The Importance of Project Cost Management

IT projects have a poor track record for meeting cost goals

Average cost overrun from 1995 CHAOS study was 189% of the original estimates; improved to 145% in the 2001 study

In 1995, cancelled IT projects cost the U.S. over $81 billion

Page 3: Setting Your Fees Project Cost and Setting Your Fees.

What is Cost and Project Cost Management?

Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange

Costs are usually measured in monetary units like dollars

Project cost management includes the processes required to ensure that the project is completed within an approved budget

Page 4: Setting Your Fees Project Cost and Setting Your Fees.

Project Cost Management Processes

Resource planning: determining what resources and quantities of them should be used

Cost estimating: developing an estimate of the costs and resources needed to complete a project

Cost budgeting: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance

Cost control: controlling changes to the project budget

Page 5: Setting Your Fees Project Cost and Setting Your Fees.

Basic Principles of Cost Management

Most CEOs and boards know a lot more about finance than IT, so IT project managers must speak their language Profits are revenues minus expenses Life cycle costing is estimating the cost of a project

plus the maintenance costs of the products it produces

Cash flow analysis is determining the estimated annual costs and benefits for a project

Benefits and costs can be tangible or intangible, direct or indirect

Sunk cost should not be a criteria in project selection

Page 6: Setting Your Fees Project Cost and Setting Your Fees.

Developing the Project Budget Cost Estimation Steps

1. Defining what resources will be needed to perform the work

2. Determining the quantity of resources that are needed

3. Defining the cost of using each resource 4. Calculating the cost of the task or activity 5. Ensuring that the resources are leveled,

that is, resources have not been over allocated.

Page 7: Setting Your Fees Project Cost and Setting Your Fees.

Types of Costs

Direct Indirect Sunk Learning Curve Reserves

Page 8: Setting Your Fees Project Cost and Setting Your Fees.

Client wants you to do the work in its entirety just as proposed

You have to be scientific about your fees

Must be able to break it down into components

Your fees must do four things

Page 9: Setting Your Fees Project Cost and Setting Your Fees.

Fees Must Provide Four Things Must provide with personal income

appropriate to your skills, knowledge, and experience

Must meet all the costs of running your business

Must provide a surplus or profit (to recompense you for the risk you’re taking with your resources)

Must enable to you to compete effectively in your chosen market

Page 10: Setting Your Fees Project Cost and Setting Your Fees.

Step-By-Step Calculation

1. Make an assessment of what your skills, knowledge and experience would bring in marketplace as an employee (i. e. annual salary).

2. Find your working days in a year by subtracting number of weekends from 365 days.

3. Divide salary in No. 1 by the working days to get your labor rate.

Page 11: Setting Your Fees Project Cost and Setting Your Fees.

Step-By-Step Calculation

4. Forecast the day you expect to be able to bill clients, on average, each month.

5. List and cost all your monthly overheads6. Multiply each monthly cost by 12 and add

these up to get annual cost of being in business

7. Divide the annual overhead by the number of days in a year which you expect to invoice to customers

8. Add No. 3 and No.7 to get Total Cost9. Add your profit margin

Page 12: Setting Your Fees Project Cost and Setting Your Fees.

OVERHEADS

Monthly Annual ($)Secretary 1,000 12,000*

Office rent 250 3000*

Telephone 100 1200Postage 65 780Personnel benefits 40 480*

Equipment 25 300Stationery 12 144

Page 13: Setting Your Fees Project Cost and Setting Your Fees.

OVERHEADS Marketing

Personnel (5 days) 958 11,496*

Direct Mkt (2.5 x d. labor rate) 500 6,000 Practice management 958 11,496*

(5 days) Dues and subscriptions 12 144

Automotive 345 4, 140 Insurance 26 312 Accounting and legal 225 2,700 Miscellaneous 200 2,400*

Page 14: Setting Your Fees Project Cost and Setting Your Fees.

OVERHEADS Totals 4,716 56,592 Day you expect to invoice 144 days Daily overhead rate = 56,592/144=

393.00 Total cost of doing business =

191.50 + 393.00 = 584.50 Profit (15-25%) = 146.13 GRAND TOTAL = 730.63 == 735.00/day

Page 15: Setting Your Fees Project Cost and Setting Your Fees.

Finalizing the Project Schedule and Budget Project schedule and budget may

require several iterations before it is acceptable to the sponsor, the project manager, and the project team

Once the project schedule and project plan are accepted, the project plan becomes the baseline plan.

Once accepted, the project manager and project team have the authority to execute or carry out the plan.

Page 16: Setting Your Fees Project Cost and Setting Your Fees.

Cost of Software DefectsWhen Defect is Detected Typical Cost of Correction

User Requirements $100-$1,000Coding/Unit Testing $1,000 or moreSystem Testing $7,000 - $8,000Acceptance Testing $1,000 - $100,000After Implementation Up to millions of dollars

It is important to spend money up-front on IT projects to avoid spending a lot more later.

Page 17: Setting Your Fees Project Cost and Setting Your Fees.

Resource Planning

The nature of the project and the organization will affect resource planning

Some questions to consider: How difficult will it be to do specific tasks on the

project? Is there anything unique in this project’s scope

statement that will affect resources? What is the organization’s history in doing similar

tasks? Does the organization have or can they acquire

the people, equipment, and materials that are capable and available for performing the work?

Page 18: Setting Your Fees Project Cost and Setting Your Fees.

Types of Cost EstimatesType of Estimate When Done Why Done How Accurate

Rough Order ofMagnitude (ROM)

Very early in theproject life cycle,often 3–5 yearsbefore projectcompletion

Provides roughballpark of cost forselection decisions

–25%, +75%

Budgetary Early, 1–2 years out Puts dollars in thebudget plans

–10%, +25%

Definitive Later in the project, <1 year out

Provides details forpurchases, estimateactual costs

–5%, +10%

Page 19: Setting Your Fees Project Cost and Setting Your Fees.

