Site Survey Documents

for

Radio Network Planning

Description and Instruction

Page 2: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 2 of 32

Table of Contents

1. OVERVIEW OF THE DOCUMENTS............................................................................................................3

2. SEARCH AREA................................................................................................................................................4

3. RADIO PLANNING EVALUATION .............................................................................................................6

4. SITE SURVEY REPORT.................................................................................................................................7

5. SITE SURVEY REPORT PART I (ACQUISITION)....................................................................................8

5.1 OVERVIEW BUILDING DATA ......................................................................................................................105.2 RADIO PROPAGATION SPECIFIC DATA ...........................................................................................10

6. SITE SURVEY REPORT PART II (RADIO PLANNING)........................................................................23

6.1 ANTENNA CONFIGURATION .......................................................................................................................236.2 UNIT TO BE INSTALLED: .............................................................................................................................23

7. SITE SURVEY REPORT PART III (CIVIL WORKS) ..............................................................................24

7.1 ACCESS INFORMATION ...............................................................................................................................247.2 OPERATING ROOM DETAILS OR CONTAINER ...............................................................................................257.3 AIR-CONDITIONING ....................................................................................................................................277.4 POWER SUPPLY...........................................................................................................................................277.5 EARTHLING ................................................................................................................................................287.6 CABLE LAYOUT DETAILS ............................................................................................................................287.7 ROOF LAYOUT............................................................................................................................................297.8 SAFETY EQUIPMENT FOR CLIMBING:...........................................................................................................32

Page 3: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 3 of 32

1. OVERVIEW OF THE DOCUMENTS

The following diagram shows the different documents in the context of the radio networksurvey process:

Search Area

Site Survey Report Part I(Acquisition)

Site Survey Report Part II(Radio Planning)

Site Survey Report Part III(Civil Works)

Radio Planning Evaluation

Contract

Sender Receiver

Radio NetworkPlanning

Department

AcquisitionTeam

Radio NetworkPlanning

Department

Radio NetworkPlanning

Department

Radio NetworkPlanning

Department

Civil Works /Documentation

Civil WorksSurvey

Department

Civil Works /Documentation

AcquisitionTeam

AcquisitionTeam

Document

Page 4: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 4 of 32

2. SEARCH AREA

To be filled by radio planning department:Network area name will be defined by radio planning department.If a concrete candidate has been identified then the Site Name can be determined by the radioplanning department. In general the site name should correspond to the address or othercharacteristics.The Site No. (site number) will be defined by the radio planning departmentThe network Phase will be defined by the radio planning department. Changes of the phasewill be carried out by the network planning department only.The Cand. (candidate) can be indicated by a letter, i.e. A, but this is not a ranking of thecandidates.The Priority of the search area will be defined by the radio planning department for the wholesearch area (search ring)Date of issue of search area report (SAR Date)RF Responsible: Radio planner who issued the search area report

Network Area Name Site Name:

Site-No:: Phase Cand.: Priority:

Address(street, district)

Map No.: Scale:

SAR Date: RF Responsible:

To be filled by radio planning department:Co-ordinates either of the concrete site or the co-ordinates of the search area (centre of searchring)AMSL: total terrain heightSearch area range: radius of the search area

Description of the coverage objective per sector

Latitude Longitude

AMSL: Search area range

SECTOR 1:

SECTOR 2:Coverage Objectives

SECTOR 3:

To be filled by radio planning department:What is the Antenna Height from street level up to the bottom of the antenna in the NominalPlan?Type of site: Building, tower, etc.Will be a High Power amplifier (HPA) used?Will be a Low Noise Amplifier (LNA) used?Will be a power splitter used?How many sectors will be planned?

Page 5: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 5 of 32

Which BTS configuration (i.e. 2/2/2) will be implemented?Which BTS type will be recommended (i. e. BS-61) ?Which combiner type will be used (i. e. DUCOM 4:1)?

