Session Two Dispute Resolution
Transcript of Session Two Dispute Resolution
-
7/30/2019 Session Two Dispute Resolution
1/10
Session Two Dispute Resolution
What are the alternative dispute resolutions?Dispute resolution JCT SBC/QDispute resolution NEC 3
DISPUTES
Disputes arise due to series of factors that combine to form disagreements and
ultimately disputes:
People diversity, motivating factors, preconception on roles, project success
or failure, business relations
Causes of contractual disputes in construction:
Late payment
Insufficient payment
Claim for loss and/or expense
Claim for EOT (extension of time to contract period)
Methods of dispute resolution
If dispute arises parties not compelled to resort to the courts for settling it canchoose amicable method needs to be signed and agreed by parties in writing
Non adversarial ADR
Use of courts expensive, uncertain and time consuming, Adjudication,
arbitration or litigation. Usually parties represented by council whose skill lies in
arguing and scoring points over each other Adversarial
Resolution Methods
Steps Non adversarial
Prevention Risk allocation, incentives, partnering
Negotiation direct or step negotiations
Standing Neutral Architects ruling, dispute review board, standing arbitrator
Non binding resolution Mediation, mini trial, early neutral evaluation, expert opinion
1
-
7/30/2019 Session Two Dispute Resolution
2/10
Steps Adversarial
Temporarily binding Adjudication
Binding Arbitration
LitigationNB: As you go through each of these steps costs will increase andcommunication will decrease.
Non-Adversarial route
NegotiationThree recognisable stages
Preparation What would you like to achieve What you intend to achieve
What you must achieve What is your walk away price
Negotiation Explore Formulate alternative solutions Bargaining and settlement
Post negotiation Cards on table, all things settled and drawn up as a contract
Standing Neutral Dispute Review Boards
Panel of 1 or 3 independents Appointed at the beginning of the contract Fees paid by the contractor and the client Will advise on issues as they arise with the aim of preventing them from
escalating into disputes Has a 97% success rate in the US Is to be used on 2012 Olympics construction contracts.
Non binding resolutionThese procedures are informal, cheap and investigatory rather than accusatorial.Interchangeable and therefore collectively referred to as reconciliation privatenon adversarial methods of resolving disagreement. Also known as intermediary
step between dispute and courts
ADR alternative dispute resolution Mediation agreement between parties Conciliation Private enquiry Mini trial
Mediation
Involves a third party helping the parties to the contract to work out asolution between themselves
2
-
7/30/2019 Session Two Dispute Resolution
3/10
The mediator should not express his views, if he cant get the parties toagree then he walks away and the process ends
Mini trial The parties have a short time (a day or two) to put their cases to a panel
made of senior executives from each company Still a negotiated agreement.
Expert Determination The parties put the facts before an expert who gives an opinion on the
outcome
Early Neutral Evaluation Similar to above
ADVERSARIAL ROUTES
Adversarial Three methods Adjudication Arbitration
Litigation
1. Adjudication
History Used in construction contracts since 1976 where parties agreed to
submit disputes of a certain type to an adjudicator Was used on NEC conditions Began to be incorporated into main contracts Latham report recommended adjudication as a 1st instance
resolution method HGCR Act 1996 introduced adjudication as a right for all parties
to construction contracts
AdjudicationTwo routes for decision notification
Decision issued in the form of an order Party who gained an award apply to court for 2nd order(a
mandatory injunction) instructing the other party to comply withadjudicators order
Not often followed in respect of paymentOR Issue proceedings claiming the sum due An application for summary judgement (Macob Engineering Ltd v
Morrison Construction Ltd (1999) Section 108(1)of the Construction Act (Housing Grants,
Construction and Regeneration Act 1996) creates a statutory rightto adjudication, designed to produce a decision which is, at least,
temporarily binding on the parties. It includes the procedures tobe followed
3
-
7/30/2019 Session Two Dispute Resolution
4/10
Prior to Construction Act only Arbitration and Litigation Adjudication revolutionised dispute resolution. Most cases
previously dealt with by courts or arbitration now adjudication.Out of 15000 cases which came to adjudication from May 1998 to2005 only 300 went to courts.
