PROJECT : ARKEMA LYCHEE PROJECT CONTROL ROOM & SUPPORT BUILDING,KERTEH, KEMAMAN, TERENGGANU DARUL IMAN
PLANNING FOR SITE ACTIVITIES 21/08/13 - 25/08/13
Date Location Description works activities
Admin buildinginstallation rebar & formwork for pile cap and column stumpdismantle 10 nos formwork pile cap
Control roominstallation rebar for slabinstallation formwork for slab perimeter
Lockersmark center line for pile cap formworkinstallation pile plug Ѳ 400 for 26 nos
Laboratoryinstallation pile plugmark center line for pile cap formwork
SS 9101lay bitumen coating for pile capback filling & compacting for pile cap
SS 9102pump the water pondingas built for cut off pile mark center line for pile cap formwork
Admin buildingconcreting works for pile capdismantle formwork and bitumen coating for pile cap
Control roominstallation rebar and formwork for slabpiping works for toilet location
Lockers concreting works for pile plugLaboratory cut off pile
SS 9101field density testinstallation rebar for ground beam
SS 9102 installation rebar for pile cap
Admin buildingdismantle formwork and lay bitumen coating for pile capback filling & compacting for pile cap
Control roominstallation rebar and formwork for slabpiping works for toilet location
Lockers installation rebar and formwork for pile capLaboratory continue cut off pile
SS 9101 installation rebar and formwork for ground beamSS 9102 installation rebar and formwork for pile cap
Admin building installation rebar for ground beamControl room installation rebar for slab
Lockers installation rebar and formwork for pile capLaboratory pile plug and concreting work
SS 9101 installation rebar and formwork for ground beamSS 9102 installation rebar and formwork for pile cap
Admin buildingdismantle formwork for ground beaminstallation rebar and formwork for column
Control room curing concreting for slabLockers installation rebar for pile cap
Laboratory installation rabr for pile capSS 9101 installation rebar and formwork for ground beamSS 9102 installation rebar and formwork for pile cap
Prepared by :
Name : Khairul Adli
Position : Project Engineer
21/08/2013 Wednesday
22/08/2013 Thursday ( extend to night shift)
23/08/2013 Friday
24/08/2013 Saturday
( extend to night shift)
25/08/2013 Sunday
(extend to night shift)