SinBerBEST Annual Meeting, 09-10, Jan, 2013,...
Transcript of SinBerBEST Annual Meeting, 09-10, Jan, 2013,...
Building Energy Saving through Life-Cycle
Optimization, Commissioning and Diagnosis
– Experiences in International Commerce
Center (ICC) of Hong Kong Shengwei Wang
Chair Professor of Building Services Engineering
Building Energy and Automation Research Laboratory, Institute of Sustainable Urban Development/Department of Building Services Engineering
The Hong Kong Polytechnic University
1
SinBerBEST Annual Meeting, 09-10, Jan, 2013, Singapore
Outline of Presentation
• Basic approaches for building energy saving
• Life-cycle diagnosis/commissioning and optimization
• Technologies and deliverables
• Research areas and expertise
• Application Case 1 – ICC
• Application Case 2 – A Hotel Building
• Recent existing Building Energy Projects
2
Basic Approaches for Energy Efficient Buildings
• Reduced heating/cooling loads
– Building envelope design, passive design, etc.
• Use of energy efficient building systems and technologies
• Optimization of system and technology integration, operation and control
– Life-cycle commissioning, design optimization, control optimization, etc.
3
Team’s Research Objectives and Applicable
Deliverables
• Life-cycle Diagnosis/Commissioning
and Optimization
4
Objectives of Diagnosis/Commissioning and Optimization
Objective of Diagnosis/Commissioning
• To ensure the operation performance of the systems delivered meet the design intent.
Objective of optimization
• To push the operation performance of the systems delivered to approach the best, often exceed the design intent.
5
Steps towards Energy Efficient Buildings
Make designs proper and correct
Optimize designs and selections
Construct/install systems correctly
Ensure systems operate as good as intent
Push systems approach the best
Design Stage
Construction Stage
Operation Stage
and T&C Stage
6
Content of Diagnosis/commissioning
• Design configuration; • Component selection and sizing; • Installation; • (Monitoring and control) instrumentation; • Test and commissioning; • Operation and control; • Maintenance, etc.
Deviations of performances of a deliverable from its design
intent come from different sources at different stages, diagnosis
and commissioning should cover different stages:
8
Design Intent vs Deliverable
Content of Optimization ___________________________________________________________________________
Optimization of HVAC&R systems
Optimization could be performed at different stages allowing the
systems to provide expected quality of services (comfort and health
environment) with reduced (minimum) energy consumption by
means of:
• Optimizing design configuration;
• Optimizing selection and sizing;
• Optimizing (monitoring/control) instrumentation;
• Optimal operation and control, etc.
9
Examples of Technologies • Building Performance Quick Evaluation and Diagnostic Tool
• Detailed Evaluation and Diagnostic Tool for A/C and BA systems
• Building System Online Performance Simulation Test Platform
• Existing Building Commissioning and Upgrading Assessment Tool
• BA Control and Diagnosis Strategy Online Test Platform
• Package of Online Optimal and Energy Efficient Control and Fault
Diagnosis Strategies
• Intelligent Building Integration and management Platform-IBmanager
11
Both new building development and Existing
Building Energy Saving are the targets.
