Session20-21

download Session20-21

of 27

Transcript of Session20-21

  • 7/30/2019 Session20-21

    1/27

    SESSIONS 20 & 21

    Scheduling

  • 7/30/2019 Session20-21

    2/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Determines how company resources should be

    integrated.

    Important for projecting time-phased resourceutilisation requirements.

    Provides a basis for visually tracking

    performance.

    Serves as a master plan for information.

  • 7/30/2019 Session20-21

    3/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Identify all major events and dates clearly.

    Establish number of activities and level of

    breakdown structure.Define sequence of work through a network

    where interrelationships between events can be

    identified.

    Relate schedules directly to WBS.

    Identify time constraints and resources required

    for each event.

  • 7/30/2019 Session20-21

    4/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    1. Summary schedules:

    for management and planners

    2. Detailed schedules:

    for doers and lower-level control

    Most organisations develop multiple

    schedules:

    Provide a means to

    authorise and control

    manpower, inventory

    investment, and cash

    flow.

    Provides data for

    material and capacity

    planning

    Co-ordinate

    marketing,

    manufacturing,

    engineering, and

    finance activities

    Provides an overallmeasure of

    performance

  • 7/30/2019 Session20-21

    5/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Secondary objectives of scheduling: Studying alternatives

    Developing an optimal schedule

    Using resources effectively

    Communicating Refining the estimating criteria

    Obtaining good project control

    Providing for easy revisions

    Primary objective of scheduling:

    To co-ordinate activities in the master plan

    To complete the project within time, cost, and

    least risk.

  • 7/30/2019 Session20-21

    6/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Provides top management with a means to

    authorise and control manpower levels, inventory

    investment, and cash flow.

    Co-ordinate marketing, manufacturing,

    engineering, and finance activities

    Provides an overall measure of performance

    Provides data for material and capacity planning

  • 7/30/2019 Session20-21

    7/27DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    An appropriate scheduling system:-

    bar charts

    milestone charts network

    A listing of activities at the project level or lower

    The possible interrelationships between activities,

    this can be accomplished by logic networks,

    critical path networks, or PERT network.

    Activity time estimates

  • 7/30/2019 Session20-21

    8/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

  • 7/30/2019 Session20-21

    9/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Most common techniques:

    1. Gantt or bar charts

    2. Milestone charts

    3. Networks Programme Evaluation and Review Technique

    (PERT)

    The Critical Path Method (CPM)

    On-the-Arrow-Diagram Method

    On-the-Node-Diagram Method or Precedence DiagramMethod

    4. Line of balance

  • 7/30/2019 Session20-21

    10/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    The oldest, simplest planning,

    scheduling and contracting

    technique.

    Represents the time period

    allocated to the various tasks or

    activities.

    An activity is a task or closely

    related group of tasks whose

    performance contributes tocompletion of the overall

    project.

    Activities are entered down the

    side in chronological order.

    Operatio

    n

    Time

    Excavation

    Sub-structure

  • 7/30/2019 Session20-21

    11/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Easily understood

    Extremely useful for comparing planned and actual progress Easy and quick to prepare

    Require less revision and updating than other moresophisticated systems.

    Logical interconnections are difficult to comprehend.

    Difficult to reconstruct the logic and recognise sequence

    constraints

    Difficult to use for forecasting the effects that changes in a

    particular activity will have on the overall schedule, or

    even to project the progress of an individual activity.

  • 7/30/2019 Session20-21

    12/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

  • 7/30/2019 Session20-21

    13/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    A powerful analytical tool for project planning and control.

    Based on the rigorous application of logic network.

    PERT Originally developed in 1958 and 1959

    Introduced by the Special Projects Office of the U.S. Navy

    on the Polaris Weapon System in 1958

    At the same time the DuPont Company initiated theCritical Path Method (CPM) technique. This particularly

    concentrated in the construction and process industries.

  • 7/30/2019 Session20-21

    14/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Reveals interdependencies and problem areas i.e.determines where the greatest effort should be made

    Can determine the probabilities of meeting a specifieddeadlines by development of alternative plans.

