Short term mine sequencing using geological uncertainty

28
7/23/2019 Short term mine sequencing using geological uncertainty http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 1/28 Short term mine sequencing using geological uncertainty indexes - An application to the Carajás Iron Ore Complex  Prof. Rodrigo de Lemos Peroni Mining Engineer José Edson Aragão da Silva

Transcript of Short term mine sequencing using geological uncertainty

Page 1: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 1/28

Short term mine sequencing

using geological uncertainty

indexes - An application to the

Carajás Iron Ore Complex 

Prof. Rodrigo de Lemos Peroni

Mining Engineer José Edson Aragão da Silva

Page 2: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 2/28

 IntroductionGoal

Objectives

 Methodology Case Study

Results

 Conclusions

Presentation Outline

Page 3: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 3/28

Motivation

Different quality from planning, mainly in the weekly mineplanning.

Possible causes:

• Some mines are getting close to exhaustion, ore close to the

contact zones and/or, intrinsic variability of the deposits.;

Posing the problem 

1 – Predicted quality detachment in the monthly plan when

compared to the executed grades.

2 – High variability in the weekly plans when compared to the

monthly plan.3 – Absence of a good forecast beyond a week.

4 – Lack of knowledge of geological uncertainties impacting the mine

planning.

Introduction

 Introduction

 Goal

 Objectives

 Methodology

 Results

 Conclusions

Page 4: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 4/28

Goal:

Develop a short-term sequencingmethodology to improve the predictability of

quality in the weekly period and to assess the

geological uncertainty of the planned blocks;

 Introduction

 Goal

 Objectives

 Methodology

 Results

 Conclusions

Introduction

Page 5: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 5/28

 Objectives: 

 Implement a methodology of weekly sequencing;

Model the Fe grade uncertainties in the N5 mine;

Analyze the geological uncertainty during the mining

periods, aiming to know the risks associated to the

mining areas;

Compare the average quality given by the estimated

block model with the E-Type (Kriged) calculated from

the simulations.

Introduction

 Introduction

 Goal

 Objectives

 Methodology

 Results

 Conclusions

Page 6: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 6/28

Estimated block model:

Very popular in the mining industry; 

• Estimate mineral resources;

• In the last decades there were verified discrepancies when

compared to production results;

It is “accepted” that the main reasons to a poor reconciliationare related with the uncertainty in the geological interpretation

and with the estimates.

Factors that might affect the estimate uncertainty 

1 – Change of support;

2 – Lack of sampling, bad sampling or protocols;

3 – Interpolation errors;

4 – Smooth effect.

Methodology

 Introduction

 Goal

 Objectives

 Methodology

 Results

 Conclusions

Page 7: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 7/28

Geostatistical simulation

• Firstly proposed in the 70’s as a method to provide

a quantitative assessment of the local uncertainty.

sequential Gaussian simulation (sGs)

• Started in the 90´s;

•“Widely” used compared to other simulationalgorithms;

 Introduction

 Goal

 Objectives

 Methodology -

Simulation

 Results

 Conclusions

Methodology

Page 8: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 8/28

General view

Unknown deposit Geological dataset

Equally probable

models

 Introduction

 Goal

 Objectives

 Methodology -

Simulation

 Results

 Conclusions

Methodology

Page 9: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 9/28

 

Simulations generated using the sGsim implemented within SGEMs:

Dataset

EDA

VariogramHematites

sGs 100 Simulations

 Introduction

  Goal

 Objectives

 Methodology -

Simulation

 Results

 Conclusions

Methodology

Page 10: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 10/28

Case Study

Page 11: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 11/28

 

Page 12: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 12/28

 

Case Study

N5W, N5E, N5EN e N5Sul

Page 13: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 13/28

 

Case Study

Page 14: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 14/28

 

Page 15: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 15/28

 

Page 16: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 16/28

N5W

N5E

N5S

Case study – N5 Mine

Main aspects: 

• Hematites – HF, HC e HMN;

• Product: Sinter Feed;

• Main variable – Fegl;