Building Life-cycle Diagnosis, Commissioning and Optimization
- International Commerce Centre (ICC)
12
Our Roles in ICC Project
Independent Energy Consultant (Independent Commissioning Agent)
To Develop the HVAC Energy Optimal Control System
490 m
118 F
13
Virtual Building System – Dynamic simulation platform of the complex HVACR system
Chiller One
TYPE 23
Chiller Four
TYPE 23
Chiller Six
TYPE 23
Chiller Two
TYPE 23
Chiller Three
TYPE 23
Chiller Five
TYPE 23
CTA Three
TYPE 1
CTB One
TYPE 2
CTA Five
TYPE 1
CTA Two
TYPE 1
CTA Four
TYPE 1
CTB Two
TYPE 2
CTA One
TYPE 1
CTB Five
TYPE 2
CTB Four
TYPE 2
CTB Three
TYPE 2
CTA Six
TYPE 1
Cooling tower controller
TYPE 3&54&55
Mixing after chiller condensers
TYPE 4
Mixing after cooling towers
TYPE 5
Data Reader
TYPE 9
Chiller sequence controller
TYPE 50
Mixing & Bypass
TYPE 67
Return pipe
TYPE 31 Supply pipe
TYPE 31
Pump & network
TYPE 12
AHUs
TYPE 63
PID control
TYPE 42
Pump sequence
TYPE 39
HX modeling&mixingTYPE 41
HX sequence
TYPE 39
PID control
TYPE 43
Tao,i
Load & status of AHUs
TYPE 49
Pump & network
TYPE 13
AHUs
TYPE 21
PD optimizerTYPE 7
PID control
TYPE 20
Pump sequence
TYPE 39
PID control
TYPE 43
Tao,i
VPi
PDset
Pump & network
TYPE 14
PID control
TYPE 43
PID control
TYPE 43
Mixing
TYPE 48
Tw,out
HX modeling&mixing TYPE 36
HX sequence
TYPE 39
Pump & network
TYPE 17
AHUs
TYPE 63
PID control
TYPE 42
Pump sequence
TYPE 39
PID control
TYPE 43
Tao,i
Pump & network
TYPE 15
PID control
TYPE 43
PID control
TYPE 43
Mixing & bypass
TYPE 19
Tw,o
ut
Load & status of AHUs
TYPE 35
Pump & network
TYPE 18
AHUs
TYPE 63
PID control
TYPE 42
PID control
TYPE 43
Tao,i
HX modeling&mixing TYPE 37
HX sequence
TYPE 39
Pump & network
TYPE 16
PID control
TYPE 43
PID control
TYPE 43Mixing & bypass
TYPE 45
PD optimizerTYPE 6
VPi
PDset
PD optimizerTYPE 8
Pump sequence
TYPE 39
PDset
PD optimizerTYPE 62
PDset
Mixing
TYPE 47
Mixing
TYPE 47
Tw,su
p
Mw,i
On/
Off
of
AH
Us
Mw
& P
Dm
eas
Npu
Freq
On/
Off
of
AH
Us
Mw,i
Mw
& P
Dm
eas
Freq
Npu
Nhx
Tw,su
p
Tw,in &Mw
Tw,su
p
Mw,set
Mw,measFreq
Mw,i
VPi
Npu
Freq
VPi
Mw,i
Freq
Npu
Mw
& P
Dm
eas
Nhx
Mw
Tw,sup&MwMw,set
Mw,measFreqNhx
Load
Nhx
Nhx
Tw,su
p
Tw,out
Ma,
i&Ta
,inMa,i&Ta,in
Ma,i&Ta,in
On/Off of AHUs
On/Off of AHUsOn/Off of AHUs
Mw & Tw,rtn Mw & Tw,rtn
On/Off of AHUs Ma,i&Ta,in
On/
Off
of
AH
Us
On/Off of AHUs
Load
Tw,su
pTw
,rtn
& M
w
Tw,rtn & Mw
Tw,in
Mw
& T
w,in
Tw,sup & MwMw & Tw,rtn
Nhx
Mw
Mw
,&w
,in
Tw,rt
n&
Mw
Mw,measFreq
Mw,set
Mw
Nch On/Off On/Off On/Off On/Off On/Off On/Off
Tw,ch,out Tw,ch,out Tw,ch,out Tw,ch,out Tw,ch,out Tw,ch,out
Tsup
Tsup
Mw
,tot&
Trt
n
Nch Tw,cd,out Tw,cd,out Tw,cd,out Tw,cd,out Tw,cd,out Tw,cd,out
Tw,cd,in
Mw,tot&Tw,ct,inTw,cd,outOn/Off,i&Freq,i
Zone 2
Zone 1Zone 3&4
NumberN:
Valve positionVP:
Pressure differentialPD:
FrequencyFreq:
Cooling loadLoad:
Water or air flow rateM:
TemperatureT:
Component type numberTYPE XX:
NumberN:
Valve positionVP:
Pressure differentialPD:
FrequencyFreq:
Cooling loadLoad:
Water or air flow rateM:
TemperatureT:
