            1    

Page 79: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 7 en 01 No. of p. 17

      Reactive Power, Q           1    

      Voltage, U           1    

Current, I                       1 

                       

DCO  2L3 ISO  Open/Close                   1 

2L5 CB   Open/Close                    1 

2L7 ISO  Open/Close                   1 

   ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

                      

LINE 3  DPI  3L1 E/S  On/Off  1             

      3L3 ISO  On/Off  1             

3L5 CB   On/Off                    1 

   3L7 ISO  On/Off                    1             

                      

SPI  MPT‐Main Prot. Trip     1 

BPT‐Back up  Prot. Trip     1 

   TCF‐Trip Circuit Faulty     1 

   SCF‐Spring Charge Fail    1 

SF6 LOW 1ST Step  1 

SF6 LOW 2ND Step  1 

Bay Faulty  1 

Master Trip Operated 1 

DC Source Fail  1 

Remote/Local  1 

Auto Reclose Operated  1 

Auto Reclose Lockout  1 

21 Relay Fail  1 

   AMI  Active Power, P            1    

      Reactive Power, Q           1    

      Voltage, U           1    

Current, I                       1 

                       

   DCO  3L3 ISO  Open/Close       1       

3L5 CB   Open/Close  1 

3L7 ISO  Open/Close 1 

                       

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

Tx 1 BAY  DPI  1H3 ISO On/Off                   1 

1H0 CB On/Off                   1 

SPI  MPT‐Main Prot. Trip     1 

BPT‐Back up  Prot. Trip     1 

   TCF‐Trip Circuit Faulty     1 

   SCF‐Spring Charge Fail    1 

SF6 LOW 1ST Step  1 

SF6 LOW 2ND Step  1 

Page 80: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 8 en 01 No. of p. 17

Bay Faulty  1 

Master Trip Operated 1 

DC Source Fail  1 

Remote/Local  1 

Auto Reclose Operated  1 

Auto Reclose Lockout  1 

Buchholz Trip  1 

Winding Temperature Trip  1 

Oil Temperature Trip  1 

Oil Level Alarm  1 

TC Manual/Auto  1 

TC Master/Follower  1 

AMI  Active Power, P            1 

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

DCO  1H3 ISO Open/Close                    1 

1H0 CB Open/Close                    1 

TC Raise/Lower                    1 

ITI  Energy, KWHR Imp              1 

   Energy, KVARHR Imp              1 

Tx 2 BAY  DPI  2H3  ISO On/Off                   1 

2H0 CB On/Off                   1 

SPI  MPT‐Main Prot. Trip     1 

BPT‐Back up  Prot. Trip     1 

   TCF‐Trip Circuit Faulty     1 

   SCF‐Spring Charge Fail    1 

SF6 LOW 1ST Step  1 

SF6 LOW 2ND Step  1 

Bay Faulty  1 

Master Trip Operated 1 

DC Source Fail  1 

Remote/Local  1 

Auto Reclose Operated  1 

Auto Reclose Lockout  1 

Buchholz Trip  1 

Winding Temperature Trip  1 

Oil Temperature Trip  1 

Oil Level Alarm  1 

TC Manual/Auto  1 

TC Master/Follower  1 

AMI  Active Power, P            1 

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

Page 81: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 9 en 01 No. of p. 17

DCO  2H3 ISO Open/Close                    1 

2H0 CB Open/Close                    1 

TC Raise/Lower                    1 

ITI  Energy, KWHR Imp              1 

      Energy, KVARHR Imp              1 

INCOMER 1  DPI  INC 1  E/S On/Off                   1 

INC1  CB On/Off                   1 

SPI  MPT‐Main Prot. Trip     1 

BPT‐Back up  Prot. Trip     1 

   TCF‐Trip Circuit Faulty     1 

   SCF‐Spring Charge Fail    1 

SF6 LOW 1ST Step  1 

SF6 LOW 2ND Step  1 

Remote/Local  1 

AMI  Active Power, P            1 

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

DCO  INC1  CB Open/Close                    1 

ITI  Energy, KWHR Imp              1 

   Energy, KVARHR Imp              1 

INCOMER2  DPI  INC 2  E/S On/Off                   1 

INC2  CB On/Off                   1 

SPI  MPT‐Main Prot. Trip     1 

BPT‐Back up  Prot. Trip     1 

   TCF‐Trip Circuit Faulty     1 

   SCF‐Spring Charge Fail    1 

SF6 LOW 1ST Step  1 

SF6 LOW 2ND Step  1 

Remote/Local  1 

AMI  Active Power, P            1 

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

DCO  INC2  CB Open/Close 

ITI  Energy, KWHR Imp 

   Energy, KVARHR Imp 

CAPACITOR FDR1  DPI  CB On/Off  1             

E/S On/Off                    1 

Page 82: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 10 en 01 No. of p. 17

