Transcript of Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4...
![Page 1: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/1.jpg)
1
Sines LNG terminal
GASTECH 2005
![Page 2: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/2.jpg)
2
Location of SINES LNG RECEIVING TERMINAL (Portugal)
![Page 3: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/3.jpg)
3
Contract award
Contract awarded on 13/11/00As result of international competitionTRACTEBEL consortium selected for:
Price levelClose link to LNG operators through TBL group
![Page 4: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/4.jpg)
4
Project challenges
Tight schedule: 37 months
Integration in an existing harbour, still under development
Congested area
between public roads, railways and coal terminal
![Page 5: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/5.jpg)
5
Plant view of SINES LNG RECEIVING TERMINAL
Process areaJetty with bearthingand unloading facilities
Seawaterintake
Service area with main service building
![Page 6: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/6.jpg)
6
Sea water intake
![Page 7: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/7.jpg)
7
SINES Aerial view
![Page 8: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/8.jpg)
8
Aerial view (general facilities)
![Page 9: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/9.jpg)
9
Terminal performances
Unloading:Ship from 35 000 thru 165 000 m³Unloading rate: 10 000 m³/hr
Storage:2 tanks of 120 000 m³ net capacity
Sendout:300 000 Nm³/hr as average900 000 Nm³/hr in peak84 barg
Truck loading3000 trucks per year
![Page 10: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/10.jpg)
10
SINES Unloading
![Page 11: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/11.jpg)
11
Terminal installation overview – on plot area
Open rack vaporizers
High pressure booster pumps
Truck loadingStorage tanks
2 x 120,000 m3
Boil-off compressors & unloading blowers
Space for future Phase 2
Gas metering & trunk line station
Ship unloadingline
![Page 12: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/12.jpg)
12
Process area: compressor and pumps shelters
![Page 13: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/13.jpg)
13
SINES Storage and vaporisation
![Page 14: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/14.jpg)
14
New technologies and HSE approach
In the design
During construction
For operators
![Page 15: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/15.jpg)
15
New approaches in the design
Intensive use of electronic mailing to allow « real time » coordination betweenpartners and with fieldEDMS for document circulationFull ISO 9000 complianceDynamic simulation for earthquakecalculationElectronic 3D model
![Page 16: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/16.jpg)
16
New approaches in the design (foll’d)
Dampeners to absorb dynamic loads from waterhammer in unloading linesIntegrated control & command systemFiber optic cablesErgonomic study of the control room andoperators offices interfaces
Better communicationFaster response in case of alarm or emergencyCorrect lighting to avoid useless constrains
Wireless telephonic system
![Page 17: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/17.jpg)
17
HSE policy during construction
Spent manhours: 3 950 000 hrsNb of accident:
Without lost time: 29With lost time: 8
Nb of near-misses: 48Nb of lost days: 168Lost-time index = 2.04 (<21, Portuguese standard)Nb of safety induction training: 3730Nb of toolbox meetings: 346Nb of attendees to toolbox meetings: 10 370
![Page 18: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/18.jpg)
18
Foreseen for operation
PMSInterfaces between DCS and PMS to download information needed for preventive and condition basedmaintenancesAsset management systemWalk-inside 3D model allowing operatorto simulate the field interventions
![Page 19: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/19.jpg)
19
Approach towards EN 1473
Hazard definition and management
earthquake
![Page 20: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/20.jpg)
20
Hazard Definition and Management
Quantitive Risk AssessmentHazard : identificationConsequence ModellingProbability
Risk matrix & level of risks as per annexes K/L
Appropriate prevention & investigation
IIIIIIIII> 10-21
IIIIIIIII10-4 – 10-22
IIIIIIIIIII10-6 – 10-43
IIIIIIIIIIIII10-8 – 10-64
IIIIIIIIIIIIIII< 10-85
IIIIIIIVV
ConsequenceProbability
Not acceptableI
To be improvedII
AcceptableIII
![Page 21: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/21.jpg)
21
TGE seismic approachearthquake levels
As per EN 1473 definitionsOBE = operation basic earthquake
Plant must remain operational after earthquakeNon-essential components could be damaged provided it will not affect the plant safe operation
SSE = safe shutdown earthquakeDesign as per classificationOperation resume could require important repairsNeed to keep monitoring of important tank and process data
![Page 22: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/22.jpg)
22
Seismicity
Area in seismic area0.15 g acceleration for OBE0.5 g acceleration for SSE
Acceleration value at the ground levelNeed to develop a global approach to
guarantee integrity and stability of systems and structure but without over-design
![Page 23: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/23.jpg)
23
TGE seismic approach as per EN 1473classification
4 classes on a safety point of view:Class A: vital for safetyClass B: failure could bring an additional hazardClass C: could not collapse as collapse could affect A or B classified itemsClass D: other items for which no specific requirements
Other considerations (operating costs or capital losses): to be discussed with client
![Page 24: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/24.jpg)
24
TGE seismic approachclassification matrix table
XClass C
XClass B
XClass A
stabilityintegrityoperationCriteriaclass
![Page 25: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/25.jpg)
25
TGE seismic approachbasic principle
Plant will be shutdown after any earthquake
Operator decision or seismic detectorEquipment would trip from vibration
Plant will be fully inspected prior to resume operation:
OperabilityIntegritystability
![Page 26: Sines LNG terminal - NTNU Conferences/2005/SDS...aClose link to LNG operators through TBL group. 4 Project challenges Tight schedule: 37 months Integration in an existing harbour,](https://reader031.fdocuments.us/reader031/viewer/2022022516/5b03d22c7f8b9a41528b9398/html5/thumbnails/26.jpg)
26
Thank you for your attention