Session20-21
-
Upload
town-obio-etete -
Category
Documents
-
view
217 -
download
0
Transcript of Session20-21
-
7/30/2019 Session20-21
1/27
SESSIONS 20 & 21
Scheduling
-
7/30/2019 Session20-21
2/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Determines how company resources should be
integrated.
Important for projecting time-phased resourceutilisation requirements.
Provides a basis for visually tracking
performance.
Serves as a master plan for information.
-
7/30/2019 Session20-21
3/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Identify all major events and dates clearly.
Establish number of activities and level of
breakdown structure.Define sequence of work through a network
where interrelationships between events can be
identified.
Relate schedules directly to WBS.
Identify time constraints and resources required
for each event.
-
7/30/2019 Session20-21
4/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
1. Summary schedules:
for management and planners
2. Detailed schedules:
for doers and lower-level control
Most organisations develop multiple
schedules:
Provide a means to
authorise and control
manpower, inventory
investment, and cash
flow.
Provides data for
material and capacity
planning
Co-ordinate
marketing,
manufacturing,
engineering, and
finance activities
Provides an overallmeasure of
performance
-
7/30/2019 Session20-21
5/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Secondary objectives of scheduling: Studying alternatives
Developing an optimal schedule
Using resources effectively
Communicating Refining the estimating criteria
Obtaining good project control
Providing for easy revisions
Primary objective of scheduling:
To co-ordinate activities in the master plan
To complete the project within time, cost, and
least risk.
-
7/30/2019 Session20-21
6/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Provides top management with a means to
authorise and control manpower levels, inventory
investment, and cash flow.
Co-ordinate marketing, manufacturing,
engineering, and finance activities
Provides an overall measure of performance
Provides data for material and capacity planning
-
7/30/2019 Session20-21
7/27DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
An appropriate scheduling system:-
bar charts
milestone charts network
A listing of activities at the project level or lower
The possible interrelationships between activities,
this can be accomplished by logic networks,
critical path networks, or PERT network.
Activity time estimates
-
7/30/2019 Session20-21
8/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
-
7/30/2019 Session20-21
9/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Most common techniques:
1. Gantt or bar charts
2. Milestone charts
3. Networks Programme Evaluation and Review Technique
(PERT)
The Critical Path Method (CPM)
On-the-Arrow-Diagram Method
On-the-Node-Diagram Method or Precedence DiagramMethod
4. Line of balance
-
7/30/2019 Session20-21
10/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
The oldest, simplest planning,
scheduling and contracting
technique.
Represents the time period
allocated to the various tasks or
activities.
An activity is a task or closely
related group of tasks whose
performance contributes tocompletion of the overall
project.
Activities are entered down the
side in chronological order.
Operatio
n
Time
Excavation
Sub-structure
-
7/30/2019 Session20-21
11/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Easily understood
Extremely useful for comparing planned and actual progress Easy and quick to prepare
Require less revision and updating than other moresophisticated systems.
Logical interconnections are difficult to comprehend.
Difficult to reconstruct the logic and recognise sequence
constraints
Difficult to use for forecasting the effects that changes in a
particular activity will have on the overall schedule, or
even to project the progress of an individual activity.
-
7/30/2019 Session20-21
12/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
-
7/30/2019 Session20-21
13/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
A powerful analytical tool for project planning and control.
Based on the rigorous application of logic network.
PERT Originally developed in 1958 and 1959
Introduced by the Special Projects Office of the U.S. Navy
on the Polaris Weapon System in 1958
At the same time the DuPont Company initiated theCritical Path Method (CPM) technique. This particularly
concentrated in the construction and process industries.
-
7/30/2019 Session20-21
14/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Reveals interdependencies and problem areas i.e.determines where the greatest effort should be made
Can determine the probabilities of meeting a specifieddeadlines by development of alternative plans.
Ability to evaluate the effect of changes in the programme.
Allows a large amount of sophisticated data to bepresented in a well-organised diagram.
Can become very complex
More data is required for the analysis
Expensive to maintain
Best for large, complex programmes
Complicated for repetitive tasks
-
7/30/2019 Session20-21
15/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
PERT
Uses three time estimates Optimistic, Most-likely,
Pessimistic
Probabilistic in nature,allows us to calculate therisk in completing theproject.
Used in R&D projectswhere risks in calculatingtime durations have a highvariability.
CPM Uses one time estimate
Deterministic in nature
Used for constructionprojects that resourcedependent and based onaccurate time estimates
-
7/30/2019 Session20-21
16/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
All tasks must be visualised in a manner clear
enough to be put down in a network which
comprises events and activities; i.e. follow the
work breakdown structure.
Events and activities must be sequenced under a
highly logical set of ground rules.
Time estimates must be made for each activity on
the network.
Critical path and float times are computed
-
7/30/2019 Session20-21
17/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Three types:
1. Mandatory dependencies- hard logic:
dependencies that cannot change2. Discretionary dependencies- soft logic: may be
at the discretion of the project manager, may
change from one project to another
3. External dependencies- may be beyond the
control of the project manager.
-
7/30/2019 Session20-21
18/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
A network provides the following information:
Interdependencies of activities
Project completion time
Impact of late starts
Impact of early starts
Trade-offs between resources and time
What if exercises Cost of a crash programme
Slippages in planning/performance
Evaluation of performance
-
7/30/2019 Session20-21
19/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
EVENTACTIVITY
EVENT
Networks are composed of events and activities
An event is the starting or ending point for a group of
activities
An activity is the work required to proceed from one event
to another.
-
7/30/2019 Session20-21
20/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Job description
EVENT EVENT
Start of activity Finish of activity
i j
Duration
Well testingStart of activity Finish of activity
3 77 days
-
7/30/2019 Session20-21
21/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Defining the sequence of events:
Logical flow of work is established by asking the
following questions: What job/s immediately precede this one?
What job/s immediately follow this one?
What job/s can be done concurrently?The answers to these questions are compounded in
an arrow diagram.
-
7/30/2019 Session20-21
22/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
ExcavateErect formwork Pour concrete
1 432
21
3
5
4
Burst point
Plaster walls
1
5
3
2Rough plumbing
4
Sink
-
7/30/2019 Session20-21
23/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Length & shape of the arrow does not give anysignificant information of the activity or to theresources it consumes.
Until or unless all activities, leading to an eventare completed, the event is not completed. Noactivity can start until the proceeding events are
completed. Time Flows from left to right.
The activity is identified by its start and finishevents number.
-
7/30/2019 Session20-21
24/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
i j
D
E
D
E
DummyD
E
Dummy
A C
Real
dummy
10
-
7/30/2019 Session20-21
25/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
A
B D
C
Dummy
DB
A C
-
7/30/2019 Session20-21
26/27
DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA
Activities A, B, and C can start together. Once B
is complete, D can start. E can start when A is
complete, and F can start when A and D are
complete. G and H can start when B and C are
complete, and J when E, F and G are complete.
Draw the network and number the nodes.
-
7/30/2019 Session20-21
27/27
DR ASSEM AL-HAJJ Univation RGU
A
C
B1
E2
D3
G
H4
F5
J6 7
A, B, and C can
start together
Once B is
complete, D can
start
Once A is
complete, E can
start
F can start when
A and D are
complete
G and H can startwhen B and C arecomplete
J can start when
E, F and G are
complete