Although decision not binding in adjudication 80% of casesaccepted by parties.Since Construction Act came into force nos of constructiondisputes coming to courts has reduced to about third of what itwas
Key points Either party has the right to give notice at any time of theirintention to refer disputes to adjudication There is a timetable for adjudication
Adjudicator to be appointed within 7 days of the above notice The adjudicators decision must be within 28 days of the referral
(which can be extended by agreement by another 14 days) The adjudicator must act impartially The adjudicator can act on his own initiative to ascertain the
facts and the law related to the dispute The adjudicators decision is binding until its final determination
by litigation, arbitration or agreement. The adjudicator is immune from liability for his actions or
omissions
Key stages in Adjudication Notice of Adjudication Appointment of the Adjudicator A dispute which has crystallised will be referred to adjudication
within 7 days of the notice The Referral Notice The Response to the Referral Notice Decision making by the adjudicator The writing of the decision Correction of the decision Enforcement of the decision
Notice of Adjudication Purpose is to inform the other party that a dispute has arisen
served by the Referring party Requires evidence as to the nature of the dispute minutes,
letters and witnessstatements.
4
-
7/30/2019 Session Two Dispute Resolution
5/10
Appointment of the Adjudicator Three basic routes Parties agree the adjudicator after the dispute has arisen The adjudicator is named in the contract An application is made to the ANB (adjudicator nominating body)
to nominate one
Adjudicators Fee Rate to be agreed with the parties prior to Adjudicator accepting
the appointment Will be paid by both parties equally
The Referral Notice States the referring parties claim Has the tactical advantage of being able to be fully explained
and supported by evidence as it can be prepared before theclock starts ticking. Defending parties do not have thisadvantage
Known as ambush can also be carefully timed e.g. many areserved just before Christmas when parties may be on holidayand the clock is still ticking!
Must contain the same points of claim as those given in theNotice of Adjudication
Response to the Referral
Responding parties reply to the matters referred
Powers of the Adjudicator Adjudicator can carry out investigations to ascertain the facts
and the law concerning the matters in dispute, which caninvolve: Meeting parties together or separately Visit site Carry out tests Obtain legal and technical experts Use his own knowledge
The adjudicator must be careful to comply with the rules ofnatural justice.
The Decision Adjudicators can only make decisions on matters referred to
them. A decision should Give clear directions to the parties as to what they have to do
Be easy to enforce Avoid suspicion of bias
5
-
7/30/2019 Session Two Dispute Resolution
6/10
Power to correct a Decision An adjudicator has no power to change his decision once it is
published
However, the decision can be revised to Correct clerical or accidental errors Provide Clarification Remove ambiguity Make good an omission within a reasonable time.
Adjudication SummaryAdjudication to satisfy Act (avoid intervention of Scheme) contract
must: Enable a party to give written notice at any time to all other
parties of their intention to refer dispute to adjudication Notice includes nature of dispute and relief sought Adjudicator named in contract/nominated body (professional)
5days to nominate an adjudicator, 2 days to confirm Adjudicator must not be an employee of party in dispute Provide a timetable appoint adjudicator and referring dispute
within 7 days Adjudicator can demand documents from the parties, appoint
expert advisors, make site visits etc Adjudicator to reach decision within 28 days can extend by up
to 14 days
Adjudication GenerallyNo method by which decision can be appealed as inherently bindingtemporarily. If dispute dealt with by arbitration or litigation startafresh 3 grounds on which enforcement of adjudicators decisionresisted:
1) Lack of jurisdiction one of conditions not fulfilled (The ProjectConsultancy Group v Trustees of the Gray Trust (1999)
2) Error of law has the adjudicator answered the right question(Bouygues UK Ltd v Dahl Jensen UK Ltd(2000)
3) Procedural unfairness follow principals of natural justice notbias, acts fairly (Discain Project Services Ltd v OpecprimeDevelopment Ltd(2000): Barnes & Elliot Ltd v Taylor WoodrowHoldings Ltd(2004) adjudicators decision not made within time ltds
An adjudicator has no power to change his decision once it ispublished, However, the decision can be revised to Correct clerical or accidental errors
Provide Clarification Remove ambiguity
6
-
7/30/2019 Session Two Dispute Resolution
7/10
Make good an omission within a reasonable time.
Relevant Case law Bouygues V Dahl Jensen (2000)
Error in adjudicators decision stands even if the liquidation ofone party mean that the referring party will not be able to recouplosses.
Glencot Development vs Ben Barrett & Son (Contractors) Ltd(2001) Natural justice and potential bias.