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

      Remote/Local  1          

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

OTC FDR  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

Remote/Local  1 

                       

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

TEMPLE 2 FDR  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

Auto Reclose Operated  1 

Remote/Local  1 

                       

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

Page 83: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 11 en 01 No. of p. 17

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

                       

DONHOLM FDR  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

Auto Reclose Operated  1 

Remote/Local  1 

                 

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

LOCAL TX 100KVA  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

Remote/Local  1 

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

JEEVANJI 1 FDR  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

Auto Reclose Operated  1 

Remote/Local  1 

                       

Page 84: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 12 en 01 No. of p. 17

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

RIVER RD FDR  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

Auto Reclose Operated  1 

      Remote/Local  1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

BUS SECTION  DPI  CB On/Off  1 

SPI  MPT‐Main Prot. Trip     1 

   TCF‐Trip Circuit Faulty     1 

   SCF‐Spring Charge Fail    1 

Remote/Local  1 

MUTHURWA FDR  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

      Remote/Local  1          

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

   Current, I                       1    

Page 85: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 13 en 01 No. of p. 17

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

SPARE1 FDR  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

      Remote/Local  1          

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

JEEVANJI 2 FDR  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

Remote/Local  1 

                       

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

LOCAL TX  100KVA  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

Remote/Local  1 

                       

Page 86: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 14 en 01 No. of p. 17

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

SPARE 1  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

Remote/Local  1 

                       

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

KIKOMBA  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

Remote/Local  1 

                       

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

TEMPLE 1  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

Page 87: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 15 en 01 No. of p. 17

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

Remote/Local  1 

                       

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

CAPACITOR FDR2  DPI  CB On/Off  1             

E/S On/Off                    1 

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      Auto Reclose Operated  1          

Remote/Local  1 

                       

   DCO  CB Open/Close        1       

                       

   AMI  Active Power, P            1    

   Reactive Power, Q           1 

   Voltage, U           1 

Current, I                       1 

                       

   ITI  Energy, KWHR              1 

      Energy, KVARHR              1 

Station  DPI  Station Remote/Supervisory  1             

                       

   SPI  48 DC Battery Alarm    1          

      48 DC Charger Alarm    1          

      48V Charger A Fail Alarm    1          

      48V Charger B Fail Alarm    1          

      RTU Alarm     1          

      Communications Alarm    1          

      110V DC Battery Alarm    1          

      110V DC Charger Alarm    1          

      110V DC Charger A Fail Alarm    1          

      110V DC Charger B Fail Alarm    1          

      Smoke in Control Room     1          

                       

   AMI  48V DC1           1    

      48V DC2           1    

      110V DC1           1    

Page 88: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 16 en 01 No. of p. 17

      110V DC2           1    

                    

Total  52  179  31  92  42 

10.2 Installation and adaptation works

Siemens SICAM 1703 ACP CP 6014 gateway available but not yet connected to any

communication device.

It is expected to install and ADSS cable to the station through IT & T project. A multiplexer shall

therefore be required in this station for final connection to NCC

11. Enclosures

9.1 Site Survey Report

9.2 Detailed plant drawings

9.3 Control Room layout

9.4 Equipment Room Layout

9.4

12. Notes

distance from the site (km) 13.3 km from Juja rd NCC Nearby buildings Muthurwa Market & Machakos Country Bus Station Nearby industries Jua Kali light industries Type of soil Black cotton Soil Water availability Available Special authority pass Permit to work Type of area Urban Power supply 240V ac Pass issued by: Nairobi Area Regional Control

Page 89: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Muthurwa 66/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 17 en 01 No. of p. 17

13. Photographic Report

Pic.1: RTU cabinet with Siemens SICAM 1703 ACP CP 6014 gateway but not yet connected to radio.

