PROCEDURE TITLE :PROJECT CONTROL Revisio DAILY SITE REPORT F/PCSB/ Project Proposed Housing Design Bukit Banyan Date : 10/30/2015 Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine Rain Hours affected by rain : Daily Workforce Summary Staff SkilledUnskilled Total Plant / Machineries Engineer 1 1 Piling Rig Supervisor 1 1 2 Bar bending machine Carpenter/General Worker 20 20 Bar cutting machine Barbender 10 10 Plate compactor Bricklayer 12 12 Backhoe Tiler 4 4 Forklift Electrician Wireman 3 3 Lorry Plumber 4 4 Crane Machine Operator 4 4 Total 60 Site Activities 717/718 : Installation of telcomunication cabel electrical part in progress 721/722 : Installation of formwork roof beam and flat roof water tank in progress Bricklayer lay and bond brick to construct brickwork at ground floor slab of housing wall 727/728 : Installation of pilecap spun piles foundation in progress 726/725 : Installation of pilecap spun piles foundation in progress 739/740 : Installation of telcomunication cabel electrical part in progress 745/746 : Bricklayer construct fencing house in progress Tiling of works architecture part in progress Lanscape of works in progress 899/900 : Installation of formwork 1st floor slab and continous beam in progress 927/928 : Installation of conduit electrical part in progress Installation of UPVC pipe mechanical part at 1st floor slab in progress Barbender Yard : Cut and bend tensile steel bar and mild steel bar on site in progress Note: Please attach additional page if required. Prepared By ………………………… SC / PC / PE / SE / SSS / SS PARAMOUNT CONSTRUCTION SDN BHD

description

useful daily

Transcript of Site Daily - October

Page 1: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/30/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 20 20 Bar cutting machine 1Barbender 10 10 Plate compactor 0Bricklayer 12 12 Backhoe 2Tiler 4 4 Forklift 1Electrician Wireman 3 3 Lorry 1Plumber 4 4 Crane 0Machine Operator 4 4

Total 60

Site Activities

717/718 : Installation of telcomunication cabel electrical part in progress721/722 : Installation of formwork roof beam and flat roof water tank in progress : Bricklayer lay and bond brick to construct brickwork at ground floor slab of housing wall in progress727/728 : Installation of pilecap spun piles foundation in progress726/725 : Installation of pilecap spun piles foundation in progress739/740 : Installation of telcomunication cabel electrical part in progress745/746 : Bricklayer construct fencing house in progress : Tiling of works architecture part in progress : Lanscape of works in progress899/900 : Installation of formwork 1st floor slab and continous beam in progress927/928 : Installation of conduit electrical part in progress : Installation of UPVC pipe mechanical part at 1st floor slab in progress

Barbender Yard : Cut and bend tensile steel bar and mild steel bar on site in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 2: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/29/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 25 25 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 9 9 Backhoe 2Tiler 4 4 Forklift 1Electrician Wireman 2 2 Lorry 2Plumber 6 6 Crane 25t 1Concretor 8 8Machine Operator 6 6

Total 74Site Activities

717/718 : Installation of telcomunication cabel electrical part in progress719/720 : Setting out door frame position at 1st floor slab in progress721/722 : Installation of formwork roof beam and flat roof water tank in progress : Bricklayer lay and bond brick to construct brickwork at ground floor slab of housing wall in progress727/728 : Installation of pilecap spun piles foundation in progress726/725 : Installation of pilecap spun piles foundation in progress735/736 : Removal of soffit formwork 1st floor slab in progress739/740 : Installation of telcomunication cabel electrical part in progress745/746 : Bricklayer construct fencing house in progress : Tiling of works architecture part in progress : Lanscape of works in progress899/900 : Installation of formwork 1st floor slab and continous beam in progress901/902 : Removal of formwork ground floor column in progress927/928 : Installation of conduit electrical part in progress : Installation of UPVC pipe mechanical part at 1st floor slab in progress

931/932 : *Concreting of works roof beam and flat roof water tank in progress (23m³ G25N)737/738 : *Concreting of works upper roof beam and stifffener in progress (6m³ G25N)735/736 : *Concreting of works R.C staircase in progress (6m³ G25N)

