Show and tell

1
BIM BIM BIM BIM BIM BIM BIM BIM RICS PROPERTY JOURNAL 14 MAY/JUNE 2014 UPFRONT RICS HQ BIM Les Pickford is a freelance editor and journalist [email protected] Continuing his series following the RICS BIM project at Parliament Square, Les Pickford looks at a software vendor showcase that compared how different software packages extracted quantities from the RICS model Show and tell B uilding information modelling (BIM) will mean a change of approach and new challenges for construction professionals, says James Fiske, RICS Director of Delivery and Operations. “For example, taking quantities directly from a model means that its quality is critical, particularly component naming and coding.” To understand this area more, RICS held a software vendor showcase that challenged four suppliers to use the BIM model in place at its headquarters and to extract quantities typically required for early-stage construction estimates, e.g. gross internal floor area (GIFA) and elemental unit quantities. RICS wanted to understand: b how easily software could take off quantities b the challenges faced and the assumptions made b vendor results compared to RICS-supplied ‘tape measure’ figures b the consistency of results between the vendors b how much checking of outputs was required b considerations for BIM of existing buildings. The main finding was the wide variances in extracted quantities between vendors (see Figure 1). Using GIFA and a newbuild cost of £4,000/m 2 , the difference in cost estimates was £5m. The original brief for the laser scan was to provide walk-throughs for events, and it was only later that other uses were considered. That made the model a tough test for tools aimed primarily at newbuild projects. “I think this was mainly due to an incomplete model, because surveyors could not scan all areas during office hours, for example the restaurant,” suggests Paul Burrows, a Solutions Architect at BCIS. “All vendors were given full computer-aided design [CAD] floor plans and copies of the building’s original 1898 drawings, but only one used this. Its floor area calculation was within 50m 2 of ours.” Burrows summarises the other findings as: b models for existing buildings will rely much more on human skill and interpretation, and assumptions about what the model ‘means’ b cost planning objects NRM1: Order of cost estimating and cost planning for capital building works are not included as standard in Revit (which created the model) and so modellers did not classify against this list. This has implications when construction professionals later procure building works (NRM2) and manage facilities (NRM3) b two vendors revisited the original 3D model because they did not trust Industry Foundation Classes (IFC) outputs. This was not a criticism of IFC, more that applications do not output IFC consistently. “The showcase provided useful pointers for developing our model, including quality standards and valid or invalid assumptions to make,” says Burrows. His advice for others considering BIM is: b models for existing buildings (using scanned laser surveys) will be very different from a newbuild model because they lack structural detail b do your own evaluation using your most experienced estimators against two models (new and existing buildings) b ask how the software supports your professional judgment in your normal tasks. Is it easy to navigate and spot problems? Can you make corrections and apply your assumptions? b understand different vendor approaches, e.g. overseas design and procurement practice can be very different from the UK (involving architects, quantity surveyors and contractors). “The importance of a quantity surveyor’s professional judgment is highlighted when making sense of a model,” says Burrows, “especially one for an existing building that was created by scanning and importing the data.” b For more details of the Showcase, visit www.rics.org/bim Related competencies include: Data management Figure 1 The variances in element unit quantities between vendors -60% -40% -20% 0% 20% 40% 60% RICS result Vendor results Key Floor finishes Ceiling finishes Fittings, furnishings and equipment Substructure Frame Upper floors Roof Stairs and ramps External walls Windows and external doors Internal doors Wall finishes Internal walls and partitions Services

description

Continuing his series following the RICS BIM project at Parliament Square, Les Pickford looks at a software vendor showcase that compared how different software packages extracted quantities from the RICS model

Transcript of Show and tell

BIMBIMBIMBIMBIMBIMBIMBIM

RICS PROPERTY

JOURNAL

1 4 M A Y/J U N E 2 0 1 4

UPFRONTRICS HQ BIM

Les Pickford is a freelance editor and [email protected]

Continuing his series following the RICS BIM project at Parliament Square,

Les Pickford looks at a software vendor showcase that compared how

different software packages extracted quantities from the RICS model

Show and tell

Building information

modelling (BIM)

will mean a change

of approach and

new challenges

for construction

professionals, says

James Fiske, RICS Director of Delivery

and Operations. “For example, taking

quantities directly from a model means

that its quality is critical, particularly

component naming and coding.”

To understand this area more, RICS

held a software vendor showcase that

challenged four suppliers to use the BIM

model in place at its headquarters and

to extract quantities typically required

for early-stage construction estimates,

e.g. gross internal floor area (GIFA) and

elemental unit quantities. RICS wanted

to understand:

b how easily software could take

oW quantities

b the challenges faced and the

assumptions made

b vendor results compared to

RICS-supplied ‘tape measure’ figures

b the consistency of results between

the vendors

b how much checking of outputs

was required

b considerations for BIM of

existing buildings.

The main finding was the wide variances

in extracted quantities between vendors

(see Figure 1). Using GIFA and a newbuild

cost of £4,000/m2, the diWerence in

cost estimates was £5m. The original

brief for the laser scan was to provide

walk-throughs for events, and it was only

later that other uses were considered.

That made the model a tough test for

tools aimed primarily at newbuild projects.

“I think this was mainly due to an

incomplete model, because surveyors

could not scan all areas during occe

hours, for example the restaurant,”

suggests Paul Burrows, a Solutions

Architect at BCIS. “All vendors were

given full computer-aided design [CAD]

floor plans and copies of the building’s

original 1898 drawings, but only one used

this. Its floor area calculation was within

50m2 of ours.”

Burrows summarises the other

findings as:

b models for existing buildings will

rely much more on human skill and

interpretation, and assumptions about

what the model ‘means’

b cost planning objects NRM1: Order

of cost estimating and cost planning for

capital building works are not included

as standard in Revit (which created the

model) and so modellers did not classify

against this list. This has implications

when construction professionals later

procure building works (NRM2) and

manage facilities (NRM3)

b two vendors revisited the original

3D model because they did not trust

Industry Foundation Classes (IFC)

outputs. This was not a criticism of IFC,

more that applications do not output IFC

consistently.

“The showcase provided useful pointers

for developing our model, including

quality standards and valid or invalid

assumptions to make,” says Burrows. His

advice for others considering BIM is:

b models for existing buildings (using

scanned laser surveys) will be very

diWerent from a newbuild model because

they lack structural detail

b do your own evaluation using your

most experienced estimators against

two models (new and existing buildings)

b ask how the software supports your

professional judgment in your normal

tasks. Is it easy to navigate and spot

problems? Can you make corrections

and apply your assumptions?

b understand diWerent vendor

approaches, e.g. overseas design

and procurement practice can be

very diWerent from the UK (involving

architects, quantity surveyors and

contractors).

“The importance of a quantity surveyor’s

professional judgment is highlighted

when making sense of a model,” says

Burrows, “especially one for an existing

building that was created by scanning

and importing the data.” b

For more details of the Showcase, visit www.rics.org/bim

Related competencies include: Data management

Figure 1The variances in element unit quantities between vendors

-60% -40% -20% 0% 20% 40% 60%

RICS result

Vendor results

Key

Floor finishes

Ceiling finishes

Fittings, furnishings and equipment

Substructure

Frame

Upper floors

Roof

Stairs and ramps

External walls

Windows and external doors

Internal doors

Wall finishes

Internal walls and partitions

Services