Pic.2: Battery room

Page 90: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 17

Site Survey Report

To: Projects Engineer

Station: Nairobi West 66/11kV

1. General: Information

Project Site survey

Site Survey Engineers Metrine Jelagat & Tony Angatia

Survey Date 17th September 2014

Station Name & Contact Nairobi West 66/11 kV

Region &Town Nairobi West, Nairobi

Distance to Site(km) 16.1 km from Juja Rd NCC

Station Coordinates 1.310715°S,36.828613°E, 2366m

Access Road Kiganjo Avenue off Mombasa Rd

Station Voltage 66/11 kV

Cable Trenches Available

Notes:

The substation is situated along Kiganjo Avenue off Mombasa Road. There is an existing FOX515

multiplexer which shares its cabinet with an ETL equipment for PLC. The equipment is currently

in the old control building.

There also exists an RTU 560 and its marshalling cubicle in the station but they are not installed

The station is a 66/11KV substation with 66kV equipment located outdoors. There is a new 11kV, indoor switchboard type ABB , currently being installed at the station. The control and protection equipment for the transformers and 66kV lines are located in the old control building. The 11kV breakers are as shown in the room layout drawing of the new control building There are four 66KV lines and fifteen 11KV feeders and two transformers.

Page 91: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 2 en 01 No. of p. 17

2. Drawings Single Line Diagram

TX2

W33

1L5

1L3

1L1U/G Cable to RAGATI S/S NGONG RD

W37

1H0

2L7

2L5

2L3

2L1

2H3

2H0

BC

TX1

INC1 INC2

W39

OUT GOING FEEDERS

2H2W32

EMBAKASSI2EMBAKASSI1

To old Control room To old Control room

66/11kV 45MVA

11kV switchboard New Control room

66/11kV 45MVA

Page 92: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 3 en 01 No. of p. 17

The 11kv feeder panels in the new building are not yet labelled.

Station Layout

Page 93: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 4 en 01 No. of p. 17

3. Equipment Room

Location 1. New Control room

2. Old Control Room

Room type and Floor Stone building, concrete floor

Ceiling type Iron Sheets

L x W x H in meters 23.77x6.46x4.46m- new control room

AC Power 240/415 VAC

DC Power 110V for protection,

30V for protection of old 11kV switchboard- old control room

48V for scada and communication- old control Battery/charger

room

Rectifier Available

Batteries Available

Power Distribution Board Available

Grounding System Substation earthing

Security Guard at the gate, Room secured with non standard

contractor’s padlock

Access Road Kiganjo Avenue off Mombasa Rd

RTU/SAS RTU 560 in the old control room but not mounted

Marshalling Marshalling cubicle in the old control room but not mounted

Cable Routes Available

Communication Equipment Fox 515 equipment in the old control room

Page 94: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 5 en 01 No. of p. 17

4. RTU Available but not installed

5. Marshalling Cubicles Available but not installed

6. Communication Equipment Fox 515 available

7. Room layout

.

8. AC Supply 240/415VAC available

9. DC Supply 110V protection, 48V Scada and telecoms in the old control room

10. Plant Interface 10.1 Signals list

Attached

10.2 Installation and adaptation works The 11kV switchboard has been entirely replaced. Station adaptation works shall be required for the

board to a new RTU under this contract. The 66kV line relay panels & Transformer Panels are

Page 95: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 6 en 01 No. of p. 17

currently located in the old control building. Adaptation works for the same shall be required, these

are currently located in the old control building.

The distance between the two control buildings is approximately 50m

11. Enclosures 9.1 Site Survey Report

9.2 Detailed plant drawings

9.3 Control Room layout

9.4 Equipment Room Layout

12. Notes distance from the site (km) 16.1 km from Juja Rd NCC Nearby buildings Kongoni Primary School, Kenya Institute of Mass

Communication Nearby industries Industrial Area, CMC Type of soil Black Cotton Water availability Water available Special authority pass Permit to work Type of area Residential Power supply 240VAC Pass issued by: Nairobi Area Regional Control

Page 96: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 7 en 01 No. of p. 17

13. Photographic Report

Pic.1: ODF in the new building is on the floor next to 110 DC charger & not yet fitted to the wall

Pic.2: The outgoing 11kV feeders under construction in the new control building

Pic.3: New control building Pic.4:

Signal list

Nairobi West 66/11kV Signal list

OBJECT TYPE SIGNAL Indications Alarms Commands Measurands

Energy Meter Inputs

66kV

LINE 1 DPI 1L1 E/S On/Off 1

1L3 ISO On/Off 1 1L5 CB On/Off

1 W33 ISO On/Off

1

SPI MPT-Main Prot. Trip 1

BPT-Back up Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1 SF6 LOW 1ST Step 1 SF6 LOW 2ND Step 1 Bay Faulty 1 Master Trip Operated 1 DC Source Fail 1 Remote/Local 1

