Siemens Wind Power 29-09-2011

12
1 Siemens Wind Power Primavera From 0 – 1835 licenses in 3 years © Siemens AG 2011. All rights reserved. One of the world’s leading suppliers of wind power solutions Siemens Wind Power Facts! Siemens Wind Power facts Installed Base: > 9,600 turbines with > 13,400 MW capacity 1) Installed: 2,300 MW in 2010 7,800 employees globally Record order backlog of 11 billion © Siemens AG 2011. All rights reserved. Page 2 Record order backlog of ~ 11 billion Revenue in 2010: ~ € 3,2 billion 1) June 2011 No. 1 in offshore wind power

Transcript of Siemens Wind Power 29-09-2011

Page 1: Siemens Wind Power 29-09-2011

1

Siemens Wind Power

Primavera

From 0 – 1835 licenses in 3 years

© Siemens AG 2011. All rights reserved.© Siemens AG 2011. All rights reserved.

One of the world’s leading suppliers of wind power solutions

Siemens Wind Power Facts!

Siemens Wind Power facts

Installed Base: > 9,600 turbines with > 13,400 MW capacity1)

Installed: 2,300 MW in 2010

7,800 employees globally

Record order backlog of € 11 billion

© Siemens AG 2011. All rights reserved.Page 2

Record order backlog of ~ € 11 billion

Revenue in 2010: ~ € 3,2 billion

1) June 2011

No. 1 in offshore wind power

Page 2: Siemens Wind Power 29-09-2011

2

Primavera@Wind

Implementation of Primavera in Siemens Wind Power

Th i ht j t d th i ht t th i ht ti !The right project and the right resources at the right time!

Primavera users

1200

1400

1600

1800

2000

© Siemens AG 2011. All rights reserved.Page 3

0

200

400

600

800

1000

2008 2009 2010 2011

Primavera users

Starting point – Winter 2007/2008

• Management in Wind Farm installation area have an issue:• The number of wind Farm

installation projects is growing and the complexity is increasing

• A tool is needed to get overview of:• Schedule• Resources • Cost

© Siemens AG 2011. All rights reserved.Page 4

• Our CEO Knew Primavera so that was chosen:• 60 licenses were bought• WestSoft was engaged to

implement

• Ready to Go-Live in autumn 2008!

Page 3: Siemens Wind Power 29-09-2011

3

Step 2 – What about the rest?

PM area goes to IT to get IT infrastructure in place…..

At the same time the engineering department realize they also need a projectAt the same time the engineering department realize they also need a project- , task and ressource management tool, and approach IT

It gets political!

© Siemens AG 2011. All rights reserved.Page 5

Business case – Easy ☺

It is essential for both Engineering and Siemens Wind Power as such to be able to effectively control all tasks projects project portfolios and resources into effectively control all tasks, projects, project portfolios and resources in Engineering

The current and future growth presents a challenge in continued efficiency per employee. The efficiency improvement is estimated to be at least 5%, which results in a ROI as defined below:

Engineering salary budget FY09 xxxC t P M th

© Siemens AG 2011. All rights reserved.Page 6

Cost Pr Month xxxIncrease of effectiveness(%) 5Saved due to higher effectiveness (month) +500 Mio DKR pr. Month

Page 4: Siemens Wind Power 29-09-2011

4

Choose tool: Not that easy

The IT department wants to ensure the right tool is selected. An investigation project is started to investigate SAP/PS MSP and PrimaveraAn investigation project is started to investigate SAP/PS, MSP and Primavera.

During the investogatin one more department joined the team: Global Blades

Now comes a period of workshops, Product presentations, discussions etc.

MSP was quickly ruled out

26 f i ti ti t t d

© Siemens AG 2011. All rights reserved.Page 7

26 pages of investigation report was created

8 month later the conclusion!

Primavera is the preferred platform!

Critical requirements:

Support increased day-to-day project management

Provide standard project execution structure for planning & monitoring in Projects & Logistics for all regions

Enable capacity planning and resource forecasting for equipment/manpower/components across projects

© Siemens AG 2011. All rights reserved.Page 8

Support long-term planning of cross-project uncertainties through ‘what-if’ scenarios (Not Possible in SAP/PS)

Page 5: Siemens Wind Power 29-09-2011

5

Project

The project was approved in may 2009

Primavera specialist was hiredWestsoft was involved

Get Going!

© Siemens AG 2011. All rights reserved.Page 9

Scope

Engineering: • Manpower ressource Management for R&D Projectsp g j• Task Management in the departments• Project Management tool for +50 PM’s• Time Registration for 600 engineers• Overall project schedule for R&D projects using templates• Portfolio Overview

Global blades• Portfolio Overview for internal projects

© Siemens AG 2011. All rights reserved.Page 10

• Time Registrati0n on project activities for 120 employees• PM tool for +15 PM’s

Projects & Logistics• Project Scheduling tool• Critical ressource Management (vessels, cranes….)