Antenna Height:(street level to bottomantenna)

TYPE OF SITE

HPA: LNA:POWERSPLITTER:

Number of sectors BTS ConfigurationRecommended BTS type Combiner Type

To be filled by radio planning department:What are the azimuths in degree of the Nominal Plan?What are the antenna types used in the Nominal Plan?How many antennas per sectors will be required?What is the EIRP per sector in the Nominal Plan?

Sector 1 Sector 2 Sector 3

Azimuth ( deg):

Antenna Type

Number of Antennas

EIRP ( dBm ):

Minimum one photograph per building candidate from street level is required.A block of buildings count as several candidates in order to able to determine a differentranking. But additional candidates have to be found in order to increase the possibility forcontracts.

Page 6: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 6 of 32

3. RADIO PLANNING EVALUATION

The whole document have to be filled by radio planning department.Site specific data Site No. Site Name and Candidate according to Search Area document.Co ordinates have to be checked and compared with the planning tool.Search area and deviation have to be checked.Antenna orientation have to be fixed.

Site No. Site Name Candidate

Acquisition Company

Project co-ordinates (Nominalcell plan from Tornado)

Lat.: Long.:

Survey report co-ordinates Lat.: Long.:

Radio Planning checked co-ordinates (from Tornado)

Lat.: Long.:

Search Area (m) Distance from Search Area (m)

Prediction height (m)

Missing information

Antenna orientation Sector 1: Sector 2: Sector 3:

The phase, priority, rank and Qual. Ind. (quality index) have to be determinedPhase: Phase of the search area (i. e. 1,2,3)Priority: Priority of the search area (i. e. high, medium, low)Rank: Ranking of the Candidates in the search area (i. e. 1,2,3, ...)Qual. Ind. : Quality of the Candidate (i. e. ++ , + , O , - , -- )

Decision whether the candidate is acceptable or not / Remark also the reasons

Radio Planning Acceptance YES NO

Phase: Priority: Rank: Qual. Ind.

Decision whether the candidate is to reject or not / Remark also the reasons

Radio Planning Rejection YES NO

Page 7: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 7 of 32

4. SITE SURVEY REPORT

The site survey report is divided in three parts:Part I: Site Survey Report (to be filled during first site survey by site acquisition company)Part II: Radio Planning Part (to be filled during final site survey after site evaluation by radioplanning department)Part III: General Site Data (to be filled during final site survey after site evaluation byimplementation team)

Part I is required for the radio planning department for the evaluation of the candidate and theranking of the candidates.If a candidate is accepted and ranked by the radio planning department the site acquisition cannegotiate a contract. Is a contract signed by the owner a final site survey will be carried out.During the final site survey the content of Part I will be checked and Part II and Part III will becompleted.

Photographs:Using digital cameras will speed up the site survey process (no delay because of developingseveral copies) and especially the distribution and filing of the information will be easier.A zoom of 50 – 60mm should be used so that the pictures are comparable with the view of ahuman eye.Photographs should be taken as such that buildings and obstacles can be seen. Thereforepictures should mainly contain the roofs of buildings, not the sky.

To be filled by acquisition company:Site Name can be defined as site address or as other characteristics.To be filled by acquisition company:Site Number is defined in accordance with search area report. A letter will be added to thesearch area number to name the Candidate. The letter does not indicate the priority of thesite.Example: search area number: 1050; site number: 1050AThe site number has to be unique. A site number can only be changed by the radio planningdepartment.

Page 8: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 8 of 32

5. SITE SURVEY REPORT PART I (ACQUISITION)

To be filled by acquisition company:Person who carried out the radio site survey. Date when site survey had been done.To be filled by acquisition company:Person who performed the site survey documentation. Date when site survey documentationhad been done.To be filled by acquisition company:Name of acquisition company which carried out the site survey.

