S. L. King & Associates, Inc. Engineers Planners Managers Aviation Safety, Security &
Severud Associates Consulting Engineers PC
-
Upload
beau-matthews -
Category
Documents
-
view
27 -
download
1
description
Transcript of Severud Associates Consulting Engineers PC
Severud Associates Consulting Engineers PC
Museum of the American IndianWashington, D.C.
Yale University Ingalls Hockey RinkNew Haven, CT
Eventi Hotel839 6th Avenue, New York, NY
US Airways Terminal, Philadelphia International Airport
The US Mission to the UNNew York, NY
Severud Associates Consulting Engineers PC
Bank of America TowerNew York, NY
Jefferson National Expansion MemorialSaint Louis, MO
The Times Square Edition701 7th Avenue, New York, NY
Typical Concrete Strength and Stiffness Specs for High Rise (Over 500 feet) in NYC
Spec concrete strength 6 ksi to 12 ksiActual concrete strength 6 ksi to 19 ksiSpecified E value 4.7Mpsi to 6.6MpsiActual E value 8Mpsi maxNo. concrete mixes 10 - 20w/c ratio 0.29 to 0.35 (verified by microwave test)
Concrete Placement Rules
95% max water content added at the plant. Max 5% water available for addition at the site.
5% held water added on site only to raise the slump of the concrete.
Superplasticizer to be made available on site during all concrete placing operations, for re-dosage as required. All trucks delivering to the site shall be supplied with a re-dosage chart.
All concrete trucks arriving to the jobsite will have a computerized batch ticket to be given to the inspector for review prior to pouring concrete.
The batch ticket must indicate truck number, total batch size, strength in psi, time of discharge, amounts of materials added at the plant, percentage of moisture in the aggregate.
Trucks arriving on site without the computerized batch ticket shall be rejected.
Concrete Placement Rules (cont.)
Pre-approved design mixes and admixtures only. A pre-approved mix is defined as one having the exact same constituent proportions and constituent sources. Any truck arriving on site with a mix or admixture that is different than the approved design mixes shall be rejected.
Pour time limit = 90 minutes after leaving plant, with a possible extension to 120 minutes (pending the temperature of the concrete).
However, if the mix is provided with a hydration control admixture that has been pre-approved, this time limit may exceed 120 minutes.
Lab shall measure concrete temperature after 90 minutes.
700F < Temperature < 900F : Inspector’s or Engineer’s call
Temperature > 950F : concrete is rejected regardless of mix time
Temperature < 500F : concrete is rejected regardless of mix time
Concrete Placement RulesTime > 120 minutes : concrete is rejected (unless the mix is provided with a pre-approved hydration control admixture)
Slump exceeds max value shown on design mix (with tolerances): concrete is rejected
No concrete placement without both Severud and the testing lab present
An insulated coring box with sufficient room to place all the required samples shall be provided on site.
A microwave oven will be provided at the site to verify the moisture content in the concrete in accordance with the specifications.
Slump tests for every 50 yards of concrete placed, and at any time upon a request from Severud, at the point of discharge (at the truck).
The contractor will be responsible for delivering the required samples from the point of placement to the concrete inspector on request every 150 cubic yards if concrete is placed using a pump.
Typical 8,000psi Mix – Vertical Elements
Typical 8,000psi Mix – Vertical Elements
Typical 10,000psi Mix – Vertical Elements
Typical 10,000psi Mix – Vertical Elements
Typical 12,000psi Mix – Vertical Elements
Typical 12,000psi Mix – Vertical Elements
Modulus E Chart for Test Cylinders
Modulus of Elasticity and Poisson’s Ratio: ASTM C469 / C469M–14
Microwave Oven Testing
• Used to test water content and water cementitious ratio of discharged concrete at the site
• AASHTO T318 for Guidelines• One test per every five trucks (or fifty yards), typically• Used for verification of water content, not for rejection*
• * if it is a frequent issue, rejection and remediation will be required
Microwave Test Equipment(Courtesy of National Concrete Pavement Technology Center)
THANK YOU