Typical Problems with IT Cost Estimates

Developing an estimate for a large software project is a complex task requiring a significant amount of effort. Remember that estimates are done at various stages of the project

Many people doing estimates have little experience doing them. Try to provide training and mentoring

People have a bias toward underestimation. Review estimates and ask important questions to make sure estimates are not biased

Management wants a number for a bid, not a real estimate. Project managers must negotiate with project sponsors to create realistic cost estimates

Page 20: Setting Your Fees Project Cost and Setting Your Fees.

Business Systems Replacement Project Cost Estimate Overview

Page 21: Setting Your Fees Project Cost and Setting Your Fees.

Business Systems Replacement Project Cash Flow Analysis

FY95

($000)

FY96

($000)

FY97

($000)

3 YearTotal($000)

Future AnnualCosts/Savings

($000)CostsOracle/PM Software(List Price)

992 500 0 1492 0

60% Discount (595) (595)Oracle Credits (397) 0 (397)

Net Cash for Software 0 500 500Software Maintenance 0 90 250 340 250Hardware & Maintenance 0 270 270 540 270Consulting &Training 205 320 0 525 0Tax & Acquisition 0 150 80 230 50Total Purchased Costs 205 1330 600 2135 570Information Services &Technology (IS&T)

500 1850 1200 3550 0

Finance/Other Staff 200 990 580 1770Total Costs 905 4170 2380 7455 570

SavingsMainframe (101) (483) (584) (597)Finance/Asset/PM (160) (1160) (1320) (2320)IS&T Support/Data Entry (88) (384) (472) (800)Interest 0 (25) (25) (103)Total Savings (349) (2052) (2401) (3820)

Net Cost (Savings) 905 3821 328 5054 (3250)

8 Year InternalRate of Return

35%

Page 22: Setting Your Fees Project Cost and Setting Your Fees.

Cost Budgeting

Cost budgeting involves allocating the project cost estimate to individual work items and providing a cost baseline

For example, in the Business Systems Replacement project, there was a total purchased cost estimate for FY97 of $600,000 and another $1.2 million for Information Services and Technology

These amounts were allocated to appropriate budgets as shown in the next table.

Page 23: Setting Your Fees Project Cost and Setting Your Fees.

Business Systems Replacement Project Budget Estimates for FY97 and Explanations

Budget Category Estimated Costs ExplanationHeadcount (FTE) 13 Included are 9 programmer/analysts, 2

database analysts, 2 infrastructuretechnicians.

Compensation $1,008,500 Calculated by employee change notices(ECNs) and assumed a 4% pay increase inJune. Overload support was planned at$10,000.

Consultant/PurchasedServices

$424,500 Expected consulting needs in support of theProject Accounting and Cascadeimplementation efforts; maintenanceexpenses associated with the Hewlett-Packard (HP) computing platforms;maintenance expenses associated with thesoftware purchased in support of the BSRproject.

Travel $25,000 Incidental travel expenses incurred insupport of the BSR project, most associatedwith attendance of user conferences andoff-site training.

Depreciation $91,000 Included is the per head share ofworkstation depreciation, the Cascade HPplatform depreciation, and the depreciationexpense associated with capitalizedsoftware purchases.

Rents/Leases $98,000 Expenses associated with the Mach1computing platforms.

Other Suppliesand Expenses

$153,000 Incidental expenses associated with thingssuch as training, reward and recognition,long distance phone charges, miscellaneousoffice supplies.

Total Costs $1,800,000

Page 24: Setting Your Fees Project Cost and Setting Your Fees.

Cost Control

Project cost control includes monitoring cost performance ensuring that only appropriate project

changes are included in a revised cost baseline

informing project stakeholders of authorized changes to the project that will affect costs

Page 25: Setting Your Fees Project Cost and Setting Your Fees.

Cost Control Input Form for Business Systems Replacement ProjectWBS#: 6.8.1.2 Description: Design Interface Process -

Customer InformationRevision: Revision Date:

Assignments ForecastHours per day Effort (in hours) Calculated

Responsible: SMC Role: PA Availability: 6 Optimistic: 20Most Likely: 30 Plan

Effort:30 Hrs

Involved: Role: Availability: Pessimistic: 40

Involved: Role: Availability: PlanDuration

:

5 Days

Involved: Role: Availability: Delay (Days):

Description Assumptions

Results / Deliverables Dependencies Predecessors (WBS#): Successors (WBS#):

4.7

Develop an operational process design for the Customer Informationinterface from the Invoicing System to Oracle Receivables. This task willaccept as input the business/functional requirements developed during thetactical analysis phase and produce as output a physical operational design,which provides the specifications, required for code development.

Process Design Document - Technical - Operation/Physical DFD - Process Specifications - Interface Data Map

- All business rules and issues will be resolved prior to this task.- The ERD & data model for Oracle Receivables & any Oracleextension required will be completed and available prior to this task.- The ERD for the Invoicing System will be completed and availableprior to this task.- Few iterations of the review/modify cycle will be required.- Primarily a documentation task.

Page 26: Setting Your Fees Project Cost and Setting Your Fees.

Project Portfolio Management

Many organizations collect and control an entire suite of projects or investments as one set of interrelated activities in a portfolio

Five levels for project portfolio management Put all your projects in one database Prioritize the projects in your database Divide your projects into two or three budgets

based on type of investment Automate the repository Apply modern portfolio theory, including risk-

return tools that map project risk on a curve

Page 27: Setting Your Fees Project Cost and Setting Your Fees.