Survey done by: Date:

Documentation done by: Date:

Acquisition Company:

To be filled by acquisition company:Site Number is defined in accordance with search area report. A letter will be added to thesearch area number. The letter does not indicate the priority of the site.Example: search area number: 1050; site number: 1050AThe site number has to be unique. A site number can only be changed by the radio planningdepartment.To be filled by acquisition company:Site Name is defined as site address.To be filled by radio planning department:The radio planning department defines a Rank and Quality Index from their radio planningpoint of view after the evaluation of several sites. The radio planning department has the rightto change these values afterwards. Available neighbour sites have an influence on the siteranking and quality index. Both values are also given to the acquisition on the Radio planningevaluation document.

To be filled by acquisition company:Co-ordinates should be taken by the GPS with one digit after the comma. The GPS shouldregister several satellites to be more accurate. The requested co-ordination system is:(European 1950)To be filled by acquisition company:The height of a site is defined as building height in meter.To be filled by acquisition company:The number of floors can be distinguished in a ground floor, the other floors and an elevatorbox or extra high floor. Example: 1+ 6+ 1 means a house with a bigger ground floor, 6 otherfloors and an elevator box.To be filled by acquisition company:A description and pictures of other transmitting antennas is required. The frequency band isalso of interest.

Site Specific Data:

Site No.: Site Name: Candidate:

Phase: Priority: Rank: Qual. Ind.

Address:

Page 9: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 9 of 32

Contact Person:Address:

Tel:Fax:

Co-ordinates: Longitude: Latitude: GPS: MAP:

Height of a site number of floors:

Site type: Tower Building Chimney Other

Roof type:

Comments

Other systems transmitting antennas(existing or planned)

Description:

To be filled by acquisition company:Mark the ownership of the property.

Acquisition probability One owner Multi

property

Company

building

Admin. Building Owned by xxx Others

Yes

To be filled by acquisition company:It is very important to know for the project rollout how long the estimated contract period will befor the site.Estimation concerning contract period:

Short

Medium

Long

To be filled by local SIEMENS Acquisition Manager:Site Survey Documentation checked on completenessby Acquisition Company Manager : __________________, on ______________

To be filled by radio planning department:Site Survey Documentation accepted on qualityby Radio Network Planning : __________________, on ______________

To be filled by radio planning department:Ranking and Quality Index givenby Radio Network Planning : __________________, on ______________

To be filled by radio planning department:Site rejectedby Radio Network Planning : __________________, on ______________

Page 10: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 10 of 32

To be filled by acquisition company:This part is important for the installation.

5.1 Overview Building DataTo be filled by site acquisition company:The following tables contain main building data which should be known right from thebeginning.

Building constructionStaircase dimensionElevator dimensionIs the Roof top flat? Yes NoRoof materialAccess to the floorRoof dimensionAvailable room (>10m2) Yes NoRoom dimension

Drilling allowed Yes No Heavy truck access Yes No

If no access with truck or mobile crane. how will we transport equipment to roof

Existing infrastructure Yes NoAccess to PTT’s fiber networkAccess to xxx’s fiber networkEarthingPower 220V ACElectric companyDistance to Power meters

5.2 RADIO PROPAGATION SPECIFIC DATA

5.2.1 Antenna Specific DataProposal to be done by site acquisition company:

Sector no: 1 Sector no: 2 Sector no: 3

Antenna type:

Direction:

Proposed antenna

direction; degrees

on compass

Proposed

antenna direction;

degrees on

compass

Proposed antenna

direction; degrees

on compass

Page 11: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 11 of 32

Height of Antenna:

Total antenna

height from street

level to bottom of

antenna

Total antenna

height from street

level to bottom of

antenna

Total antenna

height from street

level to bottom of

antenna

wall wall wall

mast mast mast

roof roof roof

tower reeling tower reeling tower reeling

Way of installation:

Mark with x appropriate answer

other other other

Page 12: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 12 of 32

5.2.2 Site Location map

To be filled by acquisition company:Use a street map so that the site location can easily be found.Mark the building.Use one Map per site/candidate.