Page 6: Siemens Wind Power 29-09-2011

6

Scope of work

To create templates for all departments and project types

Definition of Roles and Responsibilities

IT Infrastructure

© Siemens AG 2011. All rights reserved.Page 11

Internationalization - Siemens facilities and offices

International Scope

Shanghai (blades/ nacelle / hub/ under

construction)

Singapore

Beijing

CairoOrlando

Mexico City

Hutchinson (nacelle)

Boulder (Wind & aerodynamics)

Aachen (DE) (mechanics, generators grid, offshore)

Aalborg (blades prod. & R&D blade design, planned for Quantum Blade and testing)

Houston

India (planned)

MadridFt. Madison (Blades)

Keele (UK) Sheffield (UK) Den Haag (NL)

© Siemens AG 2011. All rights reserved.Page 12

MelbourneSantiago

Sao Paolo

Taastrup (Aerodynamics, structural dynamics, electrical systems)

Hamburg (Europe HQ)Bremen

Brande (Global HQ)

Ølgod (hubs)

Engesvang (blades)

Supply chain Sales hubs Other sales R&D

(planned)

Page 7: Siemens Wind Power 29-09-2011

7

Timeline

Projects & Logistics area were approved to continue may 2009 and got the infrastructure up and runninginfrastructure up and running.

Important milestones:April 1st 2010 all Wind Farm installation projects are included!October 1st. all projects are updated with progress

Engineering and Global Blades: G li il 2010

© Siemens AG 2011. All rights reserved.Page 13

Go-live: april 2010

Challenges!

© Siemens AG 2011. All rights reserved.

Page 8: Siemens Wind Power 29-09-2011

8

Growth!

While we were trying to improve the way we work, the company still grows

Employees (by end of fiscal year)

When Primavera started we were 3300 emplyees. Now: +7500

More people are hired than we can manage to get trained.

After 3 years, we still have many new and unexperienced users !!!

We still Grow!

© Siemens AG 2011. All rights reserved.Page 15

Average growth (05-10): 42% p.a.

504,200

2,800

FY2009

5,500

3,800

1,700

FY2008

5,300

3,900

1,400

FY2007

3,300

2,500

800

FY2006

2,200

1,800400

FY2005

1,2001,150

FY2010

7,000

DenmarkGlobal

Resistance

ManagementWhat do we need that for? Just give me a spreadsheet!What do we need that for? Just give me a spreadsheet!

EmployeesPrimavera is awfull!Double time registrationsPlanning: I do not need that!

Customers

© Siemens AG 2011. All rights reserved.Page 16

Using other systems!

Page 9: Siemens Wind Power 29-09-2011

9

Primavera Support

We underestimated the requirements for supporting staff

Primavera users

2000pp g

We did not manage to get enough people on board in time!

Problems: TrainingTemplatesTechnical isues

0

200

400

600

800

1000

1200

1400

1600

1800

2008 2009 2010 2011

Primavera users

S t

© Siemens AG 2011. All rights reserved.Page 17

Technical isues

We still miss skilled staff

Support

0

2

4

6

8

10

12

14

2008 2009 2010 2011

Support

IT infrastructure

We were first movers on a large number of users on the web interface. Needed some rework and specialist involvementsome rework and specialist involvement.

Performance decreases with the increased number of users. Continued development by IT is required

© Siemens AG 2011. All rights reserved.Page 18

Page 10: Siemens Wind Power 29-09-2011

10

Wrong assumption

Planning and scheduling: PM’s must do that!

No!

Americas knew that and hired planners.

Now we are hiring planners in the rest of the world

© Siemens AG 2011. All rights reserved.Page 19

Other experiences

Keeping projects updated with progress is not to be underestimated! Monitoring and follow up is criticaland follow up is critical

Roles and Responsibilities must be clearly defined

It must be easy to use a tool, or it will not be used

Documentaion is critical!

Y t l t d l t t ff lf i ti

© Siemens AG 2011. All rights reserved.Page 20

You must plan to develop your support staff yourself, so prepare in time

Page 11: Siemens Wind Power 29-09-2011

11

Why did we succeed?

Stubbornness and dedicationStubbornness and dedication

Good people!

Support from WestSoft

Urgent needs for support to headcount planning process during financial crisis!

© Siemens AG 2011. All rights reserved.Page 21

Todays status

1835 users totally spread across all of our organisation

Primavera is widely accepted and Management have realized the potential

Increased demands from the market require more and better project- and portfolio Management

Ongoing changes to the organisation forces continued ”selling”

© Siemens AG 2011. All rights reserved.Page 22

It was the right thing to do!

Page 12: Siemens Wind Power 29-09-2011

12

Thank you !

Lene Golriz

Siemens Wind Power – Offshore

+45-30375571