2. Arbitration
Arbitration is a procedure for the resolution of disputes which isunder control of the parties and traditionally been constructionindustries preferred means of settling disputes. Conditions ofarbitration are: Decision/award must be capable of enforcement as if a
judgement of a court Binding contractual agreement to submit dispute to arbitration by
a third party chosen by the parties or in accordance with theirinstructions
Reference to arbitration in accordance with whatever procedure
laid down in the agreement Governed by the Arbitration Act 1996 Requires
A contract A valid arbitration agreement A dispute
Amec Civil Engineering Ltd. v Secretary of State for Transport(2000), defines disputes
A claim is not the same as a dispute
A claim must be rejected and resubmitted in order to become adispute
Process Once a dispute has arisen and it is ascertained that there is a
valid arbitration agreement Claiming party prepares a statement of case Defendants then prepare a statement of defence Defendants can ask for further and better particulars and can
prepare a counterclaim
All documents should be disclosed
7
-
7/30/2019 Session Two Dispute Resolution
8/10
Arbitration Act 1996 procedure:Principles
Object of arbitration is that it obtains a fair resolution of disputesby impartial tribunal without unnecessary delay or expense
Parties free to agree how their disputes are resolved
Court does not intervene unless act states so
Duties Act fairly and impartially Opportunity given for each party to put forward its case Adopt suitable procedures so as to provide fair means for theresolution of the matters to be determined while avoidingunnecessary expense and delay
Arbitration procedure in general Standard set of rules Arbitrator can make provisional awards Arbitrator add interest to any sum due Make orders for any liability for cost
Arbitration Act has bought about two sets of rules: Construction Industry Model Arbitration Rules 2005(CIMAR) 3Nr full procedure, documents only & short hearing
Institute of Civil Engineers Arbitration Procedure 2006(ICE)
However clear cut the dispute is it is still a dispute and if fallswithin a valid arbitration clause defendant entitled to havedispute heard at arbitration ( Halki Shipping Corp v Sopex OilsLtd (1997)
Arbitration Act control by courts Courts power to remove an arbitrator when1. Justifiable doubts as to arbitrators impartiality (Verital Shipping
Corporation v Anglo Canadian Cement Ltd (1966); Turner (EastAsia) PTE Ltd v Builders Federal(Hong Kong) (1988)
2. Arbitrator lacks qualifications3. Doubt to arbitrators physical/mental capacity to conductarbitration4. Arbitrator failed to conduct proceedings
Courts power to give ruling on particular point of law
Advantages of Arbitration
Hearings are private The award is published privately
8
-
7/30/2019 Session Two Dispute Resolution
9/10
Parties can choose their own arbitrator who will be a specialist inthe particular field
Venue and times are flexible dictated by party agreement Less formal Lawyers are optional
Arbitrator can award security for costs Can be cheaper Can have a documents only option Arbitrator can award interest and costsDisadvantages of Arbitration Rights of appeal are restricted Not ideal for multi-party disputes The arbitrator and the venue have to be paid for within the
duration A reluctant party may be less robustly dealt with
3. Litigation Process in which disputes are settled by a court Usually the Technology and Construction Court 8 circuit judges
Litigation dispute settled by action of the courtWhich court will depend on: Size of dispute below certain size go to county court. Building &
civil engineering cases of significant size tried in Technology and
Construction Court specialist division of High Court Nature of dispute which division of High Court Location tried locally or circuit judge for High Court
Litigation procedure April 1999 civil litigation governed by CivilProcedure Rules (CPR); Enables courts to deal with cases justly parties on equal footing,
saving expense, ways which are proportionate (amount ofmoney, importance, complexity, financial position), dealt withexpeditiously & fairly, allotting appropriate court resources
Litigation remedies1) Summary Judgement enables court to dispose of claim, defence
or particular issue without full trial. Saves money and time2) Interim payment enables claimant to apply for an order for
interim payment on account of damages or other sumsdefendant liable to pay
Advantages of Arbitration to litigation
Cost generally cheaper if not complex construction project
9
-
7/30/2019 Session Two Dispute Resolution
10/10
Speed generally on smaller less complex projects which do notrequire a trial
Technical complexity arbitrator has technical expertise andappointed by
both parties
Convenience time and place arranged to suit parties Privacy not officially in the public domain Commercial expediency less confrontational nature parties can
continue business after Parties can insist that arbitrator visits site
Disadvantage Cannot insist on witnesses being present
Advantages of litigation to arbitration
Third parties can be introduced Legal aid available Legal complexity where a point of law better to have it decided
by judge than arbitrator who has no legal qualifications Decisiveness arbitrators tend to not rule wholly in favour of one
party prefer split the difference
10