Auto Reclose Operated 1

Auto Reclose Lockout 1

21 Relay Fail 1

DCO 1L5 CB Open/Close

1

Page 97: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 8 en 01 No. of p. 17

1

LINE 2 DPI W39 ISO On/Off 1

SPI MPT-Main Prot. Trip 1

BPT-Back up Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1 SF6 LOW 1ST Step 1 SF6 LOW 2ND Step 1 Bay Faulty 1 Master Trip Operated 1 DC Source Fail 1 Remote/Local 1

Auto Reclose Operated 1

Auto Reclose Lockout 1

21 Relay Fail 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

DCO CB Open/Close 1

ITI Energy, KWHR Imp 1

Energy, KVARHR Imp 1

LINE 3 DPI 2L3 ISO On/Off 1

2L5 CB On/Off 1

W38 ISO On/Off 1

SPI MPT-Main Prot. Trip 1

BPT-Back up Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1 SF6 LOW 1ST Step 1 SF6 LOW 2ND Step 1 Bay Faulty 1 Master Trip Operated 1 DC Source Fail 1 Remote/Local 1

Auto Reclose Operated 1

Auto Reclose Lockout 1

21 Relay Fail 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current,I 1

Page 98: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 9 en 01 No. of p. 17

DCO 2L5 CB Open/Close 1

ITI Energy, KWHR 1

Energy, KVARHR 1

BUSBAR SECTION DPI 2H2 ISO On/Off 1

LINE 4 DPI W32 ISO On/Off 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

DCO CB Open/Close 1

ITI Energy, KWHR Imp 1

Energy, KVARHR Imp 1

Tx 1 BAY DPI W37 ISO On/Off 1

1H0 CB On/Off 1

SPI MPT-Main Prot. Trip 1

BPT-Back up Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1 SF6 LOW 1ST Step 1 SF6 LOW 2ND Step 1 Bay Faulty 1 Master Trip Operated 1 DC Source Fail 1 Remote/Local 1

Auto Reclose Operated 1

Auto Reclose Lockout 1

Buchholz Trip 1

Winding Temperature Trip 1

Oil Temperature Trip 1

Oil Level Alarm 1

TC Manual/Auto 1

TC Master/Follower 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

DCO CB Open/Close 1

Page 99: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 10 en 01 No. of p. 17

ITI Energy, KWHR Imp 1

Energy, KVARHR Imp 1

Tx 2 BAY DPI 2H3 ISO On/Off 1

2H0 CB On/Off 1

SPI MPT-Main Prot. Trip 1

BPT-Back up Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1 SF6 LOW 1ST Step 1 SF6 LOW 2ND Step 1 Bay Faulty 1 Master Trip Operated 1 DC Source Fail 1 Remote/Local 1

Auto Reclose Operated 1

Auto Reclose Lockout 1

Buchholz Trip 1

Winding Temperature Trip 1

Oil Temperature Trip 1

Oil Level Alarm 1

TC Manual/Auto 1

TC Master/Follower 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

DCO CB Open/Close 1

ITI Energy, KWHR Imp 1

Energy, KVARHR Imp 1

INCOMER 1 DPI INC 1 E/S On/Off 1

INC1 CB On/Off 1

SPI MPT-Main Prot. Trip 1

BPT-Back up Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1 SF6 LOW 1ST Step 1 SF6 LOW 2ND Step 1 Remote/Local 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I

Page 100: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 11 en 01 No. of p. 17

1

DCO INC1 CB Open/Close 1

ITI Energy, KWHR Imp 1

Energy, KVARHR Imp 1

INCOMER2 DPI INC 2 E/S On/Off 1

INC2 CB On/Off 1

SPI MPT-Main Prot. Trip 1

BPT-Back up Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1 SF6 LOW 1ST Step 1 SF6 LOW 2ND Step 1 Remote/Local 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

DCO INC2 CB Open/Close

ITI Energy, KWHR Imp

Energy, KVARHR Imp

K16 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1

Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K15 OUTGOING DPI CB On/Off 1

E/S On/Off

Page 101: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 12 en 01 No. of p. 17

1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1

Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K14 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1

Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K13 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1

Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Page 102: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 13 en 01 No. of p. 17

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K12 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1

Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K11 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1 Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K10 OUTGOING DPI CB On/Off 1