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 3: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/28/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 21 21 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 14 14 Backhoe 2Tiler 4 4 Forklift 1Concretor 7 7 Lorry 1Electrician 2 2 Crane 25t 1Machine Operator 5 5

Total 67

Site Activities

717/718 : Installation of telcomunication cabel electrical part in progress719/720 : Setting out door frame position at 1st floor slab in progress721/722 : Installation of formwork roof beam and flat roof water tank in progress : Bricklayer lay and bond brick to construct brickwork at ground floor slab of housing wall in progress727/728 : Installation of pilecap spun piles foundation in progress726/725 : Installation of pilecap spun piles foundation in progress735/736 : Removal of soffit formwork 1st floor slab in progress745/746 : Bricklayer construct fencing house in progress : Tiling of works architecture part in progress : Lanscape of works in progress899/900 : Installation of formwork 1st floor slab and continous beam in progress927/928 : Fixing rebar and lay BRC of works at 1st floor slab and continous beam in progress

929/930 : *Concreting of works 1st floor column in progress (5m³ G25N)929/930 : *Concreting of works R.C staircase in progress (6m³ G25N)901/902 : *Concreting of works ground floor column in progress (5m³ G25N)923/924 : *Concreting of works ground floor beam in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 4: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/27/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 17 17 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 15 15 Backhoe 2Tiler 4 4 Forklift 1Ceiling Worker 0 0 Lorry 1Electrician & Plumber 0 0 Crane 0Machine Operator 4 4

Total 54

Site Activities

721/722 : Installation of formwork roof beam and slab water tank in progress727/728 : Installation of formwork pilecap spun piles foundation in progress739/740 : Bricklayer lay and bond brick to construct brickwork in construction of house wall in progress745/746 : Bricklayer construct fencing house in progress : Tiling of works architecture part in progress905/906 : Fixing rebar of works pilecap spun piles foundation in progress927/928 : Fixing rebar and lay BRC of works at 1st floor slab and continous beam in progress931/932 : Installation of conduit electrical part at roof beam in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 5: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/26/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 20 20 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 13 13 Backhoe 2Tiler 4 4 Forklift 1Ceiling Worker 0 0 Lorry 1Concretor 0 0 Crane 25t 0Machine Operator 4 4

Total 55

Site Activities

721/722 : Installation of formwork roof beam and slab water tank in progress733/734 : Fixing rebar of works pilecap spun piles foundation in progress735/736 : Fixing rebar of works r.c staircase in progress739/740 : Bricklayer lay and bond brick to construct brickwork in construction of house wall in progress745/746 : Bricklayer construct fencing house in progress : Tiling of works architecture part in progress901/902 : Installation of formwork ground floor column in progress923/924 : Fixing rebar of works ground floor beam in progress929/930 : Installation of formwork tread and riser r.c staircase in progress931/932 : Fixing rebar of works roof beam and BRC slab water tank in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 6: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/25/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 0 0 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 20 20 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 13 13 Backhoe 2Tiler 4 4 Forklift 1Ceiling Worker 0 0 Lorry 1Concretor 0 0 Crane 0Machine Operator 4 4

Total 54

Site Activities

721/722 : Installation of formwork roof beam and slab water tank in progress733/734 : Installation of formwork pilecap foundation in progress735/736 : Installation of formwork soffit R.C staircase in progress739/740 : Bricklayer lay and bond brick to construct brickwork in construction of house wall in progress745/746 : Bricklayer construct fencing house in progress : Tiling of works architecture part in progress901/902 : Fixing rebar of works ground floor column in progress923/924 : Installation of formwork ground floor beam in progress929/930 : Installation of formwork tread and riser r.c staircase in progress931/932 : Fixing rebar of works roof beam and BRC slab water tank in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 7: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/24/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 0 1 1 Bar bending machine 2Carpenter/General Worker 15 15 Bar cutting machine 1Barbender 10 10 Plate compactor 0Bricklayer 12 12 Backhoe 2Tiler 4 4 Forklift 1Ceiling Worker 0 0 Lorry 1Concretor 0 0 Crane 0Machine Operator 4 4