Page 13: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 13 of 32

5.2.3 Antenna installation and roof sketchTo be filled by acquisition company:Do a roof sketch with measured size of roof.Mark the proposed antenna locations and the proposed antenna directions. Mark alternativesas well. Measure the distance between the antenna locations and the roof edge in the antennadirection.Mark the positions where all photos (panoramic photos, etc.) had been made and indicate thephoto numbers.Indicate if any restrictions exist for antenna placement.

To be verified by radio planning department during site evaluation.

1.

Approved by Radio:Signature

Date:

Page 14: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 14 of 32

5.2.4 Layout Building (show the high levels)

To be filled by acquisition company.To be verified by radio planning department during site evaluation.

Approved by Radio:Signature

Date:

Page 15: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 15 of 32

5.2.5 Site photos (from ground level)

To be filled by acquisition company:Make photographs from the site so that the building can be identified. If this is a new candidateproposed by site acquisition follow the search area guidelines as well.

Page 16: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 16 of 32

5.2.6 Roof Photos

To be filled by acquisition company:Photograph from the roof access. Indicate if access is problematic.Photographs of the roof.

Page 17: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 17 of 32

5.2.7 BTS place photos

To be filled by acquisition company:Photograph of the proposed BTS location. Indicate whether restrictions concerning BTSplacements exist.

Page 18: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 18 of 32

5.2.8 Panorama photos from roof level each 30 deg. Panorama starts fromnorth direction and then pictures are taken clockwise.

To be filled by acquisition company:Compass shall be visible on the picture. Therefore mistakes will be avoided. If i.e. two elevatorboxes are on the roof then panoramic photos shall be taken from both boxes. Document whichphotos where taken from which box. Mark the position where the panoramic photos had beentaken. Clearly indicate the locations where the panoramic photos had been taken, especiallywhen several locations were used for panoramic photos. Indicate which photo number hadbeen made at a location.

Page 19: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 19 of 32

5.2.9 Photos in direction of each antenna at antenna location (three photosper antenna)

To be filled by acquisition company:Make photos in proposed antenna directions (app. 90 degrees). Try to make the photos at theantenna location and at their proposed height. Indicate which pictures belong to an antennalocation.

Page 20: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 20 of 32

To be filled by acquisition company:Azimuth range in degree; values on the compass;Distance in meterHeight in meter defined as building height including elevator boxesCharacteristic description of the obstacle so that the obstacle can be identified on thepictures.

5.2.10 Obstacles: describe all obstructing obstacles (<200m) of height equalor higher than the site# Azimuth Distance Height

AGL

Description

1

2

3

4

5

6

7

8

9

10

11

12

5.2.10.1 Notes:

To be filled by acquisition company:Any other information

Page 21: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 21 of 32

5.2.10.2 Obstacle mapTo be filled by acquisition company:The distance between two circles correspond to 50m. Mark the positions of the differentobstacles, add the obstacle number and draw the shape of the obstacle. Draw lines from thecentre of the circle via the edges of the obstacles to the biggest circle in order to make theshadowing effects visible.

45º

90º270

225

180

135

335

50m 100m 150m 200m 250m300

Completely free of obstacles. (If there are not any obstacles mark herewith a “X”)

1

Page 22: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 22 of 32

5.2.10.3 Obstacle Pictures:

To be filled by acquisition company:

Make separate pictures of the obstacles and indicate the obstacle number.