• Period considered: 2011 – 2013;• Post processed block model

Localização das amostras da Mina de N5

 Introduction

 Goal

 Objectives

 Methodology -

Simulation

 Results

 Conclusions

Case Study

Final Block Dimensions:

25m x 25m x 15m

Page 17: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 17/28

 

Validation

• Histograms

Histograma dos dados

Histograma das realizações

 Introduction

  Goal

 Objectives

 Methodology -

Simulation

 Results

 Conclusions

Methodology

Mean

66.86%

Variance

5.99

50 realizations

Page 18: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 18/28

 

Validation

• Variogram Introduction

  Goal

 Objectives

 Methodology -

Simulation

 Results

 Conclusions

Methodology

Page 19: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 19/28

Export

Simulations(.CSV)

Calculation ofUncertainty Flag on model

The probability was post processed in

Excel considering the number of times

the criteria Fegl>= 65% was attended.

 Introduction

  Goal

 Objectives

 Methodology -

Simulation

 Results

 Conclusions

Methodology

Page 20: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 20/28

Export

simulations(.csv)

Calculation of

uncertainty Flag on model

 Introduction

  Goal

 Objectives

 Methodology -

Simulation

 Results

 Conclusions

Methodology

Page 21: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 21/28

Input parameters for sequencing.

 Introduction

  Goal

 Objectives

 Methodology -

Sequencing

 Results

 Conclusions

Technical parameters for sequencing

Model Name

Plant Production (per year)

Plant Recovery

Studied Variable

Reference content (Goal)

Period

65%

Weekly

N5 (Kriging)

50Mt

Global Iron grade (Fegl)

92%

  Input data

Page 22: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 22/28

The blue shades show the areas where the probability of the FEGL content presents

values above 65% are extremely low.

Areas in intense orange and red shades are areas of low uncertainty considering theypresent more than 80% probability to have FEGL grades above the defined cutoff of 65%.

Areas in green and yellow are areas of high uncertainty and or 40 to 60 % probability and

must be better assessed.

Week1 - 46

Week

47

ahead

 Introduction

  Goal

 Objectives

 Methodology -

Simulation

 Results

 Conclusions

Results

Probability map for the Fe content present grades above 65%.

Page 23: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 23/28

To carry out the sequencing in weekly plans, the simulations were fed to the Minesched®

software. The implemented algorithm allows good operational flexibility.

 Introduction

  Goal

 Objectives

 Methodology -

Sequencing

 Results

 Conclusions

Results

Page 24: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 24/28

 Results

Areas

shown inthe map.

Graphs presenting the quality and performed geological uncertainty ofeach period. 

Note that, although almost all periods have reached the goal of quality

(Kriging model), the associated risks, after week 46, are high, and

confirmed by the low probability of achieving the target grade (65%).

 Introduction

  Goal

 Objectives

 Methodology

 Results

 Conclusions

Page 25: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 25/28

The methodology allowed the predictability of

qualities in periods of mining;

 The application of geostatistical simulation

technique has proven to be a valuable tool toapproach the uncertainty of the variable FEGL;

Using the methodology suggested here, it was noted

that the results may assist short-term and mediumterm planning in the preparation of weekly and

monthly plans and in decision making, when periods

of operational difficulties are identified.

Conclusions

 Introduction

  Goal

 Objectives

 Methodology

 Results

 Conclusions

Page 26: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 26/28

Apply the methodology in other iron ore

mines in the Carajás complex and other

mining complexes from VALE;

Spread the methodology in the short-term

and medium term iron ore planning areas and

other commodities in the company;

Next steps

 Introduction

  Goal

 Objectives

 Methodology

 Results

 Conclusions

Page 27: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 27/28

Aknowledgements

• VALE

• UFRGS/PPGEM

Page 28: Short term mine sequencing using geological uncertainty

7/23/2019 Short term mine sequencing using geological uncertainty

http://slidepdf.com/reader/full/short-term-mine-sequencing-using-geological-uncertainty 28/28

Thank You!

Gracias!

Obrigado!

Rodrigo Peroni

[email protected]