E/S On/Off 1

Page 103: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 14 en 01 No. of p. 17

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1

Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

BUS SECTION DPI CB On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1 Remote/Local 1

K07 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1 Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K06 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Page 104: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 15 en 01 No. of p. 17

Auto Reclose Operated 1

Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K05 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1

Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K04 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1

Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

Page 105: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 16 en 01 No. of p. 17

ITI Energy, KWHR 1

Energy, KVARHR 1

K03 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1 Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K02 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

SCF-Spring Charge Fail 1

Auto Reclose Operated 1 Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

K01 OUTGOING DPI CB On/Off 1

E/S On/Off 1

SPI MPT-Main Prot. Trip 1

TCF-Trip Circuit Faulty 1

Page 106: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nairobi West 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 17 en 01 No. of p. 17

SCF-Spring Charge Fail 1

Auto Reclose Operated 1

Remote/Local 1

DCO CB Open/Close 1

AMI Active Power, P 1

Reactive Power, Q 1

Voltage, U 1

Current, I 1

ITI Energy, KWHR 1

Energy, KVARHR 1

Station DPI Station Remote/Supervisory 1

SPI 48 DC Battery Alarm 1

48 DC Charger Alarm 1

48V Charger A Fail Alarm 1

48V Charger B Fail Alarm 1

RTU Alarm 1

Communications Alarm 1

110V DC Battery Alarm 1

110V DC Charger Alarm 1

110V DC Charger A Fail Alarm 1

110V DC Charger B Fail Alarm 1

Smoke in Control Room 1

AMI 48V DC1 1

48V DC2 1

110V DC1 1

110V DC2 1

Total 48 174 22 88 40

Page 107: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project Nyaga 33/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 9

Site Survey Report

To: Projects Engineer

Station: Nyaga Substation 33/11kV

1. General: Information

Project Site survey

Site Survey Engineers Metrine Jelagat

Survey Date 10th September 2014

Station Name & Contact Nyaga S/S 33/11 kV

Region &Town Nairobi North, Nairobi

Distance to Site(km) 40 km from Juja Control, 14 km from Ruiru town

Station Coordinates 1.0881160S, 36.8628190 E, 1698m ASL

Access Road Githunguri Rd from Ruiru Town, tarmac

Station Voltage 33/11 kV

Cable Trenches Under Construction

Notes:

The substation is situated along Ruiru- Githunguri Road. The station is currently under

construction, to include a new transformer bay

The substation shall have two 33/11KV , 7.5MVA transformer with an outdoor 11kv switch gear. The 11kV side has 2 incomers which are 11kV autoreclosures and airbreak switches and 4 feeders all controlled from outdoor A/B switches and autoreclosures

The new control room shall accommodate, two transformers and 66kV line protection panels and tap changer control panels.

There exists no SCADA equipment for the station.

There is no existing RTU.

Page 108: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nyaga 33/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 2 en 01 No. of p. 9

2. Drawings

X113 1L3

33 kV A/B SW.

33KV VWVE

TX17.5MVA

TX27.5MVA

Local TX

1L1

Single Line Diagram

33 kV

33 kV A/B SW

33 kV A/B SW.

33 kV A/B SW

33 kV A/B SW.

New feeder New feederGithunguri feeder Ruiru Feeder

RuiruGatundu West

33 kV

33KV VWVE

Page 109: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nyaga 33/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 3 en 01 No. of p. 9

3. Equipment Room

4. RTU It is proposed to install a new RTU in the control room as indicated on the room layout. Average length of cables shall be 15 meters and shall all be for bottom entry.

5. Marshalling Cubicles Not Available

6. Communication Equipment No communication equipment available at the station.

Location Control Panel room

Room type and Floor Stone building, concrete floor

Ceiling type Iron Sheets

L x W x H in meters 10x4.5x4M

AC Power 240/415 VAC

DC Power 30V for protection

Rectifier Not Available

Batteries Available

Power Distribution Board Available

Grounding System Substation Under Construction

Security Guard at the gate, Room secured with standard padlock

Access Road Southern Bypass -Ruiru – Githunguri Rd

RTU/SAS Not Available

Marshalling Not Available

Cable Routes Under construction

Communication Eqpt No communication equipment

Page 110: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nyaga 33/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 4 en 01 No. of p. 9

The most probable solution for communication

i. Option 1 an ADSS could be run from Ruiru S/S (about 20 Km from Ruiru S/S) and a multiplex equipment installed

ii. Option 2, install a radio mast plus radio equipment

7. Room layout

Communication room layout.