Component type numberTYPE XX:
Supplysup:Heat exchangerhx:
wb:
ct:
cd:
rtn:
in:
ao:
meas:
w:
Subscript
Wet-bulb
Cooling tower
Condenser
Return
Inlet
Air outlet
Measurement
Water
Set-pointset:
Chillerch:
Dry-bulbdb:
Outletout:
Pumppu:
Totaltot:
Individuali:
Aira:
Supplysup:Heat exchangerhx:
wb:
ct:
cd:
rtn:
in:
ao:
meas:
w:
Subscript
Wet-bulb
Cooling tower
Condenser
Return
Inlet
Air outlet
Measurement
Water
Set-pointset:
Chillerch:
Dry-bulbdb:
Outletout:
Pumppu:
Totaltot:
Individuali:
Aira:
Tw,out & Mw Tw,out & Mw Tw,out & Mw Tw,out & MwTw,out & MwTw,out & MwTw,out & Mw Tw,out & MwTw,out & Mw Tw,out & Mw
Mw,tot&Tw,ct,out
Pump sequence
TYPE 39NpuMw
Pump sequence
TYPE 39
Npu
Mw
Mixing
TYPE 60
Tw,rtn & Mw,tot
Twb&
Tdb
Tw,out,i
Mixing
TYPE 61
Mw,tot & Tw,rtn
Zone airflow rates
Zone 1
Zone 2 Zones 3&4
Virtual Building
System Simulated
BA & Strategies
(updated throughout the entire
process)
• Verifying/improving the system configuration and component selection including the chiller system, water system (primary/secondary system), heat rejection system (cooling towers), fresh air system etc.
• Verifying and improving the metering system for proper local control, and the original proposed control logics at the design stage.
• Proposal of additional metering system for implementing supervisory control and diagnosis strategies and related facilities for implementing these strategies
Commissioning at Design Stage
Design commissioning mainly concerns the future
operation and control performance of HVAC systems,
including:
HX-42 HX-42 HX-42 HX-42 HX-42 HX-42 HX-42
(S-B
)
FROM OFFICE FLOORS (43-77)
TO OFFICE FLOORS (43-77)
(S-B
)
HX-78HX-78HX-78
TO OFFICE FLOORSS (79-98)
FROM OFFICE FLOORS (79-98)
(S-B
)(S
-B)
SCHWP-42-01 to 03SCHWP-42-04 to 06
SCHWP-78-01 to 03
SCHWP-06-06 to 09
To Z
on
e 3&
4
Fro
m Z
on
e 3&
4
Flow meter
Bypass valve
EVAPORATOR EVAPORATOR EVAPORATOR EVAPORATOREVAPORATOREVAPORAROR
WCC-06a-01
(2040 Ton)
PCHWP-06-01
FROM OFFICCE FLOORS(7-41)
TO OFFICE FLOORS(7-41)
HX-42
PCHWP-06-02 PCHWP-06-03 PCHWP-06-04 PCHWP-06-05 PCHWP-06-06
WCC-06a-02
(2040 Ton)
WCC-06a-04
(2040 Ton)WCC-06a-03
(2040 Ton)
WCC-06a-05
(2040 Ton)WCC-06a-06
(2040 Ton)
CDWP-06-01 CDWP-06-02 CDWP-06-04CDWP-06-03 CDWP-06-05 CDWP-06-06
A
F
D
CA
B
E
B
D
C
E
F
Secondary water circuit for Zone 1
Secondary water circuit for Zone 2
Secondary water circuit for Zone
3 and Zone 4
Primary water circuit
Chiller circuit
Cooling water circuit
(S-B
)
FROM PODIUM & BASEMENT
TO PODIUM & BASEMENT
HX-06
(S-B
)(S
-B)
(S-B
)
FROM OFFICE FLOORS (43-77)
TO OFFICE FLOORS (43-77)
(S-B
)
CONDENSER CONDENSER CONDENSER CONDENSER CONDENSER CONDENSER
HX-78HX-78HX-78
TO OFFICE FLOORSS (79-98)
FROM OFFICE FLOORS (79-98)
(S-B
)(S
-B)
SCHWP-42-01 to 03SCHWP-42-04 to 06
SCHWP-78-01 to 03
PCHWP-78-03PCHWP-78-01 PCHWP-78-02
PCHWP-42-01 PCHWP-42-02 PCHWP-42-03 PCHWP-42-04 PCHWP-42-05 PCHWP-42-06 PCHWP-42-07
SCHWP-06-06 to 09
SCHWP-06-03 to 05
SCHWP-06-01 to 02
SCHWP-06-10 to 12
