Shrinkage Forum 04 June 2013
-
Upload
giacomo-allen -
Category
Documents
-
view
35 -
download
0
description
Transcript of Shrinkage Forum 04 June 2013
Shrinkage Forum 04 June 2013
Roy Malin
2
Best Practice - Areas of Inconsistency
Area Background Action
Definition of All-PE systems
Used to identify networks that are to be classified as ‘All-PE’; the primary use for this is for excluding these networks to report an average system pressure in mixed material networks.
It was agreed that an All-PE network should be defined as a network that contains >95% PE pipe by length. To be updated with next version of leakage model.
MEG Sampling The sampling frequency of MEG concentrations varied between DNs. NGGD and NGN samples monthly, SGN quarterly and WWU do not use MEG.
There are no specific guidelines recommending MEG sampling frequency. No change to current practice.
Customers on NONET Networks
Some DNs allocate un-noded meter points to their NONET Networks, whilst others do not.
It was agreed that the DNs would review the numbers of such customers to determine significance.
Mains Data Extraction Date
NGGD take an extract of mains data on 1 April each year. The other DNs take a later extract, allowing time for the systems to be updated with work completed during the previous year.
It is considered that the leakage extract should reflect the actual mains position at the end of the year. NGGD will adopt an approach consistent with this.
Calorific Value Each element of leakage is estimated in cubic metres of natural gas and it is necessary to convert this into energy. NGGD uses CV data published by National Grid Gas Transmission, whereas the other DNs use data provided by their gas quality team
NGGD will look at adopting a similar approach to the other DNs.
3
Licence Obligations – Shrinkage and Leakage Model
DNs have a Licence obligation to maintain a Shrinkage and
Leakage Model
The inclusion of Shrinkage is a new addition for the RIIO price
control period
Need to expand current model to include Theft of Gas (ToG) and
Own Use Gas (OUG)
Propose that the current ToG and OUG processes are adopted
into the Shrinkage and Leakage Model
Propose that this be done alongside the proposed Low Pressure
Service Model changes
4
Low Pressure Service Model Modification
In February 2012, National Grid published a consultation on a proposed revision to
the Leakage Model in respect of the calculation of leakage from low pressure
services
For leakage estimation purposes, services are split into four categories: Steel
Service to Metallic Main, PE Service to Metallic Main, Steel Service to PE Main and
PE service to PE main.
2002/03 National Leakage Tests established that only service connections to
metallic mains leak
Establish a new ‘baseline’ estimate of the number of services in each of the
categories (using mains replacement data)
Update model to capture the impact on leakage of service transfers (model
previously updated to capture the impact of service relays)
5
Impact of LP Service Model Change
Impact is consistent with that already published for 2013/14 Initial Shrinkage Proposals
Establish a new ‘baseline’ estimate of the number of services
The RIIO Shrinkage and Leakage Baselines based on v1.3 Model
Impact determined by comparing the 2010/11 v1.3 Model output with that from the revised
model for the same year
Impact will be the same for each year of the RIIO Price Control Period
Inclusion of Service Transfers
Average no transfers/km x anticipated mains replacement length x leakage rate
Impact will be cumulative from 2011/12 and over the RIIO Period