Total 47

Site Activities

721/722 : Installation of formwork roof beam and slab water tank in progress733/734 : Installation of formwork pilecap foundation in progress735/736 : Removal of formwork 1st floor slab and continous beam in progress739/740 : Bricklayer lay and bond brick to construct brickwork in construction of house wall in progress745/746 : Bricklayer construct fencing house in progress : Tiling of works architecture part in progress899/900 : Installation of formwork 1st floor slab and continous beam in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 8: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/23/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 15 15 Bar cutting machine 1Barbender 11 11 Plate compactor 0Tiler 4 4 Backhoe 2Handrail Installer 3 3 Forklift 1Bricklayer 12 12 Lorry 1Machine Operator 4 4 Crane 0

Total 52

Site Activities

721/722 : Installation of formwork roof beam and slab water tank in progress735/736 : Removal of formwork 1st floor slab and continous beam in progress739/740 : Bricklayer lay and bond brick to construct brickwork in construction of house wall in progress745/746 : Bricklayer construct fencing house in progress : Installation of staircase steel handrail in progress : Tiling of works architecture part in progress901/902 : Installation of formwork ground floor column in progress923/924 : Installation of formwork ground floor beam in progress927/928 : Installation of formwork flat roof car porch in progress929/930 : Removal of formwork soffit 1st floor slab and continous beam in progress931/932 : Fixing of rebar roof beam and BRC slab water tank in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 9: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/22/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 22 22 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 7 7 Backhoe 2Tiler 4 4 Forklift 1Concretor 7 7 Lorry 1Machine Operator 5 5 Crane 1Handrail Installer 3 3

Total 62

Site Activities

721/722 : Installation of formwork roof beam and slab water tank in progress735/736 : Removal of formwork 1st floor slab and continous beam in progress739/740 : Bricklayer lay and bond brick to construct brickwork in construction of house wall in progress745/746 : Bricklayer construct fencing house in progress : Installation of staircase steel handrail in progress : Tiling of works architecture part in progress901/902 : Fixing rebar of works 1st floor column in progress903/904 : Fixing rebar of works pad footing foundation in progress929/930 : Removal of formwork soffit 1st floor slab and continous beam in progress931/932 : Fixing rebar of works roof beam and slab water tank in progress

729/730 : *Concreting of works pilecap foundation in progress (9.5m³ G25N)731/732 : *Concreting of works pilecap foundation in progress (9.5m³ G25N)

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 10: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/21/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 15 15 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 7 7 Backhoe 2Concretor 7 7 Forklift 1Machine Operator 6 6 Lorry 2Handrail Woker 3 3 Crane 25t 1

Total 52

Site Activities

719/720 : Bricklayer lay brick to construct brickwork in construction of house wall in progress737/738 : Removal of formwork upper roof beam and stiffener in progress745/746 : Bricklayer construct fencing house in progress : Installation of staircase steel handrail in progress897/898 : Marking 1st floor column position in progress923/924 : Lean concrete base ground floor beam in progress929/930 : Marking 1st floor column position in progress931/932 : Installation of formwork roof beam and slab water tank in progress

735/736 : *Concreting of works 1st floor slab and continous beam in progress (65m³ G25N)927/928 : *Concreting of works apron car porch in progress (5m³ G25N)

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 11: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/20/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 17 17 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 10 10 Backhoe 2Window Installer 3 3 Forklift 1Machine Operator 4 4 Lorry 1

Crane 25t 0

Total 48

Site Activities

719/720 : Bricklayer lay brick to construct brickwork in construction of house wall in progress737/738 : Fixing rebar of works upper roof beam and stiffener in progress745/746 : Bricklayer construct fencing house in progress : Installation of casement window at 1st floor slab and ground floor slab in progress897/898 : Removal of formwork soffit 1st floor slab and continous beam in progress905/906 : Installation of formwork pilecap spun piles foundation in progress929/930 : Removal of formwork soffit 1st floor slab and continous beam in progress931/932 : Installation of formwork roof beam and slab water tank in progress

Barbender Yard : Cut and bend tensile steel bar and mild steel bar on site in progress

``

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 12: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/19/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 0 0 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 17 17 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 5 5 Backhoe 2Plumber 6 6 Forklift 1Machine Operator 4 4 Lorry 1

