Site Planning Activities for Construction

2
PROJECT : ARKEMA LYCHEE PROJEC BUILDING,KERTEH, KEMAMAN, TERE PLANNING FOR SITE ACTIVITIES 2 Date Location Admin building Control room Lockers Laboratory SS 9101 SS 9102 Admin building Control room Lockers Laboratory SS 9101 SS 9102 Admin building Control room Lockers Laboratory SS 9101 SS 9102 Admin building Control room Lockers Laboratory SS 9101 SS 9102 Admin building Control room Lockers Laboratory SS 9101 SS 9102 Prepared by : Name : Position : 21/08/2013 Wednesday 22/08/2013 Thursday ( extend to night shift) 23/08/2013 Friday 24/08/2013 Saturday ( extend to night shift) 25/08/2013 Sunday (extend to night shift)

description

This file shown how to planning construction activities for building

Transcript of Site Planning Activities for Construction

Page 1: Site Planning Activities for Construction

PROJECT : ARKEMA LYCHEE PROJECT CONTROL ROOM & SUPPORT BUILDING,KERTEH, KEMAMAN, TERENGGANU DARUL IMAN

PLANNING FOR SITE ACTIVITIES 21/08/13 - 25/08/13

Date Location Description works activities

Admin buildinginstallation rebar & formwork for pile cap and column stumpdismantle 10 nos formwork pile cap

Control roominstallation rebar for slabinstallation formwork for slab perimeter

Lockersmark center line for pile cap formworkinstallation pile plug Ѳ 400 for 26 nos

Laboratoryinstallation pile plugmark center line for pile cap formwork

SS 9101lay bitumen coating for pile capback filling & compacting for pile cap

SS 9102pump the water pondingas built for cut off pile mark center line for pile cap formwork

Admin buildingconcreting works for pile capdismantle formwork and bitumen coating for pile cap

Control roominstallation rebar and formwork for slabpiping works for toilet location

Lockers concreting works for pile plugLaboratory cut off pile

SS 9101field density testinstallation rebar for ground beam

SS 9102 installation rebar for pile cap

Admin buildingdismantle formwork and lay bitumen coating for pile capback filling & compacting for pile cap

Control roominstallation rebar and formwork for slabpiping works for toilet location

Lockers installation rebar and formwork for pile capLaboratory continue cut off pile

SS 9101 installation rebar and formwork for ground beamSS 9102 installation rebar and formwork for pile cap

Admin building installation rebar for ground beamControl room installation rebar for slab

Lockers installation rebar and formwork for pile capLaboratory pile plug and concreting work

SS 9101 installation rebar and formwork for ground beamSS 9102 installation rebar and formwork for pile cap

Admin buildingdismantle formwork for ground beaminstallation rebar and formwork for column

Control room curing concreting for slabLockers installation rebar for pile cap

Laboratory installation rabr for pile capSS 9101 installation rebar and formwork for ground beamSS 9102 installation rebar and formwork for pile cap

Prepared by :

Name : Khairul Adli

Position : Project Engineer

21/08/2013 Wednesday

22/08/2013 Thursday ( extend to night shift)

23/08/2013 Friday

24/08/2013 Saturday

( extend to night shift)

25/08/2013 Sunday

(extend to night shift)