Page 23: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 23 of 32

6. SITE SURVEY REPORT PART II (RADIO PLANNING)

6.1 Antenna Configuration

NUMBER OF SECTORSSector no: 1 Sector no: 2 Sector no: 3

Antenna type:

Combiner type

HPA

LNA

Power Splitter

EIRP

Direction/Azimuth:

Total Tilt:

Mechanical tilt:

Electrical tilt:

Number of Carriers

Approximate Cable Length

Cable Type

Height of Antenna:(street level to bottom of antenna)

wall wall wall

mast mast mast

roof roof roof

tower reeling tower reeling tower reeling

Way of installation:

Mark with x appropriate answer

other other other

6.2 Unit to be installed:BS-60 ❑ BS-61 ❑BS-20 ❑ BS-21 ❑ BS-22 ❑BS-11 ❑BS-240 ❑ BS-241 ❑

Additional microwave ❑

Typical values for the attenuation of cables.Table for cables:Attenuation [dB / 100 m]Type 900 MHz 1800 MHz1/2 “ 7,3 11,07/8 ” 4,1 6,21 1/4 ” 2,9 4,51 5/8 2,5 4,0

Page 24: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 24 of 32

7. SITE SURVEY REPORT PART III (CIVIL WORKS)

7.1 Access information

7.1.1 Access road:

7.1.2 Unloading point, difficulties etc.:

7.1.3 Minimum space in the clear of transport way inside the building:

Width: __________ mm Height: ___________ mm

7.1.4 Lift available?

YES NO

7.1.5 Space in the clear of lift:

Length: _________ Width: _________ Height: _________ mm

- Load capacity of lift: __________ kg

7.1.6 Remarks

Page 25: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 25 of 32

7.1.7 Remarks on access

7.2 Operating room details or container

Operation container room

7.2.1 Unit to be installed

BS60 BS61 BS20 BS21 BS22Number of pcs.

BS11 BS240 BS241Number of pcs.

7.2.2 Dimensions

- Length: __________ in mm- Width : __________ in mm- Height: __________ in mm

7.2.3 Restriction in space in the clear of mounting area

YES NO

7.2.4 If yes, what restrictions:

Page 26: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 26 of 32

7.2.5 Key deposit location

7.2.6 Wall type

Concrete Brick Others

Thickness ____________________mm

7.2.7 Remarks

7.2.8 Sketch of BTS room:

Page 27: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 27 of 32

7.3 Air-conditioning

7.3.1 Must be an Air-conditioning system provided?

YES NO

7.3.2 Remarks

7.4 Power supply

7.4.1 Power supply provided?

YES NO

Date it will be provided by __________________________

Will be provided from __________________________

Distance between power distributor and BTS _____________

7.4.2 Will be provided a new current supply?

YES NO

7.4.3 Remarks

Page 28: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 28 of 32

7.4.4 Generator available?

YES NO

Power: KW

7.5 Earthling

7.5.1 Is available existing earthling system and also we can use it?

YES NO

7.5.2 Will be necessary to provide a new earthling system?

YES NO

7.5.3 Lightning protection

- Antenna feeder cable, mast

7.6 Cable layout details

7.6.1 Cable trays

-Type of cable trays

Min. width of cable traysCover of cable trays :

Page 29: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 29 of 32

7.6.2 Remarks

7.6.3 Cable layout details

- 2-Mbit-links available

YES NO

- Length of Antenna cables _____________________________

- Type of antenna cable _____________________________

7.7 Roof layout

7.7.1 Dimensions of the roof for mounting BTS:

- Height: ______________ in mm

- Width: ______________ in mm

7.7.2 Restriction in space in the clear of mounting area

YES NO

Page 30: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 30 of 32

7.7.3 If yes, what restrictions

7.7.4 Roof characteristicsRoof type

7.7.5 Wall type to hang BTS

Concrete Brick Others

Thickness __________________ mm

7.7.6 Remarks

7.7.7 Wall type to hang antenna holders

Concrete Brick Others

Thickness __________________ mm

Page 31: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 31 of 32

7.7.8 Remarks

7.7.9 Number of antenna holders for GSM

7.7.10 Number of antenna holders for MW

7.7.11 Access to GSM antennas

7.7.12 Access to MW

Page 32: Site Survey Description for RN Planning

file name:Site_Survey_Description.doc Page 32 of 32

7.7.13 Sketch of the roof (incl. cables, earthling, grounding)

7.8 Safety equipment for climbing: