Session36-37
-
Upload
town-obio-etete -
Category
Documents
-
view
214 -
download
0
Transcript of Session36-37
-
7/30/2019 Session36-37
1/19
SESSIONS 36 & 37
Cost Estimation & Budget
-
7/30/2019 Session36-37
2/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Not an exact science
WBS cost is a good starting point
Do not leave anything out Estimating forms
Estimators:Optimistic estimators
Pessimistic estimators
Inconsistent estimators
Accurate estimators
-
7/30/2019 Session36-37
3/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Estimates for material and equipment costs
Contingency allowances
Cost escalation (changes in prices) Changes in staff
Provisional sums
Foreign currencies
Reviewing of estimates
The learning curve
Pressure for low estimates
-
7/30/2019 Session36-37
4/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Use of widely optimistic estimates
Unawareness of good cost or time estimate
practices Number of things producing errors in cost
estimates are unlimited
Allowance for waste and spoilage
Bad luck: unpredicted delays
-
7/30/2019 Session36-37
5/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Consider a project that requires 25 units of a
complex electronic device to be assembled.
The firm is experienced in building electronic
equipment but has never before made this specific
device.
If the firm is to make many such devices, it would
use about 70 hrs of direct labour per unit.
-
7/30/2019 Session36-37
6/19
If labour is paid a wage of $12 per hr, and ifbenefits equal 28% of the wage rate, the estimated
labour cost for 25 units is
(1.28)($12/hr)(25 units)(70 hr/unit) = $26,880
Is this an underestimate or overestimate of actual
labour cost?
-
7/30/2019 Session36-37
7/19
Studies shown that human performance usually
improves when a task is repeated.
In general, performance improves by a fixed
percent each time production doubles.
This is called the LEARNING RATE
If an individual requires 10 minutes to accomplish
a certain task the first time it is attempted and only8 minutes the second time, that person has 80%
learning rate.
-
7/30/2019 Session36-37
8/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
If the output doubles again from 2 to 4 we would
expect the 4th item to be produced in
8(0.8) = 6.4 minutes
Similarly the 8th item will be produced in
6.4(0.8) = 5.12 minutes
-
7/30/2019 Session36-37
9/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Tn = time required for the nth unit of output
T1 = time required for the initial unit of output
n = number of units to be produced
r = log decimal learning rate/log 2
Total time required for all units of a production run of size N is
r
nnTT
1
N
n
r
nTtimetotal1
1
-
7/30/2019 Session36-37
10/19
Assuming that after producing the 20th unit, there is no
significant further improvement.
If Tn=70 hrs, the time required for the first unit is
r
n
n
TT 1
r = log 0.85/log 2 = -0.235
T1 = 141.3 hr
The multiplier = 12.40
(12.40)(141.3 hr) = 1752.12
The last five units were produced in the stead-state time
of 70 hrs each
1752.12 + 5(70 hr) = 2102.12 hr
-
7/30/2019 Session36-37
11/19
Direct labour cost =2101.12($12)!1.28) = $32,288.56
Difference with first estimate =
$32,288.56 - $26,880 = $5,408.56
Accuracy = about 17%
-
7/30/2019 Session36-37
12/19
Number of units
Time
Additional time
used for learning
Effects of ignoring learning curve
Time chargedwithout allowance
for learning
-
7/30/2019 Session36-37
13/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
3Definitive
estimate/Detaile
d estimating
1Order-ofmagnitude
2Approximateestimate or
top-downestimate
Made without
detailed
engineering data
May use past
experience, scale
factors,parametric curves
or capacity
estimates
Made without detailed
engineering dataProrated from
previous projectssimilar in scope and
capacityThis is estimating byanalogue, parametric
curves, rule of thumband indexed cost ofsimilar activities
adjusted for capacityand technology.
Prepared from well-
defined engineering
data including vendorquotes, fairly
complete plans,
specifications, unit
prices, and estimate to
complete.
Type of
Estimates
-
7/30/2019 Session36-37
14/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Standard Project Estimating
WBS Level Type of Estimate Estimate Method Accuracy
1 Rough order of magnitude Parametric -25%, +75%
2,3 Approximate estimating Analogy -10%, +25%
4,5,6 Definitive Engineering buildup -5%, +10%
-
7/30/2019 Session36-37
15/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Definition
An agreed and approved sum of moneyallocated for expenditure on a specific
work scope
-
7/30/2019 Session36-37
16/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Budgets are the means by which project
costs can be compared with financial
resources, and they enable decisions to betaken concerning the provision and
deployment of Company funds
(Shell Project Management Guidelines)
Budgetary control enables activities to be
matched to financial capabilities
-
7/30/2019 Session36-37
17/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
A budget requires a forecast of resources
needed for the project, quantities, when
needed, how much they will cost ..
The influence of history is strong in the
budget of ongoing activity.
-
7/30/2019 Session36-37
18/19
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Many entries may become last years
figure plus X percent
Guidance can be used from similar projects
Project budgets are based on forecasts of
resource usage and associated costs. Thisinvolves risk.
-
7/30/2019 Session36-37
19/19
DR ASSEM AL-HAJJ, Univation, RGUP j t M t d E i SITP SPDC NIGERIA
BUDGET TYPES
TOP-DOWNBOTTOM-UP
Collecting judgements &experiences of top and middlemanagers, and available past
data concerning similaractivities
Managers estimate overallproject cost as well as costs of
major subprojects.Budget is broken down into
successively finer detail,starting from
top
following
the WBS
Follows the WBS
People doing the work are
consulted regarding times andbudgets
Estimates are made in terms of
resources e.g. labour hours
and materials
Task budgets are aggregated to
give the total direct costsUsually a more accurate
method
Top-
down is
commo
n
Botto
m-up
is rare
Advantage 1
budgets
can be
developed
quite
accurately
Advantage 2
small yet
costly tasks
need not be
individuall
y identified