Crane 25t 0

Total 45

Site Activities

719/720 : Removal of formwork upper roof beam and stiffener in progress729/730 : Fixing of rebar of works pilecap spun piles foundation in progress731/732 : Fixing of rebar of works pilecap spun piles foundation in progress737/738 : Installation of formwork upper roof beam and stiffener in progress745/746 : Installation of gully trap mechanical part in progress : Bricklayer construct fencing house in progress897/898 : Removal of formwork soffit 1st floor slab and continous beam in progress905/906 : Installation of formwork pilecap spun piles foundation in progress929/930 : Removal of formwork soffit 1st floor slab and continous beam in progress931/932 : Installation of formwork roof beam and slab water tank in progress

`Barbender Yard : Cut and bend tensile steel bar and mild steel bar on site in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 13: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/18/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 0 1 1 Bar bending machine 2Carpenter/General Worker 17 17 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 5 5 Backhoe 2Plumber 6 6 Forklift 1Machine Operator 4 4 Lorry 1

Crane 25t 0

Total 45

Site Activities

719/720 : Removal of formwork upper roof beam and stiffener in progress729/730 : Fixing of rebar of works pilecap spun piles foundation in progress731/732 : Fixing of rebar of works pilecap spun piles foundation in progress737/738 : Removal of formwork roof beam and slab water tank in progress745/746 : Installation of gully trap mechanical part in progress : Bricklayer construct fencing house in progress905/906 : Installation of formwork pilecap foudation in progress923/924 : Installation of formwork ground floor beam in progress

Barbender Yard : Cut and bend tensile steel bar and mild steel bar on site in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 14: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/17/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 0 1 1 Bar bending machine 2Carpenter/General Worker 24 24 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 5 5 Backhoe 1Tiler 5 5 Forklift 1Plumber 5 5 Lorry 2Machine Operator 4 4 Crane 25t 0

Total 52

Site Activities

729/730 : Fixing of rebar of works pilecap spun piles foundation in progress731/732 : Fixing of rebar of works pilecap spun piles foundation in progress737/738 : Removal of formwork roof beam and slab water tank in progress745/746 : Installation of gully trap mechanical part in progress : Bricklayer construct fencing house in progress905/906 : Installation of formwork pilecap foudation in progress923/924 : Installation of formwork ground floor beam in progress

Barbender Yard : Cut and bend tensile steel bar and mild steel bar on site in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 15: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/16/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 15 15 Bar cutting machine 1Barbender 11 11 Plate compactor 0Tiler 6 6 Backhoe 2Window Worker 4 4 Forklift 1Concretor 7 7 Lorry 0Plumber 6 6 Crane 25t 1Machine Operator 4 4

Total 56

Site Activities

737/738 : Removal of formwork roof beam and slab water tank in progress745/746 : Tiling of works architecture part at wall kitchen and store area in progress : Installation of casement frame window and sliding door in progress : Installation of gully trap mechanical part in progress905/906 : Installation of formwork pilecap foudation in progress923/924 : Installation of formwork ground floor beam in progress927/928 : Installation of 1st floor slab and continous beam in progress929/930 : Removal of formwork 1st floor slab and continous beam in progress

719/720 : *Concreting of works upper roof beam in progress (5m³ G25N)723/724 : *Concreting of works reinforcement concrete staircase in progress (5m³ G25N)931/932 : *Concreting of works reinforcement concrete staircase in progress (5m³ G25N)

Barbender Yard : Cut and bend tensile steel bar and mild steel bar on site in progress : Unloading BRC cut to size 1st floor slab and roof slab in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 16: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/15/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 0 0 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 23 23 Bar cutting machine 1Barbender 11 11 Plate compactor 0Tiler 6 6 Backhoe 2Window Worker 4 4 Forklift 1Electrician 2 2 Lorry 2Plumber 6 6 Crane 25t 0Machine Operator 5 5

Total 58

Site Activities

713/714 : Installation of mechanical part plumbing works prior brickwall plastering in progress 721/722 : Installation of formwork roof beam and slab water tank in progress735/736 : Installation of conduit electrical part at 1st floor slab and beam in progress : Installation of formwork 1st floor slab and continous beam in progress743/744 : Installation of conduit electrical part internal brickwall in progress745/746 : Tiling of works architecture part at kitchen and store area in progress : Installation of casement frame window and sliding door in progress : Installation of gully trap mechanical part in progress899/900 : Installation of formwork 1st floor slab and continous beam in progress925/926 : Lay BRC sheet at ground floor slab in progress927/928 : Installation of formwork 1st floor slab and continous beam in progress929/930 : Removal of formwork 1st floor slab and continous beam in progress931/932 : Installation of formwork roof beam and slab water tank in progress933/934 : Excavation of works 1.5m depth pad footing foundation in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 17: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/14/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 0 0 Piling Rig 0Supervisor 0 0 0 Bar bending machine 2Carpenter/General Worker 0 0 Bar cutting machine 1Barbender 0 0 Plate compactor 0Bricklayer 0 0 Backhoe 0Plumber 0 0 Forklift 0Machine operator 0 0 Lorry 0

Crane 25t 0

Total 0

Site Activities

Remarks : Public Holiday

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 18: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/13/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 23 23 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 5 5 Backhoe 2Tiler 6 6 Forklift 1Plumber 6 6 Lorry 2Window Worker 4 4 Crane 45t 1Concretor 7 7Machine Operator 6 6

Total 71Site Activities

715/716 : Plastering of works ground floor slab in progress721/722 : Installation of formwork roof beam and slab water tank in progress735/736 : Fixing rebar of works 1st floor slab and continous beam in progress : Installation of conduit electrical part at 1st floor slab and continous beam in progress737/738 : Removal of formwork roof beam and slab water tank in progress745/746 : Tiling of works architecture part at kitchen and store area in progress : Installation of casement frame window in progress : Installation of gully trap mechanical part in progress : Bricklayer construct fencing house in progress899/900 : Installation of formwork 1st floor slab and continous beam in progress925/926 : Spread poison anti-termite at sub-structure base in progress931/932 : Removal of formwork 1st floor slab and continous beam in progress933/934 : Excavation of works 1.5m depth pad footing foundation in progress

929/930 : *Concreting of works 1st floor slab and continous beam in progress (63m³ G25N)721/722 : *Concreting of works 1st floor column in progress (6m³ G25N)

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 19: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/12/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 24 24 Bar cutting machine 1Barbender 11 11 Plate compactor 0Plasterer 4 4 Backhoe 2Concretor 7 7 Forklift 1Tiler 6 6 Lorry 2Window Worker 4 4 Crane 25t 1Plumber 6 6Machine Operator 6 6

Total 71Site Activities

713/714 : Plastering of works ground floor slab in progress719/720 : Installation of formwork upper roof beam in progress723/724 : Installation of formwork riser r.c staircase in progress729/730 : Installation of formwork pilecap foundation in progress731/732 : Installation of formwork pilecap foundation in progress735/736 : Fixing rebar of works 1st floor slab and continous beam in progress745/746 : Tiling of works architecture part at kitchen and store area in progress : Installation of casement frame window in progress : Installation of mechanical part basin and pedestal water closet at bathroom in progress897/898 : Setting out door frame position for bonding brickworks in progress899/900 : Installation of formwork 1st floor slab and continous beam in progress927/928 : Installation of formwork 1st floor slab and continous beam in progress933/934 : Excavation of works 1.5m depth pad footing foundation in progress

737/738 : *Concreting of works roof beam and slab water tank in progress (22m³ G25N)907/908 : *Concreting of works pilecap foundation in progress (9m³ G25N)909/910 : *Concreting of works pilecap foundation in progress (9m³ G25N)

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 20: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/11/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 0 0 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 24 24 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 0 0 Backhoe 2Plasterer 4 4 Forklift 1Tiler 6 6 Lorry 2Machine Operator 5 5 Crane 25t 0

Total 52

Site Activities

713/714 : Plastering of works ground floor slab in progress719/720 : Installation of formwork upper roof beam in progress721/722 : Installation of formwork 1st floor column in progress735/736 : Installation of formwork 1st floor slab and continous beam in progress745/746 : Tiling of works architecture part at wall kitchen and terrace in progress899/900 : Installation of formwork 1st floor slab and continous beam in progress927/928 : Installation of formwork 1st floor slab and continous beam in progress929/930 : Installation of formwork bathroom drop 1st floor slab in progress931/932 : Installation of formwork riser R.C staircase in progress933/934 : Excavation of works 1.5m depth pad footing foundation in progress

Barbender Yard : Cut and bend deformed bar on site in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 21: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/10/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 0 1 1 Bar bending machine 2Carpenter/General Worker 24 24 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 7 7 Backhoe 2Tiler 6 6 Forklift 1Concretor 7 7 Lorry 2Machine Operator 6 6 Crane 25t 1

Total 63

Site Activities

719/720 : Installlation of formwork upper roof beam and stiffener in progress : Bricklayer lay brick to construct brickwork in construction of house wall in progress735/736 : Installation of formwork 1st floor slab and continous beam in progress745/746 : Tiling of works architecture part at living area in progress909/910 : Fixing rebar of works pilecap spun piles foundation in progress907/908: Fixing rebar of works pilecap spun piles foundation in progress919/920 : Backfilling soil earth at sub-structure base for well compacted in progress921/922 : Backfilling soil earth at sub-structure base for well compacted in progress927/928 : Installation of formwork 1st floor slab and continous beam in progress929/930 : Fixing rebar of works 1st floor slab and continous beam in progress931/932 : Fixing rebar of works reinforcement concrete staircase in progress

899/900 *Concreting of works ground floor column in progress (6.5m³ G25N) 931/932 : *Concreting of works 1st floor column in progress (6.5m³ G25N)911/912 : *Concreting of works pilecap spun piles foundation (10m³ G25N)913/914 : *Concreting of works pilecap spun piles foundation (10m³ G25N)

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 22: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/9/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 20 20 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 7 7 Backhoe 2Tiler 6 6 Forklift 1Machine operator 4 4 Lorry 1

Crane 25t 0

Total 51

Site Activities

719/720 : Installlation of formwork upper roof beam and stiffener in progress : Bricklayer lay brick to construct brickwork in construction of house wall in progress735/736 : Installation of formwork 1st floor slab and continous beam in progress745/746 : Tiling of works architecture part at living area in progress899/900 : Installation of formwork ground floor column in progress 909/910 : Fixing rebar of works pilecap spun piles foundation in progress927/928 : Installation of formwork 1st floor slab and continous beam in progress929/930 : Fixing rebar of works 1st floor slab and continous beam in progress931/932 : Installation of formwork 1st floor column in progress

Barbender Yard : Cut and bend deformed bar on site in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 23: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/8/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 21 21 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 7 7 Backhoe 2Tiler 6 6 Forklift 1Machine Operator 5 5 Lorry 2

Crane 25t 0

Total 53

Site Activities

719/720 : Bricklayer lay brick to construct brickwork in construction of house wall in progress723/724 : Setting out frame door position for brickwall bonding in progress733/734 : Excavation of works 1.75m depth spun piles foundation in prog735/736 : Installation of formwork 1st floor slab and continous beam in progress737/738 : Fixing rebar of works roof beam and slab water tank in progress745/746 : Tiling of works architecture part at living area in progress909/910 : Fixing rebar of works pilecap spun piles foundation in progress927/928 : Installation of formwork 1st floor slab and continous beam in progress929/930 ; Fixing rebar of works 1st floor slab and continous beam in progress

Barbender Yard : Cut and bend deformed bar on site in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 24: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/7/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 22 22 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 8 8 Backhoe 2Tiler 7 7 Forklift 1Machine Operator 4 4 Lorry 1

Crane 25t 0

Total 55

Site Activities

713/714 : Site clearing material debris on site in progress719/720 : Bricklayer lay brick to construct brickwork in construction of house wall in progress737/738 : Fixing rebar of works roof beam and slab water tank in progress745/746 : Bricklayer lay brick to construct fencing brickwall in progress : Tiling of works architecture part at living area in progress897/898 : Removal of formwork 1st floor slab and continous beam in progress899/900 : Installation of formwork ground floor column in progress911/912 : Fixing rebar of works pilecap spun piles foundation in progress927/928 : Installation of formwork 1st floor slab and continous beam in progress931/932 : Removal of formwork 1st floor slab and continous beam in progress

Barbender Yard : Cut and bend deformed bar on site in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 25: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/6/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries QtyEngineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 28 28 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 7 7 Backhoe 2Tiler 5 5 Forklift 1Concretor 7 7 Lorry 2Ceiling Worker 2 2 Crane 25t 1Machine Operator 6 6

Total 69

Site Activities

719/720 : Bricklayer lay brick to construct brickwork in construction of house wall in progress723/724 : Removal of formwork 1st floor slab and continous beam in progress : Installation of soffit formwork reinforcement concrete staircase in progress 733/734 : Cut off spun piles level in progress737/738 : Fixing rebar of works roof beam and slab water tank in progress745/746 : Bricklayer lay brick to construct fencing brickwall in progress : Installation of asbestos suspended ceiling at master bedroom area in progress : Tiling of works architecture part at living area in progress897/898 : Removal of formwork 1st floor slab and continous beam in progress899/900 : Installation of formwork ground floor column in progress911/912 : Fixing rebar of works pilecap spun piles foundation in progress913/914 : Fixing rebar of works pilecap spun piles foundation in progress927/928 : Installation of formwork 1st floor slab and continous beam in progress931/932 : Removal of formwork 1st floor slab and continous beam in progress

719/720 : *Concreting of works roof beam and slab water tank in progress (23m³ G25N)

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 26: Site Daily - October

PROCEDURE TITLE : PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/5/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 21 21 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 8 8 Backhoe 2Tiler 5 5 Forklift 1Ceiling Worker 2 2 Lorry 2Machine Operator 5 5 Crane 25t 0

Total 55

Site Activities

723/724 : Removal of formwork 1st floor slab and continous beam in progress731/732 : Excavation of works 1.75m depth spun piles foundation in progress735/736 : Installation of formwork soffit 1st floor slab and continous beam in progress739/740 : Bricklayer lay brick to construct brickwork in construction of house wall in progress745/746 : Installation asbestos suspended ceiling at ground floor in progress : Tiling of works architecture part at living area in progress897/898 : Removal of formwork 1st floor slab and continous beam in progress899/900 : Fixing rebar of works ground floor column in progress913/914 : Fixing rebar of works pilecap spun piles foundation in progress927/928 : Installation of formwork 1st floor slab and continous beam in progress931/932 : Removal of formwork 1st floor slab and continous beam in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 27: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/4/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 20 20 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 8 8 Backhoe 2Ceiling Worker 2 2 Forklift 1Machine Operator 5 5 Lorry 2

Crane 0

Total 49

Site Activities

723/724 : Removal of formwork 1st floor slab and continous beam in progress731/732 : Excavation of works 1.75m depth spun piles foundation in progress735/736 : Installation of formwork soffit 1st floor slab and continous beam in progress739/740 : Bricklayer lay brick to construct brickwork in construction of house wall in progress745/746 : Installation asbestos suspended ceiling at ground floor in progress897/898 : Removal of formwork 1st floor slab and continous beam in progress907/908 : Fixing rebar of works pilecap spun piles foundation in progress927/928 : Installation of formwork soffit 1st floor slab and continous beam in progress931/932 : Removal of formwork 1st floor slab and continous beam in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 28: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/3/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 24 24 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 7 7 Backhoe 2Tiler 4 4 Forklift 1Ceiling Worker 2 2 Lorry 1Machine Operator 4 4 Crane 25t 0

Total 55

Site Activities

721/722 : Fixing rebar of works 1st floor column in progress731/732 : Excavation of works 1.75m depth spun piles foundation in progress735/736 : Installation of formwork soffit 1st floor slab and continous beam in progress737/738 : Installation of formwork roof beam and slab water tank in progress739/740 : Removal of formwork R.C staircase tread and riser in progress741/742 : Bricklayer lay brick to construct brickwork in construction of house wall in progress745/746 : Tiling of works architecture part at living area in progress : Installation asbestos suspended ceiling at ground floor slab in progress899/900 : Fixing rebar of works ground floor column in progress927/928 : Installation of formwork soffit 1st floor slab and continous beam in progress931/932 : Fixing rebar of works 1st floor column in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 29: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/2/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 24 24 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 8 8 Backhoe 2Plumber 4 4 Forklift 1Tiler 4 4 Lorry 2Ceiling Worker 2 2 Crane 25t 1Concretor 7 7Machine Operator 6 6