Page 111: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nyaga 33/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 5 en 01 No. of p. 9

8. AC Supply The room is still under construction

9. DC Supply

New 48v DC system is required. There is a 30V system for protection. The new system shall be located in the battery room next to the 30V DC charger as shown in the room layout diagram.

10. Plant Interface 10.1 Signals list

Attached

10.2 Installation and adaptation works An RTU and marshalling cubicle and a fiber optic terminal equipment to be installed at the

station. Cabling from all switch gear to the marshalling will need to be installed

11. Enclosures 9.1 Site Survey Report

9.2 Detailed plant drawings

9.3 Control Room layout

9.4 Equipment Room Layout

Page 112: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nyaga 33/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 6 en 01 No. of p. 9

12. Notes distance from the site (km) 40 km from Juja Control Nearby buildings Kwa Maiko shopping Centre Nearby industries Kangaita Coffee farms Type of soil Red Soil Water availability Special authority pass Permit to work Type of area Farm land Power supply 240VAC Pass issued by: Nairobi area control

13. photographic Report

Battery Room Station under construction

Signal list

Airport 66/11kV Signal list

OBJECT  TYPE  SIGNAL  Indications  Alarms  Commands  Measurands 

Energy Meter Inputs 

33kV  LINE 1 (Ruiru)  DPI E/S On/Off 1

   ISO On/Off 1

 

   AMI Active Power, P 1

   Reactive Power, Q 1

   Voltage, U 1

  

LINE 2 ( Gatundu West)  DPI E/S On/Off 1

   ISO On/Off 1

 

   AMI Active Power, P 1

   Reactive Power, Q 1

Page 113: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nyaga 33/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 7 en 01 No. of p. 9

   Voltage, U 1

  

33kV Busbar  DPI ISO On/Off 1

   DCO ISO Close/Open 1

TX1 BAY  DPI CB x114 On/Off 1

  

   SPI MPT‐Main Prot. Trip 1

   BPT‐Backup Prot. Trip 1

   Protection Faulty 1

  

   DCO CB x114 Open/Close 1

  

TX2 BAY  DPI CB On/Off 1

  

   SPI MPT‐Main Prot. Trip 1

   BPT‐Backup Prot. Trip 1

   Protection Faulty 1

  

   DCO CB Open/Close 1

  

TX1  DPI TC Auto/Manual 1

   TC Local/Remote 1

  

   SPI TTA‐Temp Alarm 1

   TTT TEMP TRIP 1

   TBA BUCH AL 1

   TBT BUCH TRIP 1

   TOL OIL LEVEL ALARM 1

   TGA TX GENERAL AL 1

   TGT TX GEN TRIP 1

   TBS TX OUT OF STEP 1

  

   DCO TC Auto/Manual 1

  

   RCO TC Raise/Lower 1

  

   AMI Tap Position 1

  

TX2  DPI TC Auto/Manual 1

   TC Local/Remote 1

  

   SPI TTA‐Temp Alarm 1

   TTT TEMP TRIP 1

   TBA BUCH AL 1

   TBT BUCH TRIP 1

   TOL OIL LEVEL ALARM 1

   TGA TX GENERAL AL 1

   TGT TX GEN TRIP 1

   TBS TX OUT OF STEP 1

  

   DCO TC Auto/Manual 1

  

Page 114: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nyaga 33/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 8 en 01 No. of p. 9

   RCO TC Raise/Lower 1

  

   AMI Tap Position 1

  

11 KV 

INCOMER 1  DPI CB INC1 On/Off 1

  

   DCO CB INC 1 Open/Close 1

 

   AMI Active Power, P 1

   Reactive Power, Q 1

   Voltage, U 1

  

INCOMER 2  DPI CB INC2 On/Off 1

  

   DCO CB INC 2 Open/Close 1

 

   AMI Active Power, P 1

   Reactive Power, Q 1

   Voltage, U 1

  

 11kV BUSBAR  AMI Volts, kV 1

  

11kV Feeders 

New feeder 1  DPI CB On/Off 1

  

   DCO CB Open/Close 1

 

   AMI Active Power, P 1

   Reactive Power, Q 1

   Voltage, U 1

  

Ruiru  DPI CB On/Off 1

  

   DCO CB Open/Close 1

 

   AMI Active Power, P 1

   Reactive Power, Q 1

   Voltage, U 1

  