    Ability to evaluate the effect of changes in the programme.

    Allows a large amount of sophisticated data to bepresented in a well-organised diagram.

    Can become very complex

    More data is required for the analysis

    Expensive to maintain

    Best for large, complex programmes

    Complicated for repetitive tasks

  • 7/30/2019 Session20-21

    15/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    PERT

    Uses three time estimates Optimistic, Most-likely,

    Pessimistic

    Probabilistic in nature,allows us to calculate therisk in completing theproject.

    Used in R&D projectswhere risks in calculatingtime durations have a highvariability.

    CPM Uses one time estimate

    Deterministic in nature

    Used for constructionprojects that resourcedependent and based onaccurate time estimates

  • 7/30/2019 Session20-21

    16/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    All tasks must be visualised in a manner clear

    enough to be put down in a network which

    comprises events and activities; i.e. follow the

    work breakdown structure.

    Events and activities must be sequenced under a

    highly logical set of ground rules.

    Time estimates must be made for each activity on

    the network.

    Critical path and float times are computed

  • 7/30/2019 Session20-21

    17/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Three types:

    1. Mandatory dependencies- hard logic:

    dependencies that cannot change2. Discretionary dependencies- soft logic: may be

    at the discretion of the project manager, may

    change from one project to another

    3. External dependencies- may be beyond the

    control of the project manager.

  • 7/30/2019 Session20-21

    18/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    A network provides the following information:

    Interdependencies of activities

    Project completion time

    Impact of late starts

    Impact of early starts

    Trade-offs between resources and time

    What if exercises Cost of a crash programme

    Slippages in planning/performance

    Evaluation of performance

  • 7/30/2019 Session20-21

    19/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    EVENTACTIVITY

    EVENT

    Networks are composed of events and activities

    An event is the starting or ending point for a group of

    activities

    An activity is the work required to proceed from one event

    to another.

  • 7/30/2019 Session20-21

    20/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Job description

    EVENT EVENT

    Start of activity Finish of activity

    i j

    Duration

    Well testingStart of activity Finish of activity

    3 77 days

  • 7/30/2019 Session20-21

    21/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Defining the sequence of events:

    Logical flow of work is established by asking the

    following questions: What job/s immediately precede this one?

    What job/s immediately follow this one?

    What job/s can be done concurrently?The answers to these questions are compounded in

    an arrow diagram.

  • 7/30/2019 Session20-21

    22/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    ExcavateErect formwork Pour concrete

    1 432

    21

    3

    5

    4

    Burst point

    Plaster walls

    1

    5

    3

    2Rough plumbing

    4

    Sink

  • 7/30/2019 Session20-21

    23/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Length & shape of the arrow does not give anysignificant information of the activity or to theresources it consumes.

    Until or unless all activities, leading to an eventare completed, the event is not completed. Noactivity can start until the proceeding events are

    completed. Time Flows from left to right.

    The activity is identified by its start and finishevents number.

  • 7/30/2019 Session20-21

    24/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    i j

    D

    E

    D

    E

    DummyD

    E

    Dummy

    A C

    Real

    dummy

    10

  • 7/30/2019 Session20-21

    25/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    A

    B D

    C

    Dummy

    DB

    A C

  • 7/30/2019 Session20-21

    26/27

    DR ASSEM AL-HAJJ, Univation, RGUProject Management and Economics. SITP-SPDC, NIGERIA

    Activities A, B, and C can start together. Once B

    is complete, D can start. E can start when A is

    complete, and F can start when A and D are

    complete. G and H can start when B and C are

    complete, and J when E, F and G are complete.

    Draw the network and number the nodes.

  • 7/30/2019 Session20-21

    27/27

    DR ASSEM AL-HAJJ Univation RGU

    A

    C

    B1

    E2

    D3

    G

    H4

    F5

    J6 7

    A, B, and C can

    start together

    Once B is

    complete, D can

    start

    Once A is

    complete, E can

    start

    F can start when

    A and D are

    complete

    G and H can startwhen B and C arecomplete

    J can start when

    E, F and G are

    complete