SETTLEMENT MARKERS The settlement marker is used to measure a localised settlement or heave of roads, slopes, embankments, utility pipes and cables. INSTALLATION AND MONITORING Concrete Nail Concrete Nail Painting Concrete Structure 50mm Schematic diagram of installed settlement marker in soil Schematic diagram of installed settlement marker on concrete Crosssection of Utilities/Services 10 cms Backfill soil 75 mm dia Heavy duty PVC pipe with Cap 16 mm dia mild steel rod 50x50x4mm steel plate Varied Length Backfill soil Schematic diagram of installed settlement marker on utility Settlement Marker on Concrete Installed on a Pavement Settlement Marker for Utility services Settlement Marker in Ground The monitoring of settlement marker is carried out by leveling survey and readings are taken at regular intervals to check any settlement or heave. 800 minimum 100Ф PVC or Steel Tube Convex End Sand Fill 75 mm Ф hole filled with cement grout after placingin the steel rod. 25Ф Steel rod Concrete to be painted in yellow Concrete

Transcript of SETTLEMENT MARKERS - Geosmartgeosmart.com.sg/technical/Geotechnical_Instruments.pdf · SETTLEMENT...

Page 1: SETTLEMENT MARKERS - Geosmartgeosmart.com.sg/technical/Geotechnical_Instruments.pdf · SETTLEMENT MARKERS The settlement marker is used to measure a localised settlement or heave

 

SETTLEMENT MARKERS The settlement marker is used to measure a localised settlement or heave of roads, slopes, 

embankments, utility pipes and cables. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

INSTALLATION AND MONITORING 

 

 

 

 

 

Concrete Nail

Concrete Nail

Painting

Concrete Structure 

50mm 

Schematic diagram of installed settlement marker in soil 

Schematic diagram of installed settlement marker on concrete 

Cross‐section of Utilities/Services 10 cms 

Backfill soil 

75 mm dia Heavy duty PVC pipe with Cap 

16 mm dia mild steel rod 

50x50x4mm steel plate

Varied

 Len

gth 

Backfill soil

Schematic diagram of installed settlement marker on utility 

Settlement Marker on Concrete Installed on a Pavement 

Settlement Marker for Utility services Settlement Marker in Ground 

The monitoring of settlement marker is carried out by leveling survey and readings are taken at regular intervals to 

check any settlement or heave. 

800 minim

um 

100Ф PVC or Steel Tube 

Convex End 

Sand Fill 

75 mm Ф hole filled with cement grout after placing‐in the steel rod. 

25Ф Steel rod 

Concrete to be painted in yellow

Concrete

Page 2: SETTLEMENT MARKERS - Geosmartgeosmart.com.sg/technical/Geotechnical_Instruments.pdf · SETTLEMENT MARKERS The settlement marker is used to measure a localised settlement or heave

GROUNDWATER STANDPIPE Measures fluctuation of ground water level. It is used as part of a system for early detection 

of water loss that could cause ground settlement. 

 

INSTALLATION 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MONITORING  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Schematic diagram of ground water stand pipe

Bottom Cap 

Ground Level 

Protective Cover 

Coarse Grain Sand 

Bentonite Pellets 

Perforated PVC Pipe 

Water level indicator

A cap and protective box  is placed over  the  water  standpipe  tube opening to prevent disturbance.  

Ground water level is measured by using water level indicator. The probe of water level indicator is lowered down into the water standpipe until light or buzzer indicates contact with the water. Depth to water level is measured from the measuring tape attached to the indicator. 

 

Page 3: SETTLEMENT MARKERS - Geosmartgeosmart.com.sg/technical/Geotechnical_Instruments.pdf · SETTLEMENT MARKERS The settlement marker is used to measure a localised settlement or heave

VIBRATING WIRE PEIZOMETER Measures changes in the ground water pressure at different depths. It is used as part of a system for early detection of change in water pressure that could cause ground settlement. 

INSTALLATION 

 

To terminal

Coarse Grain Sand 

 Ground Level

   

 

Grout

Bentonite Pellets 

 

 

 Electric Cable 

Vibrating wire Piezometer tip 

 

 

 

Vibrating wire piezometer tip 

 

 Schematic diagram

 

 

 

 

 

 

 

 

  The borehole with vibrating wire piezometer installed is kept in a protective metal box to prevent damage & disturbance to the instrument.  

MONITORING 

 

 

 

 

 

 

 

 Vibrating wire piezometer 

data logger 

 The vibrating wire piezometer is connected to the read out unit and the ground water pressure readings are recorded and stored in the data logger 

 

 

Page 4: SETTLEMENT MARKERS - Geosmartgeosmart.com.sg/technical/Geotechnical_Instruments.pdf · SETTLEMENT MARKERS The settlement marker is used to measure a localised settlement or heave

INCLINOMETER Measures lateral movements of the ground, retaining walls and piles for early detection of 

any disturbance or effect to structures and property due to construction activity. 

 

INSTALLATION 

 

 

 

 

 

 

 

 

 

 

MONITORING  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The inclinometer probe is lowered down in to the casing and at every 0.5 m intervals it records the lateral movement. The raw data obtained is transmitted from the inclinometer probe to a read out or a PDA by Bluetooth technology. 

 After  the  installation  of inclinometer casing in the hole,  the  casing  top  is capped  to  prevent  the entry of foreign particles.  

Metal  protective  boxes are used to prevent the instruments from being disturbed.  Instrument identification  is  affixed on to the box. 

Schematic diagram of inclinometer casing

Grout

Protective cover

Ground Level 

Bottom 

Inclinometer casing

Inclinometer probe 

Cross section view of inclinometer probe inside the casing during monitoring works 

 

Page 5: SETTLEMENT MARKERS - Geosmartgeosmart.com.sg/technical/Geotechnical_Instruments.pdf · SETTLEMENT MARKERS The settlement marker is used to measure a localised settlement or heave

MAGNETIC EXTENSOMETER Measures settlement of the ground at various depths for early detection of any disturbance 

or effect due to construction activity. 

 

INSTALLATION 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MONITORING  

 

 

 

 

 

 

 

 

 

 

 

 

 

The magnetic extensometer probe is lowered down into the casing untill light or buzzer indicates the contact with the spider magnet. Depth of the magnet is measured from the measuring tape attached to the probe. 

 

Installed casing is capped and kept in a protective metal box to prevent damage & disturbance  

 

Schematic diagram of magnetic extensometer

Magnetic extensometer probe & spider magnet