Githunguri  DPI CB On/Off 1

  

   DCO CB Open/Close 1

 

   AMI Active Power, P 1

   Reactive Power, Q 1

   Voltage, U 1

  

New Feeder 2  DPI CB On/Off 1

  

   DCO CB Open/Close 1

 

Page 115: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Nyaga 33/11 kV Substation Prep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

Doc. no. Lang. Rev. ind. Page 9 en 01 No. of p. 9

   AMI Active Power, P 1

   Reactive Power, Q 1

   Voltage, U 1

  

Station  DPI Station Remote/Supervisory 1

  

   SPI 48 DC Battery Alarm 1

   48 DC Charger Alarm 1

   RTU Alarm 1

   Communications Alarm 1

   110V DC Battery Alarm 1

   110V DC Charger Alarm 1

  

   AMI 48V DC 1

   110V DC 1

  

Total  18  28  13  30  2 

Page 116: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appr Project Steel Billets 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Resp. dept Projects Status

Doc. no. Lang. Rev. ind. Page 1 en 01 No. of p. 9

Site Survey Report

To: Projects Engineer

Station: Steel Billets Substation 66/11kV

1. General: Information

Project Site survey

Site Survey Engineers Metrine Jelagat

Survey Date 10th September 2014

Station Name & Contact Steel Billets S/S 33/11 kV

Region &Town Nairobi North, Nairobi

Distance to Site(km) 1.5 km from Juja Control

Station Coordinates

Access Road Juja Road

Station Voltage 66/11 kV

Cable Trenches Undergoing construction

Notes:

The substation consists of one 66KV line, two 23 MVA transformers, the 11kV board has been decommissioned to be constructed anew The substation is situated at a turn off from the Juja Rd near Tononoka steel mills.

There is no radio but there is a communication mast installed in the station

An RTU was installed at the station but has since been recovered and parts used for other

stations

Page 117: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

A

P

T

Appro Prep. Title

Repo

2. Drawin

The 11

3. Equipm

Location

Room typ

Ceiling typ

L x W x H

AC Power

DC Power

Rectifier

Batteries

Power Dis

Grounding

ort on Site Vi

ngs

kV Board is

ment Room

e and Floo

pe

in meters

r

r

stribution B

g System

isit

s yet to be c

m

1

or S

I

N

N

A

Board N

S

Date

constructed

11kV room

Stone buildi

Iron Sheets

Not Availab

Not Availab

Available in

Available in

Not Availab

Station unde

Project

Customer

Dept

, the contro

ing, concret

ble

ble

n the decom

n the decom

ble

er construct

Steel B

Kenya P

Projects

ol room is em

te floor

missioned c

mmissioned

tion

illets 66/11 k

Power & Ligh

Sta

mpty

control room

control roo

kV Substatio

hting Co Ltd

atus

en 01

m

om

on

No. of p. 9

Page 118: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Steel Billets 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 9

4. RTU

A vandalised RTU 560 with cables in the decommissioned control room

5. Marshalling Cubicles Available in the decommissioned control room

6. Communication Equipment A communication mast exists, but there is no radio

7. Room layout

Room still under construction

8. AC Supply Room still under construction

9. DC Supply 110V protection, 48V Scada and telecoms in the decommissioned control building

10. Plant Interface 10.1 Signals list

Attached

10.2 Installation and adaptation works It is required that a complete scada equipment is installed at the station once the 11 kV board is

replaced. Details of the 11kV board are yet to be availed.

The 66kV side is still existing and would also need to be rewired to a new scada equipment.

A communication mast exists at the station, a radio would be required at the station for

communication to Juja control site.

Security Guard at the gate, Room secured with standard padlock

Access Road Juja Rd

RTU/SAS Decommissioned RTU560 with parts vanadalised

Marshalling Available with parts vandalised

Cable Routes New control room under construction

Communication Eqpt Radio communication mast available but no radio

Page 119: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Steel Billets 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 9

11. Enclosures 9.1 Site Survey Report

9.2 Detailed plant drawings

9.3 Control Room layout

9.4 Equipment Room Layout

12. Notes distance from the site (km) 1.5 km from Juja Control Nearby buildings Tononoka Steel Mills Nearby industries Tononoka Steel Mills Type of soil Black Cotton Water availability Water available from city council Special authority pass Permit to work Type of area Commercial Power supply 240VAC Pass issued by: Nairobi area control

