SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.
-
Upload
dortha-french -
Category
Documents
-
view
217 -
download
0
Transcript of SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.
![Page 1: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/1.jpg)
SFOBB East Span Seismic Safety Project
Dan Ambuhl, Specifications Engineer, Caltrans
![Page 2: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/2.jpg)
SFOBB East Span Seismic Safety Project
Selected Special Provisions
• Welding
• Structural Steel Audits
• Temporary Towers
• Mass Concrete
• Cable System
• Steel Structures Main Span
• Steel Structures YBI
![Page 3: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/3.jpg)
SFOBB East Span Seismic Safety Project
• Applies to all Structural Steel
• Contractor responsible for QC
• CT has prerogative for QA
Welding
![Page 4: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/4.jpg)
SFOBB East Span Seismic Safety Project
• QC Plan is required
• Quality Control Plan– CT Qualification Requirement
– All UT personnel must be qualified by CT
• QC Inspector shall represent Contractor
• Document Submittals
Welding QC
![Page 5: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/5.jpg)
SFOBB East Span Seismic Safety Project
• Quality Assurance at Engineer discretion
• QA Inspector shall represent Engineer
Welding QA
![Page 6: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/6.jpg)
SFOBB East Span Seismic Safety Project
• Steel Audits – General Steel Meeting– Contractor’s Self Audit– CT Audit
Structural Steel Audit
![Page 7: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/7.jpg)
SFOBB East Span Seismic Safety Project
Temporary Towers• Footings
– Timber piles will not be allowed– Driving system submittal is required– Dynamic monitoring is required
• Towers– Specified to be made of steel– Working drawings will be required– Buy America does not apply to temporary works
![Page 8: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/8.jpg)
SFOBB East Span Seismic Safety Project
• Consists of portions of piles, pile caps, pier columns and cap beams.
• Thermal Control Plan is required
• Demonstration pours are required
Mass Concrete
![Page 9: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/9.jpg)
SFOBB East Span Seismic Safety Project
Cable System
• Cable System– Cable Wire Rod– PPWS Strand– S-Wire Cable Wrapping– Corrosion System
• Suspender System
![Page 10: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/10.jpg)
SFOBB East Span Seismic Safety Project
Steel Structures Main Span
• Typical Structural Steel– Girders, plates, connections– Full Scale Mock ups will be required, for
details shown on the plans
![Page 11: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/11.jpg)
SFOBB East Span Seismic Safety Project
Steel Structures Main Span
• Non Typical Structural Steel– Hinge Pipe Beams– Castings
• Tower Saddle may be cast in max. of 3 pieces
– Modular Joint Seal Assemblies, Circular Segmented Bearings
– Travelers– Substation components & service platforms
![Page 12: SFOBB East Span Seismic Safety Project Dan Ambuhl, Specifications Engineer, Caltrans.](https://reader035.fdocuments.us/reader035/viewer/2022081702/56649f135503460f94c2763a/html5/thumbnails/12.jpg)
SFOBB East Span Seismic Safety Project
Steel Structures YBI• All structural steel is on the Temporary
Detour Structure
• Buy America does not apply to temporary structures