Change has no significant impact on incentives for DNs:
Re-baseline to 2010/11 - Baselines and Actual quantities will adjust by the same amount
Service Transfers – Baseline will be adjusted by an amount based on average transfer workload,
whereas Actual quantity will be based actual transfer workload
6
Impact of Model Change – Re-baseline 2010/11
2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21
EA EoE -12.0 -12.0 -12.0 -12.0 -12.0 -12.0 -12.0 -12.0
EM EoE -24.4 -24.4 -24.4 -24.4 -24.4 -24.4 -24.4 -24.4
NT LN -31.4 -31.4 -31.4 -31.4 -31.4 -31.4 -31.4 -31.4
NW NW -17.3 -17.3 -17.3 -17.3 -17.3 -17.3 -17.3 -17.3
WM WM -3.6 -3.6 -3.6 -3.6 -3.6 -3.6 -3.6 -3.6
NE NGN 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4
NO NGN -3.5 -3.5 -3.5 -3.5 -3.5 -3.5 -3.5 -3.5
SC SC
To Follow
SE SO
SO SO
SW WWU -3.0 -3.0 -3.0 -3.0 -3.0 -3.0 -3.0 -3.0
WN WWU -1.7 -1.7 -1.7 -1.7 -1.7 -1.7 -1.7 -1.7
WS WWU -3.2 -3.2 -3.2 -3.2 -3.2 -3.2 -3.2 -3.2
7
Impact of Model Change – Service Transfers
2011/12 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21
EA EoE -0.3 -0.9 -1.2 -1.5 -1.8 -2.1 -2.4 -2.7 -3.0
EM EoE -0.4 -1.2 -1.6 -2.0 -2.4 -2.8 -3.2 -3.6 -4.0
NT LN -0.2 -0.6 -0.8 -1.0 -1.2 -1.4 -1.6 -1.8 -2.0
NW NW -0.4 -1.2 -1.6 -2.0 -2.4 -2.8 -3.2 -3.6 -4.0
WM WM -0.3 -0.9 -1.2 -1.5 -1.8 -2.1 -2.4 -2.7 -3.0
NE NGN -0.3 -0.9 -1.2 -1.5 -1.8 -2.1 -2.4 -2.7 -3.0
NO NGN -0.2 -0.6 -0.8 -1.0 -1.2 -1.4 -1.6 -1.8 -2.0
SC SC
To Follow
SE SO
SO SO
SW WWU -0.2 -0.7 -0.9 -1.2 -1.4 -1.6 -1.8 -2.1 -2.3
WN WWU 0.0 -0.1 -0.2 -0.2 -0.3 -0.3 -0.4 -0.4 -0.4
WS WWU -0.1 -0.4 -0.6 -0.7 -0.8 -1.0 -1.1 -1.2 -1.4
8
Impact of Model Change – Combined (GWh)
2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21
EoE -37 -39 -39 -40 -41 -41 -42 -43
LN -32 -32 -32 -32 -33 -33 -33 -33
NW -18 -19 -19 -19 -20 -20 -21 -21
WM -4 -5 -5 -5 -5 -6 -6 -6
NGN -3 -4 -4 -5 -5 -6 -6 -7
SC
SO
WWU -8 -9 -10 -10 -10 -11 -11 -12
9
AGI Venting - Current Model
Current Methodology
‘Fixed’ values based on a 1994 Watt Committee report
National estimate
Derivation unknown
National value apportioned across LDZs at time of Network Sale
Approximately 5% of over all emissions
10
AGI Venting - Background
Two routinely venting components
Positioners
Controllers
Venting occurs both in steady state and during control actions
Each AGI usually has a number of Positioners and Controllers
Positioners and Controllers originally designed to work with
compressed air but modified to work with gas, as readily available
on site.
11
AGI Venting - Proposal
Proposed Methodology
‘Activity’ based estimation
Based on number of Positioners and Controllers
Estimate of Steady-state Venting
Manufacturers Data
Estimate of Operational Venting
12
AGI Venting – IFI Project
Key deliverables
Verify Manufacturers Data
Establish relationship between venting rate and control system
operating pressure for steady-state venting
Identify levels of venting in operation
Investigate the potential to relate operational venting to
telemetered flow and pressure data
The viability of this will be assessed when data is available
13
AGI Venting – Verification Manufacturers Data
Bristol Babcock Controller
0.05cfm @ 20 PSI
Verified by lab tests
Linear relationship between
control pressure and venting
Fisher Positioner
0.3cfm @ 100 PSI
Verified by lab tests
Linear relationship between
control pressure and venting
14
AGI Venting – Next Steps
End of July – Complete IFI Work
August – Complete inventory of existing equipment
September – Issue Consultation on AGI Venting
October – Report on Consultation issued to Ofgem
December – Ofgem decision (in time for 2014/15
Shrinkage Proposals)