13. Photographic Report RTU at site Marshalling Cubicle

Signal list as per original Station

Page 120: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Steel Billets 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 9

Steel Billets 66/11kV Signal list

OBJECT  TYPE  SIGNAL  Indications  Alarms  Commands  Measurands 

Energy Meter Inputs 

66kV                   66kV LINE   DPI  1L7 ISO  On/Off  1             

      1H5 ISO  On/Off  1             

      1L5 CB  On/Off  1             

                      

   DCO  1L5 CB  Open/Close        1       

                      

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

      SF6 LOW second step    1          

                      

TX1 BAY               

    DPI  ISO 3H3 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

                       

                       

TX2 BAY             

    DPI  ISO 2H3 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BPT‐Backup Prot. Trip     1          

               

TX1  DPI  TC Auto/Manual  1             

      TC Local/Remote  1             

       TC Master/Follower   1             

               

   SPI  TTA‐Temp Alarm     1          

      TTT TEMP TRIP     1          

      TBA BUCH AL     1          

      TBT BUCH TRIP     1          

      TOL OIL LEVEL ALARM    1          

      TGA TX GENERAL AL     1          

      TGT TX GEN TRIP     1          

      TBS TX OUT OF STEP    1          

                       

                       

   RCO  TC Raise/Lower        1       

                       

   AMI  Tap Position           1    

                       

Page 121: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Steel Billets 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 9

TX2  DPI  TC Auto/Manual  1             

      TC Local/Remote  1             

       TC Master/Follower   1             

   SPI  TTA‐Temp Alarm     1          

      TTT TEMP TRIP     1          

      TBA BUCH AL     1          

      TBT BUCH TRIP     1          

      TOL OIL LEVEL ALARM    1          

      TGA TX GENERAL AL     1          

      TGT TX GEN TRIP     1          

      TBS TX OUT OF STEP    1          

                       

                       

   RCO  TC Raise/Lower        1       

                       

   AMI  Tap Position           1    

                       

11 KV                      

INCOMER 1  DPI  CB INC1 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

      SF6 LOW second step    1          

                       

   DCO  CB INC 1 Open/Close        1       

                      

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

      Amps           1    

                       

   ITI  Energy, KWHR               1 

      Energy, KVARHR               1 

                       

INCOMER 2  DPI  CB INC2 On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      BYF‐Bay Faulty     1          

      Protection Faulty     1          

      TCF‐Trip Circuit Faulty     1          

      Lockout relay operated     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

      SF6 LOW second step    1          

                       

   DCO  CB INC 2 Open/Close        1       

                      

   AMI  Volts, kV           1    

      Active Power, P           1    

      Reactive Power, Q           1    

Page 122: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Steel Billets 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 9

      Amps           1    

                       

   ITI  Energy, KWHR               1 

      Energy, KVARHR               1 

                       

11kV BUSBAR  DPI  ISO BC  On/Off  1             

                       

   DCO  ISO BC  Open/Close        1       

                       

   AMI  Volts, kV           1    

      Frequency, F           1    

                       

11kV Feeders                      

Jacaranda  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

Eastleigh  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

                       

Sunrise  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

                       

VOK  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

Page 123: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Steel Billets 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 9

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

                       

Tononoka  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

                       

KCC  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

                       

Kayole  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail    1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

Komarock  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail     1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

Page 124: Site Survey Report - kplc.co.ke · A marshalling cubicle and a fiber optic terminal equipment to be installed at the station. Cabling from all switch gear to the marshalling will

Appro Project Steel Billets 66/11 kV SubstationPrep. Date Customer Kenya Power & Lighting Co Ltd Title

Report on Site Visit Dept Projects Status

en 01 No. of p. 9

PFCF  DPI  CB On/Off  1             

                       

   SPI  MPT‐Main Prot. Trip     1          

      TCF‐Trip Circuit Faulty     1          

      SCF‐Spring Charge Fail     1          

      SF6 LOW first step     1          

                       

   DCO  CB Open/Close        1       

                       

   AMI  Amps           1    

                       

                       

Station  DPI  Station Remote/Supervisory  1             

                       

   SPI  48 DC Battery Alarm    1          

      48 DC Charger Alarm    1          

      RTU Alarm     1          

      Communications Alarm    1          

      110V DC Battery Alarm    1          

      110V DC Charger Alarm    1          

                       

   AMI  48V DC1           1    

      48V DC2           1    

      110V DC1           1    

      110V DC2           1    

                    

Total  24  88  15  25  4