To cooling towersFrom cooling towers
HX-42 HX-42 HX-42 HX-42 HX-42 HX-42
HX-06
Original System Revised System
System Design Verification and Optimization Secondary water loop systems of 3rd/4th zones
Primary pumps are omitted
Comparison between Two systems
0
200
400
600
800
1000
1200
1400
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (h )
Pu
mp
pow
er (
kW)
Original design
Alternative design
Typical sunny-summer day
Annual Pump Energy Saving is 1M kWh/水泵年节能量为1百万kWh
Optimal control strategies for central air-conditioning systems
Chiller sequence, optimal start
Optimal chiller sequence - based on a more accurate cooling load
prediction using data fusion method, and considering demand
limiting
Adaptive online strategy for optimal start - based on simplified sub-
system dynamic models
Ventilation strategy for multi-zone air-conditioning system
Optimal ventilation control strategy - based on ventilation needs of
individual zones and the energy benefits of fresh air intake
Peak demand limiting and overall electricity cost
management
19
Chilled water system optimization
Optimal pressure differential set point reset strategy
Optimal pump sequence logic
Optimal heat exchanger sequence logic
Optimal control strategy for pumps in the cold water side of heat
exchangers
Optimal chilled water supply temperature set-point reset strategy
Cooling water system optimization
Optimal condenser inlet water temperature set point reset strategy
Optimal cooling tower sequence
Optimal control strategies for central air-conditioning systems
20
From cooling source
HX
HX
Temperature controller
Differential pressure controller
Temperature
set-pointPressure
differential set-point
To coolingsource
Secondary side of HX Primary side of HX
Temperature controller
Temperature
set-point
MM
ΔP
TT
TT
To terminal
units
From terminal units
Modulating
valves
MM
HX
HX
TT TM
Temperature controller
Water flowcontroller
Temperature
set-point
Water flow
set-point
To terminal
units
From terminal units
Secondary side of HX Primary side of HX
TM
From cooling source
To coolingsource
Original implemented strategy – differential pressure control and by resorting to the modulating valve
Revised strategy – cascade controller without using any modulating valve
Optimal Control of Variable Speed Pumps
Speed control of pumps distributing water to heat exchangers
21
Site practically tests show that the proposed strategy can provide stable and reliable control. Compared to original implemented strategy, about 22.0% savings for pumps before heat exchangers in Zone 1 was achieved.
Energy consumption (kWh)
Pumps Number
(standby) Original
strategy
(kWh)
Alternative
Strategy
(kWh)
Saving
(kWh)
Primary pumps in Zone 1 1(1) 528,008 456,132 71,876
Primary pumps for Zones 3&4 3(1) 921,235 795,830 125,405
Primary pumps in Zone 4 2(1) 401,008 346,420 54,588
Total saving of the primary pumps 251,869
Energy saving of primary pumps before
heat exchanges due to the use of
PolyU strategy is about 250,000 kWh.