Total 69Site Activities

715/716 : Installation of sanitary plumbing elbow connection upvc piping in progress723/724 : Removal of formwork 1st floor slab and continous beam in progress729/730 : Excavation of works 1.75m depth spun piles foundation in progress735/736 : Installation of formwork soffit 1st floor slab and continous beam in progress737/738 : Installation of formwork roof beam and slab water tank in progress741/742 : Bricklayer lay brick to construct brickwork in construction of house wall in progress745/746 : Tiling of works architecture part at living area in progress : Installation asbestos suspended ceiling at ground floor slab in progress925/926 : Backfilling of soil sub-structure base in progress929/930 : Fixing rebar of works 1st floor slab and continous beam in progress931/932 : Removal of formwork 1st floor slab and continous beam in progress

923/924 : *Concreting of works pad footing foundation in progress (15m³ G25N)739/740 : *Concreting of works upper roof beam in progress (7m³ G25N)927/928 : *Concreting of works ground floor column in progress (6m³ G25N)739/740 : *Concreting of works R.C staircase in progress (7m³ G25N)721/722 : *Concreting of works R.C staircase in progress (7m³ G25N)

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 30: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL. Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/1/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskilled Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 1 1 2 Bar bending machine 2Carpenter/General Worker 26 26 Bar cutting machine 1Barbender 11 11 Plate compactor 0Bricklayer 10 10 Backhoe 2Concretor 7 7 Forklift 1Plumber 5 5 Lorry 2Tiler 4 4 Crane 25t 1Machine Operator 6 6

Total 72

Site Activities

719/720 : Fixing rebar of works roof beam and slab water tank in progress : Installation of conduit electrical part at roof beam in progress723/724 : Removal of formwork 1st floor slab and continous beam in progress735/736 : Installation of formwork soffit 1st floor slab and continous beam in progress737/738 : Installation of formwork roof beam and slab water tank in progress739/740 : Fixing rebar of works upper roof beam and stiffener in progress741/742 : Bricklayer lay brick to construct brickwork in construction of house wall in progress745/746 : Tiling of works architecture part at bathroom wall ground floor slab and bathroom 1st floor slab in progress : Installation asbestos suspended ceiling at ground floor slab in progress897/898 : Installation of formwork bathroom drop 1st floor slab in progress899/900 : Marking ground floor column position in progress925/926 : Installation of sanitary plumbing mechanical part at sub-structure base in progress931/932 : Marking 1st floor slab column position in progress

897/898 : *Concreting of works 1st floor slab and continous beam in progress (45m³ G25N)923/924 : *Concreting of works pad footing foundation in progress (10m³ G25N)

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD

Page 31: Site Daily - October

PROCEDURE TITLE :PROJECT CONTROL Revision No.01DAILY SITE REPORT F/PCSB/P/PC/03/1.

Project : Proposed Housing Design Bukit Banyan Date : 10/31/2015Area / Section : Eugenia III, 72 Unit Double Storey Semi-Detached Weather : Fine

RainHours affected by rain :

Daily Workforce Summary Staff Skilled Unskille Total Plant / Machineries Qty.Engineer 1 1 Piling Rig 0Supervisor 0 1 1 Bar bending machine 2Carpenter/General Worker 20 20 Bar cutting machine 1Barbender 10 10 Plate compactor 0Bricklayer 12 12 Backhoe 2Tiler 4 4 Forklift 1Electrician Wireman 3 3 Lorry 1Machine Operator 4 4 Crane 0

Total 55

Site Activities

717/718 : Installation of telcomunication cabel electrical part in progress723/724 : Bricklayer lay and bond brick to construct brickwork at ground floor slab of housing wall in progress727/728 : Fixing of rebar works pilecap spun piles foundation in progress726/725 : Fixing of rebar works pilecap spun piles foundation in progress739/740 : Installation of telcomunication cabel electrical part in progress745/746 : Bricklayer construct fencing house in progress : Tiling of works architecture part in progress : Lanscape of works in progress899/900 : Installation of formwork 1st floor slab and continous beam in progress927/928 : Installation of conduit electrical part in progress

Barbender Yard : Cut and bend tensile steel bar and mild steel bar on site in progress

Note: Please attach additional page if required.

Prepared By

…………………………SC / PC / PE / SE / SSS / SS

PARAMOUNT CONSTRUCTION SDN BHD