Performance test and evaluation
Due to the low load of Zone 1 in ICC at current stage, a simulation test of annual energy savings by using PolyU strategy is performed
22
At first-level warning, increase airflow rate by 20% when
plume potential is marginal
At second-level warning, increase airflow by 40% when
plume potential is high
Start heating using heat pumps when visual plume is
observed
Decision
maker
Platform for predicting
plume occurring possibility
Normal operation when there is no predicted plume
occurs
Operating Condition Power Consumption
Cooling
Water
Temp Set-
point
Cooling
Tower
Number
Cooling
Tower
Freq
Chiller
Power
Cooling
Tower
Power
Total
Power Difference
Operation modes
°C - Hz kW kW kW kW %
Reference 22.7 3 26.51 856.2 59.1 915.35 -- --
First-level warning 21.3 3 30.74 836.2 93.0 929.2 14.0 1.5
Second-level warming 20.1 3 35.52 819.9 145.9 965.8 50.6 5.5
Using heat pumps 22.7 3CT+1HP 26.51 856.2 59.1 1215.2 300 32.8
Visible Plume Abatement
Additional energy consumption for plume control could
be reduced from 32.8% to 5.5% or 1.5% at low Load
25
Cooling Load Measurement based on Data-Fusion
Cooling load measurement
Direct measurement of building cooling load
Qdm = cpwρwMw(Tw,rtn-Tw,sup)
cpw is the water specific thermal capacity; ρw is the water density;
Mw is water flow rate; Tw,rtn,Tw,sup are chilled water return/supply
temp.
Indirect measurement of building cooling load
Qim = f(Pcom,Tcd,Tev)
Pcom is chiller power consumption; Tcd,Tev are chiller
condensing/evaporating temperatures
27
Robust building cooling load measurement technique Based on Data Fusion
Data fusion to merge “Direct measurement” and “Indirect
measurement” improving the accuracy and reliability of building
cooling load measurement
Chiller 1 Chiller n
Central Chilling Plant
Chiller
Model 1
Direct Load
measurement
Data Fusion
Engine
+
Wch,n,Tev,n,Tcd,n
Tsup Mw
Trtn
Qdm
Qin,1 Qin,n
Qload (Fused cooling load)
rload (Degree of confidence)
…
Advanced soft
measurement system
Chiller
Model n
Wch,1,Tev,1,Tcd,1
28
High degree of confidence => Accurate and relatively aggressive control
Low degree of confidence => Safe control and warning
for maintenance check
Medium degree of confidence => Less aggressive and
safer control
Robust Chiller Sequencing Control Based on Enhanced
Cooling Load Measurement Technique
29
Summary of Energy Benefits
• 1,000,000 kWh energy consumption is saved due to the modification on the secondary water loops of Zone 3 & 4
• 2,360,000 kWh , (about 5.1% of annual energy consumption of chillers and cooling towers) of the cooling system can be saving due to the change from single speed to variable speed using VFD
• 607,000 kWh , (about 2.8% of annual energy consumption of chillers and cooling towers) of the cooling system will be wasted
when the lowest frequency is limited at 37 Hz
• 3, 500,000 kWh (about 7%) of the total energy consumption of HVAC system) can be saved using PolyU control strategies based on the original design
Saving by Control Optimization – compared with the
case when the HVAC system operates correctly as the
original design intent. 3.5M per year
Saving by Commissioning (Improving the system configuration and selection) – compared with the
original design. About 3.5 M per year
The annual total energy
saving is about 7.0M kWh !
30
Contributions in supporting ICC building in getting
HK-BEAM Platinum Certificate
Annual Energy Use Reduction By 14.6% to get extra 2 credits
Peak Demand Reduction By 26.9% to get extra 2 credits
Optimal Control Strategies “Innovation” for extra 1 credits
Grade Overall
Performance
Platinum 75% Excellent
Gold 65% Very Good
Silver 55% Good
Bronze 40% Above average
The overall assessment grade is based
on the percentage of applicable credits
(about 145) gained in 5 categories: site
aspects , material aspects , energy
use,water use , and IAQ (vision 4/04 ).
Gold
72.7%)
5 credits (3.5%)
Platinum
76.2%)
H V
A C
A New Hotel Development in Sheung Wan
(Holiday Inn Express)
Independent Energy Consultant (Independent Commissioning Agent)
To Develop the HVAC Energy Optimal Control System
33
Summary of Energy Benefits
Saving by Commissioning (Improving the system configuration and
selection) and Control Optimization – compared with the case
when the HVAC system operates correctly as the
original design intent. 20% saved annually